SlideShare a Scribd company logo
1 of 27
Download to read offline
CM-307 – Site Development April 9, 2011
  Page 1 
 
Pratt Institute
CM-307 – Site Development
April 9, 2011
9:00 AM – 12:00 PM
Site Surveying Field Trip to Franklin D. Roosevelt, Four Freedoms Park
Construction Manager: Sciame
Student Participants:
Norman Chan
Kurtis Egan
Robert Fazio
Fidan Gjonbalaj
Petronilla Gonzalez-Magno
Andy Kim
Jonah Klein
Sandy Noisette
Industry Representatives:
Joseph Mizzi/Sciame
Andrew Sciame/Sciame
Anthony Turturro/Sciame
Avraam Papzoglou/Fehringer Surveying
As part of the curriculum of CM-307 Site Development the students met with
professional constructors at the construction site of the Franklin D. Roosevelt Four
Freedoms Park Project from 9:00 AM until 12:00 PM on Saturday, April 9, 2011.
The Franklin D. Roosevelt Four Freedoms Park is a public park designed by the late
Louis I. Kahn, and currently under construction on the south point of Roosevelt
Island in the East River of New York City. Sciame is the Construction Manager for
the project. Fehringer Surveying provides site surveying and establishes
benchmarks and axis lines for the project. Project completion is anticipated in the
spring or summer of 2012.
The students were introduced to the surveyor’s equipment:
- CST Berger AK-10 Automatic Level
- Rod
- Trimble S6 Total Station
The students worked under the supervision of a licensed surveyor to confirm an
elevation at the far end of the site from an established benchmark. The students
learned about front sights and back sights. The students worked in two groups of
four students each and recorded the elevations from the benchmark. The actual
CM-307 – Site Development April 9, 2011
  Page 2 
 
elevation difference was 12.0 feet, the surveying teams surveyed elevation
differences of 11.985 feet and 11.95 feet. The surveying sheets are attached.
Following the surveying exercise, the students were given a demonstration of the
capabilities of a Trimble S6 Total Station to provide layout for a theoretical
foundation to set stake points. The labor saving advantages of Global Positioning
System (GPS) based surveying technology was discussed, as well as the continuing
need to understand and apply sound surveying principles in order to avoid costly
errors in the field.
Other topics discussed included:
- Goals of site surveying
- The different means and methods of surveying
- Assessing accuracy and cost for different surveying methods
- Assessing site access
- Developing a site logistics plan
- Developing a site development phasing plan
- Developing accurate scope of work for the sub-contractors
- Coordinating the schedule of work for multiple sub-contractors
- Reviewing cost of leasing equipment: cranes, excavation equipment, etc.
- Working with the A/E team to identify and resolve constructability issues
Students and surveyors
CM-307 – Site Development April 9, 2011
  Page 3 
 
Architect’s rendering
Architect’s rendering
Phasing and logistics plan
CM-307 – Site Development April 9, 2011
  Page 4 
 
Waste characterization plan
Site trailer
Setting up
CM-307 – Site Development April 9, 2011
  Page 5 
 
Setting up
Surveying instructions
CM-307 – Site Development April 9, 2011
  Page 6 
 
Surveying tools
Sighting through the level
CM-307 – Site Development April 9, 2011
  Page 7 
 
Equipment discussion
Site benchmark
CM-307 – Site Development April 9, 2011
  Page 8 
 
Site benchmark
Sighting through the level
CM-307 – Site Development April 9, 2011
  Page 9 
 
Holding the rod
Rod station point
CM-307 – Site Development April 9, 2011
  Page 10 
 
Formwork for new river wall
Detail of rod
CM-307 – Site Development April 9, 2011
  Page 11 
 
Rod level
Student holding the rod
CM-307 – Site Development April 9, 2011
  Page 12 
 
Sighting through the level
Sighting through the level
CM-307 – Site Development April 9, 2011
  Page 13 
 
Sighting through the level
Detail of level
CM-307 – Site Development April 9, 2011
  Page 14 
 
Detail of south point
Detail of south point
Detail of west wall and rip-rap
CM-307 – Site Development April 9, 2011
  Page 15 
 
Detail of pumps at south point
Rod at south point
CM-307 – Site Development April 9, 2011
  Page 16 
 
Level sighting rod at south point
Crane
CM-307 – Site Development April 9, 2011
  Page 17 
 
Northwest edge of site
The results!
Team A survey results
CM-307 – Site Development April 9, 2011
  Page 18 
 
Team B survey results
GPS total station demonstration
CM-307 – Site Development April 9, 2011
  Page 19 
 
GPS total station demonstration
GPS total station demonstration
GPS total station demonstration
CM-307 – Site Development April 9, 2011
  Page 20 
 
Station point
GPS total station demonstration
CM-307 – Site Development April 9, 2011
  Page 21 
 
GPS total station demonstration
GPS total station demonstration
CM-307 – Site Development April 9, 2011
  Page 22 
 
GPS total station demonstration
GPS total station demonstration
CM-307 – Site Development April 9, 2011
  Page 23 
 
Site_Surveying_Class (2)
Site_Surveying_Class (2)
Site_Surveying_Class (2)
Site_Surveying_Class (2)

More Related Content

What's hot

Career History - Ross Ullman - March 2015
Career History - Ross Ullman - March 2015Career History - Ross Ullman - March 2015
Career History - Ross Ullman - March 2015Ross Ullman
 
Donald J resume Word 2 copy
Donald J resume Word 2 copyDonald J resume Word 2 copy
Donald J resume Word 2 copydon rawson
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingVDOT Northern Virginia
 
1 Resume
1 Resume1 Resume
1 ResumeF NADAL
 
13 October.Henley bfl report
13 October.Henley bfl report13 October.Henley bfl report
13 October.Henley bfl reportKate Watson
 
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)Seann Smith, AICP
 
SP-6-05 Flagler Avenue Retail-Residential Project
SP-6-05 Flagler Avenue Retail-Residential ProjectSP-6-05 Flagler Avenue Retail-Residential Project
SP-6-05 Flagler Avenue Retail-Residential ProjectSeann Smith, AICP
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016VDOT Northern Virginia
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020Fairfax County
 
Various Highways and Bridge design projects_Atkins UK
Various Highways and Bridge design projects_Atkins UKVarious Highways and Bridge design projects_Atkins UK
Various Highways and Bridge design projects_Atkins UKImran Siddiqui
 
Highway design raport(final) (group 2)
Highway design raport(final) (group 2)Highway design raport(final) (group 2)
Highway design raport(final) (group 2)haayaav
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck finalCrosstown TO
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingVDOT Northern Virginia
 
Jaimin Hooper - Resume
Jaimin Hooper - ResumeJaimin Hooper - Resume
Jaimin Hooper - ResumeJaimin Hooper
 

What's hot (20)

Career History - Ross Ullman - March 2015
Career History - Ross Ullman - March 2015Career History - Ross Ullman - March 2015
Career History - Ross Ullman - March 2015
 
Donald J resume Word 2 copy
Donald J resume Word 2 copyDonald J resume Word 2 copy
Donald J resume Word 2 copy
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
 
1 Resume
1 Resume1 Resume
1 Resume
 
13 October.Henley bfl report
13 October.Henley bfl report13 October.Henley bfl report
13 October.Henley bfl report
 
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
Preliminary Plat Staff Report (S-6-05 NSB SE Interchange)
 
SP-6-05 Flagler Avenue Retail-Residential Project
SP-6-05 Flagler Avenue Retail-Residential ProjectSP-6-05 Flagler Avenue Retail-Residential Project
SP-6-05 Flagler Avenue Retail-Residential Project
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
curriculum vitae
curriculum vitaecurriculum vitae
curriculum vitae
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020
 
GOVIND LATWAL
GOVIND LATWALGOVIND LATWAL
GOVIND LATWAL
 
Drawing And Report
Drawing And Report Drawing And Report
Drawing And Report
 
Various Highways and Bridge design projects_Atkins UK
Various Highways and Bridge design projects_Atkins UKVarious Highways and Bridge design projects_Atkins UK
Various Highways and Bridge design projects_Atkins UK
 
Highway design raport(final) (group 2)
Highway design raport(final) (group 2)Highway design raport(final) (group 2)
Highway design raport(final) (group 2)
 
Richard Greeley
Richard GreeleyRichard Greeley
Richard Greeley
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
Jaimin Hooper - Resume
Jaimin Hooper - ResumeJaimin Hooper - Resume
Jaimin Hooper - Resume
 

Similar to Site_Surveying_Class (2)

I495 route 9 sac meeting 1 9 8-11
I495 route 9 sac meeting  1 9 8-11I495 route 9 sac meeting  1 9 8-11
I495 route 9 sac meeting 1 9 8-11absnakcac
 
Report 2013 - 2014
Report 2013 - 2014Report 2013 - 2014
Report 2013 - 2014Bavik Sing
 
PowerPoint Westmoreland Street Bike Lanes - substantial completion
PowerPoint   Westmoreland Street Bike Lanes - substantial completionPowerPoint   Westmoreland Street Bike Lanes - substantial completion
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16Don Dwyer
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road WalkwayFairfax County
 
Morgantown progress 20110110_mpo
Morgantown progress 20110110_mpoMorgantown progress 20110110_mpo
Morgantown progress 20110110_mpoJing Zhang, AICP
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk Fairfax County
 
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook Trail
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook TrailSubstantial Completion - HMSAMS-Innovation Center to Arrowbrook Trail
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook TrailFairfax County
 
03. Highway Planning and highway components.pptx
03. Highway Planning and highway components.pptx03. Highway Planning and highway components.pptx
03. Highway Planning and highway components.pptxGhulam Mehdi Sahito
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docxVijay Kumar
 
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
 

Similar to Site_Surveying_Class (2) (20)

I495 route 9 sac meeting 1 9 8-11
I495 route 9 sac meeting  1 9 8-11I495 route 9 sac meeting  1 9 8-11
I495 route 9 sac meeting 1 9 8-11
 
Report 2013 - 2014
Report 2013 - 2014Report 2013 - 2014
Report 2013 - 2014
 
Technical Report
Technical ReportTechnical Report
Technical Report
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
PowerPoint Westmoreland Street Bike Lanes - substantial completion
PowerPoint   Westmoreland Street Bike Lanes - substantial completionPowerPoint   Westmoreland Street Bike Lanes - substantial completion
PowerPoint Westmoreland Street Bike Lanes - substantial completion
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
PM tools and techniques
PM tools and techniquesPM tools and techniques
PM tools and techniques
 
Morgantown progress 20110110_mpo
Morgantown progress 20110110_mpoMorgantown progress 20110110_mpo
Morgantown progress 20110110_mpo
 
Quander Road Walkway
Quander Road WalkwayQuander Road Walkway
Quander Road Walkway
 
convert_255356
convert_255356convert_255356
convert_255356
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk
 
Frank.Vrenjak.2
Frank.Vrenjak.2Frank.Vrenjak.2
Frank.Vrenjak.2
 
John Asuquo
John AsuquoJohn Asuquo
John Asuquo
 
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook Trail
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook TrailSubstantial Completion - HMSAMS-Innovation Center to Arrowbrook Trail
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook Trail
 
03. Highway Planning and highway components.pptx
03. Highway Planning and highway components.pptx03. Highway Planning and highway components.pptx
03. Highway Planning and highway components.pptx
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docx
 
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
 

Site_Surveying_Class (2)

  • 1. CM-307 – Site Development April 9, 2011   Page 1    Pratt Institute CM-307 – Site Development April 9, 2011 9:00 AM – 12:00 PM Site Surveying Field Trip to Franklin D. Roosevelt, Four Freedoms Park Construction Manager: Sciame Student Participants: Norman Chan Kurtis Egan Robert Fazio Fidan Gjonbalaj Petronilla Gonzalez-Magno Andy Kim Jonah Klein Sandy Noisette Industry Representatives: Joseph Mizzi/Sciame Andrew Sciame/Sciame Anthony Turturro/Sciame Avraam Papzoglou/Fehringer Surveying As part of the curriculum of CM-307 Site Development the students met with professional constructors at the construction site of the Franklin D. Roosevelt Four Freedoms Park Project from 9:00 AM until 12:00 PM on Saturday, April 9, 2011. The Franklin D. Roosevelt Four Freedoms Park is a public park designed by the late Louis I. Kahn, and currently under construction on the south point of Roosevelt Island in the East River of New York City. Sciame is the Construction Manager for the project. Fehringer Surveying provides site surveying and establishes benchmarks and axis lines for the project. Project completion is anticipated in the spring or summer of 2012. The students were introduced to the surveyor’s equipment: - CST Berger AK-10 Automatic Level - Rod - Trimble S6 Total Station The students worked under the supervision of a licensed surveyor to confirm an elevation at the far end of the site from an established benchmark. The students learned about front sights and back sights. The students worked in two groups of four students each and recorded the elevations from the benchmark. The actual
  • 2. CM-307 – Site Development April 9, 2011   Page 2    elevation difference was 12.0 feet, the surveying teams surveyed elevation differences of 11.985 feet and 11.95 feet. The surveying sheets are attached. Following the surveying exercise, the students were given a demonstration of the capabilities of a Trimble S6 Total Station to provide layout for a theoretical foundation to set stake points. The labor saving advantages of Global Positioning System (GPS) based surveying technology was discussed, as well as the continuing need to understand and apply sound surveying principles in order to avoid costly errors in the field. Other topics discussed included: - Goals of site surveying - The different means and methods of surveying - Assessing accuracy and cost for different surveying methods - Assessing site access - Developing a site logistics plan - Developing a site development phasing plan - Developing accurate scope of work for the sub-contractors - Coordinating the schedule of work for multiple sub-contractors - Reviewing cost of leasing equipment: cranes, excavation equipment, etc. - Working with the A/E team to identify and resolve constructability issues Students and surveyors
  • 3. CM-307 – Site Development April 9, 2011   Page 3    Architect’s rendering Architect’s rendering Phasing and logistics plan
  • 4. CM-307 – Site Development April 9, 2011   Page 4    Waste characterization plan Site trailer Setting up
  • 5. CM-307 – Site Development April 9, 2011   Page 5    Setting up Surveying instructions
  • 6. CM-307 – Site Development April 9, 2011   Page 6    Surveying tools Sighting through the level
  • 7. CM-307 – Site Development April 9, 2011   Page 7    Equipment discussion Site benchmark
  • 8. CM-307 – Site Development April 9, 2011   Page 8    Site benchmark Sighting through the level
  • 9. CM-307 – Site Development April 9, 2011   Page 9    Holding the rod Rod station point
  • 10. CM-307 – Site Development April 9, 2011   Page 10    Formwork for new river wall Detail of rod
  • 11. CM-307 – Site Development April 9, 2011   Page 11    Rod level Student holding the rod
  • 12. CM-307 – Site Development April 9, 2011   Page 12    Sighting through the level Sighting through the level
  • 13. CM-307 – Site Development April 9, 2011   Page 13    Sighting through the level Detail of level
  • 14. CM-307 – Site Development April 9, 2011   Page 14    Detail of south point Detail of south point Detail of west wall and rip-rap
  • 15. CM-307 – Site Development April 9, 2011   Page 15    Detail of pumps at south point Rod at south point
  • 16. CM-307 – Site Development April 9, 2011   Page 16    Level sighting rod at south point Crane
  • 17. CM-307 – Site Development April 9, 2011   Page 17    Northwest edge of site The results! Team A survey results
  • 18. CM-307 – Site Development April 9, 2011   Page 18    Team B survey results GPS total station demonstration
  • 19. CM-307 – Site Development April 9, 2011   Page 19    GPS total station demonstration GPS total station demonstration GPS total station demonstration
  • 20. CM-307 – Site Development April 9, 2011   Page 20    Station point GPS total station demonstration
  • 21. CM-307 – Site Development April 9, 2011   Page 21    GPS total station demonstration GPS total station demonstration
  • 22. CM-307 – Site Development April 9, 2011   Page 22    GPS total station demonstration GPS total station demonstration
  • 23. CM-307 – Site Development April 9, 2011   Page 23