SlideShare a Scribd company logo
1 of 44
Download to read offline
Kanata Light Rail Transit Planning and
Environmental Assessment Study
Public Open House 1
June 5, 2017
Transportation Services Department
1
Open House Objectives
• Introductions;
• Study Overview;
• Study Design and Schedule;
• Identification of Alternative Corridors;
• Corridor Evaluation Methodology & Initial Results;
and,
• Next Steps.
2
Study Goals
• Determine the Preferred Corridor;
• Determine the Recommended Plan for LRT
alignment and stations; and,
• Determine project staging and implementation.
3
Context for the Study
• Confederation Line opens in 2018.
• Stage 2 Extension of Confederation Line West
opens in 2023
4
Study Schedule
Spring 2017:
Existing Conditions & Corridor Selection
*Consultation Groups and Public Open House 1*
Summer/Fall 2017:
Evaluation of Designs
*Meet with Consultation Groups*
Fall/Winter 2017/18:
Recommended Plan
*Consultation Groups and Public Open House 2*
*Present to Committee and Council*
Spring 2018:
Commence Transit Project Assessment Process
Pre-Planning
Phase
EA Phase
5
Study Process
• Environmental Assessment requirements
addressed through Transit Project Assessment
Process (TPAP); and
• Documented in Environmental Project Report
(EPR).
6
Guiding Principles
• Provide transportation that complements the character and
quality of the corridors and communities;
• Respect the integrity of the natural environment & cultural
and heritage traits;
• Enhance the economic health of the study area; and,
• Early, ongoing, inclusive and transparent stakeholder and
public engagement.
7
Need & Justification
• TPAP permits the City to rely on prior planning;
• Potential corridors identified and assessed; and,
• Ridership trends.
– Significant number of trips cross the Greenbelt.
• Half of Kanata jobs filled by Kanata residents.
– Increase in internal trips being taken.
• Mode split is currently only 3% for these trips.
8
LRT Requirements
• Extension of Confederation Line.
– Technology and geometric constraints set.
– Completely grade separated.
• One corridor.
– Insufficient ridership for multiple corridors.
– Branching of the line will be challenging.
9
TMP (2013) - Ultimate Network
10
TMP (2013) – Affordable Network
Proposed Extension of
LRT to Moodie (Stage 2)
11
Existing Conditions
• Collect existing information based on
desktop exercise;
• Level of detail suitable for corridor
evaluation; and,
• More detailed analysis of conditions will be
documented for the preferred corridor.
12
NCC Greenbelt Master Plan (2013)
Shirley’s Bay
Sector Plan
Stoney Swamp
Sector Plan
13
Existing Transportation Conditions
14
Existing Transportation Conditions
15
OC Transpo Routes
16
Existing Natural Conditions
17
Existing Natural Conditions
18
Existing Social Conditions
19
Existing Social Conditions
20
Intensification Opportunities
21
Alternative Corridors
• 13 potential corridors identified.
- North, South, and Central to Highway 417.
- Palladium assumed as western terminus.
• All compatible with proposed extension of
LRT to Moodie (Stage 2).
22
Corridors (North of HWY 417)
23
Corridors (Central & South of HWY 417)
24
Corridor Screening Methodology
• All 13 corridors subject to preliminary
screening; and,
• Combination of quantitative, qualitative, and
comparative assessment.
Least Preferred Most Preferred
■ ▲ ●
Limited positive effect
Major impact
Highest cost
Good positive effect
Minor impact
Moderate cost
Greatest positive effect
Negligible impact
Lowest cost
25
Criteria Categories
1. Ridership Potential and Network Connectivity;
2. Transit Oriented Development & City Building;
3. Effect on Natural Environment;
4. Effect on Social Environment;
5. Complexity; and,
6. Capital and Operational Cost.
26
Corridor 1: Carling/March/Terry Fox
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ● ■ ▲ ■ ■
27
Corridor 2: Carling/Rail/Terry Fox
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ▲ ■ ▲ ▲ ■
28
Corridor 3: 417/Rail/March/Terry Fox
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ● ■ ■ ▲ ■
29
Corridor 4: 417/Rail/Terry Fox
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ■ ■ ■ ▲ ▲
30
Corridor 5: 417/March/Terry Fox
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
● ● ■ ▲ ■ ■
31
Corridor 6: 417/March/Rail/Terry Fox
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ■ ■ ▲ ■ ■
32
Corridor 7: 417/Campeau
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
■ ▲ ● ▲ ▲ ▲
33
Corridor 8: North Side of Highway 417
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
● ● ● ● ● ●
34
Corridor 9: Highway 417 Median
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ● ● ▲ ■ ●
35
Corridor 10: South Side of Highway 417
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ● ● ▲ ▲ ●
36
Corridor 11: Timm/Katimavik/Palladium
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
■ ▲ ▲ ▲ ▲ ▲
37
Corridor 12: TransCanada Trail/Hazeldean
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ▲ ▲ ▲ ■ ▲
38
Corridor 13: TransCanada Trail
Ridership Potential
& Network
Connectivity
TOD & City
Building
Opportunities
Natural
Environment
Impacts
Social
Environment
Impact
Complexity
Capital &
Operational Costs
▲ ▲ ▲ ■ ▲ ▲
39
Preliminary Preferred Corridor
Alignments
1 2 3 4 5 6 7 8 9 10 11 12 13
1. Ridership Potential
and Network
Connectivity
▲ ▲ ▲ ▲ ● ▲ ■ ● ▲ ▲ ■ ▲ ▲
2. TOD & City Building
Opportunities ● ▲ ● ■ ● ■ ▲ ● ● ● ▲ ▲ ▲
3. Natural
Environment Impacts ■ ■ ■ ■ ■ ■ ● ● ● ● ▲ ▲ ▲
4. Social Environment
Impacts ▲ ▲ ■ ■ ▲ ▲ ▲ ● ▲ ▲ ▲ ▲ ■
5. Complexity ■ ▲ ▲ ▲ ■ ■ ▲ ● ■ ▲ ▲ ■ ▲
6. Capital and
Operational Costs ■ ■ ■ ▲ ■ ■ ▲ ● ● ● ▲ ▲ ▲
SUMMARY
■ ■ ■ ■ ■ ■ ▲ ● ▲ ▲ ■ ■ ■
40
Preliminary Preferred: Corridor 8
• Provides transit spine equally connecting all of
Kanata
• Supports future March & Fernbank BRT Corridors
• No significant environmental or social impacts
• Supports development objectives along route
• Cost effective to build and operate
41
Additional Analysis
• Based on feedback and ridership potential,
further analyses is required for:
- Corridors 5 and 13, alongside Corridor 8
42
Next Steps
• Based on feedback from consultation groups
and public, project team will:
– Further analysis of Corridors 5, 8, 13;
– Confirm the preliminary preferred corridor;
– Develop alternative designs; and,
– Develop recommended plan.
• Public Open House #2 late 2017
43
QUESTIONS?
www.Ottawa.ca/KanataLRT
www.Ottawa.ca/KanataTLR
Contact: Angela Taylor
(613)580-2424 Ext. 15210
angela.taylor@ottawa.ca

More Related Content

What's hot

Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...Toronto Public Consultation Unit
 
Scarborough Subway Extension - Draft Public Consultation Plan
Scarborough Subway Extension - Draft Public Consultation PlanScarborough Subway Extension - Draft Public Consultation Plan
Scarborough Subway Extension - Draft Public Consultation PlanToronto Public Consultation Unit
 
Scarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation ReportScarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation ReportToronto Public Consultation Unit
 
Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016Toronto Public Consultation Unit
 
Scarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of ReferenceScarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of ReferenceToronto Public Consultation Unit
 

What's hot (20)

Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...
 
Scarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of ReferenceScarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of Reference
 
February Transit Update Presentation
February Transit Update PresentationFebruary Transit Update Presentation
February Transit Update Presentation
 
Scarborough Subway Extension - Draft Public Consultation Plan
Scarborough Subway Extension - Draft Public Consultation PlanScarborough Subway Extension - Draft Public Consultation Plan
Scarborough Subway Extension - Draft Public Consultation Plan
 
Toronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting PresentationToronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting Presentation
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
Scarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation ReportScarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation Report
 
Scarborough Subway Extension Final Evaluation Criteria
Scarborough Subway Extension Final Evaluation CriteriaScarborough Subway Extension Final Evaluation Criteria
Scarborough Subway Extension Final Evaluation Criteria
 
2015 06-15 relief line presentation
2015 06-15 relief line presentation2015 06-15 relief line presentation
2015 06-15 relief line presentation
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
February-March Consultation Report
February-March Consultation ReportFebruary-March Consultation Report
February-March Consultation Report
 
Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016Scarborough Subway Extension SAG Meeting - February 8, 2016
Scarborough Subway Extension SAG Meeting - February 8, 2016
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
15-03 Relief Line Public Meeting Presentation
15-03 Relief Line Public Meeting Presentation15-03 Relief Line Public Meeting Presentation
15-03 Relief Line Public Meeting Presentation
 
Scarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of ReferenceScarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of Reference
 
Relief Line - Draft Evaluation Process and Criteria
Relief Line - Draft Evaluation Process and CriteriaRelief Line - Draft Evaluation Process and Criteria
Relief Line - Draft Evaluation Process and Criteria
 
Evaluation process and criteria june 2 2015 final
Evaluation process and criteria june 2 2015 finalEvaluation process and criteria june 2 2015 final
Evaluation process and criteria june 2 2015 final
 
15 03-24 rlpa sag1 presentation
15 03-24 rlpa sag1 presentation15 03-24 rlpa sag1 presentation
15 03-24 rlpa sag1 presentation
 
AICPA GPAC presentation
AICPA GPAC presentationAICPA GPAC presentation
AICPA GPAC presentation
 

Similar to Kanata LRT Planning and Environmental Assessment Study

Cycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity PresentationCycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity Presentationdirectionsto2050
 
Transbay presentation-2-14-13
Transbay presentation-2-14-13Transbay presentation-2-14-13
Transbay presentation-2-14-13Adina Levin
 
Kp rail visionevent_18nov2015
Kp rail visionevent_18nov2015Kp rail visionevent_18nov2015
Kp rail visionevent_18nov2015Barry Scott
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...JumpingJaq
 
Scarborough Subway Extension Stakeholder Advisory Group Meeting 1
Scarborough Subway Extension Stakeholder Advisory Group Meeting 1Scarborough Subway Extension Stakeholder Advisory Group Meeting 1
Scarborough Subway Extension Stakeholder Advisory Group Meeting 1Toronto Public Consultation Unit
 
RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...
RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...
RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...Rail~Volution
 
North Corridor Transit Project - December 16th Board Briefing
North Corridor Transit Project - December 16th Board BriefingNorth Corridor Transit Project - December 16th Board Briefing
North Corridor Transit Project - December 16th Board Briefingseatransitblog
 
Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018
Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018Fairfax County
 
Wynn Transportation Plan
Wynn Transportation PlanWynn Transportation Plan
Wynn Transportation PlanEverettUnited
 
Roadspace Allocation for Better Streets
Roadspace Allocation for Better StreetsRoadspace Allocation for Better Streets
Roadspace Allocation for Better StreetsDesign South East
 

Similar to Kanata LRT Planning and Environmental Assessment Study (20)

SmartTrack Presentation - June, 2015
SmartTrack Presentation - June, 2015SmartTrack Presentation - June, 2015
SmartTrack Presentation - June, 2015
 
November 3, 2021 CTAC Virtual Workshop
November 3, 2021 CTAC Virtual WorkshopNovember 3, 2021 CTAC Virtual Workshop
November 3, 2021 CTAC Virtual Workshop
 
SmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network PlanningSmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network Planning
 
Cycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity PresentationCycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity Presentation
 
June Relief Line Update
June Relief Line UpdateJune Relief Line Update
June Relief Line Update
 
SMART Plan Corridors' PD&Es Update
SMART Plan Corridors' PD&Es UpdateSMART Plan Corridors' PD&Es Update
SMART Plan Corridors' PD&Es Update
 
BPAC April 21, 2020 Virtual Meeting
BPAC April 21, 2020 Virtual MeetingBPAC April 21, 2020 Virtual Meeting
BPAC April 21, 2020 Virtual Meeting
 
Transbay presentation-2-14-13
Transbay presentation-2-14-13Transbay presentation-2-14-13
Transbay presentation-2-14-13
 
Miami DDA Board SMART Plan Update presentation
Miami DDA Board SMART Plan Update presentationMiami DDA Board SMART Plan Update presentation
Miami DDA Board SMART Plan Update presentation
 
Kp rail visionevent_18nov2015
Kp rail visionevent_18nov2015Kp rail visionevent_18nov2015
Kp rail visionevent_18nov2015
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...
 
Scarborough Subway Extension Stakeholder Advisory Group Meeting 1
Scarborough Subway Extension Stakeholder Advisory Group Meeting 1Scarborough Subway Extension Stakeholder Advisory Group Meeting 1
Scarborough Subway Extension Stakeholder Advisory Group Meeting 1
 
Relief Line Project Assessment Phase 1A Consultation Presentation
Relief Line Project Assessment Phase 1A Consultation PresentationRelief Line Project Assessment Phase 1A Consultation Presentation
Relief Line Project Assessment Phase 1A Consultation Presentation
 
RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...
RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...
RV 2014: Urban Circulator Roundtable: Shaping Cities one Challenge at a Time ...
 
North Corridor Transit Project - December 16th Board Briefing
North Corridor Transit Project - December 16th Board BriefingNorth Corridor Transit Project - December 16th Board Briefing
North Corridor Transit Project - December 16th Board Briefing
 
Cuyahoga Greenways: Community Meeting #4
Cuyahoga Greenways: Community Meeting #4Cuyahoga Greenways: Community Meeting #4
Cuyahoga Greenways: Community Meeting #4
 
Wellborn Community Plan
Wellborn Community PlanWellborn Community Plan
Wellborn Community Plan
 
Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018
Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
 
Wynn Transportation Plan
Wynn Transportation PlanWynn Transportation Plan
Wynn Transportation Plan
 
Roadspace Allocation for Better Streets
Roadspace Allocation for Better StreetsRoadspace Allocation for Better Streets
Roadspace Allocation for Better Streets
 

More from StittsvilleCentral.ca

Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookBill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookStittsvilleCentral.ca
 
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsMayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsStittsvilleCentral.ca
 
Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016StittsvilleCentral.ca
 
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadPublic Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadStittsvilleCentral.ca
 
Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015StittsvilleCentral.ca
 
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsMemo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsStittsvilleCentral.ca
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyStittsvilleCentral.ca
 
Stittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsvilleCentral.ca
 
Stittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsvilleCentral.ca
 
Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017StittsvilleCentral.ca
 
March 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaMarch 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaStittsvilleCentral.ca
 
Memo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentMemo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentStittsvilleCentral.ca
 
Cash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationCash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationStittsvilleCentral.ca
 
Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017StittsvilleCentral.ca
 
Zoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsZoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsStittsvilleCentral.ca
 
Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)StittsvilleCentral.ca
 
Official Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland PolicyOfficial Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland PolicyStittsvilleCentral.ca
 

More from StittsvilleCentral.ca (20)

Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookBill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
 
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsMayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
 
Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016
 
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadPublic Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
 
Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015
 
Ottawa BIA overview
Ottawa BIA overviewOttawa BIA overview
Ottawa BIA overview
 
Ontario BIA handbook 2010
Ontario BIA handbook 2010Ontario BIA handbook 2010
Ontario BIA handbook 2010
 
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsMemo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
 
Stittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept Plan
 
Stittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept Images
 
City of Ottawa Noise By-Law Review
City of Ottawa Noise By-Law ReviewCity of Ottawa Noise By-Law Review
City of Ottawa Noise By-Law Review
 
Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017
 
March 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaMarch 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of Ottawa
 
Memo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentMemo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendment
 
Cash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationCash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentation
 
Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017
 
Zoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsZoning application summary - Farmers' Markets
Zoning application summary - Farmers' Markets
 
Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)
 
Official Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland PolicyOfficial Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland Policy
 

Recently uploaded

AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerOmarCabrera39
 
Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfauroraaudrey4826
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaignanjanibaddipudi1
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...Ismail Fahmi
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Axel Bruns
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationReyMonsales
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Ismail Fahmi
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfauroraaudrey4826
 

Recently uploaded (16)

AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert Oppenheimer
 
Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdf
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and information
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdf
 

Kanata LRT Planning and Environmental Assessment Study

  • 1. Kanata Light Rail Transit Planning and Environmental Assessment Study Public Open House 1 June 5, 2017 Transportation Services Department
  • 2. 1 Open House Objectives • Introductions; • Study Overview; • Study Design and Schedule; • Identification of Alternative Corridors; • Corridor Evaluation Methodology & Initial Results; and, • Next Steps.
  • 3. 2 Study Goals • Determine the Preferred Corridor; • Determine the Recommended Plan for LRT alignment and stations; and, • Determine project staging and implementation.
  • 4. 3 Context for the Study • Confederation Line opens in 2018. • Stage 2 Extension of Confederation Line West opens in 2023
  • 5. 4 Study Schedule Spring 2017: Existing Conditions & Corridor Selection *Consultation Groups and Public Open House 1* Summer/Fall 2017: Evaluation of Designs *Meet with Consultation Groups* Fall/Winter 2017/18: Recommended Plan *Consultation Groups and Public Open House 2* *Present to Committee and Council* Spring 2018: Commence Transit Project Assessment Process Pre-Planning Phase EA Phase
  • 6. 5 Study Process • Environmental Assessment requirements addressed through Transit Project Assessment Process (TPAP); and • Documented in Environmental Project Report (EPR).
  • 7. 6 Guiding Principles • Provide transportation that complements the character and quality of the corridors and communities; • Respect the integrity of the natural environment & cultural and heritage traits; • Enhance the economic health of the study area; and, • Early, ongoing, inclusive and transparent stakeholder and public engagement.
  • 8. 7 Need & Justification • TPAP permits the City to rely on prior planning; • Potential corridors identified and assessed; and, • Ridership trends. – Significant number of trips cross the Greenbelt. • Half of Kanata jobs filled by Kanata residents. – Increase in internal trips being taken. • Mode split is currently only 3% for these trips.
  • 9. 8 LRT Requirements • Extension of Confederation Line. – Technology and geometric constraints set. – Completely grade separated. • One corridor. – Insufficient ridership for multiple corridors. – Branching of the line will be challenging.
  • 10. 9 TMP (2013) - Ultimate Network
  • 11. 10 TMP (2013) – Affordable Network Proposed Extension of LRT to Moodie (Stage 2)
  • 12. 11 Existing Conditions • Collect existing information based on desktop exercise; • Level of detail suitable for corridor evaluation; and, • More detailed analysis of conditions will be documented for the preferred corridor.
  • 13. 12 NCC Greenbelt Master Plan (2013) Shirley’s Bay Sector Plan Stoney Swamp Sector Plan
  • 22. 21 Alternative Corridors • 13 potential corridors identified. - North, South, and Central to Highway 417. - Palladium assumed as western terminus. • All compatible with proposed extension of LRT to Moodie (Stage 2).
  • 24. 23 Corridors (Central & South of HWY 417)
  • 25. 24 Corridor Screening Methodology • All 13 corridors subject to preliminary screening; and, • Combination of quantitative, qualitative, and comparative assessment. Least Preferred Most Preferred ■ ▲ ● Limited positive effect Major impact Highest cost Good positive effect Minor impact Moderate cost Greatest positive effect Negligible impact Lowest cost
  • 26. 25 Criteria Categories 1. Ridership Potential and Network Connectivity; 2. Transit Oriented Development & City Building; 3. Effect on Natural Environment; 4. Effect on Social Environment; 5. Complexity; and, 6. Capital and Operational Cost.
  • 27. 26 Corridor 1: Carling/March/Terry Fox Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ● ■ ▲ ■ ■
  • 28. 27 Corridor 2: Carling/Rail/Terry Fox Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ▲ ■ ▲ ▲ ■
  • 29. 28 Corridor 3: 417/Rail/March/Terry Fox Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ● ■ ■ ▲ ■
  • 30. 29 Corridor 4: 417/Rail/Terry Fox Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ■ ■ ■ ▲ ▲
  • 31. 30 Corridor 5: 417/March/Terry Fox Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ● ● ■ ▲ ■ ■
  • 32. 31 Corridor 6: 417/March/Rail/Terry Fox Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ■ ■ ▲ ■ ■
  • 33. 32 Corridor 7: 417/Campeau Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ■ ▲ ● ▲ ▲ ▲
  • 34. 33 Corridor 8: North Side of Highway 417 Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ● ● ● ● ● ●
  • 35. 34 Corridor 9: Highway 417 Median Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ● ● ▲ ■ ●
  • 36. 35 Corridor 10: South Side of Highway 417 Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ● ● ▲ ▲ ●
  • 37. 36 Corridor 11: Timm/Katimavik/Palladium Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ■ ▲ ▲ ▲ ▲ ▲
  • 38. 37 Corridor 12: TransCanada Trail/Hazeldean Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ▲ ▲ ▲ ■ ▲
  • 39. 38 Corridor 13: TransCanada Trail Ridership Potential & Network Connectivity TOD & City Building Opportunities Natural Environment Impacts Social Environment Impact Complexity Capital & Operational Costs ▲ ▲ ▲ ■ ▲ ▲
  • 40. 39 Preliminary Preferred Corridor Alignments 1 2 3 4 5 6 7 8 9 10 11 12 13 1. Ridership Potential and Network Connectivity ▲ ▲ ▲ ▲ ● ▲ ■ ● ▲ ▲ ■ ▲ ▲ 2. TOD & City Building Opportunities ● ▲ ● ■ ● ■ ▲ ● ● ● ▲ ▲ ▲ 3. Natural Environment Impacts ■ ■ ■ ■ ■ ■ ● ● ● ● ▲ ▲ ▲ 4. Social Environment Impacts ▲ ▲ ■ ■ ▲ ▲ ▲ ● ▲ ▲ ▲ ▲ ■ 5. Complexity ■ ▲ ▲ ▲ ■ ■ ▲ ● ■ ▲ ▲ ■ ▲ 6. Capital and Operational Costs ■ ■ ■ ▲ ■ ■ ▲ ● ● ● ▲ ▲ ▲ SUMMARY ■ ■ ■ ■ ■ ■ ▲ ● ▲ ▲ ■ ■ ■
  • 41. 40 Preliminary Preferred: Corridor 8 • Provides transit spine equally connecting all of Kanata • Supports future March & Fernbank BRT Corridors • No significant environmental or social impacts • Supports development objectives along route • Cost effective to build and operate
  • 42. 41 Additional Analysis • Based on feedback and ridership potential, further analyses is required for: - Corridors 5 and 13, alongside Corridor 8
  • 43. 42 Next Steps • Based on feedback from consultation groups and public, project team will: – Further analysis of Corridors 5, 8, 13; – Confirm the preliminary preferred corridor; – Develop alternative designs; and, – Develop recommended plan. • Public Open House #2 late 2017