SlideShare a Scribd company logo
1 of 25
Project Planning, Scheduling
and Resource allocation
PM Process Summary
Launch Plan
Recruitandorganizeprojectteam
Establishteamoperatingrules
Levelproject resources
Assignwork
Monitor & Control
Progress
Establishprogressreportingsystem
Setupchangecontrolprocess
Defineproblemescalationprocess
Monitorprogressvs. plan
Reviseproject plan
Close Out Project
Obtainclientacceptance
Installproject deliverables
Completeprojectdocumentation
Completepost-implementationaudit
Issuefinalproject report
Develop Detailed Plan
Identifyproject activities
Estimateactivity duration
Determineresourcerequirements
Construct/ analyzeproject network
Prepareproject schedule
Define Project
Stateneed,problemoropportunity
Defineproject objectives
Identifysuccesscriteria
Listassumptions,risksand
obstacles
Defineprojectscopeandwork
breakdownstructure
Feedback
AdaptedfromProject Management, 1987 Kepner-Tregoe, Inc.
andEffective Project Management byR.K.Wysocki,R. Beck Jr.
&D.B. Crane(Wiley, 1995)
“Failing to plan is planning to fail”
Planning:
“what” is going to be done, “how”, “where”, by
“whom”, and “when” for effective monitoring and
control of complex projects
“Itsabouttime”
Scheduling:
“what” will be done, and “who” will be working
relative timing of tasks & time frames
a concise description of the plan
Three Basic Steps to a Project Schedule
Scheduling Techniques
Gantt or bar charts
Milestone charts
Line of balance
Networks
Program Evaluation and Review Technique (PERT)
Critical Path Method (CPM)]
Graphical Evaluation and Review Technique (GERT)
Precedence Diagram Method (PDM)
 Graphical
representation
shows horizontal
bars against a
time scale
 At summary or
detailed levels
Gantt or Simple Bar Chart
http://www.maxwideman.com/issacons/index.htm
Types of Schedules
 Graphical
representation
shows milestone
dates
 Identifies key
points in the
project's life span
 The bars are not
necessarily visible
Milestone Chart

 Graphical
representation
shows progress
relative to plan
In this case, behind
schedule
 No indication of
final completion
Progress Bar Chart
 Graphical
representation shows
original baseline
schedule (red bars)
and actual progress
relative to current
plan
 No indication of final
completion
Bar Chart Status Report
The Work Break Down Structure (WBS)
An organizational tool for complex projects
A first step in creating a schedule
Useful for defining the Scope of Work
After decided how to do the work
Consists of:
Goal statement for project
Subdividing goal into smaller & smaller portions
ExampleWBS
W a r e h o u s e W B S
SiteBoundari
es El
evati
on
D
ataP
oi
nts
Buildi
ng
Footpri
nts B
Locate
uri
edServi
ces
Survey SoilsA
nal
ysi
s ExcavateSoil Backfill &C
om
pact
SiteP
reparati
on Foundati
on Structural System
s Fi
ni
shi
ng
w
Toconstructa5-unit
arehouseforlighti
ndustry
C
o
m
pl
ex
Could be used to define scope of
work for surveyor sub-contract
Background
Allahabad, about 600 km southeast of Delhi in Uttar
Pradesh (UP) State, is a major industrial city along National
Highway 2.
The city is divided into the four districts of Allahabad, Naini,
Jhusi and Phaphamau.
The adjacent Naini District across the River Yamuna is the
industrial center where communication, automobile,
fertilizer, textile and related industry companies are located.
The only traffic route connecting these two districts was the
existing bridge over the River Yamuna (Yamuna Bridge).
The existing bridge (Yamuna Bridge) is a combined
highway-railway bridge constructed at the end of the 19th
century, and its narrow two lanes were straining to cope
with the increasing size and weight of the vehicles.
Out of concern over the safety of the decaying bridge,
construction of a new substitute bridge was urgently
needed.
Objective
Construct a four-lane bridge
Replace the existing old two-lane bridge
Alleviating chronic traffic congestion
Borrower/ExecutingAgency
Borrower: The President of India
Executing Agency: The Ministry of Surface
Transport (current Ministry of Shipping, Road
Transport and Highways)
Outline of Loan Agreement
Loan Amount / Loan Disbursed 10,037 million yen / 7,515 million yen
Amount
Exchange of Notes / Loan Agreement December 1993 / January 1994
Terms and Conditions
-Interest Rate
-Repayment Period (Grace Period)
-Procurement
2.6%
30 years (10 years)
General untied
Final Disbursement Date March 2005
Main Contractors J/V of Hyundai Engineering Co. Ltd.
(Korea) and Hindustan Construction Co.
Ltd. (India)
Total Bridge Length: 1640 m
Width of superstructure 26 m
Main spans: 185 m – 260 m – 185 m
Output
The main scope of this
project include the
construction of a four-lane
cable-stayed bridge (Naini
Bridge; length, 1,640 m)
and approach roads (total
length: 3,806 m) was
implemented almost entirely
as planned.
In addition, based on recommendations suggested
in JBIC’s study the project scope was expanded
to include installation of toll booths and
monitoring equipment such as the weigh-in
motion system and the wind and structural health
monitoring system (WASHMS).
Projectperiod
The project period was scheduled from January 1994 to July
2004 (ten years and seven months), which is four years and
four months longer than the planned period from January
1994 to March 2000 (six years three months) or 169% of the
planned period.
The project cost was 8,807 million yen 3,097 million yen less
than the planned 11,904 million yen or 74% of the planned
project cost. In terms of rupee, the actual cost was 3,145
million rupees which is almost equal to the planned 3,217
rupees.
ProjectCost
InvolvementofMaurer Söhne
Maurer Soehne manufactured 4 Swivel Joist Expansion
Joints with a length of 24,40 m each. This cross-
sectional width of the superstructure considers 4
highway traffic lanes and two lateral 3m - tracks for
“other” traffic and pedestrians.
Due to transport reasons, the joints were delivered in two
pieces to be connected on job site. The joints can
accommodate movements of 400 mm (at both
abutments) and 360 mm and 600 mm
respectively at the pylons.
Operationandmaintenance status
On the Naini Bridge, weather observation devices,
which check conditions and measure the weight
and gradient of pylons, are set at seven positions
and are monitored 24 hours from the observation
equipment control room in the toll booth control
building.
Effectiveness
Traffic volume
Time saving Congestion length
decrease and time saving

More Related Content

What's hot

Orange line train project impact in environmental pollution
Orange line train project impact in environmental pollutionOrange line train project impact in environmental pollution
Orange line train project impact in environmental pollutionShahzaib Khan
 
project work presentation on road feasibility study (need to be corrected but...
project work presentation on road feasibility study (need to be corrected but...project work presentation on road feasibility study (need to be corrected but...
project work presentation on road feasibility study (need to be corrected but...Rakesh Sunari Magar
 
Making of mughal road..
Making of mughal road..Making of mughal road..
Making of mughal road..humairab1
 
Highway design raport(final) (group 2)
Highway design raport(final) (group 2)Highway design raport(final) (group 2)
Highway design raport(final) (group 2)haayaav
 
Introduction to tranportation
Introduction to tranportationIntroduction to tranportation
Introduction to tranportationSatyamkumar Jha
 
highway development in india
highway development in indiahighway development in india
highway development in indiaPrathi Baa
 
Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016Toronto Public Consultation Unit
 
14 ce2014 te-intro
14 ce2014 te-intro14 ce2014 te-intro
14 ce2014 te-introPrathi Baa
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyStittsvilleCentral.ca
 

What's hot (20)

Orange line train project impact in environmental pollution
Orange line train project impact in environmental pollutionOrange line train project impact in environmental pollution
Orange line train project impact in environmental pollution
 
Rolling Climate Change, Transportation & Land Use Planning into One Innovativ...
Rolling Climate Change, Transportation & Land Use Planning into One Innovativ...Rolling Climate Change, Transportation & Land Use Planning into One Innovativ...
Rolling Climate Change, Transportation & Land Use Planning into One Innovativ...
 
project work presentation on road feasibility study (need to be corrected but...
project work presentation on road feasibility study (need to be corrected but...project work presentation on road feasibility study (need to be corrected but...
project work presentation on road feasibility study (need to be corrected but...
 
Making of mughal road..
Making of mughal road..Making of mughal road..
Making of mughal road..
 
Scarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of ReferenceScarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of Reference
 
February-March Consultation Report
February-March Consultation ReportFebruary-March Consultation Report
February-March Consultation Report
 
John Rahaim - Transit Center District Plan
John Rahaim - Transit Center District PlanJohn Rahaim - Transit Center District Plan
John Rahaim - Transit Center District Plan
 
Highway design raport(final) (group 2)
Highway design raport(final) (group 2)Highway design raport(final) (group 2)
Highway design raport(final) (group 2)
 
Scarborough Subway Extension - Public Consultation Plan
Scarborough Subway Extension - Public Consultation PlanScarborough Subway Extension - Public Consultation Plan
Scarborough Subway Extension - Public Consultation Plan
 
Introduction to tranportation
Introduction to tranportationIntroduction to tranportation
Introduction to tranportation
 
ORahman-Resume
ORahman-ResumeORahman-Resume
ORahman-Resume
 
AICPA GPAC presentation
AICPA GPAC presentationAICPA GPAC presentation
AICPA GPAC presentation
 
Coordinated Transit Planning in Toronto
Coordinated Transit Planning in TorontoCoordinated Transit Planning in Toronto
Coordinated Transit Planning in Toronto
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016
 
Draft Relief Line Corridor Evaluation
Draft Relief Line Corridor EvaluationDraft Relief Line Corridor Evaluation
Draft Relief Line Corridor Evaluation
 
2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG
 
14 ce2014 te-intro
14 ce2014 te-intro14 ce2014 te-intro
14 ce2014 te-intro
 
Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
 

Similar to 3 planning and scheduling

Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROIRJET Journal
 
Analysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in BangladeshAnalysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in BangladeshRituSaha3
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesaUtsav Tripathy
 
Running Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docx
Running Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docxRunning Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docx
Running Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docxcharisellington63520
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaNarendra Vasudeva
 
CV Shray Jain
CV Shray Jain CV Shray Jain
CV Shray Jain Shray Jain
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
 
Civil engineer strategic
Civil engineer strategicCivil engineer strategic
Civil engineer strategicssuser351e58
 
The Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development ProjectThe Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development ProjectKKM Architects
 
Design of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterDesign of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterIRJET Journal
 
Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Jayesh Kambli
 
Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Peter A. Hanna, CPM
 
Zade Couch - resume
Zade Couch - resumeZade Couch - resume
Zade Couch - resumeZade Couch
 

Similar to 3 planning and scheduling (20)

Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
 
Analysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in BangladeshAnalysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesa
 
MERAJ UL HUDA CV
MERAJ UL HUDA CVMERAJ UL HUDA CV
MERAJ UL HUDA CV
 
Running Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docx
Running Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docxRunning Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docx
Running Head PROJECT MANAGEMENT-ROAD REHABILITATION PROJECT.docx
 
Muhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CVMuhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CV
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
Mina Mourad CV
Mina Mourad CVMina Mourad CV
Mina Mourad CV
 
Akhtar Resume
Akhtar ResumeAkhtar Resume
Akhtar Resume
 
CV Shray Jain
CV Shray Jain CV Shray Jain
CV Shray Jain
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
Civil engineer strategic
Civil engineer strategicCivil engineer strategic
Civil engineer strategic
 
The Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development ProjectThe Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development Project
 
Design of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant WaterDesign of Highway with Major Bridge on Stagnant Water
Design of Highway with Major Bridge on Stagnant Water
 
Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)
 
cv Updated M.Anwar
cv Updated M.Anwarcv Updated M.Anwar
cv Updated M.Anwar
 
Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6Contrack Watts Newsletter-Issue 6
Contrack Watts Newsletter-Issue 6
 
Zade Couch - resume
Zade Couch - resumeZade Couch - resume
Zade Couch - resume
 
Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15
 

More from Dr.R. SELVAM

7 breakeven analysis
7 breakeven analysis7 breakeven analysis
7 breakeven analysisDr.R. SELVAM
 
6 fixed assets, current assets, depreciation methods
6 fixed assets, current assets, depreciation methods6 fixed assets, current assets, depreciation methods
6 fixed assets, current assets, depreciation methodsDr.R. SELVAM
 
5 preparation and interpretation of balance sheets
5 preparation and interpretation of balance sheets5 preparation and interpretation of balance sheets
5 preparation and interpretation of balance sheetsDr.R. SELVAM
 
4 acounting principle
4 acounting principle4 acounting principle
4 acounting principleDr.R. SELVAM
 
3 capital structure
3 capital structure3 capital structure
3 capital structureDr.R. SELVAM
 
1 sources of finance
1 sources of finance1 sources of finance
1 sources of financeDr.R. SELVAM
 
4 b. capital budgeting and cost analysis performance evaluation
4 b. capital budgeting and cost analysis   performance evaluation4 b. capital budgeting and cost analysis   performance evaluation
4 b. capital budgeting and cost analysis performance evaluationDr.R. SELVAM
 
4 a. capital budgeting and cost analysis
4 a. capital budgeting and cost analysis4 a. capital budgeting and cost analysis
4 a. capital budgeting and cost analysisDr.R. SELVAM
 
3 capital budgeting
3 capital budgeting3 capital budgeting
3 capital budgetingDr.R. SELVAM
 
1 current assement management
1 current assement management1 current assement management
1 current assement managementDr.R. SELVAM
 
2 b. project termination
2 b. project termination2 b. project termination
2 b. project terminationDr.R. SELVAM
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditingDr.R. SELVAM
 
1 b, evaluation of project
1 b, evaluation of project1 b, evaluation of project
1 b, evaluation of projectDr.R. SELVAM
 
1 a, monitoring and evaluation of PM
1 a, monitoring and evaluation of PM1 a, monitoring and evaluation of PM
1 a, monitoring and evaluation of PMDr.R. SELVAM
 
3 industrial hydraulic circuits shapping, milling, drilling
3 industrial hydraulic circuits   shapping, milling, drilling3 industrial hydraulic circuits   shapping, milling, drilling
3 industrial hydraulic circuits shapping, milling, drillingDr.R. SELVAM
 
2 maintenance of hydraulic systems
2 maintenance of hydraulic systems2 maintenance of hydraulic systems
2 maintenance of hydraulic systemsDr.R. SELVAM
 
1 hydraulic troubleshooting
1 hydraulic troubleshooting1 hydraulic troubleshooting
1 hydraulic troubleshootingDr.R. SELVAM
 
3 c. industrial pneumatic circuit logic
3 c. industrial pneumatic circuit   logic3 c. industrial pneumatic circuit   logic
3 c. industrial pneumatic circuit logicDr.R. SELVAM
 

More from Dr.R. SELVAM (20)

7 breakeven analysis
7 breakeven analysis7 breakeven analysis
7 breakeven analysis
 
6 fixed assets, current assets, depreciation methods
6 fixed assets, current assets, depreciation methods6 fixed assets, current assets, depreciation methods
6 fixed assets, current assets, depreciation methods
 
5 preparation and interpretation of balance sheets
5 preparation and interpretation of balance sheets5 preparation and interpretation of balance sheets
5 preparation and interpretation of balance sheets
 
4 acounting principle
4 acounting principle4 acounting principle
4 acounting principle
 
3 capital structure
3 capital structure3 capital structure
3 capital structure
 
1 sources of finance
1 sources of finance1 sources of finance
1 sources of finance
 
2 term loan
2 term loan2 term loan
2 term loan
 
4 b. capital budgeting and cost analysis performance evaluation
4 b. capital budgeting and cost analysis   performance evaluation4 b. capital budgeting and cost analysis   performance evaluation
4 b. capital budgeting and cost analysis performance evaluation
 
4 a. capital budgeting and cost analysis
4 a. capital budgeting and cost analysis4 a. capital budgeting and cost analysis
4 a. capital budgeting and cost analysis
 
3 capital budgeting
3 capital budgeting3 capital budgeting
3 capital budgeting
 
2 working capital
2 working capital2 working capital
2 working capital
 
1 current assement management
1 current assement management1 current assement management
1 current assement management
 
2 b. project termination
2 b. project termination2 b. project termination
2 b. project termination
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditing
 
1 b, evaluation of project
1 b, evaluation of project1 b, evaluation of project
1 b, evaluation of project
 
1 a, monitoring and evaluation of PM
1 a, monitoring and evaluation of PM1 a, monitoring and evaluation of PM
1 a, monitoring and evaluation of PM
 
3 industrial hydraulic circuits shapping, milling, drilling
3 industrial hydraulic circuits   shapping, milling, drilling3 industrial hydraulic circuits   shapping, milling, drilling
3 industrial hydraulic circuits shapping, milling, drilling
 
2 maintenance of hydraulic systems
2 maintenance of hydraulic systems2 maintenance of hydraulic systems
2 maintenance of hydraulic systems
 
1 hydraulic troubleshooting
1 hydraulic troubleshooting1 hydraulic troubleshooting
1 hydraulic troubleshooting
 
3 c. industrial pneumatic circuit logic
3 c. industrial pneumatic circuit   logic3 c. industrial pneumatic circuit   logic
3 c. industrial pneumatic circuit logic
 

Recently uploaded

Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonJericReyAuditor
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Science lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lessonScience lesson Moon for 4th quarter lesson
Science lesson Moon for 4th quarter lesson
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

3 planning and scheduling

  • 1. Project Planning, Scheduling and Resource allocation
  • 2. PM Process Summary Launch Plan Recruitandorganizeprojectteam Establishteamoperatingrules Levelproject resources Assignwork Monitor & Control Progress Establishprogressreportingsystem Setupchangecontrolprocess Defineproblemescalationprocess Monitorprogressvs. plan Reviseproject plan Close Out Project Obtainclientacceptance Installproject deliverables Completeprojectdocumentation Completepost-implementationaudit Issuefinalproject report Develop Detailed Plan Identifyproject activities Estimateactivity duration Determineresourcerequirements Construct/ analyzeproject network Prepareproject schedule Define Project Stateneed,problemoropportunity Defineproject objectives Identifysuccesscriteria Listassumptions,risksand obstacles Defineprojectscopeandwork breakdownstructure Feedback AdaptedfromProject Management, 1987 Kepner-Tregoe, Inc. andEffective Project Management byR.K.Wysocki,R. Beck Jr. &D.B. Crane(Wiley, 1995)
  • 3. “Failing to plan is planning to fail” Planning: “what” is going to be done, “how”, “where”, by “whom”, and “when” for effective monitoring and control of complex projects
  • 4. “Itsabouttime” Scheduling: “what” will be done, and “who” will be working relative timing of tasks & time frames a concise description of the plan
  • 5. Three Basic Steps to a Project Schedule
  • 6. Scheduling Techniques Gantt or bar charts Milestone charts Line of balance Networks Program Evaluation and Review Technique (PERT) Critical Path Method (CPM)] Graphical Evaluation and Review Technique (GERT) Precedence Diagram Method (PDM)
  • 7.  Graphical representation shows horizontal bars against a time scale  At summary or detailed levels Gantt or Simple Bar Chart http://www.maxwideman.com/issacons/index.htm Types of Schedules
  • 8.  Graphical representation shows milestone dates  Identifies key points in the project's life span  The bars are not necessarily visible Milestone Chart
  • 9.   Graphical representation shows progress relative to plan In this case, behind schedule  No indication of final completion Progress Bar Chart
  • 10.  Graphical representation shows original baseline schedule (red bars) and actual progress relative to current plan  No indication of final completion Bar Chart Status Report
  • 11. The Work Break Down Structure (WBS) An organizational tool for complex projects A first step in creating a schedule Useful for defining the Scope of Work After decided how to do the work Consists of: Goal statement for project Subdividing goal into smaller & smaller portions
  • 12. ExampleWBS W a r e h o u s e W B S SiteBoundari es El evati on D ataP oi nts Buildi ng Footpri nts B Locate uri edServi ces Survey SoilsA nal ysi s ExcavateSoil Backfill &C om pact SiteP reparati on Foundati on Structural System s Fi ni shi ng w Toconstructa5-unit arehouseforlighti ndustry C o m pl ex Could be used to define scope of work for surveyor sub-contract
  • 13. Background Allahabad, about 600 km southeast of Delhi in Uttar Pradesh (UP) State, is a major industrial city along National Highway 2. The city is divided into the four districts of Allahabad, Naini, Jhusi and Phaphamau. The adjacent Naini District across the River Yamuna is the industrial center where communication, automobile, fertilizer, textile and related industry companies are located. The only traffic route connecting these two districts was the existing bridge over the River Yamuna (Yamuna Bridge).
  • 14. The existing bridge (Yamuna Bridge) is a combined highway-railway bridge constructed at the end of the 19th century, and its narrow two lanes were straining to cope with the increasing size and weight of the vehicles. Out of concern over the safety of the decaying bridge, construction of a new substitute bridge was urgently needed.
  • 15. Objective Construct a four-lane bridge Replace the existing old two-lane bridge Alleviating chronic traffic congestion
  • 16. Borrower/ExecutingAgency Borrower: The President of India Executing Agency: The Ministry of Surface Transport (current Ministry of Shipping, Road Transport and Highways)
  • 17. Outline of Loan Agreement Loan Amount / Loan Disbursed 10,037 million yen / 7,515 million yen Amount Exchange of Notes / Loan Agreement December 1993 / January 1994 Terms and Conditions -Interest Rate -Repayment Period (Grace Period) -Procurement 2.6% 30 years (10 years) General untied Final Disbursement Date March 2005 Main Contractors J/V of Hyundai Engineering Co. Ltd. (Korea) and Hindustan Construction Co. Ltd. (India) Total Bridge Length: 1640 m Width of superstructure 26 m Main spans: 185 m – 260 m – 185 m
  • 18. Output The main scope of this project include the construction of a four-lane cable-stayed bridge (Naini Bridge; length, 1,640 m) and approach roads (total length: 3,806 m) was implemented almost entirely as planned.
  • 19. In addition, based on recommendations suggested in JBIC’s study the project scope was expanded to include installation of toll booths and monitoring equipment such as the weigh-in motion system and the wind and structural health monitoring system (WASHMS).
  • 20. Projectperiod The project period was scheduled from January 1994 to July 2004 (ten years and seven months), which is four years and four months longer than the planned period from January 1994 to March 2000 (six years three months) or 169% of the planned period. The project cost was 8,807 million yen 3,097 million yen less than the planned 11,904 million yen or 74% of the planned project cost. In terms of rupee, the actual cost was 3,145 million rupees which is almost equal to the planned 3,217 rupees. ProjectCost
  • 21. InvolvementofMaurer Söhne Maurer Soehne manufactured 4 Swivel Joist Expansion Joints with a length of 24,40 m each. This cross- sectional width of the superstructure considers 4 highway traffic lanes and two lateral 3m - tracks for “other” traffic and pedestrians. Due to transport reasons, the joints were delivered in two pieces to be connected on job site. The joints can accommodate movements of 400 mm (at both abutments) and 360 mm and 600 mm respectively at the pylons.
  • 22. Operationandmaintenance status On the Naini Bridge, weather observation devices, which check conditions and measure the weight and gradient of pylons, are set at seven positions and are monitored 24 hours from the observation equipment control room in the toll booth control building.
  • 23.
  • 24.
  • 25. Effectiveness Traffic volume Time saving Congestion length decrease and time saving