SlideShare a Scribd company logo
1 of 26
PLASTIC CELL FILLED
CONCRETE PAVEMENT
PREPARED BY : ADITHYA DINESH
S5 CIVIL ENGINEERING
ROLL NO : 8
CONTENTS
 INTRODUCTION
 THE CONCEPT
 PLASTIC CELL
 PREPARATION OF SUBGRADE
 SUBBASE
 CONCRETE
 CONSTRUCTION
 CURING (Continue.....)
2
 OPENING TO TRAFFIC
 APPERANCE OF TOP SURFACE
 PAVEMENT THICKNESS OF FLEXIBLE CONCRETE
 ADVANTAGES
 DISADVANTAGES
 QUALITY TEST AFTER CONSTRUCTION
 CONCLUSION
3
INTRODUCTION
 Under PMGSY, the rural road network has experienced aconsiderable growth.
 The good quality roads being constructed, immensely contribute in the progress of the
country.
 Most of the low volume village roads being constructed are flexible pavements provided
with a thin bituminous surface.
 Quite often these roads get damaged due to overloaded vehicles, inadequate drainage
facility and water logging problems, and hence require early periodic maintenance.
 The technology developed by IIT Kharagpur, known as cell filled concrete pavement,
has proved to be very promising solution for this issue.
 It provides long lasting concrete pavements (permanent asset) at low initial cost which
are almost maintenance free. This also generates employment opportunities in rural
areas.
4
THE CONCEPT
 The technology consists of covering the compacted sub grade/sub base with a formwork
of plastic cells as shown in figure 1.
 The formwork of plastic cells is stretched and iron spikes are driven at the corners of the
cells so that the formwork remains taut.
 Nylon ropes through the cell walls prevent collapse of the cells during the placing
concrete or stones into the cells.
5
Figure 1: Welding and Stitching of plastic sheet strips at 300mm interval
Figure 2: Stretched cell placed over compacted GSB layer 6
 Different types of concrete such as conventional concrete/ zero slump concrete with a 28
day characteristic compressive strength of 30 Mpa is placed into the cells.
 The subgrade/ subbase have the proper camber, the top of the cells also will have the
same camber.
 After leveling the concrete, a vibratory/ static road roller of 6 to 8 ton capacity may be
used for compaction.
 One or two static passes followed by two vibratory pass and again one or two static pass
will bring about the necessary compaction.
 The exact number of passes will depend upon the angularity of aggregates and trials have
to be made to determine the number of passes.
 Static rolling with more number of passes may bring about the necessary compaction
because of lower thickness.
 The cell walls get curled both vertically and horizontally during the construction to bring
about the three dimensional interlocking among the concrete blocks.
7
 Formwork of plastic cells can be made from reclaimed high density polythylene
(HDPE) sheets of thickness 0.22mm to about 0.25mm.
 Plastic sheet manufacturers can supply rolls of strips 50mm to 100mm wide depending
upon the depth requiremnt.
 Waste low density polyethylene(LDPE) is available in plenty and the recycled LDPE
sheets of thickness 0.3.to 0.35 mm can be used for making the formwork of cells.
 Readymade formwork of cells also can be obtained from the market.
8
PLASTIC CELLS
 Iron spikes of about 200mm long are used to keep the cell walls taut.
 Nylon threads are used for preventing collapse of cell walls during the placement of
concrete.
 The spikes are to be taken out for use at other places as soon as concrete is filled into
the cells.Nylon threads also can be taken out after the placement concrete.
 Formwork of cells should be so stitched that one roll of cells for a pavement width of
3.75m has a length of about 10 to 20m upon stretching.
 LDPE sheets may weigh more because of greater thickness requirement for stiffness.
9
Iron spikes
Figure 3: Tightening of plastic cell using Iron spikes and nylon treads
10
PROCESS OF MAKING CELL FILLED CONCRETE PAVEMENT
PREPARATION OF SUBGRADE
11
 The subgrade forms the top 300mm thick portion of the embankment and it should be
prepared as per Specifications for Rural Roads.
 The subgrade in embankment is compacted in two layers usually to a higher standard
than the embankment.
 If the embankment soil is poor, the top 300mm of the subgrade may consist of good
quality material from borrow pits with CBR exceeding five.
 It should be compacted to atleast 100% of Maximum Dry Density as per IS:2729 (Part
7).
 The expansive black cotton soil(BCS) should be compacted to a minimum of 95% of
the maximum dry density with moisture content 2% higher than the optimum.
 A BCS can be stabilized by lime to impart improved strength tothe subgrade in addition
to reducing swell and shrinkage of the soil.
SUBBASE
 The subbase may consist of laterite boulder consolidation, water bound macadam, wet
mix macadam, jhama brick consolidation, crusher runmacadam, lime-fly ash-aggregate
mixtures, lime stabilized soil, cementstab ilized soil and others with proprietary
stabilisers.
 Locally available aggregates such as murrum and kankar mixed with lime fly ash may
also be used.
 The locally available materials such as natural gravel/soil aggregate or blended with
suitable aggregate fractions of stone, gravel, moorum, sand or combination of these
materials depending on the grading required.
 The subbase should be provided with stone/concrete block or Brick on edge should be
laid on either side of the carriageway projecting 50 to 100 mm above the
subgrade/subbase for the confinement and protection.
 150mm of cementitious subbase with minimum 7 day strength of 1.5 Mpa is 12
CONCRETE
 Conventional concrete having 28 day strength of 30Mpa with slump of about 30 to 50
mm can be used for filling up the cell.
 Super plasticiser should be used to reduce water requirement for the desired slump.
 Coarse aggregate should consist of strong crushed stone or crushed gravel with
aggregate impact value lesser than 30.
 The maximum size of aggregates should not exceed 26.5 mm.
 For very low volume roads with motorized traffic less than 50 vehicles per day, gravels
from river bed, pit run gravel deposits may also be used.
 Fine aggregate should consist of clean natural sand or crushed stone or combination of
the two can be used.
13
 Aggregates, sand and cement should be proportioned by weight.
 wooden or iron measuring boxes may be used to maeasure ingredients by volume after
calibrating with weigh batcher.
 A permanent mark should be made on a suitable container to allow only specified
quantity of water.
Figure 4: Concrete placement 14
15
CONSTRUCTION
 Construction of embankment, subgrade and subbase should be done as per
Specifications for Rural Roads. Proper camber as applicable to rural roads should be
provided.
 Drainage layer also should be provided in high rainfall area
 Formwork of plastic cells may be laid across the compacted subbase and put under
tension with iron spikes so that cells are close to squares in plan.
 Nylon threads passing through the cells 10 mm below the top of the cells should be
used to prevent the cells from collapsing during the filling of the cells with concrete.
 If any stitch of the cells opens up during tensioning, it should be stapled near the top,
middle and the bottom. Concrete should be filled into the cells to a depth of about 120
mm which is about 20 mm higher than the depth of the cell.
16
 Uniformity of level should be checked before the compaction.
 The iron spikes should be taken out after the cells are filled up with concrete.
 Some amount of water may evaporate during mixing, transportation and placing during
hot weather and this may result in a dry mix. Additional water may have to be added
during the mixing in such cases.
 walk behind vibratory roller and vibratory plate compactors/earth rammer may also be
used for compaction of concrete.
 Small rollers are easy to manage in narrow village roads. Pan vibrators can be used for
the compaction of the conventional concrete having a slump of about 30 to 40 mm.
17
Figure 5: Construction procedure carried out at site.
18
CURING
 Camber of about 3 to 3.5 % specified for rural roads, wet jute/coir mats and wet paddy
straw provide better water curing option and light traffic can be allowed to move on the
surface.
 In water ponding method, water accumulates on the lower side of the mud enclosure
whereas the higher part becomes dry soon.
Figure 6: Curing of concrete by wet paddy straw and ponding
OPENING TO TRAFFIC
 Concrete surface can be opened to light traffic such as bi-cycle, auto rickshaw,
motorcycle etc after two days of curing.
 Heavy traffic vehicles such as iron rimmed bullock cart, bus, truck, tractor etc can be
permitted after 14 days when concrete is sufficiently strong.
Figure 7: Opening to traffic 19
APPERANCE OF TOP SURFACE
 The outline of the plastic formwork is clearly seen.
 The formwork of cells 100 mm deep may not always be visible if concrete thickness is
more than 100mm at some locations.
 Cracks would form at the locations of the plastic sheets showing the pattern of the
formwork of plastic cells after application of traffic for some months.
Figure 8: Apperance of top surface of cell filled pavement
20
ADVANTAGE OF CELL FILLED CONCRETE PAVEMENT
 Use of recycled plastic.

 Expansion or contraction joints are not required and hence maintenance of joints is
eliminated.
 The cost of construction is considerably reduced when compared to conventional
cement concrete pavement.
 The consumption of aggregates is almost reduced to 50% when compared to normal
CC pavements.

 Due to high stiffness, the overall crust requirement gets reduced hence economical for
low volume of roads.
 If the individual block fails, then it can be easily replaced without much effort and
with least cost.
21
DISADVANTAGE OF CELL FILLED CONCRETE PAVEMENT
 The preparation of the cells is cumbersome.
 The cells gets disturbed while placing the concrete and hence proper care is required.
 Placing of the concrete without disturbing the cells slows down the progress.
 Consumption of labour is more, more labour oriented work.

 Due to slow progress, the actual turn out of the men and machinery is less than the
normal construction.
 The cost of providing Kerb is additional and is timeconsuming.
 Possibility of formation of cold joints between two successive concrete layers leads to
failure (as observed in Karnataka) requires treatment at cold construction joints.
22
QUALITY TEST AFTER CONSTRUCTION
 Destructive testing - Extracting core after casting and test for the quality.
 Non destructive testing -By visual observations for blow up, corner breaks, cracking,
faulting, pumping etc.
 Benkal beam deflection test
 Deflection meaurements taken at
 0.9m from the edge for the main road of width 5.5 m
 0.6m from the edge for the other road of width 3.75 m
 Deflection measurements are taken at every 100m interval
 An axial load of 8.2 tons and tyre pressure of 5.6 kg/sqcm
23
Figure 9: Benkal beam test Figure 10: core extraction machine
CONCLUSION
 Cell filled concrete pavement can be recommended for weak base and sub-base layers
instead of flexible pavement, since it showed resistance to structural durability.
 Cell filled concrete pavements has very little effect to the riding comfort in terms of
roughness.
 Construction of Cell Fill Concrete Pavement is advantageous compared to
Conventional Concrete and Asphalt Pavement. Since cell filled roads are economical
(cost per km) to conventional concrete roads and they need very less annual
maintenance (as per good PCI rate) compared to flexible roads.

 Conventional and cell filled Concrete roads could be a solution for the rural roads
because of the life of concrete roads. It’s beneficial to use cell filled in low volume
traffic condition.
 Cell Fill Concrete roads is a challenge in the rural road construction with the effective
diversion of traffic. 25
THANK YOU
26

More Related Content

What's hot

Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 
Concrete Honeycombs
Concrete Honeycombs Concrete Honeycombs
Concrete Honeycombs Dimuthuchat
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavementsShaik Asif Ahmed
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-damKHUSHBU SHAH
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)SSudhaVelan
 
Pavement failures and maintenance
Pavement failures and maintenancePavement failures and maintenance
Pavement failures and maintenanceSatyapal Singh
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignRiaz Zalil
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESHImrul Quesh
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part IISachin Kulkarni
 
Presentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionPresentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionSelf-employed
 
Pervious or Porous Concrete
Pervious or Porous ConcretePervious or Porous Concrete
Pervious or Porous ConcreteMANUJ sinh
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
Lightweight concrete
Lightweight concreteLightweight concrete
Lightweight concreteARUN KUMAR
 
Reinforced earth walls
Reinforced earth wallsReinforced earth walls
Reinforced earth wallsRaju Sabarish
 
Light weight concrete
Light weight concreteLight weight concrete
Light weight concretedevesha y jog
 

What's hot (20)

Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
Concrete Honeycombs
Concrete Honeycombs Concrete Honeycombs
Concrete Honeycombs
 
Benkelman beam
Benkelman beamBenkelman beam
Benkelman beam
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavements
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Pavement failures and maintenance
Pavement failures and maintenancePavement failures and maintenance
Pavement failures and maintenance
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Presentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionPresentation on Summer internship on Road Construction
Presentation on Summer internship on Road Construction
 
Pervious or Porous Concrete
Pervious or Porous ConcretePervious or Porous Concrete
Pervious or Porous Concrete
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Lightweight concrete
Lightweight concreteLightweight concrete
Lightweight concrete
 
Reinforced earth walls
Reinforced earth wallsReinforced earth walls
Reinforced earth walls
 
Unit 5
Unit 5Unit 5
Unit 5
 
Pumped Concrete
Pumped Concrete Pumped Concrete
Pumped Concrete
 
Light weight concrete
Light weight concreteLight weight concrete
Light weight concrete
 

Similar to Benefits of Cell Filled Concrete Pavement for Rural Roads

Concrete (types of road)
Concrete (types of road)Concrete (types of road)
Concrete (types of road)Ali Rizgar
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
cement concrete road construction procedure
cement concrete road construction procedure cement concrete road construction procedure
cement concrete road construction procedure jaknap123456
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
No fine concrete
No fine concreteNo fine concrete
No fine concretekaran verma
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)Anil Gupta
 
494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptx494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptxPitambaramsrinivas
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesRaghvendraBajpai3
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavementAminat Aliu
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
No fine concrete. or pervious concrete
No fine concrete. or pervious concreteNo fine concrete. or pervious concrete
No fine concrete. or pervious concreteDigant Patel
 
Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal liningsaibabu48
 

Similar to Benefits of Cell Filled Concrete Pavement for Rural Roads (20)

Concrete (types of road)
Concrete (types of road)Concrete (types of road)
Concrete (types of road)
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
cement concrete road construction procedure
cement concrete road construction procedure cement concrete road construction procedure
cement concrete road construction procedure
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
No fine concrete
No fine concreteNo fine concrete
No fine concrete
 
ppt on training civil report on shuttering
ppt on training civil report on shutteringppt on training civil report on shuttering
ppt on training civil report on shuttering
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
road drainage
road drainageroad drainage
road drainage
 
494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptx494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptx
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic Wastes
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavement
 
Field work
Field workField work
Field work
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
No fine concrete. or pervious concrete
No fine concrete. or pervious concreteNo fine concrete. or pervious concrete
No fine concrete. or pervious concrete
 
Special Concrete.pdf
Special Concrete.pdfSpecial Concrete.pdf
Special Concrete.pdf
 
Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal lining
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Recently uploaded (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 

Benefits of Cell Filled Concrete Pavement for Rural Roads

  • 1. PLASTIC CELL FILLED CONCRETE PAVEMENT PREPARED BY : ADITHYA DINESH S5 CIVIL ENGINEERING ROLL NO : 8
  • 2. CONTENTS  INTRODUCTION  THE CONCEPT  PLASTIC CELL  PREPARATION OF SUBGRADE  SUBBASE  CONCRETE  CONSTRUCTION  CURING (Continue.....) 2
  • 3.  OPENING TO TRAFFIC  APPERANCE OF TOP SURFACE  PAVEMENT THICKNESS OF FLEXIBLE CONCRETE  ADVANTAGES  DISADVANTAGES  QUALITY TEST AFTER CONSTRUCTION  CONCLUSION 3
  • 4. INTRODUCTION  Under PMGSY, the rural road network has experienced aconsiderable growth.  The good quality roads being constructed, immensely contribute in the progress of the country.  Most of the low volume village roads being constructed are flexible pavements provided with a thin bituminous surface.  Quite often these roads get damaged due to overloaded vehicles, inadequate drainage facility and water logging problems, and hence require early periodic maintenance.  The technology developed by IIT Kharagpur, known as cell filled concrete pavement, has proved to be very promising solution for this issue.  It provides long lasting concrete pavements (permanent asset) at low initial cost which are almost maintenance free. This also generates employment opportunities in rural areas. 4
  • 5. THE CONCEPT  The technology consists of covering the compacted sub grade/sub base with a formwork of plastic cells as shown in figure 1.  The formwork of plastic cells is stretched and iron spikes are driven at the corners of the cells so that the formwork remains taut.  Nylon ropes through the cell walls prevent collapse of the cells during the placing concrete or stones into the cells. 5
  • 6. Figure 1: Welding and Stitching of plastic sheet strips at 300mm interval Figure 2: Stretched cell placed over compacted GSB layer 6
  • 7.  Different types of concrete such as conventional concrete/ zero slump concrete with a 28 day characteristic compressive strength of 30 Mpa is placed into the cells.  The subgrade/ subbase have the proper camber, the top of the cells also will have the same camber.  After leveling the concrete, a vibratory/ static road roller of 6 to 8 ton capacity may be used for compaction.  One or two static passes followed by two vibratory pass and again one or two static pass will bring about the necessary compaction.  The exact number of passes will depend upon the angularity of aggregates and trials have to be made to determine the number of passes.  Static rolling with more number of passes may bring about the necessary compaction because of lower thickness.  The cell walls get curled both vertically and horizontally during the construction to bring about the three dimensional interlocking among the concrete blocks. 7
  • 8.  Formwork of plastic cells can be made from reclaimed high density polythylene (HDPE) sheets of thickness 0.22mm to about 0.25mm.  Plastic sheet manufacturers can supply rolls of strips 50mm to 100mm wide depending upon the depth requiremnt.  Waste low density polyethylene(LDPE) is available in plenty and the recycled LDPE sheets of thickness 0.3.to 0.35 mm can be used for making the formwork of cells.  Readymade formwork of cells also can be obtained from the market. 8 PLASTIC CELLS
  • 9.  Iron spikes of about 200mm long are used to keep the cell walls taut.  Nylon threads are used for preventing collapse of cell walls during the placement of concrete.  The spikes are to be taken out for use at other places as soon as concrete is filled into the cells.Nylon threads also can be taken out after the placement concrete.  Formwork of cells should be so stitched that one roll of cells for a pavement width of 3.75m has a length of about 10 to 20m upon stretching.  LDPE sheets may weigh more because of greater thickness requirement for stiffness. 9 Iron spikes Figure 3: Tightening of plastic cell using Iron spikes and nylon treads
  • 10. 10 PROCESS OF MAKING CELL FILLED CONCRETE PAVEMENT
  • 11. PREPARATION OF SUBGRADE 11  The subgrade forms the top 300mm thick portion of the embankment and it should be prepared as per Specifications for Rural Roads.  The subgrade in embankment is compacted in two layers usually to a higher standard than the embankment.  If the embankment soil is poor, the top 300mm of the subgrade may consist of good quality material from borrow pits with CBR exceeding five.  It should be compacted to atleast 100% of Maximum Dry Density as per IS:2729 (Part 7).  The expansive black cotton soil(BCS) should be compacted to a minimum of 95% of the maximum dry density with moisture content 2% higher than the optimum.  A BCS can be stabilized by lime to impart improved strength tothe subgrade in addition to reducing swell and shrinkage of the soil.
  • 12. SUBBASE  The subbase may consist of laterite boulder consolidation, water bound macadam, wet mix macadam, jhama brick consolidation, crusher runmacadam, lime-fly ash-aggregate mixtures, lime stabilized soil, cementstab ilized soil and others with proprietary stabilisers.  Locally available aggregates such as murrum and kankar mixed with lime fly ash may also be used.  The locally available materials such as natural gravel/soil aggregate or blended with suitable aggregate fractions of stone, gravel, moorum, sand or combination of these materials depending on the grading required.  The subbase should be provided with stone/concrete block or Brick on edge should be laid on either side of the carriageway projecting 50 to 100 mm above the subgrade/subbase for the confinement and protection.  150mm of cementitious subbase with minimum 7 day strength of 1.5 Mpa is 12
  • 13. CONCRETE  Conventional concrete having 28 day strength of 30Mpa with slump of about 30 to 50 mm can be used for filling up the cell.  Super plasticiser should be used to reduce water requirement for the desired slump.  Coarse aggregate should consist of strong crushed stone or crushed gravel with aggregate impact value lesser than 30.  The maximum size of aggregates should not exceed 26.5 mm.  For very low volume roads with motorized traffic less than 50 vehicles per day, gravels from river bed, pit run gravel deposits may also be used.  Fine aggregate should consist of clean natural sand or crushed stone or combination of the two can be used. 13
  • 14.  Aggregates, sand and cement should be proportioned by weight.  wooden or iron measuring boxes may be used to maeasure ingredients by volume after calibrating with weigh batcher.  A permanent mark should be made on a suitable container to allow only specified quantity of water. Figure 4: Concrete placement 14
  • 15. 15 CONSTRUCTION  Construction of embankment, subgrade and subbase should be done as per Specifications for Rural Roads. Proper camber as applicable to rural roads should be provided.  Drainage layer also should be provided in high rainfall area  Formwork of plastic cells may be laid across the compacted subbase and put under tension with iron spikes so that cells are close to squares in plan.  Nylon threads passing through the cells 10 mm below the top of the cells should be used to prevent the cells from collapsing during the filling of the cells with concrete.  If any stitch of the cells opens up during tensioning, it should be stapled near the top, middle and the bottom. Concrete should be filled into the cells to a depth of about 120 mm which is about 20 mm higher than the depth of the cell.
  • 16. 16  Uniformity of level should be checked before the compaction.  The iron spikes should be taken out after the cells are filled up with concrete.  Some amount of water may evaporate during mixing, transportation and placing during hot weather and this may result in a dry mix. Additional water may have to be added during the mixing in such cases.  walk behind vibratory roller and vibratory plate compactors/earth rammer may also be used for compaction of concrete.  Small rollers are easy to manage in narrow village roads. Pan vibrators can be used for the compaction of the conventional concrete having a slump of about 30 to 40 mm.
  • 17. 17 Figure 5: Construction procedure carried out at site.
  • 18. 18 CURING  Camber of about 3 to 3.5 % specified for rural roads, wet jute/coir mats and wet paddy straw provide better water curing option and light traffic can be allowed to move on the surface.  In water ponding method, water accumulates on the lower side of the mud enclosure whereas the higher part becomes dry soon. Figure 6: Curing of concrete by wet paddy straw and ponding
  • 19. OPENING TO TRAFFIC  Concrete surface can be opened to light traffic such as bi-cycle, auto rickshaw, motorcycle etc after two days of curing.  Heavy traffic vehicles such as iron rimmed bullock cart, bus, truck, tractor etc can be permitted after 14 days when concrete is sufficiently strong. Figure 7: Opening to traffic 19
  • 20. APPERANCE OF TOP SURFACE  The outline of the plastic formwork is clearly seen.  The formwork of cells 100 mm deep may not always be visible if concrete thickness is more than 100mm at some locations.  Cracks would form at the locations of the plastic sheets showing the pattern of the formwork of plastic cells after application of traffic for some months. Figure 8: Apperance of top surface of cell filled pavement 20
  • 21. ADVANTAGE OF CELL FILLED CONCRETE PAVEMENT  Use of recycled plastic.   Expansion or contraction joints are not required and hence maintenance of joints is eliminated.  The cost of construction is considerably reduced when compared to conventional cement concrete pavement.  The consumption of aggregates is almost reduced to 50% when compared to normal CC pavements.   Due to high stiffness, the overall crust requirement gets reduced hence economical for low volume of roads.  If the individual block fails, then it can be easily replaced without much effort and with least cost. 21
  • 22. DISADVANTAGE OF CELL FILLED CONCRETE PAVEMENT  The preparation of the cells is cumbersome.  The cells gets disturbed while placing the concrete and hence proper care is required.  Placing of the concrete without disturbing the cells slows down the progress.  Consumption of labour is more, more labour oriented work.   Due to slow progress, the actual turn out of the men and machinery is less than the normal construction.  The cost of providing Kerb is additional and is timeconsuming.  Possibility of formation of cold joints between two successive concrete layers leads to failure (as observed in Karnataka) requires treatment at cold construction joints. 22
  • 23. QUALITY TEST AFTER CONSTRUCTION  Destructive testing - Extracting core after casting and test for the quality.  Non destructive testing -By visual observations for blow up, corner breaks, cracking, faulting, pumping etc.  Benkal beam deflection test  Deflection meaurements taken at  0.9m from the edge for the main road of width 5.5 m  0.6m from the edge for the other road of width 3.75 m  Deflection measurements are taken at every 100m interval  An axial load of 8.2 tons and tyre pressure of 5.6 kg/sqcm 23
  • 24. Figure 9: Benkal beam test Figure 10: core extraction machine
  • 25. CONCLUSION  Cell filled concrete pavement can be recommended for weak base and sub-base layers instead of flexible pavement, since it showed resistance to structural durability.  Cell filled concrete pavements has very little effect to the riding comfort in terms of roughness.  Construction of Cell Fill Concrete Pavement is advantageous compared to Conventional Concrete and Asphalt Pavement. Since cell filled roads are economical (cost per km) to conventional concrete roads and they need very less annual maintenance (as per good PCI rate) compared to flexible roads.   Conventional and cell filled Concrete roads could be a solution for the rural roads because of the life of concrete roads. It’s beneficial to use cell filled in low volume traffic condition.  Cell Fill Concrete roads is a challenge in the rural road construction with the effective diversion of traffic. 25