SlideShare a Scribd company logo
1 of 23
Download to read offline
NASA PM Challenge 2009




Assessing Schedule Health - STAT!




                   Glen Harrison & Ken Poole
                   NASA/MSFC/CS40 PP&A Team
                   256-544-3385 & 256-544-2419
Agenda

1. Purpose
1. Purpose

2. Background
2. Background

3. Tool Description
3. Tool Description

4. Key Benefits
4. Key Benefits

5. Output Examples
5. Output Examples

6. Demonstration
6. Demonstration
                      1
Purpose


Introduce the NASA developed Schedule
Test and Assessment Tool (STAT)
     Capabilities
     Benefits

Enhance audience awareness of the
importance of determining schedule
credibility



                                        2
Background

           Why Assess Schedules?




Because…
The schedule may not reflect an accurate
and truthful picture (the plan and/or status
may be inaccurate or the scheduling
process may be flawed)
           Ignorance or Deceit?
                                               3
Background (Cont.)
         Why Assess Schedules?
Other Considerations…
1. Schedule may not reflect the total scope of work

2. An inaccurate model of the planned implementation
   provides an incorrect basis for resource planning

3. Schedule may not identify the critical path

4. Schedule may not be integrated
      Internally (task interdependencies)
      Externally (other NASA Centers, contractor schedules,
      international partner or university schedules, etc.)

5. Improves internal schedule development & maintenance
6. Improves/validates Performance Measurement Baseline

7. Heightened interest by DCMA in schedule credibility
                                                              4
Background (Cont.)

                          Identify Needs
                           Identify Needs
Recognized need for improvements to processes/tools for project schedule
           development, assessment, analysis, and reporting.



    Support              Automate
                         Automate             Report
                                              Report               Assess
                                                                   Assess



 Assists Projects in       Increased            Detailed,          Schedule
      Schedule             Efficiency in    Intermediate and     Assessment for
    Development           Manpower and       Executive Level      Internal and
                               Time             Reporting           External
    Improves &                                                     Schedules
    Validates On-
              On-      Quick-Turnaround
                       Quick-               Combination of
   going Schedule         Assessments        Objective and     Objective Metrics to
     Credibility                              Subjective        Quantify Schedule
                       Increased Accuracy     Reporting             Problems
                              in Data


                                                                                      5
Background (Cont.)
                 Objective IMS Credibility Indicators
How Many or What Percentage of …
1. Tasks/milestones with no predecessors?
2. Tasks/milestones with no successors?
3. Tasks with no “finish” successors assigned?
4. Imposed task/milestone constraints (or deadlines) within schedule?
5. Tasks/milestones with missing, inaccurate, or out-of-date status?
6. Summary tasks with interdependencies assigned?
7. Tasks marked as milestones?
8. Task/milestone dates are baselined?
9. Tasks/milestones that have very little Total Slack?
10. Tasks/milestones have Total Slack values that are too high?
11. Tasks with “estimated” durations? (MSP default or placeholder durations)
12. Major milestones have slipped?
13. Monthly baseline completions are missed and by how much?
14. Quantity of SS & FF logic relationships are used?
                Subjective IMS Credibility Indicators
1. Work-off trends (past actuals vs. projected plan)
2. Low “Slack” analysis
3. Task duration profile
                                                                               6
Tool Description

              COM Add-in for Microsoft Project (.NET 2.0)
              Produces Microsoft Excel Charts and Graphs
              Wizard Interface used to automate process

        Schedule Test & Assessment Tool
 Health Check            Trend Analysis                   Reporting


Integrity & Health            Performance                 Assessment
    Indicators               History & Future              Reporting
 • Current Status Date         • Historical completion    •Detailed Reports
 • Remaining Duration             rates                   •Analyst summary
 • Missing Predecessors        • Credibility of planned     report
 • Missing Successors             completion rates        • Mgmt overview
 • Quantity of Constraints     • Indicates work             report
 • Missing Status                “bow-wave”
 • Completion Stats            • Indicates baseline
 • High/Low Float Stats           credibility

                                                                              7
Key Benefits

1. Efficient use of manpower
1. Efficient use of manpower

2. Enhance schedule quality
2. Enhance schedule quality

3. Timely schedule analysis
3. Timely schedule analysis

4. Objective schedule assessment
4. Objective schedule assessment

5. Easy to use and understand
5. Easy to use and understand

6. Prerequisite to risk assessment
6. Prerequisite to risk assessment

                                     8
Output Examples


                  9
Schedule Health Check

CS40 Schedule Health Check
                                                                                                    Overall Project Health Status Indicator
Project Name: Project XYZ IMS 1.19a.mpp                                                               2.1      Y                     1.35        R


Schedule Status                                                                                                                                Check for Improvements
Description                                                                              Current                             Previous                  Change (C-P)
Current Start (Note: earliest activity Early Start Date)                                 4/5/2006                             4/5/2006
Current Finish (Note: latest activity Early Finish Date)                                7/27/2009                             7/5/2009                22         0%
Approximate Remaining Work Days                                                             684                                  668                  16         2%
Is this schedule externally linked to other schedules?                                       N                                    N
Status Date                                                                            10/31/2006                            8/30/2006                63

Task and Milestone Count                    (Note: These counts exclude summary tasks)                        Is the Status Date Current?
Description                                                                      Count          % of Total           Count         % of Total          Change (C-P)
Total Tasks and Milestones                                                       3057                                3021                             36
Completed Tasks and Milestones                                                    501                16%              387                13%         114          4%
To Go Tasks and Milestones                                                       2556                84%             2634                87%         -78         -4%

Logic        (Note: These counts exclude summary and started/completed tasks)
                                                                                  Missing Interdependencies & Number of Constraints
Tasks and Milestones Without Predecessors                                          170               7%        Y       290               11%     R   120         -4%
Tasks and Milestones Without Successors                                            393               15%       R       425               16%     R    32         -1%
Constraints (Note: other than ASAP including deadlines)                            235               9%        G       403               15%     R   168         -6%
Summaries with Logic Ties (see note below)                                           5               0%        G         8               0%      G     3          0%
Tasks and Milestones Needing Updates      Incorrect Status                         105               4%        Y       235               9%      R   130         -5%
Actuals after Status Date                                                           40               2%        Y        52               2%      Y    12          0%
Tasks marked as Milestones (Note: having a duration of > 0)                          0               0%        G         3               0%      Y     3          0%
Note: The summaries with logic ties number is calculated as a percentage of tasks and milestones.


Additional Schedule Information                               Additional Key Indicators
Tasks with No Finish Ties                                                          17                 1%               25                1%
Recurring Tasks                                                                    33                 1%               38                1%
Tasks and Milestones with Estimated Duration                                        1                 0%                0                0%
Schedule traceable to WBS (Y/N)                                                    Y                                    Y
Realistic Critical Path(s) (Y/N)                                                   N                                    N
Schedule Baselined Tasks                                                         2783                91%              2569               85%
Resource Loaded (Y/N)                                                           Partially                               N
Tasks and Milestones with 10 days or less Total Float                             724                28%              1533               58%         -809       -30%
Tasks with Total Float > 25% of remaining duration                                793                31%               910               35%         -117        -4%

                                                                                                                                                                       10
Schedule Health Check (cont’d.)


                          Worksheet tabs provide the
                             detailed findings for
                          assessment and correction




                                              11
Schedule Performance Trend

300

      Project XYZ Schedule Performance & Work-Off Trend Analysis
                      Data Date

250
                                        Historical Trend in Task
                                        Completion Rates Serves as an
                                        Indicator in Determining if
                                        Planned Rates are Credible
200



                                                                        Actual Finish
                                                                        Current Finish
150
                                                                        Baseline Finish
                                                                        Status Date



100




50




  0
Au 04




      09
Au 05




Au 06




Au 07




Au 08
D 04




D 05




D 06




D 07




D 08
O 4




O 5




O 6




O 7




O 8
Ju 5




Ju 7




Ju 9
Ap 5




Ap 6

Ju 6




Ap 7




Ap 8

Ju 8




Ap 9
Fe 4




Fe 5




Fe 6




Fe 7




Fe 8
      0




      0




      0




      0




      0
     0

     0




     0




     0

     0




     0




     0

     0
     0




     0
    -0




    -0




    -0




    -0




    -0
   n-




   n-
   n-




   n-




   n-




   n-
    -




    -
    -




    -




  g-

    -
  g-




  g-




  g-




  g-
  b-

   r-




  b-

   r-




  b-

   r-




  b-

   r-




  b-

   r-
  ct




  ct
  ct




  ct




  ct
 ec




 ec




 ec




 ec




 ec
Ju




                                                                          12
Schedule Assessment Summary Report

                                                Overall Summary Rating
                   Schedule Assessment Summary Report
                   Project XYZ Master Schedule
                   Status As of Oct-06

Automated                  R                       Schedule Assessment Summary Comments                                      Y                 Manual stoplight
stoplight rating                                           1. Too early in project to determine if req'd                                       rating can be
                   Criteria: Avg.of Weighted               work-off rates are too optimistic.                       User defined adjustment
based on           Support Rationale                       2. Incomplete logic network indicates suspect            to the overall rating
                                                                                                                                               applied based on
performance        R is <= 150 (50%),                      schedule dates & critical path.                                                     additional insights
criteria and       Y is 175 - 225 (58% - 75%)              3. Key milestone slips did not reflect                                              and information
                   G is >=250 (83%)                        impact to Launch readiness date.
weighting


                      Schedule Formulation and Integrity
                             Y                           Schedule Formulation and Integrity: (Weighting 50%)

                   Criteria: (Health Matrix)                   Key Schedule Formulation and Integrity Indicators
                   Matches Overall               500
                                                                                    15%
                   Project Schedule Indicator    400
                   Scorecard Value:
                                                 300                                                       9%
                   100                                         7%
                                                 200                2556                                                            4%
 Stoplight rating and data are                   100                    Based on 2556 to go tasks and milestones.

 from current Schedule Health                      0
                                                       Missing Predecessors   Missing Successors   Imposed Constraints     Inaccurate Status
 Check
                                                   Based on 2556 to go tasks and milestones.

                                                                                                                                                         13
Schedule Assessment Summary Report


                               Schedule Performance Trend Data

         R                                 Schedule Performance Trend: (Weighting 25%)

Criteria:Past 6 Months vs                             Schedule Performance & Work Off
                                                        Act            Fcst            BL         Status
          Next 6 Months
                            300
  R is >20%                       6 Mo Avg Compl = 61/mo.                                     6 Mo Avg Planned = 175/mo.
  Y is 11-20%               250
                            6 Mo Avg Compl =6 Mo Avg Planned =
  G is <=10%                                61                                              175
                            200
Scorecard Value:            6 Mo Avg Compl =6 Mo Avg Planned = 175/mo.
25                          150         38139
     Historical Trend in    Project Start Date: Jun-04
                            100
      Task Completion
     Rates Serves as an      50
        Indicator in
       Determining if         0
     Planned Rates are            Apr-06       Jun-06         Aug-06          Oct-06        Dec-06         Feb-07     Apr-07
          Credible          Project Start Date: Jun-04


  Note: Be sure to evaluate whether the numbers provide an accurate analysis
                                                                                                                       14
Schedule Assessment Summary Report

                         Baseline vs. Actual Finishes Analysis

                                              Schedule Baseline vs. Actual Finishes
                                                BL        Act         Fcst        Status        BER
           3500                                                                                                              2

           3000                                                     Current Cum Forecast                                     1.8




                                                                                                                                   Base Exec Rate
                                                                                                                             1.6
                   Baseline Execution Rate
           2500                                                                                                              1.4
Finishes




                                                                                                                             1.2
           2000
                                                                                                                             1
           1500                                                                                 Cum Baseline
                                                                                                                             0.8
           1000                                                                                                              0.6
                                                                                                                             0.4
            500                                                                                                              0.2
                                                                             Cum Actual Completions
              0                                                                                                              0
                  Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun-
                   04   04   04   05   05   05   05   06   06   06   06   07   07   07   07   08   08   08   08   09   09




           BER = Monthly Baseline Plan Completed / Total Monthly Baseline Plan
                                    (Note: BER = DoD “Hit or Miss” Tripwire)


                                                                                                                                   15
Schedule Assessment Summary Report


                   Schedule Milestone Comparison
            R                  Schedule Milestone Comparison: (Weighting 25%)
Criteria:          ID   WBS   DESCRIPTION                                 BASELINE     CURRENT      VARIANCE
  R is >= 20d      26    0    Systems Requirements Review (SRR)            7/11/2006    7/11/2006       0
  Y is 11-19d      27    0    Preliminary Design Review (PDR)               9/8/2006     9/8/2006      0
  G is <=10d       30    0    Critical Design Review (CDR)                 2/20/2007     4/9/2007      35
Scorecard Value:   32    0    System Test Readiness Review (STRR)         10/15/2007   10/15/2007       0
25                 33    0    Space Vehicle I&T Start                      9/18/2007   11/19/2007      45
                   36    0    Space Vehicle I&T Complete (Sell off comp    8/28/2008    8/28/2008      0
                   38    0    Flight Readiness Review (FRR)               10/21/2008   10/22/2008      2
                   39    0    Launch Readiness Review (LRR)               10/27/2008   10/28/2008      2
                   40    0    Launch                                      10/28/2008   10/28/2008      0




                                             Maximum Milestone Limit = 20


   NOTE: Key milestone slips are one indicator of unfavorable schedule
          performance that could impact project completion.


                                                                                                               16
Schedule Assessment Summary Report


                                                        To p 5 Critical Path s
                           40
                                      Indicates constraints
                           30         used inappropriately or
                                      tasks that have not been
                   Tasks


                           20         broken down adequately.

                           10

                            0
                                       -33              -25           -22          -21            -19
                                                          T o tal S lack V alu es
If this % is
greater than                                                                                            If this % is
50% then the                                             Schedule Total Slack Analysis                  greater than
schedule is                         1500
                                                                                                        50% then
typically too                                                                                           tasks are
                                                                        41%
optimistic                                                                                              probably not
                            Tasks




                                    1000                                                    31%         sequenced
and needs                                         28%
re-planning.                                                                                            accurately
                                    500

                                       0
                                             Tasks <= 10d TS           Balance           TS > 25% RD
                                                               Total Slack Categories

         Caution: The above total Slack information is based solely on the project’s IMS
         logic network (i.e.; predecessors, successors, constraints, etc.). Credibility of the
         data correlates directly to the quality reflected in the Schedule Health Check rating.
                                                                                                             17
Schedule Assessment Summary Report

              Logic Relationship Types
                              Logic Relationship Types
                       Based on Total Schedule Tasks & Milestones


                      Logic Relationship Typeslogic should relationships
                                         Network
                                             “Finish to Start”
                                                               be predominately




                                                                           Finish to Start (7606, 89%)

                                                                           Finish to Finish (258, 3%)

                                                                           Start to Start   (328, 4%)


                                                                           Start to Finish (328, 4%)




Total Relationships: 8520                           Total Tasks & Milestones: 3057
 (7606, (258, 3%)          (328, 4%)                           (328, 4%)
 Total Relationships: 8520
# of Relationships with Negative lags:        542       Negative lags should be minimal
 # of Relationships with Negative lags: 542



                                                                                                         18
Schedule Assessment Summary Report

                              Remaining Duration Profile
                                                       Remaining Duration Profile
                                                     Based on To Go Tasks & Milestones



                                             Remaining Duration Profile

                     900                   843
                     800
                                                                              Duration profile data
                                                                              indicates the level of IMS
Tasks & Milestones




                     700
                                                                              detail. Task durations
                     600                                           512        should be discrete and
                     500      449                       433
                                                                              measurable
                     400
                     300
                                                                             173
                     200
                                                                                         79
                     100                                                                            45        22
                      0
                           Milestones   1hr - 2wks   2wks - 1mo   1 - 3mo   3 - 6mo   6mo - 1yr   1 - 2yrs   > 2yrs
           To Go Tasks & Milestones: 2556
           Total Remaining Milestones: 449
                                                                     Durations
           Total Remaining Tasks: 2107
        Total Remainingtasks excluded
           Note: Summary
                           Tasks: 2107                                       To Go Tasks & Milestones: 2556
        Total Remaining Milestones: 449                                      Note: Summary tasks excluded



                                                                                                                      19
Schedule Assessment Summary Report
                              Management Overview Report
                              Project: Project XYZ IMS 1.19a
                              Status As of Oct-06

                                                                                                                                                                        User defined adjustment to the overall rating
                                R             Management Summary Comments                                                                                                        Y

 Management                                    1. Too early in project to determine if required work-off rates are too
                                                    optimistic based on baseline plan vs. actual finishes to date.
                                                2. Incomplete logic network indicates suspect schedule dates and
                                                                                                                                                                        Comments:
                                                                                                                                                                        The Schedule Performance & Work-off
                                                                                                                                                                        Trend should realistically be yellow. Not


Overview Report
                                                critical path identification.                                                                                           enough "actuals" history of sustained
                                                3. Key milestone slips did not reflect impact to Launch readiness date.                                                 task completions to determine if future
                                                                                                                                                                        required rates are too optimistic.



   (page 1)                   Supporting Rationale:


                                Y             Schedule Formulation and Integrity: (Weighting 50%)
                                                                                                                                                          Comments:
                                                      Key Schedule Formulation and Integrity Indicators                                                   Yellow indicator reflects enough weaknesses
                                                                                                                                                          in the logic network to make schedule data
                                500                                                                                                                       suspect. Incomplete task interdependency
                                                                             15%
                                400                                                                                                                       assignments along with invalid use of fixed
                                300                                                                9%                                                     task constraints and missing or incorrect
                                                 7%                                                                                                       task status significantly hinders the ability to
Provides a format for brief     200
                                100
                                                                                                                            4%                            identify the project critical path with a
                                                                                                                                                          reasonable level of confidence. Sound
 analysis explanation for         0
                                       Missing Predecessors       Missing Successors        Imposed Constraints      Inaccurate Status
                                                                                                                                                          "what-if" analysis is also hindered.

  management reporting              Based on 2556 to go tasks and milestones.



                                R             Schedule Performance Trend: (Weighting 25%)
                                                                                                                                                          Comments:
                                                           Schedule Performance & Work Off                                                                While the rating indicator is currently red, it
                                                Act                   Fcst             BL                  Status                                         should be noted that based on baseline vs.
                              300
                                                                                                                                                          actual completions to-date it is too early to
                                      6 Mo Avg Compl = 61/mo.                                             6 Mo Avg Planned = 182/mo.                      determine if the projected task completion
                              250                                                                                                                         rates are realistically achievable. Therefore,
                              200                                                                                                                         it is recommended that the red performance
                              150                                                                                                                         indicator should be considered yellow to
                                                                                                                                                          allow for 2 additional months of accomplish-
                              100                                                                                                                         ment data to be considered in the analysis.
                               50
                                0
                                     Apr-06       Jun-06          Aug-06           Oct-06        Dec-06         Feb-07         Apr-07

                               Project Start Date: Jun-04


                                                 Schedule Baseline vs. Actual Finishes Analysis
                                                                                                                                                          Comments:
                                                      Schedule Baseline vs. Actual Finishes                                                               The overall cum actuals to-date shows tracking
                                                                                                                                                          reasonably well with the baseline plan. However, the
                                                BL              Act            Fcst            Status             BER                                     the monthly baseline execution rates indicate that more
                               3500                                                                                               2                       management focus should placed on completing the right
                                                                                                                                        Base Exec Index

                                                                                                                                  1.8                     tasks.
                               3000                                                                                               1.6
                               2500                                                                                               1.4
                               2000                                                                                               1.2
                                                                                                                                  1
                               1500                                                                                               0.8
                               1000                                                                                               0.6
                                                                                                                                  0.4
                                500                                                                                               0.2
                                  0                                                                                               0
                                Se 04
                                D 04
                                M 04
                                Ju 05
                                Se 05
                                D 05
                                M 05
                                Ju 06
                                Se 06
                                D 06
                                M 06
                                Ju 07
                                Se 07
                                D 07
                                M 07
                                Ju 08
                                Se 08
                                D 08
                                M 08
                                Ju 09
                                    09
                                  p-

                                   -
                                   -


                                  p-

                                   -
                                   -


                                  p-

                                   -
                                   -


                                  p-

                                   -
                                   -


                                  p-

                                   -
                                   -
                                  n-




                                  n-




                                  n-




                                  n-




                                  n-




                                  n-
                                 ar




                                 ar




                                 ar




                                 ar




                                 ar
                                 ec




                                 ec




                                 ec




                                 ec




                                 ec
                                Ju




                                                                                                                                                                                                                        20
Schedule Assessment Summary Report
                    R                Schedule Milestone Comparison: (Weighting 25%)
                    ID                 DESCRIPTION                     BASELINE          CURRENT         VAR   Comments:
                    30       Critical Design Review (CDR)              2/20/2007          4/9/2007        35   Significant project milestones "CDR" & "Space
                    33       Space Vehicle I&T Start                   9/18/2007         11/19/2007       45   Vehicle I&T Start" are each slipping approxi-
                                                                                                               mately 2 months. These slips should realistically
                                                                                                               cause slips to "Launch Readiness Review" (LRR)
                                                                                                               and "Launch" dates, but the schedule does not
                                                                                                               reflect that. This is a further indication of
                                                                                                               significant interdependencies that have been

 Management                                                                                                    ommitted or are incorrect. It is recommended
                                                                                                               that additional review and validation of task
                                                                                                               sequencing be accomplished by responsible
                                                                                                               planning and technical leads.
Overview Report
   (page 2)

                                                      Critical Path Analysis
                                                                                                               Comments:
                                                            Top 5 Critical Paths                               The -33 day critical path which includes 11 tasks
                            50                                                                                 does not appear to be credible. Typically, the
                            40                                                                                 primary critical path will contain a larger number
                                                                                                               of task/milestones than the secondary low float
                    Tasks




                            30
                                                                                                               paths. Secondary low float paths are usually
                            20                                                                                 spur paths which have some type of inter-
                            10                                                                                 dependency to the primary critical path and will
                                                                                                               not contain as many tasks. This is also another
                             0                                                                                 indication that too many date constraints have
                                        -33           -25             -22          -21             -20
                                                                                                               been assigned within the schedule or too many
                                                            Total Slack Values                                 long duration tasks are on the Critical Path.

                                               Schedule Total Slack Analysis
                                                                                                               Comments:
                                                    Schedule Total Slack Analysis                              This metric indicates a high percentage of tasks
                            1500                                                                               with high Total Slack values. This is a further
                                                                       41%                                     indication that logic relationships are potentially
                            1000                                                                               incorrect or missing.
                    Tasks




                                              28%                                            31%

                             500

                                 0
                                         Tasks <= 10d TS             Balance             TS > 25% RD
                                                                   X Values

                  Miscellaneous Comments
                  The schedule should be reviewed and validated by appropriate planning and technical leads, with particular attention being
                  paid to task and milestone sequencing and date constraints.
                                                                                                                                                                     21
Demonstration


                22

More Related Content

What's hot

Noneman.steven
Noneman.stevenNoneman.steven
Noneman.stevenNASAPMC
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey NASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliottNASAPMC
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinalNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Carol.mullenax
Carol.mullenaxCarol.mullenax
Carol.mullenaxNASAPMC
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvinNASAPMC
 
Healy edward
Healy edwardHealy edward
Healy edwardNASAPMC
 
Blythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 finalBlythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 finalNASAPMC
 
Duncan.william
Duncan.williamDuncan.william
Duncan.williamNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Lindley.johnson.pe
Lindley.johnson.peLindley.johnson.pe
Lindley.johnson.peNASAPMC
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jimNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Jim.cassidy
Jim.cassidyJim.cassidy
Jim.cassidyNASAPMC
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyersNASAPMC
 

What's hot (20)

Noneman.steven
Noneman.stevenNoneman.steven
Noneman.steven
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Carol.mullenax
Carol.mullenaxCarol.mullenax
Carol.mullenax
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvin
 
Healy edward
Healy edwardHealy edward
Healy edward
 
Blythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 finalBlythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 final
 
Duncan.william
Duncan.williamDuncan.william
Duncan.william
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Lindley.johnson.pe
Lindley.johnson.peLindley.johnson.pe
Lindley.johnson.pe
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Jim.cassidy
Jim.cassidyJim.cassidy
Jim.cassidy
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
 

Similar to Harrison.g.poole.k

Borchardt.poole.majerowicz
Borchardt.poole.majerowiczBorchardt.poole.majerowicz
Borchardt.poole.majerowiczNASAPMC
 
project time management
 project time management project time management
project time managementHira Atiq
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Sdlc checklist
Sdlc checklistSdlc checklist
Sdlc checklistMwandayi
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinhNASAPMC
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Key Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationKey Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationAlithya
 
Lean Six Sigma Green Belt Services Certification Brochure
Lean Six Sigma Green Belt Services Certification BrochureLean Six Sigma Green Belt Services Certification Brochure
Lean Six Sigma Green Belt Services Certification BrochurePartner
 

Similar to Harrison.g.poole.k (20)

Borchardt.poole.majerowicz
Borchardt.poole.majerowiczBorchardt.poole.majerowicz
Borchardt.poole.majerowicz
 
project time management
 project time management project time management
project time management
 
PMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time managementPMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time management
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Sdlc checklist
Sdlc checklistSdlc checklist
Sdlc checklist
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinh
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Key Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationKey Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning Implementation
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Pmt 06
Pmt 06Pmt 06
Pmt 06
 
Lean six-sigma-project-charter-template
Lean six-sigma-project-charter-templateLean six-sigma-project-charter-template
Lean six-sigma-project-charter-template
 
Lean Six Sigma Green Belt Services Certification Brochure
Lean Six Sigma Green Belt Services Certification BrochureLean Six Sigma Green Belt Services Certification Brochure
Lean Six Sigma Green Belt Services Certification Brochure
 
Plannin gss
Plannin gssPlannin gss
Plannin gss
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Recently uploaded

How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 

Recently uploaded (20)

How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 

Harrison.g.poole.k

  • 1. NASA PM Challenge 2009 Assessing Schedule Health - STAT! Glen Harrison & Ken Poole NASA/MSFC/CS40 PP&A Team 256-544-3385 & 256-544-2419
  • 2. Agenda 1. Purpose 1. Purpose 2. Background 2. Background 3. Tool Description 3. Tool Description 4. Key Benefits 4. Key Benefits 5. Output Examples 5. Output Examples 6. Demonstration 6. Demonstration 1
  • 3. Purpose Introduce the NASA developed Schedule Test and Assessment Tool (STAT) Capabilities Benefits Enhance audience awareness of the importance of determining schedule credibility 2
  • 4. Background Why Assess Schedules? Because… The schedule may not reflect an accurate and truthful picture (the plan and/or status may be inaccurate or the scheduling process may be flawed) Ignorance or Deceit? 3
  • 5. Background (Cont.) Why Assess Schedules? Other Considerations… 1. Schedule may not reflect the total scope of work 2. An inaccurate model of the planned implementation provides an incorrect basis for resource planning 3. Schedule may not identify the critical path 4. Schedule may not be integrated Internally (task interdependencies) Externally (other NASA Centers, contractor schedules, international partner or university schedules, etc.) 5. Improves internal schedule development & maintenance 6. Improves/validates Performance Measurement Baseline 7. Heightened interest by DCMA in schedule credibility 4
  • 6. Background (Cont.) Identify Needs Identify Needs Recognized need for improvements to processes/tools for project schedule development, assessment, analysis, and reporting. Support Automate Automate Report Report Assess Assess Assists Projects in Increased Detailed, Schedule Schedule Efficiency in Intermediate and Assessment for Development Manpower and Executive Level Internal and Time Reporting External Improves & Schedules Validates On- On- Quick-Turnaround Quick- Combination of going Schedule Assessments Objective and Objective Metrics to Credibility Subjective Quantify Schedule Increased Accuracy Reporting Problems in Data 5
  • 7. Background (Cont.) Objective IMS Credibility Indicators How Many or What Percentage of … 1. Tasks/milestones with no predecessors? 2. Tasks/milestones with no successors? 3. Tasks with no “finish” successors assigned? 4. Imposed task/milestone constraints (or deadlines) within schedule? 5. Tasks/milestones with missing, inaccurate, or out-of-date status? 6. Summary tasks with interdependencies assigned? 7. Tasks marked as milestones? 8. Task/milestone dates are baselined? 9. Tasks/milestones that have very little Total Slack? 10. Tasks/milestones have Total Slack values that are too high? 11. Tasks with “estimated” durations? (MSP default or placeholder durations) 12. Major milestones have slipped? 13. Monthly baseline completions are missed and by how much? 14. Quantity of SS & FF logic relationships are used? Subjective IMS Credibility Indicators 1. Work-off trends (past actuals vs. projected plan) 2. Low “Slack” analysis 3. Task duration profile 6
  • 8. Tool Description COM Add-in for Microsoft Project (.NET 2.0) Produces Microsoft Excel Charts and Graphs Wizard Interface used to automate process Schedule Test & Assessment Tool Health Check Trend Analysis Reporting Integrity & Health Performance Assessment Indicators History & Future Reporting • Current Status Date • Historical completion •Detailed Reports • Remaining Duration rates •Analyst summary • Missing Predecessors • Credibility of planned report • Missing Successors completion rates • Mgmt overview • Quantity of Constraints • Indicates work report • Missing Status “bow-wave” • Completion Stats • Indicates baseline • High/Low Float Stats credibility 7
  • 9. Key Benefits 1. Efficient use of manpower 1. Efficient use of manpower 2. Enhance schedule quality 2. Enhance schedule quality 3. Timely schedule analysis 3. Timely schedule analysis 4. Objective schedule assessment 4. Objective schedule assessment 5. Easy to use and understand 5. Easy to use and understand 6. Prerequisite to risk assessment 6. Prerequisite to risk assessment 8
  • 11. Schedule Health Check CS40 Schedule Health Check Overall Project Health Status Indicator Project Name: Project XYZ IMS 1.19a.mpp 2.1 Y 1.35 R Schedule Status Check for Improvements Description Current Previous Change (C-P) Current Start (Note: earliest activity Early Start Date) 4/5/2006 4/5/2006 Current Finish (Note: latest activity Early Finish Date) 7/27/2009 7/5/2009 22 0% Approximate Remaining Work Days 684 668 16 2% Is this schedule externally linked to other schedules? N N Status Date 10/31/2006 8/30/2006 63 Task and Milestone Count (Note: These counts exclude summary tasks) Is the Status Date Current? Description Count % of Total Count % of Total Change (C-P) Total Tasks and Milestones 3057 3021 36 Completed Tasks and Milestones 501 16% 387 13% 114 4% To Go Tasks and Milestones 2556 84% 2634 87% -78 -4% Logic (Note: These counts exclude summary and started/completed tasks) Missing Interdependencies & Number of Constraints Tasks and Milestones Without Predecessors 170 7% Y 290 11% R 120 -4% Tasks and Milestones Without Successors 393 15% R 425 16% R 32 -1% Constraints (Note: other than ASAP including deadlines) 235 9% G 403 15% R 168 -6% Summaries with Logic Ties (see note below) 5 0% G 8 0% G 3 0% Tasks and Milestones Needing Updates Incorrect Status 105 4% Y 235 9% R 130 -5% Actuals after Status Date 40 2% Y 52 2% Y 12 0% Tasks marked as Milestones (Note: having a duration of > 0) 0 0% G 3 0% Y 3 0% Note: The summaries with logic ties number is calculated as a percentage of tasks and milestones. Additional Schedule Information Additional Key Indicators Tasks with No Finish Ties 17 1% 25 1% Recurring Tasks 33 1% 38 1% Tasks and Milestones with Estimated Duration 1 0% 0 0% Schedule traceable to WBS (Y/N) Y Y Realistic Critical Path(s) (Y/N) N N Schedule Baselined Tasks 2783 91% 2569 85% Resource Loaded (Y/N) Partially N Tasks and Milestones with 10 days or less Total Float 724 28% 1533 58% -809 -30% Tasks with Total Float > 25% of remaining duration 793 31% 910 35% -117 -4% 10
  • 12. Schedule Health Check (cont’d.) Worksheet tabs provide the detailed findings for assessment and correction 11
  • 13. Schedule Performance Trend 300 Project XYZ Schedule Performance & Work-Off Trend Analysis Data Date 250 Historical Trend in Task Completion Rates Serves as an Indicator in Determining if Planned Rates are Credible 200 Actual Finish Current Finish 150 Baseline Finish Status Date 100 50 0 Au 04 09 Au 05 Au 06 Au 07 Au 08 D 04 D 05 D 06 D 07 D 08 O 4 O 5 O 6 O 7 O 8 Ju 5 Ju 7 Ju 9 Ap 5 Ap 6 Ju 6 Ap 7 Ap 8 Ju 8 Ap 9 Fe 4 Fe 5 Fe 6 Fe 7 Fe 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -0 -0 -0 -0 -0 n- n- n- n- n- n- - - - - g- - g- g- g- g- b- r- b- r- b- r- b- r- b- r- ct ct ct ct ct ec ec ec ec ec Ju 12
  • 14. Schedule Assessment Summary Report Overall Summary Rating Schedule Assessment Summary Report Project XYZ Master Schedule Status As of Oct-06 Automated R Schedule Assessment Summary Comments Y Manual stoplight stoplight rating 1. Too early in project to determine if req'd rating can be Criteria: Avg.of Weighted work-off rates are too optimistic. User defined adjustment based on Support Rationale 2. Incomplete logic network indicates suspect to the overall rating applied based on performance R is <= 150 (50%), schedule dates & critical path. additional insights criteria and Y is 175 - 225 (58% - 75%) 3. Key milestone slips did not reflect and information G is >=250 (83%) impact to Launch readiness date. weighting Schedule Formulation and Integrity Y Schedule Formulation and Integrity: (Weighting 50%) Criteria: (Health Matrix) Key Schedule Formulation and Integrity Indicators Matches Overall 500 15% Project Schedule Indicator 400 Scorecard Value: 300 9% 100 7% 200 2556 4% Stoplight rating and data are 100 Based on 2556 to go tasks and milestones. from current Schedule Health 0 Missing Predecessors Missing Successors Imposed Constraints Inaccurate Status Check Based on 2556 to go tasks and milestones. 13
  • 15. Schedule Assessment Summary Report Schedule Performance Trend Data R Schedule Performance Trend: (Weighting 25%) Criteria:Past 6 Months vs Schedule Performance & Work Off Act Fcst BL Status Next 6 Months 300 R is >20% 6 Mo Avg Compl = 61/mo. 6 Mo Avg Planned = 175/mo. Y is 11-20% 250 6 Mo Avg Compl =6 Mo Avg Planned = G is <=10% 61 175 200 Scorecard Value: 6 Mo Avg Compl =6 Mo Avg Planned = 175/mo. 25 150 38139 Historical Trend in Project Start Date: Jun-04 100 Task Completion Rates Serves as an 50 Indicator in Determining if 0 Planned Rates are Apr-06 Jun-06 Aug-06 Oct-06 Dec-06 Feb-07 Apr-07 Credible Project Start Date: Jun-04 Note: Be sure to evaluate whether the numbers provide an accurate analysis 14
  • 16. Schedule Assessment Summary Report Baseline vs. Actual Finishes Analysis Schedule Baseline vs. Actual Finishes BL Act Fcst Status BER 3500 2 3000 Current Cum Forecast 1.8 Base Exec Rate 1.6 Baseline Execution Rate 2500 1.4 Finishes 1.2 2000 1 1500 Cum Baseline 0.8 1000 0.6 0.4 500 0.2 Cum Actual Completions 0 0 Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- Sep- Dec- Mar- Jun- 04 04 04 05 05 05 05 06 06 06 06 07 07 07 07 08 08 08 08 09 09 BER = Monthly Baseline Plan Completed / Total Monthly Baseline Plan (Note: BER = DoD “Hit or Miss” Tripwire) 15
  • 17. Schedule Assessment Summary Report Schedule Milestone Comparison R Schedule Milestone Comparison: (Weighting 25%) Criteria: ID WBS DESCRIPTION BASELINE CURRENT VARIANCE R is >= 20d 26 0 Systems Requirements Review (SRR) 7/11/2006 7/11/2006 0 Y is 11-19d 27 0 Preliminary Design Review (PDR) 9/8/2006 9/8/2006 0 G is <=10d 30 0 Critical Design Review (CDR) 2/20/2007 4/9/2007 35 Scorecard Value: 32 0 System Test Readiness Review (STRR) 10/15/2007 10/15/2007 0 25 33 0 Space Vehicle I&T Start 9/18/2007 11/19/2007 45 36 0 Space Vehicle I&T Complete (Sell off comp 8/28/2008 8/28/2008 0 38 0 Flight Readiness Review (FRR) 10/21/2008 10/22/2008 2 39 0 Launch Readiness Review (LRR) 10/27/2008 10/28/2008 2 40 0 Launch 10/28/2008 10/28/2008 0 Maximum Milestone Limit = 20 NOTE: Key milestone slips are one indicator of unfavorable schedule performance that could impact project completion. 16
  • 18. Schedule Assessment Summary Report To p 5 Critical Path s 40 Indicates constraints 30 used inappropriately or tasks that have not been Tasks 20 broken down adequately. 10 0 -33 -25 -22 -21 -19 T o tal S lack V alu es If this % is greater than If this % is 50% then the Schedule Total Slack Analysis greater than schedule is 1500 50% then typically too tasks are 41% optimistic probably not Tasks 1000 31% sequenced and needs 28% re-planning. accurately 500 0 Tasks <= 10d TS Balance TS > 25% RD Total Slack Categories Caution: The above total Slack information is based solely on the project’s IMS logic network (i.e.; predecessors, successors, constraints, etc.). Credibility of the data correlates directly to the quality reflected in the Schedule Health Check rating. 17
  • 19. Schedule Assessment Summary Report Logic Relationship Types Logic Relationship Types Based on Total Schedule Tasks & Milestones Logic Relationship Typeslogic should relationships Network “Finish to Start” be predominately Finish to Start (7606, 89%) Finish to Finish (258, 3%) Start to Start (328, 4%) Start to Finish (328, 4%) Total Relationships: 8520 Total Tasks & Milestones: 3057 (7606, (258, 3%) (328, 4%) (328, 4%) Total Relationships: 8520 # of Relationships with Negative lags: 542 Negative lags should be minimal # of Relationships with Negative lags: 542 18
  • 20. Schedule Assessment Summary Report Remaining Duration Profile Remaining Duration Profile Based on To Go Tasks & Milestones Remaining Duration Profile 900 843 800 Duration profile data indicates the level of IMS Tasks & Milestones 700 detail. Task durations 600 512 should be discrete and 500 449 433 measurable 400 300 173 200 79 100 45 22 0 Milestones 1hr - 2wks 2wks - 1mo 1 - 3mo 3 - 6mo 6mo - 1yr 1 - 2yrs > 2yrs To Go Tasks & Milestones: 2556 Total Remaining Milestones: 449 Durations Total Remaining Tasks: 2107 Total Remainingtasks excluded Note: Summary Tasks: 2107 To Go Tasks & Milestones: 2556 Total Remaining Milestones: 449 Note: Summary tasks excluded 19
  • 21. Schedule Assessment Summary Report Management Overview Report Project: Project XYZ IMS 1.19a Status As of Oct-06 User defined adjustment to the overall rating R Management Summary Comments Y Management 1. Too early in project to determine if required work-off rates are too optimistic based on baseline plan vs. actual finishes to date. 2. Incomplete logic network indicates suspect schedule dates and Comments: The Schedule Performance & Work-off Trend should realistically be yellow. Not Overview Report critical path identification. enough "actuals" history of sustained 3. Key milestone slips did not reflect impact to Launch readiness date. task completions to determine if future required rates are too optimistic. (page 1) Supporting Rationale: Y Schedule Formulation and Integrity: (Weighting 50%) Comments: Key Schedule Formulation and Integrity Indicators Yellow indicator reflects enough weaknesses in the logic network to make schedule data 500 suspect. Incomplete task interdependency 15% 400 assignments along with invalid use of fixed 300 9% task constraints and missing or incorrect 7% task status significantly hinders the ability to Provides a format for brief 200 100 4% identify the project critical path with a reasonable level of confidence. Sound analysis explanation for 0 Missing Predecessors Missing Successors Imposed Constraints Inaccurate Status "what-if" analysis is also hindered. management reporting Based on 2556 to go tasks and milestones. R Schedule Performance Trend: (Weighting 25%) Comments: Schedule Performance & Work Off While the rating indicator is currently red, it Act Fcst BL Status should be noted that based on baseline vs. 300 actual completions to-date it is too early to 6 Mo Avg Compl = 61/mo. 6 Mo Avg Planned = 182/mo. determine if the projected task completion 250 rates are realistically achievable. Therefore, 200 it is recommended that the red performance 150 indicator should be considered yellow to allow for 2 additional months of accomplish- 100 ment data to be considered in the analysis. 50 0 Apr-06 Jun-06 Aug-06 Oct-06 Dec-06 Feb-07 Apr-07 Project Start Date: Jun-04 Schedule Baseline vs. Actual Finishes Analysis Comments: Schedule Baseline vs. Actual Finishes The overall cum actuals to-date shows tracking reasonably well with the baseline plan. However, the BL Act Fcst Status BER the monthly baseline execution rates indicate that more 3500 2 management focus should placed on completing the right Base Exec Index 1.8 tasks. 3000 1.6 2500 1.4 2000 1.2 1 1500 0.8 1000 0.6 0.4 500 0.2 0 0 Se 04 D 04 M 04 Ju 05 Se 05 D 05 M 05 Ju 06 Se 06 D 06 M 06 Ju 07 Se 07 D 07 M 07 Ju 08 Se 08 D 08 M 08 Ju 09 09 p- - - p- - - p- - - p- - - p- - - n- n- n- n- n- n- ar ar ar ar ar ec ec ec ec ec Ju 20
  • 22. Schedule Assessment Summary Report R Schedule Milestone Comparison: (Weighting 25%) ID DESCRIPTION BASELINE CURRENT VAR Comments: 30 Critical Design Review (CDR) 2/20/2007 4/9/2007 35 Significant project milestones "CDR" & "Space 33 Space Vehicle I&T Start 9/18/2007 11/19/2007 45 Vehicle I&T Start" are each slipping approxi- mately 2 months. These slips should realistically cause slips to "Launch Readiness Review" (LRR) and "Launch" dates, but the schedule does not reflect that. This is a further indication of significant interdependencies that have been Management ommitted or are incorrect. It is recommended that additional review and validation of task sequencing be accomplished by responsible planning and technical leads. Overview Report (page 2) Critical Path Analysis Comments: Top 5 Critical Paths The -33 day critical path which includes 11 tasks 50 does not appear to be credible. Typically, the 40 primary critical path will contain a larger number of task/milestones than the secondary low float Tasks 30 paths. Secondary low float paths are usually 20 spur paths which have some type of inter- 10 dependency to the primary critical path and will not contain as many tasks. This is also another 0 indication that too many date constraints have -33 -25 -22 -21 -20 been assigned within the schedule or too many Total Slack Values long duration tasks are on the Critical Path. Schedule Total Slack Analysis Comments: Schedule Total Slack Analysis This metric indicates a high percentage of tasks 1500 with high Total Slack values. This is a further 41% indication that logic relationships are potentially 1000 incorrect or missing. Tasks 28% 31% 500 0 Tasks <= 10d TS Balance TS > 25% RD X Values Miscellaneous Comments The schedule should be reviewed and validated by appropriate planning and technical leads, with particular attention being paid to task and milestone sequencing and date constraints. 21