SlideShare a Scribd company logo
1 of 11
Download to read offline
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Case Study of DCS Upgrade: How to
Reduce Stress During Execution
The Reliance Industries Hazira complex, which manufactures a wide range of polymers,
polyesters, fiber intermediates, and petrochemicals, needed to determine the best way to
update the industrial automation system. The complex commissioned a naphtha cracker plant
in March 1997 using then state-of-the-art technology, including a UNIX-based control
system. Over the years, there had been a progression of vendors developing new systems
based on the latest technological platforms and then declaring their older systems obsolete.
Many of the components of the UNIX-based control system had been declared obsolete, and
the vendor had withdrawn active support, spares, and engineering resources. There was a
decreasing availability of spares, which were very expensive. The distributed control system
(DCS) is critical for plant operation; the obsolescence and unavailability of spares directly
affected the availability of the system for plant operation. Because electronic components
degrade over time, the failure rates of components was increasing. All these factors increased
the time and effort to restore a failure.
Evaluation philosophy
The company’s evaluation philosophy for developing an upgrade plan was based on the
following major criteria:
• Plant safety and reliability were of prime importance.
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
• Efforts should be made to prolong or stretch the system life as long as possible without
compromising safety or plant reliability.
• If the reliability of the existing system could be enhanced with a partial upgrade, it was
preferred.
• If the partial upgrade of the system was not possible or did not improve the reliability of the
system, efforts should be made to keep the full upgrade cost to a minimum.
Evaluation
A partial system upgrade was not suggested, because it would only improve the visualization,
but not the reliability, of controllers, I/O modules, and other hardware components. Also,
keeping in mind the remaining installed base at the site, other plants would benefit from the
spares generated by removing hardware from this plant. The final recommendation was a full
cracker plant control system upgrade.
Project scope
The following table shows an inventory of the existing DCS hardware.
•
•
•
•
•
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Update considerations
In the initial stage of the project, it was decided that the new system should be similar to the
existing system in terms of the visualization, faceplates, and programming to avoid confusion
between an actual problem in the field and a programming error.
The technical requirements the plant considered during the engineering stage included:
• time scheduling for minimum downtime during plant shutdown
• interfacing to existing field instruments
• reliability and safety of process areas
• redundancy features
• creating fresh logics in the new system from the existing system
• converting proportional, integral, derivative (PID) tuning parameters from the existing
system
• graphical design similar to the existing system for ease of operation
• communication with third-party systems
• advanced process control (APC) program modification
• third-party historian program modification
• secured network architecture
Method followed
Time scheduling was the biggest challenge for the entire team, with a very limited number of
days for executing the job, which included removing and fitting new system panels, removing
all the components from the marshalling panels, removing and fitting new alarm consoles,
formatting and installing DCS servers, replacing old operator stations with new ones,
removing existing control network cables and laying new ones, and replacing all the power
circuit breakers.
The upgrade was to be performed in the short duration of a shutdown. To restrict the cost, the
team decided not to replace the I/O panels, but only the internal components. This would also
minimize the carbon footprint of this project. It would take a lot of time to remove and fix
components individually, so the team decided to mount components on a plate and install the
plate in the panels. All the components, such as I/O modules, communication modules,
barriers, terminal blocks, and power supplies, were installed on the plate at the vendor’s
factory, and factory acceptance testing (FAT) was performed on the same setup.
To meet the desired system reliability, redundant controllers, communication modules, and
some analog output cards, power supplies, and diode ORings (creating logical OR
relationships) were connected in cross redundancy to avoid a single-point failure of any
device in the distribution. Power supply units were only loaded at less than 35 percent of
capacity.
The software function blocks did not have the functionality of the old system, so many
customized blocks were created in the new system, including blocks for APC and digital
loops. A team of specialized engineers, including process personnel, tested the logic in the
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
new system. This team visited the vendor a couple of times before conducting the FAT to
ensure that the logic worked per the existing control and automation philosophy.
The project’s new controller supported a significantly larger number of I/O than the existing
controllers. The plant preferred not to merge the I/O in one controller, but had them
distributed in the controllers exactly following the existing philosophy. No controllers were
designed to have third-party communication and I/O communication together.
It was decided in the design basis that all electronic components and cards should comply
with the ANSI/ISA-71.04-2013, G3 classification. The installed components must operate for
a minimum of 48 hours under extreme conditions: temperature at 0–50°C; relative humidity
at 10–96 percent at 32°C noncondensing; maximum vibration at 0.2 G, 20–300 Hz;
maximum displacement at 0.01 inches; 5–20 Hz. Considering the constant improvements
performed in the plant during normal plant operations, it was decided to restrict the controller
load to less than 40 percent, network load to less than 50 percent, free memory to greater than
50 percent, and power supply load to less than 40 percent.
Considering the failures of the power supply and diode ORing across the site, a redundant
power supply with a redundant diode ORing scheme was used for this project. An active
diode ORing with a load-sharing indication and alarm relay was also used.
Exhaustive FAT and SAT procedures were developed, and 100 percent loop testing and
redundancy testing of controllers, power supplies, I/O modules, communication networks,
and servers were performed. The team also performed 100 percent graphic testing and alarm
simulation. All the closed loops were checked and 100 percent APC functioning and OPC
communication was tested. During the SAT, the Profibus signature was taken for all the
nodes and was preserved for future reference.
Consequences and mitigation plan
Following are the key risks involved in the project:
Accurate as-built information unavailable
Consequence: If the information available is not accurate, panel wiring and closed-loop
operation in the field will be affected. Also, several instruments in the field may remain left
out, affecting the complete plant operation and causing a delay in the startup of the plant.
Mitigation plan: To provide an accurate project design basis, several walk-downs and manual
surveys were performed to verify existing documentation was accurate. This activity was
performed while the plant was running and did not affect the plant operation. The team took
several photographs of the existing wiring in the panels, noted the color code of every field
cable, noted every termination where they found a discrepancy with the existing drawing, and
prepared a detailed file consisting of all the information collected. This file was the key to the
successful implementation of this project.
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Manually converting the program to the new system
Consequence: If the program built in the system is not accurate per the old program, it will
affect the entire plant operation. The running process may trip many times, causing safety
concerns in the plant and a financial loss.
Mitigation plan: The only trusted document available for the programming was the existing
program running in the old system. First, it was important to understand the difference
between the logic block functions of the old system and that of the new system. The team
listed the functional differences between the two, and modified the new blocks to function
according to the old blocks. They decided to include the experts in the old system, from the
vendor as well as the user side, in the engineering team of the new system. This was one of
the crucial moves for ensuring a smooth upgrade. Several weeks were spent on this activity.
Once the compatible logic blocks were built in the new system, a trial test was performed to
check the operation of the blocks. On finding the operation satisfactory, clearance was given
to the vendor to continue building the program. At this point, the team calculated the
optimistic and the pessimistic time to complete the project execution, and all worked
wholeheartedly to meet the deadline.
Building visualization in the new system
Consequence: If the conversion is not proper, plant operation will be affected, as operators
will not be able to take quick actions when required. Because graphics are the main interface
between the operation team and the new system, faults in the graphics will directly affect the
operation team’s acceptance of the new system.
Mitigation plan: The panel operators were used to the old visualization, so it was decided that
the visualization in the system should be a look-alike of the old system, and the latest
visualization features should not be used in this upgrade. This would help the operators
accept the new system and also avoid confusion between actual problems in the field and
improper mapping of tags in the graphics during the plant startup. Once the visualization was
built in the new system, the engineering team performed a test. This test included verifying
the sketches on the graphics and mapping tags to the graphic element, alarm window, trend
window, group graphic windows, group trend window, and faceplate functioning. Once this
test was approved, the vendor was permitted to build more graphics.
Converting the PID tuning parameters
A PID controller is a control-loop feedback mechanism commonly used in industrial control
systems. A PID controller continuously calculates an “error value” as the difference between
a measured process variable and a desired set point. The tuning parameter directly influences
the accuracy of the control loop, and thereby the quality of the product. The value of these
parameters can only be fixed during the running plant operation. These values are a critical
asset for the plant, as they are fixed by the years of experience in operating the plant.
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Consequence: Steady-state operation of the plant will be affected, with a direct influence on
the quality of the product.
Mitigation plan: The vendor had developed a mathematical equation and a tool for converting
the tuning parameters from the old system to the new system. The vendor had verified this
tool at a different conversion project where the company was satisfied by the results of the
conversion, and hence it was readily accepted in this project. Later the team found the results
of this tool were quite accurate.
Third-party communication
Online analyzers, machine-condition monitoring systems, turbine-governing systems,
antisurge systems, and plant emergency shutdown systems are standalone systems critical for
plant operation. They maintain the quality of the product, control the safe operations of
compressors, and maintain the efficiency of the compressors and safe operation of the plant.
The readings of these systems must be continuously available for the operators. The
communication between the DCS and these systems is done with a Modbus protocol, which
is tricky and time consuming to configure.
Consequence: This will have an impact during the plant startup when operators will not be
able to see some data from the online analyzers, machine vibration conditions, and data from
the emergency shutdown system of the plant. This will also affect the steady-state operation
of the plant.
Mitigation plan: It was possible to complete this activity during the preshutdown period of
the project. The team arranged a spare controller and developed a test setup where the
running third-party system communicated with the new system. All the wiring diagrams,
communication settings, and response times were noted and later were directly implemented
in the new system. This way it became quite easy to establish the communication with the
actual new system.
Removing old components and fitting new ones in the panel
Consequence: If this activity is not completed in the planned time period, it will affect the
entire startup of the plant.
Mitigation plan: All the cables in the panels were not to be cut and removed immediately.
Multicore cables from the field and power cables from the main control board cabinet were to
be retained, so it was not easy to execute the system changeover during the shutdown period.
To meet this challenge, several drawings were prepared for each panel indicating which
cables and ducts were to be cut and removed and which cables were to be retained, where the
ferrules were to be changed, where the lugs were to be replaced, and TBs were marked where
there was interpanel wiring. Markings to distinguish between removal and retention were
done in each panel. All the electricians were trained to thoroughly understand the drawing.
To test the amount of time it would take to remove and fix the components in the panel, a
mock operation was performed during the FAT. For this, a fully loaded spare panel was
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
shifted from the site to the FAT area. During the mock operation, the team noted the time
required, all the challenges faced, and the tools required, and they planned improvements.
This activity helped a lot during the actual execution of replacing the components in each
panel.
Building secured network architecture
Newer control systems are highly network based and use common standards for
communication protocols. Many controllers are Internet Protocol addressable. Standard
operating systems, such as Windows, are increasingly used in industrial control systems,
which are now typically connected to remote controllers via private networks. The ability to
access the system as a result of this interoperability exposes network assets to infiltration and
subsequent manipulation of sensitive operations. Furthermore, increasingly sophisticated
cyberattack tools can exploit vulnerabilities in commercial off-the-shelf system components,
communication methods, and common operating systems found in modern control systems.
Consequences: This affects the safety of the plant and can have a financial implication on
failure. This may affect the entire business operation and can also have a social impact.
Mitigation plan: Considering the current scenario around the world and the constant increase
in the cyberthreat, the team decided on a secured network architecture with twin firewalls
installed in the system. They preferred that the two firewalls were of different makes. This
would help minimize any network-related threats. Antivirus software was installed in each
system, making sure it was set to run the latest definition files. All the USB ports, CD/DVD
drives, the autorun feature of Windows, the Windows scheduler, the remote desktop feature,
and all the spare network ports were disabled. The auto log-off feature was enabled. These
steps help prevent any virus attack on the system.
APC implementation
Consequences: Steady-state operation of the plant will be affected, minimizing the efficiency
of the process and having a direct financial effect.
Mitigation plan: APC implementation was a challenge in itself, because the new system did
not have similar functionality to the old system. All the programing blocks of the old system
were studied in detail, and blocks were developed in the system with the same functionality.
APC will communicate with the new system via a dedicated OPC station. In the old system,
the OPC wrote in a data block, but these data blocks were not available in the new system. To
meet this requirement, thousands of tags were created, which will not use the license. The
communication between the APC and these tags via OPC was tested during the FAT. All the
programs for taking a loop in APC and removing a loop from APC were tested during the
FAT period. The team performed 100 percent testing. Many data types required by APC that
were supported by the old system and were not supported by the new system were found
during the FAT. These data types were created in the new system and were mapped in the
APC program. APC communication was established during the shutdown period, but the
APC program in the APC controllers was modified in the post-shutdown period. Earlier, in
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
the UNIX-based system, a separate PC provided operator interface to the APC. In the new
system, a link to an Internet browser was provided for the operator to have the APC interface
in the DCS screen itself, so a separate PC was not required. Once the plant was started, the
APC program was tested for one of the furnaces, and in a week all the other APC programs
were modified. Similar modifications were also done in a real-time optimizer and third-party
historian.
Technological improvements
With this upgrade, we added some of modern automation’s state-of-the-art technology. Some
of the noticeable improvements were:
• Secured network: The new system network was based on the demilitarized zone (DMZ)
architecture implemented using a twin firewall configuration. One firewall isolates the
enterprise network from the plant network, and another firewall isolates the plant network
from the control network, thereby creating a secured DMZ network. Both the firewalls are of
a different make and can only be configured using a standalone configuration laptop.
• Enhanced diagnostic features: Diagnostic logs are generated for each module, with
master/slave in the hardware topology; they can be saved and analyzed for root-cause
analysis and preventive maintenance. A Web-based diagnostic portal, where we can view
warnings and controller errors, communication modules, and slave modules, is available in
the system.
• Smart client: This smart client is a true thin-client office workplace that seamlessly retrieves
data from the system and connected third-party systems. The smart client is a dashboard
visualization application that provides a read-only view into the system and allows the user
to call up graphics.
• Redundancy at the I/O level: For certain super-critical output tags that affect the production
and safety of the entire plant, we have installed redundant analog output cards. During the
normal course of operation, the cards share current demand from the field devices. Each
card is capable of supplying the full demand current from the field devices. When one card
fails, the other identifies the need of current in the circuit and supplies the full current.
• Twin active diode-ORing scheme: Dual ORs with a load-sharing indicator are used in this
project, which helps us monitor the load sharing between the two power supplies. This gives
us an opportunity to identify a probable failure. Along with a redundant power supply, we
have also installed a redundant diode ORing.
Results
Proper planning and coordination with the vendor resulted in an efficient installation and
commissioning of the new system. All the 14,000 I/O, marshalling panels, system panels,
alarm consoles, servers, and operator stations were successfully replaced in a very limited
time. It is a success story for the entire team; we completed the project well within the
planned period. The project can be summarized with the statement: more stress on planning
reduces stress during execution.
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Article Source: This guest blog post was written by Sunny R. Desai, an engineer in the
DCS/PLC/SCADA department at Reliance Industries Ltd. A version of this article originally
was published at InTech magazine.
iFluids Engineering ICS / DCS / SCADA Engineering Design,
Procurement, Integration, Testing, Commissioning &
Troubleshooting Services
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
Cyber Security Services Provided by iFluids Engineering < To know more send email to
john@ifluids.com>
•IT Security Awareness
•ISO 27001 Introduction & ISMS Primer
•Essentials of ICS Engineering
•Essentials of SIS and Safety Life Cycle
Contact john@ifluids.com (or) info@ifluids.com
Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com
•ICS Security and Network Management
•Identity and Access Management
For more information regarding iFluids Engineering Services & Past Project Track Record
please visit here
Disclaimer: All information and content contained in this website are provided solely for
general information and reference purposes. TM information, Images & any copyrighted
material inadvertently published or depicted belong to rightfull owner and iFluids doesnt claim
to be its own.

More Related Content

What's hot

How to Get Started With Advanced Contro
How to Get Started With Advanced ControHow to Get Started With Advanced Contro
How to Get Started With Advanced ControEmerson Exchange
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurementsEmerson Exchange
 
Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Emerson Exchange
 
Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...Emerson Exchange
 
Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Emerson Exchange
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleRicky Smith CMRP, CMRT
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisAnas Momen
 
Aerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves moneyAerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves moneyIntelligentManufacturingInstitute
 
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Emerson Exchange
 
Application of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unitApplication of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unitEmerson Exchange
 
Advanced control foundation tools and techniques
Advanced control foundation   tools and techniquesAdvanced control foundation   tools and techniques
Advanced control foundation tools and techniquesEmerson Exchange
 
Delta v advanced control overview_en
Delta v advanced control overview_enDelta v advanced control overview_en
Delta v advanced control overview_enLuis Atencio
 
The semantic web an inside look at the creation of control loop foundation
The semantic web   an inside look at the creation of control loop foundationThe semantic web   an inside look at the creation of control loop foundation
The semantic web an inside look at the creation of control loop foundationEmerson Exchange
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
Commissioning highly interactive process an approach for tuning control loops
Commissioning highly interactive process an approach for tuning control loopsCommissioning highly interactive process an approach for tuning control loops
Commissioning highly interactive process an approach for tuning control loopsEmerson Exchange
 
Utilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control PerformanceUtilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control PerformanceEmerson Exchange
 
Mechanical completion handbook1
Mechanical completion handbook1Mechanical completion handbook1
Mechanical completion handbook1zulfikar N joel
 
Addressing control applications using wireless hart devices
Addressing control applications using wireless hart devicesAddressing control applications using wireless hart devices
Addressing control applications using wireless hart devicesEmerson Exchange
 

What's hot (19)

How to Get Started With Advanced Contro
How to Get Started With Advanced ControHow to Get Started With Advanced Contro
How to Get Started With Advanced Contro
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurements
 
Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2Modernization Lessons Learned -Part 2
Modernization Lessons Learned -Part 2
 
Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...Improving continuous process operation using data analytics delta v applicati...
Improving continuous process operation using data analytics delta v applicati...
 
Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2Maximizing the return on your control investment meet the experts sessions part2
Maximizing the return on your control investment meet the experts sessions part2
 
Reliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made SimpleReliability Centered Maintenance Made Simple
Reliability Centered Maintenance Made Simple
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
 
Aerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves moneyAerospace maintenance facility increases utilization by 50%, saves money
Aerospace maintenance facility increases utilization by 50%, saves money
 
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...Calibration Excellence: Intelligent Application of Smart Technology is Just t...
Calibration Excellence: Intelligent Application of Smart Technology is Just t...
 
Application of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unitApplication of online data analytics to a continuous process polybutene unit
Application of online data analytics to a continuous process polybutene unit
 
Advanced control foundation tools and techniques
Advanced control foundation   tools and techniquesAdvanced control foundation   tools and techniques
Advanced control foundation tools and techniques
 
Delta v advanced control overview_en
Delta v advanced control overview_enDelta v advanced control overview_en
Delta v advanced control overview_en
 
The semantic web an inside look at the creation of control loop foundation
The semantic web   an inside look at the creation of control loop foundationThe semantic web   an inside look at the creation of control loop foundation
The semantic web an inside look at the creation of control loop foundation
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Commissioning highly interactive process an approach for tuning control loops
Commissioning highly interactive process an approach for tuning control loopsCommissioning highly interactive process an approach for tuning control loops
Commissioning highly interactive process an approach for tuning control loops
 
Utilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control PerformanceUtilizing DeltaV Advanced Control Innovations to Improve Control Performance
Utilizing DeltaV Advanced Control Innovations to Improve Control Performance
 
MS CV May 2016
MS CV May 2016MS CV May 2016
MS CV May 2016
 
Mechanical completion handbook1
Mechanical completion handbook1Mechanical completion handbook1
Mechanical completion handbook1
 
Addressing control applications using wireless hart devices
Addressing control applications using wireless hart devicesAddressing control applications using wireless hart devices
Addressing control applications using wireless hart devices
 

Similar to Case study of dcs upgrade how to reduce stress during execution

Formal Methods for Dependable Neural Networks
Formal Methods for Dependable Neural Networks Formal Methods for Dependable Neural Networks
Formal Methods for Dependable Neural Networks Chih-Hong Cheng
 
CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510Arif Nusyirwan
 
Driving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsDriving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsOptima Control Solutions
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editorseldhoev
 
Chapter7_ControlLoop-1.pdf
Chapter7_ControlLoop-1.pdfChapter7_ControlLoop-1.pdf
Chapter7_ControlLoop-1.pdfJoshua25806
 
DESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTURE
DESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTUREDESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTURE
DESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTUREVLSICS Design
 
Embedded Systems Q and A M.Sc.(IT) PART II SEM III
Embedded Systems Q and A M.Sc.(IT) PART II SEM IIIEmbedded Systems Q and A M.Sc.(IT) PART II SEM III
Embedded Systems Q and A M.Sc.(IT) PART II SEM IIINi
 
Avanced process control enteprise management system
Avanced process control enteprise management systemAvanced process control enteprise management system
Avanced process control enteprise management systemGyan Prakash
 
Analysis of a high availability and data integration solution of an electroni...
Analysis of a high availability and data integration solution of an electroni...Analysis of a high availability and data integration solution of an electroni...
Analysis of a high availability and data integration solution of an electroni...IvanZennaro
 
Training feedback Basavaraju
Training feedback BasavarajuTraining feedback Basavaraju
Training feedback BasavarajuBasavaraju YM
 
KP Controls CV 1.4
KP Controls CV 1.4KP Controls CV 1.4
KP Controls CV 1.4kevin pratt
 
Intelligent instrumentation and power plant simulators
Intelligent instrumentation and power plant simulatorsIntelligent instrumentation and power plant simulators
Intelligent instrumentation and power plant simulatorsSelvam Sethurathinam
 
wp-01070-hardware-software-coverification-fpga
wp-01070-hardware-software-coverification-fpgawp-01070-hardware-software-coverification-fpga
wp-01070-hardware-software-coverification-fpgaGautam Kavipurapu
 
Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...
Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...
Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...Tero Aaltonen
 
Asset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsAsset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsARC Advisory Group
 
RA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx SystemsRA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx SystemsRockwell Automation
 

Similar to Case study of dcs upgrade how to reduce stress during execution (20)

Formal Methods for Dependable Neural Networks
Formal Methods for Dependable Neural Networks Formal Methods for Dependable Neural Networks
Formal Methods for Dependable Neural Networks
 
CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510
 
Driving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsDriving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System Migrations
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editors
 
Chapter7_ControlLoop-1.pdf
Chapter7_ControlLoop-1.pdfChapter7_ControlLoop-1.pdf
Chapter7_ControlLoop-1.pdf
 
DESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTURE
DESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTUREDESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTURE
DESIGN APPROACH FOR FAULT TOLERANCE IN FPGA ARCHITECTURE
 
Embedded Systems Q and A M.Sc.(IT) PART II SEM III
Embedded Systems Q and A M.Sc.(IT) PART II SEM IIIEmbedded Systems Q and A M.Sc.(IT) PART II SEM III
Embedded Systems Q and A M.Sc.(IT) PART II SEM III
 
Avanced process control enteprise management system
Avanced process control enteprise management systemAvanced process control enteprise management system
Avanced process control enteprise management system
 
Analysis of a high availability and data integration solution of an electroni...
Analysis of a high availability and data integration solution of an electroni...Analysis of a high availability and data integration solution of an electroni...
Analysis of a high availability and data integration solution of an electroni...
 
Training feedback Basavaraju
Training feedback BasavarajuTraining feedback Basavaraju
Training feedback Basavaraju
 
KP Controls CV 1.4
KP Controls CV 1.4KP Controls CV 1.4
KP Controls CV 1.4
 
Intelligent instrumentation and power plant simulators
Intelligent instrumentation and power plant simulatorsIntelligent instrumentation and power plant simulators
Intelligent instrumentation and power plant simulators
 
wp-01070-hardware-software-coverification-fpga
wp-01070-hardware-software-coverification-fpgawp-01070-hardware-software-coverification-fpga
wp-01070-hardware-software-coverification-fpga
 
vinayak_Resume_18112014
vinayak_Resume_18112014vinayak_Resume_18112014
vinayak_Resume_18112014
 
Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...
Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...
Overcoming Obstacles in Bringing Android Automotive Infotainment Systems to M...
 
Ankur Goel Resume
Ankur Goel ResumeAnkur Goel Resume
Ankur Goel Resume
 
TechComp_overview_brief
TechComp_overview_briefTechComp_overview_brief
TechComp_overview_brief
 
Effective Plant Management
Effective Plant ManagementEffective Plant Management
Effective Plant Management
 
Asset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsAsset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety Solutions
 
RA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx SystemsRA TechED 2019 - PR03 - Implementation of PlantPAx Systems
RA TechED 2019 - PR03 - Implementation of PlantPAx Systems
 

More from John Kingsley

Get yourself trained or Certified for IEC 62443 and other trainings.pdf
Get yourself trained or Certified for IEC 62443 and other trainings.pdfGet yourself trained or Certified for IEC 62443 and other trainings.pdf
Get yourself trained or Certified for IEC 62443 and other trainings.pdfJohn Kingsley
 
MODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDING
MODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDINGMODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDING
MODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDINGJohn Kingsley
 
Reliability, availability, maintainability (RAM) study, on reciprocating comp...
Reliability, availability, maintainability (RAM) study, on reciprocating comp...Reliability, availability, maintainability (RAM) study, on reciprocating comp...
Reliability, availability, maintainability (RAM) study, on reciprocating comp...John Kingsley
 
Introduction to oil and gas exploration and processing
Introduction to oil and gas exploration and processingIntroduction to oil and gas exploration and processing
Introduction to oil and gas exploration and processingJohn Kingsley
 
iFluids Engineering Introduction
iFluids Engineering IntroductioniFluids Engineering Introduction
iFluids Engineering IntroductionJohn Kingsley
 
iFluids Engineering Brochure
iFluids Engineering BrochureiFluids Engineering Brochure
iFluids Engineering BrochureJohn Kingsley
 
iFluids Engienering Capability Presentation
iFluids Engienering Capability PresentationiFluids Engienering Capability Presentation
iFluids Engienering Capability PresentationJohn Kingsley
 
Hazop Training - Intermediate Level Course iFluids
Hazop Training  -  Intermediate Level Course iFluidsHazop Training  -  Intermediate Level Course iFluids
Hazop Training - Intermediate Level Course iFluidsJohn Kingsley
 
Introduction to PSM Online Interactive Training
Introduction to PSM Online Interactive TrainingIntroduction to PSM Online Interactive Training
Introduction to PSM Online Interactive TrainingJohn Kingsley
 
Sil assessment Risk Graph and LOPA Training iFluids
Sil assessment Risk Graph and LOPA Training iFluidsSil assessment Risk Graph and LOPA Training iFluids
Sil assessment Risk Graph and LOPA Training iFluidsJohn Kingsley
 
Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsJohn Kingsley
 
John kingsley OT ICS SCADA Cyber security consultant
John kingsley OT ICS SCADA Cyber security consultantJohn kingsley OT ICS SCADA Cyber security consultant
John kingsley OT ICS SCADA Cyber security consultantJohn Kingsley
 
iFluids Lean Six Sigma Case Study oil & gas
iFluids Lean Six Sigma Case Study oil & gasiFluids Lean Six Sigma Case Study oil & gas
iFluids Lean Six Sigma Case Study oil & gasJohn Kingsley
 
iFluids Behaviour based safety services and training
iFluids Behaviour based safety services and trainingiFluids Behaviour based safety services and training
iFluids Behaviour based safety services and trainingJohn Kingsley
 
iFluids Tank Inspection services
iFluids Tank Inspection servicesiFluids Tank Inspection services
iFluids Tank Inspection servicesJohn Kingsley
 
iFluids Cybersecurity Seminar CIC Qatar 2018 Agenda
iFluids Cybersecurity Seminar  CIC Qatar 2018 AgendaiFluids Cybersecurity Seminar  CIC Qatar 2018 Agenda
iFluids Cybersecurity Seminar CIC Qatar 2018 AgendaJohn Kingsley
 
How to write a plant operating manual
How to write a plant operating manualHow to write a plant operating manual
How to write a plant operating manualJohn Kingsley
 
Hydrocarbon leak detection in tank farms
Hydrocarbon leak detection in tank farmsHydrocarbon leak detection in tank farms
Hydrocarbon leak detection in tank farmsJohn Kingsley
 
Guide to specifying visual signals
Guide to specifying visual signalsGuide to specifying visual signals
Guide to specifying visual signalsJohn Kingsley
 
Introduction to bowtie : A barrier-based approach to risk
Introduction to bowtie : A barrier-based approach to riskIntroduction to bowtie : A barrier-based approach to risk
Introduction to bowtie : A barrier-based approach to riskJohn Kingsley
 

More from John Kingsley (20)

Get yourself trained or Certified for IEC 62443 and other trainings.pdf
Get yourself trained or Certified for IEC 62443 and other trainings.pdfGet yourself trained or Certified for IEC 62443 and other trainings.pdf
Get yourself trained or Certified for IEC 62443 and other trainings.pdf
 
MODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDING
MODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDINGMODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDING
MODIFICATION OF EXISTING FACILITIES FOR 20% ETHANOL BLENDING
 
Reliability, availability, maintainability (RAM) study, on reciprocating comp...
Reliability, availability, maintainability (RAM) study, on reciprocating comp...Reliability, availability, maintainability (RAM) study, on reciprocating comp...
Reliability, availability, maintainability (RAM) study, on reciprocating comp...
 
Introduction to oil and gas exploration and processing
Introduction to oil and gas exploration and processingIntroduction to oil and gas exploration and processing
Introduction to oil and gas exploration and processing
 
iFluids Engineering Introduction
iFluids Engineering IntroductioniFluids Engineering Introduction
iFluids Engineering Introduction
 
iFluids Engineering Brochure
iFluids Engineering BrochureiFluids Engineering Brochure
iFluids Engineering Brochure
 
iFluids Engienering Capability Presentation
iFluids Engienering Capability PresentationiFluids Engienering Capability Presentation
iFluids Engienering Capability Presentation
 
Hazop Training - Intermediate Level Course iFluids
Hazop Training  -  Intermediate Level Course iFluidsHazop Training  -  Intermediate Level Course iFluids
Hazop Training - Intermediate Level Course iFluids
 
Introduction to PSM Online Interactive Training
Introduction to PSM Online Interactive TrainingIntroduction to PSM Online Interactive Training
Introduction to PSM Online Interactive Training
 
Sil assessment Risk Graph and LOPA Training iFluids
Sil assessment Risk Graph and LOPA Training iFluidsSil assessment Risk Graph and LOPA Training iFluids
Sil assessment Risk Graph and LOPA Training iFluids
 
Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluids
 
John kingsley OT ICS SCADA Cyber security consultant
John kingsley OT ICS SCADA Cyber security consultantJohn kingsley OT ICS SCADA Cyber security consultant
John kingsley OT ICS SCADA Cyber security consultant
 
iFluids Lean Six Sigma Case Study oil & gas
iFluids Lean Six Sigma Case Study oil & gasiFluids Lean Six Sigma Case Study oil & gas
iFluids Lean Six Sigma Case Study oil & gas
 
iFluids Behaviour based safety services and training
iFluids Behaviour based safety services and trainingiFluids Behaviour based safety services and training
iFluids Behaviour based safety services and training
 
iFluids Tank Inspection services
iFluids Tank Inspection servicesiFluids Tank Inspection services
iFluids Tank Inspection services
 
iFluids Cybersecurity Seminar CIC Qatar 2018 Agenda
iFluids Cybersecurity Seminar  CIC Qatar 2018 AgendaiFluids Cybersecurity Seminar  CIC Qatar 2018 Agenda
iFluids Cybersecurity Seminar CIC Qatar 2018 Agenda
 
How to write a plant operating manual
How to write a plant operating manualHow to write a plant operating manual
How to write a plant operating manual
 
Hydrocarbon leak detection in tank farms
Hydrocarbon leak detection in tank farmsHydrocarbon leak detection in tank farms
Hydrocarbon leak detection in tank farms
 
Guide to specifying visual signals
Guide to specifying visual signalsGuide to specifying visual signals
Guide to specifying visual signals
 
Introduction to bowtie : A barrier-based approach to risk
Introduction to bowtie : A barrier-based approach to riskIntroduction to bowtie : A barrier-based approach to risk
Introduction to bowtie : A barrier-based approach to risk
 

Recently uploaded

8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 

Recently uploaded (20)

8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 

Case study of dcs upgrade how to reduce stress during execution

  • 1. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com Case Study of DCS Upgrade: How to Reduce Stress During Execution The Reliance Industries Hazira complex, which manufactures a wide range of polymers, polyesters, fiber intermediates, and petrochemicals, needed to determine the best way to update the industrial automation system. The complex commissioned a naphtha cracker plant in March 1997 using then state-of-the-art technology, including a UNIX-based control system. Over the years, there had been a progression of vendors developing new systems based on the latest technological platforms and then declaring their older systems obsolete. Many of the components of the UNIX-based control system had been declared obsolete, and the vendor had withdrawn active support, spares, and engineering resources. There was a decreasing availability of spares, which were very expensive. The distributed control system (DCS) is critical for plant operation; the obsolescence and unavailability of spares directly affected the availability of the system for plant operation. Because electronic components degrade over time, the failure rates of components was increasing. All these factors increased the time and effort to restore a failure. Evaluation philosophy The company’s evaluation philosophy for developing an upgrade plan was based on the following major criteria: • Plant safety and reliability were of prime importance.
  • 2. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com • Efforts should be made to prolong or stretch the system life as long as possible without compromising safety or plant reliability. • If the reliability of the existing system could be enhanced with a partial upgrade, it was preferred. • If the partial upgrade of the system was not possible or did not improve the reliability of the system, efforts should be made to keep the full upgrade cost to a minimum. Evaluation A partial system upgrade was not suggested, because it would only improve the visualization, but not the reliability, of controllers, I/O modules, and other hardware components. Also, keeping in mind the remaining installed base at the site, other plants would benefit from the spares generated by removing hardware from this plant. The final recommendation was a full cracker plant control system upgrade. Project scope The following table shows an inventory of the existing DCS hardware. • • • • •
  • 3. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com Update considerations In the initial stage of the project, it was decided that the new system should be similar to the existing system in terms of the visualization, faceplates, and programming to avoid confusion between an actual problem in the field and a programming error. The technical requirements the plant considered during the engineering stage included: • time scheduling for minimum downtime during plant shutdown • interfacing to existing field instruments • reliability and safety of process areas • redundancy features • creating fresh logics in the new system from the existing system • converting proportional, integral, derivative (PID) tuning parameters from the existing system • graphical design similar to the existing system for ease of operation • communication with third-party systems • advanced process control (APC) program modification • third-party historian program modification • secured network architecture Method followed Time scheduling was the biggest challenge for the entire team, with a very limited number of days for executing the job, which included removing and fitting new system panels, removing all the components from the marshalling panels, removing and fitting new alarm consoles, formatting and installing DCS servers, replacing old operator stations with new ones, removing existing control network cables and laying new ones, and replacing all the power circuit breakers. The upgrade was to be performed in the short duration of a shutdown. To restrict the cost, the team decided not to replace the I/O panels, but only the internal components. This would also minimize the carbon footprint of this project. It would take a lot of time to remove and fix components individually, so the team decided to mount components on a plate and install the plate in the panels. All the components, such as I/O modules, communication modules, barriers, terminal blocks, and power supplies, were installed on the plate at the vendor’s factory, and factory acceptance testing (FAT) was performed on the same setup. To meet the desired system reliability, redundant controllers, communication modules, and some analog output cards, power supplies, and diode ORings (creating logical OR relationships) were connected in cross redundancy to avoid a single-point failure of any device in the distribution. Power supply units were only loaded at less than 35 percent of capacity. The software function blocks did not have the functionality of the old system, so many customized blocks were created in the new system, including blocks for APC and digital loops. A team of specialized engineers, including process personnel, tested the logic in the
  • 4. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com new system. This team visited the vendor a couple of times before conducting the FAT to ensure that the logic worked per the existing control and automation philosophy. The project’s new controller supported a significantly larger number of I/O than the existing controllers. The plant preferred not to merge the I/O in one controller, but had them distributed in the controllers exactly following the existing philosophy. No controllers were designed to have third-party communication and I/O communication together. It was decided in the design basis that all electronic components and cards should comply with the ANSI/ISA-71.04-2013, G3 classification. The installed components must operate for a minimum of 48 hours under extreme conditions: temperature at 0–50°C; relative humidity at 10–96 percent at 32°C noncondensing; maximum vibration at 0.2 G, 20–300 Hz; maximum displacement at 0.01 inches; 5–20 Hz. Considering the constant improvements performed in the plant during normal plant operations, it was decided to restrict the controller load to less than 40 percent, network load to less than 50 percent, free memory to greater than 50 percent, and power supply load to less than 40 percent. Considering the failures of the power supply and diode ORing across the site, a redundant power supply with a redundant diode ORing scheme was used for this project. An active diode ORing with a load-sharing indication and alarm relay was also used. Exhaustive FAT and SAT procedures were developed, and 100 percent loop testing and redundancy testing of controllers, power supplies, I/O modules, communication networks, and servers were performed. The team also performed 100 percent graphic testing and alarm simulation. All the closed loops were checked and 100 percent APC functioning and OPC communication was tested. During the SAT, the Profibus signature was taken for all the nodes and was preserved for future reference. Consequences and mitigation plan Following are the key risks involved in the project: Accurate as-built information unavailable Consequence: If the information available is not accurate, panel wiring and closed-loop operation in the field will be affected. Also, several instruments in the field may remain left out, affecting the complete plant operation and causing a delay in the startup of the plant. Mitigation plan: To provide an accurate project design basis, several walk-downs and manual surveys were performed to verify existing documentation was accurate. This activity was performed while the plant was running and did not affect the plant operation. The team took several photographs of the existing wiring in the panels, noted the color code of every field cable, noted every termination where they found a discrepancy with the existing drawing, and prepared a detailed file consisting of all the information collected. This file was the key to the successful implementation of this project.
  • 5. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com Manually converting the program to the new system Consequence: If the program built in the system is not accurate per the old program, it will affect the entire plant operation. The running process may trip many times, causing safety concerns in the plant and a financial loss. Mitigation plan: The only trusted document available for the programming was the existing program running in the old system. First, it was important to understand the difference between the logic block functions of the old system and that of the new system. The team listed the functional differences between the two, and modified the new blocks to function according to the old blocks. They decided to include the experts in the old system, from the vendor as well as the user side, in the engineering team of the new system. This was one of the crucial moves for ensuring a smooth upgrade. Several weeks were spent on this activity. Once the compatible logic blocks were built in the new system, a trial test was performed to check the operation of the blocks. On finding the operation satisfactory, clearance was given to the vendor to continue building the program. At this point, the team calculated the optimistic and the pessimistic time to complete the project execution, and all worked wholeheartedly to meet the deadline. Building visualization in the new system Consequence: If the conversion is not proper, plant operation will be affected, as operators will not be able to take quick actions when required. Because graphics are the main interface between the operation team and the new system, faults in the graphics will directly affect the operation team’s acceptance of the new system. Mitigation plan: The panel operators were used to the old visualization, so it was decided that the visualization in the system should be a look-alike of the old system, and the latest visualization features should not be used in this upgrade. This would help the operators accept the new system and also avoid confusion between actual problems in the field and improper mapping of tags in the graphics during the plant startup. Once the visualization was built in the new system, the engineering team performed a test. This test included verifying the sketches on the graphics and mapping tags to the graphic element, alarm window, trend window, group graphic windows, group trend window, and faceplate functioning. Once this test was approved, the vendor was permitted to build more graphics. Converting the PID tuning parameters A PID controller is a control-loop feedback mechanism commonly used in industrial control systems. A PID controller continuously calculates an “error value” as the difference between a measured process variable and a desired set point. The tuning parameter directly influences the accuracy of the control loop, and thereby the quality of the product. The value of these parameters can only be fixed during the running plant operation. These values are a critical asset for the plant, as they are fixed by the years of experience in operating the plant.
  • 6. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com Consequence: Steady-state operation of the plant will be affected, with a direct influence on the quality of the product. Mitigation plan: The vendor had developed a mathematical equation and a tool for converting the tuning parameters from the old system to the new system. The vendor had verified this tool at a different conversion project where the company was satisfied by the results of the conversion, and hence it was readily accepted in this project. Later the team found the results of this tool were quite accurate. Third-party communication Online analyzers, machine-condition monitoring systems, turbine-governing systems, antisurge systems, and plant emergency shutdown systems are standalone systems critical for plant operation. They maintain the quality of the product, control the safe operations of compressors, and maintain the efficiency of the compressors and safe operation of the plant. The readings of these systems must be continuously available for the operators. The communication between the DCS and these systems is done with a Modbus protocol, which is tricky and time consuming to configure. Consequence: This will have an impact during the plant startup when operators will not be able to see some data from the online analyzers, machine vibration conditions, and data from the emergency shutdown system of the plant. This will also affect the steady-state operation of the plant. Mitigation plan: It was possible to complete this activity during the preshutdown period of the project. The team arranged a spare controller and developed a test setup where the running third-party system communicated with the new system. All the wiring diagrams, communication settings, and response times were noted and later were directly implemented in the new system. This way it became quite easy to establish the communication with the actual new system. Removing old components and fitting new ones in the panel Consequence: If this activity is not completed in the planned time period, it will affect the entire startup of the plant. Mitigation plan: All the cables in the panels were not to be cut and removed immediately. Multicore cables from the field and power cables from the main control board cabinet were to be retained, so it was not easy to execute the system changeover during the shutdown period. To meet this challenge, several drawings were prepared for each panel indicating which cables and ducts were to be cut and removed and which cables were to be retained, where the ferrules were to be changed, where the lugs were to be replaced, and TBs were marked where there was interpanel wiring. Markings to distinguish between removal and retention were done in each panel. All the electricians were trained to thoroughly understand the drawing. To test the amount of time it would take to remove and fix the components in the panel, a mock operation was performed during the FAT. For this, a fully loaded spare panel was
  • 7. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com shifted from the site to the FAT area. During the mock operation, the team noted the time required, all the challenges faced, and the tools required, and they planned improvements. This activity helped a lot during the actual execution of replacing the components in each panel. Building secured network architecture Newer control systems are highly network based and use common standards for communication protocols. Many controllers are Internet Protocol addressable. Standard operating systems, such as Windows, are increasingly used in industrial control systems, which are now typically connected to remote controllers via private networks. The ability to access the system as a result of this interoperability exposes network assets to infiltration and subsequent manipulation of sensitive operations. Furthermore, increasingly sophisticated cyberattack tools can exploit vulnerabilities in commercial off-the-shelf system components, communication methods, and common operating systems found in modern control systems. Consequences: This affects the safety of the plant and can have a financial implication on failure. This may affect the entire business operation and can also have a social impact. Mitigation plan: Considering the current scenario around the world and the constant increase in the cyberthreat, the team decided on a secured network architecture with twin firewalls installed in the system. They preferred that the two firewalls were of different makes. This would help minimize any network-related threats. Antivirus software was installed in each system, making sure it was set to run the latest definition files. All the USB ports, CD/DVD drives, the autorun feature of Windows, the Windows scheduler, the remote desktop feature, and all the spare network ports were disabled. The auto log-off feature was enabled. These steps help prevent any virus attack on the system. APC implementation Consequences: Steady-state operation of the plant will be affected, minimizing the efficiency of the process and having a direct financial effect. Mitigation plan: APC implementation was a challenge in itself, because the new system did not have similar functionality to the old system. All the programing blocks of the old system were studied in detail, and blocks were developed in the system with the same functionality. APC will communicate with the new system via a dedicated OPC station. In the old system, the OPC wrote in a data block, but these data blocks were not available in the new system. To meet this requirement, thousands of tags were created, which will not use the license. The communication between the APC and these tags via OPC was tested during the FAT. All the programs for taking a loop in APC and removing a loop from APC were tested during the FAT period. The team performed 100 percent testing. Many data types required by APC that were supported by the old system and were not supported by the new system were found during the FAT. These data types were created in the new system and were mapped in the APC program. APC communication was established during the shutdown period, but the APC program in the APC controllers was modified in the post-shutdown period. Earlier, in
  • 8. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com the UNIX-based system, a separate PC provided operator interface to the APC. In the new system, a link to an Internet browser was provided for the operator to have the APC interface in the DCS screen itself, so a separate PC was not required. Once the plant was started, the APC program was tested for one of the furnaces, and in a week all the other APC programs were modified. Similar modifications were also done in a real-time optimizer and third-party historian. Technological improvements With this upgrade, we added some of modern automation’s state-of-the-art technology. Some of the noticeable improvements were: • Secured network: The new system network was based on the demilitarized zone (DMZ) architecture implemented using a twin firewall configuration. One firewall isolates the enterprise network from the plant network, and another firewall isolates the plant network from the control network, thereby creating a secured DMZ network. Both the firewalls are of a different make and can only be configured using a standalone configuration laptop. • Enhanced diagnostic features: Diagnostic logs are generated for each module, with master/slave in the hardware topology; they can be saved and analyzed for root-cause analysis and preventive maintenance. A Web-based diagnostic portal, where we can view warnings and controller errors, communication modules, and slave modules, is available in the system. • Smart client: This smart client is a true thin-client office workplace that seamlessly retrieves data from the system and connected third-party systems. The smart client is a dashboard visualization application that provides a read-only view into the system and allows the user to call up graphics. • Redundancy at the I/O level: For certain super-critical output tags that affect the production and safety of the entire plant, we have installed redundant analog output cards. During the normal course of operation, the cards share current demand from the field devices. Each card is capable of supplying the full demand current from the field devices. When one card fails, the other identifies the need of current in the circuit and supplies the full current. • Twin active diode-ORing scheme: Dual ORs with a load-sharing indicator are used in this project, which helps us monitor the load sharing between the two power supplies. This gives us an opportunity to identify a probable failure. Along with a redundant power supply, we have also installed a redundant diode ORing. Results Proper planning and coordination with the vendor resulted in an efficient installation and commissioning of the new system. All the 14,000 I/O, marshalling panels, system panels, alarm consoles, servers, and operator stations were successfully replaced in a very limited time. It is a success story for the entire team; we completed the project well within the planned period. The project can be summarized with the statement: more stress on planning reduces stress during execution.
  • 9. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com Article Source: This guest blog post was written by Sunny R. Desai, an engineer in the DCS/PLC/SCADA department at Reliance Industries Ltd. A version of this article originally was published at InTech magazine. iFluids Engineering ICS / DCS / SCADA Engineering Design, Procurement, Integration, Testing, Commissioning & Troubleshooting Services
  • 10. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com Cyber Security Services Provided by iFluids Engineering < To know more send email to john@ifluids.com> •IT Security Awareness •ISO 27001 Introduction & ISMS Primer •Essentials of ICS Engineering •Essentials of SIS and Safety Life Cycle
  • 11. Contact john@ifluids.com (or) info@ifluids.com Contact john@ifluids.com (or) info@ifluids.com , www.ifluids.com •ICS Security and Network Management •Identity and Access Management For more information regarding iFluids Engineering Services & Past Project Track Record please visit here Disclaimer: All information and content contained in this website are provided solely for general information and reference purposes. TM information, Images & any copyrighted material inadvertently published or depicted belong to rightfull owner and iFluids doesnt claim to be its own.