Management of Medium-Size /
Revamping Projects
Oil & Gas Downstream Projects
8. Project Control
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013
©
2011
-
IFP
Training
Management of Medium-Size /
Revamping Projects: course content
I. Introduction
II. Preliminary Studies
III. Basic Engineering (or FEED)
IV. EPC Contracting
V. Organization and Engineering
VI. Procurement
VII. HSE, Quality and Risk Management
VIII. Project Control (cost/schedule)
IX. Construction and Fabrication Management
X. Completion / Commissioning / Start-up / Closure
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 2
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 3
Module 7 Contents
1. Project control 04 - 06
2. Scheduling and progress control 07 - 26
3. Cost estimating and control 27 - 55
ATTACHMENTS (slides 56 to 82)
I. WBS and Schedule examples
II. More about Progress Control
III. Cost Reporting details/examples
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 4
Project Control
Scope / Objectives
 Scope:
• Engineering, Procurement and Construction stages of the project
(including main Contractor, Subcontractors and Suppliers)
• Mainly Cost and Schedule (for HSE and Quality: see previous chapter)
 Schedule Control objectives:
• Establish an optimized project schedule, accepted by all contributors
• Determine constraints and critical path
• Define method to measure progress, and apply it throughout execution
 Cost Control objectives:
• According to Owner cost structure, produce an optimized Cost Estimate
• Make sure the budget is kept under control
− Using appropriate tools
− Defining roles and responsibilities at all levels
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 5
Project Control
Process
(Monthly)
SCHEDULE
STATUS LINE
(Monthly)
PROGRESS
CALCULATION
(Monthly)
COST
CALCULATION
Trend Analysis
Baseline
Schedule
Schedule
Status
Planned
Progress
PROJECT PROGRESS
CONTROL SYSTEM
(Activities weights
USD, mhrs)
PROJECT
SCHEDULE
SYSTEM (e.g CPM)
PROJECT COST
CONTROL SYSTEM
(USD)
Actual
Progress
Progress Analysis
Progress Forecast
Initial
Budget
Cost Analysis Cost
Forecast
Expenses &
Committments
CONTROL
ACTION
CONTROL
ACTION
CONTROL
ACTION
« FEEDBACK »
PROCESSES
PROJECT
WORK
BREAK
DOWN
(WBS)
STRUCTURE:
Activities
Split
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 6
Project Control
Communication / Reporting
 Frequent communication / reporting is critical for performance
 It enables the Project Manager to obtain
• A clear picture of the Project progress vs budget and schedule
• A timely identification of adverse trends / threats
 It allows the Project Team:
• To react and take immediate corrective actions,
• If necessary, to design strategic recovery plans
• To communicate with Owner and avoid last-minute surprises
 Cost and Schedule can be both critical (but it depends on contract type)
• To Owner (more often, Schedule)
• To Engineering Contractor (more often, Cost)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 7
Scheduling and progress control
 Owner Scheduling
• Work Breakdown Structure
• Scheduling, Schedule levels
• Critical path
• Schedule revisions
• Scheduling tool
 Contractor Scheduling
• Same content as above
 Progress Control
• Progress measurement
• Recovery Plan
• Schedule re-baselining
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 8
Owner Scheduling
Work Breakdown Structure
 The objective of the WBS is to provide an organised structure
covering the whole content of the project and to include, at
different levels of detail, the information necessary to monitor,
control and correctly report all project activities
 The project WBS takes consideration of:
• Project configuration (size, geographical and technical nature)
• Project management considerations (split of responsibilities, contracting
strategy / packages, reporting requirements)
 It is generally organized (for an EPC schedule), by:
• A geographical divisions: Work Packages / Areas / units
• Work subdivisions (engineering disciplines, construction trades...)
See examples in Attachment I
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 9
Owner Scheduling
Purpose
 Owner may have to prepare a Schedule for various reasons, e.g.:
• A consolidated Project schedule (Project split into several EPC packages)
• Preliminary Project schedule at pre-Project stage (Owner leader)
• Commercial reasons (e.g. external customer commitments)
• Schedule with contingency, vs. the one discussed with EPC Contractor
 Level-0 Owner schedule will generally be presented as a Bart Chart
 More detailed levels will also be developed, using PERT/CPM
 Schedule presentation will be consistent with Owner WBS
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 10
year J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
JACKET & FLARE 4
Basic Engineering 4
CFT - EPCI 5
Detail Engineering
Procurement 8
Construction 1
Installation
TOPSIDES 4
Basic Engineering 4
CFT - EPCI 8
Detail Engineering 10
Procurement 11
Construction & Transportation
Installation
Hook up & commissionning
PIPELINES & CABLES 3
Engineering 3
CFT 9
Procurement & transport
Installation
DRILLING & COMPLETION
PRODUCTION 27
Owner Scheduling
Bart Chart example for 4 packages
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 11
Owner Scheduling
Schedule types
Scheduling: a fundamental task of Project Management
 In Revamp projects, Schedule and Cost can be closely interrelated
 Bar Chart: common way to prepare the first-pass schedule
• Easy to prepare, to read (condensed format, 1 line per activity)
• More difficult to see critical path and to evaluate impact of changes
 PERT (Project Evaluation and Review Technique) ... then PDM
• Determination of Critical Path
• Sequencing logics is built into the schedule
• Then, bar charts can be produced from the network
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 12
Owner Scheduling
Schedule levels
 Level 0 – Project Master Schedule:
• Executive summary schedule used for reporting at Management level
• Frozen at Project Sanction = Initial Baseline Schedule
• Shows target dates, key milestones and main phases
 Level 1 – Integrated Project Control Schedule:
• Time-scale logic diagram
• Decision steps, contracts sequence, work package summary activities, LLIs
• Major milestones and overall project critical path
 Level 2 and 3 – Contractor and sub-contractor Schedules
• Cover all the activities/tasks of the Contracts
• All milestones necessary to control contractors’ physical progress
• Procurement of main equipment and fabrication, construction,
installation, commissioning, with the critical path
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 13
Owner Scheduling
Links between activities and critical path
 Network is built with activities predecessors and followers &,
linked by End-Start, Start-Start, or End-End link
 Critical path: path of activities with no float
• Provides shortest project duration
• Goes through a series of activities from Project Start to Project
Completion (e.g. studies and technical evaluation, delivery of some
equipment, fabrication, site installation, hook-up, drilling)
Float
Float
Critical Path
Critical Path
Critical Path
Critical Path
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 14
Owner Scheduling
Example: Gantt bar chart
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 15
Owner Scheduling
Schedule revisions
 Baseline Schedule revisions performed on Project Manager
decision in case of significant changes or delays
 Detailed assessment, based on Level 2 schedule, of all remaining
activities (internal / contractors), duration & sequences including:
• Actual physical progress and achieved milestones
• Manhours progress and actual vs estimated productivity
• Upcoming Change Orders (requested or potential) impacts on
schedules
• Performance of simulation schedules and “what-if” scenario as well
as detailed schedules risks analysis performed by/with the Risks
Assessment Manager.
 Contractors may also need to revise their Baseline Schedules
which may cause a revision of Company schedule
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 16
Owner Scheduling
Common softwares
 Scheduling: common softwares for Medium & Small Projects:
• MS-Project for small EPC projects, preliminary studies, FEED
• Primavera for EPC phase (and FEED if necessary)
 For presentation purposes:
• Level 0 (on Excel, with information extracted from Primavera Level 1)
• Level 1 or 2 only for specific critical activities
 Progress reports : often prepared with Excel
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 17
Contractor Scheduling
Differences
 Scheduling by EPC Contractor: more detailed than Owner
• A detailed WBS/OBS is prepared to define areas and work phases
for the project schedule & progress reporting
• Scheduling hierarchy generally includes 4 main Levels for the
concerned EPC contract, plus many sub-level schedules
 Contractor responsibility on schedule compliance
• Depends on the contract type (and therefore on Owner priorities)
• May have financial consequences for him (or not)
 Owner control on Contractor progress has to be applied
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 18
Contractor Scheduling
EPC schedule hierarchy
 Level 0 schedule: Project Master Schedule: milestones dates and main work phases
 Level 1: Overall Project Schedule with, for major WBS areas:
• Engineering by discipline (major engg milestones: PIDs, Plot Plan, MTOs,
Reviews...),
• Procurement with LLIs and major equipment purchasing / delivery,
• Construction by trade, pre-com/com, milestones dates (MC, RFC, RFSU…)
• Critical path
 Level 2 schedule: Areas Schedule: CPM network; all activities according to WBS / OBS
• All engineering activities by discipline and deliverables category,
• Procurement activities for all equipment & bulks requisitions,
• Construction by trade or construction packages, pre-com / com,
• Detail critical path from CPM
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 19
Contractor Scheduling
EPC schedule hierarchy
 Level 3: Detailed Schedules
• Engineering deliverables (usually with engineering progress measurement system)
• Procurement schedule (may be with procurement progress measurement system)
• Site Level 3 CPM construction schedule, with Level 3 construction contractor
subcontract schedules, in line with Level 2 schedule; used for progress reporting
• Site CPM pre-commissioning / commissioning schedule detailed by Areas / Units /
Systems / Tasks and used for progress reporting
• For Revamped areas: Shut-down schedules by Job Cards
A 3 months look-ahead schedule may be used for reporting
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 20
Contractor Scheduling
Key elements to consider
 Contractual milestones for achievements of the whole project or intermediary.
 LLI (Long Lead Items), when applicable: items on the project critical path
 Global project size and engineering, procurement and construction resources
requirements versus their availability for the concerned project / site (progress
rates) will translate into required manhours at peak and feasible progress rate
 For Revamping projects: Planned shut-downs calendar times and durations
 Standard « statistic » progress curves with % completion vs. project duration in
% are available to provide a reference progress for each activity:
• Engineering by discipline (process, equipment, civil, piping, E/I/A)
• Procurement (main equipment, bulk material)
• Construction (For each trade: Civil, U/G piping, Piping pre-fabrication,
equipment erection, piping erection, instrumentation, painting, insulation)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 21
Contractor Scheduling
Typical critical path
 Typical critical path for an E/P onshore project usually includes:
• Long Lead Items (including erection and installation)
• Process PIDs (approved by Owner for design)
• Main equipment purchases (including inspection/transportation)
• Piping isometrics, pre-fabrication and installation
• Control loop checks at the end of construction
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 22
Contractor Scheduling
Schedule of Revamp projects
Revamping Project Schedule is strongly influenced by:
 Production objectives vs time: new production milestones after revamp
 « Usual shut-downs » planned time and duration (need to minimize production
outage time, including upstream and/or downstream facilities)
 Work authorised during pre-shutdown phases in live facilities: if too limited,
amount of work during S/D and construction may become:
• More/very expensive
• Higher HSE/Reliability risk
• Even unrealistic  delays and/or major Quality concerns
 Consider using available Owner supervision & commissioning staff
Carefully review schedule constraints with Owner during FEED,
to avoid subsequent trouble and change orders
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 23
Progress control
Purpose
 Compare actual progress vs schedule. Several ways:
• Milestones
• Overall physical progress
• Physical progress of the Critical Path
• Expected completion date vs plan
• Manhours progress vs detailed schedule
 Analyze trends to decide if corrective actions are necessary
 Depending on contract type, Owner validation may be required
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 24
Progress control
Progress reporting
 Periodic Progress Reports: a key Project Management tool
 Address progress, but also all key events, problem areas and
higher level problem areas (« areas of concern »)
 Prepared:
• Daily at site (construction / pre-com / com).
• Weekly for Head Office activities and for construction
• Monthly
• Issued before periodic Owner / Main Contractor review meetings
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 25
Prepares
Daily report (constr)
Weekly report
Monthly reprt
Feedback
Incident
Close-out
SUB CONTRACTORS
Reviews, Responds,
Consolidates Oper. Centers
& Site Reports
Alerts
Feedback
Incident
Close-out
Monitors,
Monthly
Monitors,
Recommends
Monthly
Incident
Close-out
JV
STEERING COMMITTEE
CONTRACTOR PROJECT MANAGEMENT TEAM
CONTRACTORS
CONTRACTOR
MANAGEMENT
Progress control
Progress reporting
MONTHLY MEETING
MONTHLY MEETING
COMPANY PROJECT MANAGEMENT TEAM
MONTHLY MEETING
Prepares
Daily report (constr)
Weekly report
Monthly report
Alerts
Feedback
Incident
Close-out
Prepares
Daily report (constr)
Weekly report
Monthly reprt
Alerts
Feedback
Incident
Close-out
WEEKLY MEETING
WEEKLY MEETING
DAILY MEETING (Constr.)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 26
Progress control
Progress reporting
Typical CONTENT
 Executive Summary
 HSE performance
 Engineering
 Procurement
 Subcontracting
 Construction
 Pre-com / Com
 Project Controls
 Quality
 Areas of Concern
 Major events, achievements, problem areas,
highlights
 HSE statistics, near misses register
 Progress S curves, tabulations: planned, actual,
forecast for Project, Work Packages, global E,
Disciplines, P, global C, C by areas/ units, C by trades
 Milestones status
 COI/COR register
 Invoices register
 Cash flow actual & predictions
 Procurement materials status reports
 NCR register
 Documents register
 Level 1 Project Schedule with progress status; Trend
analysis; recovery plan
 Manpower histograms planned & actual
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 27
Progress control
Progress measurement
 Split project activities according to structure close to the WBS
 Define weights to each line, using adequate units (€, manhours…)
 For each Work package, aggregate these tasks by Levels :
• 1: Work-Package or sub-project
• 2: Categories: home office services, procurement, construction…
• 3: Sub-categories: engineering discipline, requisition, construction trade
• 4: Tasks: engineering deliverables, equipment, construction items
• 5: Elementary steps: drawings, fabrication, construction works
 During execution:
• Measure progress achieved for each elementary step
• Then, aggregate to the different Levels and compute overall progress
See examples/illustrations in Attachment II
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 28
Progress control
Progress curves
0% 0% 1% 2% 3% 4% 6% 7%
9%
11%
14%
17%
20%
25%
30%
35%
40%
46%
51%
56%
61%
67%
70%
73%
76%
79%
82%
84%
85%
87%
90%
92%
95%
97%
99%
100%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Months
TYPICAL PROGRESS CURVES
Engineering Procurement Fabrication
Construction Commissioning Total
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 29
Progress control
Progress curves
 Engineering « S » progress curves are prepared from Level 3 schedule
(typically during the first 3 months of the contract)
 More detailed “S” curves are prepared during Execution:
• Detailed construction / fabrication curve
• Field erection curve
• Installation / commissioning curve
 First « S » progress curves and histograms can be prepared from Level 2
schedule and manhours estimates; they allow to check that
construction scheme is realistic for construction contractors
 Until the Project EPC schedule is issued, a 3-month look-ahead schedule
is prepared to anticipate short-term schedule and resource concerns
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 30
Progress control
Typical causes for EPC contractors delays
 Insufficient manpower resources (quantity and/or quality)
 Supplier or Subcontractors (careful on sub-sub-contracting !)
 Strikes, disturbances related to local environment
 Underestimates (manhours, bulk quantities)
 Equipment Quality unacceptable non-conformances
 Late information, comments or reviews from Owner
This list is incomplete. Other ideas ?...
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 31
Cost Estimating and Control
• Cost estimating
• Cost reporting and control
• Change Management
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 32
Cost Estimating and control
Scope and objectives
 Scope: Project CAPEX (OPEX is not in the scope)
 Objectives:
• Estimate the project CAPEX and propose the overall budget
• Make sure that this budget is acceptable to all contributors
− Sufficient to assure Project HSE/Quality performance
− Generating acceptable profit for each stakeholder
» Owner
» EPC contractor
» Suppliers and Subcontractors
− Consistent with the cost and schedule constraints
− Allowing adequate risk management
• Organize the Cost Reporting/Control process (involving Owner)
• Define the Change Management process (involving Owner)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 33
Cost Estimating
Budget
 Any Project has a controlled and approved Budget
 The Budget may be adjusted (Revised Budget) during the Project Life:
• Budget transfer from other projects
• Scope deletions or additions, approved by Owner
 Structurally, the budget is expected to increase as Project develops
 At the end of the Project:
• Cost analysis will establish the “Final cost”
− After Mechanical Completion and Handover
− Once claims are settled and invoices paid
• The final Cost Control report is issued
• Comparison with Revised Budget allows to draw feedback lessons
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 34
Cost estimating
Methodology
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 35
Main Equipment
Bulk
Fabrication/Construction(onshore/offshore)
Engineering Services
Management & Supervision
Surveys
Transportation
Temporary Facilities
Construction camps
Insurance
Commissioning
Direct Costs
Contingencies
Facilities Cost Estimate
Indirect Costs
General
Expenses
Associated Expenses
+
+
+
+
=
Direct Costs + Indirect Costs = Technical Costs
Cost estimating
Structure
Fabrication / Construction cost are the highest costs and the most difficult to estimate,
in particular for works in revamped process units and brown field; they are very site dependent (productivity)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 36
Cost estimating
Preliminary Estimate: a Challenge
 CAPEX estimate usual desired accuracy is +/- 30% for « new » or « expanded »
parts of projects in existing facilities, which may be relatively easy if the Plant
is recent and cost data base available or difficult depending on:
• Project complexity and location
• Onshore or Offshore projects
• Concerned facilities
• Modifications to facilities (Expansion, Debottleneck, Upgrade, Revamp)
 The CAPEX estimating method will depend on:
• Cost data base (Owner and/or Contractor) for works at that location
• Nature of facilities (onshore or offshore, subsea or surface, new or
revamped process units, interconnecting with work in brown field…),
 The CAPEX estimate should be prepared with a memorandum underlying
assumptions, estimating methodology, uncertainties and risks
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 37
Cost estimating
Preliminary Estimate: a Challenge
 Estimating methods are global as project details such as P&IDs are not prepared; the
estimating methodology will combine available cost data base and estimating tool box.
 Estimators use cost data breakdowns, unit costs, etc. from similar recent project units at
the location, or at similar (in terms of cost) location, with corrections for location
(importance of construction cost), escalation, and other foreseen different project
conditions. (Often the estimators will use units information from several projects).
 Many « factors » are used for so called « factored estimates »:
• Scaling factor: P1 / Po = (C1 / Co)0.65
• Factored estimate from equipment cost: P installed= K x P equipment
K may range from 2 to 6 depending on equipment type
For revamped areas an other K1 factor is to be applied on top
• Global factor on top of Direct Costs: Total cost = K x Project Direct Cost
• A cost factor can be used for transportation (onshore projects)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 38
Cost estimating
Preliminary Estimate: a Challenge
 Cost information is gathered from all possible sources at the time, e.g:
• Major / special equipment or packages (glycol treatment, water
treatment, utilities and power packages, etc.): prices from Vendors
« budget » quotes.
• Interconnecting preliminary quantities estimated by engineering from
preliminary MTOs & unit costs used from previous project at the facilities,
for bulks cost & for construction cost; quotations from Vendors for large
pipe / pipelines
• Engineering, construction supervision manhours may be estimated by
ratios.
• Contingencies or CRP (Contingency, Risks and Profit) factor, added on top
of estimate
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 39
Cost estimating
CAPEX estimate during FEED
 CAPEX estimate prepared according WBS/OBS; desired accuracy +/- 15%
 Estimate is Quantities x Unit Costs
 Construction cost is all-in construction mhrs rates x construction mhrs
 Construction cost: the most important cost item, the most difficult to estimate
 CRP (Contingency, Risks and Profit factor) is added on top of the cost estimate
 CAPEX estimate prepared with a memorandum underlying assumptions,
estimating methodology, uncertainties and risks.
 Estimating methodology principles are presented on next slides
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 40
Cost estimating
CAPEX estimate during FEED
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 41
Cost estimating
CAPEX estimate during FEED
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 42
Cost Control process
Owner perspective
 Owner cost control process and involvement in tracking cost
components depends on the type of EPC contract
 If a contract is on Reimbursable basis, Owner will have access to
all cost elements and is responsible for the complete Project cost
 If a contract is on a Lump Sum basis, Owner will have access only
to the cost items specified in the contract
 Owner will have access to the cost estimate to support change
orders, approve them, and include them to Cost Control process
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 43
Cost Reporting and Control
Forecast
 Purpose : determine the Forecast to Complete
 Cost Forecast is updated on a regular basis (typically, monthly)
 Cost Forecast may anticipate on non-finalized commitments
 Cost Forecast requires a good knowledge of technical matters
 Cost Forecast may introduce some budget transfer
 Cost Forecast includes proper management of Contingencies
• Advisable not to consume them during the early stages
• Corporate rules (Owner and/or Contractor) may exist
• The Project Manager has ultimate authority
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 45
Cost Reporting and Control
Organisation principles
Cost control organisation includes mainly:
 Cost Control Manager, assisted by Cost Controllers depending on
Project size, responsible for global project cost control and
reporting to operationally to the Project Control Manager and
functionnaly to the Contractor Management (in case of a JV, will
report to JV Project Manager on one hand and, on the other
hand, to Partner Management within its own organisation, issues
being then adressed if necessary by the JV Steering Committee)
 Site Cost Control Manager responsible for cost control at the site
and reporting operationnally to the Site Manager but functionally
to the Cost Control Manager
 Cost Estimators to estimate project cost changes and reporting to
the Project Control Manager
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 46
Cost Reporting and Control
Cost Controller duties (1/2)
Mainly coordinates with:
 Engineering and scheduling / progress control organisations to control engineering
manhours cost expenditure, planned mobilisation and trends from productivity
and personnel mhrs rates, and to control bulks quantities trends considering
MTOs vs their engineering documents basis
 Procurement to control Vendors offers versus budget (advise budget target before
negotiations, check and approve CBTs and Vendor price), and track P.Os change
trends
 Fabrication / construction contracts management to control cost and trends versus
budget (before transfer of construction contracts administration the site)
 Site cost control to control site costs and trends
 Project Management for allocation and use of technical cost contingencies or
global project risks provisions
Prepares costs expenses reports, forecast and monthly cost reports; also prepares
change orders
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 47
Cost Reporting and Control
Cost Controller duties (2/2)
Mainly Coordinates with:
 Fabrication / Construction / Pre-com / com Management to control site
supervision cost (mobilised cost, planned mobilisation, daily rates costs...)
 Site Contracts Administrator(s) / quantities surveyors and Scheduling /
Progress Control Manager to control current construction cost, establish
forecasts from anticipated quantities variations, productivity, and additional
work orders
 Site procurement for local purchases
 Site Administration Manager for site running costs control (accommodation /
camps, TCF...)
 Prepares back-charges to Vendors and Construction Contractors as applicable,
insurance claims in case of damages during transport or at site
 Prepares site costs expenses reports, forecast and monthly cost reports; also
prepares change orders
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 48
Cost Reporting and Control
Periodic actions
 Day-to-day:
• Review work progress and consistency with contract terms
• Inform Management of any non-budgeted items
• Review all invoices received and consistency with contract terms
 Typically on a monthly basis:
• Calculate the escalation formulae and price revisions, if any
• Manage the various provisions
• Review the estimate to complete and the final forecast
 Less frequently (quarterly, annually, or ad hoc):
• Formal reporting to EPC Management, Owner and Partners
• Regulatory reporting if applicable (e.g. tax)
• Propose budget revisions
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 49
Cost Reporting and Control
Keys of effective cost control
 Timely and serious estimate of Engineering Manhours
 Bulk Quantities estimate based on complete detail engineering
 Check of Suppliers and Fabrication/Construction contracts:
• Estimates based on up-to-date verified info
• Actual costs timely compared to estimate, and challenged
• Rigorous Procurement procedures, no by-pass
 Schedule changes: careful about cost consequences
 Rigourous Change Management
 Accurate and timely Reporting / Forecasting to Management
 Timely followup of cost control actions decided by the team
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 50
Management of change
Process
Management of Change
Covers all changes to contract
Engineering Deviation Requests
• Cover deviations to contractual
reference standards or already
Approved Design Specifications
• Written Procedure
• Deviation Requests Register
• Clear Owner approval authority
Change Order Procedure
• Covers Additions, Modifications
and Deletions to Project scope,
with impact on Project cost,
schedule, process performance
• Procedure includes:
− Change Process
− Change Orders Log
− Approvals
• Change Requests Register
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 51
Management of change
Deviation requests/engineering queries
 Clarify or ask a deviation to a contractual document, for the purpose of
developing the detail engineering and procurement requisitions
Usually due to:
• Conflicting requirements in different documents
• Proposal of an engineering improvement
• Required materials not consistent with local availability
 Ask a deviation to already approved requisition documents
Usually due to:
• Proposal of a supply improvement
• Availability of raw materials different from requirements
• Vendors fabrication or test standards different from requirements
• Standard packages or skids
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 52
Management of change
Change order procedure
A “Change Order” is not an anomaly
• When cost variations are not due to Contractor and potentially give rise to
a Change Order: Contractor notifies Company and prepares a Change
Order Request (COR) with an estimate and formal request to be usually
submitted within 2 weeks maximum to Company.
• Company may also need to change the scope, or to exert Options provided
under the contract, or for any reason to ask Contractor to change its work
thru a Change Order Instruction (COI). Company then notifies Contractor
with an estimate to be usually submitted within 2 weeks maximum to
Company.
• Change Orders are monitored by the Project Cost Management team and
recorded as soon as they are identified on a Change Order Register.
• Change Orders estimates are evaluated by the Contractor (using contract
unit costs as available), and checked by Company Cost Management team.
• Change Orders need to be formalized and agreed by all Parties and will
therefore be transferred to Project budgets (Company and Contractor)
only after Approval by Company.
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 53
Management of change
Cost trends caused by Owner
 Project definition unclear or incomplete
 Scope changes during execution
 Delayed access to construction areas
 Missing elements or information
 Wrong assumptions on market costs
 Unclear interfaces between contractors
 Conflicts with EPC Contractor, or Suppliers, or Subcontractors
 Insufficient quality of Project Management Team
 Delays in achieving Owner tasks
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 54
Management of change
Cost trends caused by Environment
 Unplanned inflation rate or exchange rate changes
 Weather catastrophy (cyclones, flooding, earthquakes)
 Political trouble (strikes, wars, unplanned regulatory changes)
 Delays to obtain working visas
 Unexpectedly low productivity due to bad weather
 Unforeseen difficulties (soils or sea bed conditions)
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 55
Management of change
Cost trends caused by EPC Contractor
 Initial Price too low
 Insufficient qualification of Project Management Team
 Inability to forecast on time
 Sub-contractors lack of performance
 Estimating errors (incomplete/incorrect technical info)
 Insufficient provisions or contingency
 Missing cost elements
 Wrong assumptions on supplier/subcontractor markets
©
2011
-
IFP
Training
Key points to keep in mind
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 56
Project control
 Owner has a critical role in controlling EPC Contractor performance
 This role depends on the contract type but is always to be assured
 Scheduling:
• May be quite critical on Revamping projects (shutdown windows)
• Smaller projects need simpler tools
• Critical path should be clearly identified and optimized
 Cost estimating:
• Up-to-date cost databases are a key to effective estimating
• Accuracy of Cost Control estimate should be around 10%
• Estimate used for approval (FEED stage) should be based on quantities
 Cost and Schedule control:
• Monitoring methods should be clearly defined in the EPC contract
• For Revamping projects, may be closely inter-related
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 57
ATTACHMENTS
I. WBS and Schedule examples
II. More about progress control
III. Cost reporting details/examples
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 58
ATTACHMENT I
WBS and Schedule examples
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 65
ATTACHMENT II
More about Progress Control
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 66
Principle split
% according to USD values
OVERALL
PROJECT
WORK PACKAGE 1 WORK PACKAGE 2
HOME OFFICE MANUFACTURING CONSTRUCTION AND HOME OFFICE MANUFACTURING CONSTRUCTION AND
SERVICES DELIVERY PRECOMMISSIONING SERVICES DELIVERY PRECOMMISSIONING
15% 35% 50% 15% 35% 50%
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 67
Principle split – Weights sample onshore
% according to mhrs for services and USD for procurement
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 68
FPSO 28,6%
TOPSIDES
Engineering 10,6%
Procurement 34,2%
Construction 16,8%
Integration 3,3%
Towing FPSO & Flotel 2,1%
Tie-in precomm and Comm 1,8%
HULL & L Q 31,2%
SPS 14,3%
Engineering 4,0%
Procurement 22,1%
Manufacturing 67,3%
Systems Testing 3,3%
Transport 3,3%
UFR 24,5%
Engineering 4,5%
Procurement 36,2%
Construction 14,5%
Offshore Installation 27,8%
OLT 17,0%
DRILLING 32,7%
Drilling Rig 42,8%
Rig Contract Services 57,2%
TOTAL 100,0%
Progress measurement: Weighting sample offshore
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 71
Recovery plan example: loss of mobilisation at year end
and drifting
ACTUAL PROGRESS
ON TIME UNTIL END DEC.
BUT DRIFTING
RECOVERY PLAN:
INCREASE MOBILISATION
TO INCREASE PROGRESS
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 72
Project Schedule sample: Gas Plant 2 Trains extension and
upgrade – S/Ds Planning
One
major S/D
initially
Four S/Ds
at actual
EPC time
start
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 73
Progress curves: Schedule Baseline Revisions
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 74
JC preparation progress curve
Preparation of JCs may take several months: procedure for
preparation, progress control to be implemented
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 75
Fabrication scheduling
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 76
Scheduling transportation to site
 Transportation to site of the main components is not very difficult
by itself, but the coordination of this activity can be a real
challenge
 The speed of the spread(s) transporting the main components is
directly calculated from the distance and the marine spread
speed + some provisions for bad weather, adverse wind, …
 The capacity of the transportation barge or vessel must be
assessed carefully: transporting 2000 tons, 5000 tons or even
30000 tons is a case by case study
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 77
Scheduling offshore installation
Initial scheduling of offshore installation requires:
 Detailed analysis of the scope: number and main characteristics
of all modules / decks / jackets / pipelines / floating storage…
 Evaluation of the marine construction equipment required:
• Derrick barge – crane capacity
• Pipe Laying Barge – stinger – max pipe size – type of welding
• Offshore tie-in means: ROV…
• Trenching, shore approach equipment
• Drilling rigs type…
The schedule will be reviewed after contractors selection
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 78
Scheduling offshore installation
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 79
Scheduling hook-up
 Hook-up time is highly dependant upon the yard fabrication and
its level of completion
 It is fundamental to reduce as much as possible the hook-up
work: hook-up is very costly and always critical
 No hook-up without accommodation
 No hook-up without a good logistic and supporting equipment
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 80
ATTACHMENT III
Cost Reporting details/examples
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 82
* Level 0 = Project
1 = Phase
2 = Major Work Split
3 = Commitment
4 = Work Package
Company Cost Report Format Principles
Project Level*
Description
(1)
Approve
d
Budget
(2)
Scope
Change
(3)
Budget
Transfer
(4)
Current
Budget
(1+2+3)
(5)
Commit
(6)
Estimate
To
Complete
(7)
Forecast
(5+6)
(8)
Variance
(+/-)
(4-7)
(9)
Expend.
Incurred
(10)
Approved
Invoices
AFE
X
Y
Z
100
50
90
0
0
0
0
10
- 10
100
60
80
90
60
80
12
0
- 5
102
60
75
2
0
- 5
70
60
73
65
60
65
Sub-total 240 0 0 240 230 7 237 - 3 203 190
Provisions
Contingen
cy
24 0 0 24 0 22 22 - 2 0 0
Total 264 0 0 264 230 29 259 - 5 203 190
©
2011
-
IFP
Training
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 83
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
CODE DESCRIPTION
APPROVED
BUDGET
SCOPE
CHANGE
BUDGET
TRANSFER
CURRENT
BUDGET
(1+2+3)
COMMITMENT
ESTIMATE to
COMPLETE
FORECAST
(5+6)
Variance
(+/ -) (7-
4)
Expenditure
Incurred
Approved
Invoices
100 Initial Studies 13350 0 0 13350 13350 0 13350 0
200 Wellhead Connect. 54550 0 0 54550 51550 3000 54550 0 30 26
300 Production Pltf 137320 0 -10000 127320 118380 8940 127320 0 12760 10000
400 Quarter Pltf 37070 0 -500 36570 34500 2070 36570 0 6383 5073
500 FPSO 42430 0 2700 45130 43170 1960 45130 0 18823 16450
600 Buoy & Sealines 12900 0 0 12900 0 12900 12900 0 45 42
700 Management 5600 0 0 5600 0 5600 5600 0 15 15
Sub-Total 303220 0 -7800 295420 260950 34470 295420 0 38056 31606
800 Provisions (rate) 2100 0 -10 2090 0 2090 2090 0 10 10
900 Contingency 12430 0 0 12430 0 12430 12430 0 0 0
**** TOTAL 317750 0 -7810 309940 260950 48990 309940 0 38066 31616
PROJECT: ANGELA PAPYRUS
LEVEL 0
TOTAL E&P XXXX
DATE: OCT 2003 ALL IN k US$
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
CODE DESCRIPTION
APPROVED
BUDGET
SCOPE
CHANGE
BUDGET
TRANSFER
CURRENT
BUDGET
(1+2+3)
COMMITMENT
ESTIMATE to
COMPLETE
FORECAST
(5+6)
Variance
(+/ -)
(7-4)
Expenditure
Incurred
Approved
Invoices
210 Gen. Mngt & Serv 2200 0 0 2200 2200 0 2200 0 350 0
220 Engineering 4400 323 0 4723 4523 200 4723 0 0 0
230 Mal & Eqpt supply 8500 645 0 9145 9045 100 9145 0 0 0
240 Onshore fab 22500 1682 0 24182 23582 600 24182 0 0 0
250 Transportation 3550 0 0 3550 3450 100 3550 0 0 0
260 Offshore Works 16500 0 -500 16000 15800 200 16000 0 0 0
270 Hook-up Wks 6200 0 0 6200 6000 200 6200 0 0 0
280 Commissioning sup 3200 0 -1800 1400 1000 400 1400 0 0 0
290 Spare parts 950 0 -350 600 550 50 600 0 0 0
2*** TOTAL 68000 2650 -2650 68000 66150 1850 68000 0 350 0
PROJECT: ANGELA PAPYRUS
LEVEL 1 WELLHEAD PF & CONNECTION
TOTAL E&P XXXX
DATE: OCT 2004
ALL IN k US$
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
CODE DESCRIPTION
APPROVED
BUDGET
SCOPE
CHANGE
BUDGET
TRANSFER
CURRENT
BUDGET
(1+2+3)
COMMITMENT
ESTIMATE to
COMPLETE
FORECAST
(5+6)
Variance
(+/ -)
(7-4)
Expenditures
Incurred
Approved
Invoices
310 Long lead Items 28630 0 -4200 24430 24430 0 24430 0 4800 2400
320 Gen. Mngt & Serv 2640 0 0 2640 2400 240 2640 0 240 240
330 Engineering 4680 0 -700 3980 3600 380 3980 0 720 360
340 Mal & Eqpt supply 45840 0 -5100 40740 40300 440 40740 0 4500 4500
350 Onshore fab 16480 0 0 16480 16150 330 16480 0 2500 2500
360 Transportation 4500 0 0 4500 4500 0 4500 0 0 0
370 Offshore Works 18000 0 0 18000 14500 3500 18000 0 0 0
380 Hook-up Wks 8500 0 0 8500 6200 2300 8500 0 0 0
380 Commissioning sup 4850 0 0 4850 3800 1050 4850 0 0 0
390 Spare parts 3200 0 0 3200 2500 700 3200 0 0 0
3*** TOTAL 137320 0 -10000 127320 118380 8940 127320 0 12760 10000
PROJECT: ANGELA PAPYRUS
LEVEL 1 Production Platform
TOTAL E&P XXXX
DATE: OCT 2004
ALL IN k US$
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
CODE DESCRIPTION
APPROVED
BUDGET
SCOPE
CHANGE
BUDGET
TRANSFER
CURRENT
BUDGET
(1+2+3)
COMMITMENT
ESTIMATE to
COMPLETE
FORECAST
(5+6)
Variance
(+/ -)
(7-4)
Expenditure
Incurred
Approved
Invoices
410 Long lead Items 2560 0 0 2560 2560 0 2560 0 2560 1250
420 Gen. Mngt & Serv 1200 0 0 1200 1200 0 1200 0 240 240
430 Engineering 2150 0 0 2150 2050 100 2150 0 410 410
440 Mal & Eqpt supply 12720 0 -250 12470 11890 580 12470 0 2600 2600
450 Onshore fab 6140 0 0 6140 5725 415 6140 0 573 573
460 Transportation 2200 0 0 2200 2125 75 2200 0 0 0
470 Offshore Works 5400 0 0 5400 5100 300 5400 0 0 0
480 Hook-up Wks 3600 0 -250 3350 2950 400 3350 0 0 0
480 Commissioning sup 800 0 0 800 600 200 800 0 0 0
490 Spare parts 300 0 0 300 300 0 300 0 0 0
4*** TOTAL 37070 0 -500 36570 34500 2070 36570 0 6383 5073
PROJECT: ANGELA PAPYRUS
LEVEL 1 Quarter Platform
TOTAL E&P XXXX
DATE: OCT 2004
ALL IN k US$
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
CODE DESCRIPTION
APPROVED
BUDGET
SCOPE
CHANGE
BUDGET
TRANSFER
CURRENT
BUDGET
(1+2+3)
COMMITMENT
ESTIMATE to
COMPLETE
FORECAST
(5+6)
Variance
(+/ -)
(7-4)
Expenditure
Incurred
Approved
Invoices
510 Purchase Hull 12500 0 1500 14000 14000 0 14000 0 14000 14000
520 Gen. Mngt & Serv 1500 0 0 1500 1400 100 1500 0 240 240
530 Engineering 3650 0 0 3650 3500 150 3650 0 410 410
540 Mal & Eqpt supply 10200 0 0 10200 9900 300 10200 0 3600 1800
550 Onshore fab 6500 0 0 6500 5900 600 6500 0 573 0
560 Towing 1800 0 0 1800 1800 0 1800 0 0 0
570 Offshore Works 2500 0 0 2500 2200 300 2500 0 0 0
580 Hook-up Wks 2280 0 1200 3480 3100 380 3480 0 0 0
580 Commissioning sup 1100 0 0 1100 970 130 1100 0 0 0
590 Spare parts 400 0 0 400 400 0 400 0 0 0
5*** TOTAL 42430 0 2700 45130 43170 1960 45130 0 18823 16450
PROJECT: ANGELA PAPYRUS
LEVEL 1 FPSO & BUOY
TOTAL E&P XXXX
DATE: OCT 2004
ALL IN k US$
Cost monitoring example

More Related Content

What's hot

How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013Ong-Art Sanpinit
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
RESUME-Piping Design Engineer - 13+Years Exp
RESUME-Piping Design Engineer - 13+Years ExpRESUME-Piping Design Engineer - 13+Years Exp
RESUME-Piping Design Engineer - 13+Years ExpSURENDRA BABU
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionJaswin Sood
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Construction site engineer performance appraisal
Construction site engineer performance appraisalConstruction site engineer performance appraisal
Construction site engineer performance appraisalmollyhenderson260
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Project management basics variations and change control
Project management basics variations and change controlProject management basics variations and change control
Project management basics variations and change controlClaire Davies
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Indra Pandu Prasetyo
 

What's hot (20)

How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
RESUME-Piping Design Engineer - 13+Years Exp
RESUME-Piping Design Engineer - 13+Years ExpRESUME-Piping Design Engineer - 13+Years Exp
RESUME-Piping Design Engineer - 13+Years Exp
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Construction site engineer performance appraisal
Construction site engineer performance appraisalConstruction site engineer performance appraisal
Construction site engineer performance appraisal
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project management basics variations and change control
Project management basics variations and change controlProject management basics variations and change control
Project management basics variations and change control
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
 

Similar to 08-Project-Control-ppt.ppt

45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11Robert (Bob) Owens
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2David Greig
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CVSajith Nair
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - LatestPeter White
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar BeheraTarun Behera
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
Ch5ProjectPlanning.ppt
Ch5ProjectPlanning.pptCh5ProjectPlanning.ppt
Ch5ProjectPlanning.pptMDNoyonIslam6
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Anthony Davies
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfAYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfrinkumandaljis
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsJeremie Averous
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...Egyptian Engineers Association
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerSankar Sundaram PMP
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineerSankar Sundaram PMP
 

Similar to 08-Project-Control-ppt.ppt (20)

45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CV
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Peter White CV
Peter White CV Peter White CV
Peter White CV
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Ch5ProjectPlanning.ppt
Ch5ProjectPlanning.pptCh5ProjectPlanning.ppt
Ch5ProjectPlanning.ppt
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfAYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdf
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 

More from TecnicoItca

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdfTecnicoItca
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.pptTecnicoItca
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTecnicoItca
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptTecnicoItca
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptxTecnicoItca
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.pptTecnicoItca
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTecnicoItca
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.pptTecnicoItca
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.pptTecnicoItca
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.pptTecnicoItca
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxTecnicoItca
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptTecnicoItca
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptxTecnicoItca
 

More from TecnicoItca (20)

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdf
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.ppt
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptx
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.ppt
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptx
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.ppt
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.ppt
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.ppt
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.ppt
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

08-Project-Control-ppt.ppt

  • 1. Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 8. Project Control RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013
  • 2. © 2011 - IFP Training Management of Medium-Size / Revamping Projects: course content I. Introduction II. Preliminary Studies III. Basic Engineering (or FEED) IV. EPC Contracting V. Organization and Engineering VI. Procurement VII. HSE, Quality and Risk Management VIII. Project Control (cost/schedule) IX. Construction and Fabrication Management X. Completion / Commissioning / Start-up / Closure RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 2
  • 3. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 3 Module 7 Contents 1. Project control 04 - 06 2. Scheduling and progress control 07 - 26 3. Cost estimating and control 27 - 55 ATTACHMENTS (slides 56 to 82) I. WBS and Schedule examples II. More about Progress Control III. Cost Reporting details/examples
  • 4. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 4 Project Control Scope / Objectives  Scope: • Engineering, Procurement and Construction stages of the project (including main Contractor, Subcontractors and Suppliers) • Mainly Cost and Schedule (for HSE and Quality: see previous chapter)  Schedule Control objectives: • Establish an optimized project schedule, accepted by all contributors • Determine constraints and critical path • Define method to measure progress, and apply it throughout execution  Cost Control objectives: • According to Owner cost structure, produce an optimized Cost Estimate • Make sure the budget is kept under control − Using appropriate tools − Defining roles and responsibilities at all levels
  • 5. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 5 Project Control Process (Monthly) SCHEDULE STATUS LINE (Monthly) PROGRESS CALCULATION (Monthly) COST CALCULATION Trend Analysis Baseline Schedule Schedule Status Planned Progress PROJECT PROGRESS CONTROL SYSTEM (Activities weights USD, mhrs) PROJECT SCHEDULE SYSTEM (e.g CPM) PROJECT COST CONTROL SYSTEM (USD) Actual Progress Progress Analysis Progress Forecast Initial Budget Cost Analysis Cost Forecast Expenses & Committments CONTROL ACTION CONTROL ACTION CONTROL ACTION « FEEDBACK » PROCESSES PROJECT WORK BREAK DOWN (WBS) STRUCTURE: Activities Split
  • 6. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 6 Project Control Communication / Reporting  Frequent communication / reporting is critical for performance  It enables the Project Manager to obtain • A clear picture of the Project progress vs budget and schedule • A timely identification of adverse trends / threats  It allows the Project Team: • To react and take immediate corrective actions, • If necessary, to design strategic recovery plans • To communicate with Owner and avoid last-minute surprises  Cost and Schedule can be both critical (but it depends on contract type) • To Owner (more often, Schedule) • To Engineering Contractor (more often, Cost)
  • 7. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 7 Scheduling and progress control  Owner Scheduling • Work Breakdown Structure • Scheduling, Schedule levels • Critical path • Schedule revisions • Scheduling tool  Contractor Scheduling • Same content as above  Progress Control • Progress measurement • Recovery Plan • Schedule re-baselining
  • 8. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 8 Owner Scheduling Work Breakdown Structure  The objective of the WBS is to provide an organised structure covering the whole content of the project and to include, at different levels of detail, the information necessary to monitor, control and correctly report all project activities  The project WBS takes consideration of: • Project configuration (size, geographical and technical nature) • Project management considerations (split of responsibilities, contracting strategy / packages, reporting requirements)  It is generally organized (for an EPC schedule), by: • A geographical divisions: Work Packages / Areas / units • Work subdivisions (engineering disciplines, construction trades...) See examples in Attachment I
  • 9. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 9 Owner Scheduling Purpose  Owner may have to prepare a Schedule for various reasons, e.g.: • A consolidated Project schedule (Project split into several EPC packages) • Preliminary Project schedule at pre-Project stage (Owner leader) • Commercial reasons (e.g. external customer commitments) • Schedule with contingency, vs. the one discussed with EPC Contractor  Level-0 Owner schedule will generally be presented as a Bart Chart  More detailed levels will also be developed, using PERT/CPM  Schedule presentation will be consistent with Owner WBS
  • 10. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 10 year J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O JACKET & FLARE 4 Basic Engineering 4 CFT - EPCI 5 Detail Engineering Procurement 8 Construction 1 Installation TOPSIDES 4 Basic Engineering 4 CFT - EPCI 8 Detail Engineering 10 Procurement 11 Construction & Transportation Installation Hook up & commissionning PIPELINES & CABLES 3 Engineering 3 CFT 9 Procurement & transport Installation DRILLING & COMPLETION PRODUCTION 27 Owner Scheduling Bart Chart example for 4 packages
  • 11. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 11 Owner Scheduling Schedule types Scheduling: a fundamental task of Project Management  In Revamp projects, Schedule and Cost can be closely interrelated  Bar Chart: common way to prepare the first-pass schedule • Easy to prepare, to read (condensed format, 1 line per activity) • More difficult to see critical path and to evaluate impact of changes  PERT (Project Evaluation and Review Technique) ... then PDM • Determination of Critical Path • Sequencing logics is built into the schedule • Then, bar charts can be produced from the network
  • 12. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 12 Owner Scheduling Schedule levels  Level 0 – Project Master Schedule: • Executive summary schedule used for reporting at Management level • Frozen at Project Sanction = Initial Baseline Schedule • Shows target dates, key milestones and main phases  Level 1 – Integrated Project Control Schedule: • Time-scale logic diagram • Decision steps, contracts sequence, work package summary activities, LLIs • Major milestones and overall project critical path  Level 2 and 3 – Contractor and sub-contractor Schedules • Cover all the activities/tasks of the Contracts • All milestones necessary to control contractors’ physical progress • Procurement of main equipment and fabrication, construction, installation, commissioning, with the critical path
  • 13. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 13 Owner Scheduling Links between activities and critical path  Network is built with activities predecessors and followers &, linked by End-Start, Start-Start, or End-End link  Critical path: path of activities with no float • Provides shortest project duration • Goes through a series of activities from Project Start to Project Completion (e.g. studies and technical evaluation, delivery of some equipment, fabrication, site installation, hook-up, drilling) Float Float Critical Path Critical Path Critical Path Critical Path
  • 14. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 14 Owner Scheduling Example: Gantt bar chart
  • 15. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 15 Owner Scheduling Schedule revisions  Baseline Schedule revisions performed on Project Manager decision in case of significant changes or delays  Detailed assessment, based on Level 2 schedule, of all remaining activities (internal / contractors), duration & sequences including: • Actual physical progress and achieved milestones • Manhours progress and actual vs estimated productivity • Upcoming Change Orders (requested or potential) impacts on schedules • Performance of simulation schedules and “what-if” scenario as well as detailed schedules risks analysis performed by/with the Risks Assessment Manager.  Contractors may also need to revise their Baseline Schedules which may cause a revision of Company schedule
  • 16. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 16 Owner Scheduling Common softwares  Scheduling: common softwares for Medium & Small Projects: • MS-Project for small EPC projects, preliminary studies, FEED • Primavera for EPC phase (and FEED if necessary)  For presentation purposes: • Level 0 (on Excel, with information extracted from Primavera Level 1) • Level 1 or 2 only for specific critical activities  Progress reports : often prepared with Excel
  • 17. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 17 Contractor Scheduling Differences  Scheduling by EPC Contractor: more detailed than Owner • A detailed WBS/OBS is prepared to define areas and work phases for the project schedule & progress reporting • Scheduling hierarchy generally includes 4 main Levels for the concerned EPC contract, plus many sub-level schedules  Contractor responsibility on schedule compliance • Depends on the contract type (and therefore on Owner priorities) • May have financial consequences for him (or not)  Owner control on Contractor progress has to be applied
  • 18. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 18 Contractor Scheduling EPC schedule hierarchy  Level 0 schedule: Project Master Schedule: milestones dates and main work phases  Level 1: Overall Project Schedule with, for major WBS areas: • Engineering by discipline (major engg milestones: PIDs, Plot Plan, MTOs, Reviews...), • Procurement with LLIs and major equipment purchasing / delivery, • Construction by trade, pre-com/com, milestones dates (MC, RFC, RFSU…) • Critical path  Level 2 schedule: Areas Schedule: CPM network; all activities according to WBS / OBS • All engineering activities by discipline and deliverables category, • Procurement activities for all equipment & bulks requisitions, • Construction by trade or construction packages, pre-com / com, • Detail critical path from CPM
  • 19. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 19 Contractor Scheduling EPC schedule hierarchy  Level 3: Detailed Schedules • Engineering deliverables (usually with engineering progress measurement system) • Procurement schedule (may be with procurement progress measurement system) • Site Level 3 CPM construction schedule, with Level 3 construction contractor subcontract schedules, in line with Level 2 schedule; used for progress reporting • Site CPM pre-commissioning / commissioning schedule detailed by Areas / Units / Systems / Tasks and used for progress reporting • For Revamped areas: Shut-down schedules by Job Cards A 3 months look-ahead schedule may be used for reporting
  • 20. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 20 Contractor Scheduling Key elements to consider  Contractual milestones for achievements of the whole project or intermediary.  LLI (Long Lead Items), when applicable: items on the project critical path  Global project size and engineering, procurement and construction resources requirements versus their availability for the concerned project / site (progress rates) will translate into required manhours at peak and feasible progress rate  For Revamping projects: Planned shut-downs calendar times and durations  Standard « statistic » progress curves with % completion vs. project duration in % are available to provide a reference progress for each activity: • Engineering by discipline (process, equipment, civil, piping, E/I/A) • Procurement (main equipment, bulk material) • Construction (For each trade: Civil, U/G piping, Piping pre-fabrication, equipment erection, piping erection, instrumentation, painting, insulation)
  • 21. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 21 Contractor Scheduling Typical critical path  Typical critical path for an E/P onshore project usually includes: • Long Lead Items (including erection and installation) • Process PIDs (approved by Owner for design) • Main equipment purchases (including inspection/transportation) • Piping isometrics, pre-fabrication and installation • Control loop checks at the end of construction
  • 22. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 22 Contractor Scheduling Schedule of Revamp projects Revamping Project Schedule is strongly influenced by:  Production objectives vs time: new production milestones after revamp  « Usual shut-downs » planned time and duration (need to minimize production outage time, including upstream and/or downstream facilities)  Work authorised during pre-shutdown phases in live facilities: if too limited, amount of work during S/D and construction may become: • More/very expensive • Higher HSE/Reliability risk • Even unrealistic  delays and/or major Quality concerns  Consider using available Owner supervision & commissioning staff Carefully review schedule constraints with Owner during FEED, to avoid subsequent trouble and change orders
  • 23. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 23 Progress control Purpose  Compare actual progress vs schedule. Several ways: • Milestones • Overall physical progress • Physical progress of the Critical Path • Expected completion date vs plan • Manhours progress vs detailed schedule  Analyze trends to decide if corrective actions are necessary  Depending on contract type, Owner validation may be required
  • 24. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 24 Progress control Progress reporting  Periodic Progress Reports: a key Project Management tool  Address progress, but also all key events, problem areas and higher level problem areas (« areas of concern »)  Prepared: • Daily at site (construction / pre-com / com). • Weekly for Head Office activities and for construction • Monthly • Issued before periodic Owner / Main Contractor review meetings
  • 25. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 25 Prepares Daily report (constr) Weekly report Monthly reprt Feedback Incident Close-out SUB CONTRACTORS Reviews, Responds, Consolidates Oper. Centers & Site Reports Alerts Feedback Incident Close-out Monitors, Monthly Monitors, Recommends Monthly Incident Close-out JV STEERING COMMITTEE CONTRACTOR PROJECT MANAGEMENT TEAM CONTRACTORS CONTRACTOR MANAGEMENT Progress control Progress reporting MONTHLY MEETING MONTHLY MEETING COMPANY PROJECT MANAGEMENT TEAM MONTHLY MEETING Prepares Daily report (constr) Weekly report Monthly report Alerts Feedback Incident Close-out Prepares Daily report (constr) Weekly report Monthly reprt Alerts Feedback Incident Close-out WEEKLY MEETING WEEKLY MEETING DAILY MEETING (Constr.)
  • 26. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 26 Progress control Progress reporting Typical CONTENT  Executive Summary  HSE performance  Engineering  Procurement  Subcontracting  Construction  Pre-com / Com  Project Controls  Quality  Areas of Concern  Major events, achievements, problem areas, highlights  HSE statistics, near misses register  Progress S curves, tabulations: planned, actual, forecast for Project, Work Packages, global E, Disciplines, P, global C, C by areas/ units, C by trades  Milestones status  COI/COR register  Invoices register  Cash flow actual & predictions  Procurement materials status reports  NCR register  Documents register  Level 1 Project Schedule with progress status; Trend analysis; recovery plan  Manpower histograms planned & actual
  • 27. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 27 Progress control Progress measurement  Split project activities according to structure close to the WBS  Define weights to each line, using adequate units (€, manhours…)  For each Work package, aggregate these tasks by Levels : • 1: Work-Package or sub-project • 2: Categories: home office services, procurement, construction… • 3: Sub-categories: engineering discipline, requisition, construction trade • 4: Tasks: engineering deliverables, equipment, construction items • 5: Elementary steps: drawings, fabrication, construction works  During execution: • Measure progress achieved for each elementary step • Then, aggregate to the different Levels and compute overall progress See examples/illustrations in Attachment II
  • 28. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 28 Progress control Progress curves 0% 0% 1% 2% 3% 4% 6% 7% 9% 11% 14% 17% 20% 25% 30% 35% 40% 46% 51% 56% 61% 67% 70% 73% 76% 79% 82% 84% 85% 87% 90% 92% 95% 97% 99% 100% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Months TYPICAL PROGRESS CURVES Engineering Procurement Fabrication Construction Commissioning Total
  • 29. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 29 Progress control Progress curves  Engineering « S » progress curves are prepared from Level 3 schedule (typically during the first 3 months of the contract)  More detailed “S” curves are prepared during Execution: • Detailed construction / fabrication curve • Field erection curve • Installation / commissioning curve  First « S » progress curves and histograms can be prepared from Level 2 schedule and manhours estimates; they allow to check that construction scheme is realistic for construction contractors  Until the Project EPC schedule is issued, a 3-month look-ahead schedule is prepared to anticipate short-term schedule and resource concerns
  • 30. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 30 Progress control Typical causes for EPC contractors delays  Insufficient manpower resources (quantity and/or quality)  Supplier or Subcontractors (careful on sub-sub-contracting !)  Strikes, disturbances related to local environment  Underestimates (manhours, bulk quantities)  Equipment Quality unacceptable non-conformances  Late information, comments or reviews from Owner This list is incomplete. Other ideas ?...
  • 31. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 31 Cost Estimating and Control • Cost estimating • Cost reporting and control • Change Management
  • 32. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 32 Cost Estimating and control Scope and objectives  Scope: Project CAPEX (OPEX is not in the scope)  Objectives: • Estimate the project CAPEX and propose the overall budget • Make sure that this budget is acceptable to all contributors − Sufficient to assure Project HSE/Quality performance − Generating acceptable profit for each stakeholder » Owner » EPC contractor » Suppliers and Subcontractors − Consistent with the cost and schedule constraints − Allowing adequate risk management • Organize the Cost Reporting/Control process (involving Owner) • Define the Change Management process (involving Owner)
  • 33. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 33 Cost Estimating Budget  Any Project has a controlled and approved Budget  The Budget may be adjusted (Revised Budget) during the Project Life: • Budget transfer from other projects • Scope deletions or additions, approved by Owner  Structurally, the budget is expected to increase as Project develops  At the end of the Project: • Cost analysis will establish the “Final cost” − After Mechanical Completion and Handover − Once claims are settled and invoices paid • The final Cost Control report is issued • Comparison with Revised Budget allows to draw feedback lessons
  • 34. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 34 Cost estimating Methodology
  • 35. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 35 Main Equipment Bulk Fabrication/Construction(onshore/offshore) Engineering Services Management & Supervision Surveys Transportation Temporary Facilities Construction camps Insurance Commissioning Direct Costs Contingencies Facilities Cost Estimate Indirect Costs General Expenses Associated Expenses + + + + = Direct Costs + Indirect Costs = Technical Costs Cost estimating Structure Fabrication / Construction cost are the highest costs and the most difficult to estimate, in particular for works in revamped process units and brown field; they are very site dependent (productivity)
  • 36. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 36 Cost estimating Preliminary Estimate: a Challenge  CAPEX estimate usual desired accuracy is +/- 30% for « new » or « expanded » parts of projects in existing facilities, which may be relatively easy if the Plant is recent and cost data base available or difficult depending on: • Project complexity and location • Onshore or Offshore projects • Concerned facilities • Modifications to facilities (Expansion, Debottleneck, Upgrade, Revamp)  The CAPEX estimating method will depend on: • Cost data base (Owner and/or Contractor) for works at that location • Nature of facilities (onshore or offshore, subsea or surface, new or revamped process units, interconnecting with work in brown field…),  The CAPEX estimate should be prepared with a memorandum underlying assumptions, estimating methodology, uncertainties and risks
  • 37. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 37 Cost estimating Preliminary Estimate: a Challenge  Estimating methods are global as project details such as P&IDs are not prepared; the estimating methodology will combine available cost data base and estimating tool box.  Estimators use cost data breakdowns, unit costs, etc. from similar recent project units at the location, or at similar (in terms of cost) location, with corrections for location (importance of construction cost), escalation, and other foreseen different project conditions. (Often the estimators will use units information from several projects).  Many « factors » are used for so called « factored estimates »: • Scaling factor: P1 / Po = (C1 / Co)0.65 • Factored estimate from equipment cost: P installed= K x P equipment K may range from 2 to 6 depending on equipment type For revamped areas an other K1 factor is to be applied on top • Global factor on top of Direct Costs: Total cost = K x Project Direct Cost • A cost factor can be used for transportation (onshore projects)
  • 38. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 38 Cost estimating Preliminary Estimate: a Challenge  Cost information is gathered from all possible sources at the time, e.g: • Major / special equipment or packages (glycol treatment, water treatment, utilities and power packages, etc.): prices from Vendors « budget » quotes. • Interconnecting preliminary quantities estimated by engineering from preliminary MTOs & unit costs used from previous project at the facilities, for bulks cost & for construction cost; quotations from Vendors for large pipe / pipelines • Engineering, construction supervision manhours may be estimated by ratios. • Contingencies or CRP (Contingency, Risks and Profit) factor, added on top of estimate
  • 39. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 39 Cost estimating CAPEX estimate during FEED  CAPEX estimate prepared according WBS/OBS; desired accuracy +/- 15%  Estimate is Quantities x Unit Costs  Construction cost is all-in construction mhrs rates x construction mhrs  Construction cost: the most important cost item, the most difficult to estimate  CRP (Contingency, Risks and Profit factor) is added on top of the cost estimate  CAPEX estimate prepared with a memorandum underlying assumptions, estimating methodology, uncertainties and risks.  Estimating methodology principles are presented on next slides
  • 40. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 40 Cost estimating CAPEX estimate during FEED
  • 41. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 41 Cost estimating CAPEX estimate during FEED
  • 42. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 42 Cost Control process Owner perspective  Owner cost control process and involvement in tracking cost components depends on the type of EPC contract  If a contract is on Reimbursable basis, Owner will have access to all cost elements and is responsible for the complete Project cost  If a contract is on a Lump Sum basis, Owner will have access only to the cost items specified in the contract  Owner will have access to the cost estimate to support change orders, approve them, and include them to Cost Control process
  • 43. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 43 Cost Reporting and Control Forecast  Purpose : determine the Forecast to Complete  Cost Forecast is updated on a regular basis (typically, monthly)  Cost Forecast may anticipate on non-finalized commitments  Cost Forecast requires a good knowledge of technical matters  Cost Forecast may introduce some budget transfer  Cost Forecast includes proper management of Contingencies • Advisable not to consume them during the early stages • Corporate rules (Owner and/or Contractor) may exist • The Project Manager has ultimate authority
  • 44. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 45 Cost Reporting and Control Organisation principles Cost control organisation includes mainly:  Cost Control Manager, assisted by Cost Controllers depending on Project size, responsible for global project cost control and reporting to operationally to the Project Control Manager and functionnaly to the Contractor Management (in case of a JV, will report to JV Project Manager on one hand and, on the other hand, to Partner Management within its own organisation, issues being then adressed if necessary by the JV Steering Committee)  Site Cost Control Manager responsible for cost control at the site and reporting operationnally to the Site Manager but functionally to the Cost Control Manager  Cost Estimators to estimate project cost changes and reporting to the Project Control Manager
  • 45. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 46 Cost Reporting and Control Cost Controller duties (1/2) Mainly coordinates with:  Engineering and scheduling / progress control organisations to control engineering manhours cost expenditure, planned mobilisation and trends from productivity and personnel mhrs rates, and to control bulks quantities trends considering MTOs vs their engineering documents basis  Procurement to control Vendors offers versus budget (advise budget target before negotiations, check and approve CBTs and Vendor price), and track P.Os change trends  Fabrication / construction contracts management to control cost and trends versus budget (before transfer of construction contracts administration the site)  Site cost control to control site costs and trends  Project Management for allocation and use of technical cost contingencies or global project risks provisions Prepares costs expenses reports, forecast and monthly cost reports; also prepares change orders
  • 46. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 47 Cost Reporting and Control Cost Controller duties (2/2) Mainly Coordinates with:  Fabrication / Construction / Pre-com / com Management to control site supervision cost (mobilised cost, planned mobilisation, daily rates costs...)  Site Contracts Administrator(s) / quantities surveyors and Scheduling / Progress Control Manager to control current construction cost, establish forecasts from anticipated quantities variations, productivity, and additional work orders  Site procurement for local purchases  Site Administration Manager for site running costs control (accommodation / camps, TCF...)  Prepares back-charges to Vendors and Construction Contractors as applicable, insurance claims in case of damages during transport or at site  Prepares site costs expenses reports, forecast and monthly cost reports; also prepares change orders
  • 47. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 48 Cost Reporting and Control Periodic actions  Day-to-day: • Review work progress and consistency with contract terms • Inform Management of any non-budgeted items • Review all invoices received and consistency with contract terms  Typically on a monthly basis: • Calculate the escalation formulae and price revisions, if any • Manage the various provisions • Review the estimate to complete and the final forecast  Less frequently (quarterly, annually, or ad hoc): • Formal reporting to EPC Management, Owner and Partners • Regulatory reporting if applicable (e.g. tax) • Propose budget revisions
  • 48. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 49 Cost Reporting and Control Keys of effective cost control  Timely and serious estimate of Engineering Manhours  Bulk Quantities estimate based on complete detail engineering  Check of Suppliers and Fabrication/Construction contracts: • Estimates based on up-to-date verified info • Actual costs timely compared to estimate, and challenged • Rigorous Procurement procedures, no by-pass  Schedule changes: careful about cost consequences  Rigourous Change Management  Accurate and timely Reporting / Forecasting to Management  Timely followup of cost control actions decided by the team
  • 49. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 50 Management of change Process Management of Change Covers all changes to contract Engineering Deviation Requests • Cover deviations to contractual reference standards or already Approved Design Specifications • Written Procedure • Deviation Requests Register • Clear Owner approval authority Change Order Procedure • Covers Additions, Modifications and Deletions to Project scope, with impact on Project cost, schedule, process performance • Procedure includes: − Change Process − Change Orders Log − Approvals • Change Requests Register
  • 50. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 51 Management of change Deviation requests/engineering queries  Clarify or ask a deviation to a contractual document, for the purpose of developing the detail engineering and procurement requisitions Usually due to: • Conflicting requirements in different documents • Proposal of an engineering improvement • Required materials not consistent with local availability  Ask a deviation to already approved requisition documents Usually due to: • Proposal of a supply improvement • Availability of raw materials different from requirements • Vendors fabrication or test standards different from requirements • Standard packages or skids
  • 51. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 52 Management of change Change order procedure A “Change Order” is not an anomaly • When cost variations are not due to Contractor and potentially give rise to a Change Order: Contractor notifies Company and prepares a Change Order Request (COR) with an estimate and formal request to be usually submitted within 2 weeks maximum to Company. • Company may also need to change the scope, or to exert Options provided under the contract, or for any reason to ask Contractor to change its work thru a Change Order Instruction (COI). Company then notifies Contractor with an estimate to be usually submitted within 2 weeks maximum to Company. • Change Orders are monitored by the Project Cost Management team and recorded as soon as they are identified on a Change Order Register. • Change Orders estimates are evaluated by the Contractor (using contract unit costs as available), and checked by Company Cost Management team. • Change Orders need to be formalized and agreed by all Parties and will therefore be transferred to Project budgets (Company and Contractor) only after Approval by Company.
  • 52. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 53 Management of change Cost trends caused by Owner  Project definition unclear or incomplete  Scope changes during execution  Delayed access to construction areas  Missing elements or information  Wrong assumptions on market costs  Unclear interfaces between contractors  Conflicts with EPC Contractor, or Suppliers, or Subcontractors  Insufficient quality of Project Management Team  Delays in achieving Owner tasks
  • 53. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 54 Management of change Cost trends caused by Environment  Unplanned inflation rate or exchange rate changes  Weather catastrophy (cyclones, flooding, earthquakes)  Political trouble (strikes, wars, unplanned regulatory changes)  Delays to obtain working visas  Unexpectedly low productivity due to bad weather  Unforeseen difficulties (soils or sea bed conditions)
  • 54. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 55 Management of change Cost trends caused by EPC Contractor  Initial Price too low  Insufficient qualification of Project Management Team  Inability to forecast on time  Sub-contractors lack of performance  Estimating errors (incomplete/incorrect technical info)  Insufficient provisions or contingency  Missing cost elements  Wrong assumptions on supplier/subcontractor markets
  • 55. © 2011 - IFP Training Key points to keep in mind RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 56 Project control  Owner has a critical role in controlling EPC Contractor performance  This role depends on the contract type but is always to be assured  Scheduling: • May be quite critical on Revamping projects (shutdown windows) • Smaller projects need simpler tools • Critical path should be clearly identified and optimized  Cost estimating: • Up-to-date cost databases are a key to effective estimating • Accuracy of Cost Control estimate should be around 10% • Estimate used for approval (FEED stage) should be based on quantities  Cost and Schedule control: • Monitoring methods should be clearly defined in the EPC contract • For Revamping projects, may be closely inter-related
  • 56. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 57 ATTACHMENTS I. WBS and Schedule examples II. More about progress control III. Cost reporting details/examples
  • 57. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 58 ATTACHMENT I WBS and Schedule examples
  • 58. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 65 ATTACHMENT II More about Progress Control
  • 59. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 66 Principle split % according to USD values OVERALL PROJECT WORK PACKAGE 1 WORK PACKAGE 2 HOME OFFICE MANUFACTURING CONSTRUCTION AND HOME OFFICE MANUFACTURING CONSTRUCTION AND SERVICES DELIVERY PRECOMMISSIONING SERVICES DELIVERY PRECOMMISSIONING 15% 35% 50% 15% 35% 50%
  • 60. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 67 Principle split – Weights sample onshore % according to mhrs for services and USD for procurement
  • 61. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 68 FPSO 28,6% TOPSIDES Engineering 10,6% Procurement 34,2% Construction 16,8% Integration 3,3% Towing FPSO & Flotel 2,1% Tie-in precomm and Comm 1,8% HULL & L Q 31,2% SPS 14,3% Engineering 4,0% Procurement 22,1% Manufacturing 67,3% Systems Testing 3,3% Transport 3,3% UFR 24,5% Engineering 4,5% Procurement 36,2% Construction 14,5% Offshore Installation 27,8% OLT 17,0% DRILLING 32,7% Drilling Rig 42,8% Rig Contract Services 57,2% TOTAL 100,0% Progress measurement: Weighting sample offshore
  • 62. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 71 Recovery plan example: loss of mobilisation at year end and drifting ACTUAL PROGRESS ON TIME UNTIL END DEC. BUT DRIFTING RECOVERY PLAN: INCREASE MOBILISATION TO INCREASE PROGRESS
  • 63. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 72 Project Schedule sample: Gas Plant 2 Trains extension and upgrade – S/Ds Planning One major S/D initially Four S/Ds at actual EPC time start
  • 64. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 73 Progress curves: Schedule Baseline Revisions
  • 65. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 74 JC preparation progress curve Preparation of JCs may take several months: procedure for preparation, progress control to be implemented
  • 66. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 75 Fabrication scheduling
  • 67. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 76 Scheduling transportation to site  Transportation to site of the main components is not very difficult by itself, but the coordination of this activity can be a real challenge  The speed of the spread(s) transporting the main components is directly calculated from the distance and the marine spread speed + some provisions for bad weather, adverse wind, …  The capacity of the transportation barge or vessel must be assessed carefully: transporting 2000 tons, 5000 tons or even 30000 tons is a case by case study
  • 68. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 77 Scheduling offshore installation Initial scheduling of offshore installation requires:  Detailed analysis of the scope: number and main characteristics of all modules / decks / jackets / pipelines / floating storage…  Evaluation of the marine construction equipment required: • Derrick barge – crane capacity • Pipe Laying Barge – stinger – max pipe size – type of welding • Offshore tie-in means: ROV… • Trenching, shore approach equipment • Drilling rigs type… The schedule will be reviewed after contractors selection
  • 69. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 78 Scheduling offshore installation
  • 70. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 79 Scheduling hook-up  Hook-up time is highly dependant upon the yard fabrication and its level of completion  It is fundamental to reduce as much as possible the hook-up work: hook-up is very costly and always critical  No hook-up without accommodation  No hook-up without a good logistic and supporting equipment
  • 71. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 80 ATTACHMENT III Cost Reporting details/examples
  • 72. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 82 * Level 0 = Project 1 = Phase 2 = Major Work Split 3 = Commitment 4 = Work Package Company Cost Report Format Principles Project Level* Description (1) Approve d Budget (2) Scope Change (3) Budget Transfer (4) Current Budget (1+2+3) (5) Commit (6) Estimate To Complete (7) Forecast (5+6) (8) Variance (+/-) (4-7) (9) Expend. Incurred (10) Approved Invoices AFE X Y Z 100 50 90 0 0 0 0 10 - 10 100 60 80 90 60 80 12 0 - 5 102 60 75 2 0 - 5 70 60 73 65 60 65 Sub-total 240 0 0 240 230 7 237 - 3 203 190 Provisions Contingen cy 24 0 0 24 0 22 22 - 2 0 0 Total 264 0 0 264 230 29 259 - 5 203 190
  • 73. © 2011 - IFP Training RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013 83 (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) CODE DESCRIPTION APPROVED BUDGET SCOPE CHANGE BUDGET TRANSFER CURRENT BUDGET (1+2+3) COMMITMENT ESTIMATE to COMPLETE FORECAST (5+6) Variance (+/ -) (7- 4) Expenditure Incurred Approved Invoices 100 Initial Studies 13350 0 0 13350 13350 0 13350 0 200 Wellhead Connect. 54550 0 0 54550 51550 3000 54550 0 30 26 300 Production Pltf 137320 0 -10000 127320 118380 8940 127320 0 12760 10000 400 Quarter Pltf 37070 0 -500 36570 34500 2070 36570 0 6383 5073 500 FPSO 42430 0 2700 45130 43170 1960 45130 0 18823 16450 600 Buoy & Sealines 12900 0 0 12900 0 12900 12900 0 45 42 700 Management 5600 0 0 5600 0 5600 5600 0 15 15 Sub-Total 303220 0 -7800 295420 260950 34470 295420 0 38056 31606 800 Provisions (rate) 2100 0 -10 2090 0 2090 2090 0 10 10 900 Contingency 12430 0 0 12430 0 12430 12430 0 0 0 **** TOTAL 317750 0 -7810 309940 260950 48990 309940 0 38066 31616 PROJECT: ANGELA PAPYRUS LEVEL 0 TOTAL E&P XXXX DATE: OCT 2003 ALL IN k US$ (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) CODE DESCRIPTION APPROVED BUDGET SCOPE CHANGE BUDGET TRANSFER CURRENT BUDGET (1+2+3) COMMITMENT ESTIMATE to COMPLETE FORECAST (5+6) Variance (+/ -) (7-4) Expenditure Incurred Approved Invoices 210 Gen. Mngt & Serv 2200 0 0 2200 2200 0 2200 0 350 0 220 Engineering 4400 323 0 4723 4523 200 4723 0 0 0 230 Mal & Eqpt supply 8500 645 0 9145 9045 100 9145 0 0 0 240 Onshore fab 22500 1682 0 24182 23582 600 24182 0 0 0 250 Transportation 3550 0 0 3550 3450 100 3550 0 0 0 260 Offshore Works 16500 0 -500 16000 15800 200 16000 0 0 0 270 Hook-up Wks 6200 0 0 6200 6000 200 6200 0 0 0 280 Commissioning sup 3200 0 -1800 1400 1000 400 1400 0 0 0 290 Spare parts 950 0 -350 600 550 50 600 0 0 0 2*** TOTAL 68000 2650 -2650 68000 66150 1850 68000 0 350 0 PROJECT: ANGELA PAPYRUS LEVEL 1 WELLHEAD PF & CONNECTION TOTAL E&P XXXX DATE: OCT 2004 ALL IN k US$ (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) CODE DESCRIPTION APPROVED BUDGET SCOPE CHANGE BUDGET TRANSFER CURRENT BUDGET (1+2+3) COMMITMENT ESTIMATE to COMPLETE FORECAST (5+6) Variance (+/ -) (7-4) Expenditures Incurred Approved Invoices 310 Long lead Items 28630 0 -4200 24430 24430 0 24430 0 4800 2400 320 Gen. Mngt & Serv 2640 0 0 2640 2400 240 2640 0 240 240 330 Engineering 4680 0 -700 3980 3600 380 3980 0 720 360 340 Mal & Eqpt supply 45840 0 -5100 40740 40300 440 40740 0 4500 4500 350 Onshore fab 16480 0 0 16480 16150 330 16480 0 2500 2500 360 Transportation 4500 0 0 4500 4500 0 4500 0 0 0 370 Offshore Works 18000 0 0 18000 14500 3500 18000 0 0 0 380 Hook-up Wks 8500 0 0 8500 6200 2300 8500 0 0 0 380 Commissioning sup 4850 0 0 4850 3800 1050 4850 0 0 0 390 Spare parts 3200 0 0 3200 2500 700 3200 0 0 0 3*** TOTAL 137320 0 -10000 127320 118380 8940 127320 0 12760 10000 PROJECT: ANGELA PAPYRUS LEVEL 1 Production Platform TOTAL E&P XXXX DATE: OCT 2004 ALL IN k US$ (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) CODE DESCRIPTION APPROVED BUDGET SCOPE CHANGE BUDGET TRANSFER CURRENT BUDGET (1+2+3) COMMITMENT ESTIMATE to COMPLETE FORECAST (5+6) Variance (+/ -) (7-4) Expenditure Incurred Approved Invoices 410 Long lead Items 2560 0 0 2560 2560 0 2560 0 2560 1250 420 Gen. Mngt & Serv 1200 0 0 1200 1200 0 1200 0 240 240 430 Engineering 2150 0 0 2150 2050 100 2150 0 410 410 440 Mal & Eqpt supply 12720 0 -250 12470 11890 580 12470 0 2600 2600 450 Onshore fab 6140 0 0 6140 5725 415 6140 0 573 573 460 Transportation 2200 0 0 2200 2125 75 2200 0 0 0 470 Offshore Works 5400 0 0 5400 5100 300 5400 0 0 0 480 Hook-up Wks 3600 0 -250 3350 2950 400 3350 0 0 0 480 Commissioning sup 800 0 0 800 600 200 800 0 0 0 490 Spare parts 300 0 0 300 300 0 300 0 0 0 4*** TOTAL 37070 0 -500 36570 34500 2070 36570 0 6383 5073 PROJECT: ANGELA PAPYRUS LEVEL 1 Quarter Platform TOTAL E&P XXXX DATE: OCT 2004 ALL IN k US$ (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) CODE DESCRIPTION APPROVED BUDGET SCOPE CHANGE BUDGET TRANSFER CURRENT BUDGET (1+2+3) COMMITMENT ESTIMATE to COMPLETE FORECAST (5+6) Variance (+/ -) (7-4) Expenditure Incurred Approved Invoices 510 Purchase Hull 12500 0 1500 14000 14000 0 14000 0 14000 14000 520 Gen. Mngt & Serv 1500 0 0 1500 1400 100 1500 0 240 240 530 Engineering 3650 0 0 3650 3500 150 3650 0 410 410 540 Mal & Eqpt supply 10200 0 0 10200 9900 300 10200 0 3600 1800 550 Onshore fab 6500 0 0 6500 5900 600 6500 0 573 0 560 Towing 1800 0 0 1800 1800 0 1800 0 0 0 570 Offshore Works 2500 0 0 2500 2200 300 2500 0 0 0 580 Hook-up Wks 2280 0 1200 3480 3100 380 3480 0 0 0 580 Commissioning sup 1100 0 0 1100 970 130 1100 0 0 0 590 Spare parts 400 0 0 400 400 0 400 0 0 0 5*** TOTAL 42430 0 2700 45130 43170 1960 45130 0 18823 16450 PROJECT: ANGELA PAPYRUS LEVEL 1 FPSO & BUOY TOTAL E&P XXXX DATE: OCT 2004 ALL IN k US$ Cost monitoring example