iFluids Engineering ICS / DCS / SCADA Engineering Design, Procurement, Integration, Testing, Commissioning & Troubleshooting Services
Article Source: This guest blog post was written by Sunny R. Desai, an engineer in the DCS/PLC/SCADA department at Reliance Industries Ltd. A version of this article originally was published at InTech magazine.
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
Case study of dcs upgrade how to reduce stress during execution
1. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Case Study of DCS Upgrade: How to
Reduce Stress During Execution
The Reliance Industries Hazira complex, which manufactures a wide range of polymers,
polyesters, fiber intermediates, and petrochemicals, needed to determine the best way to
update the industrial automation system. The complex commissioned a naphtha cracker plant
in March 1997 using then state-of-the-art technology, including a UNIX-based control
system. Over the years, there had been a progression of vendors developing new systems
based on the latest technological platforms and then declaring their older systems obsolete.
Many of the components of the UNIX-based control system had been declared obsolete, and
the vendor had withdrawn active support, spares, and engineering resources. There was a
decreasing availability of spares, which were very expensive. The distributed control system
(DCS) is critical for plant operation; the obsolescence and unavailability of spares directly
affected the availability of the system for plant operation. Because electronic components
degrade over time, the failure rates of components was increasing. All these factors increased
the time and effort to restore a failure.
Evaluation philosophy
The company’s evaluation philosophy for developing an upgrade plan was based on the
following major criteria:
• Plant safety and reliability were of prime importance.
2. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
• Efforts should be made to prolong or stretch the system life as long as possible without
compromising safety or plant reliability.
• If the reliability of the existing system could be enhanced with a partial upgrade, it was
preferred.
• If the partial upgrade of the system was not possible or did not improve the reliability of the
system, efforts should be made to keep the full upgrade cost to a minimum.
Evaluation
A partial system upgrade was not suggested, because it would only improve the visualization,
but not the reliability, of controllers, I/O modules, and other hardware components. Also,
keeping in mind the remaining installed base at the site, other plants would benefit from the
spares generated by removing hardware from this plant. The final recommendation was a full
cracker plant control system upgrade.
Project scope
The following table shows an inventory of the existing DCS hardware.
•
•
•
•
•
3. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Update considerations
In the initial stage of the project, it was decided that the new system should be similar to the
existing system in terms of the visualization, faceplates, and programming to avoid confusion
between an actual problem in the field and a programming error.
The technical requirements the plant considered during the engineering stage included:
• time scheduling for minimum downtime during plant shutdown
• interfacing to existing field instruments
• reliability and safety of process areas
• redundancy features
• creating fresh logics in the new system from the existing system
• converting proportional, integral, derivative (PID) tuning parameters from the existing
system
• graphical design similar to the existing system for ease of operation
• communication with third-party systems
• advanced process control (APC) program modification
• third-party historian program modification
• secured network architecture
Method followed
Time scheduling was the biggest challenge for the entire team, with a very limited number of
days for executing the job, which included removing and fitting new system panels, removing
all the components from the marshalling panels, removing and fitting new alarm consoles,
formatting and installing DCS servers, replacing old operator stations with new ones,
removing existing control network cables and laying new ones, and replacing all the power
circuit breakers.
The upgrade was to be performed in the short duration of a shutdown. To restrict the cost, the
team decided not to replace the I/O panels, but only the internal components. This would also
minimize the carbon footprint of this project. It would take a lot of time to remove and fix
components individually, so the team decided to mount components on a plate and install the
plate in the panels. All the components, such as I/O modules, communication modules,
barriers, terminal blocks, and power supplies, were installed on the plate at the vendor’s
factory, and factory acceptance testing (FAT) was performed on the same setup.
To meet the desired system reliability, redundant controllers, communication modules, and
some analog output cards, power supplies, and diode ORings (creating logical OR
relationships) were connected in cross redundancy to avoid a single-point failure of any
device in the distribution. Power supply units were only loaded at less than 35 percent of
capacity.
The software function blocks did not have the functionality of the old system, so many
customized blocks were created in the new system, including blocks for APC and digital
loops. A team of specialized engineers, including process personnel, tested the logic in the
4. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
new system. This team visited the vendor a couple of times before conducting the FAT to
ensure that the logic worked per the existing control and automation philosophy.
The project’s new controller supported a significantly larger number of I/O than the existing
controllers. The plant preferred not to merge the I/O in one controller, but had them
distributed in the controllers exactly following the existing philosophy. No controllers were
designed to have third-party communication and I/O communication together.
It was decided in the design basis that all electronic components and cards should comply
with the ANSI/ISA-71.04-2013, G3 classification. The installed components must operate for
a minimum of 48 hours under extreme conditions: temperature at 0–50°C; relative humidity
at 10–96 percent at 32°C noncondensing; maximum vibration at 0.2 G, 20–300 Hz;
maximum displacement at 0.01 inches; 5–20 Hz. Considering the constant improvements
performed in the plant during normal plant operations, it was decided to restrict the controller
load to less than 40 percent, network load to less than 50 percent, free memory to greater than
50 percent, and power supply load to less than 40 percent.
Considering the failures of the power supply and diode ORing across the site, a redundant
power supply with a redundant diode ORing scheme was used for this project. An active
diode ORing with a load-sharing indication and alarm relay was also used.
Exhaustive FAT and SAT procedures were developed, and 100 percent loop testing and
redundancy testing of controllers, power supplies, I/O modules, communication networks,
and servers were performed. The team also performed 100 percent graphic testing and alarm
simulation. All the closed loops were checked and 100 percent APC functioning and OPC
communication was tested. During the SAT, the Profibus signature was taken for all the
nodes and was preserved for future reference.
Consequences and mitigation plan
Following are the key risks involved in the project:
Accurate as-built information unavailable
Consequence: If the information available is not accurate, panel wiring and closed-loop
operation in the field will be affected. Also, several instruments in the field may remain left
out, affecting the complete plant operation and causing a delay in the startup of the plant.
Mitigation plan: To provide an accurate project design basis, several walk-downs and manual
surveys were performed to verify existing documentation was accurate. This activity was
performed while the plant was running and did not affect the plant operation. The team took
several photographs of the existing wiring in the panels, noted the color code of every field
cable, noted every termination where they found a discrepancy with the existing drawing, and
prepared a detailed file consisting of all the information collected. This file was the key to the
successful implementation of this project.
5. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Manually converting the program to the new system
Consequence: If the program built in the system is not accurate per the old program, it will
affect the entire plant operation. The running process may trip many times, causing safety
concerns in the plant and a financial loss.
Mitigation plan: The only trusted document available for the programming was the existing
program running in the old system. First, it was important to understand the difference
between the logic block functions of the old system and that of the new system. The team
listed the functional differences between the two, and modified the new blocks to function
according to the old blocks. They decided to include the experts in the old system, from the
vendor as well as the user side, in the engineering team of the new system. This was one of
the crucial moves for ensuring a smooth upgrade. Several weeks were spent on this activity.
Once the compatible logic blocks were built in the new system, a trial test was performed to
check the operation of the blocks. On finding the operation satisfactory, clearance was given
to the vendor to continue building the program. At this point, the team calculated the
optimistic and the pessimistic time to complete the project execution, and all worked
wholeheartedly to meet the deadline.
Building visualization in the new system
Consequence: If the conversion is not proper, plant operation will be affected, as operators
will not be able to take quick actions when required. Because graphics are the main interface
between the operation team and the new system, faults in the graphics will directly affect the
operation team’s acceptance of the new system.
Mitigation plan: The panel operators were used to the old visualization, so it was decided that
the visualization in the system should be a look-alike of the old system, and the latest
visualization features should not be used in this upgrade. This would help the operators
accept the new system and also avoid confusion between actual problems in the field and
improper mapping of tags in the graphics during the plant startup. Once the visualization was
built in the new system, the engineering team performed a test. This test included verifying
the sketches on the graphics and mapping tags to the graphic element, alarm window, trend
window, group graphic windows, group trend window, and faceplate functioning. Once this
test was approved, the vendor was permitted to build more graphics.
Converting the PID tuning parameters
A PID controller is a control-loop feedback mechanism commonly used in industrial control
systems. A PID controller continuously calculates an “error value” as the difference between
a measured process variable and a desired set point. The tuning parameter directly influences
the accuracy of the control loop, and thereby the quality of the product. The value of these
parameters can only be fixed during the running plant operation. These values are a critical
asset for the plant, as they are fixed by the years of experience in operating the plant.
6. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Consequence: Steady-state operation of the plant will be affected, with a direct influence on
the quality of the product.
Mitigation plan: The vendor had developed a mathematical equation and a tool for converting
the tuning parameters from the old system to the new system. The vendor had verified this
tool at a different conversion project where the company was satisfied by the results of the
conversion, and hence it was readily accepted in this project. Later the team found the results
of this tool were quite accurate.
Third-party communication
Online analyzers, machine-condition monitoring systems, turbine-governing systems,
antisurge systems, and plant emergency shutdown systems are standalone systems critical for
plant operation. They maintain the quality of the product, control the safe operations of
compressors, and maintain the efficiency of the compressors and safe operation of the plant.
The readings of these systems must be continuously available for the operators. The
communication between the DCS and these systems is done with a Modbus protocol, which
is tricky and time consuming to configure.
Consequence: This will have an impact during the plant startup when operators will not be
able to see some data from the online analyzers, machine vibration conditions, and data from
the emergency shutdown system of the plant. This will also affect the steady-state operation
of the plant.
Mitigation plan: It was possible to complete this activity during the preshutdown period of
the project. The team arranged a spare controller and developed a test setup where the
running third-party system communicated with the new system. All the wiring diagrams,
communication settings, and response times were noted and later were directly implemented
in the new system. This way it became quite easy to establish the communication with the
actual new system.
Removing old components and fitting new ones in the panel
Consequence: If this activity is not completed in the planned time period, it will affect the
entire startup of the plant.
Mitigation plan: All the cables in the panels were not to be cut and removed immediately.
Multicore cables from the field and power cables from the main control board cabinet were to
be retained, so it was not easy to execute the system changeover during the shutdown period.
To meet this challenge, several drawings were prepared for each panel indicating which
cables and ducts were to be cut and removed and which cables were to be retained, where the
ferrules were to be changed, where the lugs were to be replaced, and TBs were marked where
there was interpanel wiring. Markings to distinguish between removal and retention were
done in each panel. All the electricians were trained to thoroughly understand the drawing.
To test the amount of time it would take to remove and fix the components in the panel, a
mock operation was performed during the FAT. For this, a fully loaded spare panel was
7. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
shifted from the site to the FAT area. During the mock operation, the team noted the time
required, all the challenges faced, and the tools required, and they planned improvements.
This activity helped a lot during the actual execution of replacing the components in each
panel.
Building secured network architecture
Newer control systems are highly network based and use common standards for
communication protocols. Many controllers are Internet Protocol addressable. Standard
operating systems, such as Windows, are increasingly used in industrial control systems,
which are now typically connected to remote controllers via private networks. The ability to
access the system as a result of this interoperability exposes network assets to infiltration and
subsequent manipulation of sensitive operations. Furthermore, increasingly sophisticated
cyberattack tools can exploit vulnerabilities in commercial off-the-shelf system components,
communication methods, and common operating systems found in modern control systems.
Consequences: This affects the safety of the plant and can have a financial implication on
failure. This may affect the entire business operation and can also have a social impact.
Mitigation plan: Considering the current scenario around the world and the constant increase
in the cyberthreat, the team decided on a secured network architecture with twin firewalls
installed in the system. They preferred that the two firewalls were of different makes. This
would help minimize any network-related threats. Antivirus software was installed in each
system, making sure it was set to run the latest definition files. All the USB ports, CD/DVD
drives, the autorun feature of Windows, the Windows scheduler, the remote desktop feature,
and all the spare network ports were disabled. The auto log-off feature was enabled. These
steps help prevent any virus attack on the system.
APC implementation
Consequences: Steady-state operation of the plant will be affected, minimizing the efficiency
of the process and having a direct financial effect.
Mitigation plan: APC implementation was a challenge in itself, because the new system did
not have similar functionality to the old system. All the programing blocks of the old system
were studied in detail, and blocks were developed in the system with the same functionality.
APC will communicate with the new system via a dedicated OPC station. In the old system,
the OPC wrote in a data block, but these data blocks were not available in the new system. To
meet this requirement, thousands of tags were created, which will not use the license. The
communication between the APC and these tags via OPC was tested during the FAT. All the
programs for taking a loop in APC and removing a loop from APC were tested during the
FAT period. The team performed 100 percent testing. Many data types required by APC that
were supported by the old system and were not supported by the new system were found
during the FAT. These data types were created in the new system and were mapped in the
APC program. APC communication was established during the shutdown period, but the
APC program in the APC controllers was modified in the post-shutdown period. Earlier, in
8. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
the UNIX-based system, a separate PC provided operator interface to the APC. In the new
system, a link to an Internet browser was provided for the operator to have the APC interface
in the DCS screen itself, so a separate PC was not required. Once the plant was started, the
APC program was tested for one of the furnaces, and in a week all the other APC programs
were modified. Similar modifications were also done in a real-time optimizer and third-party
historian.
Technological improvements
With this upgrade, we added some of modern automation’s state-of-the-art technology. Some
of the noticeable improvements were:
• Secured network: The new system network was based on the demilitarized zone (DMZ)
architecture implemented using a twin firewall configuration. One firewall isolates the
enterprise network from the plant network, and another firewall isolates the plant network
from the control network, thereby creating a secured DMZ network. Both the firewalls are of
a different make and can only be configured using a standalone configuration laptop.
• Enhanced diagnostic features: Diagnostic logs are generated for each module, with
master/slave in the hardware topology; they can be saved and analyzed for root-cause
analysis and preventive maintenance. A Web-based diagnostic portal, where we can view
warnings and controller errors, communication modules, and slave modules, is available in
the system.
• Smart client: This smart client is a true thin-client office workplace that seamlessly retrieves
data from the system and connected third-party systems. The smart client is a dashboard
visualization application that provides a read-only view into the system and allows the user
to call up graphics.
• Redundancy at the I/O level: For certain super-critical output tags that affect the production
and safety of the entire plant, we have installed redundant analog output cards. During the
normal course of operation, the cards share current demand from the field devices. Each
card is capable of supplying the full demand current from the field devices. When one card
fails, the other identifies the need of current in the circuit and supplies the full current.
• Twin active diode-ORing scheme: Dual ORs with a load-sharing indicator are used in this
project, which helps us monitor the load sharing between the two power supplies. This gives
us an opportunity to identify a probable failure. Along with a redundant power supply, we
have also installed a redundant diode ORing.
Results
Proper planning and coordination with the vendor resulted in an efficient installation and
commissioning of the new system. All the 14,000 I/O, marshalling panels, system panels,
alarm consoles, servers, and operator stations were successfully replaced in a very limited
time. It is a success story for the entire team; we completed the project well within the
planned period. The project can be summarized with the statement: more stress on planning
reduces stress during execution.
9. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Article Source: This guest blog post was written by Sunny R. Desai, an engineer in the
DCS/PLC/SCADA department at Reliance Industries Ltd. A version of this article originally
was published at InTech magazine.
iFluids Engineering ICS / DCS / SCADA Engineering Design,
Procurement, Integration, Testing, Commissioning &
Troubleshooting Services
10. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Cyber Security Services Provided by iFluids Engineering < To know more send email to
john@ifluids.com>
•IT Security Awareness
•ISO 27001 Introduction & ISMS Primer
•Essentials of ICS Engineering
•Essentials of SIS and Safety Life Cycle
11. Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
•ICS Security and Network Management
•Identity and Access Management
For more information regarding iFluids Engineering Services & Past Project Track Record
please visit here
Disclaimer: All information and content contained in this website are provided solely for
general information and reference purposes. TM information, Images & any copyrighted
material inadvertently published or depicted belong to rightfull owner and iFluids doesnt claim
to be its own.