PROJECT MANAGEMENT (MGT60403)
DEFINING AND DOCUMENTING A PROJECT
A REPORT BY:
CHAI PHEY CHIAT 0334480
TUTOR: AR. EMMANUEL CANLAS
DOUBLE STOREY DETACHED INDUSTRIAL BUILDING,
LIMBANG, SARAWAK
CONTENTS
1.0 PROJECT INTRODUCTION
2.0 TEAM MEMBERS IN A PROJECT TEAM
2.1 ROLES AND RESPONSIBILITIES OF THE ARCHITECT AS LEAD CONSULTANT
2.2 ROLES AND RESPONSIBILITIES OF OTHER CONSULTANTS
3.0 ORGANIZATION STRUCTURE
4.0 STAKEHOLDERS
5.0 PROJECT INFORMATION
5.1 OBJECTIVES AND GOALS
5.2 IMPLEMENTATION PHASES
5.3 IMPLEMENTATION TOOLS
5.4 MONITORING TOOLS & STRATEGIES
5.5 SUCCESS CRITERIA
6.0 CONCLUSION (REFLECTION WRITING)
1.0 PROJECT INTRODUCTION
This is a project located in Limbang, Sarawak where the clients planned to have an industrial building for
cold-storage storage and also a management office within the proposal. The total cost of the project is
RM885900 which is within the estimated budget, and the quality of the construction is up to the expected
standard.
Since this project is located in Sarawak, the procedure of project management will be a bit different, but the
outcome of a successful building is the same due to the three different criteria which shall be discussed in the
report.
From this report, Architect plays an important part in the project, which the Architect involves from the starting of
the project until the end of the project, coordinate with other consultants to make the project successful. The roles
of an Architect can be seen from any section in this report. It shows that Architect’s involvement is very
important in a project and as a lead consultant.
Project Name : Double Storey Detached Industrial Building ( For Non-Combustible Material)
Project Function : Commercial
Project Location : Lot 1686, Limbang Town District
Project Budget : RM 890 000
Project Duration : 30 months (August 2017 to January 2020)
Client : Lim Lan Chuan & Ngu Ung Siew
2.0 TEAM MEMBERS IN A PROJECT TEAM
2.1 ROLES AND RESPONSIBILITIES OF THE ARCHITECT AS LEAD CONSULTANT
2.1.1 COMPANY’S BACKGROUND
John Lau Architect is founded by John Lau
Ngee Tack, a registered architect with PAM.
It is an architecture firm established in 1996
and is based in Miri, Sarawak
john lau Architect
2.1.2 ROLES OF THE ARCHITECT
PRE-DESIGN SERVICES:
1. Conduct feasibility and environmental impact studies
2. Site selection
3. Prepare cost analysis and land-use studies
4. Specify design requirements
BASIC SERVICES:
1. Schematic Design Phase
a. Understanding of project brief and goals given by
the client.
b. Meetings with clients, production of sketches, basic
building designs
c. Initial rough cost estimation based on building
design selected by client’s aesthetic preferences
d. Establishment of rough drawings regarding the size,
location, and the relationship between spaces
2. Design Development
a. Prepare for the submission of drawings to local
authorities for approval
b. Revise drawings with specific detail and design
modification
c. Update for the estimation of cost
3. Contract Documentation
a. Production of detailed drawings for the
construction of projects with specification
b. Tender drawings production and preparation
of Bill of Quantity
c. Preparation of tender drawings and
documents to obtain necessary permits
4. Contract Implementation & Management
a. Periodic progress checking to ensure
contractor follows contract document.
b. Keep track of the project progress to avoid
scope growth, cost overrun or schedule delays.
5. Final Completion
a. Final testing, inspection and payment
b. Issue final certificate of payment to client and
contractor.
POST-CONSTRUCTION SERVICES:
1. Conduct test and construction cost payment
2. Facilities Management
3. Advise on energy efficiency measures
4. Evaluate building design to the needs of occupants
5. Make necessary improvements
6. Works as interior designer or M&E consultants
2.2 ROLES AND RESPONSIBILITIES OF OTHER CONSULTANTS
2.2.1 CIVIL AND STRUCTURAL (C&S) ENGINEER
Roles of C&S Engineer in this Project
1. Initial Stage
• Site investigation and verification of the site feasibility
2. Design Stage
• Provide consultancy services including:
- Design and construction planning
- Execution and maintenance of infrastructure works
• C&S Engineers are Professional Engineer with Practising Certificate (PEPC) to be
Submitting Person (SP) to submit and deal with Appendix B projects to authorities.
3. Construction Phase
• Monitoring the construction activities are done to meet the quality standards that
comply with statutory and regulatory phases, within the planned schedules and
budgets.
4. FInal Stage
• Verification of the completed infrastructure works
• The chosen SP certify the selected Form G for infrastructure works before the
issuance of Occupation Permit (OP).
• The submission of Form F can only be done by C&S Engineer that is eligible to be
Principal Submitting Person (PSP) as listed in Appendix B and C of the Joint
Memorandum.
WONG TIEN HUA & associates
BUILDING & CIVIL ENGINEERING CONSULTANT,
Lot 634, 1st Floor, North Yu-Seng Road,
P.O.Box 1144, 98008 MIRI.
Tel / Fax: 085-411449
Form G to be certified by Submitting
Person (SP):
Form G1 - Earthworks
Form G3 - Foundations
Form G4 - Structural
Form G5 - Internal Cold Water Plumbing
Form G6 - Internal Sanitary Plumbing
Form G8 - Fire Fighting Passive
Form G12 - Building
Form G13 - External Water Supply
Form G14 - Sewerage Reticulation
Form G15 - Sewerage Treatment Plant
Form G17 - Road and Drainage
Form G19 - External Main Drain
Form G21 - Landscape
2.2.2 MECHANICAL AND ELECTRICAL (M&E) ENGINEER
Roles of M&E Engineer
1. Design Stage
• Start on structure as well as plumbing, electrical, ventilation systems energy analysis and any other
project specific systems.
2. Construction Stage
• Ensure construction activities are done to meet the quality standards that are comply with statutory
and regulatory phases, within the planned schedules and budgets.
3. Final Stage
• The M&E Engineer that is chosen as the SP would require to certify the selected Form G for
infrastructure works before the issuance of Occupation Permit (OP).
Form G to be certified by Submitting Person (SP):
Form G5 - Internal Cold Water Plumbing (Mechanical)
Form G6 - Internal Sanitary Plumbing (Mechanical)
Form G7 - Internal Electrical (Mechanical)
Form G9 - Fire Fighting Active (Mechanical)
Form G10 - Mechanical Ventilation (Mechanical)
Form G11 - Lift / Escalator (Mechanical)
Form G16 - External Electrical (Electrical)
Form G18 - Street Lighting (Electrical)
Form G20 - Telecom (Electrical)
SUKIADA ENGINEERING SDN. BHD.
MIRI
2.2.3 QUANTITY SURVEYOR
LANCE LAW (Free Lance Quantity Surveyor)
Roles of Quantity Surveyor
● Known as the construction cost consultant or commercial manager to manage project finances and
contractual relationships.
● Give advice to client what is affordable to be built on site, provides particular scope of work periodically
with detailed cost information, and manage legal and contractual matters.
1. Pre-Construction Stage
• Work on the estimation of materials, time, and labour costs
• Provide preliminary cost estimates and plans for the development of projects
• Preparation of tender document and estimation of construction cost
• Provide advice for the selection of contractors
• Organize calling of tenders
2. Construction Stage
• Variation evaluation
• Preparation of certificate of progress payment
• Evaluate progress claim through site evaluation
3. Post-Construction Stage
• Assess Building Replacement Value for insurance
• Final settlement of final project account
2.2.4 LAND SURVEYOR
BLESSES EARTH SURVEY SERVICES Miri, Sarawak
Roles of Land Surveyor
● Determine property bounderies
● Take exact measurements required from the site
● Provides data related to the contour, gravitation, shape, location, elevation, or dimension of land or land
features on or near the earth's surface for engineering, mapmaking, mining, land evaluation, construction,
and other purposes.
2.2.5 MAIN CONTRACTOR
MEGA AMPLE SDN. BHD. MIRI, SARAWAK
Roles of the Main Contractor (Appointed under Lump Sump Contract)
• Responsible in planning, monitoring and controlling the entire construction works during construction phase
• Provides a fixed budgets according to the required set of tender document produced by Quantity Surveyor
• Provides supervision, information and instruction to the workers on site while complying with health and safety
specifications.
3.0 ORGANIZATION STRUCTURE
Client:
Lim Lan Chuan
Ngu Ung Siew
Architect / Project Manager:
John Lau Architect
Civil & Structural Engineer:
WONG TIEN HUA &
associates
Mechanical & Electrical Engineer:
SUKIADA ENGINEERING
SDN. BHD.
Main Contractor:
MEGA AMPLE SDN. BHD.
Consultants
Quantity Surveyor:
Lance Law
(Free-Lance Quantity Surveyor)
Land Surveyor:
BLESSED EARTH
SURVEY SERVICES
4.0 STAKEHOLDERS
An individual or a party (group or organization) who has an interest to invest in a project which will affect and cause an
impact throughout the process and completion of a project.
The stakeholders can be further divided into:
Internal Stakeholder: Individuals or groups who are involved in operational processes, directly or financially, or both
External Stakeholder: Indirectly influenced by the organization’s operation, have no financial stake in the organization
Double Storey Detached
Industrial Building
Internal Stakeholder
Demand
External Stackholder
Client:
• Lim Lan Chuan
• Ngu Ung Siew
Supply
Consultants:
• Architects
John Lau Architect
• Civil & Structural Engineer
WONG TIEN HUA & Associates
• Mechanical & Electrical Engineer
Sukiada Engineering
• Quantity Surveyor
Lance Law (Free Lance Quantity Surveyor)
• Land Surveyor
Blessed Earth Survey Services
Supply
Contractor:
• Main Contractor
Mega Ample Sdn. Bhd.
Public
Local Governments:
• Limbang Council District
Regulatory Agencies:
• Sarawak Energy (SESCO)
• Laku Management Sdn. Bhd.
(Water Supply)
• Jabatan Bomba dan
Penyelamat Malaysia (BOMBA)
• Jabatan Kerja Raya (JKR)
• Drainage Irrigation
Department Limbang Division
(DID)
• Telekom Malaysia (TM)
Landowner
Media
Private
5.0 PROJECT INFORMATION
Every project requires a process in order to make it as a successful project:
● Includes identification of objectives and goals of a project,
● running of the construction implementation phases with the integration of implementation tools,
● determine the tools and construction strategies,
● and achieving the successful criteria for the project by having a balance between cost, time, and
quality.
5.1 OBJECTIVES AND GOALS
● to complete each phases of this project accordingly as stated in the contract on time and make sure of
its best quality presented to the client.
The objectives and goals of the project:
1. To determine the project objectives and plans including precise scope of work, budgeting, setting
performance requirements, project participants and make sure each the project is following the scheduled
timeline
2. To ensure finances are under control through proper time management and minimal changes
3. To perform strict supervision to solve project issues and conflicts to reduce project failing risk
4. To conduct proper construction management to achieve satisfactory outcomes in all aspects in terms of
progress, standards, finance, time, resources, materials, and equipments.
5.2 IMPLEMENTATION PHASE
Schematic Design Design Development Contract Documentation
Contract Implementation
& Management
Final Completion
5.2.1 SCHEMATIC DESIGN
5.2.1.1 DESIGN BRIEF
● The clients initiated the schematic design stage by approaching to John Lau Architect by using conventional
procurement method where the Architect is given the responsibility to approach other consultant teams.
● The clients gave full responsibility for the Architect to build up a concept and vision.
● This means the Architect has to develop the project brief himself.
● The consultants then carried out feasibility study for the project based on the current market value and demands.
● Clients requested a double storey detached industrial building for non-combustible material on lot 1686 at
Limbang Town District.
5.2.1.2 SUBMISSION FOR APPROVAL
● A new building must be submitted for approval to State Planning Authority (SPA) but this project is an
exception from the list.
● The land itself has the title for ‘Industrial Use Only’ and therefore it is not required for SPA approval as the
client requested for an industrial building, unless the new building to be built is a building with other
purposes.
5.2.2 DESIGN DEVELOPMENT
● Development Order (DO) Approval is not needed to be obtained from the Authority.
● Schematic plans and elevations are revised to include details and specification required for the construction to be
understood by the contractor.
● Project budget could be determined by the Quantity Surveyor and the schedule of construction work could be
done by the contractor with the finalized building plans and drawings.
5.2.2.1 DRAWINGS PREPARATION
● The drawings were reviewed by the
Architect to produce detailed design
drawings with elaborated floor plans,
sections, elevations, detailings as well
as door and window schedules.
● The drawings also will be included with
materials used for the structures.
● The detailed design drawings will be
forwarded to other consultants for
further detailing according to their
respective job scope.
The C&S Engineer:
● Designed detailed infrastructure
plans and prepared the structural
plans and load report of the building.
The M&E Engineer:
● Responsible to design detailed
mechanical and electrical plan.
Quantity Surveyor:
● Draft cost estimation to tally with the
budget.
Contractors
● Obtain materials’ specifications from
the supplier together with the
quotation required.
The above drawing is the detailed floor plan drawn by
the Architect.
The below drawing is one of the drawings prepared by
Civil and Structural Engineer.
5.2.2.2 CLIENTS’ APPROVAL
● A meeting known as Client-Consultant Meeting (CCM) was held to update the progress of the
project and to obtain client’s approval. Aspects that were discussed:
1. Confirmation of building design
2. Building drawings
3. Other consultants’ progress
● An agreement was made between the architect and the client regarding the amendments and
cost adjustments after the discussion.
5.2.2.3 SUBMISSION OF DRAWINGS FOR BUILDING APPROVAL
Once drawings approved, drawings were
submitted for building approval which include:
1. 1 set to Limbang District Council
2. 2 sets to BOMBA
3. 1 set to Sarawak Energy (SESCO)
4. 1 set to Laku Management Sdn. Bhd.
(Water Supply)
5. 1 set to Jabatan Kerja Raya (JKR)
6. 1 set to Drainage Irrigation Department
(DID) Limbang Division
7. 1 set to Telekom Malaysia (TM)
● Submission of drawings for building
approval in Sarawak: no pre-consultation
and technical meeting with the local
authorities is required.
● Drawings were coloured before they were
submitted for approval. Each submission
takes about 1 or 2 months to get
processed.
● The drawings will be rejected for the first
time. The Architect and the other
consultants would revise the rejected
drawings, reprint, and resubmitted.
● Once approved, it is the end of design
development phase.
The above drawing is the one of the Building Plan
submission drawings
5.2.3 CONTRACT DOCUMENTATION
● It is a phase that all the required materials, the constructions, and the structures to be documented
by the Quantity Surveyor to allow the commencement of works by the contractor.
● Further revised of drawings with details to produce the tender drawings and the construction
drawings.
5.2.3.1 TENDER DOCUMENTATION
● The document includes detailed drawings and specification details prepared by consultants,
and Bill of Quantity (BQ) that are delivered by the Quantity Surveyor.
● John Lau Architect was fully responsible for the tender drawings’ updates prior to CCM.
● Bill of Quantities (BQ) is prepared by Quantity Surveyor and was prepared in a “taking off”
process (process of identifying elements of construction) which cost of construction is
estimated from measurements based on consultants’ drawings.
● Quantity Surveyor provides the scope of works, specification, project items with quantities
through the information that was given and identified from the tender drawings.
5.2.3.2 TENDER INVITATION
The project undergone negotiated tender: Clients invite their own desired contractors to go for
tendering process. 3 contractors of their choice are the selected for this project.
5.2.3.3 TENDER EVALUATION
5.2.3.4 AWARD OF CONTRACT
● John Lau Architect and the clients are responsible for the tender evaluation.
● Interviews are needed to be attended by the 3 contractors of the clients’ choice in order to get
evaluated by the architects and the clients.
● After interviews between the selected contractors and the architect together with clients, clients
will select the best tender of their choice. (Mega Ample Sdn. Bhd. was awarded)
● The contract of agreement is done by the clients’ side, it is signed in between the clients and the
contractor prior agree to the details and conditions of the contract. It acts as the evidence of the
acceptance of contract.
5.2.4 CONTRACT IMPLEMENTATION AND MANAGEMENT
5.2.4.1 PRE-COMMENCEMENT PHASE
5.2.4.2 PROJECT QUALITY COMPLIANCE PLAN (PQP)
This phase took around two weeks to process which include:
1. Initial meeting to introduce the team and agreement of the methods and timeline.
2. Compilation and hand over the required documents to contractor.
3. Site supervisory staff briefing to ensure construction works are done within the specific technical
documentation and construction permit.
4. Submission of Borang B to the local council to notify the commencement of work, which the
notification for the commencement of work is to be received by the contractors.
● Prepared by the contractor to report the roles of the parties involved and the important details to
achieve the quality in the project.
● To assure the quality of the construction, weekly work progress and inspection checklist are given,
● A set of forms including Request for Information and other forms are attached for daily records.
5.2.4.3 COMMENCEMENT OF WORK
A) SITE MEETING
● Discuss progress report and issues that might affect construction.
● Done monthly or during claim payment made since the starting of construction.
● No Minutes of Meeting is done as it is regarded as non-formal meeting and site works among
the architect, contractor, and clients.
B) REQUEST FOR INFORMATION
● RFI is to resolve the issues arose during the early construction process to reduce the costly
corrective measures.
● It is requested by the contractor where architect is needed to provide building plans and
structural plans, and exact detail roofing plan to be approved by C&S Engineer.
● The contractor also requested for handrail details for the manufacturing team to build.
C) ARCHITECT’S INTRUCTION (AI) AND NON-CONFORMENCE REPORT
● Architect’s Intruction is the instructions given by the contract administrator to the contractor.
● AI is only given since some materials cannot be found in Limbang as there are limited sources.
● Non-Conformence Report (NRC) is the issuance of report if the contractor used the materials that
are not approved by the client, failure in design and strength, not following construction
method as per clients’ choice, and other reason.
● No NRC is issued to the contractor since the architect will amend or approve accordingly to suit
the availability of materials in Limbang as long as materials are equivalent to specifications.
D) VARIATION ORDER (VO)
● The alteration of work added to the existing order in terms of alteration of design, the quantity
needed for works, and the modification of sequence of work.
● Issued by the architect and clients in this project which then mentioned to contractor to carry out
alternative changes.
● VO will directly affect the cost and the completion date of the project.
E) REQUEST FOR INSPECTION
F) CERTIFICATE OF PRACTICAL COMPLETION (CPC)
G) INTERIM PAYMENT
● Done by the local authorities to come and inspect and to test the performance of every
structures and services.
● Random investigation towards the industrial building project, which there was no issue regarding
this inspection.
● Issued by the architect to the contractor if the building is done with no defects or damages and
according to specified in the tender documentation.
● CPC allows full collection of payment excluding retention sum that would be released to the
contractor if no defects were found.
● Legally declared the end of the contractor’s liability other than making good defects.
● Certificate of Claim (COC) done in different stages by
the contractor and will be submitted to John Lau
Architect with a summary of work done percentage,
descriptions of items and quantity that have been
used for the construction on site.
● QS will prepare letter of valuation with valuation
certificate before approval of interim claim.
5.2.5 FINAL COMPLETION
5.2.5.1 ISSUANCE OF OCCUPATION PERMIT
5.2.5.2 DEFECT LIABILITY PERIOD (DLP)
Occupation Permit (OP) is required to certify the building that it has comply with necessary approval
and is safe to be used by the occupants before it was handed to the clients. Documents needed:
• Cover letter Principal Submitting Person (PSP) to Jabatan Kawalan Bangunan
• Notice of completion of excavation for foundation
• Borang B
• Borang E
• Borang F
These documents are submitted by Principal Submitting Person (PSP) and Ar. John Lau Ngee Teck is to
submit them once the building was done prior to clients’ approval
● DLP will be started once project handover to clients.
● Known as ‘Warranty Period’ and contractor is responsible to rectify all the defects.
● Last for one year to ensure that the building is well function.
5.2.5.3 ISSUANCE OF FINAL CERTIFICATE
● QS will prepare financial statement for final payment certificate.
● Signed off by contractor as the final settlement.
● The issuance means the construction has been completed and payment is based on final
account agreed by consultants and contractor.
5.3 IMPLEMENTATION TOOLS
Digital softwares were used to complete the drawings and 3D
model of the building:
1. AutoCad
• For drafting of drawings since starting of schematic
design phase to construction phase.
2. Sketchup
• Tool for 3D model to provide illustrations to clients.
Drafting & Design
Digital softwares are needed to keep track all informations in
an organized manner:
1. Microsoft Word
2. Microsoft Excel
3. Microsoft Powerpoint
Documentation
5.4 MONITORING TOOLS & STRATEGIES
● Provide visual overview of a schedule, timeline to keep track plan and to coordinate tasks.
● Display extra information such as the responsibility of the person in charge, overlapping tasks and linking of tasks, and
sequence of each phase in project.
A) Gantt Chart
● Known as the Minutes of Meeting (MoM) to record important information and any issue by meeting participants.
● An agreement agreed by all parties and will be taken as legal instruction in the project.
● There are three types of meetings in the project:
i) Client-Consultant Meeting (CCM)
● Update the progress of project to obtain client’s approval.
● Involves the client and consultants to follow up design progress
● Any disagreement must be raised within predefined period (3 days) from the official copy issuance of written MoM.
ii) Technical Meeting
● Short meeting aimed to solve technical issues and only involves technical team.
● Carried out after the site inspection where issues and concerns will be elaborated.
iii) Site Meeting
● Involves all parties: client, consultants, and contractors which is done monthly or during every claim payment made to
review the progress of the construction works.
● Some of the major issues can be recorded in construction site meeting:
Weather reports, Problem with quality, Circumstances that could violate the contract, Cost impactable issues,
Construction conflicts, Health and safety issues, Design issues, Off-site fabrication and payments
B) Meeting Minutes
5.5 SUCCESS CRITERIA
● The project success factors consists of elements that are required to make sure the project’s successful
completion and this is normally defined in the 3 main aspect known as ‘The Triplet Constraint’.
● Consists of three different factors which are often used to measure the successful level of a project, known as
time, scope, and cost.
TIME
SCOPE COST
QUALITY
● It is able to produce a good quality of project.
● To satisfy these triple success criteria in any project, changing in any will affect the others’ constraints.
● In order to produce a successful project, it is to balance the three factors:
TIME
● The schedule itself is completed with the estimated amount of time to construct the project which allows the
project to be completed before the deadline.
● This industrial building project did not undergo Extension of Time (EOT) and completed in the estimated time.
● The project was done within 30 months.
COST
● Budget should be considered as the criteria for success, which this will benefit both clients and stakeholders.
● The project was designed and constructed within a limited budget (Under RM 890 000).
SCOPE
● It deals with specific requirements and tasks needed to be completed in the project as required.
● If the project is out of control, the cost or time will be increased. In this project.
● No error in this building project and also, all the outcome of the project has been successfully met to the project
brief.
6.0 CONCLUSION (REFLECTION WRITING)
As a conclusion, it can be seen that the project management process is effective in controlling the duration of the project
and it is able to build up a successful project. The projects are easier to be managed in this controlled manner although the
process might seem different between the process in West Malaysia and in Sarawak. Some of the process might not be the
same as what are used throughout the Malaysia but the method of delivering and the goal towards the project is the
same.
In overall, what I have learnt from this internship training is the that are needed to be done by the Architects are practically
important to design and build a building for the client. As what I experienced from my training is, the Architects act as the
coordinator between the consultants, contractors, and the clients, and also the Architects play an important role in
delivering tasks from the beginning of the project until the end of the project. By listing out all the tasks that the
Architects are involved in any particular object, it can be seen that Architects are just not about drafting and drawings and
designing but the Architects are the main person to guide all the process in the project.
In order to build a successful project in real life, it is to deliberate the tasks effectively to all the parties involved in any of
the project. Architects have to think rationally in order to perform tasks and not to bias with any of the parties in order to
get a successful deliverable project to the client.
In order to deliver a successful project, it can be seen that a successful project depends on 3 criteria mainly: Time, Cost, and
Scope. From this triplet constraint for the project, any of the change of the criteria might change the final outcome of the
project or the change of the other two criteria. In order to make a project successful to be constructed, it is to be done
within the Time, Cost, and also the Scope.

More Related Content

What's hot

Project management
Project managementProject management
Project managementBenjamin Tan
 
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...Yamini Kahaliya
 
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmDesign Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmSamuel Boone
 
Preventing savar like tragedy by engr. golam mostafa
Preventing savar like tragedy by engr. golam mostafaPreventing savar like tragedy by engr. golam mostafa
Preventing savar like tragedy by engr. golam mostafaSakib Nizam
 
number 1 Res 2013 Rod Taylor-2
number 1 Res 2013    Rod  Taylor-2number 1 Res 2013    Rod  Taylor-2
number 1 Res 2013 Rod Taylor-2Rodney Taylor
 
Regulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in BangaloreRegulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in Bangalorepiasi sinha
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr Bhavana Deshpande
 
jafar hussain 07-06-2014
jafar hussain 07-06-2014jafar hussain 07-06-2014
jafar hussain 07-06-2014jafar hussain
 
DJ's Corporate Experience & Performance Package (Complete-2014)
DJ's Corporate Experience & Performance Package (Complete-2014)DJ's Corporate Experience & Performance Package (Complete-2014)
DJ's Corporate Experience & Performance Package (Complete-2014)Daniel J Fernandez II
 

What's hot (19)

Mohamed khairy CV
Mohamed khairy CVMohamed khairy CV
Mohamed khairy CV
 
Project management
Project managementProject management
Project management
 
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
 
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmDesign Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
 
Preventing savar like tragedy by engr. golam mostafa
Preventing savar like tragedy by engr. golam mostafaPreventing savar like tragedy by engr. golam mostafa
Preventing savar like tragedy by engr. golam mostafa
 
number 1 Res 2013 Rod Taylor-2
number 1 Res 2013    Rod  Taylor-2number 1 Res 2013    Rod  Taylor-2
number 1 Res 2013 Rod Taylor-2
 
CV - HV-1
CV - HV-1CV - HV-1
CV - HV-1
 
Regulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in BangaloreRegulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in Bangalore
 
Muneer CV 2016
Muneer CV 2016Muneer CV 2016
Muneer CV 2016
 
Oberoi Hotel
Oberoi HotelOberoi Hotel
Oberoi Hotel
 
Pm final
Pm finalPm final
Pm final
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Kandil_Sameh_AR50360
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
Mohannad Al Twait-CV1
Mohannad Al Twait-CV1Mohannad Al Twait-CV1
Mohannad Al Twait-CV1
 
jafar hussain 07-06-2014
jafar hussain 07-06-2014jafar hussain 07-06-2014
jafar hussain 07-06-2014
 
Yihui's pm final
Yihui's pm finalYihui's pm final
Yihui's pm final
 
DJ's Corporate Experience & Performance Package (Complete-2014)
DJ's Corporate Experience & Performance Package (Complete-2014)DJ's Corporate Experience & Performance Package (Complete-2014)
DJ's Corporate Experience & Performance Package (Complete-2014)
 
Mc cv updated 2017
Mc cv   updated 2017Mc cv   updated 2017
Mc cv updated 2017
 
1 Essam CV
1 Essam CV1 Essam CV
1 Essam CV
 

Similar to Project Management Assignment 1

Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Project management (1)
Project management (1)Project management (1)
Project management (1)aarenneoone
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1 Weng Chuan
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a projectJing Fan Koh
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1zerospaces_
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slideSithick Mohamed .
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CVTawfig Adham
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management PlanAnuragBhat7
 
Akhtar Mahmood - Construction Site Engineer (1).doc
Akhtar Mahmood - Construction Site Engineer (1).docAkhtar Mahmood - Construction Site Engineer (1).doc
Akhtar Mahmood - Construction Site Engineer (1).docShahbazAhmad953994
 
7 Design Phases in Architectural Design Process
7 Design Phases in Architectural Design Process7 Design Phases in Architectural Design Process
7 Design Phases in Architectural Design Processarananeust
 
Banesh Pai _ MEP Engineer
Banesh Pai _ MEP EngineerBanesh Pai _ MEP Engineer
Banesh Pai _ MEP EngineerBaneshwar Pai
 
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...REDceo.net
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectIOSR Journals
 

Similar to Project Management Assignment 1 (20)

Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a project
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
 
Real estate investment
Real estate investmentReal estate investment
Real estate investment
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CV
 
RIBA Revit.pdf
RIBA Revit.pdfRIBA Revit.pdf
RIBA Revit.pdf
 
CV
CVCV
CV
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
 
CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015
 
bmc cv (2)
bmc cv (2)bmc cv (2)
bmc cv (2)
 
Akhtar Mahmood - Construction Site Engineer (1).doc
Akhtar Mahmood - Construction Site Engineer (1).docAkhtar Mahmood - Construction Site Engineer (1).doc
Akhtar Mahmood - Construction Site Engineer (1).doc
 
7 Design Phases in Architectural Design Process
7 Design Phases in Architectural Design Process7 Design Phases in Architectural Design Process
7 Design Phases in Architectural Design Process
 
Banesh Pai _ MEP Engineer
Banesh Pai _ MEP EngineerBanesh Pai _ MEP Engineer
Banesh Pai _ MEP Engineer
 
Magazine (ICI)
Magazine (ICI)Magazine (ICI)
Magazine (ICI)
 
MAGAZINE.ppt
MAGAZINE.pptMAGAZINE.ppt
MAGAZINE.ppt
 
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
 

More from DavidJPCChai

The Son of Man - Rene Magritte
The Son of Man - Rene MagritteThe Son of Man - Rene Magritte
The Son of Man - Rene MagritteDavidJPCChai
 
Personal Narrative Essay
Personal Narrative EssayPersonal Narrative Essay
Personal Narrative EssayDavidJPCChai
 
Assignement 2: Structural Analysis
Assignement 2: Structural AnalysisAssignement 2: Structural Analysis
Assignement 2: Structural AnalysisDavidJPCChai
 
Project 1: Structural Design Post Mortem
Project 1: Structural Design Post MortemProject 1: Structural Design Post Mortem
Project 1: Structural Design Post MortemDavidJPCChai
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management ReportDavidJPCChai
 
Does the Home Environment Affect Work from Home?
Does the Home Environment Affect Work from Home?Does the Home Environment Affect Work from Home?
Does the Home Environment Affect Work from Home?DavidJPCChai
 
Building Science II Project 1 Presentation Slides
Building Science II Project 1 Presentation SlidesBuilding Science II Project 1 Presentation Slides
Building Science II Project 1 Presentation SlidesDavidJPCChai
 
Building Science II Project 1 Report
Building Science II Project 1 ReportBuilding Science II Project 1 Report
Building Science II Project 1 ReportDavidJPCChai
 
Building Technology I Project 2
Building Technology I Project 2Building Technology I Project 2
Building Technology I Project 2DavidJPCChai
 
Building Technology I Project 1
Building Technology I Project 1Building Technology I Project 1
Building Technology I Project 1DavidJPCChai
 
Synopsis for Project 2
Synopsis for Project 2Synopsis for Project 2
Synopsis for Project 2DavidJPCChai
 
Building Services Report
Building Services ReportBuilding Services Report
Building Services ReportDavidJPCChai
 
Research in Asian Architecture
Research in Asian ArchitectureResearch in Asian Architecture
Research in Asian ArchitectureDavidJPCChai
 
Culture and History Report
Culture and History ReportCulture and History Report
Culture and History ReportDavidJPCChai
 

More from DavidJPCChai (16)

The Son of Man - Rene Magritte
The Son of Man - Rene MagritteThe Son of Man - Rene Magritte
The Son of Man - Rene Magritte
 
Personal Narrative Essay
Personal Narrative EssayPersonal Narrative Essay
Personal Narrative Essay
 
Think Sheets
Think SheetsThink Sheets
Think Sheets
 
Assignement 2: Structural Analysis
Assignement 2: Structural AnalysisAssignement 2: Structural Analysis
Assignement 2: Structural Analysis
 
Project 1: Structural Design Post Mortem
Project 1: Structural Design Post MortemProject 1: Structural Design Post Mortem
Project 1: Structural Design Post Mortem
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Report
 
Does the Home Environment Affect Work from Home?
Does the Home Environment Affect Work from Home?Does the Home Environment Affect Work from Home?
Does the Home Environment Affect Work from Home?
 
Building Science II Project 1 Presentation Slides
Building Science II Project 1 Presentation SlidesBuilding Science II Project 1 Presentation Slides
Building Science II Project 1 Presentation Slides
 
Building Science II Project 1 Report
Building Science II Project 1 ReportBuilding Science II Project 1 Report
Building Science II Project 1 Report
 
Building Technology I Project 2
Building Technology I Project 2Building Technology I Project 2
Building Technology I Project 2
 
Building Technology I Project 1
Building Technology I Project 1Building Technology I Project 1
Building Technology I Project 1
 
Synopsis for Project 2
Synopsis for Project 2Synopsis for Project 2
Synopsis for Project 2
 
Comparative Essay
Comparative EssayComparative Essay
Comparative Essay
 
Building Services Report
Building Services ReportBuilding Services Report
Building Services Report
 
Research in Asian Architecture
Research in Asian ArchitectureResearch in Asian Architecture
Research in Asian Architecture
 
Culture and History Report
Culture and History ReportCulture and History Report
Culture and History Report
 

Recently uploaded

Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 

Recently uploaded (20)

Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 

Project Management Assignment 1

  • 1. PROJECT MANAGEMENT (MGT60403) DEFINING AND DOCUMENTING A PROJECT A REPORT BY: CHAI PHEY CHIAT 0334480 TUTOR: AR. EMMANUEL CANLAS DOUBLE STOREY DETACHED INDUSTRIAL BUILDING, LIMBANG, SARAWAK
  • 2. CONTENTS 1.0 PROJECT INTRODUCTION 2.0 TEAM MEMBERS IN A PROJECT TEAM 2.1 ROLES AND RESPONSIBILITIES OF THE ARCHITECT AS LEAD CONSULTANT 2.2 ROLES AND RESPONSIBILITIES OF OTHER CONSULTANTS 3.0 ORGANIZATION STRUCTURE 4.0 STAKEHOLDERS 5.0 PROJECT INFORMATION 5.1 OBJECTIVES AND GOALS 5.2 IMPLEMENTATION PHASES 5.3 IMPLEMENTATION TOOLS 5.4 MONITORING TOOLS & STRATEGIES 5.5 SUCCESS CRITERIA 6.0 CONCLUSION (REFLECTION WRITING)
  • 3. 1.0 PROJECT INTRODUCTION This is a project located in Limbang, Sarawak where the clients planned to have an industrial building for cold-storage storage and also a management office within the proposal. The total cost of the project is RM885900 which is within the estimated budget, and the quality of the construction is up to the expected standard. Since this project is located in Sarawak, the procedure of project management will be a bit different, but the outcome of a successful building is the same due to the three different criteria which shall be discussed in the report. From this report, Architect plays an important part in the project, which the Architect involves from the starting of the project until the end of the project, coordinate with other consultants to make the project successful. The roles of an Architect can be seen from any section in this report. It shows that Architect’s involvement is very important in a project and as a lead consultant. Project Name : Double Storey Detached Industrial Building ( For Non-Combustible Material) Project Function : Commercial Project Location : Lot 1686, Limbang Town District Project Budget : RM 890 000 Project Duration : 30 months (August 2017 to January 2020) Client : Lim Lan Chuan & Ngu Ung Siew
  • 4. 2.0 TEAM MEMBERS IN A PROJECT TEAM 2.1 ROLES AND RESPONSIBILITIES OF THE ARCHITECT AS LEAD CONSULTANT 2.1.1 COMPANY’S BACKGROUND John Lau Architect is founded by John Lau Ngee Tack, a registered architect with PAM. It is an architecture firm established in 1996 and is based in Miri, Sarawak john lau Architect 2.1.2 ROLES OF THE ARCHITECT PRE-DESIGN SERVICES: 1. Conduct feasibility and environmental impact studies 2. Site selection 3. Prepare cost analysis and land-use studies 4. Specify design requirements BASIC SERVICES: 1. Schematic Design Phase a. Understanding of project brief and goals given by the client. b. Meetings with clients, production of sketches, basic building designs c. Initial rough cost estimation based on building design selected by client’s aesthetic preferences d. Establishment of rough drawings regarding the size, location, and the relationship between spaces 2. Design Development a. Prepare for the submission of drawings to local authorities for approval b. Revise drawings with specific detail and design modification c. Update for the estimation of cost 3. Contract Documentation a. Production of detailed drawings for the construction of projects with specification b. Tender drawings production and preparation of Bill of Quantity c. Preparation of tender drawings and documents to obtain necessary permits 4. Contract Implementation & Management a. Periodic progress checking to ensure contractor follows contract document. b. Keep track of the project progress to avoid scope growth, cost overrun or schedule delays. 5. Final Completion a. Final testing, inspection and payment b. Issue final certificate of payment to client and contractor. POST-CONSTRUCTION SERVICES: 1. Conduct test and construction cost payment 2. Facilities Management 3. Advise on energy efficiency measures 4. Evaluate building design to the needs of occupants 5. Make necessary improvements 6. Works as interior designer or M&E consultants
  • 5. 2.2 ROLES AND RESPONSIBILITIES OF OTHER CONSULTANTS 2.2.1 CIVIL AND STRUCTURAL (C&S) ENGINEER Roles of C&S Engineer in this Project 1. Initial Stage • Site investigation and verification of the site feasibility 2. Design Stage • Provide consultancy services including: - Design and construction planning - Execution and maintenance of infrastructure works • C&S Engineers are Professional Engineer with Practising Certificate (PEPC) to be Submitting Person (SP) to submit and deal with Appendix B projects to authorities. 3. Construction Phase • Monitoring the construction activities are done to meet the quality standards that comply with statutory and regulatory phases, within the planned schedules and budgets. 4. FInal Stage • Verification of the completed infrastructure works • The chosen SP certify the selected Form G for infrastructure works before the issuance of Occupation Permit (OP). • The submission of Form F can only be done by C&S Engineer that is eligible to be Principal Submitting Person (PSP) as listed in Appendix B and C of the Joint Memorandum. WONG TIEN HUA & associates BUILDING & CIVIL ENGINEERING CONSULTANT, Lot 634, 1st Floor, North Yu-Seng Road, P.O.Box 1144, 98008 MIRI. Tel / Fax: 085-411449 Form G to be certified by Submitting Person (SP): Form G1 - Earthworks Form G3 - Foundations Form G4 - Structural Form G5 - Internal Cold Water Plumbing Form G6 - Internal Sanitary Plumbing Form G8 - Fire Fighting Passive Form G12 - Building Form G13 - External Water Supply Form G14 - Sewerage Reticulation Form G15 - Sewerage Treatment Plant Form G17 - Road and Drainage Form G19 - External Main Drain Form G21 - Landscape
  • 6. 2.2.2 MECHANICAL AND ELECTRICAL (M&E) ENGINEER Roles of M&E Engineer 1. Design Stage • Start on structure as well as plumbing, electrical, ventilation systems energy analysis and any other project specific systems. 2. Construction Stage • Ensure construction activities are done to meet the quality standards that are comply with statutory and regulatory phases, within the planned schedules and budgets. 3. Final Stage • The M&E Engineer that is chosen as the SP would require to certify the selected Form G for infrastructure works before the issuance of Occupation Permit (OP). Form G to be certified by Submitting Person (SP): Form G5 - Internal Cold Water Plumbing (Mechanical) Form G6 - Internal Sanitary Plumbing (Mechanical) Form G7 - Internal Electrical (Mechanical) Form G9 - Fire Fighting Active (Mechanical) Form G10 - Mechanical Ventilation (Mechanical) Form G11 - Lift / Escalator (Mechanical) Form G16 - External Electrical (Electrical) Form G18 - Street Lighting (Electrical) Form G20 - Telecom (Electrical) SUKIADA ENGINEERING SDN. BHD. MIRI
  • 7. 2.2.3 QUANTITY SURVEYOR LANCE LAW (Free Lance Quantity Surveyor) Roles of Quantity Surveyor ● Known as the construction cost consultant or commercial manager to manage project finances and contractual relationships. ● Give advice to client what is affordable to be built on site, provides particular scope of work periodically with detailed cost information, and manage legal and contractual matters. 1. Pre-Construction Stage • Work on the estimation of materials, time, and labour costs • Provide preliminary cost estimates and plans for the development of projects • Preparation of tender document and estimation of construction cost • Provide advice for the selection of contractors • Organize calling of tenders 2. Construction Stage • Variation evaluation • Preparation of certificate of progress payment • Evaluate progress claim through site evaluation 3. Post-Construction Stage • Assess Building Replacement Value for insurance • Final settlement of final project account
  • 8. 2.2.4 LAND SURVEYOR BLESSES EARTH SURVEY SERVICES Miri, Sarawak Roles of Land Surveyor ● Determine property bounderies ● Take exact measurements required from the site ● Provides data related to the contour, gravitation, shape, location, elevation, or dimension of land or land features on or near the earth's surface for engineering, mapmaking, mining, land evaluation, construction, and other purposes. 2.2.5 MAIN CONTRACTOR MEGA AMPLE SDN. BHD. MIRI, SARAWAK Roles of the Main Contractor (Appointed under Lump Sump Contract) • Responsible in planning, monitoring and controlling the entire construction works during construction phase • Provides a fixed budgets according to the required set of tender document produced by Quantity Surveyor • Provides supervision, information and instruction to the workers on site while complying with health and safety specifications.
  • 9. 3.0 ORGANIZATION STRUCTURE Client: Lim Lan Chuan Ngu Ung Siew Architect / Project Manager: John Lau Architect Civil & Structural Engineer: WONG TIEN HUA & associates Mechanical & Electrical Engineer: SUKIADA ENGINEERING SDN. BHD. Main Contractor: MEGA AMPLE SDN. BHD. Consultants Quantity Surveyor: Lance Law (Free-Lance Quantity Surveyor) Land Surveyor: BLESSED EARTH SURVEY SERVICES
  • 10. 4.0 STAKEHOLDERS An individual or a party (group or organization) who has an interest to invest in a project which will affect and cause an impact throughout the process and completion of a project. The stakeholders can be further divided into: Internal Stakeholder: Individuals or groups who are involved in operational processes, directly or financially, or both External Stakeholder: Indirectly influenced by the organization’s operation, have no financial stake in the organization Double Storey Detached Industrial Building Internal Stakeholder Demand External Stackholder Client: • Lim Lan Chuan • Ngu Ung Siew Supply Consultants: • Architects John Lau Architect • Civil & Structural Engineer WONG TIEN HUA & Associates • Mechanical & Electrical Engineer Sukiada Engineering • Quantity Surveyor Lance Law (Free Lance Quantity Surveyor) • Land Surveyor Blessed Earth Survey Services Supply Contractor: • Main Contractor Mega Ample Sdn. Bhd. Public Local Governments: • Limbang Council District Regulatory Agencies: • Sarawak Energy (SESCO) • Laku Management Sdn. Bhd. (Water Supply) • Jabatan Bomba dan Penyelamat Malaysia (BOMBA) • Jabatan Kerja Raya (JKR) • Drainage Irrigation Department Limbang Division (DID) • Telekom Malaysia (TM) Landowner Media Private
  • 11. 5.0 PROJECT INFORMATION Every project requires a process in order to make it as a successful project: ● Includes identification of objectives and goals of a project, ● running of the construction implementation phases with the integration of implementation tools, ● determine the tools and construction strategies, ● and achieving the successful criteria for the project by having a balance between cost, time, and quality. 5.1 OBJECTIVES AND GOALS ● to complete each phases of this project accordingly as stated in the contract on time and make sure of its best quality presented to the client. The objectives and goals of the project: 1. To determine the project objectives and plans including precise scope of work, budgeting, setting performance requirements, project participants and make sure each the project is following the scheduled timeline 2. To ensure finances are under control through proper time management and minimal changes 3. To perform strict supervision to solve project issues and conflicts to reduce project failing risk 4. To conduct proper construction management to achieve satisfactory outcomes in all aspects in terms of progress, standards, finance, time, resources, materials, and equipments.
  • 12. 5.2 IMPLEMENTATION PHASE Schematic Design Design Development Contract Documentation Contract Implementation & Management Final Completion 5.2.1 SCHEMATIC DESIGN 5.2.1.1 DESIGN BRIEF ● The clients initiated the schematic design stage by approaching to John Lau Architect by using conventional procurement method where the Architect is given the responsibility to approach other consultant teams. ● The clients gave full responsibility for the Architect to build up a concept and vision. ● This means the Architect has to develop the project brief himself. ● The consultants then carried out feasibility study for the project based on the current market value and demands. ● Clients requested a double storey detached industrial building for non-combustible material on lot 1686 at Limbang Town District. 5.2.1.2 SUBMISSION FOR APPROVAL ● A new building must be submitted for approval to State Planning Authority (SPA) but this project is an exception from the list. ● The land itself has the title for ‘Industrial Use Only’ and therefore it is not required for SPA approval as the client requested for an industrial building, unless the new building to be built is a building with other purposes. 5.2.2 DESIGN DEVELOPMENT ● Development Order (DO) Approval is not needed to be obtained from the Authority. ● Schematic plans and elevations are revised to include details and specification required for the construction to be understood by the contractor. ● Project budget could be determined by the Quantity Surveyor and the schedule of construction work could be done by the contractor with the finalized building plans and drawings.
  • 13. 5.2.2.1 DRAWINGS PREPARATION ● The drawings were reviewed by the Architect to produce detailed design drawings with elaborated floor plans, sections, elevations, detailings as well as door and window schedules. ● The drawings also will be included with materials used for the structures. ● The detailed design drawings will be forwarded to other consultants for further detailing according to their respective job scope. The C&S Engineer: ● Designed detailed infrastructure plans and prepared the structural plans and load report of the building. The M&E Engineer: ● Responsible to design detailed mechanical and electrical plan. Quantity Surveyor: ● Draft cost estimation to tally with the budget. Contractors ● Obtain materials’ specifications from the supplier together with the quotation required. The above drawing is the detailed floor plan drawn by the Architect. The below drawing is one of the drawings prepared by Civil and Structural Engineer.
  • 14. 5.2.2.2 CLIENTS’ APPROVAL ● A meeting known as Client-Consultant Meeting (CCM) was held to update the progress of the project and to obtain client’s approval. Aspects that were discussed: 1. Confirmation of building design 2. Building drawings 3. Other consultants’ progress ● An agreement was made between the architect and the client regarding the amendments and cost adjustments after the discussion. 5.2.2.3 SUBMISSION OF DRAWINGS FOR BUILDING APPROVAL Once drawings approved, drawings were submitted for building approval which include: 1. 1 set to Limbang District Council 2. 2 sets to BOMBA 3. 1 set to Sarawak Energy (SESCO) 4. 1 set to Laku Management Sdn. Bhd. (Water Supply) 5. 1 set to Jabatan Kerja Raya (JKR) 6. 1 set to Drainage Irrigation Department (DID) Limbang Division 7. 1 set to Telekom Malaysia (TM) ● Submission of drawings for building approval in Sarawak: no pre-consultation and technical meeting with the local authorities is required. ● Drawings were coloured before they were submitted for approval. Each submission takes about 1 or 2 months to get processed. ● The drawings will be rejected for the first time. The Architect and the other consultants would revise the rejected drawings, reprint, and resubmitted. ● Once approved, it is the end of design development phase. The above drawing is the one of the Building Plan submission drawings
  • 15. 5.2.3 CONTRACT DOCUMENTATION ● It is a phase that all the required materials, the constructions, and the structures to be documented by the Quantity Surveyor to allow the commencement of works by the contractor. ● Further revised of drawings with details to produce the tender drawings and the construction drawings. 5.2.3.1 TENDER DOCUMENTATION ● The document includes detailed drawings and specification details prepared by consultants, and Bill of Quantity (BQ) that are delivered by the Quantity Surveyor. ● John Lau Architect was fully responsible for the tender drawings’ updates prior to CCM. ● Bill of Quantities (BQ) is prepared by Quantity Surveyor and was prepared in a “taking off” process (process of identifying elements of construction) which cost of construction is estimated from measurements based on consultants’ drawings. ● Quantity Surveyor provides the scope of works, specification, project items with quantities through the information that was given and identified from the tender drawings. 5.2.3.2 TENDER INVITATION The project undergone negotiated tender: Clients invite their own desired contractors to go for tendering process. 3 contractors of their choice are the selected for this project. 5.2.3.3 TENDER EVALUATION 5.2.3.4 AWARD OF CONTRACT ● John Lau Architect and the clients are responsible for the tender evaluation. ● Interviews are needed to be attended by the 3 contractors of the clients’ choice in order to get evaluated by the architects and the clients. ● After interviews between the selected contractors and the architect together with clients, clients will select the best tender of their choice. (Mega Ample Sdn. Bhd. was awarded) ● The contract of agreement is done by the clients’ side, it is signed in between the clients and the contractor prior agree to the details and conditions of the contract. It acts as the evidence of the acceptance of contract.
  • 16. 5.2.4 CONTRACT IMPLEMENTATION AND MANAGEMENT 5.2.4.1 PRE-COMMENCEMENT PHASE 5.2.4.2 PROJECT QUALITY COMPLIANCE PLAN (PQP) This phase took around two weeks to process which include: 1. Initial meeting to introduce the team and agreement of the methods and timeline. 2. Compilation and hand over the required documents to contractor. 3. Site supervisory staff briefing to ensure construction works are done within the specific technical documentation and construction permit. 4. Submission of Borang B to the local council to notify the commencement of work, which the notification for the commencement of work is to be received by the contractors. ● Prepared by the contractor to report the roles of the parties involved and the important details to achieve the quality in the project. ● To assure the quality of the construction, weekly work progress and inspection checklist are given, ● A set of forms including Request for Information and other forms are attached for daily records. 5.2.4.3 COMMENCEMENT OF WORK A) SITE MEETING ● Discuss progress report and issues that might affect construction. ● Done monthly or during claim payment made since the starting of construction. ● No Minutes of Meeting is done as it is regarded as non-formal meeting and site works among the architect, contractor, and clients. B) REQUEST FOR INFORMATION ● RFI is to resolve the issues arose during the early construction process to reduce the costly corrective measures. ● It is requested by the contractor where architect is needed to provide building plans and structural plans, and exact detail roofing plan to be approved by C&S Engineer. ● The contractor also requested for handrail details for the manufacturing team to build.
  • 17. C) ARCHITECT’S INTRUCTION (AI) AND NON-CONFORMENCE REPORT ● Architect’s Intruction is the instructions given by the contract administrator to the contractor. ● AI is only given since some materials cannot be found in Limbang as there are limited sources. ● Non-Conformence Report (NRC) is the issuance of report if the contractor used the materials that are not approved by the client, failure in design and strength, not following construction method as per clients’ choice, and other reason. ● No NRC is issued to the contractor since the architect will amend or approve accordingly to suit the availability of materials in Limbang as long as materials are equivalent to specifications. D) VARIATION ORDER (VO) ● The alteration of work added to the existing order in terms of alteration of design, the quantity needed for works, and the modification of sequence of work. ● Issued by the architect and clients in this project which then mentioned to contractor to carry out alternative changes. ● VO will directly affect the cost and the completion date of the project.
  • 18. E) REQUEST FOR INSPECTION F) CERTIFICATE OF PRACTICAL COMPLETION (CPC) G) INTERIM PAYMENT ● Done by the local authorities to come and inspect and to test the performance of every structures and services. ● Random investigation towards the industrial building project, which there was no issue regarding this inspection. ● Issued by the architect to the contractor if the building is done with no defects or damages and according to specified in the tender documentation. ● CPC allows full collection of payment excluding retention sum that would be released to the contractor if no defects were found. ● Legally declared the end of the contractor’s liability other than making good defects. ● Certificate of Claim (COC) done in different stages by the contractor and will be submitted to John Lau Architect with a summary of work done percentage, descriptions of items and quantity that have been used for the construction on site. ● QS will prepare letter of valuation with valuation certificate before approval of interim claim.
  • 19. 5.2.5 FINAL COMPLETION 5.2.5.1 ISSUANCE OF OCCUPATION PERMIT 5.2.5.2 DEFECT LIABILITY PERIOD (DLP) Occupation Permit (OP) is required to certify the building that it has comply with necessary approval and is safe to be used by the occupants before it was handed to the clients. Documents needed: • Cover letter Principal Submitting Person (PSP) to Jabatan Kawalan Bangunan • Notice of completion of excavation for foundation • Borang B • Borang E • Borang F These documents are submitted by Principal Submitting Person (PSP) and Ar. John Lau Ngee Teck is to submit them once the building was done prior to clients’ approval ● DLP will be started once project handover to clients. ● Known as ‘Warranty Period’ and contractor is responsible to rectify all the defects. ● Last for one year to ensure that the building is well function. 5.2.5.3 ISSUANCE OF FINAL CERTIFICATE ● QS will prepare financial statement for final payment certificate. ● Signed off by contractor as the final settlement. ● The issuance means the construction has been completed and payment is based on final account agreed by consultants and contractor.
  • 20. 5.3 IMPLEMENTATION TOOLS Digital softwares were used to complete the drawings and 3D model of the building: 1. AutoCad • For drafting of drawings since starting of schematic design phase to construction phase. 2. Sketchup • Tool for 3D model to provide illustrations to clients. Drafting & Design Digital softwares are needed to keep track all informations in an organized manner: 1. Microsoft Word 2. Microsoft Excel 3. Microsoft Powerpoint Documentation 5.4 MONITORING TOOLS & STRATEGIES ● Provide visual overview of a schedule, timeline to keep track plan and to coordinate tasks. ● Display extra information such as the responsibility of the person in charge, overlapping tasks and linking of tasks, and sequence of each phase in project. A) Gantt Chart ● Known as the Minutes of Meeting (MoM) to record important information and any issue by meeting participants. ● An agreement agreed by all parties and will be taken as legal instruction in the project. ● There are three types of meetings in the project: i) Client-Consultant Meeting (CCM) ● Update the progress of project to obtain client’s approval. ● Involves the client and consultants to follow up design progress ● Any disagreement must be raised within predefined period (3 days) from the official copy issuance of written MoM. ii) Technical Meeting ● Short meeting aimed to solve technical issues and only involves technical team. ● Carried out after the site inspection where issues and concerns will be elaborated. iii) Site Meeting ● Involves all parties: client, consultants, and contractors which is done monthly or during every claim payment made to review the progress of the construction works. ● Some of the major issues can be recorded in construction site meeting: Weather reports, Problem with quality, Circumstances that could violate the contract, Cost impactable issues, Construction conflicts, Health and safety issues, Design issues, Off-site fabrication and payments B) Meeting Minutes
  • 21. 5.5 SUCCESS CRITERIA ● The project success factors consists of elements that are required to make sure the project’s successful completion and this is normally defined in the 3 main aspect known as ‘The Triplet Constraint’. ● Consists of three different factors which are often used to measure the successful level of a project, known as time, scope, and cost. TIME SCOPE COST QUALITY ● It is able to produce a good quality of project. ● To satisfy these triple success criteria in any project, changing in any will affect the others’ constraints. ● In order to produce a successful project, it is to balance the three factors: TIME ● The schedule itself is completed with the estimated amount of time to construct the project which allows the project to be completed before the deadline. ● This industrial building project did not undergo Extension of Time (EOT) and completed in the estimated time. ● The project was done within 30 months. COST ● Budget should be considered as the criteria for success, which this will benefit both clients and stakeholders. ● The project was designed and constructed within a limited budget (Under RM 890 000). SCOPE ● It deals with specific requirements and tasks needed to be completed in the project as required. ● If the project is out of control, the cost or time will be increased. In this project. ● No error in this building project and also, all the outcome of the project has been successfully met to the project brief.
  • 22. 6.0 CONCLUSION (REFLECTION WRITING) As a conclusion, it can be seen that the project management process is effective in controlling the duration of the project and it is able to build up a successful project. The projects are easier to be managed in this controlled manner although the process might seem different between the process in West Malaysia and in Sarawak. Some of the process might not be the same as what are used throughout the Malaysia but the method of delivering and the goal towards the project is the same. In overall, what I have learnt from this internship training is the that are needed to be done by the Architects are practically important to design and build a building for the client. As what I experienced from my training is, the Architects act as the coordinator between the consultants, contractors, and the clients, and also the Architects play an important role in delivering tasks from the beginning of the project until the end of the project. By listing out all the tasks that the Architects are involved in any particular object, it can be seen that Architects are just not about drafting and drawings and designing but the Architects are the main person to guide all the process in the project. In order to build a successful project in real life, it is to deliberate the tasks effectively to all the parties involved in any of the project. Architects have to think rationally in order to perform tasks and not to bias with any of the parties in order to get a successful deliverable project to the client. In order to deliver a successful project, it can be seen that a successful project depends on 3 criteria mainly: Time, Cost, and Scope. From this triplet constraint for the project, any of the change of the criteria might change the final outcome of the project or the change of the other two criteria. In order to make a project successful to be constructed, it is to be done within the Time, Cost, and also the Scope.