SlideShare a Scribd company logo
1 of 37
Construction
Technology
Theory question
A client is preparing to construct a 3-storey shop-house with
2-storey basement. The shop-house is located in town, the
subsoil condition is cohesive and the water table is far below
the surface. However, there are some factors that need to be
considered before constructing the building which involves
cost.
A) List FIVE (5) choices that may influence the cost involved.
B) Discuss the characteristics of all the Five(5) choices listed above.
2
3
4
5 FACTORS THAT
INFLUENCE
THE COST
WATER
TABLE
MATERIA
L
STORAGE
5
SUBSOIL
Surrounding
Factors
Machineries &
Equipment
Surrounding Factor
6
1.
Accessibility to
Site
Security
Accessibility to
Resources
Accessibility to
Site - Town Site
7
The pathway for the construction
machineries and the materials to be
transported from off the site to the site.
â—Ź Minimum Space for maneuverability
â—Ź Will be sharing main roads with general public
How it will cost ?
8
â—Ź Delivery use might be regulated to low peak period only : 10am-3pm to avoid the
happening of unnecessary jam in town area.
â—Ź Delay the progress of the on-going project.
- Contractor remains on site longer than allowed for & incurred additional cost.
- Management and supervisory staff salaries + associated cost
- Overhead cost for machineries & equipment
- Storage cost & double handling(increase risk of damages & theft)
- Extension of construction insurance
Accessibility to
Resources-Town
Site
9
â—Ź Resources in terms of the labours, machineries and
equipment and construction materials that are needed to aid
in the progress of the on-going construction project.
How it will cost?
10
â—Ź Located in main population :Easy accessibility to materials and labor resources.
â—Ź Cost lesser : Reduce travelling fees to obtain supplier of labour & material resource.
: Small project minimises resources use.
â—Ź Cost more : In terms of preparation of materials. Eg: mixing of concrete could not be
done on site--->order premixed concrete in a premix truck.
Security
11
The effort taken to ensure the
surrounding of the on-going site is not
interrupted as well as to ensure the
safety of the public.
How it will cost?
12
â—Ź Probably surrounded with facilities such as
schools, shops, police/fire station and etc.
â—Ź Needed Temporary Hoarding :
- prevent intruders/trespassers
-ensuring safety of general public
â—Ź Cost is incurred for installation fees &
materials fees ( aluminium hoarding).
MACHINERY
Machinery are used to execute construction tasks, most
frequently ones involving earthwork operations
2.
MACHINERIES
MACHINERY USES
Task performed include: excavating, spreading &
flattening of soil
EQUIPMENT-SCAFFOLDING
➢ A temporary structure from which
persons can gain access to place of
work
➢ 3-storey shop-house construction
➢ Raises workers and equipments to
higher level.
HOW IT WILL COST?
➢ Rental fees - depending on size and capacity
➢ Time - to set up the scaffolding
SERVICES
Any underground services running?
Location:town, probably yes.
Excavation & underground Services includes:
â—Ź Electricity cables
â—Ź Water pipes
â—Ź Pipes
18
SERVICES
19
How does it affect construction?
Damages on underground
cables might cause injuries
due to electric shock,
explosion, and flames.
20
How it costs money?
â–Ş Requires suitable devices
➢ Locating devices to trace cables
➢ Renting of equipments
21
How it costs money?
â–Ş Requires skilled labour
➢ Someone who is experienced in underground cable detection techniques
â–Ş Takes time
➢ Might need hand digging with insulated tools
22
How it costs money?
â–Ş Planning the work
➢ Permit to be obtained for work
➢ Checking with nearby organisations and get plan for location of the cables.
➢ Contact with the electricity companies if there is a need for cutting off supplies.
➢ 5 days notice to customers whose supply is to be disconnected.
23
MATERIAL
STORAGE
Non-transitory,
semi-permanent placement
of materials.
3.
Keep materials protected from
weather,theft, and deterioration.
TYPES OF MATERIAL TO BE STORED
METHOD OF STORING
Materials Storing Methods
Bricks â—Ź Stack on dry firm ground
â—Ź 50 bricks long, 10 bricks high
â—Ź Bricks of each truck load in 1 stack
Steel Bars â—Ź Store bars of different classes, sizes and lengths separately
â—Ź Coat steel reinforcement with cement wash
â—Ź Stack it above ground level 150mm if stored for long period.
Cement â—Ź Store in dry, leak proof and as moisture proof
â—Ź Stack the cement bags off the floor on wooden planks, 150-200mm
above the floor
How it costs money?
â–Ş Materials stored off site
➢ Need to consider secure facility
➢ Get insurance coverage in case of theft or damage
➢ Stored close to the construction site
â–Ş Labors
➢ Handling and managing the material.
â–Ş Utilities
➢ Heat/temperature control
27
How it costs money?
â–Ş Facilities
➢ Renting of cabin or container.
â–Ş Storage equipments
➢ Racks and shelves
➢ Storage at height- guard rails needed
â–Ş Security
➢ Fire protection system
➢ Guard service
28
MATERIAL STORAGE
29
WATER TABLE4.
Perched Water Table Main Water Table
Perched Water Table Main Water Table
- Defined as a reservoir of water on the
ground maintained temporarily or
permanently above the standing water
level on the ground.
- water may stay on the ground at high
level, before the water draining down
to true water table.
- the standing water level in the ground
- All the pores of the ground (soil) below
that position is saturated (zone of
saturation)
- Ground above that position is
unsaturated ( zone of aeration )
- Water pressure = atmospheric pressure.
How it costs money?
Higher water table
- More water pumping off from the site.
- More water proofing work.
- Higher cost.
Lower Water Table
- Less water pumping off from the site.
- Less water proofing work.
- Lower cost.
SUBSOIL
5. HARD ROCK CLAY
SOIL GRAVEL
HARD ROCK GRAVEL CLAY SAND
- Good for
foundation.
- High excavation
cost.
- Most
suitable
subsoil.
- Strong and
easily
drained.
- Mostly use
- Good bearing
soil.
- But does not
drain water
well.
- Pores between
particles are wide.
- Loose
- Subject to
movement.
How it costs money?
Cohesive
- Excavation take time.
- Higher cost.
- Fill in gravel rocks for water proofing at basement.
Thanks!
37

More Related Content

What's hot

Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & EquipmentsGAURAV. H .TANDON
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication constructionDivya Vishnoi
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated StructuresBoopathi Raja
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and RehabilitationGAURAV. H .TANDON
 
Sulphur infiltrated concrete
Sulphur infiltrated concreteSulphur infiltrated concrete
Sulphur infiltrated concretesuraj bhanushali
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTShankar Ramasamy
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptBALAMURUGANR53
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsAnkit Patel
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
Types of formwork
Types of formworkTypes of formwork
Types of formworkAglaia Connect
 
Formwork
FormworkFormwork
Formworknatesh0142
 
Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....SJMIT,now NMAMIT NITTE
 
Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Srishti Wakhloo
 
Distress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesDistress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesZaid Ansari
 
Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)arun naga sai
 

What's hot (20)

Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Sulphur infiltrated concrete
Sulphur infiltrated concreteSulphur infiltrated concrete
Sulphur infiltrated concrete
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairs
 
Maintenance of concrete structures
Maintenance of concrete structuresMaintenance of concrete structures
Maintenance of concrete structures
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Formwork
FormworkFormwork
Formwork
 
Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....
 
Mix design-ppt
Mix design-pptMix design-ppt
Mix design-ppt
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment Management
 
Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs
 
Distress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesDistress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniques
 
Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)
 

Similar to 5 Factors Influencing Construction Cost for a 3-Storey Shop-House

Energy efficient construction and training practices - 2 Weather shielding
Energy efficient construction and training practices - 2 Weather shieldingEnergy efficient construction and training practices - 2 Weather shielding
Energy efficient construction and training practices - 2 Weather shieldingMotiva
 
Report on HIGH RISE
Report on HIGH RISE Report on HIGH RISE
Report on HIGH RISE Isratul Shaon
 
Ct2 presentation
Ct2 presentationCt2 presentation
Ct2 presentationqayyum23
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docxbrian157854
 
Shotcrete concrete
Shotcrete concreteShotcrete concrete
Shotcrete concretesrinivas cnu
 
SHOTCRETE TECHNOLOGY
SHOTCRETE TECHNOLOGYSHOTCRETE TECHNOLOGY
SHOTCRETE TECHNOLOGYseminarppts
 
Introduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building StructuresIntroduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building Structureshegdenisarga23
 
3 4 chemplantdesign-general plant consideration
3 4 chemplantdesign-general plant consideration3 4 chemplantdesign-general plant consideration
3 4 chemplantdesign-general plant considerationayimsevenfold
 
1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdf1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdfahsansaeed78
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouringBharatha Rathnayke
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concreteBala murali
 
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nick Vukovich
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesAr Jitendra
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingIRJET Journal
 
World Water Day 2014
World Water Day 2014World Water Day 2014
World Water Day 2014Tandarayen Kevin
 
Presentation FFFT
Presentation FFFTPresentation FFFT
Presentation FFFTGunar Krause
 

Similar to 5 Factors Influencing Construction Cost for a 3-Storey Shop-House (20)

Q1 presentation
Q1 presentationQ1 presentation
Q1 presentation
 
Energy efficient construction and training practices - 2 Weather shielding
Energy efficient construction and training practices - 2 Weather shieldingEnergy efficient construction and training practices - 2 Weather shielding
Energy efficient construction and training practices - 2 Weather shielding
 
Report on HIGH RISE
Report on HIGH RISE Report on HIGH RISE
Report on HIGH RISE
 
Ct2 presentation
Ct2 presentationCt2 presentation
Ct2 presentation
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docx
 
Shotcrete concrete
Shotcrete concreteShotcrete concrete
Shotcrete concrete
 
SHOTCRETE TECHNOLOGY
SHOTCRETE TECHNOLOGYSHOTCRETE TECHNOLOGY
SHOTCRETE TECHNOLOGY
 
Introduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building StructuresIntroduction to Underground Structures _ Building Structures
Introduction to Underground Structures _ Building Structures
 
Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
3 4 chemplantdesign-general plant consideration
3 4 chemplantdesign-general plant consideration3 4 chemplantdesign-general plant consideration
3 4 chemplantdesign-general plant consideration
 
1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdf1661351022Unit 3 1054-V1 Site Organisation.pdf
1661351022Unit 3 1054-V1 Site Organisation.pdf
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
NDL FUEL STATION OPERATION
NDL FUEL STATION OPERATIONNDL FUEL STATION OPERATION
NDL FUEL STATION OPERATION
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment Building
 
World Water Day 2014
World Water Day 2014World Water Day 2014
World Water Day 2014
 
Presentation FFFT
Presentation FFFTPresentation FFFT
Presentation FFFT
 

More from Sze Ting Kuek

Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete pilesSze Ting Kuek
 
Assignment for niro visit mar 2018
Assignment for niro visit mar 2018Assignment for niro visit mar 2018
Assignment for niro visit mar 2018Sze Ting Kuek
 
Site surveying assignment
Site surveying assignmentSite surveying assignment
Site surveying assignmentSze Ting Kuek
 
Sustainable wastewater treatment report
Sustainable wastewater treatment reportSustainable wastewater treatment report
Sustainable wastewater treatment reportSze Ting Kuek
 
Building Material - wastewater treatment
Building Material - wastewater treatmentBuilding Material - wastewater treatment
Building Material - wastewater treatmentSze Ting Kuek
 
Site report assignment
Site report assignmentSite report assignment
Site report assignmentSze Ting Kuek
 
Law presentation
Law presentationLaw presentation
Law presentationSze Ting Kuek
 
PASAR SENI BOOKLET
PASAR SENI BOOKLETPASAR SENI BOOKLET
PASAR SENI BOOKLETSze Ting Kuek
 
Final project - video
Final project - videoFinal project - video
Final project - videoSze Ting Kuek
 
Scrapebook Taman Negara
Scrapebook Taman NegaraScrapebook Taman Negara
Scrapebook Taman NegaraSze Ting Kuek
 
MINI JOURNAL 1
MINI JOURNAL 1MINI JOURNAL 1
MINI JOURNAL 1Sze Ting Kuek
 
Enbe final project brief
Enbe final project briefEnbe final project brief
Enbe final project briefSze Ting Kuek
 
Enbe.project one july 2016 (1)
Enbe.project one july 2016 (1)Enbe.project one july 2016 (1)
Enbe.project one july 2016 (1)Sze Ting Kuek
 
Cts assignment 3 brief
Cts assignment 3 briefCts assignment 3 brief
Cts assignment 3 briefSze Ting Kuek
 
Assignment 01 cts august2016
Assignment 01 cts august2016Assignment 01 cts august2016
Assignment 01 cts august2016Sze Ting Kuek
 

More from Sze Ting Kuek (20)

Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete piles
 
Assignment for niro visit mar 2018
Assignment for niro visit mar 2018Assignment for niro visit mar 2018
Assignment for niro visit mar 2018
 
Site surveying assignment
Site surveying assignmentSite surveying assignment
Site surveying assignment
 
Sustainable wastewater treatment report
Sustainable wastewater treatment reportSustainable wastewater treatment report
Sustainable wastewater treatment report
 
Building Material - wastewater treatment
Building Material - wastewater treatmentBuilding Material - wastewater treatment
Building Material - wastewater treatment
 
Site report assignment
Site report assignmentSite report assignment
Site report assignment
 
Law presentation
Law presentationLaw presentation
Law presentation
 
MJ 2
MJ 2MJ 2
MJ 2
 
PASAR SENI BOOKLET
PASAR SENI BOOKLETPASAR SENI BOOKLET
PASAR SENI BOOKLET
 
idj 2
idj 2 idj 2
idj 2
 
idj 2
idj 2 idj 2
idj 2
 
Final project - video
Final project - videoFinal project - video
Final project - video
 
Scrapebook Taman Negara
Scrapebook Taman NegaraScrapebook Taman Negara
Scrapebook Taman Negara
 
MINI JOURNAL 1
MINI JOURNAL 1MINI JOURNAL 1
MINI JOURNAL 1
 
IDJ 1
IDJ 1IDJ 1
IDJ 1
 
Enbe final project brief
Enbe final project briefEnbe final project brief
Enbe final project brief
 
Enbe.project one july 2016 (1)
Enbe.project one july 2016 (1)Enbe.project one july 2016 (1)
Enbe.project one july 2016 (1)
 
Cts assignment 3 brief
Cts assignment 3 briefCts assignment 3 brief
Cts assignment 3 brief
 
Cts Ass 2
Cts Ass 2Cts Ass 2
Cts Ass 2
 
Assignment 01 cts august2016
Assignment 01 cts august2016Assignment 01 cts august2016
Assignment 01 cts august2016
 

Recently uploaded

AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)Dr. Mazin Mohamed alkathiri
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 

Recently uploaded (20)

AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 

5 Factors Influencing Construction Cost for a 3-Storey Shop-House

  • 2. Theory question A client is preparing to construct a 3-storey shop-house with 2-storey basement. The shop-house is located in town, the subsoil condition is cohesive and the water table is far below the surface. However, there are some factors that need to be considered before constructing the building which involves cost. A) List FIVE (5) choices that may influence the cost involved. B) Discuss the characteristics of all the Five(5) choices listed above. 2
  • 3. 3
  • 4. 4
  • 5. 5 FACTORS THAT INFLUENCE THE COST WATER TABLE MATERIA L STORAGE 5 SUBSOIL Surrounding Factors Machineries & Equipment
  • 7. Accessibility to Site - Town Site 7 The pathway for the construction machineries and the materials to be transported from off the site to the site. â—Ź Minimum Space for maneuverability â—Ź Will be sharing main roads with general public
  • 8. How it will cost ? 8 â—Ź Delivery use might be regulated to low peak period only : 10am-3pm to avoid the happening of unnecessary jam in town area. â—Ź Delay the progress of the on-going project. - Contractor remains on site longer than allowed for & incurred additional cost. - Management and supervisory staff salaries + associated cost - Overhead cost for machineries & equipment - Storage cost & double handling(increase risk of damages & theft) - Extension of construction insurance
  • 9. Accessibility to Resources-Town Site 9 â—Ź Resources in terms of the labours, machineries and equipment and construction materials that are needed to aid in the progress of the on-going construction project.
  • 10. How it will cost? 10 â—Ź Located in main population :Easy accessibility to materials and labor resources. â—Ź Cost lesser : Reduce travelling fees to obtain supplier of labour & material resource. : Small project minimises resources use. â—Ź Cost more : In terms of preparation of materials. Eg: mixing of concrete could not be done on site--->order premixed concrete in a premix truck.
  • 11. Security 11 The effort taken to ensure the surrounding of the on-going site is not interrupted as well as to ensure the safety of the public.
  • 12. How it will cost? 12 â—Ź Probably surrounded with facilities such as schools, shops, police/fire station and etc. â—Ź Needed Temporary Hoarding : - prevent intruders/trespassers -ensuring safety of general public â—Ź Cost is incurred for installation fees & materials fees ( aluminium hoarding).
  • 13. MACHINERY Machinery are used to execute construction tasks, most frequently ones involving earthwork operations 2.
  • 15. MACHINERY USES Task performed include: excavating, spreading & flattening of soil
  • 16. EQUIPMENT-SCAFFOLDING ➢ A temporary structure from which persons can gain access to place of work ➢ 3-storey shop-house construction ➢ Raises workers and equipments to higher level.
  • 17. HOW IT WILL COST? ➢ Rental fees - depending on size and capacity ➢ Time - to set up the scaffolding
  • 18. SERVICES Any underground services running? Location:town, probably yes. Excavation & underground Services includes: â—Ź Electricity cables â—Ź Water pipes â—Ź Pipes 18
  • 20. How does it affect construction? Damages on underground cables might cause injuries due to electric shock, explosion, and flames. 20
  • 21. How it costs money? â–Ş Requires suitable devices ➢ Locating devices to trace cables ➢ Renting of equipments 21
  • 22. How it costs money? â–Ş Requires skilled labour ➢ Someone who is experienced in underground cable detection techniques â–Ş Takes time ➢ Might need hand digging with insulated tools 22
  • 23. How it costs money? â–Ş Planning the work ➢ Permit to be obtained for work ➢ Checking with nearby organisations and get plan for location of the cables. ➢ Contact with the electricity companies if there is a need for cutting off supplies. ➢ 5 days notice to customers whose supply is to be disconnected. 23
  • 24. MATERIAL STORAGE Non-transitory, semi-permanent placement of materials. 3. Keep materials protected from weather,theft, and deterioration.
  • 25. TYPES OF MATERIAL TO BE STORED
  • 26. METHOD OF STORING Materials Storing Methods Bricks â—Ź Stack on dry firm ground â—Ź 50 bricks long, 10 bricks high â—Ź Bricks of each truck load in 1 stack Steel Bars â—Ź Store bars of different classes, sizes and lengths separately â—Ź Coat steel reinforcement with cement wash â—Ź Stack it above ground level 150mm if stored for long period. Cement â—Ź Store in dry, leak proof and as moisture proof â—Ź Stack the cement bags off the floor on wooden planks, 150-200mm above the floor
  • 27. How it costs money? â–Ş Materials stored off site ➢ Need to consider secure facility ➢ Get insurance coverage in case of theft or damage ➢ Stored close to the construction site â–Ş Labors ➢ Handling and managing the material. â–Ş Utilities ➢ Heat/temperature control 27
  • 28. How it costs money? â–Ş Facilities ➢ Renting of cabin or container. â–Ş Storage equipments ➢ Racks and shelves ➢ Storage at height- guard rails needed â–Ş Security ➢ Fire protection system ➢ Guard service 28
  • 30. WATER TABLE4. Perched Water Table Main Water Table
  • 31. Perched Water Table Main Water Table - Defined as a reservoir of water on the ground maintained temporarily or permanently above the standing water level on the ground. - water may stay on the ground at high level, before the water draining down to true water table. - the standing water level in the ground - All the pores of the ground (soil) below that position is saturated (zone of saturation) - Ground above that position is unsaturated ( zone of aeration ) - Water pressure = atmospheric pressure.
  • 32.
  • 33. How it costs money? Higher water table - More water pumping off from the site. - More water proofing work. - Higher cost. Lower Water Table - Less water pumping off from the site. - Less water proofing work. - Lower cost.
  • 34. SUBSOIL 5. HARD ROCK CLAY SOIL GRAVEL
  • 35. HARD ROCK GRAVEL CLAY SAND - Good for foundation. - High excavation cost. - Most suitable subsoil. - Strong and easily drained. - Mostly use - Good bearing soil. - But does not drain water well. - Pores between particles are wide. - Loose - Subject to movement.
  • 36. How it costs money? Cohesive - Excavation take time. - Higher cost. - Fill in gravel rocks for water proofing at basement.