Mr Liam Joseph Henry.
Senior Site Manager/Construction Manager / Package Site Manager.
Construction / Rail
London Work Address
Flat 1
325 Purely way
Waddon
East Croydon
CR0 4NU
-----------------------------------------------------
Home Address
9 Woodville Avenue
Middleborough
Cleveland
TS4 3BE
Mobile 07576-348955
Email Address hcml50@outlook.com.
Skype address Liam.Henry175
DOB 01/02/1966.
Available Start date 2016 need to give notice at current contract.
Freelance or Direct
Personal profile
I am a highly experienced, well organized and motivated professional, with a keen eye for detail. Has a proven
ability to work extremely well under pressure, effectively and efficiently. I have a can do attitude with the ability to
lead and meet deadlines in plenty of time. I am an innovative thinker with strong ambitions and is known not to
fail atwhatever task is given and constraints putupon me .
Currently, I am seeking a new career opportunity, either permanent or contract, to utilize my strong skills and
qualifications. As an individual with the determination to succeed, I believe I would be a great asset to any
organization. I have excellentcommunication skillswith exceptional stakeholder management skilled.
Looking at working around the uk and travel and accommodations will be in my own my costs within the day work
rate i get agreed with clients or Agency .
Projects workingon Now
Started 1st /8/2016
Drivingthe project to completion
Permasteelisa Uk ltd
Novetel Hotel projects 40 floors Tower canary wharf
Freelance contractRole Construction Manager.
1)Construction Manager Prater Ltd (Drivingthe project)
completed on the 1st end of contract .
London Bridge Train station Redevelopments Project Network Rail & Constains Constriction Ltd 15 Platforms .
Cladding and Curtain walling and steel packages and directing Prater ltd In house Management Team to there in
house policies and directing to keep to program dates And supervising all Prater subcontractors ,steel
erectors/painters /cladders/curtain-wallers/Roofers/ coded welders.
Senior sitemanager Driving the project to completion
2)Caddicks construction Group 50 Apartments at York train station refurbishments £5million on time and Budget.
3)Construction Manager Drivingthe projectto completion )
Lidi / Tesco Projects On behalf Johnson Construction Group.
4) Construction Manager drivingthe projects)
Student accommodations New Builds for Watkins and Jones group Uk wide as freelance site manager or
subcontractor and Others.
5)Construction Manager)
New build construction projects,Tower blocks /Health Centers / Listed buildings.
6)Construction Manager)
Refurbishments in all styles of building,from£2 million to £20 Million
7) Senior Construction Manager Alu Nasa MiddleEastQatar .
Drivingseveral projects with international workforcemainly Asian )
Football Stadiums in Qatar steel and cladding/ Curtain Walling for the royal family for 2022 world cup
7) Senior Construction Manager Drivingthe projects to completion)
A new state of the art Library,for HRH Sheik Mossa in Doha Qatar .
8) Site Manager ibex Interiors
Drivingthe project to hand over )
NHS refurbishments UK wide fasttrack out of hours projects C4 head office£14Miliion
9) Site Manager)
Claddingall systems on tower blocks UK wide and Europe Freelance For Agencies.
10) Senior Construction Manager)
Large Solar projects UK wide.£500 Million pounds projects in total 2014& 2015.
DrivingThe projects Forward .
11) Senior Construction Manager and advisory and drivingtheprojects to completion.
Multinational projectand investments company’s Conergy Uk Large solar projects
12) Site Manager freelance)
Kier Construction Ltd £35 Million New Build of a mental health centre and secure unit in Wigan.
13)Site Manager )
Screw-fix frame works fitout across theUK..
14) Site Manager 3 blocks Drivingthe projects )
Social Housingapartments blocks in Gibraltaron behalf of the Gibraltar Governments /UK Governments.
Strong finishingdetailson internals and externals finishesacross all modes of the construction phases.
Employment History
Currently working on freelance roles for Kalcrest Agency for Caddicks Group Ltd .
D&B £5 million refurbishments of 50 apartments at York train station New roof, EWI Render and parklex
cladding products and rain screen cladding metsec and Cp boards finish with EPDM finishes .
Also phase 2 and phase 3 internals packages drywall and all M/E works .
Senior Construction Consultant/Senior Project Manager (Conergy UK) 6 months contract completed please
see references
Consulting with all international Project Managers for Conergy UK for the following duties:
CDM legislation
HSE legislation
Installinglocal and UK civil contractorswith proven solar experience.
Meeting programdates and related financial constraints.
Overseeing all siteconstruction and related activities.
Client- Local Government/Council and Council.
Site facing.
Weekly/monthly meetings (onsite) as and when required.
CDM health and safety facingand any other related safety issues.
Duties
• Overseeing all ProjectManagers and Sub-Contractors to ensure they are meeting company deadlines and
meeting installation specifications
• Installingall SiteManagers through LH Site Management Ltd
Apr 2013 to Apr 2014 Senior Construction Manager (Alu-Nasa Part of Salaam International Investments
group)
A specialistfaçadecontractor,undertakinghigh risecommercial projects hotels and leisureprojects
Qatar National library Lu-sail FootBall Stadium/ Qatar downtown New city /and livingquarters/ officetower
blocks/ commercial developments .and much more!
Duties
• Execute the projectdelivery plan
• Determine and organiseprojectdelivery teams
• Determine safeand efficient working methods
• Provideteams with workingsequences and programmed targets
• Manage project delivery teams- logistics,surveying,QA and installation
• Attend clientco-ordination meetings
• Review daily,weekly and monthly siteprogress reports
• Monitor, review and report on team productivity
• Chair sub-contractor coordination meeting
Achievements
• Introduced fasttrack methods for steel sub-structureinstall facades glassand full sitesetup and labour
controls,schools library’sand sportstadiums for the Qatar Governments and The Emir of Qatar.
Total Labour supervised at Alu-Nasa was approx.1200 officeand site based staff across 9 projects.I monitored said
projects within Alu-Nasa group inQatar and Dubai.Answeringonly to the ManagingDirector and Operation’s
Director for all siteoperations and siteactivities,pushingall PMs and SiteManagers to ensure targets set by senior
staff were met on time.
Jan 2010 – Mar 2013 Freelance Construction Manager/ Site Manager/ Senior Site Manager
Worked for various main and specialistcontractors on fixed term contractprojects, makingsure we had all open
fronts for the works in hand. Site based and not office bound and ensured all contractorsachieved the required
results.Projectwas concluded on time and within budget.
Roles and Achievements
• Operations Manager: Full siteset up and the delivery of 13 Solar Farms.Fasttrack installation in a period
of four months
• Senior Construction Manager: Setting up 14 sites in the North Eastof England and Scottish borders. Fast
track refurbishment of Health Centres - Norlands (UKS) ltd.
• Curtain Wall Manager:This was for 5 new build Tesco Stores in Fife, Berwick, Newcastle, Orkney Isles,
Shetland Isles and Cheshire- North CheshireHoldings Ltd.
• Senior Construction Manager: Channel 4 headquarters full cat5 & 6 rip out and refit - Ibex Interiors
• Senior Site Manager: This was for multipleprojects with the full responsibility of managinglabour teams,
material call off,quality and programmed delivery – Vast Group
• Curtain Wall Manager:6 new build Tesco Stores – Henry contracts
Apr 2007 – Jan 2009 Logistics Manager/Site Manager (Haymills (Gibraltar) Ltd), Gibraltar
Haymills (Gibraltar) Ltd is partof the UK based Haymills Contractor Ltd who undertake Government, MOD and
PrivateSector projects.
Duties
• Logistics manager to largenew build (D&B) Government social housingdevelopment
• Establish crossborder material transfer procedures
• Set up cross border decant and distribution facility
• Day to day delivery of logisticsplan to ensure site is consistently and adequately fed with plantand
materials
• Management of general labour teams engaged in the delivery and loadingout of materials
• Attend site co-ordination meetings and organizeand implement designated actions and targets
• Determine team members and allocatetasks and projects to satisfy workload requirements
Achievements
• Successfully setup of cross border decant and delivery yard with Spanish and customs with all imported
materials formthe UK
• Re-organized on-site supportteams and improved load out efficiency by 50%
•
2012-2013 IBEX INTERIORS LONDON
senior sitemanager
Channel 4 head office London £15million refurbishments works lower ground floor and 5 floors refurbishments
and face up liftliveprojects and a 24 hour operation.
Demo works across thewhole area of the buildingground to top .
Soft strip block walls/ concrete floors demolition for mezz decks installs
Drywalls and old storageareas and bikesheds.
Hard strip out of Concrete floors and reinstatewith mezzanine decks floor with new builtpod offices.
Lift shafts rip out and install newupdate lifts as per the D&B.
Control of all sub -contractors and directstaff as number 1 site manager workingunder a senior projectmanager.
Materials call offs And labour appointments and contractor appointments .
Waste call off for skips to Bream, Cafe van requests within the carbon foot print.
Logistics of all sitetraffic in and out,on a rota, due to the tight locations.
All permits for demo works and permits to work in red sensitiveareas and liveareas was my remit.
Achievements
Completion of the project 2013 To budget and accidentfree.
Jan 2005 – Mar 2007 Site Manager/Package Manager (Hillstone Developments Ltd)
New build developer of houses and apartment blocks.
Duties
• Senior Site Manager to dedicated to approved sites via MD <
• Prime responsibility for delivery,H&S and sitedelivery
• Day to day runningof Appointed sites .
• Providesub-contractors with work packages and programmed target dates
• Attend and report monthly projectreview meetings with visitingcontractmanager
Nov 2003 – Dec 2004 Site Manager (Henry and Fadian Site Services)
Specialistcladdingand curtain wallingcontractor
Duties
• Head Site Manager
• Allocatesub-contractpackages
• Prime responsibility for delivery,H&S and sitedelivery
• Day to day runningof site
• Liaisewith off-site pod production facility in Poland
• Forward planningfor siteinstallation of pods and final finishing
• Site set up
• Chair siteco-ordination meetings
Achievements
• Successful completion of Manchester University student accommodation
• Successful completion ingleBerwick Roman Catholic School
NB: Further employment history can be provided upon request.
Education & Qualifications
• SMSTS Cert managers (2020)
• CSCS Card managers (2020)
• IOSH Cert managers (2020)
• Café Van- Environmental Cert OPEN
• FireMarshall Cert (2018)
• Traffic Marshall managers (2018 )
• Workingat Heights Cert (2018)
• Harness AssessmentCert (2018)
• Asbestos Awareness UKATA managers (2018)
• Confine spaceManagers (2018)
• FirstAid at Work 3 Day Appointed Person (2018)
• Forkliftrough terrain Cert (2018)
• PTS DCCR Rail Card with up to date Medical
• Currently working towards NEBOSH Gen Con Cert (Ongoing 2015 )
• Degree in Construction Management will becomplete in Aug 2016 (ongoing)
Other notable skills:
PC Literate .
References
ContactableReferences availableupon request from old and new projects areavailable .
Copies Certifications on Request and areCITB and HSE approved Trainingcompanies .

CV Details 2016

  • 1.
    Mr Liam JosephHenry. Senior Site Manager/Construction Manager / Package Site Manager. Construction / Rail London Work Address Flat 1 325 Purely way Waddon East Croydon CR0 4NU ----------------------------------------------------- Home Address 9 Woodville Avenue Middleborough Cleveland TS4 3BE Mobile 07576-348955 Email Address hcml50@outlook.com. Skype address Liam.Henry175 DOB 01/02/1966. Available Start date 2016 need to give notice at current contract. Freelance or Direct Personal profile I am a highly experienced, well organized and motivated professional, with a keen eye for detail. Has a proven ability to work extremely well under pressure, effectively and efficiently. I have a can do attitude with the ability to lead and meet deadlines in plenty of time. I am an innovative thinker with strong ambitions and is known not to fail atwhatever task is given and constraints putupon me . Currently, I am seeking a new career opportunity, either permanent or contract, to utilize my strong skills and qualifications. As an individual with the determination to succeed, I believe I would be a great asset to any organization. I have excellentcommunication skillswith exceptional stakeholder management skilled. Looking at working around the uk and travel and accommodations will be in my own my costs within the day work rate i get agreed with clients or Agency . Projects workingon Now Started 1st /8/2016 Drivingthe project to completion Permasteelisa Uk ltd Novetel Hotel projects 40 floors Tower canary wharf
  • 2.
    Freelance contractRole ConstructionManager. 1)Construction Manager Prater Ltd (Drivingthe project) completed on the 1st end of contract . London Bridge Train station Redevelopments Project Network Rail & Constains Constriction Ltd 15 Platforms . Cladding and Curtain walling and steel packages and directing Prater ltd In house Management Team to there in house policies and directing to keep to program dates And supervising all Prater subcontractors ,steel erectors/painters /cladders/curtain-wallers/Roofers/ coded welders. Senior sitemanager Driving the project to completion 2)Caddicks construction Group 50 Apartments at York train station refurbishments £5million on time and Budget. 3)Construction Manager Drivingthe projectto completion ) Lidi / Tesco Projects On behalf Johnson Construction Group. 4) Construction Manager drivingthe projects) Student accommodations New Builds for Watkins and Jones group Uk wide as freelance site manager or subcontractor and Others. 5)Construction Manager) New build construction projects,Tower blocks /Health Centers / Listed buildings. 6)Construction Manager) Refurbishments in all styles of building,from£2 million to £20 Million 7) Senior Construction Manager Alu Nasa MiddleEastQatar . Drivingseveral projects with international workforcemainly Asian ) Football Stadiums in Qatar steel and cladding/ Curtain Walling for the royal family for 2022 world cup 7) Senior Construction Manager Drivingthe projects to completion) A new state of the art Library,for HRH Sheik Mossa in Doha Qatar . 8) Site Manager ibex Interiors Drivingthe project to hand over ) NHS refurbishments UK wide fasttrack out of hours projects C4 head office£14Miliion 9) Site Manager) Claddingall systems on tower blocks UK wide and Europe Freelance For Agencies. 10) Senior Construction Manager) Large Solar projects UK wide.£500 Million pounds projects in total 2014& 2015. DrivingThe projects Forward . 11) Senior Construction Manager and advisory and drivingtheprojects to completion. Multinational projectand investments company’s Conergy Uk Large solar projects 12) Site Manager freelance) Kier Construction Ltd £35 Million New Build of a mental health centre and secure unit in Wigan. 13)Site Manager )
  • 3.
    Screw-fix frame worksfitout across theUK.. 14) Site Manager 3 blocks Drivingthe projects ) Social Housingapartments blocks in Gibraltaron behalf of the Gibraltar Governments /UK Governments. Strong finishingdetailson internals and externals finishesacross all modes of the construction phases. Employment History Currently working on freelance roles for Kalcrest Agency for Caddicks Group Ltd . D&B £5 million refurbishments of 50 apartments at York train station New roof, EWI Render and parklex cladding products and rain screen cladding metsec and Cp boards finish with EPDM finishes . Also phase 2 and phase 3 internals packages drywall and all M/E works . Senior Construction Consultant/Senior Project Manager (Conergy UK) 6 months contract completed please see references Consulting with all international Project Managers for Conergy UK for the following duties: CDM legislation HSE legislation Installinglocal and UK civil contractorswith proven solar experience. Meeting programdates and related financial constraints. Overseeing all siteconstruction and related activities. Client- Local Government/Council and Council. Site facing. Weekly/monthly meetings (onsite) as and when required. CDM health and safety facingand any other related safety issues. Duties • Overseeing all ProjectManagers and Sub-Contractors to ensure they are meeting company deadlines and meeting installation specifications • Installingall SiteManagers through LH Site Management Ltd Apr 2013 to Apr 2014 Senior Construction Manager (Alu-Nasa Part of Salaam International Investments group) A specialistfaçadecontractor,undertakinghigh risecommercial projects hotels and leisureprojects Qatar National library Lu-sail FootBall Stadium/ Qatar downtown New city /and livingquarters/ officetower blocks/ commercial developments .and much more! Duties • Execute the projectdelivery plan • Determine and organiseprojectdelivery teams • Determine safeand efficient working methods • Provideteams with workingsequences and programmed targets • Manage project delivery teams- logistics,surveying,QA and installation • Attend clientco-ordination meetings
  • 4.
    • Review daily,weeklyand monthly siteprogress reports • Monitor, review and report on team productivity • Chair sub-contractor coordination meeting Achievements • Introduced fasttrack methods for steel sub-structureinstall facades glassand full sitesetup and labour controls,schools library’sand sportstadiums for the Qatar Governments and The Emir of Qatar. Total Labour supervised at Alu-Nasa was approx.1200 officeand site based staff across 9 projects.I monitored said projects within Alu-Nasa group inQatar and Dubai.Answeringonly to the ManagingDirector and Operation’s Director for all siteoperations and siteactivities,pushingall PMs and SiteManagers to ensure targets set by senior staff were met on time. Jan 2010 – Mar 2013 Freelance Construction Manager/ Site Manager/ Senior Site Manager Worked for various main and specialistcontractors on fixed term contractprojects, makingsure we had all open fronts for the works in hand. Site based and not office bound and ensured all contractorsachieved the required results.Projectwas concluded on time and within budget. Roles and Achievements • Operations Manager: Full siteset up and the delivery of 13 Solar Farms.Fasttrack installation in a period of four months • Senior Construction Manager: Setting up 14 sites in the North Eastof England and Scottish borders. Fast track refurbishment of Health Centres - Norlands (UKS) ltd. • Curtain Wall Manager:This was for 5 new build Tesco Stores in Fife, Berwick, Newcastle, Orkney Isles, Shetland Isles and Cheshire- North CheshireHoldings Ltd. • Senior Construction Manager: Channel 4 headquarters full cat5 & 6 rip out and refit - Ibex Interiors • Senior Site Manager: This was for multipleprojects with the full responsibility of managinglabour teams, material call off,quality and programmed delivery – Vast Group • Curtain Wall Manager:6 new build Tesco Stores – Henry contracts Apr 2007 – Jan 2009 Logistics Manager/Site Manager (Haymills (Gibraltar) Ltd), Gibraltar Haymills (Gibraltar) Ltd is partof the UK based Haymills Contractor Ltd who undertake Government, MOD and PrivateSector projects. Duties • Logistics manager to largenew build (D&B) Government social housingdevelopment • Establish crossborder material transfer procedures • Set up cross border decant and distribution facility • Day to day delivery of logisticsplan to ensure site is consistently and adequately fed with plantand materials • Management of general labour teams engaged in the delivery and loadingout of materials • Attend site co-ordination meetings and organizeand implement designated actions and targets • Determine team members and allocatetasks and projects to satisfy workload requirements Achievements
  • 5.
    • Successfully setupof cross border decant and delivery yard with Spanish and customs with all imported materials formthe UK • Re-organized on-site supportteams and improved load out efficiency by 50% • 2012-2013 IBEX INTERIORS LONDON senior sitemanager Channel 4 head office London £15million refurbishments works lower ground floor and 5 floors refurbishments and face up liftliveprojects and a 24 hour operation. Demo works across thewhole area of the buildingground to top . Soft strip block walls/ concrete floors demolition for mezz decks installs Drywalls and old storageareas and bikesheds. Hard strip out of Concrete floors and reinstatewith mezzanine decks floor with new builtpod offices. Lift shafts rip out and install newupdate lifts as per the D&B. Control of all sub -contractors and directstaff as number 1 site manager workingunder a senior projectmanager. Materials call offs And labour appointments and contractor appointments . Waste call off for skips to Bream, Cafe van requests within the carbon foot print. Logistics of all sitetraffic in and out,on a rota, due to the tight locations. All permits for demo works and permits to work in red sensitiveareas and liveareas was my remit. Achievements Completion of the project 2013 To budget and accidentfree. Jan 2005 – Mar 2007 Site Manager/Package Manager (Hillstone Developments Ltd) New build developer of houses and apartment blocks. Duties • Senior Site Manager to dedicated to approved sites via MD < • Prime responsibility for delivery,H&S and sitedelivery • Day to day runningof Appointed sites . • Providesub-contractors with work packages and programmed target dates • Attend and report monthly projectreview meetings with visitingcontractmanager Nov 2003 – Dec 2004 Site Manager (Henry and Fadian Site Services) Specialistcladdingand curtain wallingcontractor Duties • Head Site Manager • Allocatesub-contractpackages • Prime responsibility for delivery,H&S and sitedelivery • Day to day runningof site • Liaisewith off-site pod production facility in Poland • Forward planningfor siteinstallation of pods and final finishing • Site set up • Chair siteco-ordination meetings Achievements • Successful completion of Manchester University student accommodation
  • 6.
    • Successful completioningleBerwick Roman Catholic School NB: Further employment history can be provided upon request. Education & Qualifications • SMSTS Cert managers (2020) • CSCS Card managers (2020) • IOSH Cert managers (2020) • Café Van- Environmental Cert OPEN • FireMarshall Cert (2018) • Traffic Marshall managers (2018 ) • Workingat Heights Cert (2018) • Harness AssessmentCert (2018) • Asbestos Awareness UKATA managers (2018) • Confine spaceManagers (2018) • FirstAid at Work 3 Day Appointed Person (2018) • Forkliftrough terrain Cert (2018) • PTS DCCR Rail Card with up to date Medical • Currently working towards NEBOSH Gen Con Cert (Ongoing 2015 ) • Degree in Construction Management will becomplete in Aug 2016 (ongoing) Other notable skills: PC Literate . References ContactableReferences availableupon request from old and new projects areavailable . Copies Certifications on Request and areCITB and HSE approved Trainingcompanies .