SlideShare a Scribd company logo
1 of 18
Estimating
Using Effort and Duration
Project Management
Introduction to Estimation
• Estimating is argued to be one of the most difficult tasks in Project Scheduling
• This is due to the lack of available specific data regarding product resources i.e.
how much a product will cost, how long it will take etc.
• The lack of this data means that project managers can only provide estimates
• These estimates are usually wide ranging
• Wide ranging estimates are better than specific estimates which are likely to be
wrong
Estimating Project costs with Duration
and Effort
• Before the start of a project three things must be estimated:

• Duration: time the project will take
• Effort: the amount of work
• Cost: how much the project will cost financially
Estimating Project Costs with Duration
and Effort
• Effort must be estimated first
• Duration can be estimated from the amount of effort required and
the resources which are available
• Once effort and duration have been establish project costs can be
estimated using labour and non-labour items
Techniques for Estimating
• Quantitatively based or Parametric Estimating
• Analogous Estimating or As-buts
• Bottom-up Estimating
• Using Learning Curve Effects
• Wishful thinking
• Expert judgement
Parametric Estimating
• Works best when there is existing experience of similar projects
• Project is broken down into units which can then be estimated using independent
variables
• These variables are often standard or previously known variables
• Costs can be estimated from knowledge of what work is being undertaken
• Relies on repetition in previous projects
• Similar to Analogous estimating but follows a more statistical approach

• The accuracy of the data/known variables effects the accuracy of this approach
Analogues Estimating or As….Buts
•
•
•
•

Useful for early project estimates
The organisation uses previous experience which is similar to make an estimate
Use costs from previous experience as a guideline for estimation
If previous projects are not reviewed then the accuracy of previous estimates is
unknown
• Therefore previous costs etc. might not provide valuable valid estimates
• This may cause mistakes to be repeated as no learning has occurred
• Previous estimates can be used if they are reviewed and augmented
Bottom-up Estimating
• The project is broken down into estimated components
• Each component is broken down further to allow for greater understanding
• The costs of each work component is summed from the bottom up to provide an
estimation for the whole project.
Learning Curve Effects
• There will be areas of repetition in projects, repetition decreases the time
required for tasks as they are known and learning has already occurred
• Subsequent improvements in speed are seen to become smaller over time
• This can be quantified using the following formula:
Yx = Kxn
where
• x = the number of times the task has been carried out
• Yx = time taken to carry out the task the xth time
• K = time taken to carry out the task the first time
• n = log b/log 2 where b = learning rate
Wishful Thinking
Some causes of wishful thinking occurring are:
• Optimism Bias: being over-optimistic regarding timeframes and costs
• Politics: for examples when objectives are regarded as being more
important than costs
• Failure to be systematic about planning: i.e. people making estimates
can be complacent and/or unqualified
Expert Judgement
• Estimation requires a degree of expert judgement
• There is a degree of expert judgement required in the project and of the business
area.
• The project manager is assumed to have expert judgement
Problems with Estimates
• Inappropriate use of estimates: i.e. rough estimates may be used as
definitive estimates.
• Inappropriate data used to generate estimates: such as irrelevant past
experience
• Estimates are taken out of context: for example initial estimates are
used when changes have been made to the project
Nature, Role and Accuracy of Estimate
Types
Name
Nature
Role
Accuracy
Rough/Ballpark

Much uncertainty as to
what is involved

Early check on feasibility
of brief

As-buts

As was carried out
With an appropriate
previously but with some contingency factor, can
amendments
be used for proposals

Moderate

Detailed Estimates

Some initial work is
carried out to determine
what the likely problems
are going to be

Proposals

Moderate

To Finish

Much of the Project is
completed and
additional funding is
needed to complete the
tasks

Additional fund requests

High

Source: Maylor. 2010. Project Management

Very low
Parkinson’s Law
• An activity will expand to fill the time available
• A critical review of Parkinson’s Law and it’s implications can be found
in the article below
Genaro J. Gutierrez and Panagiotis Kouvelis, Parkinson's Law and Its
Implications for Project Management. Management Science. Vol.
37, No. 8 (Aug., 1991), pp. 990-1001
Techniques for Accuracy
1.
2.
3.
4.
5.
6.

Clarify the project priorities, understand the scope of the project
Incorporate time to generate estimates in the project plan
Break the project down into detailed tasks
Use learning from previous projects
Avoid making estimates to please management
Refine the project scope throughout the duration of the project to
improve accuracy
7. Use multiple estimating techniques
Techniques for Accuracy
• Bottom up estimating and Parametric estimating offer the highest
levels of accuracy
• Bottom up estimating: provides the highest level of accuracy when
there is suitable detail regarding the components
• Parametric Estimating: provides high levels of accuracy when the data
is of good quality and due to the statistical nature of the approach
Further Reading
• Maylor: Project Management, 4th ed, Chapter 6 & 8

• Chapman., and Ward. 2003. Constructively Simple Estimating: a
Project Management Example. Journal of the Operation Research
Society. 54. 1050-1058.
References
• Maylor, H., 2010. Project Management. 4th ed. Chester: Pearson
• Tom Mochal, 2006. Estimate project costs after you have estimated effort and duration. [Online]
Available at: http://www.techrepublic.com/article/estimate-/project-costs-after-you-haveestimated-effort-and-duration/ [Accessed: 07/11/13]
• CHRIS O'HALLORAN, 2013. Project Estimation Techniques and Templates. [Online] Available at:
http://strikingprojectmanagement.com/project-estimation/ [Accessed 07/11/13]
• Adele Sommers, 2013. 12 Tips for Accurate Project Estimating. [Online] Availbale at:
http://www.projectsmart.co.uk/12-tips-for-accurate-project-estimating.html [Accessed 07/11/13]

• MindTools, 2013. Estimating Time Accurately. [Online] Available at:
http://www.mindtools.com/pages/article/newPPM_01.htm [Accessed 07/11/13]

More Related Content

What's hot

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
Software engineering 11 project scheduling
Software engineering 11 project schedulingSoftware engineering 11 project scheduling
Software engineering 11 project schedulingVaibhav Khanna
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
It's not a bug, it's a feature!
It's not a bug, it's a feature!It's not a bug, it's a feature!
It's not a bug, it's a feature!SPC Adriatics
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costsmairemic
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
 
Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?SPC Adriatics
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and trackingComputer_ at_home
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)anjalatchi
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration EstimationHarsh Behl
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 

What's hot (19)

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Software engineering 11 project scheduling
Software engineering 11 project schedulingSoftware engineering 11 project scheduling
Software engineering 11 project scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
It's not a bug, it's a feature!
It's not a bug, it's a feature!It's not a bug, it's a feature!
It's not a bug, it's a feature!
 
Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 
Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?Project Server: Who can benefit from it and how?
Project Server: Who can benefit from it and how?
 
Ch03
Ch03Ch03
Ch03
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and tracking
 
Is Sks7000
Is Sks7000Is Sks7000
Is Sks7000
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 

Viewers also liked

12 Cities H1 2015 (double pages lo-res)
12 Cities H1 2015 (double pages lo-res)12 Cities H1 2015 (double pages lo-res)
12 Cities H1 2015 (double pages lo-res)Josh Gorin
 
EMPO EXPO 2015 Presentation
EMPO EXPO 2015 PresentationEMPO EXPO 2015 Presentation
EMPO EXPO 2015 PresentationNigel Parry
 
English: That mysterious language - Go! idiomas
English: That mysterious language - Go! idiomasEnglish: That mysterious language - Go! idiomas
English: That mysterious language - Go! idiomasGo! idiomas
 
Learning about food wasting
Learning about food wastingLearning about food wasting
Learning about food wastingedytatg
 
front cover Analysis
front cover Analysis front cover Analysis
front cover Analysis chloeditch
 
Battle of gettysburg
Battle of gettysburgBattle of gettysburg
Battle of gettysburgehadams
 
Strategy for a Digital World by Louisa Heinrich
Strategy for a Digital World by Louisa HeinrichStrategy for a Digital World by Louisa Heinrich
Strategy for a Digital World by Louisa HeinrichGus Murray
 
Prof Bron lecture. The A-Z of MGD
Prof Bron lecture. The A-Z of MGDProf Bron lecture. The A-Z of MGD
Prof Bron lecture. The A-Z of MGDoxfordshireloc
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Mactek promo dec.2013 low
Mactek promo dec.2013 lowMactek promo dec.2013 low
Mactek promo dec.2013 lowdikarconsult
 
Schumpeter the mommy track cae
Schumpeter the mommy track caeSchumpeter the mommy track cae
Schumpeter the mommy track caejeanphilippeguy
 

Viewers also liked (15)

12 Cities H1 2015 (double pages lo-res)
12 Cities H1 2015 (double pages lo-res)12 Cities H1 2015 (double pages lo-res)
12 Cities H1 2015 (double pages lo-res)
 
EMPO EXPO 2015 Presentation
EMPO EXPO 2015 PresentationEMPO EXPO 2015 Presentation
EMPO EXPO 2015 Presentation
 
English: That mysterious language - Go! idiomas
English: That mysterious language - Go! idiomasEnglish: That mysterious language - Go! idiomas
English: That mysterious language - Go! idiomas
 
Learning about food wasting
Learning about food wastingLearning about food wasting
Learning about food wasting
 
front cover Analysis
front cover Analysis front cover Analysis
front cover Analysis
 
Foursquare
Foursquare Foursquare
Foursquare
 
Arq. flor
Arq. florArq. flor
Arq. flor
 
All aboutmango
All aboutmangoAll aboutmango
All aboutmango
 
Battle of gettysburg
Battle of gettysburgBattle of gettysburg
Battle of gettysburg
 
IBM_WebSphere_12_23_16_PM
IBM_WebSphere_12_23_16_PMIBM_WebSphere_12_23_16_PM
IBM_WebSphere_12_23_16_PM
 
Strategy for a Digital World by Louisa Heinrich
Strategy for a Digital World by Louisa HeinrichStrategy for a Digital World by Louisa Heinrich
Strategy for a Digital World by Louisa Heinrich
 
Prof Bron lecture. The A-Z of MGD
Prof Bron lecture. The A-Z of MGDProf Bron lecture. The A-Z of MGD
Prof Bron lecture. The A-Z of MGD
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Mactek promo dec.2013 low
Mactek promo dec.2013 lowMactek promo dec.2013 low
Mactek promo dec.2013 low
 
Schumpeter the mommy track cae
Schumpeter the mommy track caeSchumpeter the mommy track cae
Schumpeter the mommy track cae
 

Similar to Estimating

Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and consPragnendra Rahevar
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdfAliaaAl4
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfAnatole9
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planningShruti Kunwar
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptxRenvic
 
Unit 3 Project management PPT documentss
Unit 3 Project management PPT documentssUnit 3 Project management PPT documentss
Unit 3 Project management PPT documentss19UBCA020HARIHARANK
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdfNabeel Ahmad
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
CISA_WK_3.pptx
CISA_WK_3.pptxCISA_WK_3.pptx
CISA_WK_3.pptxdotco
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptxgezaegebre1
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 

Similar to Estimating (20)

Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdf
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Ppt.pptx
Ppt.pptxPpt.pptx
Ppt.pptx
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdf
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planning
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
 
Unit 3 Project management PPT documentss
Unit 3 Project management PPT documentssUnit 3 Project management PPT documentss
Unit 3 Project management PPT documentss
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
CISA_WK_3.pptx
CISA_WK_3.pptxCISA_WK_3.pptx
CISA_WK_3.pptx
 
7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx7 Project planning for software engineering.pptx
7 Project planning for software engineering.pptx
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Adamson "Project Management, Predictive Planning"
Adamson "Project Management, Predictive Planning"Adamson "Project Management, Predictive Planning"
Adamson "Project Management, Predictive Planning"
 

More from Nicola2903

Network diagrams
Network diagramsNetwork diagrams
Network diagramsNicola2903
 
Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown StructureNicola2903
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureNicola2903
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project SchedulingNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt ChartNicola2903
 

More from Nicola2903 (11)

Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project Scheduling
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 

Recently uploaded

Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Neo4j
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsPrecisely
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 

Recently uploaded (20)

Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power Systems
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 

Estimating

  • 1. Estimating Using Effort and Duration Project Management
  • 2. Introduction to Estimation • Estimating is argued to be one of the most difficult tasks in Project Scheduling • This is due to the lack of available specific data regarding product resources i.e. how much a product will cost, how long it will take etc. • The lack of this data means that project managers can only provide estimates • These estimates are usually wide ranging • Wide ranging estimates are better than specific estimates which are likely to be wrong
  • 3. Estimating Project costs with Duration and Effort • Before the start of a project three things must be estimated: • Duration: time the project will take • Effort: the amount of work • Cost: how much the project will cost financially
  • 4. Estimating Project Costs with Duration and Effort • Effort must be estimated first • Duration can be estimated from the amount of effort required and the resources which are available • Once effort and duration have been establish project costs can be estimated using labour and non-labour items
  • 5. Techniques for Estimating • Quantitatively based or Parametric Estimating • Analogous Estimating or As-buts • Bottom-up Estimating • Using Learning Curve Effects • Wishful thinking • Expert judgement
  • 6. Parametric Estimating • Works best when there is existing experience of similar projects • Project is broken down into units which can then be estimated using independent variables • These variables are often standard or previously known variables • Costs can be estimated from knowledge of what work is being undertaken • Relies on repetition in previous projects • Similar to Analogous estimating but follows a more statistical approach • The accuracy of the data/known variables effects the accuracy of this approach
  • 7. Analogues Estimating or As….Buts • • • • Useful for early project estimates The organisation uses previous experience which is similar to make an estimate Use costs from previous experience as a guideline for estimation If previous projects are not reviewed then the accuracy of previous estimates is unknown • Therefore previous costs etc. might not provide valuable valid estimates • This may cause mistakes to be repeated as no learning has occurred • Previous estimates can be used if they are reviewed and augmented
  • 8. Bottom-up Estimating • The project is broken down into estimated components • Each component is broken down further to allow for greater understanding • The costs of each work component is summed from the bottom up to provide an estimation for the whole project.
  • 9. Learning Curve Effects • There will be areas of repetition in projects, repetition decreases the time required for tasks as they are known and learning has already occurred • Subsequent improvements in speed are seen to become smaller over time • This can be quantified using the following formula: Yx = Kxn where • x = the number of times the task has been carried out • Yx = time taken to carry out the task the xth time • K = time taken to carry out the task the first time • n = log b/log 2 where b = learning rate
  • 10. Wishful Thinking Some causes of wishful thinking occurring are: • Optimism Bias: being over-optimistic regarding timeframes and costs • Politics: for examples when objectives are regarded as being more important than costs • Failure to be systematic about planning: i.e. people making estimates can be complacent and/or unqualified
  • 11. Expert Judgement • Estimation requires a degree of expert judgement • There is a degree of expert judgement required in the project and of the business area. • The project manager is assumed to have expert judgement
  • 12. Problems with Estimates • Inappropriate use of estimates: i.e. rough estimates may be used as definitive estimates. • Inappropriate data used to generate estimates: such as irrelevant past experience • Estimates are taken out of context: for example initial estimates are used when changes have been made to the project
  • 13. Nature, Role and Accuracy of Estimate Types Name Nature Role Accuracy Rough/Ballpark Much uncertainty as to what is involved Early check on feasibility of brief As-buts As was carried out With an appropriate previously but with some contingency factor, can amendments be used for proposals Moderate Detailed Estimates Some initial work is carried out to determine what the likely problems are going to be Proposals Moderate To Finish Much of the Project is completed and additional funding is needed to complete the tasks Additional fund requests High Source: Maylor. 2010. Project Management Very low
  • 14. Parkinson’s Law • An activity will expand to fill the time available • A critical review of Parkinson’s Law and it’s implications can be found in the article below Genaro J. Gutierrez and Panagiotis Kouvelis, Parkinson's Law and Its Implications for Project Management. Management Science. Vol. 37, No. 8 (Aug., 1991), pp. 990-1001
  • 15. Techniques for Accuracy 1. 2. 3. 4. 5. 6. Clarify the project priorities, understand the scope of the project Incorporate time to generate estimates in the project plan Break the project down into detailed tasks Use learning from previous projects Avoid making estimates to please management Refine the project scope throughout the duration of the project to improve accuracy 7. Use multiple estimating techniques
  • 16. Techniques for Accuracy • Bottom up estimating and Parametric estimating offer the highest levels of accuracy • Bottom up estimating: provides the highest level of accuracy when there is suitable detail regarding the components • Parametric Estimating: provides high levels of accuracy when the data is of good quality and due to the statistical nature of the approach
  • 17. Further Reading • Maylor: Project Management, 4th ed, Chapter 6 & 8 • Chapman., and Ward. 2003. Constructively Simple Estimating: a Project Management Example. Journal of the Operation Research Society. 54. 1050-1058.
  • 18. References • Maylor, H., 2010. Project Management. 4th ed. Chester: Pearson • Tom Mochal, 2006. Estimate project costs after you have estimated effort and duration. [Online] Available at: http://www.techrepublic.com/article/estimate-/project-costs-after-you-haveestimated-effort-and-duration/ [Accessed: 07/11/13] • CHRIS O'HALLORAN, 2013. Project Estimation Techniques and Templates. [Online] Available at: http://strikingprojectmanagement.com/project-estimation/ [Accessed 07/11/13] • Adele Sommers, 2013. 12 Tips for Accurate Project Estimating. [Online] Availbale at: http://www.projectsmart.co.uk/12-tips-for-accurate-project-estimating.html [Accessed 07/11/13] • MindTools, 2013. Estimating Time Accurately. [Online] Available at: http://www.mindtools.com/pages/article/newPPM_01.htm [Accessed 07/11/13]