Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.
Work Breakdown Structure
Subtitle
WBS Characteristics:
▪ The Work Breakdown Structure is a hierarchy which specifies the list
of tasks involved in a project...
Packages:
▪ The split of the task list into different packages should be logical, and also
compatible with regards to cost...
Lowest Level:
▪ The lowest level of each activity on a WBS should be an individual task
▪ This task should be possible to ...
Limitations to the WBS:
▪ No consideration for the order in which tasks should be carried out, and whether a
task is depen...
Alternatives to WBS:
1. Product Breakdown Structure

2. Cost Breakdown Structure – Completed AFTER the Work
Breakdown Stru...
Product Breakdown Structure:
• This is a tool for dealing with complex
products, such as the motorcycle in the
opposite ex...
Cost Breakdown Structure:

• The CBS can only be
completed after the WBS
and PBS (if any). This is
because, for example, t...
Sources and Further Reading:
▪ Field, M. and Keller, M. (1998), Croatia: Thomson Learning
– Chapter 2.1

▪ Servello, M. an...
Work breakdown Structure
Upcoming SlideShare
Loading in …5
×
Upcoming SlideShare
work breakdown structure
Next
Download to read offline and view in fullscreen.

3

Share

Download to read offline

Work breakdown Structure

Download to read offline

Related Books

Free with a 30 day trial from Scribd

See all

Related Audiobooks

Free with a 30 day trial from Scribd

See all

Work breakdown Structure

  1. 1. Work Breakdown Structure Subtitle
  2. 2. WBS Characteristics: ▪ The Work Breakdown Structure is a hierarchy which specifies the list of tasks involved in a project – down to the finest detail. ▪ The WBS splits the task list up into major ‘packages’ ▪ On the following slide, is the WBS for the project to outsource these Learning Materials.
  3. 3. Packages: ▪ The split of the task list into different packages should be logical, and also compatible with regards to cost control and reporting. ▪ For each Package, it should be possible to test whether the entire package is completed or not. ▪ You will see 5 different packages in the previous example.
  4. 4. Lowest Level: ▪ The lowest level of each activity on a WBS should be an individual task ▪ This task should be possible to complete by an individual, or team, within a reasonable defined period of time. ▪ For example, delegating the task of drawing up action lists could be completed by an individual within a defined period of time, such as one afternoon.
  5. 5. Limitations to the WBS: ▪ No consideration for the order in which tasks should be carried out, and whether a task is dependant on another. ▪ No representation of how long each task might take. ▪ Does not show you who, or what resources are involved in each task.
  6. 6. Alternatives to WBS: 1. Product Breakdown Structure 2. Cost Breakdown Structure – Completed AFTER the Work Breakdown Structure and Product Breakdown Structure
  7. 7. Product Breakdown Structure: • This is a tool for dealing with complex products, such as the motorcycle in the opposite example. • The PBS provides a means for identifying all the components that make up a particular product. • It is worth noting the Project Management methodology PRINCE uses the PBS as an alternative to the WBS.
  8. 8. Cost Breakdown Structure: • The CBS can only be completed after the WBS and PBS (if any). This is because, for example, the costs of labour should be possible to cross reference with the WBS. • This is a tool for identifying each cost category associated with a project
  9. 9. Sources and Further Reading: ▪ Field, M. and Keller, M. (1998), Croatia: Thomson Learning – Chapter 2.1 ▪ Servello, M. and Evans, M. W. (2002) Work Breakdown Structure. Encyclopedia of Software Engineering.
  • oldance

    Jul. 26, 2020
  • NontsikeleloMasilela

    Mar. 22, 2018
  • danhnguyen1406

    Apr. 7, 2015

Views

Total views

4,244

On Slideshare

0

From embeds

0

Number of embeds

3

Actions

Downloads

103

Shares

0

Comments

0

Likes

3

×