SlideShare a Scribd company logo
1 of 27
Erection of structural
components
Paramathmeka S
M.E structural engineering
P.S.G college of technology
1
Introduction
 Erection of the structural components in
prefabricated structures play the important part in
the construction of the building.
 The erection process includes the erection of
horizontal members, vertical members or complete
unit.
 To ensure effective and quality installation proper
planning and preparatory works are required before
the erection. It includes…
2
i. Method and sequence of assembly
and erection
ii. Method of providing temporary
supports
iii. Erection tolerance
iv. Handling and rigging requirements
3
Erection plan
 The erection plan, which is normally developed
by a registered professional engineer, is used
to establish the size and location of cranes, the
location of delivery trucks, and the sequence of
erection
4
Assembly plans
 Assembly plans are similar to erection
plans, except they are more detailed
and they include time components for
element installation and placements of
concretes or grouts.
 It is recommended that project
specifications require the submission
of an assembly plan.
5
Assembly plan
includes
 Drawings depicting the assembly
procedures. The plan should be
prepared by a registered Professional
engineer.
 A work area plan, depicting items
such as utilities overhead and below
the work area, drainage inlet
structures, and protective measures.
 Details of all equipment that will be
employed for the assembly of the
structure.
 Details of all equipment to be used to
lift elements, including cranes,
excavators, lifting slings, sling hooks,
and jacks. Include crane locations,
operation radii, and lifting calculations.
 Detailed sequence of construction
and a timeline for all operations.
Account for setting and cure time for
grouts, mechanical connections,
and concrete closure pours
 Calculations for all aspects of the
assembly plan including, erection
calculations, crane capacities,
rigging calculations, temporary false
work and framing, and element
handling stresses. The calculations
should be prepared by a registered
Professional engineer
 Methods of providing temporary
support of the elements. Include
methods of adjusting and securing
the element after placement.
6
 Procedures for controlling tolerance
limits—both horizontal and vertical.
Include details of any alignment jigs,
including templates for projecting
anchors and dowels.
 A detailed installation procedure for
connecting mechanical connectors,
including grouting procedures
 Include methods for curing grout and
closure pour concrete.
 Proposed methods for installing non-
shrink grout and the sequence and
equipment for the grouting operation.
 Methods for placement of fill
materials.
 Methods for forming and sealing
closure pour.
 Methods and equipment for installation
of post-tensioning systems, including
stressing and grouting procedures.
7
Preparatory work
 Check for site accessibility
 Check for delivery checklist
 Check for adequate crane capacity and
working clearance for hosting the
elements
 Conduct sample measurements
 Conduct visual inspection.
 Check for location and condition for
lifting
 Check for accessibility for unloading
point
 Check that the storage area condition.
8
As per IS 15916:2011
 In the erection of precast elements, all the following items of work shall be
included:
a) Slinging of the precast element;
b) Tying up of erection ropes connecting to the erection hooks;
c) Cleaning of the elements and the site of erection;
d) Cleaning of the steel inserts before incorporation in the joints, lifting up of the
elements, setting them down into the correct envisaged position;
e) Adjustment to get the stipulated level, line and plumb;
f) Welding of cleats;
g) Changing of the erection tackles;
h) Putting up and removing of the necessary scaffolding or supports
i) Welding of the inserts, laying of reinforcements in joints and grouting the
joints; and
j) Finishing the joints to bring the whole work to a workmanlike finished product.
9
Installation of vertical
precast components
Installation sequence includes
 Setting out
 Lifting and installation
 Grout work
 Joist casting and sealing
10
Setting out
o Setting
reference line
and offset line
o Provide level
pads
o Fitting of
compressible
form or backer
rod on the outer
perimeter of the
wall
11
Good practices for setting
out
 Check the accuracy of
offset line
 Check the shim plate
level and stability
 Check the position for
the starter bars
 Check the compressible
form and backer rod are
properly secured
12
Lifting and installation
 Lifting and rigging
the panels
 Adjust the panel to
the position
13
Good practices for lifting
and hoisting
 Check the hoisting condition
 Check the alignment and
verticality
 Check the stability of the
erected rod before releasing
the hoisting cable
14
Grouting
work
 Prepare and seal non-
shrink motor
 Prepare and pour non-
shrink grout for pipe works
 Keep the installed panel
undisturbed for 24hours
15
Good practices
for grouting
 Before grouting check the
joint width
 The grout used must be self
compactable and must have
a free flow
 Check whether all the
horizontal joints are
properly sealed
 Collect sample test cubes
for the grout used for
important components
16
Joint casting
and sealing
 Install the joint rebar as
required
 Set up form for casting
 Carry out concrete casting
 Removes form after
sufficient strength is
attained
 Place the connecting
plates between the panels
and weld
17
Good practices for joint
casting
 Joint rebars must be
accurately placed
 During casting the formwork
should be correctly secured
 For better water tightness
the joint gap should have
proper installation of grout
18
Installation of horizontal
precast components
Installation sequence
includes
 Setting out
 Lifting and installation
 Casting of joints
19
Setting out
 Set the reference line and
the offset line
Good practice
 Check the accuracy of the
offset line
 Check the level and stability
of shim plates
 Check the dimensions of the
protruding bars
20
Lifting and installation
 Put up temporary props
 Lift and rig the
elements in position
 Align and set the level
to suit before placing
the member
21
Good practices for lifting
 Beams should be
supported minimum
at two locations
 Balcony, slabs should
be supported in more
than two locations
 Levelness of the
precast elements to be
ensured before the
joisting action
22
Casting of
joints
 For cast in situ joints
place and lap the rebars
 Set up form work for
casting of joints
 Carry out concrete
casting
23
Good practice for joints
 The joints rebars should be
accurately placed
 The formwork should be
properly placed
 Supporting beams should
be a part of formwork
24
General
considerations
 Safety precautions in the work
are of utmost importance
 Only those skilled foremen,
trained workers and fitters who
have been properly instructed
about the safety precautions to
be taken should be employed on
the job.
 Transport of people, workers or
visitors, by using cranes and
hoists should be strictly
prohibited
 In the case of tower cranes running
on rails, the track shall not have a
slope more than 0.2 percent in the
longitudinal direction. In the
transverse direction the rails shall lie
in a horizontal plane.
 The track of the crane should be
checked daily to see that all fish
plates and bolts connecting them to
the sleepers are in place and in good
condition.
25
Reference
 IS15916:2011 -Building design and erection
using prefabricated concrete — code of
practice
 CONQUAS Quality Assessment Criteria
26
THANK YOU
27

More Related Content

What's hot

Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Introduction to Building Construction
Introduction to Building Construction Introduction to Building Construction
Introduction to Building Construction Er.Karan Chauhan
 
Building maintenance
Building maintenance Building maintenance
Building maintenance Janki Patel
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDFIDHAMUKI
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONDAVIDSON ECHIDIKE
 
Construction technology presentation
Construction technology presentationConstruction technology presentation
Construction technology presentationSze Ting Kuek
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Job layout of cinstruction site
Job layout of cinstruction siteJob layout of cinstruction site
Job layout of cinstruction siteraj balar
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication constructionDivya Vishnoi
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
An introduction to the construction team
An introduction to the construction teamAn introduction to the construction team
An introduction to the construction teamCompetitive Advantage
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick WallI'mMiss Lily
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFShankar Ramasamy
 

What's hot (20)

Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Introduction to Building Construction
Introduction to Building Construction Introduction to Building Construction
Introduction to Building Construction
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
 
Construction technology presentation
Construction technology presentationConstruction technology presentation
Construction technology presentation
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Job layout of cinstruction site
Job layout of cinstruction siteJob layout of cinstruction site
Job layout of cinstruction site
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Building maintenance
Building maintenanceBuilding maintenance
Building maintenance
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
An introduction to the construction team
An introduction to the construction teamAn introduction to the construction team
An introduction to the construction team
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick Wall
 
Precast
PrecastPrecast
Precast
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 

Similar to Erection of Structural Components Guide

Precast elements
Precast elementsPrecast elements
Precast elementsShrividhyah
 
Precast elements
Precast elementsPrecast elements
Precast elementsShrividhyah
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
MFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfMFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfssuseref23d3
 
Safety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSafety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSandeep Jain
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdfXiMdhk
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfssuseref23d3
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxmahmoud909178
 
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET Journal
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated ColumnAnees Khan
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1chongyih2
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docxKaty A. Beitia G.
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 

Similar to Erection of Structural Components Guide (20)

Precast elements
Precast elementsPrecast elements
Precast elements
 
Precast elements
Precast elementsPrecast elements
Precast elements
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Column & beam
Column & beamColumn & beam
Column & beam
 
MFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfMFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdf
 
Safety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSafety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of Construction
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdf
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
Amir QC
Amir QCAmir QC
Amir QC
 
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
 
Lory Francis Navor - CV
Lory Francis Navor - CVLory Francis Navor - CV
Lory Francis Navor - CV
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Erection of Structural Components Guide

  • 1. Erection of structural components Paramathmeka S M.E structural engineering P.S.G college of technology 1
  • 2. Introduction  Erection of the structural components in prefabricated structures play the important part in the construction of the building.  The erection process includes the erection of horizontal members, vertical members or complete unit.  To ensure effective and quality installation proper planning and preparatory works are required before the erection. It includes… 2
  • 3. i. Method and sequence of assembly and erection ii. Method of providing temporary supports iii. Erection tolerance iv. Handling and rigging requirements 3
  • 4. Erection plan  The erection plan, which is normally developed by a registered professional engineer, is used to establish the size and location of cranes, the location of delivery trucks, and the sequence of erection 4
  • 5. Assembly plans  Assembly plans are similar to erection plans, except they are more detailed and they include time components for element installation and placements of concretes or grouts.  It is recommended that project specifications require the submission of an assembly plan. 5
  • 6. Assembly plan includes  Drawings depicting the assembly procedures. The plan should be prepared by a registered Professional engineer.  A work area plan, depicting items such as utilities overhead and below the work area, drainage inlet structures, and protective measures.  Details of all equipment that will be employed for the assembly of the structure.  Details of all equipment to be used to lift elements, including cranes, excavators, lifting slings, sling hooks, and jacks. Include crane locations, operation radii, and lifting calculations.  Detailed sequence of construction and a timeline for all operations. Account for setting and cure time for grouts, mechanical connections, and concrete closure pours  Calculations for all aspects of the assembly plan including, erection calculations, crane capacities, rigging calculations, temporary false work and framing, and element handling stresses. The calculations should be prepared by a registered Professional engineer  Methods of providing temporary support of the elements. Include methods of adjusting and securing the element after placement. 6
  • 7.  Procedures for controlling tolerance limits—both horizontal and vertical. Include details of any alignment jigs, including templates for projecting anchors and dowels.  A detailed installation procedure for connecting mechanical connectors, including grouting procedures  Include methods for curing grout and closure pour concrete.  Proposed methods for installing non- shrink grout and the sequence and equipment for the grouting operation.  Methods for placement of fill materials.  Methods for forming and sealing closure pour.  Methods and equipment for installation of post-tensioning systems, including stressing and grouting procedures. 7
  • 8. Preparatory work  Check for site accessibility  Check for delivery checklist  Check for adequate crane capacity and working clearance for hosting the elements  Conduct sample measurements  Conduct visual inspection.  Check for location and condition for lifting  Check for accessibility for unloading point  Check that the storage area condition. 8
  • 9. As per IS 15916:2011  In the erection of precast elements, all the following items of work shall be included: a) Slinging of the precast element; b) Tying up of erection ropes connecting to the erection hooks; c) Cleaning of the elements and the site of erection; d) Cleaning of the steel inserts before incorporation in the joints, lifting up of the elements, setting them down into the correct envisaged position; e) Adjustment to get the stipulated level, line and plumb; f) Welding of cleats; g) Changing of the erection tackles; h) Putting up and removing of the necessary scaffolding or supports i) Welding of the inserts, laying of reinforcements in joints and grouting the joints; and j) Finishing the joints to bring the whole work to a workmanlike finished product. 9
  • 10. Installation of vertical precast components Installation sequence includes  Setting out  Lifting and installation  Grout work  Joist casting and sealing 10
  • 11. Setting out o Setting reference line and offset line o Provide level pads o Fitting of compressible form or backer rod on the outer perimeter of the wall 11
  • 12. Good practices for setting out  Check the accuracy of offset line  Check the shim plate level and stability  Check the position for the starter bars  Check the compressible form and backer rod are properly secured 12
  • 13. Lifting and installation  Lifting and rigging the panels  Adjust the panel to the position 13
  • 14. Good practices for lifting and hoisting  Check the hoisting condition  Check the alignment and verticality  Check the stability of the erected rod before releasing the hoisting cable 14
  • 15. Grouting work  Prepare and seal non- shrink motor  Prepare and pour non- shrink grout for pipe works  Keep the installed panel undisturbed for 24hours 15
  • 16. Good practices for grouting  Before grouting check the joint width  The grout used must be self compactable and must have a free flow  Check whether all the horizontal joints are properly sealed  Collect sample test cubes for the grout used for important components 16
  • 17. Joint casting and sealing  Install the joint rebar as required  Set up form for casting  Carry out concrete casting  Removes form after sufficient strength is attained  Place the connecting plates between the panels and weld 17
  • 18. Good practices for joint casting  Joint rebars must be accurately placed  During casting the formwork should be correctly secured  For better water tightness the joint gap should have proper installation of grout 18
  • 19. Installation of horizontal precast components Installation sequence includes  Setting out  Lifting and installation  Casting of joints 19
  • 20. Setting out  Set the reference line and the offset line Good practice  Check the accuracy of the offset line  Check the level and stability of shim plates  Check the dimensions of the protruding bars 20
  • 21. Lifting and installation  Put up temporary props  Lift and rig the elements in position  Align and set the level to suit before placing the member 21
  • 22. Good practices for lifting  Beams should be supported minimum at two locations  Balcony, slabs should be supported in more than two locations  Levelness of the precast elements to be ensured before the joisting action 22
  • 23. Casting of joints  For cast in situ joints place and lap the rebars  Set up form work for casting of joints  Carry out concrete casting 23
  • 24. Good practice for joints  The joints rebars should be accurately placed  The formwork should be properly placed  Supporting beams should be a part of formwork 24
  • 25. General considerations  Safety precautions in the work are of utmost importance  Only those skilled foremen, trained workers and fitters who have been properly instructed about the safety precautions to be taken should be employed on the job.  Transport of people, workers or visitors, by using cranes and hoists should be strictly prohibited  In the case of tower cranes running on rails, the track shall not have a slope more than 0.2 percent in the longitudinal direction. In the transverse direction the rails shall lie in a horizontal plane.  The track of the crane should be checked daily to see that all fish plates and bolts connecting them to the sleepers are in place and in good condition. 25
  • 26. Reference  IS15916:2011 -Building design and erection using prefabricated concrete — code of practice  CONQUAS Quality Assessment Criteria 26