SlideShare a Scribd company logo
1 of 10
Download to read offline
A Review on
โ€œLabour-based Construction Technology for Sustainable Rural
Development Infrastructureโ€
SUBMITTED BY:
TSERING NGUTUK GURUNG (PAS076MSIEM017)
SUBMITTED TO:
Ar. BABURAM BHANDARI
PASHCHIMANCHAL CAMPUS
INSTITUDE OF ENGINEERING (IOE)
LAMACHOUR,POKHARA
13th
June.2021
1.Background:-
Nepal is a land-locked country which is rich in natural
diversity as well as cultural diversity. The federal
structures i.e. three tiers of government at federal,
province and local levels is implemented after the
promulgation of constitution in 2015. The major
percentage of area is hilly and mountainous area (77%of
total area).
The road construction is one of the major infrastructure
development aspects of Nepal. Due to complex geography
and topography, still many marginalized areas are
deprived of linkage to central area. Nepal has the lowest
road density in South Asia (with 47 km of road per 100 sq.
kilometres (km2
), and 2.5 km of road per 1000 people.
Local governments are planning and focusing on effective
development of rural areas. Labour based and equipment
based are two methods of road construction technologies
in the rural road construction, rehabilitation, operation,
maintenance.
2.Introduction:-
The labour-based technology is technology that applies
labour force for production and execution of road
construction with use of locally available non mechanical
tools. However the simple or immediate equipment can
be deployed in the case of increasing efficiency for the
those activities which are not performed by labour alone.
Similarly, if the construction of road is carried out by the
sophisticated or highly mechanized tools coordinated by
skilled manpower is termed as equipment based
construction technology.
3.Necessity of an appropriate technology:-
Selection of the appropriate road construction and
maintenance methods such as labour-based method or
machine-based method is necessary to be financially
viable. 18.7 percent Nepali population are living under the
poverty line currently in the country and most of them are
from rural areas. Thus to select appropriate technology for
road construction in these are deemed necessary.
Basically the selection of construction techniques depends
on various factors and both the prevalent construction
technologies have both merits and demerits. Some of
selection criteria are as follows:
โ€ข Available funds
โ€ข Project Duration
โ€ข Geography and topography of the proposed project
โ€ข Financial, economic and social status of project
affected people
โ€ข Availability and conditions of human resources;
skilled, semi-skilled, unskilled
โ€ข Acquaintedness with latest technology
โ€ข Degree of sustainability
4.Suitability of Labour-based technology in the
context of rural roads:-
However, in the context of rural areas of Nepal, labor
based construction technology is widely implemented in
order to assist in poverty alleviation. This technology is
environment friendly and sustainable in the sense that,
there is minimisation of slope cutting and preservation of
vegetation cover, mass balancing, proper management of
water, bio- engineering. The construction of road is
carried out in the agricultural slack season through labor
intensive techniques generally helps in capacity building
and creation of employment opportunities.
The green road approach generates the feeling of
ownership that assist in sustainable maintenance of road.
If a road can be built in an hour through conventional
approach using dozer and blasting, then a same road
finishing can take 15 days for a local to built using Green
road (GR) approach. To make a comparison, for the
purchase price of one bulldozer it would be possible to use
120,000 person days in labor-based road construction
using the green road approach (equivalent to
approximately 200.km of 1.5m wide trail, or .4 - 5. km of
full width earthen road) (RRF, 2004).
Labor based construction technology is a bottom up
approach that primarily focuses on social equality and
gender balance through the decentralisation and
participatory approach. Besides these superiorities over
the equipment based method, it helps to create
sustainable economic environment with optimum
utilisation of local resources, foreign exchange control and
cost reduction.
5.Advantages of equipment based construction
technology over labor based construction
technology:-
If the construction of road is carried out on the rough
terrain and complex topography then EBM is more
economical than LBM. Similarly, if the project is to be
finished within a short reach of time, EBM is an
appropriate choice. During harvesting time, local labors
may not be available.
Apart from above advantages, it has some demerits such
as
โ€ข Frequent natural disasters like landslides, debris fall
and disposals resulting into flooding
โ€ข Pollution near project area
โ€ข Disturbances to natural stability during construction (
drill and blast)
6.A case study of rural roads of Makwanpur district
Three roads were selected for the study and are as
follows:-
Name of road Total
length
(km)
Length
considered
(km)
Technology
Dandabas-Pakani 15 15 LB(GT,)
Pakani Kharka-
Baikuntha
13 13 EB
Sitalchowk-Jatiya
Pokhari
6 2.5 EB
6.1 Dandabas-Pakani LB Road
Average days of work engagement in road corridor by
local labors was 149 days that resulted in financial and
livelihood improvement with ensured additional three
months of food security. During the construction phase,
enhanced participation of dalit households and women
were ensured. The total direct cost was about NRs
1821700/km. After completion of project, significant
increase in commercial vegetable farming ( 90% of 2130
households) were observed due to market access.
6.2 Pakani- Baikuntha EB Road
EB were adopted as road alignment passes through long
stretch of forest area (about 15m) and unavailability of
local labors. The road is open for dry weather only i.e.
about seven months. Total direct cost incurred was NRs
619600/km. Average days of work engagement in road
corridor was 149 days. Additionally, it reduced cost of the
5m wife road to about NRs 619,000/km.
6.3 Sitalchowk-Jatiya Pokhari EB Road
Though itsโ€™ proposed length was 6 km ,only 2.5 km from
Sitalchowk was constructed because of intervention
caused by influential people on construction as they had
bought a large piece of commercial land.
7.Conclusion and recommendations:-
Sustainable way of constructing rural road with aim of
preservation of natural environment is of major concern.
Equipment based construction method may have higher
efficiency and productivity than labor based construction
technology but they may create environment problems
such pollution, changes in landscape, weakening the
natural stability. Similarly, requirement of highly skilled
manpower for operation, repair, maintenance of those
equipments and their transportation to the project sites
may require additional budget.
Labor based construction technology is widely used in the
rural areas because of availability of large number of
unemployed workers and local resources, materials and
tools. For financial cost comparison, the labor-based
method is generally cheaper than a machine-based
method to carry out the same tasks. Training sessions are
very much essential for effective implementation of labor
based construction method.
8.References:-
โ€ข Makwanpur DDC, 2001. Periodic District
Development Plan 2002โ€“2006.
โ€ข DOLIDAR, 1999. Approach for the Development of
Agricultural and Rural Roads: A Manual for the
Preparation of District Transport Master Plan and for
the Implementation of Rural Road Subprojects.
Kathmandu: Department of Local Infrastructure
Development and Agricultural Roads.
โ€ข Shrestha1,Diwat Kumar,2014. Labour-based
Construction Technology for Sustainable Rural
Development Infrastructure, JOURNAL OF
ADVANCED ACADEMIC RESEARCH (JAAR).
โ€ข Mulmi,Abhiman Das,2009.Green Road Approach in
Rural Road Construction for the Sustainable
Development of Nepal, Journal of Sustainable
Development, Vol. 2, No.3,Department of Roads
Ministry of Physical Planning and Works, Government
of Nepal Babarmahal, Kathmandu.
โ€ข Local Governance and Community Development
Programme (LGCDP), United Nations Development
Programme (UNDP), United Nations Environment
Programme (UNEP), 2011. Economic Analysis of Local
Government Investment in Rural Roads in Nepal
2011.

More Related Content

What's hot

Kajang sustainable development
Kajang sustainable developmentKajang sustainable development
Kajang sustainable developmentAli Alshock
ย 
IRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET Journal
ย 
Transportation engineering
Transportation engineering Transportation engineering
Transportation engineering Aminul Islam
ย 
Kajang sustainable development (1)
Kajang sustainable development (1)Kajang sustainable development (1)
Kajang sustainable development (1)engrasha
ย 
Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Pankti Jethi
ย 
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Shahadat Hossain Shakil
ย 
Feasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi ExpresswayFeasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi Expresswayvivatechijri
ย 
Land-use transport planning
Land-use transport planning Land-use transport planning
Land-use transport planning Bhavik A Shah
ย 
Mehrauli mahipalpur road widening project
Mehrauli mahipalpur road widening projectMehrauli mahipalpur road widening project
Mehrauli mahipalpur road widening projectecocollectivecitizensofvkunj
ย 
Highway planning for HIghways and Grand transport roads
Highway planning for HIghways and Grand transport roadsHighway planning for HIghways and Grand transport roads
Highway planning for HIghways and Grand transport roadsRana Ibrahim
ย 
L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1  L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1 Sachin PatiL
ย 
Narendra nagar flexible road pavement training report
Narendra nagar  flexible road pavement training reportNarendra nagar  flexible road pavement training report
Narendra nagar flexible road pavement training reportNarendra Nagar
ย 
Dhruv atal 030
Dhruv atal 030Dhruv atal 030
Dhruv atal 030DRatal2505
ย 
Highway Engineering Introduction: Lecture 1
Highway Engineering  Introduction: Lecture 1Highway Engineering  Introduction: Lecture 1
Highway Engineering Introduction: Lecture 1Raghubir Singh
ย 
TOD - Transit Oriented Development
TOD - Transit Oriented DevelopmentTOD - Transit Oriented Development
TOD - Transit Oriented DevelopmentShruthi Kshirasagar
ย 
An Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya Pradesh
An Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya PradeshAn Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya Pradesh
An Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya PradeshIRJET Journal
ย 

What's hot (19)

Kajang sustainable development
Kajang sustainable developmentKajang sustainable development
Kajang sustainable development
ย 
IRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET- Rural Road Design and Development
IRJET- Rural Road Design and Development
ย 
Transportation engineering
Transportation engineering Transportation engineering
Transportation engineering
ย 
Kajang sustainable development (1)
Kajang sustainable development (1)Kajang sustainable development (1)
Kajang sustainable development (1)
ย 
Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)
ย 
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
ย 
Feasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi ExpresswayFeasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi Expressway
ย 
Land-use transport planning
Land-use transport planning Land-use transport planning
Land-use transport planning
ย 
Mehrauli mahipalpur road widening project
Mehrauli mahipalpur road widening projectMehrauli mahipalpur road widening project
Mehrauli mahipalpur road widening project
ย 
Highway planning for HIghways and Grand transport roads
Highway planning for HIghways and Grand transport roadsHighway planning for HIghways and Grand transport roads
Highway planning for HIghways and Grand transport roads
ย 
L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1  L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1
ย 
Narendra nagar flexible road pavement training report
Narendra nagar  flexible road pavement training reportNarendra nagar  flexible road pavement training report
Narendra nagar flexible road pavement training report
ย 
TPO Integration of Land Use and Transportation in SMART Plan
TPO Integration of Land Use and Transportation in SMART PlanTPO Integration of Land Use and Transportation in SMART Plan
TPO Integration of Land Use and Transportation in SMART Plan
ย 
Dhruv atal 030
Dhruv atal 030Dhruv atal 030
Dhruv atal 030
ย 
Eia
EiaEia
Eia
ย 
Highway Engineering Introduction: Lecture 1
Highway Engineering  Introduction: Lecture 1Highway Engineering  Introduction: Lecture 1
Highway Engineering Introduction: Lecture 1
ย 
Highway planning
Highway planningHighway planning
Highway planning
ย 
TOD - Transit Oriented Development
TOD - Transit Oriented DevelopmentTOD - Transit Oriented Development
TOD - Transit Oriented Development
ย 
An Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya Pradesh
An Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya PradeshAn Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya Pradesh
An Energy Saving Pavement Management (ESPM) for Urban Roads in Madhya Pradesh
ย 

Similar to Review of lbm vs ebm, tsering 017

Why Labor Based Technology in Nepal
Why Labor Based Technology in NepalWhy Labor Based Technology in Nepal
Why Labor Based Technology in NepalManoj Neupane
ย 
Labour Based Method vs Equipment Based Method
 Labour Based Method  vs Equipment Based Method Labour Based Method  vs Equipment Based Method
Labour Based Method vs Equipment Based MethodTseringodrub Gurung
ย 
LabourbasedEquipmentbasedNepal.pdf
LabourbasedEquipmentbasedNepal.pdfLabourbasedEquipmentbasedNepal.pdf
LabourbasedEquipmentbasedNepal.pdftrilok bist
ย 
Traning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementTraning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementNIWASHISH VISWAS
ย 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement Awinash Tiwari
ย 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
ย 
Highway construction Report
Highway construction Report Highway construction Report
Highway construction Report Vikas Sukhwal
ย 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdfEr. Bam Bhandari
ย 
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdfINTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdfSANJAY ACHARYA
ย 
IRJET- A Study on Life Cycle Cost Analysis for Roads
IRJET- A Study on Life Cycle Cost Analysis for RoadsIRJET- A Study on Life Cycle Cost Analysis for Roads
IRJET- A Study on Life Cycle Cost Analysis for RoadsIRJET Journal
ย 
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."IRJET Journal
ย 
Ayushsummertrainingreport (1).pdf
Ayushsummertrainingreport (1).pdfAyushsummertrainingreport (1).pdf
Ayushsummertrainingreport (1).pdfSahilkhan467604
ย 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)Ratnesh Kushwaha
ย 
IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...
IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...
IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...IRJET Journal
ย 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highwayShivam Srivastava
ย 
CTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxCTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxAnandBaratePatil
ย 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
ย 

Similar to Review of lbm vs ebm, tsering 017 (20)

Why Labor Based Technology in Nepal
Why Labor Based Technology in NepalWhy Labor Based Technology in Nepal
Why Labor Based Technology in Nepal
ย 
Labour Based Method vs Equipment Based Method
 Labour Based Method  vs Equipment Based Method Labour Based Method  vs Equipment Based Method
Labour Based Method vs Equipment Based Method
ย 
LabourbasedEquipmentbasedNepal.pdf
LabourbasedEquipmentbasedNepal.pdfLabourbasedEquipmentbasedNepal.pdf
LabourbasedEquipmentbasedNepal.pdf
ย 
Traning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementTraning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavement
ย 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement
ย 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
ย 
Highway construction Report
Highway construction Report Highway construction Report
Highway construction Report
ย 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdf
ย 
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdfINTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
INTERNSHIP REPORT ON FLEXIBLE PAVEMENT by SANJAY ACHARYA.pdf
ย 
IRJET- A Study on Life Cycle Cost Analysis for Roads
IRJET- A Study on Life Cycle Cost Analysis for RoadsIRJET- A Study on Life Cycle Cost Analysis for Roads
IRJET- A Study on Life Cycle Cost Analysis for Roads
ย 
monorail system implication in Sri Lanka
monorail system implication in Sri Lankamonorail system implication in Sri Lanka
monorail system implication in Sri Lanka
ย 
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
ย 
Ayushsummertrainingreport (1).pdf
Ayushsummertrainingreport (1).pdfAyushsummertrainingreport (1).pdf
Ayushsummertrainingreport (1).pdf
ย 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
ย 
IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...
IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...
IRJET- Critical Assessment of Road Capacitiesand Solutions for Traffic Proble...
ย 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highway
ย 
CTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxCTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptx
ย 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
ย 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
ย 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
ย 

More from Tseringodrub Gurung

Policy and Infrastructure Development
Policy and Infrastructure DevelopmentPolicy and Infrastructure Development
Policy and Infrastructure DevelopmentTseringodrub Gurung
ย 
Infrastructure Regulatory System
Infrastructure Regulatory SystemInfrastructure Regulatory System
Infrastructure Regulatory SystemTseringodrub Gurung
ย 
Science and Technology Capacity in Pokhara
Science and Technology Capacity in PokharaScience and Technology Capacity in Pokhara
Science and Technology Capacity in PokharaTseringodrub Gurung
ย 
Sustainable development Goal No 17 ppt
Sustainable development Goal No 17 pptSustainable development Goal No 17 ppt
Sustainable development Goal No 17 pptTseringodrub Gurung
ย 
Industrial disputes and management
Industrial disputes and managementIndustrial disputes and management
Industrial disputes and managementTseringodrub Gurung
ย 

More from Tseringodrub Gurung (9)

Tax system
Tax systemTax system
Tax system
ย 
Swot Analysis
Swot AnalysisSwot Analysis
Swot Analysis
ย 
Policy and Infrastructure Development
Policy and Infrastructure DevelopmentPolicy and Infrastructure Development
Policy and Infrastructure Development
ย 
Boot model
Boot modelBoot model
Boot model
ย 
Infrastructure Regulatory System
Infrastructure Regulatory SystemInfrastructure Regulatory System
Infrastructure Regulatory System
ย 
FDI
FDIFDI
FDI
ย 
Science and Technology Capacity in Pokhara
Science and Technology Capacity in PokharaScience and Technology Capacity in Pokhara
Science and Technology Capacity in Pokhara
ย 
Sustainable development Goal No 17 ppt
Sustainable development Goal No 17 pptSustainable development Goal No 17 ppt
Sustainable development Goal No 17 ppt
ย 
Industrial disputes and management
Industrial disputes and managementIndustrial disputes and management
Industrial disputes and management
ย 

Recently uploaded

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
ย 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
ย 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
ย 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
ย 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
ย 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
ย 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
ย 
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Call Girls in Nagpur High Profile
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
ย 

Recently uploaded (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ย 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
ย 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
ย 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
ย 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
ย 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
ย 
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
ย 

Review of lbm vs ebm, tsering 017

  • 1. A Review on โ€œLabour-based Construction Technology for Sustainable Rural Development Infrastructureโ€ SUBMITTED BY: TSERING NGUTUK GURUNG (PAS076MSIEM017) SUBMITTED TO: Ar. BABURAM BHANDARI PASHCHIMANCHAL CAMPUS INSTITUDE OF ENGINEERING (IOE) LAMACHOUR,POKHARA 13th June.2021
  • 2. 1.Background:- Nepal is a land-locked country which is rich in natural diversity as well as cultural diversity. The federal structures i.e. three tiers of government at federal, province and local levels is implemented after the promulgation of constitution in 2015. The major percentage of area is hilly and mountainous area (77%of total area). The road construction is one of the major infrastructure development aspects of Nepal. Due to complex geography and topography, still many marginalized areas are deprived of linkage to central area. Nepal has the lowest road density in South Asia (with 47 km of road per 100 sq. kilometres (km2 ), and 2.5 km of road per 1000 people. Local governments are planning and focusing on effective development of rural areas. Labour based and equipment based are two methods of road construction technologies in the rural road construction, rehabilitation, operation, maintenance. 2.Introduction:- The labour-based technology is technology that applies labour force for production and execution of road construction with use of locally available non mechanical
  • 3. tools. However the simple or immediate equipment can be deployed in the case of increasing efficiency for the those activities which are not performed by labour alone. Similarly, if the construction of road is carried out by the sophisticated or highly mechanized tools coordinated by skilled manpower is termed as equipment based construction technology. 3.Necessity of an appropriate technology:- Selection of the appropriate road construction and maintenance methods such as labour-based method or machine-based method is necessary to be financially viable. 18.7 percent Nepali population are living under the poverty line currently in the country and most of them are from rural areas. Thus to select appropriate technology for road construction in these are deemed necessary. Basically the selection of construction techniques depends on various factors and both the prevalent construction technologies have both merits and demerits. Some of selection criteria are as follows: โ€ข Available funds โ€ข Project Duration โ€ข Geography and topography of the proposed project
  • 4. โ€ข Financial, economic and social status of project affected people โ€ข Availability and conditions of human resources; skilled, semi-skilled, unskilled โ€ข Acquaintedness with latest technology โ€ข Degree of sustainability 4.Suitability of Labour-based technology in the context of rural roads:- However, in the context of rural areas of Nepal, labor based construction technology is widely implemented in order to assist in poverty alleviation. This technology is environment friendly and sustainable in the sense that, there is minimisation of slope cutting and preservation of vegetation cover, mass balancing, proper management of water, bio- engineering. The construction of road is carried out in the agricultural slack season through labor intensive techniques generally helps in capacity building and creation of employment opportunities. The green road approach generates the feeling of ownership that assist in sustainable maintenance of road. If a road can be built in an hour through conventional approach using dozer and blasting, then a same road finishing can take 15 days for a local to built using Green
  • 5. road (GR) approach. To make a comparison, for the purchase price of one bulldozer it would be possible to use 120,000 person days in labor-based road construction using the green road approach (equivalent to approximately 200.km of 1.5m wide trail, or .4 - 5. km of full width earthen road) (RRF, 2004). Labor based construction technology is a bottom up approach that primarily focuses on social equality and gender balance through the decentralisation and participatory approach. Besides these superiorities over the equipment based method, it helps to create sustainable economic environment with optimum utilisation of local resources, foreign exchange control and cost reduction. 5.Advantages of equipment based construction technology over labor based construction technology:- If the construction of road is carried out on the rough terrain and complex topography then EBM is more economical than LBM. Similarly, if the project is to be finished within a short reach of time, EBM is an appropriate choice. During harvesting time, local labors may not be available.
  • 6. Apart from above advantages, it has some demerits such as โ€ข Frequent natural disasters like landslides, debris fall and disposals resulting into flooding โ€ข Pollution near project area โ€ข Disturbances to natural stability during construction ( drill and blast) 6.A case study of rural roads of Makwanpur district Three roads were selected for the study and are as follows:- Name of road Total length (km) Length considered (km) Technology Dandabas-Pakani 15 15 LB(GT,) Pakani Kharka- Baikuntha 13 13 EB Sitalchowk-Jatiya Pokhari 6 2.5 EB 6.1 Dandabas-Pakani LB Road Average days of work engagement in road corridor by local labors was 149 days that resulted in financial and
  • 7. livelihood improvement with ensured additional three months of food security. During the construction phase, enhanced participation of dalit households and women were ensured. The total direct cost was about NRs 1821700/km. After completion of project, significant increase in commercial vegetable farming ( 90% of 2130 households) were observed due to market access. 6.2 Pakani- Baikuntha EB Road EB were adopted as road alignment passes through long stretch of forest area (about 15m) and unavailability of local labors. The road is open for dry weather only i.e. about seven months. Total direct cost incurred was NRs 619600/km. Average days of work engagement in road corridor was 149 days. Additionally, it reduced cost of the 5m wife road to about NRs 619,000/km. 6.3 Sitalchowk-Jatiya Pokhari EB Road Though itsโ€™ proposed length was 6 km ,only 2.5 km from Sitalchowk was constructed because of intervention caused by influential people on construction as they had bought a large piece of commercial land.
  • 8. 7.Conclusion and recommendations:- Sustainable way of constructing rural road with aim of preservation of natural environment is of major concern. Equipment based construction method may have higher efficiency and productivity than labor based construction technology but they may create environment problems such pollution, changes in landscape, weakening the natural stability. Similarly, requirement of highly skilled manpower for operation, repair, maintenance of those equipments and their transportation to the project sites may require additional budget. Labor based construction technology is widely used in the rural areas because of availability of large number of unemployed workers and local resources, materials and tools. For financial cost comparison, the labor-based method is generally cheaper than a machine-based method to carry out the same tasks. Training sessions are very much essential for effective implementation of labor based construction method.
  • 9. 8.References:- โ€ข Makwanpur DDC, 2001. Periodic District Development Plan 2002โ€“2006. โ€ข DOLIDAR, 1999. Approach for the Development of Agricultural and Rural Roads: A Manual for the Preparation of District Transport Master Plan and for the Implementation of Rural Road Subprojects. Kathmandu: Department of Local Infrastructure Development and Agricultural Roads. โ€ข Shrestha1,Diwat Kumar,2014. Labour-based Construction Technology for Sustainable Rural Development Infrastructure, JOURNAL OF ADVANCED ACADEMIC RESEARCH (JAAR). โ€ข Mulmi,Abhiman Das,2009.Green Road Approach in Rural Road Construction for the Sustainable Development of Nepal, Journal of Sustainable Development, Vol. 2, No.3,Department of Roads Ministry of Physical Planning and Works, Government of Nepal Babarmahal, Kathmandu. โ€ข Local Governance and Community Development Programme (LGCDP), United Nations Development Programme (UNDP), United Nations Environment Programme (UNEP), 2011. Economic Analysis of Local
  • 10. Government Investment in Rural Roads in Nepal 2011.