CASTER CONCEPTS
MATTHEWS PLATING COSTS 2015
PAUL $ 13,770.00
BRAD $ 6,468.75
GAS $ 6,375.00
INSURANCE $ 400.00
REPAIR & MAINTENANCE $ 1,500.00
PLATING COST $ 150,194.50
TOTAL COSTS: $ 178,708.25
 Paul’s cost is 50% of his time
 Brad’s cost is 20% of his time
 All other expenses are actuals
 Estimation: $ 210,000
This includes:
 Cost of the oven $160,000
 Cost of the spray booth $50,000
 $210,000 loan
 Interest rate: 4.00%
 3 years, 12 payments/yr
 Resulting in a total interest of $13,201.33
Part: Sq. Feet Of Part: LBS/ PART SQ/LBS
2-71-12300-1 1.85 11.86 0.16
27-05200-1 0.39 2.11 0.18
51-08200-1nyptg 1.37 6.01 0.23
57-10200-1 0.72 4.53 0.16
74-00000-15 0.14 0.73 0.18
2-71-16601-1nyf 3.49 22.40 0.16
65-06300-1p 1.01 6.10 0.17
64-08000-12ss 0.31 1.32 0.23
73-06000-17f 1.68 9.10 0.18
66-05200-2 0.85 3.77 0.23
55-05200-1 0.43 2.33 0.19
2-51-05100-1nyds 0.66 2.75 0.24
AVERAGE SQUARE FT PER LBS SENTTO MATTHEWS 0.19
Average square ft per pound part conversion
SQUARE FOOT CALCULATION
$ 150,194.50 MATTHEWS PLATING COST IN 2015
$ 0.21 PER POUNDAT MATTHEWS
715,211.90 TOTAL LBS SENTTO MATTHEWS PLATING
0.19 AVERAGE SQUARE FOOTAGE PER POUND SENTTO MATTHEWS
135,890 TOTAL SQUARE FEET SENTTO MATTHEWS PLATING
 Cell 1:The amount paid to Matthew’s Plating in 2015
 Cell 2: Average price per pound to plate at Matthew’s Plating
 Cell 3: Cell 1/ Cell 2 –This gives the total weight in pounds sent to Matthew’s Plating in 2015
 Cell 4: Average square foot calculated with the parts on the last slide
 Cell 5: Cell 3 x Cell 4 –This gives estimated square feet sent to Matthew’s Plating in 2015
Total square feet sent to Matthew’s Plating: 135,890
Price per square foot: $0.10
Material Costs: $13,589.00
Total Overhead: $ 51,291.30
Assumptions:
•Running for 255 days/yr
•8 hrs/day
•Same amount space, more compact
system then current
Best
Case
Worst
Case
$ 50,000 in revenue
$ 100,000 in revenue

More Related Content

Similar to CCI POWDER COAT

AH CCM 10.08.18 - Item #5 - ppt AH Rate Study
AH CCM 10.08.18 - Item #5 - ppt AH Rate StudyAH CCM 10.08.18 - Item #5 - ppt AH Rate Study
AH CCM 10.08.18 - Item #5 - ppt AH Rate Studyahcitycouncil
 
AH CCM 10.22.18 Item #4 AH Rate Study
AH CCM 10.22.18 Item #4 AH Rate StudyAH CCM 10.22.18 Item #4 AH Rate Study
AH CCM 10.22.18 Item #4 AH Rate Studyahcitycouncil
 
Cost Vs Budget PowerPoint Presentation Slides
Cost Vs Budget PowerPoint Presentation SlidesCost Vs Budget PowerPoint Presentation Slides
Cost Vs Budget PowerPoint Presentation SlidesSlideTeam
 
Budget Variance Analysis PowerPoint Presentation Slides
Budget Variance Analysis PowerPoint Presentation SlidesBudget Variance Analysis PowerPoint Presentation Slides
Budget Variance Analysis PowerPoint Presentation SlidesSlideTeam
 
Budget Projection PowerPoint Presentation Slides
Budget Projection PowerPoint Presentation SlidesBudget Projection PowerPoint Presentation Slides
Budget Projection PowerPoint Presentation SlidesSlideTeam
 
Finance Budgeting PowerPoint Presentation Slides
Finance Budgeting PowerPoint Presentation SlidesFinance Budgeting PowerPoint Presentation Slides
Finance Budgeting PowerPoint Presentation SlidesSlideTeam
 
Finance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation SlidesFinance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation SlidesSlideTeam
 
Catherine fisher pwr point
Catherine fisher pwr point Catherine fisher pwr point
Catherine fisher pwr point Catherine Fisher
 
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesActual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesSlideTeam
 
130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshoppublicinvolvement
 
YorBox UK model
YorBox UK modelYorBox UK model
YorBox UK modelYorBox
 
Anders, Water Rates
Anders, Water RatesAnders, Water Rates
Anders, Water RatesTWCA
 
Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides SlideTeam
 
Depreciation sample report
Depreciation sample reportDepreciation sample report
Depreciation sample reportIndependentgroup
 
Forecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation SlidesForecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation SlidesSlideTeam
 
Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides SlideTeam
 
Plan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation SlidesPlan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation SlidesSlideTeam
 

Similar to CCI POWDER COAT (20)

Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Micro 12
Micro 12Micro 12
Micro 12
 
AH CCM 10.08.18 - Item #5 - ppt AH Rate Study
AH CCM 10.08.18 - Item #5 - ppt AH Rate StudyAH CCM 10.08.18 - Item #5 - ppt AH Rate Study
AH CCM 10.08.18 - Item #5 - ppt AH Rate Study
 
AH CCM 10.22.18 Item #4 AH Rate Study
AH CCM 10.22.18 Item #4 AH Rate StudyAH CCM 10.22.18 Item #4 AH Rate Study
AH CCM 10.22.18 Item #4 AH Rate Study
 
Cost Vs Budget PowerPoint Presentation Slides
Cost Vs Budget PowerPoint Presentation SlidesCost Vs Budget PowerPoint Presentation Slides
Cost Vs Budget PowerPoint Presentation Slides
 
Budget Variance Analysis PowerPoint Presentation Slides
Budget Variance Analysis PowerPoint Presentation SlidesBudget Variance Analysis PowerPoint Presentation Slides
Budget Variance Analysis PowerPoint Presentation Slides
 
Budget Projection PowerPoint Presentation Slides
Budget Projection PowerPoint Presentation SlidesBudget Projection PowerPoint Presentation Slides
Budget Projection PowerPoint Presentation Slides
 
Finance Budgeting PowerPoint Presentation Slides
Finance Budgeting PowerPoint Presentation SlidesFinance Budgeting PowerPoint Presentation Slides
Finance Budgeting PowerPoint Presentation Slides
 
Finance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation SlidesFinance Budgeting Powerpoint Presentation Slides
Finance Budgeting Powerpoint Presentation Slides
 
Catherine fisher pwr point
Catherine fisher pwr point Catherine fisher pwr point
Catherine fisher pwr point
 
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation SlidesActual Cost Vs Plan Projection Powerpoint Presentation Slides
Actual Cost Vs Plan Projection Powerpoint Presentation Slides
 
130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshop
 
YorBox UK model
YorBox UK modelYorBox UK model
YorBox UK model
 
Anders, Water Rates
Anders, Water RatesAnders, Water Rates
Anders, Water Rates
 
Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides Actual Cost Vs Plan Projection PowerPoint Presentation Slides
Actual Cost Vs Plan Projection PowerPoint Presentation Slides
 
Depreciation sample report
Depreciation sample reportDepreciation sample report
Depreciation sample report
 
Forecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation SlidesForecast Vs Actual Budget Powerpoint Presentation Slides
Forecast Vs Actual Budget Powerpoint Presentation Slides
 
Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides Forecast Vs Actual Budget PowerPoint Presentation Slides
Forecast Vs Actual Budget PowerPoint Presentation Slides
 
Plan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation SlidesPlan Vs Forecast PowerPoint Presentation Slides
Plan Vs Forecast PowerPoint Presentation Slides
 

CCI POWDER COAT

  • 2.
  • 3. MATTHEWS PLATING COSTS 2015 PAUL $ 13,770.00 BRAD $ 6,468.75 GAS $ 6,375.00 INSURANCE $ 400.00 REPAIR & MAINTENANCE $ 1,500.00 PLATING COST $ 150,194.50 TOTAL COSTS: $ 178,708.25  Paul’s cost is 50% of his time  Brad’s cost is 20% of his time  All other expenses are actuals
  • 4.  Estimation: $ 210,000 This includes:  Cost of the oven $160,000  Cost of the spray booth $50,000
  • 5.  $210,000 loan  Interest rate: 4.00%  3 years, 12 payments/yr  Resulting in a total interest of $13,201.33
  • 6. Part: Sq. Feet Of Part: LBS/ PART SQ/LBS 2-71-12300-1 1.85 11.86 0.16 27-05200-1 0.39 2.11 0.18 51-08200-1nyptg 1.37 6.01 0.23 57-10200-1 0.72 4.53 0.16 74-00000-15 0.14 0.73 0.18 2-71-16601-1nyf 3.49 22.40 0.16 65-06300-1p 1.01 6.10 0.17 64-08000-12ss 0.31 1.32 0.23 73-06000-17f 1.68 9.10 0.18 66-05200-2 0.85 3.77 0.23 55-05200-1 0.43 2.33 0.19 2-51-05100-1nyds 0.66 2.75 0.24 AVERAGE SQUARE FT PER LBS SENTTO MATTHEWS 0.19 Average square ft per pound part conversion
  • 7. SQUARE FOOT CALCULATION $ 150,194.50 MATTHEWS PLATING COST IN 2015 $ 0.21 PER POUNDAT MATTHEWS 715,211.90 TOTAL LBS SENTTO MATTHEWS PLATING 0.19 AVERAGE SQUARE FOOTAGE PER POUND SENTTO MATTHEWS 135,890 TOTAL SQUARE FEET SENTTO MATTHEWS PLATING  Cell 1:The amount paid to Matthew’s Plating in 2015  Cell 2: Average price per pound to plate at Matthew’s Plating  Cell 3: Cell 1/ Cell 2 –This gives the total weight in pounds sent to Matthew’s Plating in 2015  Cell 4: Average square foot calculated with the parts on the last slide  Cell 5: Cell 3 x Cell 4 –This gives estimated square feet sent to Matthew’s Plating in 2015
  • 8. Total square feet sent to Matthew’s Plating: 135,890 Price per square foot: $0.10 Material Costs: $13,589.00
  • 9.
  • 10. Total Overhead: $ 51,291.30 Assumptions: •Running for 255 days/yr •8 hrs/day •Same amount space, more compact system then current
  • 12. $ 50,000 in revenue
  • 13. $ 100,000 in revenue