The document provides a progress report for Borak Real Estate (Pvt.) Ltd for the month of October 2010. It summarizes ongoing construction projects and their progress over the last month. It also provides details on upcoming projects in the pipeline, including the present status and planned timelines. A key upcoming project discussed is the 960 acre Ichamoti-Serajdikhan Satellite Town project near Dhaka, which will involve constructing apartment buildings, residential plots, and civic facilities over a three year period.
An experimental study in using natural admixture as an alternative for chemic...
Project-Progress-Presentation.pptx
1. Monthly Progress Report of
October, 2010
BORAK REAL ESTATE (PVT.) LTD.
DEPARTMENT OF PROJECT DEVELOPMENT
2. On Going Projects Construction
Progress Details
DEPARTMENT OF PROJECT
DEVELOPMENT
3. BANANI DCC UNIQUE COMPLEX
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
44 Kemal Ataturk Avenue, Banani, Dhaka.
30 Storied Office Building cum 5 Star Hotels.
Last Month’s Construction Work
Progress Detail History
Superstructure Work
Finishing Works
Drawing, Design and various work order
Sanitary and Plumbing Work
Electromechanical work
oEscalator and Elevator
oHVAC
oSubstation & Generator
Project Construction Work Planning for
Coming Month
Risk/ Threat for Construction Work
Progress
Facing Legal Issue (If any)
4. UNIQUE HEIGHTS
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Plot # 117, Kazi Nazrul Avenue, Ramna, Dhaka – 1000.
Office Cum Residential Complex
Last Month’s Construction Work
Progress Detail History
Superstructure Work
Drawing, Design and various work
order
Sanitary and Plumbing Work
Electromechanical work
oPassenger Lift
oSubstation & Generator
Project Construction Work Planning for
Coming Month
Risk/ Threat for Construction Work
Progress
Facing Legal Issue (If any)
5. RED CRESCENT BORAK TOWER (RCBT)
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
71-72 Elephant Road, Eskaton, Dhaka.
Office cum Residential Complex.
Last Month’s
Construction Work
Progress Detail History
Superstructure Work
Finishing Works
Drawing, Design and
various work order
Sanitary and Plumbing
Work
Electromechanical work
Project Construction Work
Planning for Coming Month
Risk/ Threat for
Construction Work Progress
Facing Legal Issue (If
any)
6. UNIQUE PENINSULA GRAND CONDOMINIUM
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
22/23 Boro Mogbazar, Dhaka – 1000.
Residential Complex
(Posh Living Facilities, Swimming Pool, Gymnasium)
Last Month’s
Construction Work
Progress Detail History
Superstructure Work
Finishing Works
Drawing, Design and
various work order
Sanitary and Plumbing
Work
Electromechanical work
Project Construction Work
Planning for Coming Month
Risk/ Threat for
Construction Work Progress
Facing Legal Issue (If
any)
7. UNIQUE SUNFLOWER
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
12, Islampur, Kumartoli, Dhaka.
Residential Building.
Last Month’s Construction Work
Progress Detail History
Superstructure Work
Finishing Works
Drawing, Design and various work
order
Sanitary and Plumbing Work
Electromechanical work
Project Construction Work Planning
for Coming Month
Risk/ Threat for Construction Work
Progress
Facing Legal Issue (If any)
8. 70, DILKUSHA MOTIJHEEL PROJECT
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
70, Dilkisha, Motijheel, Dhaka
Commercial Project.
Last Month’s Construction Work
Progress Detail History
Superstructure Work
Finishing Works
Drawing, Design and various work
order
Sanitary and Plumbing Work
Electromechanical work
Project Construction Work Planning for
Coming Month
Risk/ Threat for Construction Work
Progress
Facing Legal Issue (If any)
9. PRESENT STATUS OF UPCOMING
PROJECT
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
10. BORAK JOHIR TOWER
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Kawran Bazar, Dhaka
Present Status of This Project:
Sub soil investigation/Soil test work has
been completed successfully.
New designed bill board has been installed
as per direction of top management.
All primary approval already received from
RAJUK.
Final survey by RAJUK has been
completed & submitted as well.
This project’s full phase construction work
will start very soon.
Intelligent Office Building Located @ VIP Zone
Including 5 Basement 30 Storied Office Building
Exclusive office Spaces with Central Air –
Condition
11. UNIQUE 51/B
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
51/B, Kemal Ataturk Avenue,
Banani, Dhaka
Present Status of This Project:
Sub soil investigation/ soil test has been
completed.
Already power of attorney has been
accepted by RAJUK.
Complete set architectural drawing and
design has been submitted to RAJUK.
Complete set drawing and design’s soft
copy already submitted to land owner.
Transformation of project category from
residential to commercial procedure already
submitted and its approval process will be
done within this month.
This projects full phase construction work
will start very soon.
20 Storied Intelligent Office Building
with All Modern Facilities
12. UNIQUE PACIFIC
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Gulshan 2, Dhaka
Present Status of This Project:
All legal issues with NAVANA and Doctor are almost resolved
successfully.
Power of attorney on behalf of UHRL from RAJUK for Plot # 128,
Gulshan Avenue, Dhaka has been received.
New consultant team has been invited from London (UK) and South
Korea to do the interior design, Architectural drawing and design and
project feasibility work completion.
Commercial approval processing has been completed and it is
already submitted to RAJUK.
Old Thana project’s existing structure dismantling work and parking
design of that particular has been completed successfully.
This project’s full phase construction work will start very soon.
Intelligent Office Building 5 Basement 30 Storied Building Exclusive
Shopping & Office Spaces Located @ VIP Zone including Central Air
Condition.
13. UNIQUE PARK VALLEY
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
34 & 36 Park Road, Baridhara, Dhaka
Present Status of This Project
Sub soil investigation/Soil test
already completed successfully.
All structural drawing and design
including interior design, Architectural
drawing and design has been
completed.
Borak Real Estate taken hand over
of the project land dismantling building
and install security guard already.
All RAJUK procedure and approval
including permission has been
complete.
This projects full phase construction
work will start very soon.
14 Storied Residential Building with Posh Living Facilities at
Diplomatic Zone.
14. WESTIN – 2
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Gulshn – 2, Gulshan,, Dhaka
Present Status of This Project
Sub soil investigation/ Soil test has been
completed successfully.
Newly designed high profiled billboard has been
installed as per direction of top management.
Almost all RAJUK procedure and approval
including permission has been received.
Drawing and design for 30’ access road for entry
and exit from the back side of project already
been submitted to RAJUK for their processing.
Besides, we will get approval regarding mentioned
mater from RAJUK within this month time.
All the structural drawing and design including
parking design and interior design, Architectural
drawing and design has been received from South
Korean consultant team. Besides, MNE
(Electromechanical) design preparing work going
on.
This projects full phase construction work will
start very soon.
Parking cum Commercial Building at Diplomatic Zone with 100% Fire Protection System
30 Storied Building including 600 Car Parking 6 Basements, Tower & Machine Parking
Exclusive Shopping & Office Spaces & 5 Star Service Apartments
15. UNIQUE SPRINKLE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Plot # 3 & 5, Road # 10/A, Sector # 9, Uttara, Dhaka.
Present Status of This Project
Power of attorney already accepted
by RAJUK.
Fullest architectural drawing has
been complete.
Clearance of RAJUK for the
unification of adjacent two lands
already submitted.
Sub soil investigation/ Soil test has
been completed.
Structural drawing and design work
will start very soon.
This projects full phase construction
work will start very soon.
Luxurious Residential Building.
16. UNIQUE MINERVA.
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Plot # 02, Road # 59, Gulshan -2, Dhaka
Present Status of This Project
This projects power of attorney
acceptance work under process of
RAJUK.
Honorable land owner will arrive
from London (UK) within this
month to provide the remaining
portions power of attorney.
This projects full phase
construction work will start very
soon.
Residential Building with Posh Living Facilities.
17. UNIQUE CRESCENT COMMERCIAL
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Plot # 19, Sector # 06, Dhaka- Mymensingh Highway Uttara Model Town.
Present Status of This Project
Architectural drawing and design for land
clearance purpose from RAJUK has been
completed to submitted RAJUK by in house
architect.
This projects full phase construction work
will start very soon.
Residential cum Commercial Building with All Modern Facilities.
18. DCC NORTH SOUTH PROJECT
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Gulshan -2, Dhaka
Present Status of This Project
Technical and financial
proposal already been
submitted now it is under
processing of evaluation.
We have submitted proposal
to merge two pieces of lands
for the same project.
Technically we are in good
position comparatively other
bidder.
100% Commercial Luxurious Building
19. DETAILS UPDATE OF PROJECTS IN
PIPE LINE.
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
20. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Present status of Pipe line projects
Land Area: 1 Bigha.
Location: Dhanmondi (Behind the
Dhanmondi Lake), Dhaka.
Provable Project Type: Luxurious
Apartment
Building for
posh living.
Present Status: Already offer later
issue complete to land
owner for develop
Selected land as joint
venture and 50%-50%
ratio.
21. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Present status of Pipe line projects
Land Area: 26 Katha.
Location: Adjacent Rampura TV centre,
Rampura, Dhaka.
Provable Project Type: Luxurious
Apartment
Building for
posh living.
Present Status: Already offer later
issue complete to land
owner for develop
Selected land as joint
venture and 50%-50%
ratio.
22. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Present status of Pipe line projects
Land Area: 1 Bigha.
Location: Shegun Bagicha (Behind the
Shilpa Kola Auditorium), Dhaka.
Provable Project Type: Luxurious
Apartment
Building for
posh living.
Present Status: Already offer later
issue complete to land
owner for develop
Selected land as joint
venture and 50%-50%
ratio.
23. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Present status of Pipe line projects
Land Area: 3.75 Bigha.
Location: Zigatola, Hazaribag, Dhaka.
Provable Project Type: Luxurious
Apartment
Building for
posh living.
Present Status: Already offer later
issue complete to land
owner for develop
Selected land as joint
venture and 50%-50%
ratio.
24. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Present status of Pipe line projects
PROJECT NAME & TYPE: 960 Acres Ichamoti-
Serajdikhan Satellite Town
project.
Location: Serajdikhan, Munshigonj, Dhaka.
25. INTRODUCTION OF PROJECT
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Serajdikhan, Munshigonj, Dhaka.
Distance From Dhaka City: The first phase of the project
(Ichamoti – Sirajdikhan Satellite Town) at a
distance of about 16 km from Dhaka zero point and
10 km from Mohammadpur Buddhijibi Bridge.
EstimatedCostandBudget: TK. 663596.96 LAKH.
Tenure/Durationof project:03 (THREE) years.
Sponsoring Ministry/Division: Ministryof HousingandPublicWorks.
ExecutingAgency: NationalHousingAuthority(NHA).
26. Building Type Nos. of Construction Nos. Flats
Construction
Costing/Unit
Selling Process.
1000 Sft
57 Nos. Building. 9576 Nos. 22.03 Lakh.
Considering 10% as service charge
for selling and for recovery of cost,
50% of the total cost is considered
to be recovered in 4 Years by 16
(Sixteen) installments. After that
next 50% in monthly installments
for a period of 16 Years.
Note: Recovery Period including 20
Years.
1200 Sft 43 Nos. Building. 7224 Nos. 26.43 Lakh.
1450 Sft 43 Nos. Building.
7224 Nos. 31.94 Lakh.
Total Building = 143 Nos. Total Unit/Apartment = 24024 Nos.
Plot Type Nos. of Plots. Development Costing/ katha.
Selling Process
3.00 Katha
2950 Nos. Plots
2.08 Lakh/Katha.
Considering 10% as service
charge for selling and for
recovery of cost, 50% of the total
cost is considered to be
recovered in 4 Years by 16
(Sixteen) installments. After that
next 50% in monthly
installments for a period of 16
Years.
Note: Recovery Period including
20 Years.
5.00 Katha 900 Nos. Plots
10.00 Katha 150 Nos. Plots
Total Land/ Project Area = 960 acres.
Development Work
Rest 50% (480 acres) of total area will
left for open space, playground,
graveyard, Lake, Mosque, School,
Collage, University, Market, Park etc.
Provisions for all Civic facilities are
incorporated in the project.
Total 143 Building Construction is required.
Total 4000 Plot construction is required.
Total Area of 143 Nos. Building = 28683740.82 SFT.
50% (480 acres) will be used for
both construction of Apartment
Building and Plots.
27. Total Land/ Project Area = 960 acres.
Forecasting Cost and Profit Analysis of
Project Development.
Rest of items Forecast Development
Cost Breakdown.
1200 sft 43 Nos. 15 storied building
168 nos flat on each building. Total
construction area=8668800 sft @
1889 Tk/Sft Construction cost.
Main RCC gate =10 Nos.
External Electrification in/c Street
lighting
PDB/REB Connection charge.
163705.50 Lac
TK.
197651.61 Lac
TK.
30.00 Lac TK.
12060.00 Lac
TK.
1015.00 Lac TK.
1450 sft 43 Nos. 15 storied building
168 nos flat on each building. Total
construction area=1074800 sft @
1888 Tk/Sft Construction cost.
PDB/REB Connection charge.
Miscellaneous All Expense Such as
Sub soil investigation, All drawing design testing & environmental clearance, Underground water reservoir including
Centrifugal pump & sub-mircible pump installing, RCC boundary, Septic tank, Sock well, Sewerages line, Lift
installation, 100KVA 429 nos generator, Fire management, Gas line, intercom, CCTV, Telephone line, Plantation,
Training Evaluation & monitoring, Allowance, Inspection vehicle, Office furniture and Instrument, Survey and soil
investigation, Manpower, Project Monitoring, Price escalation and Contingency. Total L/S costing for Above all
works.
63436.24 Lac TK.
TOTAL PROJECT IMPLEMENTATION CONSTING =
437898.35 Lac TK + 225698.61= 663596.96 Lac TAKA.
FROM THIS AMOUNT GOVERNMENTS INVESTMENT @ 40% = 265438.784 Lac TK.
FROM THIS AMOUNT DEVELOPERS INVESTMENT @ 60% = 398158.176 Lac TK.
Total Selling Value=126979920000TK.
Selling process.
Governments
Selling Process.
Developers
Selling Process.
Considering 10% as service
charge for selling and for
recovery of cost, 50% of
the total cost is considered
to be recovered in 4 Years
by 16 (Sixteen)
installments. After that next
50% in monthly
installments for a period of
16 Years.
Note: Recovery Period
including 20 Years.
Company
Present Selling
Process.
1015.00 Lac TK.
ORGINAL PROFIT AFTER TOTAL SELLING
SELLING VALUE = 1269799.20 Lac TK.
CONSTRUCTION AND DEVELOPMENT VALUE @ 60% INVESTMENT FROM TOTAL
PROJECT VALUE (663596.96 Lac TK) = 398158.176 Lac TK.
Total Approximately Profit= 871641.03 Lac TK.
28. Profitability Calculation of Satellite Town project
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Total Land/ Project Area = 960 acres.
Forecast Development Cost Breakdown
OF Proposed 663596.96 Lac TK. @ 60%
investment of developers.
4000 Various Sizes plot & 143 Nos.
15 Storied Buildings ownership
ratio.
Rest 60% of Whole Projects
owned by Developer.
40% of Whole Projects owned
by Government.
Total constructed area of 143 Nos. Building
1000 sft size 9576 nos Flats= 9576000 sft
1200 sft size 7224 nos Flats= 8668800 sft.
1450 sft size 7224 nos Flats= 10474800 sft.
Total Area= 28,719,600 sft. @ 60% area is applicable to
sale by developer.
Total saleable area @60%= 17231760 sft. @ 4500 TK/Sft
(Forecasting average selling price).
Total Selling Amount in TK.
7754, 2920000 TK.
29. Profitability Calculation of Satellite Town project
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Total Land/ Project Area = 960 acres.
Forecast Development Cost Breakdown
OF Proposed 663596.96 Lac TK. @ 60%
investment of developers.
4000 Various Sizes plot & 143 Nos.
15 Storied Buildings ownership
ratio.
Rest 60% of Whole Projects
owned by Developer.
40% of Whole Projects owned
by Government.
Total 4000 Nos. various size Plot will be construct.
3 katha = 29550 Nos. Plot. @ 60% for Developer= 17730
Nos. @ 8.00 Lac TK/Katha. (Saleable area = 53190 Katha).
5 Katha = 900 Nos. Plot. @60% for Developer = 540 Nos. @
8.5 Lac TK/Katha. (Saleable area = 2700 Katha).
10 Katha = 900 Nos. plot @ 60% for Developer = 540
Nos.@ 8.5 Lac TK/ Katha. Saleable area = 5400 Katha).
Total Nos. of plot =4000 Nos. @ 60% plot (2400 Nos.) is
applicable to sale by developer.
42552000000 TK (Proposed
Selling price for 3 Katha)
2295000000 TK (Proposed
selling price for 5 Katha)
4590000000 TK (Proposed
Selling price for 10 Katha)
TOTAL AMOUNT: 49437, 000000 TK.
30. Profitability Calculation of Satellite Town project
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Total Land/ Project Area = 960 acres.
Forecast Development Cost
Breakdown OF Proposed 663596.96
Lac TK. @ 60% investment of
developers.
4000 Various Sizes plot & 143 Nos.
15 Storied Buildings ownership
ratio.
TOTAL PROJECT IMPLEMENTATION CONSTING =
437898.35 Lac TK + 225698.61= 663596.96 Lac
TAKA.
FROM THIS AMOUNT GOVERNMENTS INVESTMENT
@ 40% = 265438.784 Lac TK.
FROM THIS AMOUNT DEVELOPERS
INVESTMENT @ 60% = 398158.176 Lac TK
ORGINAL PROFIT AFTER TOTAL SELLING
SELLING VALUE= 1269799.20 Lac TK.
CONSTRUCTION AND DEVELOPMENT VALUE @
60% INVESTMENT FROM TOTAL PROJECT
VALUE (663596.96 Lac TK) =398158.176 LacTK
Total Approximately Profit= 871641.03
Lac TK.
31. PROJECT DEVELOPMENT PROPOSAL SUMMARY
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Development of Ichamati – Serajdikhan Satellite
Town
GOVERNMENT OF THE PEOPLES REPUBLIC OF BANGLADESH
MINISTRY OF HOUSING & PUBLIC WORKS
33. NEWPROPOSEL FOR BUSINESS DEVELOPMENT
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
34. ReadyMixConcretePlantInstallation
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Required land for plant installation: 5 Bigha Approximately.
Mixing Plant Details:
1. Picture:
Platform Construction Summary:
As per Equipment supply companies providing drawing and design
all construction will be done.
Concrete pump Truck Mixture Carrying Truck.
37. ReadyMixConcretePlant’s Brand& Specification’s.
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Above mentioned ready mix concrete plant’s Specifications
And complete set plants rate (Approximately)
Ready Mixed Concrete Mixing Plant HZS90 (with the capacity of
90m3/h)
FOB Price:
Approximately 12 core Taka.
Including Mixture, Pump truck and
One Set Plant.
Port: Qing Dao
Minimum Order Quantity: 1 Unit/Units meet your needs
Supply Ability: 3 Unit/Units per Month meet
your needs
Payment Terms: L/C,T/T
38. ReadyMixConcretePlantInstallation
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Mixing Plant Details for Belt Conveyor type Concrete Batching Plant
Specification’s.andPictures
PlantModelPicture-1 PlantModelPicture-2
39. ReadyMixConcretePlantInstallation
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Mixing Plant Details for Belt Conveyor type Concrete Batching Plant
Specification’s.andPictures
PlantModelPicture-3 PlantModelPicture-4
40. ReadyMixConcretePlant’s Brand& Specification’s.
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Above mentioned ready mix concrete plant’s Specifications
And complete set plants rate (Approximately)
Beltconveyortypeof concretebatchingplantis thebestchoicefor
highqualityconcreteproductionor hugeconstructionproject.
Main Technical Parameters:
Model HZS50/60 HZS75/90 HZS100/120 HZS130/150
Capacity (m3/h) 50/60 75/90 100/120 130/150
Concrete Mixer Volume (L) 1000 1500 2000 3000
Aggregate Feeding Type Skip/Belt Skip/Belt Belt Conveyor Belt Conveyor
Total Installation Power (KW) 109 145 190 250
Concrete Mixer Power (KW) 37/2×18.5 45/2×30 2×37 2×55
Aggregate Weighing Range (KG) 3000 3800 5000 7500
Cement Weighing Range (KG) 600 1000 1200 1800
Discharging Height(mm) 3900 3900 3900 3900
Max. Aggregate Size (mm) 60~80 60~80 60~80 80~100
RATE: Approximately 11 core Taka. Including Mixture, Pump truck and One
Set Plant.
41. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Concrete batching plant working flow
Working Flow:
1. Set the concrete mixture ratio, based on the project standard;
2. Input the ready mixture ratio into the control system, or manual
control;
3. Start the concrete batching plant, the concrete mixer truck ready;
4. Transfer the ready mix concrete to work-site, by concrete mixer
truck or concrete pump;
5. Next batch keep batching, weighing and mixing, other parts ready
for replenishment, etc.
42. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Advantage of Using Ready mix
Concrete Plant
43. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
STONE CRUSHING PLANT
44. StoneCrushingPlantInstallation
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Required land for plant installation: 5 Bigha Approximately.
Crushing Plant Details:
1. Picture:
Platform Construction Summary:
As per Equipment supply companies providing drawing and design
all construction will be done.
Jaw Crushing Machine – 1 Jaw Crushing Machine - 2
46. ReadyMixConcretePlant’s Brand& Specification’s.
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Above mentioned Stone Crushing plant’s Specifications
And complete set plants rate (Approximately)
Characteristics of Jaw Crusher:
-High ratio of crushing,
-Even final size,
-Simple structure,
-Reliable working condition,
-Easy maintenance,
-Low operating cost.
47. ReadyMixConcretePlant’s Brand& Specification’s.
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
MainTechnical Data & Product Price:
Model
Max. Feeding Size
(mm)
Discharge Size
(mm)
Capacity (t/h) Motor Power (kW)
Overall Dimensions
(mm)
Weight (t)
PE150×250 125 10-40 1-3 5.5 896×745×935 0.8
PE250×400 200 20-60 5-20 15 1150×1275×1240 2.8
PE400×600 350 40-100 15-60 30 1700×1732×1653 6.5
PE500×750 425 50-100 50-100 55 2035×1921×2000 10.3
PE600×900 480 65-160 60-130 75 2290×2206×2370 16.5
PE750×1060 630 80-140 80-180 110 2620×2302×3110 29
PE900×1200 750 95-165 140-260 110 3789×2826×3025 54.5
PE1000×1200 850 195-265 315-550 110 3335×3182×3025 57
PE1200×1500 1020 150-300 400-800 160-220 4200×3750×3820 100.9
PEX250×750 210 25-60 10-40 22 1667×1545×1020 5
PEX250×1000 210 25-60 15-50 30 1550×1964×1380 6.5
PEX250×1200 210 25-60 20-60 37 1560×2104×1415 7.7
RATE: Approximately 6.5 core Taka. Including Conveyers belt, all related
machine and One Set Plant.
48. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Advantage of Using jaw Stone
Crushing Plant
49. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
NEED TO WIDELY REFORM
DEPARTMENTOF QUALITYCONTROLAND
INCLUDINGENGINEERINGAUDITMANAGEMENT.
(Under Construction Department)
50. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
Construction QualityControl
Construction quality control can provide quality control inspections at all stages of construction during
both commercial and residential construction projects.
Quality of the construction must be maintained throughout the duration of the project in order for a
project to be completed successfully.
Don't leave it too late; the final stages of construction are usually too late for many items to be
rectified. This may leave you with a property that does not meet your expectations and is considerably
lower value than you had budgeted on.
Qualitycontrolitemscoveredinqualitycontrolinspections:
Ensure high quality materials are used.
Ensure the related all required testing and documentation.
Ensure the materials are installed correctly.
Ensure that the quality of installation is up to the desired standard according to the client.
Ensure that the Engineers requirements are followed correctly.
Ensure the Architectural plans are followed correctly.
Ensure any variations to the project are performed correctly.
Ensure the project meets the Building Codes and Standards of Bangladesh.
Produce maintenance and defects lists for repair.
Objectiveof QualityControl
51. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
WHATWOULDBE THE CONSTRUCTION QUALITYCONTROLMANAGEMENTS
WORKFLOW?
Root of success Diagramfor Construction Quality Control Management.
On going All Finishing
Work Check &
Monitoring Including
Record Maintain.
On going Superstructure Construction Work
check & Monitoring including record maintain.
All Sanitary & Plumbing
workup to fixture fixing check
and Monitoring including
record maintain.
All construction related field test take care and
record maintain and report provide to top
management & Project management
Check the project patty cash and store
management and maintain standard
format to track the record.
Complete Project Handing Over
Procedure Maintain as per standard
handing over formate.
Related all sub contractors running and
final bill checking quantity ensuring as
per project plan and maintain record by
standard formate.
52. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
WHATWOULDBE THE CONSTRUCTION QUALITYCONTROLMANAGEMENTS
WORKFLOW?
Root of success Diagramfor Construction Quality Control Management.
QUALITY CONTROL AND
ENGINEERING AUDIT
MANAGEMENT DEPARTMENT
Above Mentioned
Responsibility maintainBy
This Department
After that Final
Out Put Is Like
That
Provide Monthly
Report to Project
management and
Top management.
53. Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
WHY CONSTRUCTIONQUALITYCONTROLMANAGEMENTS IS HIGHLY
REQUIRED?
Presently Our Esteemed Organization’s Have No Specific
Engineering Quality Control Management Department But
When SAP PS module will start journey in this organization then
this department will be highly requiredto give the support to
SAP.
54. SAP – ERP SOFTWARE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
ImplementedGoingon Under Department of Information System
An Enterprise Resource Planning (ERP) system is an
integrated application used to manage internal and external
resources, including tangible assets, financial resources,
materials, project construction, real state and human
resources. Its purpose is to facilitate the flow of information
between all business functions inside the boundaries of the
organization and manage the connections to outside
stakeholders.
SAP is the world best ERP Software having more than 70%
market share in the market.
SAP ERP provides the foundation to quickly read, evaluate,
and respond to changing business conditions with accurate,
reconciled and timely financial data.
SAP ERP automates dispute, credit, and collections
management – and offers electronic invoicing and payment
capabilities that supplement traditional accounts receivable
and accounts payable functions to accelerate and manage
cash flow.
SAP ERP gives proper inventory and purchase report.
Why we are going to using the SAP – ERP
Software
55. SAP – ERP SOFTWARE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
ImplementedGoingon Under Department of Information System
SAP ERP provides accurate project planning facilities by
which we can control total project during execution, risk
assessment and mitigation, profitability calculation, project
performance evaluation and procuring material transparently
as per project demand. We can also track the project progress
by every moment and monitor quality control of construction.
SAP ERP helps to operate effective shared-services,
collaborate with customers or suppliers, and streamline
operations to reduce costs and resource demands.
By using SAP we can transparent our business process,
reduce costs and reduce redundant working procedure.
Why we are going to using the SAP – ERP
Software
56. SAP – ERP SOFTWARE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
ImplementedGoingon Under Department of Information System
Finance (FI)
Controlling (CO)
Asset Accounting (AA)
Sales & Distribution (SD)
Material Management (MM)
Real Estate (RE)
Project Systems (PS)
Work Flow
Mobile Interfacing
Asset accounting and controlling has been focused in this
implementation with separate consultant. Newly, Workflow
and Mobile Integration module has been added in this scope.
SCOPE OF WORK IN SAP - ERP
57. SAP – ERP SOFTWARE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
ImplementedGoingon Under Department of Information System
SAP Workflow is a process tool that is
designed to facilitate and automate business
processes involving the tasks sequence
performed by the users (people in the
workplace) and ensure that the right work is
assigned in the right sequence at the right
time to the right person in the workflow.
Using SAP Workflow, each step of a
business transaction can be easily monitored
throughout the initiation and completion of
the business processes. The SAP Workflow
enables the process owners to track
deadlines, determine the workload as well as
provide statistics on the length of time to
complete work processes.
What is Workflow in SAP –
ERP Software
58. SAP – ERP SOFTWARE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
ImplementedGoingon Under Department of Information System
The SAP workflow can be linked to mail and mobile. All
workflows processes and items can be mobilized such as:
purchase or sales approval, supplier evaluation, invoices,
financial and inventory reports and even creation of new data
is possible.
Example: When a person creates a purchase requisition, their higher
authorities get automatically notified by email or mobile. Then
authority can give approval by using his desktop pc or mobile.
SAP users can see different reports by using mobile.
What is Mobile Interfacing in SAP – ERP ?
59. SAP – ERP SOFTWARE
Borak Real Estate (Pvt.) Ltd . DEPARTMENT OF PROJECT
DEVELOPMENT
ImplementedGoingon Under Department of Information System
SAP Implementer Selection: To complete the SAP Implementation, we have
already have several meeting with each of the SAP Implementer who already
have implemented SAP in several organizations.
Consultant Selection: According to our Module scopes (FICO, SD, MM, RE, PS,
BASIS, ABAP, WORK FLOW, MOBILE INTERFACING), we have been selecting
consultants by interview sessions from around 60-70 consultants. All of them are
experienced on implementing end-to-end projects and 10-12 consultants would
be selected for our implementation.
Recruitment: As per honorable Managing Directors instruction, Key Users
recruitment for different modules of SAP is under progress for smooth operation
of SAP ERP Implementation. An initial interview of around 75 candidates for Key
Users has already been done and final selection is going on. Three (03) IS team
member have already been recruited for support from technical aspect.
Project Implementation Completion: Project completion of SAP implementation
is forecasted to Go-Live within 3 – 3.5 months from the starting of
implementation. Depending upon the finalization of the Implementer, Key Users
and others; project Kick-Off could be started at the end of November.
Latest Development in USAP – ERP
On going Project’s