SlideShare a Scribd company logo
1 of 8
Download to read offline
CaseStudy
PaperMill-SouthCarolina
ROI Case Study 1
Paper Mill Saves Budget Dollars
with IR Window Program
By Martin Robinson, CMRP Level III Thermographer President, IRISS Inc.
18-1034-0001 Rev. A
Overview:
A paper mill in South Carolina had a very successful infrared inspection program that management
wanted to expand. However, the requirements of NFPA 70E were causing them to re-think their stra-
tegy since inspections of energized equipment was becoming more restrictive, more time consuming
and more costly. Furthermore, 8% of the mill’s applications had never been surveyed due to switched
interlocks (which automatically de-energize the equipment upon opening, thereby preventing access to
energized components), or due to incident energy calculations in excess of 100 cal/cm2 on certain equip-
ment (which exceeds personal protective equipment [PPE] ratings, and would place personnel in extreme
danger and open the company to OSHA fines).
CaseStudy
PaperMill-SouthCarolina
In search of alternative methods of conducting safer, standard compliant inspections, the corporate
Reliability Engineer investigated how infrared inspection windows (commonly referred to as IR
windows, viewports or sightglasses) might be utilized. It was determined that:
•	 Use of Infrared Windows for routine inspections of healthy equipment did not require the 	
	 elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating 	
	 conditions, enclosed energized equipment that has been properly installed and maintained 	
	 is not likely to pose an arc flash hazard.” In NFPA terms, an IR window maintains 		
	 an “enclosed” state for the switchgear, MCC, Transformer, etc., and maintains energized 	
	 components and circuit parts in a “guarded” condition. Therefore, the hazard/risk category 	
	 would be equal to that of reading a panel meter, using a visual inspection pane for lockout/	
	 tagout confirmations, or walking past enclosed, and energized equipment.
•	 Use of IR windows or “sightglasses” would eliminate the need for a supporting cast of 	
	 electricians to remove and reinstall panel covers. Those critical personnel would then be 	
	 available to perform other tasks which were often being outsourced.
•	 Use of infrared windows would provide an efficient method to perform inspections. This 	
	 would make more frequent inspections feasible for critical or suspect applications to ensure 	
	 plant uptime.
•	 Use of IR windows would provide non-intrusive access to electrical applications; therefore, 	
	 surveys could be conducted without elevating risk to plant assets and processes, meaning 	
	 that inspections could be conducted during peak hours for the best diagnostic data.
•	 Use of IR windows and closed panel inspection would eliminate high-risk tasks during 	
	 inspections and thereby increase safety for thermographers.
	 The focus of the mill’s initiative was to facilitate inspection of the primary switchgear in their 	
	 electrical distribution system which feeds one paper machine and several smaller 		
	 operations within the plant. An impending ten-day shutdown increased the sense of 	
	 urgency since all windows could be fitted for one machine during that period.
	 IRISS, Inc. was commissioned by the paper mill to conduct a pre-site inspection to ascertain 	
	 the optimal position and quantity of windows which would give thermographers thorough
	 visibility of desired targets. The conclusions from the initial inspection are noted in Table 1.
CaseStudy
PaperMill-SouthCarolina
Table 1
Application				 Quantity
13.8 kV Primary Switch			 15
Secondary Switchgear			 22
Transformers (13.8 kV )			 27
MCC’s					 2
Miscellaneous Switchgear		 2
Generators				 2
Total Assemblies				 70
Inspection Compartments		 147
IR Windows				 197
The customer ordered 200 units of assorted VPFR-75 (3 inch diameter) and VPFR-100 (4 inch diameter)
Infrared Inspection Windows to complete the installation. 197 windows were later installed.
Investment
Table 2
IR Window Supply and Installation
Investment
Infrared Windows (197 units assorted	 $42,050
3 & 4 inch diameter)	
Install Costs for 197 IR Windows		 $18,910
Total					 $60,960
197 VPFR infrared inspection windows totaled $42,050.00. IRISS was also retained to
supply an installation team to perform the installation of the IR windows.
Installation costs sited in Table 2 were calculated using the following assumptions:
•	 Two-man installation team at $625.00 each per day (total cost $1,300 per day) x 10 Days = 		
	$13,000.00
•	 $30.00 per window installation charge x 197 Windows = $5,910.00
CaseStudy
PaperMill-SouthCarolina
The Installation
Installation of the infrared inspection panes was conducted during three nights and three days of the
ten-day shutdown. Some installations were completed on live gear using additional safety measures;
however, the vast majority was conducted on de-energized equipment in what NFPA terms an “electrically
safe work condition.”
Although our plan allowed for twelve hour shifts, installers were quickly and safely moving at a rate
of approximately six window installations per hour, and were finishing the plant on the night shifts
within six hours. Installations during normal business hours allowed much more flexibility; therefore
all “live works” were completed during these periods. When the clients’ electricians assisted with the
installations, the installation rates were also faster than originally planned (7 to 8 windows per hour). All
window installations were completed well within the allotted timelines.
Inspection Cost Analysis
Prior to the installation of the IR windows, all infrared inspections were completed on open, energized
gear. Therefore, PPE, live works procedures, risk assessments, permits, etc. were required for all
inspections, and as noted earlier, several applications had never been surveyed due to safety restrictions.
The paper mill had previously invested in its own infrared camera and an on-staff thermographer. The
thermographer was trained and “qualified” to assist in opening panels on energized gear. Therefore,
some efficiencies were already in place when compared to a typical crew of a single thermographer and
two electricians. Consequently, the man-hour calculations for the “traditional inspection” are actually
conservative.
Table 3 details the man-hour costs for infrared surveys using in-house staff without infrared windows or
viewports. The following assumptions are made:
CaseStudy
PaperMill-SouthCarolina
•	 Total man-hours per inspection of “inspectable” equipment: 331 hours (23 days)
•	 Staff electrician internal charge-out rate $125.00 per hour
•	 Staff thermographer assists with panel removal, etc…(two-man task)
•	 PPE suit-ups twice per day, per man (30 minutes per man per suit-up)
•	 One man-hour per compartment panel for safe removal, etc. (x two for two-man team)
•	 147 individual panels to inspect (per Table 1)
After the infrared windows were installed and there was no equipment to remove panels or wear
increased levels of PPE, the task became a one-man job. The increased efficiency and economies of
motion and man-power which infrared windows provided significantly decreased the time required to
complete a survey to just two, eight-hour days for a total of
just 16 man-hours. The costs associated with an infrared survey using the IR windows are detailed in
Table 4.
Compared to the costs of traditional inspections (Table 3), the paper mill now saves $39,375 per inspection
cycle because of the efficiencies which they gain through the use of infrared windows.
ROI
Table 5 combines the data from the previous tables to illustrate the ROI for the paper mill based on the
initial investment of the IR windows, the investment in installation and the costs to perform surveys using
the windows, compared with the mill’s traditional costs of using their in-house team while not using any
windows.
Using infrared windows is shown in this example to pay dividends as early as mid-way into the second
inspection cycle, yielding almost
$18,000 in savings, which in turn can be put back into the budget by the end of the second cycle. In just
five inspection cycles the mill shows a savings of over $135,000.
Moreover, because inspections can be completed with greater ease and without increased risk to plant,
personnel and processes, the frequency of inspection cycles has been increased to quarterly, reflecting
best-practices recommendations which were previously not feasible and thought to be unattainable. The
new inspection cycle brings ROI to the plant in just one quarter, while reducing the risk of catastrophic
failure among the plant’s critical power distribution systems, which will in turn minimize production
losses due to equipment failure.
Future Installations
Additional window installations have been planned and scheduled to occur during the facility’s next
shutdown. Because the customer’s in-house electricians were trained to install infrared windows, the
installation costs for future installations will be a fraction of the cost for the original installation, saving
even more money and accelerating the ROI for additional windows.
CaseStudy
PaperMill-SouthCarolina
IR Window Supply and Installation Investment
Infrared Windows (197 units assorted 3 & 4 inch diameter)	 $42,050
Install Costs for 197 IR Windows				 $18,910
Total							 $60,960
IR Window Supply and Installation Investment
Infrared Windows (197 units assorted 3 & 4 inch diameter)	 $42,050
Install Costs for 197 IR Windows					 $18,910
Total								$60,960
Table 3
Total Cost of Traditional Inspection with In- House Team
Traditional Inspection Time		 294		 $36,750
(Hrs. x 2 per team)
PPE Suit-up Time			 37		 $4,625
(0.5 hr. x 2 per day x 2 men)
Total								 $41,375
Table 4
Total Cost of Inspection Using IR Windows
Inspection Time					 16		 $2,000
PPE Suit-up Time				 0		 $0.00
Total								 $2,000
CaseStudy
PaperMill-SouthCarolina
Table 5
ROI		 Windows	 Traditional	 ROI
197 Infrared Windows			 $42,050		 --	
Installation of Windows			 $18,910		 --	
Cost for 1st Inspection Cycle		 $ 2,000		 $41,375	
Total for 1st Cycle			 $62,960		 $41,375	 <$ 21,585>
Cost for 2nd Inspection Cycle		 $ 2,000		 $41,375	
Total for 2 Cycles			 $64,960		 $82,750	 $17,790
Cost for 3rd Inspection Cycle		 $2,000		 $41,375	
Total for 3 Cycles			 $66,960		 $124,125	 $57,165
Cost for 4th Inspection Cycle		 $2,000		 $41,375	
Total for 4 Cycles			 $68,960		 $165,500	 $96,540
Cost for 5th Inspection Cycle		 $2,000		 $41,375	
Total for 5 Cycles			 $70,960		 $206,875	 $135,915
Conclusion
This mill realized a return on investment very quickly while benefitting from the other intangibles of
infrared windows. Namely:
•	 The ability to inspect the previously un-inspectable equipment
•	 The ability to inspect critical applications more frequently
•	 The ability to more aggressively monitor any applications which are suspected to be running 	
	 to failure
•	 Increase in safety for personnel
•	 Decrease in risk to plant assets and operations due to the non-invasive nature of inspection – 	
	 safeguarding profitability
•	 Freeing up critical personnel who can be utilized for other valuable jobs in the plant rather 		
	 than removing and reinstalling panels
A portion of the financial savings were used to continue to build and strengthen the PdM program
through the purchase of a second IR camera for the maintenance electricians, further underscoring the
mill’s commitment to practical use of technology to ensure uptime while enhancing the safety of its
workers.
Infrared windows provide a cost-effective and safer alternative to traditional inspections. To learn more,
visit http://www.iriss.com/where you will find more case studies and white papers.
CaseStudy
PaperMill-SouthCarolina
To learn more about infrared windows, Electrical Preventive
Maintenance, NFPA standards or electrical thermography
please visit www.iriss.com.
“10 Things You Need to Know About Infrared Windows”
contains more information on the benefits of IR windows. To
get your free digital copy, Click Here.
Interested in IRISS IR Window Solutions? Click Here
“10 Things You Need to Know About Infrared Windows”

More Related Content

What's hot

Quest RDVI Brochure 2015
Quest RDVI Brochure 2015Quest RDVI Brochure 2015
Quest RDVI Brochure 2015
Eddie Wilson
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
Mark Platten
 
EPM In-Line Verification 24-04-2014
EPM In-Line Verification 24-04-2014EPM In-Line Verification 24-04-2014
EPM In-Line Verification 24-04-2014
Bert Roos
 

What's hot (20)

Productivity Studies of Ultra High Density (UHD) Stitching Process
Productivity Studies of Ultra High Density (UHD) Stitching ProcessProductivity Studies of Ultra High Density (UHD) Stitching Process
Productivity Studies of Ultra High Density (UHD) Stitching Process
 
Quest RDVI Brochure 2015
Quest RDVI Brochure 2015Quest RDVI Brochure 2015
Quest RDVI Brochure 2015
 
Some critical facets in air pollution
Some critical facets in air pollutionSome critical facets in air pollution
Some critical facets in air pollution
 
Types of Maintenance Inspections and its importance for the organization
Types of Maintenance Inspections and its importance for the organizationTypes of Maintenance Inspections and its importance for the organization
Types of Maintenance Inspections and its importance for the organization
 
IIOT - Analyse des données et intelligence artificielle pour l'operation opti...
IIOT - Analyse des données et intelligence artificielle pour l'operation opti...IIOT - Analyse des données et intelligence artificielle pour l'operation opti...
IIOT - Analyse des données et intelligence artificielle pour l'operation opti...
 
MET 105 Module 1
MET 105 Module 1MET 105 Module 1
MET 105 Module 1
 
SIL in de praktjk (functional Safety)
SIL in de praktjk (functional Safety)SIL in de praktjk (functional Safety)
SIL in de praktjk (functional Safety)
 
IT Computer Room Health Check
IT Computer Room Health CheckIT Computer Room Health Check
IT Computer Room Health Check
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editors
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
Reliability Centered Maintenance Case Study
 Reliability Centered Maintenance Case Study Reliability Centered Maintenance Case Study
Reliability Centered Maintenance Case Study
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements
 
Laboratory Automation Systems- Scinomix
Laboratory Automation Systems- Scinomix Laboratory Automation Systems- Scinomix
Laboratory Automation Systems- Scinomix
 
EPM In-Line Verification 24-04-2014
EPM In-Line Verification 24-04-2014EPM In-Line Verification 24-04-2014
EPM In-Line Verification 24-04-2014
 
Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control manager
 
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
 
Field Environmental Instruments Headquarters
Field Environmental Instruments HeadquartersField Environmental Instruments Headquarters
Field Environmental Instruments Headquarters
 
Condition based maintenance
Condition based maintenanceCondition based maintenance
Condition based maintenance
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurements
 
LOTO system integration with Permit to Work Software
LOTO system integration with Permit to Work SoftwareLOTO system integration with Permit to Work Software
LOTO system integration with Permit to Work Software
 

Viewers also liked

Resumee - Murali Krishna
Resumee  - Murali KrishnaResumee  - Murali Krishna
Resumee - Murali Krishna
murali krishna
 
Microsoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスド
Microsoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスドMicrosoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスド
Microsoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスド
Kazumi Hirose
 
Health Affairs-2013-ChenMed 1078-82
Health Affairs-2013-ChenMed 1078-82Health Affairs-2013-ChenMed 1078-82
Health Affairs-2013-ChenMed 1078-82
Jeffrey Kang
 
803 - 5 summer 2013 a
803 - 5 summer 2013 a803 - 5 summer 2013 a
803 - 5 summer 2013 a
bagrutonline
 
803 - 6 summer 2013 a
803 - 6 summer 2013 a803 - 6 summer 2013 a
803 - 6 summer 2013 a
bagrutonline
 
Presentation final
Presentation finalPresentation final
Presentation final
dream india
 
補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)
補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)
補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)
schoowebcampus
 

Viewers also liked (15)

Resumee - Murali Krishna
Resumee  - Murali KrishnaResumee  - Murali Krishna
Resumee - Murali Krishna
 
Microsoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスド
Microsoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスドMicrosoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスド
Microsoft azure上にwebサイトやアプリケーションを構築する方法 アドバンスド
 
Ingress
IngressIngress
Ingress
 
Health Affairs-2013-ChenMed 1078-82
Health Affairs-2013-ChenMed 1078-82Health Affairs-2013-ChenMed 1078-82
Health Affairs-2013-ChenMed 1078-82
 
ระเบียบวาระการประชุม ก.ท.จ.อุตรดิตถ์ ครั้งที่ 8/2558
ระเบียบวาระการประชุม ก.ท.จ.อุตรดิตถ์ ครั้งที่ 8/2558ระเบียบวาระการประชุม ก.ท.จ.อุตรดิตถ์ ครั้งที่ 8/2558
ระเบียบวาระการประชุม ก.ท.จ.อุตรดิตถ์ ครั้งที่ 8/2558
 
01 2.タイムライン
01 2.タイムライン01 2.タイムライン
01 2.タイムライン
 
Gli enti geometrici
Gli enti geometriciGli enti geometrici
Gli enti geometrici
 
Mafalda 2
Mafalda 2Mafalda 2
Mafalda 2
 
803 - 5 summer 2013 a
803 - 5 summer 2013 a803 - 5 summer 2013 a
803 - 5 summer 2013 a
 
803 - 6 summer 2013 a
803 - 6 summer 2013 a803 - 6 summer 2013 a
803 - 6 summer 2013 a
 
Presentation final
Presentation finalPresentation final
Presentation final
 
02 1.公募で依頼する
02 1.公募で依頼する02 1.公募で依頼する
02 1.公募で依頼する
 
Survey: Embedded Systems In Power Industry
Survey: Embedded Systems In Power IndustrySurvey: Embedded Systems In Power Industry
Survey: Embedded Systems In Power Industry
 
Analogie tra computer e cervello - Lezione 2014 Università Adulti Anziani-BL
Analogie tra computer e cervello - Lezione 2014 Università Adulti Anziani-BLAnalogie tra computer e cervello - Lezione 2014 Università Adulti Anziani-BL
Analogie tra computer e cervello - Lezione 2014 Università Adulti Anziani-BL
 
補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)
補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)
補助金で合格しやすい事業計画の作り方(主に創業補助金、ものづくり補助金)
 

Similar to CS001

ADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEM
ADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEMADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEM
ADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEM
anil badiger
 
Infrared inspection power point
Infrared inspection power pointInfrared inspection power point
Infrared inspection power point
Charles Russell
 
AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304
Niels Inderbiethen
 
Project Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power PlantProject Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power Plant
Ferdous Kabir
 
TRP Presentation
TRP Presentation TRP Presentation
TRP Presentation
trpservices
 
Trp reliability presentation 2
Trp reliability presentation 2 Trp reliability presentation 2
Trp reliability presentation 2
trpservices1
 
Whitepaper fluke
Whitepaper flukeWhitepaper fluke
Whitepaper fluke
Clair Kirby
 

Similar to CS001 (20)

ADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEM
ADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEMADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEM
ADVANTAGES AND LIMITATION OF AN AUTOMATED VISUAL INSPECTION SYSTEM
 
Infrared inspection power point
Infrared inspection power pointInfrared inspection power point
Infrared inspection power point
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
 
Qualification of analytical instrument of FTIR
Qualification of analytical instrument of FTIR Qualification of analytical instrument of FTIR
Qualification of analytical instrument of FTIR
 
AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304
 
Project Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power PlantProject Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power Plant
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Condition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence TechniqueCondition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence Technique
 
Fluke contest entry
Fluke contest entryFluke contest entry
Fluke contest entry
 
Wuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionWuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular Construction
 
Case study of DCS upgrade how to reduce stress during execution
Case study of DCS upgrade how to reduce stress during executionCase study of DCS upgrade how to reduce stress during execution
Case study of DCS upgrade how to reduce stress during execution
 
Case study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during executionCase study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during execution
 
Digital Lime trasformation
Digital Lime trasformationDigital Lime trasformation
Digital Lime trasformation
 
Digital Lime trasformation
Digital Lime trasformationDigital Lime trasformation
Digital Lime trasformation
 
TRP Presentation
TRP Presentation TRP Presentation
TRP Presentation
 
Western Iowa Tech Community College Fluke Connect Student Contest Presentation
Western Iowa Tech Community College Fluke Connect Student Contest PresentationWestern Iowa Tech Community College Fluke Connect Student Contest Presentation
Western Iowa Tech Community College Fluke Connect Student Contest Presentation
 
Energy Auditing.pptx
Energy Auditing.pptxEnergy Auditing.pptx
Energy Auditing.pptx
 
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
IRJET- FPGA Implementation of an Improved Watchdog Timer for Safety Critical ...
 
Trp reliability presentation 2
Trp reliability presentation 2 Trp reliability presentation 2
Trp reliability presentation 2
 
Whitepaper fluke
Whitepaper flukeWhitepaper fluke
Whitepaper fluke
 

More from Steve Willetts (6)

Moog Case Study
Moog Case StudyMoog Case Study
Moog Case Study
 
Iris Presentation
Iris PresentationIris Presentation
Iris Presentation
 
Thermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical MaintenanceThermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical Maintenance
 
casestudy3indd
casestudy3inddcasestudy3indd
casestudy3indd
 
casestudy2indd
casestudy2inddcasestudy2indd
casestudy2indd
 
casestudy1indd
casestudy1inddcasestudy1indd
casestudy1indd
 

CS001

  • 1. CaseStudy PaperMill-SouthCarolina ROI Case Study 1 Paper Mill Saves Budget Dollars with IR Window Program By Martin Robinson, CMRP Level III Thermographer President, IRISS Inc. 18-1034-0001 Rev. A Overview: A paper mill in South Carolina had a very successful infrared inspection program that management wanted to expand. However, the requirements of NFPA 70E were causing them to re-think their stra- tegy since inspections of energized equipment was becoming more restrictive, more time consuming and more costly. Furthermore, 8% of the mill’s applications had never been surveyed due to switched interlocks (which automatically de-energize the equipment upon opening, thereby preventing access to energized components), or due to incident energy calculations in excess of 100 cal/cm2 on certain equip- ment (which exceeds personal protective equipment [PPE] ratings, and would place personnel in extreme danger and open the company to OSHA fines).
  • 2. CaseStudy PaperMill-SouthCarolina In search of alternative methods of conducting safer, standard compliant inspections, the corporate Reliability Engineer investigated how infrared inspection windows (commonly referred to as IR windows, viewports or sightglasses) might be utilized. It was determined that: • Use of Infrared Windows for routine inspections of healthy equipment did not require the elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating conditions, enclosed energized equipment that has been properly installed and maintained is not likely to pose an arc flash hazard.” In NFPA terms, an IR window maintains an “enclosed” state for the switchgear, MCC, Transformer, etc., and maintains energized components and circuit parts in a “guarded” condition. Therefore, the hazard/risk category would be equal to that of reading a panel meter, using a visual inspection pane for lockout/ tagout confirmations, or walking past enclosed, and energized equipment. • Use of IR windows or “sightglasses” would eliminate the need for a supporting cast of electricians to remove and reinstall panel covers. Those critical personnel would then be available to perform other tasks which were often being outsourced. • Use of infrared windows would provide an efficient method to perform inspections. This would make more frequent inspections feasible for critical or suspect applications to ensure plant uptime. • Use of IR windows would provide non-intrusive access to electrical applications; therefore, surveys could be conducted without elevating risk to plant assets and processes, meaning that inspections could be conducted during peak hours for the best diagnostic data. • Use of IR windows and closed panel inspection would eliminate high-risk tasks during inspections and thereby increase safety for thermographers. The focus of the mill’s initiative was to facilitate inspection of the primary switchgear in their electrical distribution system which feeds one paper machine and several smaller operations within the plant. An impending ten-day shutdown increased the sense of urgency since all windows could be fitted for one machine during that period. IRISS, Inc. was commissioned by the paper mill to conduct a pre-site inspection to ascertain the optimal position and quantity of windows which would give thermographers thorough visibility of desired targets. The conclusions from the initial inspection are noted in Table 1.
  • 3. CaseStudy PaperMill-SouthCarolina Table 1 Application Quantity 13.8 kV Primary Switch 15 Secondary Switchgear 22 Transformers (13.8 kV ) 27 MCC’s 2 Miscellaneous Switchgear 2 Generators 2 Total Assemblies 70 Inspection Compartments 147 IR Windows 197 The customer ordered 200 units of assorted VPFR-75 (3 inch diameter) and VPFR-100 (4 inch diameter) Infrared Inspection Windows to complete the installation. 197 windows were later installed. Investment Table 2 IR Window Supply and Installation Investment Infrared Windows (197 units assorted $42,050 3 & 4 inch diameter) Install Costs for 197 IR Windows $18,910 Total $60,960 197 VPFR infrared inspection windows totaled $42,050.00. IRISS was also retained to supply an installation team to perform the installation of the IR windows. Installation costs sited in Table 2 were calculated using the following assumptions: • Two-man installation team at $625.00 each per day (total cost $1,300 per day) x 10 Days = $13,000.00 • $30.00 per window installation charge x 197 Windows = $5,910.00
  • 4. CaseStudy PaperMill-SouthCarolina The Installation Installation of the infrared inspection panes was conducted during three nights and three days of the ten-day shutdown. Some installations were completed on live gear using additional safety measures; however, the vast majority was conducted on de-energized equipment in what NFPA terms an “electrically safe work condition.” Although our plan allowed for twelve hour shifts, installers were quickly and safely moving at a rate of approximately six window installations per hour, and were finishing the plant on the night shifts within six hours. Installations during normal business hours allowed much more flexibility; therefore all “live works” were completed during these periods. When the clients’ electricians assisted with the installations, the installation rates were also faster than originally planned (7 to 8 windows per hour). All window installations were completed well within the allotted timelines. Inspection Cost Analysis Prior to the installation of the IR windows, all infrared inspections were completed on open, energized gear. Therefore, PPE, live works procedures, risk assessments, permits, etc. were required for all inspections, and as noted earlier, several applications had never been surveyed due to safety restrictions. The paper mill had previously invested in its own infrared camera and an on-staff thermographer. The thermographer was trained and “qualified” to assist in opening panels on energized gear. Therefore, some efficiencies were already in place when compared to a typical crew of a single thermographer and two electricians. Consequently, the man-hour calculations for the “traditional inspection” are actually conservative. Table 3 details the man-hour costs for infrared surveys using in-house staff without infrared windows or viewports. The following assumptions are made:
  • 5. CaseStudy PaperMill-SouthCarolina • Total man-hours per inspection of “inspectable” equipment: 331 hours (23 days) • Staff electrician internal charge-out rate $125.00 per hour • Staff thermographer assists with panel removal, etc…(two-man task) • PPE suit-ups twice per day, per man (30 minutes per man per suit-up) • One man-hour per compartment panel for safe removal, etc. (x two for two-man team) • 147 individual panels to inspect (per Table 1) After the infrared windows were installed and there was no equipment to remove panels or wear increased levels of PPE, the task became a one-man job. The increased efficiency and economies of motion and man-power which infrared windows provided significantly decreased the time required to complete a survey to just two, eight-hour days for a total of just 16 man-hours. The costs associated with an infrared survey using the IR windows are detailed in Table 4. Compared to the costs of traditional inspections (Table 3), the paper mill now saves $39,375 per inspection cycle because of the efficiencies which they gain through the use of infrared windows. ROI Table 5 combines the data from the previous tables to illustrate the ROI for the paper mill based on the initial investment of the IR windows, the investment in installation and the costs to perform surveys using the windows, compared with the mill’s traditional costs of using their in-house team while not using any windows. Using infrared windows is shown in this example to pay dividends as early as mid-way into the second inspection cycle, yielding almost $18,000 in savings, which in turn can be put back into the budget by the end of the second cycle. In just five inspection cycles the mill shows a savings of over $135,000. Moreover, because inspections can be completed with greater ease and without increased risk to plant, personnel and processes, the frequency of inspection cycles has been increased to quarterly, reflecting best-practices recommendations which were previously not feasible and thought to be unattainable. The new inspection cycle brings ROI to the plant in just one quarter, while reducing the risk of catastrophic failure among the plant’s critical power distribution systems, which will in turn minimize production losses due to equipment failure. Future Installations Additional window installations have been planned and scheduled to occur during the facility’s next shutdown. Because the customer’s in-house electricians were trained to install infrared windows, the installation costs for future installations will be a fraction of the cost for the original installation, saving even more money and accelerating the ROI for additional windows.
  • 6. CaseStudy PaperMill-SouthCarolina IR Window Supply and Installation Investment Infrared Windows (197 units assorted 3 & 4 inch diameter) $42,050 Install Costs for 197 IR Windows $18,910 Total $60,960 IR Window Supply and Installation Investment Infrared Windows (197 units assorted 3 & 4 inch diameter) $42,050 Install Costs for 197 IR Windows $18,910 Total $60,960 Table 3 Total Cost of Traditional Inspection with In- House Team Traditional Inspection Time 294 $36,750 (Hrs. x 2 per team) PPE Suit-up Time 37 $4,625 (0.5 hr. x 2 per day x 2 men) Total $41,375 Table 4 Total Cost of Inspection Using IR Windows Inspection Time 16 $2,000 PPE Suit-up Time 0 $0.00 Total $2,000
  • 7. CaseStudy PaperMill-SouthCarolina Table 5 ROI Windows Traditional ROI 197 Infrared Windows $42,050 -- Installation of Windows $18,910 -- Cost for 1st Inspection Cycle $ 2,000 $41,375 Total for 1st Cycle $62,960 $41,375 <$ 21,585> Cost for 2nd Inspection Cycle $ 2,000 $41,375 Total for 2 Cycles $64,960 $82,750 $17,790 Cost for 3rd Inspection Cycle $2,000 $41,375 Total for 3 Cycles $66,960 $124,125 $57,165 Cost for 4th Inspection Cycle $2,000 $41,375 Total for 4 Cycles $68,960 $165,500 $96,540 Cost for 5th Inspection Cycle $2,000 $41,375 Total for 5 Cycles $70,960 $206,875 $135,915 Conclusion This mill realized a return on investment very quickly while benefitting from the other intangibles of infrared windows. Namely: • The ability to inspect the previously un-inspectable equipment • The ability to inspect critical applications more frequently • The ability to more aggressively monitor any applications which are suspected to be running to failure • Increase in safety for personnel • Decrease in risk to plant assets and operations due to the non-invasive nature of inspection – safeguarding profitability • Freeing up critical personnel who can be utilized for other valuable jobs in the plant rather than removing and reinstalling panels A portion of the financial savings were used to continue to build and strengthen the PdM program through the purchase of a second IR camera for the maintenance electricians, further underscoring the mill’s commitment to practical use of technology to ensure uptime while enhancing the safety of its workers. Infrared windows provide a cost-effective and safer alternative to traditional inspections. To learn more, visit http://www.iriss.com/where you will find more case studies and white papers.
  • 8. CaseStudy PaperMill-SouthCarolina To learn more about infrared windows, Electrical Preventive Maintenance, NFPA standards or electrical thermography please visit www.iriss.com. “10 Things You Need to Know About Infrared Windows” contains more information on the benefits of IR windows. To get your free digital copy, Click Here. Interested in IRISS IR Window Solutions? Click Here “10 Things You Need to Know About Infrared Windows”