BASIC PRINCIPLE
1.
1. Mobile modular coal preparation system is a small-scale DMC coal washing plant with compact structure and arrangement.
2. DMC system also has screening machinery, dense medium cyclone, magnetic concentrate recovery system, all kinds of hopper and other
auxilliary equipment.
3. Installation of DMC system is very quick and simple, no complex requirement, only needs a plain and solid position.  It usually takes about
3-5 months to complete whole plant construction and go into production.
4. It doesn't have high requirement about feeding raw coal property, the washing performance can be capable with traditional coal washing
plant when treating hard-to-wash coal.
5. Feeding size: 50mm-1.5mm, capacity: 50-250TPH.
6. Mobile modular coal preparation plant has advantages like low electricity consumption, low water consumption and low medium
consumption. It can use industrial water and could control the ultilization of magnetite more precisely.
7. Equipped with HOT Mining coal preparation plant intelligent expert system,  the production management could be more effective and
convenient, and save labour cost meanwhile.
8. HOT Mining can customize unique mobile modular coal preparation plant according to clients' different requirement, and provides
production-operation contracting service after construction.
MODULAR CPP - PROCESS FLOWSHEET (DMC MODULAR)
MODULAR CPP - WHOLE FLOWSHEET
MODULAR CPP - WORKFLOW
1. Feeding - Raw coal material with up to 250TPH capacity goes into pre-wet-screen for desliming.
2. DMC separation - Material goes into DMC separation equipment after desliming, in this stage coal and gangue are separated from each other 
under the action of medium suspension.
3. De-medium - Coal concentrate and gangue go into de-medium screen respectively. 
4. Medium recovery - By using magnetite recovery system in magnetic separator, the concentrate could be recovered and ultilized again.
5. Water consumption - Wet desliming by using clean water or circulating water. Add clean water into de-medium screen to wash magnetite 
powder adhered to coal concentrate. 
6. Power consumption - Normal power consumption is < 50KW according to mobile modular coal preparation plant's scale.
7. Automation control - With HOT Mining industrial automation system, the module could be controlled manually or remotely and automatically. 
If product surface moisture needs to be kept at 5%-10%, an horizontal or vertical centrifuge 
could be configured to decrease product moisture furtherly.
One set of high-efficiency and quick-open filter 
press could be configured to ensure product 
quality and protect environment, as the case may 
be.
MODULAR CPP - ALTERNATIVE EQUIPMENT
We can add flotation module for coking coal in order to maximize coal concentrate recovery rate. Either agitation impeller flotation 
machine or jet flotation machine or flotation column could be chosen according to specific condition of coal features.
Jet flotation machine Agitation impeller flotation machine Micro-bubble flotation column
OTHER ALTERNATIVE MODULES - FLOTATION MODULE
36TPH Slurry Separation System
OTHER ALTERNATIVE MODULES - COARSE SLIME SEPARATION MODULE
Technical parameters - DMC Module
Capacity: 50-250 TPH
Feeding size: 50-1.5mm
Medium consumption: <1.0Kg/t raw coal
General power: <100Kw
Water consumption: <275L/min
Easy for maintenance
Flexible to move 
DESIGN METHOD - 3D DESIGN
DESIGN PROGRESS - 3D MODELING
ADVANTAGES OF 3D DESIGN
1. Strengthen engineers' understanding about whole system, which is good for design optimization.
2. Efficient and accurate design can effectively shorten later installation time.
3. A 3D-designed coal preparation plant can be delivered to client, which is good for employee training.
4. Intelligent coal preparation plant expert system can make production management more convenient.
5. Finally achieving better ecnomic benefit and ensure ROI.
CHARACTERISTICS OF MOBILE MODULAR CPP
1. Brand new process - Greatly reduce capital construction investment and increase flexibility of washing and preparation process.
2. Low investment - One-time investment of R.O.M per ton is far less than conventional coal washing plant with same equipment configuration.
3. High efficiency - Washing and preparation efficiency can reach up to 97%.
4. Great flexibility - The modules can be added or eliminated according to client's requirement, thus washing process can be changed flexibly.
5. Stable product quality - Fluctuation range of separation S.G. is <0.005.
6. Advanced process index - Power consumption <4.7 Kw/h/ton of feeding R.O.M, medium consumption<1kg/ton of feeding R.O.M (thermal coal), 
water consumption<80kg/ton of feeding R.O.M.
7. Short construction period - It only takes 3-5 months for completion and goes into operation.
8. Convenient production management - With coal preparation plant intelligent expert control system, the operation management can be more 
efficient and convenient.
9. Low instalion cost - With modular design, only small workload for on-site preparation and installation.
10. Easy to move - It only takes about 2-3 weeks for plant relocation and to be installed at other places.
Compared Item Modular CPP Conventional Middle-Small CPP (<1.2MTPA)
Capacity (MTPA)  1.2 MTPA(example) 1.2 MTPA
Construction Period 2-5 months 12-18 months
 
 
Process Technology
1. Raw coal (80-1.0mm) use big diameter cyclone to wash 
and separate, add re-washing system if needed.
2. Coarse coal slime (1.0-0.1mm) use HTBS
3. Fine coal slime (0.1-0mm) use filter press to recover, 
closed water circuit.
4. Flotation module could be added according to different 
kind of coal
1. Jig or other complicated process (most)
2. All  DMC process (few)
3. Coal slime (0.5-0mm) is recovered by filter 
press with circulating water. 
4. Flotation module can be added according to 
different coal types.
Recovery Efficiency >95%  <90-95% 
Output per manshift (ton/shift) 125  20~25 
Power consumption (Kw*h)  <4.7Kw/h average >8 Kw/h (not electricity heating) 
Media consumption
 (kg/tons of washed raw coal)
<1.00 (thermal coal) 1.5~1.8 
Water consumption
 (m³/tons washed raw coal)
<0.08  0.1~0.3 
Process cost (Yuan/ton washed raw coal) 4.50~9.00 10~18 
SCADA System AB RSLOGIX5000 control system
+ intelligent expert management system 
AB RSLOGIX5000 control system
 
Process Plant Dimension
Compact and small, which can be loaded into container or 
transported by trailer after disassembly
At least: 40*25*30m
Big land occupation and complex 
constructioPlantn
Plant and Equipment Relocation  Easy and transportable  Permanent and fixed 
COMPARISON BETWEEN MODULAR CPP AND CONVENTIONAL CPP
CAPEX COMPARISON BETWEEN MODULAR CPP AND CONVENTIONAL CPP
Civil investment Equipment investment Installation investment Other investment Total investment
Excellent Economic Return
Coal concentrate recovery rate can add 2%-4%.
Equipment reliability can add up to 95%.
Production cost can reduce 50%.
1. Reduce 80% labour
2. Reduce 20%-30% material 
consumption
3. Reduce 50% power 
consumption
4. Reduce 80% management 
cost
5. Reduce 30% equipment 
maintenance cost
Short construction period, only 2-5 months.
New conceptual design decreases process flow and 
equipment quantity, reduces plant area and infrastructure 
investment.
ROI OF MODULAR CPP
1. Save investment
2. Short construction period - for whole plant, it only takes about 2-5 months to finish
construction and achieve production
3. High washing and preparation efficiency - it can reach up to 97% as conventional DMC coal
washing plant.
4. Convenient operation management - Intelligent expert system makes it more efficient and
convenient to manage production.
5. Appliable range - Early stage raw coal treatment in power plant, small coal preparation plant
which needs to be built in a place with many mines, or the plant is located at harbour, freight
station and logistics center.
CONCLUSION OF MOBILE MODULAR CPP'S ADVANTAGES
End user: ARTHUR  J. GALLAGHER
Project name: KINCAID P&P, LLC
Location: PAWNEE, ILLINOIS
Brief Introduction of 250TPH Coal Slime Recovery CPP
1.2MTPA
Major Separation Process
• Primary classification cyclone module
• Coal concentrate spiral separation module
• Jameson flotation module
MOBILE MODULAR CPP DEMONSTRATIONS
Client: P.T. UTAH INDONESIA 
             (BHP MINERALS INTERNATIONAL)
Project: PETANGIS COAL PROJECT
Location: KALIMANTAN INDONESIA
Description
Turnkey design, construction and commissioning of a thermal coal mine and all 
associated facilities
Features
• Increased capacity to 400 tph
• Process 1.0mm x 100 mesh raw coal in spirals
• Reduce overall product surface moisture
MOBILE MODULAR CPP DEMONSTRATIONS
Brief Introduction
80TPH modular coal preparation plant
Major separation Process
80TPH tandem arranged DMC cyclone module 
- DMC separation process 
MOBILE MODULAR CPP DEMONSTRATIONS
Brief Introduction
200TPH modular coal preparation plant
1.0MTPA
Major Separation Process
DMC process
Location: Namibia, West Africa
MOBILE MODULAR CPP DEMONSTRATIONS
MOBILE MODULAR CPP DEMONSTRATIONS
Location: South Africa
Brief Introduction
180TPH modular coal preparation plant
0.9MTPA
Major Separation Process
DMC process
MOBILE MODULAR CPP DEMONSTRATIONS
Client:  Imerys Yilong Andalusite (Xinjiang)co.,ltd
             
Location: Xinjiang, China
Brief Introduction
250TPH coal slime recovery modular coal 
preparation plant
1.2MTPA
Major Separation Process
DMC process

More Related Content

What's hot

FineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement IndustryFineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement IndustryMr. FineTek
 
Presentación de Egbert Burchardt, Thyssenkrupp
Presentación de Egbert Burchardt, ThyssenkruppPresentación de Egbert Burchardt, Thyssenkrupp
Presentación de Egbert Burchardt, ThyssenkruppVoces Mineras
 
Amrt technology overview september 2014
Amrt technology overview september 2014Amrt technology overview september 2014
Amrt technology overview september 2014Victor James
 
Generation 2 Processing Overview (2014)
Generation 2 Processing Overview (2014)Generation 2 Processing Overview (2014)
Generation 2 Processing Overview (2014)Andrew P. Robertson
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plantNihar Routray
 
Get Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution TechnologyGet Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution TechnologyLOESCHE
 
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Karan Walia
 
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
 

What's hot (9)

FineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement IndustryFineTek (Taiwan) Introduction to Applications in the Cement Industry
FineTek (Taiwan) Introduction to Applications in the Cement Industry
 
Presentación de Egbert Burchardt, Thyssenkrupp
Presentación de Egbert Burchardt, ThyssenkruppPresentación de Egbert Burchardt, Thyssenkrupp
Presentación de Egbert Burchardt, Thyssenkrupp
 
Amrt technology overview september 2014
Amrt technology overview september 2014Amrt technology overview september 2014
Amrt technology overview september 2014
 
Generation 2 Processing Overview (2014)
Generation 2 Processing Overview (2014)Generation 2 Processing Overview (2014)
Generation 2 Processing Overview (2014)
 
Geo materials at Geopcamp
Geo materials at GeopcampGeo materials at Geopcamp
Geo materials at Geopcamp
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plant
 
Get Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution TechnologyGet Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution Technology
 
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
 
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
 

Similar to Truck-mounted Mobile Modular CHPP Coal Washing and Preparation Plant - Hot Mining

Auto Bricks - Tunnel Kiln and Hoffman Kiln Project Cost
Auto Bricks - Tunnel Kiln and Hoffman Kiln Project CostAuto Bricks - Tunnel Kiln and Hoffman Kiln Project Cost
Auto Bricks - Tunnel Kiln and Hoffman Kiln Project CostOashim Khan
 
Micro turbines for seminar
Micro turbines for seminarMicro turbines for seminar
Micro turbines for seminarISHFAQ NAJAR
 
Micro and small hydro energy systems
Micro and small hydro energy systemsMicro and small hydro energy systems
Micro and small hydro energy systemsParamjit Singh
 
GAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline TechnologyGAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline TechnologyKolawole E. Akinmuyiwa
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...IRJET Journal
 
JEC 030916 wide FINALR2
JEC 030916 wide FINALR2JEC 030916 wide FINALR2
JEC 030916 wide FINALR2Stephen Oman
 
Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...
Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...
Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...rajasthan technical university kota
 
Modelling of solar micro gas turbine for parabolic dish based controller appl...
Modelling of solar micro gas turbine for parabolic dish based controller appl...Modelling of solar micro gas turbine for parabolic dish based controller appl...
Modelling of solar micro gas turbine for parabolic dish based controller appl...TELKOMNIKA JOURNAL
 
Types of systems in operations
Types of systems in operationsTypes of systems in operations
Types of systems in operationsApurva Kavishwar
 
Power Plant Presentation.pptx
Power Plant Presentation.pptxPower Plant Presentation.pptx
Power Plant Presentation.pptxssuser235687
 
In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour systemKotesh Bhukya
 
A TEC Rocket Mill Mobile
A TEC Rocket Mill MobileA TEC Rocket Mill Mobile
A TEC Rocket Mill MobileA TEC Group
 
Economic selection of type of genration and types of equipment used in power...
 Economic selection of type of genration and types of equipment used in power... Economic selection of type of genration and types of equipment used in power...
Economic selection of type of genration and types of equipment used in power...Madhusudan Sharma
 
Business plan on fly ash (final)
Business plan on fly ash (final)Business plan on fly ash (final)
Business plan on fly ash (final)Vinayak Selvarajan
 

Similar to Truck-mounted Mobile Modular CHPP Coal Washing and Preparation Plant - Hot Mining (20)

09.02.2012 Modern coking coal technology, Peter Long
09.02.2012 Modern coking coal technology, Peter Long09.02.2012 Modern coking coal technology, Peter Long
09.02.2012 Modern coking coal technology, Peter Long
 
Auto Bricks - Tunnel Kiln and Hoffman Kiln Project Cost
Auto Bricks - Tunnel Kiln and Hoffman Kiln Project CostAuto Bricks - Tunnel Kiln and Hoffman Kiln Project Cost
Auto Bricks - Tunnel Kiln and Hoffman Kiln Project Cost
 
Micro turbines for seminar
Micro turbines for seminarMicro turbines for seminar
Micro turbines for seminar
 
Micro and small hydro energy systems
Micro and small hydro energy systemsMicro and small hydro energy systems
Micro and small hydro energy systems
 
GAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline TechnologyGAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
GAS-TO-POWER via Throttle Energy's Virtual Pipeline Technology
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
case study
case studycase study
case study
 
Ch3
Ch3Ch3
Ch3
 
JEC 030916 wide FINALR2
JEC 030916 wide FINALR2JEC 030916 wide FINALR2
JEC 030916 wide FINALR2
 
Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...
Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...
Bhel - technology and application overview of fuel cells-MANMOHAN SINGH CHAND...
 
Modelling of solar micro gas turbine for parabolic dish based controller appl...
Modelling of solar micro gas turbine for parabolic dish based controller appl...Modelling of solar micro gas turbine for parabolic dish based controller appl...
Modelling of solar micro gas turbine for parabolic dish based controller appl...
 
DG KHAN CEMENT
DG KHAN CEMENT DG KHAN CEMENT
DG KHAN CEMENT
 
My ppt vfd
My ppt vfdMy ppt vfd
My ppt vfd
 
Types of systems in operations
Types of systems in operationsTypes of systems in operations
Types of systems in operations
 
Power supply
Power supplyPower supply
Power supply
 
Power Plant Presentation.pptx
Power Plant Presentation.pptxPower Plant Presentation.pptx
Power Plant Presentation.pptx
 
In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour system
 
A TEC Rocket Mill Mobile
A TEC Rocket Mill MobileA TEC Rocket Mill Mobile
A TEC Rocket Mill Mobile
 
Economic selection of type of genration and types of equipment used in power...
 Economic selection of type of genration and types of equipment used in power... Economic selection of type of genration and types of equipment used in power...
Economic selection of type of genration and types of equipment used in power...
 
Business plan on fly ash (final)
Business plan on fly ash (final)Business plan on fly ash (final)
Business plan on fly ash (final)
 

More from Serena Fu

Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...
Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...
Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...Serena Fu
 
Xrt x ray transmission ore sorter intelligent dry separation-hot mining_serena
Xrt x ray transmission ore sorter intelligent dry separation-hot mining_serenaXrt x ray transmission ore sorter intelligent dry separation-hot mining_serena
Xrt x ray transmission ore sorter intelligent dry separation-hot mining_serenaSerena Fu
 
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...Serena Fu
 
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...Serena Fu
 
Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...
Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...
Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...Serena Fu
 
Aa plc-xrassa coal handling and preparation plant design instruction
Aa plc-xrassa coal handling and preparation plant design instructionAa plc-xrassa coal handling and preparation plant design instruction
Aa plc-xrassa coal handling and preparation plant design instructionSerena Fu
 
Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...
Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...
Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...Serena Fu
 
Mining and Mineral Processing Capability_HOT Mining_Serena
Mining and Mineral Processing Capability_HOT Mining_SerenaMining and Mineral Processing Capability_HOT Mining_Serena
Mining and Mineral Processing Capability_HOT Mining_SerenaSerena Fu
 
薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena
薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena
薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_SerenaSerena Fu
 
HOT PUMP PARTS
HOT PUMP PARTSHOT PUMP PARTS
HOT PUMP PARTSSerena Fu
 
Sorucing_QCP_HOT Mining
Sorucing_QCP_HOT MiningSorucing_QCP_HOT Mining
Sorucing_QCP_HOT MiningSerena Fu
 
Low Coal Seam Longwall Mining Technology_HOT Mining_Serena
Low Coal Seam Longwall Mining Technology_HOT Mining_SerenaLow Coal Seam Longwall Mining Technology_HOT Mining_Serena
Low Coal Seam Longwall Mining Technology_HOT Mining_SerenaSerena Fu
 
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...Serena Fu
 
Tender for Iran_Low Coal Seam Mining Units_HOT Mining_Serena
Tender for Iran_Low Coal Seam Mining Units_HOT Mining_SerenaTender for Iran_Low Coal Seam Mining Units_HOT Mining_Serena
Tender for Iran_Low Coal Seam Mining Units_HOT Mining_SerenaSerena Fu
 
Mineral processing equipments_HOT Mining_Serena Fu
Mineral processing equipments_HOT Mining_Serena FuMineral processing equipments_HOT Mining_Serena Fu
Mineral processing equipments_HOT Mining_Serena FuSerena Fu
 
Coal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT MiningCoal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT MiningSerena Fu
 

More from Serena Fu (16)

Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...
Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...
Application Prospect of XRT Intelligent X-ray Transmission Ore Sorter for Dry...
 
Xrt x ray transmission ore sorter intelligent dry separation-hot mining_serena
Xrt x ray transmission ore sorter intelligent dry separation-hot mining_serenaXrt x ray transmission ore sorter intelligent dry separation-hot mining_serena
Xrt x ray transmission ore sorter intelligent dry separation-hot mining_serena
 
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
 
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
190109 horizontal vibration centrifuge-clean coal-coal concentrate-hot mining...
 
Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...
Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...
Shearer afc mechanization mining_underground coal mining_low coal seam_steepl...
 
Aa plc-xrassa coal handling and preparation plant design instruction
Aa plc-xrassa coal handling and preparation plant design instructionAa plc-xrassa coal handling and preparation plant design instruction
Aa plc-xrassa coal handling and preparation plant design instruction
 
Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...
Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...
Ungerground-Mechanized-longwall-shortwall-adit-Mining-Technology_HOT_ Mining_...
 
Mining and Mineral Processing Capability_HOT Mining_Serena
Mining and Mineral Processing Capability_HOT Mining_SerenaMining and Mineral Processing Capability_HOT Mining_Serena
Mining and Mineral Processing Capability_HOT Mining_Serena
 
薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena
薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena
薄煤层综采Thin_Low Coal Seam Mining Technology_HOT Mining_Serena
 
HOT PUMP PARTS
HOT PUMP PARTSHOT PUMP PARTS
HOT PUMP PARTS
 
Sorucing_QCP_HOT Mining
Sorucing_QCP_HOT MiningSorucing_QCP_HOT Mining
Sorucing_QCP_HOT Mining
 
Low Coal Seam Longwall Mining Technology_HOT Mining_Serena
Low Coal Seam Longwall Mining Technology_HOT Mining_SerenaLow Coal Seam Longwall Mining Technology_HOT Mining_Serena
Low Coal Seam Longwall Mining Technology_HOT Mining_Serena
 
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
 
Tender for Iran_Low Coal Seam Mining Units_HOT Mining_Serena
Tender for Iran_Low Coal Seam Mining Units_HOT Mining_SerenaTender for Iran_Low Coal Seam Mining Units_HOT Mining_Serena
Tender for Iran_Low Coal Seam Mining Units_HOT Mining_Serena
 
Mineral processing equipments_HOT Mining_Serena Fu
Mineral processing equipments_HOT Mining_Serena FuMineral processing equipments_HOT Mining_Serena Fu
Mineral processing equipments_HOT Mining_Serena Fu
 
Coal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT MiningCoal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT Mining
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Truck-mounted Mobile Modular CHPP Coal Washing and Preparation Plant - Hot Mining

  • 1. 移动式模块化选煤厂 Mobile Modular Coal Preparation Plant 北京浩沃特矿业技术有限公司 Beijing HOT Mining Tech Co Ltd E-mail: serena.fu@hot-mining.com
  • 2. BASIC PRINCIPLE 1. 1. Mobile modular coal preparation system is a small-scale DMC coal washing plant with compact structure and arrangement. 2. DMC system also has screening machinery, dense medium cyclone, magnetic concentrate recovery system, all kinds of hopper and other auxilliary equipment. 3. Installation of DMC system is very quick and simple, no complex requirement, only needs a plain and solid position.  It usually takes about 3-5 months to complete whole plant construction and go into production. 4. It doesn't have high requirement about feeding raw coal property, the washing performance can be capable with traditional coal washing plant when treating hard-to-wash coal. 5. Feeding size: 50mm-1.5mm, capacity: 50-250TPH. 6. Mobile modular coal preparation plant has advantages like low electricity consumption, low water consumption and low medium consumption. It can use industrial water and could control the ultilization of magnetite more precisely. 7. Equipped with HOT Mining coal preparation plant intelligent expert system,  the production management could be more effective and convenient, and save labour cost meanwhile. 8. HOT Mining can customize unique mobile modular coal preparation plant according to clients' different requirement, and provides production-operation contracting service after construction.
  • 3. MODULAR CPP - PROCESS FLOWSHEET (DMC MODULAR)
  • 4. MODULAR CPP - WHOLE FLOWSHEET
  • 5. MODULAR CPP - WORKFLOW 1. Feeding - Raw coal material with up to 250TPH capacity goes into pre-wet-screen for desliming. 2. DMC separation - Material goes into DMC separation equipment after desliming, in this stage coal and gangue are separated from each other  under the action of medium suspension. 3. De-medium - Coal concentrate and gangue go into de-medium screen respectively.  4. Medium recovery - By using magnetite recovery system in magnetic separator, the concentrate could be recovered and ultilized again. 5. Water consumption - Wet desliming by using clean water or circulating water. Add clean water into de-medium screen to wash magnetite  powder adhered to coal concentrate.  6. Power consumption - Normal power consumption is < 50KW according to mobile modular coal preparation plant's scale. 7. Automation control - With HOT Mining industrial automation system, the module could be controlled manually or remotely and automatically. 
  • 8. 36TPH Slurry Separation System OTHER ALTERNATIVE MODULES - COARSE SLIME SEPARATION MODULE
  • 10. DESIGN PROGRESS - 3D MODELING
  • 11. ADVANTAGES OF 3D DESIGN 1. Strengthen engineers' understanding about whole system, which is good for design optimization. 2. Efficient and accurate design can effectively shorten later installation time. 3. A 3D-designed coal preparation plant can be delivered to client, which is good for employee training. 4. Intelligent coal preparation plant expert system can make production management more convenient. 5. Finally achieving better ecnomic benefit and ensure ROI.
  • 12. CHARACTERISTICS OF MOBILE MODULAR CPP 1. Brand new process - Greatly reduce capital construction investment and increase flexibility of washing and preparation process. 2. Low investment - One-time investment of R.O.M per ton is far less than conventional coal washing plant with same equipment configuration. 3. High efficiency - Washing and preparation efficiency can reach up to 97%. 4. Great flexibility - The modules can be added or eliminated according to client's requirement, thus washing process can be changed flexibly. 5. Stable product quality - Fluctuation range of separation S.G. is <0.005. 6. Advanced process index - Power consumption <4.7 Kw/h/ton of feeding R.O.M, medium consumption<1kg/ton of feeding R.O.M (thermal coal),  water consumption<80kg/ton of feeding R.O.M. 7. Short construction period - It only takes 3-5 months for completion and goes into operation. 8. Convenient production management - With coal preparation plant intelligent expert control system, the operation management can be more  efficient and convenient. 9. Low instalion cost - With modular design, only small workload for on-site preparation and installation. 10. Easy to move - It only takes about 2-3 weeks for plant relocation and to be installed at other places.
  • 13. Compared Item Modular CPP Conventional Middle-Small CPP (<1.2MTPA) Capacity (MTPA)  1.2 MTPA(example) 1.2 MTPA Construction Period 2-5 months 12-18 months     Process Technology 1. Raw coal (80-1.0mm) use big diameter cyclone to wash  and separate, add re-washing system if needed. 2. Coarse coal slime (1.0-0.1mm) use HTBS 3. Fine coal slime (0.1-0mm) use filter press to recover,  closed water circuit. 4. Flotation module could be added according to different  kind of coal 1. Jig or other complicated process (most) 2. All  DMC process (few) 3. Coal slime (0.5-0mm) is recovered by filter  press with circulating water.  4. Flotation module can be added according to  different coal types. Recovery Efficiency >95%  <90-95%  Output per manshift (ton/shift) 125  20~25  Power consumption (Kw*h)  <4.7Kw/h average >8 Kw/h (not electricity heating)  Media consumption  (kg/tons of washed raw coal) <1.00 (thermal coal) 1.5~1.8  Water consumption  (m³/tons washed raw coal) <0.08  0.1~0.3  Process cost (Yuan/ton washed raw coal) 4.50~9.00 10~18  SCADA System AB RSLOGIX5000 control system + intelligent expert management system  AB RSLOGIX5000 control system   Process Plant Dimension Compact and small, which can be loaded into container or  transported by trailer after disassembly At least: 40*25*30m Big land occupation and complex  constructioPlantn Plant and Equipment Relocation  Easy and transportable  Permanent and fixed  COMPARISON BETWEEN MODULAR CPP AND CONVENTIONAL CPP
  • 14. CAPEX COMPARISON BETWEEN MODULAR CPP AND CONVENTIONAL CPP Civil investment Equipment investment Installation investment Other investment Total investment
  • 15. Excellent Economic Return Coal concentrate recovery rate can add 2%-4%. Equipment reliability can add up to 95%. Production cost can reduce 50%. 1. Reduce 80% labour 2. Reduce 20%-30% material  consumption 3. Reduce 50% power  consumption 4. Reduce 80% management  cost 5. Reduce 30% equipment  maintenance cost Short construction period, only 2-5 months. New conceptual design decreases process flow and  equipment quantity, reduces plant area and infrastructure  investment. ROI OF MODULAR CPP
  • 16. 1. Save investment 2. Short construction period - for whole plant, it only takes about 2-5 months to finish construction and achieve production 3. High washing and preparation efficiency - it can reach up to 97% as conventional DMC coal washing plant. 4. Convenient operation management - Intelligent expert system makes it more efficient and convenient to manage production. 5. Appliable range - Early stage raw coal treatment in power plant, small coal preparation plant which needs to be built in a place with many mines, or the plant is located at harbour, freight station and logistics center. CONCLUSION OF MOBILE MODULAR CPP'S ADVANTAGES
  • 17. End user: ARTHUR  J. GALLAGHER Project name: KINCAID P&P, LLC Location: PAWNEE, ILLINOIS Brief Introduction of 250TPH Coal Slime Recovery CPP 1.2MTPA Major Separation Process • Primary classification cyclone module • Coal concentrate spiral separation module • Jameson flotation module MOBILE MODULAR CPP DEMONSTRATIONS
  • 18. Client: P.T. UTAH INDONESIA               (BHP MINERALS INTERNATIONAL) Project: PETANGIS COAL PROJECT Location: KALIMANTAN INDONESIA Description Turnkey design, construction and commissioning of a thermal coal mine and all  associated facilities Features • Increased capacity to 400 tph • Process 1.0mm x 100 mesh raw coal in spirals • Reduce overall product surface moisture MOBILE MODULAR CPP DEMONSTRATIONS
  • 19. Brief Introduction 80TPH modular coal preparation plant Major separation Process 80TPH tandem arranged DMC cyclone module  - DMC separation process  MOBILE MODULAR CPP DEMONSTRATIONS
  • 20. Brief Introduction 200TPH modular coal preparation plant 1.0MTPA Major Separation Process DMC process Location: Namibia, West Africa MOBILE MODULAR CPP DEMONSTRATIONS
  • 21. MOBILE MODULAR CPP DEMONSTRATIONS Location: South Africa Brief Introduction 180TPH modular coal preparation plant 0.9MTPA Major Separation Process DMC process
  • 22. MOBILE MODULAR CPP DEMONSTRATIONS Client:  Imerys Yilong Andalusite (Xinjiang)co.,ltd               Location: Xinjiang, China Brief Introduction 250TPH coal slime recovery modular coal  preparation plant 1.2MTPA Major Separation Process DMC process