SlideShare a Scribd company logo
1 of 41
Scheduling
Resources
and Costs
CHAPTER EIGHT
PowerPoint Presentation by Charlie Cook
Copyright © 2014 McGraw-Hill Education.
All Rights Reserved.
8–2
Where We Are Now
Overview of the Resource
Scheduling Problem
• Resources and Priorities
– Project network times are not a schedule
until resources have been assigned.
• The implicit assumption is that resources will be
available in the required amounts when needed.
• Adding new projects requires making realistic
judgments of resource availability and project
durations.
– Cost estimates are not a budget
until they have been time-phased.
8–3
8–4
Project Planning Process
FIGURE 8.1
8–5
The Resource Problem (cont’d)
• Resource Smoothing (or Leveling)
– Involves attempting to even out varying demands
on resources by using slack (delaying noncritical
activities) to manage resource utilization when
resources are adequate over the life of the project.
• Resource-Constrained Scheduling
– The duration of a project may be increased by
delaying the late start of some of its activities if
resources are not adequate to meet peak demands.
8–6
Types of Project Constraints
• Technical or Logic Constraints
– Constraints related to the networked sequence
in which project activities must occur.
• Physical Constraints
– Activities that cannot occur in parallel or are affected by
contractual or environmental conditions.
• Resource Constraints
– The absence, shortage, or unique interrelationship and
interaction characteristics of resources that require a particular
sequencing of project activities
• Kinds of Resource Constraints
– People, materials, equipment
8–7
Constraint Examples
FIGURE 8.2
8–8
Classification of a Scheduling Problem
• Classification of Problem
– Using a priority matrix will help determine if
the project is time or resource constrained.
• Time-Constrained Project
– Must be completed by an imposed date.
• Time is fixed, resources are flexible: additional resources
are required to ensure project meets schedule.
• Resource-Constrained Project
– Is one in which the level of resources available
cannot be exceeded.
• Resources are fixed, time is flexible: inadequate resources
will delay the project.
8–9
Resource Allocation Methods
• Limiting Assumptions
– Splitting activities is not allowed—once an
activity is start, it is carried to completion.
– Level of resources used for an activity cannot
be changed.
• Risk Assumptions
– Activities with the most slack pose the least
risk.
– Reduction of flexibility does not increase risk.
– The nature of an activity (easy, complex)
doesn’t increase risk.
8–10
Resource Allocation Methods (cont’d)
• Time-Constrained Projects
– Must be completed by an imposed date.
– Require use of leveling techniques that focus
on balancing or smoothing resource demands.
– Use positive slack (delaying noncritical activities)
to manage resource utilization over the duration
of the project.
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
8–11
Botanical
Garden
FIGURE 8.3
8–12
Resource Allocation Methods (cont’d)
• Resource Demand Leveling Techniques
for Time-Constrained Projects
– Advantages
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
– Disadvantages
• Loss of flexibility that occurs from reducing slack.
• Increases in the criticality of all activities.
8–13
Resource Allocation Methods (cont’d)
• Resource-Constrained Projects
– Resources are limited in quantity or availability.
– Activities are scheduled using heuristics
(rules-of-thumb) that focus on:
1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
– The parallel method is used to apply heuristics
• An iterative process starting at the first time period
of the project and scheduling period-by-period the start
of any activities using the three priority rules.
8–14
Resource-Constrained Schedule through Period 2–3
FIGURE 8.4
8–15
Resource-Constrained Schedule through Period 2–3
FIGURE 8.4 (cont’d)
8–16
Resource-Constrained Schedule through Period 2–3
FIGURE 8.4 (cont’d)
8–17
Resource-Constrained Schedule through Period 5–6
FIGURE 8.5
8–18
Resource-Constrained Schedule through Period 5–6
FIGURE 8.5 (cont’d)
8–19
Resource-Constrained Schedule through Period 5–6
FIGURE 8.5 (cont’d)
8–20
Computer Demonstration of Resource-
Constrained Scheduling
• EMR Project
– The development of a handheld electronic medical
reference guide to be used by emergency medical
technicians and paramedics.
• Problem
– There are only eight design engineers who can be
assigned to the project due to a shortage of design
engineers and commitments to other projects.
8–21
EMR Project:
Network View
Schedule before
Resources Leveled
FIGURE 8.6
8–22
EMR Project before Resources Added
FIGURE 8.7
8–23
EMR Project—Time Constrained Resource Usage View,
January 15–23
FIGURE 8.8A
8–24
Resource Loading Chart for EMR Project, January 15–23
FIGURE 8.8B
8–25
EMR Project
Network View
Schedule
after Resources
Leveled
FIGURE 8.9
8–26
EMR Project Resources Leveled
FIGURE 8.10
8–27
The Impacts of Resource-Constrained
Scheduling
• Reduces delay but reduces flexibility.
• Increases criticality of events.
• Increases scheduling complexity.
• May make the traditional critical path
no longer meaningful.
• Can break sequence of events.
• May cause parallel activities to become
sequential and critical activities with slack
to become noncritical.
8–28
Splitting
• Splitting
– A scheduling technique for creating a better project
schedule and/or increase resource utilization.
• Involves interrupting work on an activity to employ the
resource on another activity, then returning the resource
to finish the interrupted work.
• Is feasible when startup and shutdown costs are low.
• Is considered the major reason why projects fail to meet
schedule.
8–29
Splitting Activities
FIGURE 8.11
8–30
Benefits of Scheduling Resources
• Leaves time for consideration
of reasonable alternatives:
– Cost-time tradeoffs
– Changes in priorities
• Provides information for time-phased
work package budgets to assess:
– Impact of unforeseen events
– Amount of flexibility in available resources
8–31
Multiproject Resource Schedules
• Multiproject Scheduling Problems
1. Overall project slippage
• Delay on one project create delays for other projects.
2. Inefficient resource application
• The peaks and valleys of resource demands create
scheduling problems and delays for projects.
3. Resource bottlenecks
• Shortages of critical resources required for multiple
projects cause delays and schedule extensions.
8–32
Multiproject Resource Schedules (cont’d)
• Managing Multiproject Scheduling:
– Create project offices or departments to oversee
the scheduling of resources across projects.
– Use a project priority queuing system: first come,
first served for resources.
– Centralize project management: treat all projects
as a part of a “megaproject.”
– Outsource projects to reduce the number
of projects handled internally.
Using the Resource Schedule to Develop
a Project Cost Baseline
• Why a Time-Phased Budget Baseline Is Needed
– To determine if the project is on, ahead, or behind schedule and
over or under its budgeted costs?
– To know how much work has been accomplished for the
allocated money spent—the project cost baseline (planned
value, PV)
• Creating a Time-Phased Budget
– Assign each work package to one responsible person or
department and deliverable.
– Compare planned schedule and costs using an integrative
system called earned value.
8–33
8–34
Direct Labor Budget
Rollup ($000)
FIGURE 8.12
8–35
Time-Phased Work Package Budget (Labor Cost Only)
FIGURE 8.13
8–36
Two Time-Phased Work Packages (Labor Cost Only)
FIGURE 8.14
8–37
Patient Entry Project Network
FIGURE 8.15
8–38
Patient Entry Time-Phased Work Packages Assigned
FIGURE 8.16
8–39
CEBOO Project Monthly Cash Flow Statement
FIGURE 8.17
8–40
CEBOO Project Weekly Resource Usage Schedule
FIGURE 8.18
8–41
Key Terms
Heuristic
Leveling
Planned value (PV)
Resource-constrained projects
Resource smoothing
Splitting
Time-constrained projects
Time-phased budget baseline

More Related Content

Similar to PM-Chapter8-1.pptx

Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HChapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HJinElias52
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdfAmarDeo7
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Project management
Project managementProject management
Project managementtwilight89
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocationVenu Yemul
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptxArdraSabu
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 

Similar to PM-Chapter8-1.pptx (20)

Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HChapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdf
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Project management
Project managementProject management
Project management
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Time management
Time managementTime management
Time management
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptx
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 

More from TecnicoItca

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdfTecnicoItca
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.pptTecnicoItca
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTecnicoItca
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptTecnicoItca
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptxTecnicoItca
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.pptTecnicoItca
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTecnicoItca
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.pptTecnicoItca
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.pptTecnicoItca
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.pptTecnicoItca
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
Clases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptClases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptTecnicoItca
 
Valoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxValoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxTecnicoItca
 

More from TecnicoItca (20)

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdf
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.ppt
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptx
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.ppt
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptx
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.ppt
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.ppt
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.ppt
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.ppt
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Clases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptClases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.ppt
 
Valoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxValoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptx
 
Bonos-Clase.ppt
Bonos-Clase.pptBonos-Clase.ppt
Bonos-Clase.ppt
 

Recently uploaded

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information SystemsAnge Felix NSANZIYERA
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxhublikarsn
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 

Recently uploaded (20)

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 

PM-Chapter8-1.pptx

  • 1. Scheduling Resources and Costs CHAPTER EIGHT PowerPoint Presentation by Charlie Cook Copyright © 2014 McGraw-Hill Education. All Rights Reserved.
  • 3. Overview of the Resource Scheduling Problem • Resources and Priorities – Project network times are not a schedule until resources have been assigned. • The implicit assumption is that resources will be available in the required amounts when needed. • Adding new projects requires making realistic judgments of resource availability and project durations. – Cost estimates are not a budget until they have been time-phased. 8–3
  • 5. 8–5 The Resource Problem (cont’d) • Resource Smoothing (or Leveling) – Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project. • Resource-Constrained Scheduling – The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands.
  • 6. 8–6 Types of Project Constraints • Technical or Logic Constraints – Constraints related to the networked sequence in which project activities must occur. • Physical Constraints – Activities that cannot occur in parallel or are affected by contractual or environmental conditions. • Resource Constraints – The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities • Kinds of Resource Constraints – People, materials, equipment
  • 8. 8–8 Classification of a Scheduling Problem • Classification of Problem – Using a priority matrix will help determine if the project is time or resource constrained. • Time-Constrained Project – Must be completed by an imposed date. • Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. • Resource-Constrained Project – Is one in which the level of resources available cannot be exceeded. • Resources are fixed, time is flexible: inadequate resources will delay the project.
  • 9. 8–9 Resource Allocation Methods • Limiting Assumptions – Splitting activities is not allowed—once an activity is start, it is carried to completion. – Level of resources used for an activity cannot be changed. • Risk Assumptions – Activities with the most slack pose the least risk. – Reduction of flexibility does not increase risk. – The nature of an activity (easy, complex) doesn’t increase risk.
  • 10. 8–10 Resource Allocation Methods (cont’d) • Time-Constrained Projects – Must be completed by an imposed date. – Require use of leveling techniques that focus on balancing or smoothing resource demands. – Use positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project. • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized.
  • 12. 8–12 Resource Allocation Methods (cont’d) • Resource Demand Leveling Techniques for Time-Constrained Projects – Advantages • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized. – Disadvantages • Loss of flexibility that occurs from reducing slack. • Increases in the criticality of all activities.
  • 13. 8–13 Resource Allocation Methods (cont’d) • Resource-Constrained Projects – Resources are limited in quantity or availability. – Activities are scheduled using heuristics (rules-of-thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number – The parallel method is used to apply heuristics • An iterative process starting at the first time period of the project and scheduling period-by-period the start of any activities using the three priority rules.
  • 15. 8–15 Resource-Constrained Schedule through Period 2–3 FIGURE 8.4 (cont’d)
  • 16. 8–16 Resource-Constrained Schedule through Period 2–3 FIGURE 8.4 (cont’d)
  • 18. 8–18 Resource-Constrained Schedule through Period 5–6 FIGURE 8.5 (cont’d)
  • 19. 8–19 Resource-Constrained Schedule through Period 5–6 FIGURE 8.5 (cont’d)
  • 20. 8–20 Computer Demonstration of Resource- Constrained Scheduling • EMR Project – The development of a handheld electronic medical reference guide to be used by emergency medical technicians and paramedics. • Problem – There are only eight design engineers who can be assigned to the project due to a shortage of design engineers and commitments to other projects.
  • 21. 8–21 EMR Project: Network View Schedule before Resources Leveled FIGURE 8.6
  • 22. 8–22 EMR Project before Resources Added FIGURE 8.7
  • 23. 8–23 EMR Project—Time Constrained Resource Usage View, January 15–23 FIGURE 8.8A
  • 24. 8–24 Resource Loading Chart for EMR Project, January 15–23 FIGURE 8.8B
  • 25. 8–25 EMR Project Network View Schedule after Resources Leveled FIGURE 8.9
  • 26. 8–26 EMR Project Resources Leveled FIGURE 8.10
  • 27. 8–27 The Impacts of Resource-Constrained Scheduling • Reduces delay but reduces flexibility. • Increases criticality of events. • Increases scheduling complexity. • May make the traditional critical path no longer meaningful. • Can break sequence of events. • May cause parallel activities to become sequential and critical activities with slack to become noncritical.
  • 28. 8–28 Splitting • Splitting – A scheduling technique for creating a better project schedule and/or increase resource utilization. • Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work. • Is feasible when startup and shutdown costs are low. • Is considered the major reason why projects fail to meet schedule.
  • 30. 8–30 Benefits of Scheduling Resources • Leaves time for consideration of reasonable alternatives: – Cost-time tradeoffs – Changes in priorities • Provides information for time-phased work package budgets to assess: – Impact of unforeseen events – Amount of flexibility in available resources
  • 31. 8–31 Multiproject Resource Schedules • Multiproject Scheduling Problems 1. Overall project slippage • Delay on one project create delays for other projects. 2. Inefficient resource application • The peaks and valleys of resource demands create scheduling problems and delays for projects. 3. Resource bottlenecks • Shortages of critical resources required for multiple projects cause delays and schedule extensions.
  • 32. 8–32 Multiproject Resource Schedules (cont’d) • Managing Multiproject Scheduling: – Create project offices or departments to oversee the scheduling of resources across projects. – Use a project priority queuing system: first come, first served for resources. – Centralize project management: treat all projects as a part of a “megaproject.” – Outsource projects to reduce the number of projects handled internally.
  • 33. Using the Resource Schedule to Develop a Project Cost Baseline • Why a Time-Phased Budget Baseline Is Needed – To determine if the project is on, ahead, or behind schedule and over or under its budgeted costs? – To know how much work has been accomplished for the allocated money spent—the project cost baseline (planned value, PV) • Creating a Time-Phased Budget – Assign each work package to one responsible person or department and deliverable. – Compare planned schedule and costs using an integrative system called earned value. 8–33
  • 34. 8–34 Direct Labor Budget Rollup ($000) FIGURE 8.12
  • 35. 8–35 Time-Phased Work Package Budget (Labor Cost Only) FIGURE 8.13
  • 36. 8–36 Two Time-Phased Work Packages (Labor Cost Only) FIGURE 8.14
  • 37. 8–37 Patient Entry Project Network FIGURE 8.15
  • 38. 8–38 Patient Entry Time-Phased Work Packages Assigned FIGURE 8.16
  • 39. 8–39 CEBOO Project Monthly Cash Flow Statement FIGURE 8.17
  • 40. 8–40 CEBOO Project Weekly Resource Usage Schedule FIGURE 8.18
  • 41. 8–41 Key Terms Heuristic Leveling Planned value (PV) Resource-constrained projects Resource smoothing Splitting Time-constrained projects Time-phased budget baseline