1. Eng. Samir Abdel Fattah 1 Mechanical Engineer
CURRICULUM VITAE (CV)
Date: 10.6.2016
Name: SamirAhmed Abdel Fattah E-mail: samiraafattah@yahoo.com
Mobile: 002 0100 1216181
Current Post: Infrastructure Project Manager / MEP Manager
Name of Firm : Projacs International
ProjectName: City Stars Sharm El SHeikh , Egypt
-----------------------------------------------------------------------------------------------------------------------------------------
Previous PostYear2014: MEP ProjectManager
Name of Firm: SuperStyle Company - UAE
-----------------------------------------------------------------------------------------------------------------------------------------
Previous Post Year 2012 - 2013: Projects Manager
Name of Firm: PICO for Real Estate Investments - Egypt
------------------------------------------------------------------------------------------------------------------------------------------
Previous Post Year2008 -2011 & Related Portfolio: City ManagementP.M. / MEP ProjectManager
Infrastructure & Roads Portfolio
Name of Firm: AFGRE Al-Futtaim Group Real Estate - Egypt
------------------------------------------------------------------------------------------------------------------------------------------
Previous Post Year2006 – 2007& Related Department: Project Manager / ElectromechanicalSupervi
sion Engineer/ Water& Sanitation Specialist-International Operations Department
Name of Firm: Dr. Ahmed Abdel-Warith Consulting Engineers, AAW- Algeria - Mo
rocco - Rwanda - Egypt
------------------------------------------------------------------------------------------------------------------
Previous Post Year2005 : Head of MechanicalCost Estimation Department
Name of Firm: CONTRACK –INTERNATIONAL/ ORASCOM OCI
Group Companies between Contrack International USA and Orascom OCI -
Egypt
--------------------------------------------------------------------------------------------------------------------------------------
PersonalData:
Profession: B.Sc.Mechanical Engineering-Power /CairoUniversity Faculty ofEngineering / July 1990
Date ofBirth: 28th November 1967 Age: 47 years Years of Experiences: More than 25 years
Address: Bldg.142 BeverlyHills Sheikh Zayed - 6 October City / Egypt
Mobile/Tel.: 002 0100 1216181 / 002 38571614 UAE Mobile: 00971 5555 30540
Nationality: Egyptian Marital Status: Married,4 children
2. Eng. Samir Abdel Fattah 2 Mechanical Engineer
Membership in ProfessionalSocieties: Egyptian SyndicateofProfessional Engineers.
Membership in SocialSocieties : ShootingClub.
Have a Valid UAE driving Licence
Key Qualifications:
Professional Experienceat thefollowingdomains:
Real EstateInfrastructureutilities and networks
Water Treatment Plants (dams stored water,surfacewater,deep well water,desalinated water
R.O.).
WasteWater Treatment Plants (sewage,drainage,reused).
Water Sources and Resources.
Sanitation.
High PressurePump Stations(Potable,sewage).
Water Hammer Protection Systems (waterpipelines,sewageforcemains).
Firefightingsystems and firefightingpump stations systems.
Boiler rooms and heat exchangers for steam generatingand heatingsystems for touristic
villages.
MEP Works for residential and commercial buildings
Electromechanical works for Olympic swimmingpools.
Plumbing,Sanitaryand Environmental works and therelated pipenetworks for potablewater,
sewagenetworks,irrigation networks,firefightingand forcemain lines.
Industrial Manufacturingfor theHigh Pressurevessels applied for Water Hammer protection
reservoirsup to90 m3 capacity and 25 barworkingpressure,Pressurized Sand and Media
Filters for water purification and treatment.
Steel Fabricated compact treatmentplants ,and all steel and stainless steel manufacturing
applications up to30mm thickness,usinghigh technology automatic and semi automatic
weldingtechniques and insulation paintsapplications.
MV and LV Substations, Transformer Rooms and Stand by Generators.
HVAC & Ventilation Works for Residential and Commercial buildings
Education:
ㄱ SchoolEducation, Frere Bab El Look year 1972 – 1983 Primaire et Preparatoire
College de la Salle year1982 – 1985 Secondaire
ㄴ BachelorofScience, CairoUniversity- Faculty ofEngineeringEgypt, June 1990.
Major:Mechanical Engineering Department:Power.
Grade: Good; Projectgrade:Excellent
ㄷ ProfessionalCertificate , AmericanUniversity in Cairo AUC,Egypt 2000
Major:Design and Operation of Water Treatment Plants
Grade: Excellent
ㄹ ProfessionalCertificate , AmericanUniversityin CairoAUC, Egypt 2006
Major: Design and Operation of WasteWater Treatment Plants
Grade: Excellent
ㅁ ProfessionalCertificate , MENA Chapter PMI , Egypt. 2010
Major: Successful Completion of PMP Preparation Exam
MENA Recognition
3. Eng. Samir Abdel Fattah 3 Mechanical Engineer
Languages:
Language Reading Speaking Writing
Arabic (Mother Tongue)
English Excellent Excellent Excellent
French Excellent Excellent Excellent
Professionalcourses
AUTOCAD 1996
PRIMAVERA-P3, 1998.
Participation Certificatefor theDesign and Construction ofPipingSystems AUC2006.
Participation Certificatefor theDesign principles for air conditioningsystems ASHRAE
2005.
Participation Certificatefor theDesign principles for refrigeration systems ASHRAE 2005.
4. Eng. Samir Abdel Fattah 4 Mechanical Engineer
EmploymentRecord:
February2015 - Current : Projacs International
Post: MEP Manager
Project : City Stars Sharm El Sheikh / Egypt
The projectCity Stars @ Sharm El Sheikh had started, since Jan 2015, MEP & Infrastructure as well
as Finishes and some remaining civil works with cost budgetof 800 Millions L.E.
The projectcivil works, alreadystarted by year 2008, had reached a phase of main utilities and infra
structure with considerable costbudgetthat aimed to be ended within this year. FairmontHotel &
Swiss Otel planned to be renovated and soft opening by mid years 2016 and 2017consecutively. The
projects encounters 4 R.O. desalination plants capacity 4500 cubic meter per day each serving phas
e 1 and 2 as well as 4 sewage treatmentplants capacity of 3000 cubic metres per day each. The infra
structure networks have a massive work for sewage, potable and non potable water, MV and LV el
ectrical cable networks and its related distributors and transformer rooms in addition to low curren
t networks.
Main building and centrallaundry and kitchen in addition to existing hotel rooms and staff accom
modation rooms constitute a massive MEP works for chilled water plants and its networks up to FC
Us and air side related to AHUs, Fire fighting and fire alarm, plumbing and electrical works have
considerable weight.
The projacs projectmanagementand construction managementteam is composed of 6 on site and 6
at head office. Being onsite acting P.M. for budgetof more than 300 Millions L.E. it constitutes a co
nsiderable challenge that I have been successfully reaching almost80% of the required targetprogr
ess within a year.
-------------------------------------------------------------------------------------------------------------------------------------
February2014 - Jan 2015 Super Style Electromechanicalworks L.L.C. UAE
MEP ProjectManager - HVAC / F.F. & F.A. / Plumbing / Electrical & Low Current & BMS
- ManagingMEP works for Shamal School Ras Al Khaimah , with theclient MOP
W, Ministry ofPublic works and Main Contractor Al Nuaimi group
The project main MEP components includethesupply and installations for # 3 Chillers each of cap
acity 200TR and # 12 AHUs and # 2 FAHUs in addition toprimary-secondarychilled water pumps.
Firefightingsystems comprise2500sprinklersin addition to6 hydrants and 18 FHC as well as main F.F.
pump station havingelectrical,diesel and jockey pumps for main duty of 1000GPM@ 10 bar.
GRP Tanks capacities varyingfrom 300 cubic meters till 15 cubic meters weresupplied and installed serv
ing firefightingstoragerequirements as well as Domestic watertransfer pumps and its R.O.and filtratio
n units for water coolers use.
The project electrical load is 2.6 MW supported by twotransformers each ofcapacity 1.5 MW ,and distri
buted electrical loads arefulfilled through low voltagemain distribution boards and 5 MDBs and
10 SMDBs.
It worth mentioningthatchilled water system used pipes wereABS pipes (euro pipe) sizes startingas of
12 inch till feeding theAHUs & FAHUs water sidesizes 3 & 2 inch,thesystem was controlled through
5. Eng. Samir Abdel Fattah 5 Mechanical Engineer
pressureindependent control valvePICVs and controlled through BMS system tocontrol theflow accor
ding toDP sensors.Air flow is controlled via VAVs,pressureand temperaturesensors.
2012 - 2013 PICO for Real Estate Investments - Egypt : Projects Manager
Responsible for construction supervision of Water Pumping Station 20000 m3/hr and its main l
ine precastconcrete 1000mm diameter.
November2010 – December2011 Al Futtaim Group Real Estate - Cairo Festival City / New Cairo C
ity
Project Manager – City Management
SustainableIntegrated Operations is themain topic thatIwas in chargeduringthe1st pha
se of CFC program.Roles & Responsibilities weredirectlyshaped which weremainly bein direct relati
ons tomanagingOperations for thewhole Infrastructures includingits main Utilities as well as Buildin
gs main MEP works.
Jan 2008 – October2010 Al Futtaim Group Real Estate - Cairo Festival City / New Cairo City
MEP Project Manager – Infrastructure & Roads Portfolio
The project comprises theprovision ofmain infrastructureutilities for CairoFesti
val City Project.ProjectPhaseIwas fulfilled within thelast 2008 quarter and the1
st quarter 2009 and currently thesecond main phasefor Infrastructurecontractare
expedited by theMain Contractor Al Futtaim Carillion tostartthemain Infrastruc
tureprojects as ofJanuary 2010.Theproject is located at NewCairoCity,on a total
area of 700 Feddans.The CairoFestival City Master Plan comprises lifestylearea
of 500 privatevillas phased on 3 phases,and residential buildings;retailarea comp
rises an international brand names mall on 4 levels,as well as a mixed use buildin
gs, and in addition tothat twohotels areplanned.
My main scope comprised thefollowing:
Modification of gas pipelinediameter of 10 inch and length over 2 km,
through thegovernmental entity PipePetroleum Company.
Provision ofHDPE water networks diameter of355mm and lengths up to4
kms.
Provision ofM.V. cableas well as energizingmain distributor room and its
related fivetransformer rooms capacity of16 MVA, cables length of 6 km
loop.
PotablewaterPump Stations containingmain Water&Irrigation Reservoirs
each of capacity 5000m³/day,withall related electromechanical booster
systems and managementand utilities building.(Amongst City
Management Scope)
Main SewagePump Station and prospected SewageTreatment Plant.
Coordination withall related main networks,for sewage,water,irrigation
6. Eng. Samir Abdel Fattah 6 Mechanical Engineer
MV electrical networks,as well as telephonenetworkand street lighting
and remainingutilities such as District CoolingPlant and MainElectrical
Substation.(Amongst City managementScope)
2006 – 2007 Dr. Ahmed Abdel-Warith Consulting Engineers, Egypt
Project Manager / ElectromechanicalSupervision Engineer/ Water & Sanitatio
n Specialist
International Operations Department
Year 2006
Provision ofpotablewater toTlemcen city from Sekkakdam. The project is locate
d at Tlemcen city,West ofAlgeria. The objectiveoftheproject is tosupply potabl
e water toTlemcen city and it includes thefollowingcomponents:
Water treatmentplantofcapacity 20000 m³/day
Treated water reservoir 5000 m³/day
Treated water pumpingstation (SP1)and electric substation
Operatingbuildings
Office buildingand laboratory
Transmission lines (pipelineDiameter 700mm steel)from the intaketothe
water treatmentplant and reservoirand from the reservoirtotheraw water
tank( pipeline Diameter 800mm D.I.) with capacityof1000 and 5000m³;
travel length over 35 km for total transmission lines for thethreehigh
pressurepump stations up tothemain reservoir.
Water Hammer Protection systems capacities for hydropneumatic tanks
areof 45 m3, 20m3 and 22m3 capacities consecutively.
Two additional booster stations SP2 and SP3 of capacity 65000 m³/day.Each
booster associated ofone reservoir of1000m³ capacity,pump station
buildingand electric substation and administration building.
Year 2007
Several ConsultancyMissions havebeen taken placeduringthis year
and for different International standard Clients. i.e.,L office National
de L eau Potable(ONEP) Morocco- actingas General Coordinator for
Huitieme Project BADD alimentation en Eau Potableet
D”assainissement. MINITERE RWANDA actingas Project Manager/
Water &Sanitation SpecialistEngineer for theconsultancy
team(6persons,3 professors and 3 engineers).Besides a lot of
international consultancy Tenders participations (amongthem wasAl-
Futtaim Infrastructure&Roads)as well as project managingdesign
teams for JV Tenders with Orascom for hugeWater & WasteWater
Tenders,one of them was theWater treatmentplantof4Million cubic
meter per day and its main 2000mm pipelines and booster pump
station,a project of500 Million U.S.Dollars, one of thebiggest cost
estimated projectin Egypt.
7. Eng. Samir Abdel Fattah 7 Mechanical Engineer
Jan 2005 – Dec 2005 CONTRACK –INTERNATIONAL/ ORASCOM OCI
Group Companies betweenContrackInternationalUSAandOrascom OCIEgypt
Head of MechanicalCost Estimation Department
Tender cost estimation for Plumbic and Firefightingand HVAC, as well as
Special Systems such as WTP,WWTP,Fuel systems ,Diesel Electric power suppl
y stations ,Military and Airfield applications etc…
Study technical and cost estimates for plumbing;pump stations,water
treatmentplants,and firefightingworks,heatingventilation and air
conditioningsystems for projects in Egypt and at Bahrain.
Describethe design needs requested to be fulfilled by CSG ( Contrack
Stanley Group USA/Egypt)
Design Review for plumbing,mechanical systems,water hammer
protection systems,firefightingsystems,HVACsystems,water and waste
water treatmentsystemsfor military and aviation projects in Egypt and
abroad.
Coordination and justification for thetechnical and financial suppliers
offers.
Development for the technical and financial electromechanical tenders,as
well as coordination with the head office at theUSA for theinternational
submission oftenders.
Study and preparethematerial listfor procurementissues.
2004 – 2004 Arab Engineering Office/ Ibrahim Adel & Partners
ProjectManager
Responsibilities included:
Follow up 10 water treatment plants in el Wadi El Gedid ( New Valley ),
capacity of200 and 300 meters cubic per hour;contractof 14 millions L.E.
Follow up civil and mechanical engineers
Follow up installationstimeschedule
Coordinatewith governmental engineers
One year job fulfilled with high performance
2003 – 2004 QATAR BUILDING ENGINEERING CO. Doha/QATAR
ElectromechanicalDesign Engineer
Responsibilities included:
Fully responsiblefor Plumbingand firefightingworks for Qatar Petroleum
Central Office at Mesaeed, as well as follows up HVAC subcontractorand
Electrical Tradeand coordinates with civil and architectural trades.
Prepareshop drawings and Follow up engineers for plumbingand fire
fightingworks.
Pick up materialsfrom drawings and issuepurchaseorders.
Follow up Construction and installation for plumbingand networks.
Coordinatewith QA/QC beforeinstallations.
PrepareDraft for monthly invoice.
2001 – 2003 Arab Engineering Office/ Ibrahim Adel & Partners
8. Eng. Samir Abdel Fattah 8 Mechanical Engineer
Deputy GeneralManager
PreparingCost analysis for tender offers as well as preparingplanning
phases for project procedures accordingtotimescheduleand resource
scheduleagainst cash flow charts (budget range500 000 L.E. up to 15
Millions L.E).
Supervision &follow up projects technically,financiallyand coordinating
with financial manager,siteengineers and my general manager,as well as
follow up issuanceof monthly invoices and comparingdeviations from the
planned cash flow and updatingdeviations (budget range30 Millions L.E.).
Attendingmanagerial and technical meetings with clientsand project
managers for reviewingproject status,makingagreementsfor material
supplies,technical decisions as well any related timescheduleplans and
clarifications).
Follow up technical office department for preparingand issuingtheshop
drawings for theconcerned projects as well as themanufacturingshop
drawings and makingsurethat thedrawings areaccordingtocodes
technically as well as approvingthedrawings good for construction and/or
manufacturing.
Designing special topics such as:
Water Hammer Protection Systems.
SewageTreatment Plants.
Water Treatment Plants.
Boiler Room for special uses.
Electric StorageHeaters and Steam StorageHeaters.
SwimmingPools Olympic as well as ArtificialLakes.
Domestic water pump station And firefightingpump station.
PlumbingSystemsincludingall related topics and networks.
1999 – 2001 Arab Engineering Office/ Ibrahim Adel &Partners
ProjectManagementDepartmentManager
Scope of work:
Preparingand PlanningProject TimeSchedules,material listcost
estimation,cash flow charts for Plumbing&mechanical contractproject
Holliday Inn (Crown Plaza)Sharm El Sheikh Touristic Beach Resort
Capacity of450 guest rooms (budget of 6.5 Millions L.E. & 510 000 $ as
well as 2.5 Millions L.E. Variation Orders and Extra Works).Handed Over
October 2001.
Preparingand PlanningProject TimeSchedules,material listcost
estimation,cash flow charts for Plumbing& mechanical contractproject
Sol Elite (Coral Melia) Touristic Beach Resort Capacity of350 guest rooms
(budget of 6 Millions L.E. & 610 000 $ ). WorkContract Progressof50%.
Postponed by client sinceJuly 2000.
Procurement ConsultantApproval &Purchasingorders for all equipments
and materials locallyand imported supplied.
In chargeof issuingshop drawings for all plumbingand mechanical works.
Follow up workprogress on siteduringperiodic visits and attending
9. Eng. Samir Abdel Fattah 9 Mechanical Engineer
monthly and technical meetings.As well as attendingcoordination
meetings at theconsultant head officeto coordinatewith other trades.
Detail of tasks duringthis period :
First Phase:
Employment of engineers,trainingthem for appropriatetasks such as
technical officeengineer as well as employment of siteengineers.
Study of contract conditions and specifications and drawings and bill of
quantities.
Planningand preparingWorkTimeSchedule for all activities by using
PrimaveraSoftwareProgram.
Planningand preparingmaterial List Technical Submittals.
Planningand preparingShop Drawings.
Second Phase:
Preparingtechnical data and catalogues for all materials.
Procurement consultant approval for material technical data.
Preparingand issuingshop drawings for all plumbingand mechanical
works.
Procurement consultant approval for shop drawings.
Attendingtechnical meetings and coordination meetings as well as
monthly sitemeetings
Third phase:
Issuingpurchaseorders for imported materials and follow up opening
letter of credits for foreign supplies.
Follow up workprogress on siteand visitingthesites Sharm El Sheikh
periodically as well as someother projects at different places.
Preparingmonthlyforecastschedules.
Issuingand follow up purchaseorders for local material supplies.
Coordinate,with theowner project manager and his engineers,thescope
and progress of works.
Coordinate,with theowner consultant officeand his representatives,the
technical procedures for installation,commissioningand handingover.
Issuingand follow up monthly workcertificates.
1997 – 1999 ARAB ENGINEERING OFFICE
Cost Estimator and Technical Office Manager
During this Period I had successfully managetoincreasetender offers acceptance
budget up to 20 Millions L.E., as well as follow up workbudget of 5 Millions L.E.
Scope of work:
In chargeof study technical specificationsand design drawings and
preparingand pricingbill ofquantities for tender offers.
In chargeof discussingand attendingtender procurements.
Follow up the suppliers offer prices.
In chargefor follow up shop drawings and all projectstechnical data.
In chargefor follow up and monitoringtimescheduleand workprogress
for all thecompany projects.
10. Eng. Samir Abdel Fattah 10 Mechanical Engineer
1995 – 1997 Abou Youssef Contracting & Trading Office (Swim. Pools and Jacuzzi agent)
ProjectManager
Scope of work:
Supply and install and testing,commissioning,and startup all electromechanical
works for Olympic SwimmingPools – Ahly National Club atMadinatNasr (budg
et of 4 Millions L.E).
1994 – 1955 Saad Hanna Sons Contracting and Trading Co.
SeniorSite Executive Engineer
Scope of work:
In chargeof installations and testingfor all plumbingand firefighting
works includingmain networks for INTERCOTINENTAL SHARM EL
SHEIKH, capacity of250 guest rooms (budget of 1.5Millions L.E.).
In chargeof attendingtechnical sitemeetings and issuingmonthly
certificates.
In chargeof studyingany variation orders,and issuingmonthlywork
invoicecertificates.
In chargeof studyingany variation orders and issuingsitedrawings for
approval.
1993 – 1994 Sinai Company for Touristic Development
SHEIKH COAST SHARM EL SHEIKH/Seconded from Crown Home Consulta
nt Eng. Ahmed Tag
Plumbing & Mechanical& HVAC Supervision Engineer
Scope of work:
Supervision Engineer for all Plumbing&Mechanical & HVAC works for
SHEIKH COAST BEACH RESORT Phase1 at sharm el sheikh,capacity of
58 suites and 250 chalets and 500 guest rooms and 36 privatevillas (budget
of 30 Millions L.E.).
Details of my personal tasks,duties,responsibilities and activities within
this period:
In chargeof coordinatingPlumbingand Mechanical and HVAC trades with
all other trades (i.e. electrical and civil works and landscape).
Sitesupervision for electromechanical works tobecopingtheconsultant
specifications and standard codes.
In chargeof approvingor rejectingworktestsheld on siteon daily basis.
In chargeof revisingmonthlypayment certificateand signingas first
signature.
In chargeof attendingtechnical sitemeetings.
In surplus totheabove-mentioned tasks,Ihad theopportunitytosupervise
theItalian contractors for thespecial works such as Desalination Plant
Capacity of600m³/d as well as SewageTreatmentPlantcapacityof
900m³/d.
11. Eng. Samir Abdel Fattah 11 Mechanical Engineer
1990 – 1993 Arab Engineering Office Electro-mechanical contractor
ProjectSite Engineer
My scope of workwithin this period wasthefollowingprojects:
Plumbingand mechanical works for Touristic VillagePALMARIVA
HURGHADA (SOFITEL NOWADAYS), capacity of312 guest rooms,
package lump sum contract budget of4 Millions L.E. & 500 000 $.
Mechanical works for Crazy Water entertainment water city at six October
city.
Mechanical works for domestic booster pump station and sewage
treatmentplant athighly secured prison at AbouZaabal.