SlideShare a Scribd company logo
1 of 10
SHADAB HAIDER
Mobile : +91-9582412505 E-Mail :
shadabhaider786@gmail.com
Passport no. : H1791262 Validity : 28/11/2008 to
27/11/2018
Seeking Assignments in QA/QC , Project Site , Piping Welding/Fabrication ,
Inspection Expediting , Project Planning Management with a high growth
oriented organization
Preferred Location: Anywhere in India/Abroad
PROFESSIONAL PROFILE
 A competent QA/QC Oil & Gas professional with NDT Level III certification and over 8
years of cross cultural experience in the areas of QA/QC , Project Site , Piping
Welding/Fabrication , Inspection Expediting , Project Planning Management.
 Presently performing QA/QC Inspection & Expediting on behalf of “Mitsubishi Heavy
Industries Compressor, Japan for their RAPID Project, Malaysia at M/s Enpro,
Industries, Pune
 Worked in Dubai as QA/QC Project Engineer on M/s ENOC , Dubai, LLC shut down
project .
 Excellent project management ability to network with project members, consultants,
contractors, statutory agencies and customer with consummate ease.
ACADEMIA
B.Tech in Mechanical Engineering (2008) from MORADABAD INSTITUTE OF
TECHNOLOGY, MORADABADB. U.P India
PROFESSIONAL CERTIFICATION
ASNT NDT Level-III in RT, UT , PT & MT Certificate no. 224854
STANDARD AWARENESS
 Have exposure of ASME B & PV Codes, ASTM, ASME, API, BS, API, ISO, IS , IBR ,
Saudi Aramco , Gasco , Shell, EIL and other International Standards.
ORGANIZATIONAL EXPERIENCE
Company : M/s TUV-Sud , Quality Austria , RINA , Intertek , RMZ .
Role : Third Party QA/QC Inspection & Expediting
Period : From Feb 2011 to Feb 2012
Company : M/s Sravanthi Infratech Pvt. Ltd.
Role : Quality Inspection/Expediting
Period : From Feb 2011 to Feb 2012
Company : M/s Advance Valves Pvt. Ltd.
Role : Quality Inspection/Expediting
Period : From August 2008 to Nov 2010.
KEY DELIVERABLES
QC INSPECTED ITEMS
SHADAB HAIDER
 Inspection of Equipments for Oil & Gas Onshore & Offshore installation like Tanks,
pressure vessels, Heat Exchangers,Oil storage tank , Lube Oil Skids , Fuel Gas Skids ,
Boiler , Cross country pipelines, City Gas pipeline, line pipes, pipe fittings, Motors,
Horizontal Suction and Conveying Centrifugal Pumps, compressors, plates ,fabricated
Process and Power Piping, Valves, Control Valves, Pipes & Fittings, Structural Steel,
Charge Heater - Convection Module, Radiant Coils, Cross over coils , Air cooled
condenser , Fin Fan Cooler
 Lube Oil Skid inspection as per API 614 Standard
 Process & Power piping QA/QC inspection as per API , ASME & IBR Standards
 Pressure Vessels and Storage Tanks inspections as per API 510 and API 653 etc.
 Witnessing factory acceptance test of various equipment for assuring efficient
performance.
 Performing various pressure tests for pressure vessels like hydro test, air test, under
water air test and oil test as well as site inspection of vendors and customers.
 Expert on performing the Prototype and Certification Testing of equipments as per
ISO, BS and API as UL Testing, Fire Testing, Cryogenic Tests, Vacuum Test etc.
 Hands on experience in instruments like, gauges as well as digital instruments such as
vernier calliper, screw gauge, inside micro meter, digital anemometer, ferrite meter,
vibration meter, sound level meter, hardness tester, ultra sound thickness gauge, go
no go gauges, plug gauges, groove gauge, sprit level dial indicators, filler gauges and
positive material identification (PMI) machine, MPI Machine.
 Sand blasting inspection using profile meter or comparator and painting inspection
using digital coating meter.
QC PIPING , TANKS , VALVES AND OTHER ITEMS HYDRO INSPECTION
 Ensure that Pressure source and test gauge are upstream side.
 Ensure that test blinds installed are the correct thickness. Ensure that all items such
as control valves, relief valves, rupture disks, orifice plates, diaphragm instruments,
expansion joints, etc., which could be damaged during pressure test have been
removed or isolated, as indicated on the pressure test flow diagram.
 Ensure that equipment, such as filters, which have internals that may be damaged
during the pressure test are either blocked from test or that internals have been
removed
 Check all temporary supports that have been called for on the pressure test flow
diagrams, piping arrangement drawings or spool drawing to ensure that they have
been properly installed
 Ensure that equipment, such as compressors, which must not be included in the field
tests have been properly blocked off with the casing drain open
 Check open and closed position of all valves
 Check for proper installation of vents and drains
 Verify chloride content of test water when testing stainless steels
QC WELDING & NDT INSPECTION
 Verifying welding machine to ensure all equipment meet job requirement
specifications.
 Elaborating and coordinating the welding specifications, and codes/standards
 Coordination with the field subcontractors for all welding procedure specifications and
procedures qualifications reports
 Review course and effects of welding defects and take remedial actions
 Coordination with the field subcontractors and the Third Party NDT Inspection
Company
 Review of the radiographic film and all NDT reports
 Auditing of the approved Third Party NDT Inspection Company
 Reviewing the inspection and testing methods and procedures for Radiographic, Dye
Penetrant, Magnetic Particle, and Ultrasonic inspections
SHADAB HAIDER
 Witnessing of welder qualifications testing and procedures qualification testing
 Witnessing any remedial repair welding
 Reviewing of the welding summery reports
 Checking the hydrostatic test packages for NDT compliance prior to testing
 Advising the site subcontractors with regards to welding and testing
 Monitor any Post Weld Heat Treatment on site and review the completed test reporting
 Selection of welds for non destructive testing
 Recording and listing of defective welds
 Monitor the control and issue of welding electrodes
 Control the QC site welding inspectors
 Actively monitor site radiation safety
 Coordinate the issue of non-conformance reports through the site QC manager
 Compete site quality instructions to sub contractors when required
 Ensuring welding sequence as per appropriate welding procedure requirements and
also maintaining welding variables.
 Carrying out visual inspection of welds for attaining flaw less welding operation.
 Handling diverse drawings for various jobs like tube bundles, structural items, setting
plans, shells, storage tanks, etc.
 Involved in post weld heat treatment of pressure vessels (normalizing) and carrying
out final inspection before dispatch.
 Conducting welding witness procedure qualification test; monitoring welder
performance and conducting visual inspection of welds and repairs of welds in
accordance with company procedure and international codes of practice
QA MANGEMENT
 Preparation of Inspection check list in line with P.O, Data sheet , Drawings ,
specifications requirement for smooth operation of inspection & expediting
 Review of Inspection and Test Plans ( ITPs ) to verify that Contractor is performing all
required inspections and witnessing all required tests .
 Review and approval on welding documents WPS/PQR/WPQ, Heart Treatment, NDE
procedures, Hydro/Pneumatic test procedures etc.
 Witness of Inspection & testing activities at manufacturing units as per Inspection Test
plans
 Preparation of Inspection Visit reports for the inspections.
 Review of Supplier documents/MTC’s , Hydro/Pneumatic test reports , NDT reports ,
Visual dimensional reports etc. and issue of IRN's
 Responsible for Inspection , Planning and Monitoring of all Third Party Inspectors
inspection activities of all disciplines of Project .
 Coordination with Engineering team to sort out any Quality issues/Deviations
 Compiling of Manufacturers’ Data Report (Final Quality Documents) in line with project
requirement & submission to Client.
 Preparation of Monthly Inspection progress Reports.
 Evaluation & Qualification Audits of new suppliers for Vendor development
 Coordination with Third Party Inspection agencies for arranging inspections at supplier
works.
 Review of TPI inspection reports , IRNs and issue of MDCC based on the same
 Ensuring all delivery consignments are inspected prior to release for shipment.
 Expediting of manufacturing progress & follow up with suppliers to meet the delivery
within Contractual delivery.
 Issuing of dispatch instructions & coordinating for dispatch of consignments with
suppliers.
 Ensuring that the Third Party Inspections are carried out in accordance with the
marked up Inspections stipulated in the Inspection and Test plans as Witness and
Hold Points.
 Monitoring ‘RFI’ (Request For Inspection) Register, and directing TPI Inspectors for the
relevant Inspection activities at site. Preparing Weekly RFI Status.
 The preparation of the companies QA manual control and supervision of all
amendments and revisions
SHADAB HAIDER
 Control and the distribution of all the companies quality documentation
 Monitor all quality related activities on the project
 Perform all internal and external audits on behalf of the companies management
 Verify contractor quality requirements are specified to vendors and contractor
documentation submittals.
 Attend all pre-bid meetings and coordinate all project requirements with the project
bidders.
 Attend client quality management meetings
 The preparation and control of project quality system management documentation
prior to project commencement.
 Review quality inspection personnel qualifications and training requirements
 Monitor the disposition of all issued nonconformance reports.
 Monitor the progress and effectiveness of the project quality management system.
Recommend and implement improvements when required.
 Coordinate all QA/QC activities with the site QC manager
 Coordinate all QA/QC activities with the site QA/QC procurement manager
 Coordinate all quality related correspondence with the customers representatives.
 Monitor statistical method reporting.
 Action and close all customer complaints
 Control all achieve documentation upon the completion of the project.
 Quality Assurance and Quality Control in Mechanical Plants and on projects.
 Quality Management Systems based on ISO 9001:2008,
 My expertise had been to Develop, Update, Implement, monitor and maintain and
Audit Quality Management systems based on these standards
 Second Party Audits: Vendor Quality and Technical assessment, Surveillance audits
and Capability Surveys
 Environmental Controls & HSE Regulations
 Corrective and Preventive Actions
 NCR resolution and Root Cause Analysis
SITE QA/QC
 Witnessing and sentencing of all site inspections within their disciplines
 Coordinate all site inspections with the site subcontractors
 Ensure that all inspection reports are accurate and that all attached documents are
current status
 Ensure all work is correctly prepared prior to any inspection being undertaken
 Review all inspection reports for compliance
 Assist the site QC manager in the organisation, maintenance and control of the quality
system
 Liase with the site construction engineers and provide assistance when requested
 Prepare nonconformance reports to the QA manager and assist in developing
corrective actions
 Assist the QC manager and construction manager in resolving any discrepancies and
ambiguities
 Coordinate with the customers QC inspectors for the resolution of site problems
 Coordinate with the site subcontractors to ensure that communications exist and are
maintained
 Assist the site subcontractors in the resolution of drawing interpretation
 Attend the weekly QC meetings
 Review work procedures and method statements for compliance with good work
practices and the customers contract specializations
 The issuance of non-conformance reports in conjunction with the site QC manager
 The completion of QC site instructions and coordinate their closure The review of
inspection test packages during the course of construction activities
 Compliance with the site's health and safety regulations
EXPEDITING
 Handled complete inspection/expediting activities of a project for Mechanical, Electrical
SHADAB HAIDER
& Instrumentation items.
 Coordination with Engineering, Project, Purchase , Commercial ,Finance , Logistic
teams for smooth execution of Project .
 Attending Kick off meeting pre inspection meeting (PIM) at suppliers works prior
manufacturing
 Preparation of Inspection check list in line with P.O , Data sheet , Drawings ,
specifications requirement for smooth operation of inspection & expediting .
 Seek Order acknowledgements and update promise dates from suppliers
 Regularly review pending orders with suppliers and identify critical exceptions for
buyer to ensure On Time Delivery
 Co-ordinate with all internal customers to ensure that client requirements are met
 Implement checklists for suppliers to ensure that proper documentation is enclosed by
suppliers to meet local regulations and company requirements
 Clearing Supplier invoices to ensure that queries, if any are resolved by concerned
buyers
 Expedite In-House activities to ensure shortest turnaround time for our clients
 Support of data integrity in systems and documentation, including creating part
numbers, BOMs, pick lists, allocation of parts, inventory transfers
AUDITING
 Assisting the Asset Integrity Assurance Manager by acting as audit leader of assigned
audits (the audit leader will preferably be assigned to audits of his own technical
expertise)
 Managing exercises and audits to ensure the necessary strategies and controls are
demonstrably in place to assure the integrity of the assets in all phases of the project
lifecycle
 Contributing to the assurance that the facilities under development by the Company
are designed and built in such a way that integrity (and hence safety and economic
performance) can be maintained during all phases of the lifecycle
 Contributing to the preparation of look ahead plans for audits to be held
 Managing external resources in the execution of audits
 Coordinating with other auditing teams to prevent unnecessary disturbance of running
projects
 Reviewing agendas and terms of reference to ensure clarity of purpose
 Preparing external parties of the auditing team for the audit
 Compiling and issuing report and support interpretation of its contents; follow-up and
monitor closure of actions
 Coordinating reporting of external parties
OIL & GAS ELECTRO MECHANICAL PROJECT ITEMS QC INSPECTION &
EXPEDITING
 Item : GAS PRCS Supplier M/s Gas Flow Solution
Belgium
 Item : Level Transmitters Supplier M/s Magnetrol
Belgium
 Item : Valves Supplier M/s Boteli & M/s Oviko
China
 Item : Gas detector Supplier M/s Oldham
Belgium
 Item : ESDV Supplier M/s Ace Valves
Korea
 Item : Level Gauges Supplier M/s Samil
Korea
 Item : Burner Supplier M/s Reillo
Italy
 Item : Ultrasonic Flow Mtr Supplier M/s Emerson USA
 Item : GC Supplier M/s Emerson USA
 Item : Flow Computer Supplier M/s Apex
SHADAB HAIDER
Ahmedbd
 Item : PRCS Supplier M/s Nirmal Controls
Mumbai
 Item : Valves Supplier M/s Sakhi
Mumbai
 Item : DPT PT TT Supplier M/s Emerson
Mumbai
 Item : UPS System Supplier M/s Hitachi
Gndhngr
 Item : Burner Blower Supplier M/s Suntec
Ahmedbd
 Item : PSVs Supplier M/s Leser & Faiger
Aurngbd
 Item : PSVs Supplier M/s Bliss Anand
Rewari
 Item : PSVs Supplier M/s Tyco Valves
Delhi
 Item : MCC & PLC Panels Supplier M/s ATC
Noida
 Item : Cables Supplier M/s KEI
Bhiwadi
 Item : Junction Box Supplier M/s R. Stahl
Chennai
 Item : Heater Supplier M/s Sandvik
Hosur
 Item : Heater Panel Supplier M/s Sandvik
Hosur
 Item : RTDs , PGs & TGs Supplier M/s Wika
Pune
 Item : Pumps Supplier M/s KSB
Nasik
 Item : Transformers Supplier M/s Kirloskar
Mysore
 Item : Convection Module , Supplier M/s Technip KT India Ltd.
Delhi
Radiant Coils, Cross over coils Supplier M/s Technip KT India Ltd.
Delhi
Fuel Gas & Preparation Skid Supplier M/s Technip KT India Ltd.
Delhi
 Item : Valves Supplier M/s Fluidline Valves Pvt Ltd.
Ahmedbd
 Item : Valves Supplier M/s Hawa Valves
Mumbai
 Item : Valves Supplier M/s Advance Valves Pvt Ltd.
Noida
 Item : Pumps Supplier M/s WPIL
Ghaziabd
 Item : Lube Oil Skid Supplier M/s Enpro
Pune
 Item : API Tanks – API Supplier M/s Fabtec h Projects
Paradeep
 Item : Pressure Chambers Supplier M/s Micro precision
Faridabd
 Item : PEB Supplier M/s PEBS Pennar
Hyrdbd
 Item : PHE , Pumps etc Supplier M/s Frick India
Faridabd
 Item : HVAC system Supplier M/s Wolaque
SHADAB HAIDER
Delhi
 Item : Air Dryer, Comprssr Supplier M/s Atlas Copco
Pune
 Item : Filter , Reciever Supplier M/s Atlas Copco
Pune
 Item : PRS , Pumps Supplier M/s Spirax Marshall
Delhi
 Item : Flash Vessels Supplier M/s Spirax Marshall
Delhi
 Item : Magnetic Filters Supplier M/s Acme
Ahmedbd
 Item : ETP STP Supplier M/s Brisanzia
Delhi
 Item : Pumps Supplier M/s Stephenson
Mumbai
 Item : SS Storage Tanks Supplier M/s RD Engineering
Aurngbd
 Item : Pasteurizer Supplier M/s Axtel
Vadodara
 Item : Dry Batch Hopper Supplier M/s Axtel
Vadodara
 Item : Wet Mixing Tank Supplier M/s Axtel
Vadodara
 Item : Rework Hopper Supplier M/s Axtel
Vadodara
 Item : PSM Supplier M/s Axtel
Vadodara
 Item : Magma Holding Tank Supplier M/s Axtel
Vadodara
 Item : 3 Valves Supplier M/s Inoxpa
Pune
 Item : ClP System Supplier M/s Uncorn
Hyderbd
 Item : Pumps Supplier M/s Mather & Platt
Pune
 Item : Pumps Supplier M/s Syntex Pumps
Ghaziabd
 Item : EOT crane Supplier M/s Electro Mech
Pune
 Item : DM Plant package Supplier M/s GET water solution
Chennai
 Item : Fuel gas skid Supplier M/s Indicone Boilers
Faridabd
 Item : Fire fitting package Supplier M/s Agnice Fire Protection
Chennai
 Item : PRS/PRDS System Supplier M/s Circor Flow Technologies
Ahmdbd
PROJECTS & CLIENTS SERVED
 Project: NSRP Complex Project
 Client: Technip KT India Ltd.
 Project: 450 MW Combined Cycle Gas Power Plant
 Client: Sravathi Infratech Pvt Ltd.
 Project: Central UP Gas Limited (City Gas Distribution Line Project, Bareilly)
 Client: Avinash EM Projects Pvt. Ltd.
SHADAB HAIDER
 Project: Grain LNG RTLF Project
 Client: (CB&I)
 Project: XML Mariner Ethane / Propane Facility U.S.A.
 Client: Chicago Bridge & Iron (CB&I)
 Project: Jubail Export Refinery (SATORP / JERP Package – 5B)
 Client: Rotary Engg. Ltd.
 Project: Jubail Export Refinery (SATORP / JERP Package – 5B)
 Client: SK Engg. & Construction
 Project: Jubail Export Refinery (SATORP / JERP Package – 5C)
 Client: M. R. Al Khathalan for Contracting
 Project: Wasea Bulk Plant Project (BI # 10-00795)
 Client: Sinopac International Petroleum Service Co.
 Project: Mitsubishi Hitachi Power System
 Client: Mitsubishi Heavy Industries Corporation
 Project: Shell Tabangao Asset Renewal Tabangao Refinery for Euro IV Compliance
[STARTREC], Philippines
 Client: Chiyoda Philippines Corporation / Shell Projects and Technology
 Project: Mitsubishi Hitachi Power System Laboratory
 Client: Mitsubishi Hitachi Power System Laboratory
 Project: City Gas Distribution Project , Bareilly
 Client: Central UP Gas Limited (CUGL) a JV of BPCL & GAIL India.
 Project: Paradeep Phosphates Limited.
 Client: Simon India , Delhi
 Project: Paradip BOOT EPC
 Client: IOT Infrastructure & Energy Services Ltd.
 Project: Lin Kou Power Plant Renewal Project Taiwan
 Client: Mitsubishi Hitachi Power System

 Project: Rabigh IWSSP Project Saudi Arabia
 Client: Mitsubishi Hitachi Power System
 Project: ESSO PNG LNG EPC4 – 594153517
 Client: CB&I and Clough Joint Venture U.K.
 Project: Aravali Project , Cadbury Bournvita Making Plant , Dharuhera Rewari
 Client: A Joint Venture Between Cadbury India & Barmalt Gurgaon
PERSONAL DETAILS
Permanent Address : Vill- Chhajupura Sadat , Post-Amhera , District-Bijnor ,
U.P , India , 246726
Date of Birth : 10 Sep, 1986
Languages Known : English and Hindi
SHADAB HAIDER
I hereby undertake that the above mentioned information is correct & to the best of my
knowledge.
Shadab Haider
SHADAB HAIDER
I hereby undertake that the above mentioned information is correct & to the best of my
knowledge.
Shadab Haider

More Related Content

What's hot (19)

RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTOR
 
Swarup cv 3 (1)
Swarup cv 3 (1)Swarup cv 3 (1)
Swarup cv 3 (1)
 
Muhammad Imran QAQC (Welding Inspector)CSWIP
Muhammad Imran QAQC (Welding Inspector)CSWIPMuhammad Imran QAQC (Welding Inspector)CSWIP
Muhammad Imran QAQC (Welding Inspector)CSWIP
 
sonu jaiswal resume 17.02.2017
sonu jaiswal resume  17.02.2017sonu jaiswal resume  17.02.2017
sonu jaiswal resume 17.02.2017
 
Resume Abdulbari
Resume   AbdulbariResume   Abdulbari
Resume Abdulbari
 
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLC
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLCUpdated-Mohammed Khursheed -CV -Alam, VELOSI LLC
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLC
 
jaynt singh (CV) (5)
jaynt singh (CV) (5)jaynt singh (CV) (5)
jaynt singh (CV) (5)
 
C.V
C.VC.V
C.V
 
AMJResume.doc
AMJResume.docAMJResume.doc
AMJResume.doc
 
Cv for welding inspector ud 08.05.14
Cv for welding inspector ud 08.05.14Cv for welding inspector ud 08.05.14
Cv for welding inspector ud 08.05.14
 
Linsin CV
Linsin CVLinsin CV
Linsin CV
 
Amar Resume
Amar ResumeAmar Resume
Amar Resume
 
Ganesan Plant Inspector_CV
Ganesan Plant Inspector_CVGanesan Plant Inspector_CV
Ganesan Plant Inspector_CV
 
Balaji CV - 2015
Balaji CV - 2015Balaji CV - 2015
Balaji CV - 2015
 
Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1
 
Ganesan Selvakumar CV 151116_M+W
Ganesan Selvakumar CV 151116_M+WGanesan Selvakumar CV 151116_M+W
Ganesan Selvakumar CV 151116_M+W
 
SUMER_MECH_Er
SUMER_MECH_ErSUMER_MECH_Er
SUMER_MECH_Er
 
JIMJITH QC INSPECTOR
JIMJITH QC INSPECTORJIMJITH QC INSPECTOR
JIMJITH QC INSPECTOR
 
Welding Inspector - QC Inspector
Welding Inspector - QC InspectorWelding Inspector - QC Inspector
Welding Inspector - QC Inspector
 

Similar to Seeking Assignments in QA/QC , Project Site , Piping Welding/Fabrication , Inspection Expediting , Project Planning Management with a high growth oriented organization

Similar to Seeking Assignments in QA/QC , Project Site , Piping Welding/Fabrication , Inspection Expediting , Project Planning Management with a high growth oriented organization (20)

QC WELDING INSPECTOR
QC WELDING INSPECTORQC WELDING INSPECTOR
QC WELDING INSPECTOR
 
YOGARAJ CV
YOGARAJ CVYOGARAJ CV
YOGARAJ CV
 
RESUME QA QC ENGG
RESUME  QA  QC ENGGRESUME  QA  QC ENGG
RESUME QA QC ENGG
 
QA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEERQA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEER
 
CV-Kiran-Sr QAQC NOV2016
CV-Kiran-Sr QAQC NOV2016CV-Kiran-Sr QAQC NOV2016
CV-Kiran-Sr QAQC NOV2016
 
Inspection Engineer 1
Inspection Engineer 1Inspection Engineer 1
Inspection Engineer 1
 
PRAGASH-QC INSPECTION ENGG Feb'2016
PRAGASH-QC INSPECTION ENGG Feb'2016PRAGASH-QC INSPECTION ENGG Feb'2016
PRAGASH-QC INSPECTION ENGG Feb'2016
 
RAJU CV
RAJU  CVRAJU  CV
RAJU CV
 
Curriculum VITA 2 COMPLETE PIPING
Curriculum VITA 2 COMPLETE PIPINGCurriculum VITA 2 COMPLETE PIPING
Curriculum VITA 2 COMPLETE PIPING
 
Multidispline Inspector - DEEPAK Rai
Multidispline Inspector - DEEPAK RaiMultidispline Inspector - DEEPAK Rai
Multidispline Inspector - DEEPAK Rai
 
Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3
 
Prem's Resume
Prem's  ResumePrem's  Resume
Prem's Resume
 
Resume moloy
Resume moloyResume moloy
Resume moloy
 
Tahir CV
Tahir CVTahir CV
Tahir CV
 
Tahir CV
Tahir CVTahir CV
Tahir CV
 
Kailash cv
Kailash cvKailash cv
Kailash cv
 
Jaynt singh (cv) (1)
Jaynt singh (cv) (1)Jaynt singh (cv) (1)
Jaynt singh (cv) (1)
 
Jaynt singh (cv) (1)
Jaynt singh (cv) (1)Jaynt singh (cv) (1)
Jaynt singh (cv) (1)
 
Rajan Inspection Er.
Rajan Inspection Er.Rajan Inspection Er.
Rajan Inspection Er.
 
QA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrenceQA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrence
 

Seeking Assignments in QA/QC , Project Site , Piping Welding/Fabrication , Inspection Expediting , Project Planning Management with a high growth oriented organization

  • 1. SHADAB HAIDER Mobile : +91-9582412505 E-Mail : shadabhaider786@gmail.com Passport no. : H1791262 Validity : 28/11/2008 to 27/11/2018 Seeking Assignments in QA/QC , Project Site , Piping Welding/Fabrication , Inspection Expediting , Project Planning Management with a high growth oriented organization Preferred Location: Anywhere in India/Abroad PROFESSIONAL PROFILE  A competent QA/QC Oil & Gas professional with NDT Level III certification and over 8 years of cross cultural experience in the areas of QA/QC , Project Site , Piping Welding/Fabrication , Inspection Expediting , Project Planning Management.  Presently performing QA/QC Inspection & Expediting on behalf of “Mitsubishi Heavy Industries Compressor, Japan for their RAPID Project, Malaysia at M/s Enpro, Industries, Pune  Worked in Dubai as QA/QC Project Engineer on M/s ENOC , Dubai, LLC shut down project .  Excellent project management ability to network with project members, consultants, contractors, statutory agencies and customer with consummate ease. ACADEMIA B.Tech in Mechanical Engineering (2008) from MORADABAD INSTITUTE OF TECHNOLOGY, MORADABADB. U.P India PROFESSIONAL CERTIFICATION ASNT NDT Level-III in RT, UT , PT & MT Certificate no. 224854 STANDARD AWARENESS  Have exposure of ASME B & PV Codes, ASTM, ASME, API, BS, API, ISO, IS , IBR , Saudi Aramco , Gasco , Shell, EIL and other International Standards. ORGANIZATIONAL EXPERIENCE Company : M/s TUV-Sud , Quality Austria , RINA , Intertek , RMZ . Role : Third Party QA/QC Inspection & Expediting Period : From Feb 2011 to Feb 2012 Company : M/s Sravanthi Infratech Pvt. Ltd. Role : Quality Inspection/Expediting Period : From Feb 2011 to Feb 2012 Company : M/s Advance Valves Pvt. Ltd. Role : Quality Inspection/Expediting Period : From August 2008 to Nov 2010. KEY DELIVERABLES QC INSPECTED ITEMS
  • 2. SHADAB HAIDER  Inspection of Equipments for Oil & Gas Onshore & Offshore installation like Tanks, pressure vessels, Heat Exchangers,Oil storage tank , Lube Oil Skids , Fuel Gas Skids , Boiler , Cross country pipelines, City Gas pipeline, line pipes, pipe fittings, Motors, Horizontal Suction and Conveying Centrifugal Pumps, compressors, plates ,fabricated Process and Power Piping, Valves, Control Valves, Pipes & Fittings, Structural Steel, Charge Heater - Convection Module, Radiant Coils, Cross over coils , Air cooled condenser , Fin Fan Cooler  Lube Oil Skid inspection as per API 614 Standard  Process & Power piping QA/QC inspection as per API , ASME & IBR Standards  Pressure Vessels and Storage Tanks inspections as per API 510 and API 653 etc.  Witnessing factory acceptance test of various equipment for assuring efficient performance.  Performing various pressure tests for pressure vessels like hydro test, air test, under water air test and oil test as well as site inspection of vendors and customers.  Expert on performing the Prototype and Certification Testing of equipments as per ISO, BS and API as UL Testing, Fire Testing, Cryogenic Tests, Vacuum Test etc.  Hands on experience in instruments like, gauges as well as digital instruments such as vernier calliper, screw gauge, inside micro meter, digital anemometer, ferrite meter, vibration meter, sound level meter, hardness tester, ultra sound thickness gauge, go no go gauges, plug gauges, groove gauge, sprit level dial indicators, filler gauges and positive material identification (PMI) machine, MPI Machine.  Sand blasting inspection using profile meter or comparator and painting inspection using digital coating meter. QC PIPING , TANKS , VALVES AND OTHER ITEMS HYDRO INSPECTION  Ensure that Pressure source and test gauge are upstream side.  Ensure that test blinds installed are the correct thickness. Ensure that all items such as control valves, relief valves, rupture disks, orifice plates, diaphragm instruments, expansion joints, etc., which could be damaged during pressure test have been removed or isolated, as indicated on the pressure test flow diagram.  Ensure that equipment, such as filters, which have internals that may be damaged during the pressure test are either blocked from test or that internals have been removed  Check all temporary supports that have been called for on the pressure test flow diagrams, piping arrangement drawings or spool drawing to ensure that they have been properly installed  Ensure that equipment, such as compressors, which must not be included in the field tests have been properly blocked off with the casing drain open  Check open and closed position of all valves  Check for proper installation of vents and drains  Verify chloride content of test water when testing stainless steels QC WELDING & NDT INSPECTION  Verifying welding machine to ensure all equipment meet job requirement specifications.  Elaborating and coordinating the welding specifications, and codes/standards  Coordination with the field subcontractors for all welding procedure specifications and procedures qualifications reports  Review course and effects of welding defects and take remedial actions  Coordination with the field subcontractors and the Third Party NDT Inspection Company  Review of the radiographic film and all NDT reports  Auditing of the approved Third Party NDT Inspection Company  Reviewing the inspection and testing methods and procedures for Radiographic, Dye Penetrant, Magnetic Particle, and Ultrasonic inspections
  • 3. SHADAB HAIDER  Witnessing of welder qualifications testing and procedures qualification testing  Witnessing any remedial repair welding  Reviewing of the welding summery reports  Checking the hydrostatic test packages for NDT compliance prior to testing  Advising the site subcontractors with regards to welding and testing  Monitor any Post Weld Heat Treatment on site and review the completed test reporting  Selection of welds for non destructive testing  Recording and listing of defective welds  Monitor the control and issue of welding electrodes  Control the QC site welding inspectors  Actively monitor site radiation safety  Coordinate the issue of non-conformance reports through the site QC manager  Compete site quality instructions to sub contractors when required  Ensuring welding sequence as per appropriate welding procedure requirements and also maintaining welding variables.  Carrying out visual inspection of welds for attaining flaw less welding operation.  Handling diverse drawings for various jobs like tube bundles, structural items, setting plans, shells, storage tanks, etc.  Involved in post weld heat treatment of pressure vessels (normalizing) and carrying out final inspection before dispatch.  Conducting welding witness procedure qualification test; monitoring welder performance and conducting visual inspection of welds and repairs of welds in accordance with company procedure and international codes of practice QA MANGEMENT  Preparation of Inspection check list in line with P.O, Data sheet , Drawings , specifications requirement for smooth operation of inspection & expediting  Review of Inspection and Test Plans ( ITPs ) to verify that Contractor is performing all required inspections and witnessing all required tests .  Review and approval on welding documents WPS/PQR/WPQ, Heart Treatment, NDE procedures, Hydro/Pneumatic test procedures etc.  Witness of Inspection & testing activities at manufacturing units as per Inspection Test plans  Preparation of Inspection Visit reports for the inspections.  Review of Supplier documents/MTC’s , Hydro/Pneumatic test reports , NDT reports , Visual dimensional reports etc. and issue of IRN's  Responsible for Inspection , Planning and Monitoring of all Third Party Inspectors inspection activities of all disciplines of Project .  Coordination with Engineering team to sort out any Quality issues/Deviations  Compiling of Manufacturers’ Data Report (Final Quality Documents) in line with project requirement & submission to Client.  Preparation of Monthly Inspection progress Reports.  Evaluation & Qualification Audits of new suppliers for Vendor development  Coordination with Third Party Inspection agencies for arranging inspections at supplier works.  Review of TPI inspection reports , IRNs and issue of MDCC based on the same  Ensuring all delivery consignments are inspected prior to release for shipment.  Expediting of manufacturing progress & follow up with suppliers to meet the delivery within Contractual delivery.  Issuing of dispatch instructions & coordinating for dispatch of consignments with suppliers.  Ensuring that the Third Party Inspections are carried out in accordance with the marked up Inspections stipulated in the Inspection and Test plans as Witness and Hold Points.  Monitoring ‘RFI’ (Request For Inspection) Register, and directing TPI Inspectors for the relevant Inspection activities at site. Preparing Weekly RFI Status.  The preparation of the companies QA manual control and supervision of all amendments and revisions
  • 4. SHADAB HAIDER  Control and the distribution of all the companies quality documentation  Monitor all quality related activities on the project  Perform all internal and external audits on behalf of the companies management  Verify contractor quality requirements are specified to vendors and contractor documentation submittals.  Attend all pre-bid meetings and coordinate all project requirements with the project bidders.  Attend client quality management meetings  The preparation and control of project quality system management documentation prior to project commencement.  Review quality inspection personnel qualifications and training requirements  Monitor the disposition of all issued nonconformance reports.  Monitor the progress and effectiveness of the project quality management system. Recommend and implement improvements when required.  Coordinate all QA/QC activities with the site QC manager  Coordinate all QA/QC activities with the site QA/QC procurement manager  Coordinate all quality related correspondence with the customers representatives.  Monitor statistical method reporting.  Action and close all customer complaints  Control all achieve documentation upon the completion of the project.  Quality Assurance and Quality Control in Mechanical Plants and on projects.  Quality Management Systems based on ISO 9001:2008,  My expertise had been to Develop, Update, Implement, monitor and maintain and Audit Quality Management systems based on these standards  Second Party Audits: Vendor Quality and Technical assessment, Surveillance audits and Capability Surveys  Environmental Controls & HSE Regulations  Corrective and Preventive Actions  NCR resolution and Root Cause Analysis SITE QA/QC  Witnessing and sentencing of all site inspections within their disciplines  Coordinate all site inspections with the site subcontractors  Ensure that all inspection reports are accurate and that all attached documents are current status  Ensure all work is correctly prepared prior to any inspection being undertaken  Review all inspection reports for compliance  Assist the site QC manager in the organisation, maintenance and control of the quality system  Liase with the site construction engineers and provide assistance when requested  Prepare nonconformance reports to the QA manager and assist in developing corrective actions  Assist the QC manager and construction manager in resolving any discrepancies and ambiguities  Coordinate with the customers QC inspectors for the resolution of site problems  Coordinate with the site subcontractors to ensure that communications exist and are maintained  Assist the site subcontractors in the resolution of drawing interpretation  Attend the weekly QC meetings  Review work procedures and method statements for compliance with good work practices and the customers contract specializations  The issuance of non-conformance reports in conjunction with the site QC manager  The completion of QC site instructions and coordinate their closure The review of inspection test packages during the course of construction activities  Compliance with the site's health and safety regulations EXPEDITING  Handled complete inspection/expediting activities of a project for Mechanical, Electrical
  • 5. SHADAB HAIDER & Instrumentation items.  Coordination with Engineering, Project, Purchase , Commercial ,Finance , Logistic teams for smooth execution of Project .  Attending Kick off meeting pre inspection meeting (PIM) at suppliers works prior manufacturing  Preparation of Inspection check list in line with P.O , Data sheet , Drawings , specifications requirement for smooth operation of inspection & expediting .  Seek Order acknowledgements and update promise dates from suppliers  Regularly review pending orders with suppliers and identify critical exceptions for buyer to ensure On Time Delivery  Co-ordinate with all internal customers to ensure that client requirements are met  Implement checklists for suppliers to ensure that proper documentation is enclosed by suppliers to meet local regulations and company requirements  Clearing Supplier invoices to ensure that queries, if any are resolved by concerned buyers  Expedite In-House activities to ensure shortest turnaround time for our clients  Support of data integrity in systems and documentation, including creating part numbers, BOMs, pick lists, allocation of parts, inventory transfers AUDITING  Assisting the Asset Integrity Assurance Manager by acting as audit leader of assigned audits (the audit leader will preferably be assigned to audits of his own technical expertise)  Managing exercises and audits to ensure the necessary strategies and controls are demonstrably in place to assure the integrity of the assets in all phases of the project lifecycle  Contributing to the assurance that the facilities under development by the Company are designed and built in such a way that integrity (and hence safety and economic performance) can be maintained during all phases of the lifecycle  Contributing to the preparation of look ahead plans for audits to be held  Managing external resources in the execution of audits  Coordinating with other auditing teams to prevent unnecessary disturbance of running projects  Reviewing agendas and terms of reference to ensure clarity of purpose  Preparing external parties of the auditing team for the audit  Compiling and issuing report and support interpretation of its contents; follow-up and monitor closure of actions  Coordinating reporting of external parties OIL & GAS ELECTRO MECHANICAL PROJECT ITEMS QC INSPECTION & EXPEDITING  Item : GAS PRCS Supplier M/s Gas Flow Solution Belgium  Item : Level Transmitters Supplier M/s Magnetrol Belgium  Item : Valves Supplier M/s Boteli & M/s Oviko China  Item : Gas detector Supplier M/s Oldham Belgium  Item : ESDV Supplier M/s Ace Valves Korea  Item : Level Gauges Supplier M/s Samil Korea  Item : Burner Supplier M/s Reillo Italy  Item : Ultrasonic Flow Mtr Supplier M/s Emerson USA  Item : GC Supplier M/s Emerson USA  Item : Flow Computer Supplier M/s Apex
  • 6. SHADAB HAIDER Ahmedbd  Item : PRCS Supplier M/s Nirmal Controls Mumbai  Item : Valves Supplier M/s Sakhi Mumbai  Item : DPT PT TT Supplier M/s Emerson Mumbai  Item : UPS System Supplier M/s Hitachi Gndhngr  Item : Burner Blower Supplier M/s Suntec Ahmedbd  Item : PSVs Supplier M/s Leser & Faiger Aurngbd  Item : PSVs Supplier M/s Bliss Anand Rewari  Item : PSVs Supplier M/s Tyco Valves Delhi  Item : MCC & PLC Panels Supplier M/s ATC Noida  Item : Cables Supplier M/s KEI Bhiwadi  Item : Junction Box Supplier M/s R. Stahl Chennai  Item : Heater Supplier M/s Sandvik Hosur  Item : Heater Panel Supplier M/s Sandvik Hosur  Item : RTDs , PGs & TGs Supplier M/s Wika Pune  Item : Pumps Supplier M/s KSB Nasik  Item : Transformers Supplier M/s Kirloskar Mysore  Item : Convection Module , Supplier M/s Technip KT India Ltd. Delhi Radiant Coils, Cross over coils Supplier M/s Technip KT India Ltd. Delhi Fuel Gas & Preparation Skid Supplier M/s Technip KT India Ltd. Delhi  Item : Valves Supplier M/s Fluidline Valves Pvt Ltd. Ahmedbd  Item : Valves Supplier M/s Hawa Valves Mumbai  Item : Valves Supplier M/s Advance Valves Pvt Ltd. Noida  Item : Pumps Supplier M/s WPIL Ghaziabd  Item : Lube Oil Skid Supplier M/s Enpro Pune  Item : API Tanks – API Supplier M/s Fabtec h Projects Paradeep  Item : Pressure Chambers Supplier M/s Micro precision Faridabd  Item : PEB Supplier M/s PEBS Pennar Hyrdbd  Item : PHE , Pumps etc Supplier M/s Frick India Faridabd  Item : HVAC system Supplier M/s Wolaque
  • 7. SHADAB HAIDER Delhi  Item : Air Dryer, Comprssr Supplier M/s Atlas Copco Pune  Item : Filter , Reciever Supplier M/s Atlas Copco Pune  Item : PRS , Pumps Supplier M/s Spirax Marshall Delhi  Item : Flash Vessels Supplier M/s Spirax Marshall Delhi  Item : Magnetic Filters Supplier M/s Acme Ahmedbd  Item : ETP STP Supplier M/s Brisanzia Delhi  Item : Pumps Supplier M/s Stephenson Mumbai  Item : SS Storage Tanks Supplier M/s RD Engineering Aurngbd  Item : Pasteurizer Supplier M/s Axtel Vadodara  Item : Dry Batch Hopper Supplier M/s Axtel Vadodara  Item : Wet Mixing Tank Supplier M/s Axtel Vadodara  Item : Rework Hopper Supplier M/s Axtel Vadodara  Item : PSM Supplier M/s Axtel Vadodara  Item : Magma Holding Tank Supplier M/s Axtel Vadodara  Item : 3 Valves Supplier M/s Inoxpa Pune  Item : ClP System Supplier M/s Uncorn Hyderbd  Item : Pumps Supplier M/s Mather & Platt Pune  Item : Pumps Supplier M/s Syntex Pumps Ghaziabd  Item : EOT crane Supplier M/s Electro Mech Pune  Item : DM Plant package Supplier M/s GET water solution Chennai  Item : Fuel gas skid Supplier M/s Indicone Boilers Faridabd  Item : Fire fitting package Supplier M/s Agnice Fire Protection Chennai  Item : PRS/PRDS System Supplier M/s Circor Flow Technologies Ahmdbd PROJECTS & CLIENTS SERVED  Project: NSRP Complex Project  Client: Technip KT India Ltd.  Project: 450 MW Combined Cycle Gas Power Plant  Client: Sravathi Infratech Pvt Ltd.  Project: Central UP Gas Limited (City Gas Distribution Line Project, Bareilly)  Client: Avinash EM Projects Pvt. Ltd.
  • 8. SHADAB HAIDER  Project: Grain LNG RTLF Project  Client: (CB&I)  Project: XML Mariner Ethane / Propane Facility U.S.A.  Client: Chicago Bridge & Iron (CB&I)  Project: Jubail Export Refinery (SATORP / JERP Package – 5B)  Client: Rotary Engg. Ltd.  Project: Jubail Export Refinery (SATORP / JERP Package – 5B)  Client: SK Engg. & Construction  Project: Jubail Export Refinery (SATORP / JERP Package – 5C)  Client: M. R. Al Khathalan for Contracting  Project: Wasea Bulk Plant Project (BI # 10-00795)  Client: Sinopac International Petroleum Service Co.  Project: Mitsubishi Hitachi Power System  Client: Mitsubishi Heavy Industries Corporation  Project: Shell Tabangao Asset Renewal Tabangao Refinery for Euro IV Compliance [STARTREC], Philippines  Client: Chiyoda Philippines Corporation / Shell Projects and Technology  Project: Mitsubishi Hitachi Power System Laboratory  Client: Mitsubishi Hitachi Power System Laboratory  Project: City Gas Distribution Project , Bareilly  Client: Central UP Gas Limited (CUGL) a JV of BPCL & GAIL India.  Project: Paradeep Phosphates Limited.  Client: Simon India , Delhi  Project: Paradip BOOT EPC  Client: IOT Infrastructure & Energy Services Ltd.  Project: Lin Kou Power Plant Renewal Project Taiwan  Client: Mitsubishi Hitachi Power System   Project: Rabigh IWSSP Project Saudi Arabia  Client: Mitsubishi Hitachi Power System  Project: ESSO PNG LNG EPC4 – 594153517  Client: CB&I and Clough Joint Venture U.K.  Project: Aravali Project , Cadbury Bournvita Making Plant , Dharuhera Rewari  Client: A Joint Venture Between Cadbury India & Barmalt Gurgaon PERSONAL DETAILS Permanent Address : Vill- Chhajupura Sadat , Post-Amhera , District-Bijnor , U.P , India , 246726 Date of Birth : 10 Sep, 1986 Languages Known : English and Hindi
  • 9. SHADAB HAIDER I hereby undertake that the above mentioned information is correct & to the best of my knowledge. Shadab Haider
  • 10. SHADAB HAIDER I hereby undertake that the above mentioned information is correct & to the best of my knowledge. Shadab Haider