Company: ROWAD Modern Engineering
Project: GRAND HOTEL DE N'DJAMENA
Client: CFE Contracting Company Ltd
Subject: Weekly Report (No.4)
Date: 9-Feb-13
Prepared By 
Yasser Abouzeid
 
Month Week
1. Contract Details
CFE Project Manager: Olivier Mahieu Project Manager: Olivier Mahieu RME Project Manager: Mohammed Mustafa Be Auth. Representative: Mohammed Mustafa Belal
CFE Construction Manager: Marc THIOUX 0 0 RME Construction Manager: Hany Hanna Construction Manager: 0
Project Controls: 0 0 0 RME Technical OfficeManager: Yasser Abouzaid 0 0
2. Health & Safety 3. Weather
Toolbox Topic This Week : Saturday Sunny Wednesday Partly Cloudy
Sunday Sunny Thursday Sunny
Lost Workday Cases (LWDC) : Monday Sunny Friday Sunny
Restricted Workday Cases (RWDC) Tuesday Sunny
First Aid (FA) : 4. Environmental Issues
Major Property Damage (MAJPD) : Previous Report
Minor Property Damage (MINPD) : Environmental Incidents (MAXENV)
Near Miss Incidents : Environmental Incidents (MINENV)
Contract Man-Days :
Construction :
Accident Free Man-days :
Construction :
5. Key Dates LD LD Achieved Days
Start of Work Foundations of ZONE B F
Foundations of ZONE A Finish Floor of ZONE B F
Ground Floor of ZONE A Foundations of ZONE C F
Finish Floor of ZONE A Finish Floor of ZONE C F
This Period
5,437
38°C -
2
32°C -
32°C -
35°C -
38°C -
-7
15/02/2013
10/01/2013
4,687 750 5,437
4,687
09/09/2013
PROJECT
0
4
0
Total ToDateThis Period
38°C -30°C -
15
WEEKLY CONSTRUCTION STATUS REPORT
09/09/2013
0
17/01/2013
28/02/2013
5,435
A
F
0
016-Oct-13 16-Oct-13
-13
0
28-Feb-13
Contract
-9
DaysAchieved
29/10/2012
Fcst/Actual
07/11/2012 A
Previous Todate
0
2
0 0
0 0
0
0
750
750
0
5,435
750
0
4,685
0
0
4,685
0
0 0
30-Mar-13
0
0
-30
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
15/04/2013 15/04/2013
-17
Fcst/Actual
15/02/2013
Contract
29/01/2013
F
Total ToDate
0
0
2
0
2/10/2013 1 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
6. Weekly Physical Progress
7. Achievements 8. QA / QC Status
9. Specification / Designs
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
01-Nov-12
15-Nov-12
29-Nov-12
13-Dec-12
27-Dec-12
10-Jan-13
24-Jan-13
07-Feb-13
21-Feb-13
07-Mar-13
21-Mar-13
04-Apr-13
18-Apr-13
02-May-13
16-May-13
30-May-13
13-Jun-13
27-Jun-13
11-Jul-13
25-Jul-13
08-Aug-13
22-Aug-13
05-Sep-13
19-Sep-13
03-Oct-13
17-Oct-13
Plan
Actual
Struct
Total Drawing
Submittals
193
Approved 153
0
200
400
600
800
1000
1200
1400
1600
Shop Drawings
WEEK
Plan :
Actual :
Variance:
22.80%
20.45%
-2.35%
15
2/10/2013 2 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
Look Forward - Next Week
Description Description
Installed of 21 precast beams
Item
We have only 9 coulmn and finish the coulmn of ground floor 1.
2.
8.
7.
Finish of pouring semells of Building B axis bA-bM/b04-b07
1.
Installed of 59 precast slab 6 cm 1st floor of zone A
Installed of 60 precast beams
finish pouring 8 cm from axis aB-aF/a2-a10
Installed of 100 precast slab 6 cm 1st floor of zone A
Installed of 20 precast slab 6 cm ground floor of zone B Finish of pouring Footing of Building B
Pouring of 40 precast slab 6 cm for zone B
8.
Pouring of 70 precast beams
Finish of walls axis aB-aC/a11-a14a, aD/a11-a14a, aR-aO/a14, aR-aO/a11& a20-a21/aM-An
Item
7.
5.
11. WIP Current Week
Pouring of 69 precast beams 3.
2.
3.
pouring walls at axis a14a/aB-aE,aR/a11-a14& a20-a21/aL-aM
Finish Columns of ground floor
6.
4.
6.
5.
Pouring of 121 precast slab 6 cm
9.
10. Manpower Summary On Site (6 Months Look Ahead)
4. Pouring of 120 precast slab 6 cm
Wk 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Plan 0 723 765 923 923 923 923 933 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 832 832 832
Actual 0 677 804 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
350
700
1050
1400
1750
2100
2450
2800
3150
3500
2/10/2013 3 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
Labors
13. Manpower Detail (Full Time Equivalent -m/d)
CarpenterNon-Manual
Concrete LaborSteel Fixer
14 15 16 17
Plan 126 126 126 126
Actual 126 126
Cum Plan 1487 1613 1739 1865
Cum Actual 1487 1613
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0
20
40
60
80
100
120
140
14 15 16 17
Plan 210 240 300 300
Actual 133 252
Cum Plan 1162 1402 1702 2002
Cum Actual 1085 1337
0
500
1000
1500
2000
2500
0
50
100
150
200
250
300
350
14 15 16 17
Plan 160 160 198 198
Actual 167 183
Cum Plan 1808 1968 2166 2364
Cum Actual 1815 1998
0
500
1000
1500
2000
2500
0
50
100
150
200
250
14 15 16 17
Plan 116 128 158 158
Actual 99 102
Cum Plan 693 821 979 1137
Cum Actual 676 778
0
200
400
600
800
1000
1200
0
20
40
60
80
100
120
140
160
180
14 15 16 17
Plan 90 90 120 120
Actual 117 106
Cum Plan 623 713 833 953
Cum Actual 650 756
0
200
400
600
800
1000
1200
0
20
40
60
80
100
120
140
2/10/2013 4 of 9
4‐Feb 5‐Feb 6‐Feb 7‐Feb 8‐Feb 9‐Feb
Beton QY
RME
32 25 50 32 26 40
rate of pouring daily Beton QY RME
2/10/2013 5 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
14. Key Quantity Installation Tracking (Total Project)
Concrete Works
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
-
100
200
300
400
500
600
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
Cumulative
Quantitym3
Concrete Works Plan Concrete Works Actual
Concrete Works Cum Plan Concrete Works Cum Actual
2/10/2013 6 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
Steel Works
-
200
400
600
800
1,000
1,200
1,400
1,600
1,800
2,000
-
10.00
20.00
30.00
40.00
50.00
60.00
70.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
Cumulative
Quantityton
Steel Works Plan Steel Works Actual
Steel Works Cum Plan Steel Works Cum Actual
2/10/2013 7 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
Precast slabs slab 6 cm
-
500
1,000
1,500
2,000
2,500
3,000
-
20.00
40.00
60.00
80.00
100.00
120.00
140.00
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
Cumulative
Quantityno
Week no
Precast slabs slab 6 cm Plan Precast slabs slab 6 cm Actual Precast slabs slab 6 cm Cum Plan Precast slabs slab 6 cm Cum Actual
2/10/2013 8 of 9
Month Week
PROJECT
4 15
WEEKLY CONSTRUCTION STATUS REPORT
Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA
Precast Beams
-
200
400
600
800
1,000
1,200
1,400
1,600
0
10
20
30
40
50
60
70
80
10
12
14
16
18
20
22
24
26
28
30
32
34
36
Cumulative
Quantityno
Week no
Precast Beams Plan Precast Beams Actual
Precast Beams Cum Plan Precast Beams Cum Actual
2/10/2013 9 of 9

More Related Content

Similar to W15 Weekly Report RME

Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.docFeteneBefekadu
 
PLF-1408-AT-SD-CO-011 - REV 00
PLF-1408-AT-SD-CO-011 - REV 00PLF-1408-AT-SD-CO-011 - REV 00
PLF-1408-AT-SD-CO-011 - REV 00Mansoor Sakharkar
 
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdfHansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdfCanberra Institute of technology
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadiumSLIIT, Sri Lanka
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposalkjanand
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Eslam cv final 2016
Eslam cv final 2016Eslam cv final 2016
Eslam cv final 2016eslam orabi
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015Ahmed Yehia
 

Similar to W15 Weekly Report RME (20)

3. Hansons lodge.pdf
3. Hansons lodge.pdf3. Hansons lodge.pdf
3. Hansons lodge.pdf
 
Training PPT
Training PPTTraining PPT
Training PPT
 
injo slip update
injo slip updateinjo slip update
injo slip update
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
 
PLF-1408-AT-SD-CO-011 - REV 00
PLF-1408-AT-SD-CO-011 - REV 00PLF-1408-AT-SD-CO-011 - REV 00
PLF-1408-AT-SD-CO-011 - REV 00
 
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdfHansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
Hansens Lodge version 1.2 updated Layout for Ready skills updated on 171022.pdf
 
Hansens Lodge Take-off.pdf
Hansens Lodge Take-off.pdfHansens Lodge Take-off.pdf
Hansens Lodge Take-off.pdf
 
Hansens Lodge for Plan and Organise
Hansens Lodge for Plan and OrganiseHansens Lodge for Plan and Organise
Hansens Lodge for Plan and Organise
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Road Map
Road MapRoad Map
Road Map
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
Muhammad_Aslam_CV
Muhammad_Aslam_CVMuhammad_Aslam_CV
Muhammad_Aslam_CV
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Eslam cv final 2016
Eslam cv final 2016Eslam cv final 2016
Eslam cv final 2016
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015
 

W15 Weekly Report RME

  • 1.   Company: ROWAD Modern Engineering Project: GRAND HOTEL DE N'DJAMENA Client: CFE Contracting Company Ltd Subject: Weekly Report (No.4) Date: 9-Feb-13 Prepared By  Yasser Abouzeid  
  • 2. Month Week 1. Contract Details CFE Project Manager: Olivier Mahieu Project Manager: Olivier Mahieu RME Project Manager: Mohammed Mustafa Be Auth. Representative: Mohammed Mustafa Belal CFE Construction Manager: Marc THIOUX 0 0 RME Construction Manager: Hany Hanna Construction Manager: 0 Project Controls: 0 0 0 RME Technical OfficeManager: Yasser Abouzaid 0 0 2. Health & Safety 3. Weather Toolbox Topic This Week : Saturday Sunny Wednesday Partly Cloudy Sunday Sunny Thursday Sunny Lost Workday Cases (LWDC) : Monday Sunny Friday Sunny Restricted Workday Cases (RWDC) Tuesday Sunny First Aid (FA) : 4. Environmental Issues Major Property Damage (MAJPD) : Previous Report Minor Property Damage (MINPD) : Environmental Incidents (MAXENV) Near Miss Incidents : Environmental Incidents (MINENV) Contract Man-Days : Construction : Accident Free Man-days : Construction : 5. Key Dates LD LD Achieved Days Start of Work Foundations of ZONE B F Foundations of ZONE A Finish Floor of ZONE B F Ground Floor of ZONE A Foundations of ZONE C F Finish Floor of ZONE A Finish Floor of ZONE C F This Period 5,437 38°C - 2 32°C - 32°C - 35°C - 38°C - -7 15/02/2013 10/01/2013 4,687 750 5,437 4,687 09/09/2013 PROJECT 0 4 0 Total ToDateThis Period 38°C -30°C - 15 WEEKLY CONSTRUCTION STATUS REPORT 09/09/2013 0 17/01/2013 28/02/2013 5,435 A F 0 016-Oct-13 16-Oct-13 -13 0 28-Feb-13 Contract -9 DaysAchieved 29/10/2012 Fcst/Actual 07/11/2012 A Previous Todate 0 2 0 0 0 0 0 0 750 750 0 5,435 750 0 4,685 0 0 4,685 0 0 0 30-Mar-13 0 0 -30 Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA 15/04/2013 15/04/2013 -17 Fcst/Actual 15/02/2013 Contract 29/01/2013 F Total ToDate 0 0 2 0 2/10/2013 1 of 9
  • 3. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA 6. Weekly Physical Progress 7. Achievements 8. QA / QC Status 9. Specification / Designs 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 01-Nov-12 15-Nov-12 29-Nov-12 13-Dec-12 27-Dec-12 10-Jan-13 24-Jan-13 07-Feb-13 21-Feb-13 07-Mar-13 21-Mar-13 04-Apr-13 18-Apr-13 02-May-13 16-May-13 30-May-13 13-Jun-13 27-Jun-13 11-Jul-13 25-Jul-13 08-Aug-13 22-Aug-13 05-Sep-13 19-Sep-13 03-Oct-13 17-Oct-13 Plan Actual Struct Total Drawing Submittals 193 Approved 153 0 200 400 600 800 1000 1200 1400 1600 Shop Drawings WEEK Plan : Actual : Variance: 22.80% 20.45% -2.35% 15 2/10/2013 2 of 9
  • 4. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA Look Forward - Next Week Description Description Installed of 21 precast beams Item We have only 9 coulmn and finish the coulmn of ground floor 1. 2. 8. 7. Finish of pouring semells of Building B axis bA-bM/b04-b07 1. Installed of 59 precast slab 6 cm 1st floor of zone A Installed of 60 precast beams finish pouring 8 cm from axis aB-aF/a2-a10 Installed of 100 precast slab 6 cm 1st floor of zone A Installed of 20 precast slab 6 cm ground floor of zone B Finish of pouring Footing of Building B Pouring of 40 precast slab 6 cm for zone B 8. Pouring of 70 precast beams Finish of walls axis aB-aC/a11-a14a, aD/a11-a14a, aR-aO/a14, aR-aO/a11& a20-a21/aM-An Item 7. 5. 11. WIP Current Week Pouring of 69 precast beams 3. 2. 3. pouring walls at axis a14a/aB-aE,aR/a11-a14& a20-a21/aL-aM Finish Columns of ground floor 6. 4. 6. 5. Pouring of 121 precast slab 6 cm 9. 10. Manpower Summary On Site (6 Months Look Ahead) 4. Pouring of 120 precast slab 6 cm Wk 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Plan 0 723 765 923 923 923 923 933 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 940 832 832 832 Actual 0 677 804 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 350 700 1050 1400 1750 2100 2450 2800 3150 3500 2/10/2013 3 of 9
  • 5. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA Labors 13. Manpower Detail (Full Time Equivalent -m/d) CarpenterNon-Manual Concrete LaborSteel Fixer 14 15 16 17 Plan 126 126 126 126 Actual 126 126 Cum Plan 1487 1613 1739 1865 Cum Actual 1487 1613 0 200 400 600 800 1000 1200 1400 1600 1800 2000 0 20 40 60 80 100 120 140 14 15 16 17 Plan 210 240 300 300 Actual 133 252 Cum Plan 1162 1402 1702 2002 Cum Actual 1085 1337 0 500 1000 1500 2000 2500 0 50 100 150 200 250 300 350 14 15 16 17 Plan 160 160 198 198 Actual 167 183 Cum Plan 1808 1968 2166 2364 Cum Actual 1815 1998 0 500 1000 1500 2000 2500 0 50 100 150 200 250 14 15 16 17 Plan 116 128 158 158 Actual 99 102 Cum Plan 693 821 979 1137 Cum Actual 676 778 0 200 400 600 800 1000 1200 0 20 40 60 80 100 120 140 160 180 14 15 16 17 Plan 90 90 120 120 Actual 117 106 Cum Plan 623 713 833 953 Cum Actual 650 756 0 200 400 600 800 1000 1200 0 20 40 60 80 100 120 140 2/10/2013 4 of 9
  • 6. 4‐Feb 5‐Feb 6‐Feb 7‐Feb 8‐Feb 9‐Feb Beton QY RME 32 25 50 32 26 40 rate of pouring daily Beton QY RME 2/10/2013 5 of 9
  • 7. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA 14. Key Quantity Installation Tracking (Total Project) Concrete Works - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 - 100 200 300 400 500 600 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Cumulative Quantitym3 Concrete Works Plan Concrete Works Actual Concrete Works Cum Plan Concrete Works Cum Actual 2/10/2013 6 of 9
  • 8. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA Steel Works - 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 - 10.00 20.00 30.00 40.00 50.00 60.00 70.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Cumulative Quantityton Steel Works Plan Steel Works Actual Steel Works Cum Plan Steel Works Cum Actual 2/10/2013 7 of 9
  • 9. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA Precast slabs slab 6 cm - 500 1,000 1,500 2,000 2,500 3,000 - 20.00 40.00 60.00 80.00 100.00 120.00 140.00 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 Cumulative Quantityno Week no Precast slabs slab 6 cm Plan Precast slabs slab 6 cm Actual Precast slabs slab 6 cm Cum Plan Precast slabs slab 6 cm Cum Actual 2/10/2013 8 of 9
  • 10. Month Week PROJECT 4 15 WEEKLY CONSTRUCTION STATUS REPORT Contract 020/2011 :CONSTRUCTION DU GRAND HOTEL DE N'DJAMENA Precast Beams - 200 400 600 800 1,000 1,200 1,400 1,600 0 10 20 30 40 50 60 70 80 10 12 14 16 18 20 22 24 26 28 30 32 34 36 Cumulative Quantityno Week no Precast Beams Plan Precast Beams Actual Precast Beams Cum Plan Precast Beams Cum Actual 2/10/2013 9 of 9