MURUGESAN VELUSAMY
74. FIRST STREET, DAE TOWNSHIP, KALPAKKAM=603102
Tamil Nadu. INDIA
Mobile no: 8098719798
E-mail: murgi_velu@yahoo.com
murgijessi@gmail.com
Objective
♦ Seeking a challenging position in Construction Engineering & Project Engineering, in industrial &
infrastructure & Building construction firm Executions, Planning & Construction to render the
possessed skills
♦ SKILLS
• Project Management • Civil Construction Site Management • Resource Management • Relationship
Management • Project Planning & Control •Bill of Quantity & Billing & Planning & Contract •
Operations Management • Scheduling • Material Management • Tendering Bill of Quantity &
Contracting - Rate analysis • Team Management.QA/QC Specification & Quality Assurance.
Project Tracking Management.
Experience Summary
• 19 years’ experience in civil constructions in Railway Track laying, Construction of major bridges,
Industrial Pre-engineered steel structures, Railway station buildings & Roads, bridges , laying of
under water drainage works ,laying Highway Roads(Bahrain Roads Directorate)&Construction
Residential Buildings, Villas(Annai velu Pvt Co) .
• My core expertise centres on Construction like Industrial, Infrastructure, Building construction
• Execution with Quality Assurance and Quality Control, Planning, Project Monitoring and Progress
Review. Contractor billing and Rate Analysis of Quantity according to actual job and approved
rate or market rate. Rate Analysis according PWD and CPWD Rate and MES Rate schedule rate.
• I have execution knowledge across heavy Industrial Rcc work, heavy infrastructure
construction
• Precast erections Slab, I Girder, Box Girder, Pier Cap, U Girder and its fixing. Formwork &
scaffolding work for diaphragm beam, Pier, Earth work for pile cap utility etc.
Personal Details
• Date of Birth - 02nd
April 1966
• Sex - Male
• Marital Status - Married
• Nationality - Indian
• Passport -
Academic
♦ Trained in Staad pro v8i
♦ Master of Technology (M.Tech in Structural Engg) from IIT Madras in 2000
Bachelor of Engineering (B.E.) in Civil from Madurai Kamaraj University Madurai in 1983-87
♦ Higher Secondary Examination from TN H.S.E. with 73% in 1983.
♦ Secondary Examination from TN S.S.L.C. with 69% in 1981.
Page 1 of 6
Technical Skills
• Pilling work- Bored pile (up to 1200mm diameter) under major bridges in Gauge Conversion works for railway
Track. Pile testing, pile concreting.
 RCC Mass Concreting- Abutment, Pile cap, piling work for railway bridges.
RCC raft foundation, well foundation etc. piers pile cap work, bow string arch bridges in gauge conversion
rail work.
 I Girder, box girder, composite girder for super structure for railway bridges.
 RCC Frame Structure- Residential & commercial building, Pump house, Compressor House, bridge
piers and piles caps work in railway track and Rail station Buildings,
 Planning & Billing –Contract or billing ,Rate analysis, Bill of quantity, Quantity Survey, Tendering
Document, Specification analysis rate schedule analysis for back to back contracting, according, rate
schedule SR .
 Geotechnical Investigation- NDT, SAND REPLACEMENT TEST PLATE LOAD TEST.all test related Rcc and soil.
 Site Management- Design of temporary structure & false work (Staging & Scaffolding), Barricading, Road sign
board fixing.
Career Profile
Organisation Period Designation
Annai Velu Builders, Madurai. 2014(Mar) – Till Date Project Manager
Southern Railway (Govt of India) 2010(Apr)-2013(Dec) Senior Section Engineer
Habib Ali Awachi Ltd, Bahrain 2008(Feb) -2009(Dec) Project Engineer
Southern Railway (Govt of India) 1993(June)-2007(Dec) Section Engineer
Project Title 1 Construction of residential buildings and villas at Madurai (Annai Velu Builders
Pvt Ltd.)
Client Indivuvals
Company Annai Velu Pvt.Ltd.
Responsibilities • Coordination among Owner, Client, Consultant for acquiring land(Execution Section)
• Continuous progress review (Weekly) to forecast the upcoming activities, resources
requirement (like man power, plant involvement, machineries requirement etc.)
• Preparing layout plan and required house plan and structural drawings.
• monitoring labour and supervisor output and quality and quantity control
• Inspection for activities (survey, pre & post concrete supervision) with a team of junior
engineers.
Page 2 of 6
Planning Execution activity with regular construction methods.
Recourse planning ,Work management planning for achieving monthly
target
• Work schedule preparations for achieving weekly targets
Duration March2014 – PRESENT
Role Project Manager
Project Title 2 Gauge Conversion works of MG to BG from Chennai Beach to Tambaram
Client Govt of India
Company SOUTHERN RAILWAY
Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section)
• Continuous progress review (Monthly) to forecast the upcoming activities, resources
requirement (like release of GAD drawings, man power, plant involvement, machineries
requirement etc.)
• Analysis to find out lag and lead time for different activities to achieve different
milestones and identification of parallel activities to minimize the lag.
• Civil QA & OC at site
• Designing and review of different temporary, Building slab, and plate load test.
• Inspection for activities (survey, pre & post concrete supervision) with a team of junior
engineers.
Functional Area • MINOR/MAJOR BRIDGE FOUNDATION /piling work/PILE CAP
RCC/COLUMN RCC WORK- Supervision at pile cap work and column piers work
and piers cap work work rcc work M35 TO M45 utility verification, survey site
investigation, shifting
• Rcc raft- Supervision at & its Pcc Rcc box minor bridge cast in situ
RENFORCEMENT- BBS guiding & planning the reinforcement fixing
Approved GAD of Minor bridge, RUB,. Road diversion plan its approval,
Ground improvement for minor bridge and major bridge, with soil test.
• Formwork & executions planning- for minor bridge
• Collect drawing, making contractor bills, equipment planning etc .
• QA&QC- plate load test, sand replacement test slump test SPT test, Plate
load test for ground.
• Material requirement and labour planning
• Work schedule preparations
• Utility survey shifting soil & site investigation survey, alignment
checking etc.
Duration April 2010 – Dec 2013
Role Senior Section Engineer
Page 3 of 6
Project Title 3 Laying of avenue highway roads, providing storm water drainage works at Galali
and Improve ments to Highway Road between Bustain And Bahrain Airport.
Client Roads Directorate , Kingdom Of Bahrain
Company HABIB ALI AWACHI WLL, Bahrain.
Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section)
• Continuous progress review (Weekly) to forecast the upcoming activities, resources
requirement (like release of approved drawings, man power, plant involvement,
machineries requirement etc.)
• Civil QA & OC at site
• Inspection for activities (survey, pre & post concrete supervision) with a team of senior
foremen and land surveyors
Functional Area • Excavation work/laying protection PCC/laying of UPVC pipes for storm
water drainage.
STORM WATER DRAINAGE- Pipe laying ,Connecting Road gullies at road
ends
• Removing existing Road surface
• Laying road base for sub grade surface etc.
• QA&QC- sub grade load test coordinating with directorate etc.
• Work management planning according to directorate norms.
• Preparation of bill according to BOQ and codes.
• Preparing monthly programme using MS PROJECT
Duration Feb,2008 – Dec 2009
Role Project Engineer
Project Title 4 Gauge Conversion works of MG to BG from Villupuram to Pondicherry
Client Govt of India
Company SOUTHERN RAILWAY
Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section)
• Continuous progress review (Weekly) to forecast the upcoming activities, resources
requirement (like release of GAD drawings, man power, plant involvement, machineries
requirement etc.)
• Analysis to find out lag and lead time for different activities to achieve different
milestones and identification of parallel activities to minimize the lag.
• Civil QA & OC at site
• Designing and review of different temporary, Building slab, and plate load test.
• Inspection for activities (survey, pre & post concrete supervision) with a team of junior
engineers.
Page 4 of 6
Functional Area • PILE CAP RCC/COLUMN RCC WORK- Supervision at pile cap work and
PIERSCAP AND PIER and Portal structure AND STATION WORK OF
RAIL work rcc work M35 TO M60
• Rcc raft- Supervision at & its Pcc like pile cap & pile,
RENFORCEMENT- Planning the reinforcement fixing of pier And pier cap
• Formwork & executions planning- for pile cap, pier, pier cap Pranav
shutter.
• Collect drawing, making contractor bills, equipment planning etc .
• QA&QC- plate load test, sand replacement test slump test making work
method
• Work management planning for concreting according city traffic
• Work schedule preparations according site condition.
Duration Mar,2003 – Dec2007
Role Section engineer
Project Title 5 Doubling of track works from Chengal pet to Tindivanam
Client Govt of India
Company SOUTHERN RAILWAY
Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section)
• Continuous progress review (Weekly) to forecast the upcoming activities, resources
requirement (like release of GAD drawings, man power, plant involvement, machineries
requirement etc.)
• Time frame analysis to find out lag and lead time for different activities to achieve
different milestones and identification of parallel activities to minimize the lag.
• Civil QA & OC at site
• Designing and review of different temporary, Building slab, and plate load test.
• Inspection for activities (survey, pre & post concrete supervision) with a team of junior
engineers.
Functional Area • Main embankment- Supervision development earth cutting filling gravel filling wbm
filling etc
• Formwork & execution’s planning & Precast Erection like I Girder and slab
for ship lift platform over the sea and its concreting diaphragm wall etc.
• Collect drawing, making contractor bills, equipment planning etc .
• QA&QC- plate load test, sand replacement test slump test etc.
• Work management planning for precast erection of Girder and slab for
pier lift.
• Work schedule preparations For Concreting of pier lift foundation.in
Duration Mar,1999 – Feb 2003
Role Section Engineer
Page 5 of 6
Project Title 6 Additional line works of MG to BG from Chennai Egmore to Tambaram
Client
Govt of India
Company
SOUTHERN RAILWAY
Responsibilities • Coordination among Contractor, Client, Consultant (Design Section)
• Continuous progress review (Weekly) to forecast the upcoming activities, resources
requirement (like release of GAD drawings, man power, plant involvement, machineries
requirement etc.)
• Time frame analysis to find out lag and lead time for different activities to achieve
different milestones and identification of parallel activities to minimize the lag.
• Civil QA & OC at site
• Designing and review of different temporary structure , Building slab, Inspection for
activities (survey, pre & post concrete supervision) with a team of junior engineers.
Functional Area • EARH WORK- Sand cutting filling at 300mm layer for embankment and compaction
• Temporary structure- Supervision at initial setting structure like cabin, office building,
Batching plant structure.
• Precast erections- Supervision at 3km precast boundary wall within 60 days
• Hanging scaffolding Supervision of all terminal hanging scaffold activities.
Gradation of CA & FA, Compressive strength, Setting time & Consistency of cement,
Compressive strength of Concrete, Compaction testing of Soil, NDT witness, QC
documentation etc.
• Reconciliations- Progress review, monitoring making bills , meeting with client
Duration May1996 – Mar,1999
Role Section Engineer
Project Title 7 Gauge Conversion works of MG to BG from Bangalore to Hubli
Client
Govt of India
Company
SOUTHERN RAILWAY
Responsibilities • Coordination with Client , Contractor and Design consultant
• Follow and Implementation of International Safety Norms
• Preparation and modification of as built drawings
• Inspection of activities (Survey, Pre & Post concreting supervision)
Functional Area • Earth work embankment planning- work planning according schedule
• Making arrangement planning- Site supervision with progress review, resource
planning for different activity of construction raft, pile foundation, client
checking
• Execution management at site level as Form work,Rcc ,for Industrial construction
insert palate,staging,raft foundation, alignment for major bridge align ment
Duration June 1993- May, 1996
Role Section Engineer
Soft Skill
♦ Operating Platform- Windows 98,2000, NT, Vista window 7
♦ Packages- MS Office, Working knowledge, internet uses. Excel MS Project,
Present Packages
♦ Rs.5.0 lac per annum with accommodation, Conveyance, Health Insurances
♦ Notice period- 10- days for joining
Expected Packages
♦ Negotiable. No Family accommodation is required, Conveyance, Health Insurances & Group Linked Medical claim
Scheme and other facilities as per company rules.
Page 6 of 6
Signature:
Date:
Page 7 of 6

More Related Content

What's hot (20)

Kpr resume tunnel engineer
Kpr resume tunnel engineerKpr resume tunnel engineer
Kpr resume tunnel engineer
 
paramasivam resume
paramasivam resume paramasivam resume
paramasivam resume
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
 
Asstt Bridge Engineer - Bhupinder Singh
Asstt Bridge Engineer - Bhupinder SinghAsstt Bridge Engineer - Bhupinder Singh
Asstt Bridge Engineer - Bhupinder Singh
 
Ravi Resume
Ravi ResumeRavi Resume
Ravi Resume
 
S MUKHERJEE RESUME MARCH 3
S MUKHERJEE RESUME MARCH 3S MUKHERJEE RESUME MARCH 3
S MUKHERJEE RESUME MARCH 3
 
Resume
ResumeResume
Resume
 
M.s. resume 290817
M.s. resume 290817M.s. resume 290817
M.s. resume 290817
 
New (Civ) Ehsan
New (Civ) EhsanNew (Civ) Ehsan
New (Civ) Ehsan
 
Anant Gupta CV
Anant Gupta CVAnant Gupta CV
Anant Gupta CV
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
 
AVS Krishna Resume
AVS Krishna ResumeAVS Krishna Resume
AVS Krishna Resume
 
Resume (2)
Resume (2)Resume (2)
Resume (2)
 
Sankar CV
Sankar CVSankar CV
Sankar CV
 
Resume - G. Murali Reddy
Resume - G. Murali ReddyResume - G. Murali Reddy
Resume - G. Murali Reddy
 
SMUKHERJEE RESUME current
SMUKHERJEE RESUME currentSMUKHERJEE RESUME current
SMUKHERJEE RESUME current
 
GNS-Resume
GNS-ResumeGNS-Resume
GNS-Resume
 
SYED MUHAMMED ANWAR
SYED MUHAMMED ANWARSYED MUHAMMED ANWAR
SYED MUHAMMED ANWAR
 
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXPS S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
S S N PRASAD AKSHINTALA - CIVIL ME +4 YEARS EXP
 
Resume 2015
Resume 2015Resume 2015
Resume 2015
 

Viewers also liked

수원오피/공덕오피/영통오피/부평오피/서산오피
수원오피/공덕오피/영통오피/부평오피/서산오피수원오피/공덕오피/영통오피/부평오피/서산오피
수원오피/공덕오피/영통오피/부평오피/서산오피bjavjxtj3
 
Scenariusz "Pomóżmy ptakom przetrwać zimę!"
Scenariusz "Pomóżmy ptakom przetrwać zimę!"Scenariusz "Pomóżmy ptakom przetrwać zimę!"
Scenariusz "Pomóżmy ptakom przetrwać zimę!"Dominika T
 
Speech- Social Media
Speech- Social MediaSpeech- Social Media
Speech- Social MediaMichelle Via
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATRommel Siasat
 

Viewers also liked (9)

수원오피/공덕오피/영통오피/부평오피/서산오피
수원오피/공덕오피/영통오피/부평오피/서산오피수원오피/공덕오피/영통오피/부평오피/서산오피
수원오피/공덕오피/영통오피/부평오피/서산오피
 
Pro-Bono Initiative of the Year
Pro-Bono Initiative of the YearPro-Bono Initiative of the Year
Pro-Bono Initiative of the Year
 
Windows, Linux, y MAC
Windows, Linux, y MACWindows, Linux, y MAC
Windows, Linux, y MAC
 
Scenariusz "Pomóżmy ptakom przetrwać zimę!"
Scenariusz "Pomóżmy ptakom przetrwać zimę!"Scenariusz "Pomóżmy ptakom przetrwać zimę!"
Scenariusz "Pomóżmy ptakom przetrwać zimę!"
 
Domain Skills
Domain SkillsDomain Skills
Domain Skills
 
Speech- Social Media
Speech- Social MediaSpeech- Social Media
Speech- Social Media
 
Бер
БерБер
Бер
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
 
Pesos da UFPE para Sisu 2015
Pesos da UFPE para Sisu 2015Pesos da UFPE para Sisu 2015
Pesos da UFPE para Sisu 2015
 

Similar to resume frfcf murgi

Muthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMuthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMUTHUKUMAR428109
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)Sachin Chitnis
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)Sachin Chitnis
 
CV of engr. Ghulam Azhar with 14 years exp (1)
CV of engr. Ghulam Azhar with 14 years exp (1)CV of engr. Ghulam Azhar with 14 years exp (1)
CV of engr. Ghulam Azhar with 14 years exp (1)ghulam azhar kandhir
 
T.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsT.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsSHAJI GEORGE
 
Curriculum Vitae (Muzzafar)
Curriculum Vitae (Muzzafar)Curriculum Vitae (Muzzafar)
Curriculum Vitae (Muzzafar)Muzaffar Sajjad
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 

Similar to resume frfcf murgi (20)

My Fresh Cv.pdf
My Fresh Cv.pdfMy Fresh Cv.pdf
My Fresh Cv.pdf
 
Sharma cv
Sharma  cv Sharma  cv
Sharma cv
 
Muthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMuthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdf
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
Rajbir Singh-2
Rajbir Singh-2Rajbir Singh-2
Rajbir Singh-2
 
CV of engr. Ghulam Azhar with 14 years exp (1)
CV of engr. Ghulam Azhar with 14 years exp (1)CV of engr. Ghulam Azhar with 14 years exp (1)
CV of engr. Ghulam Azhar with 14 years exp (1)
 
Civil Engineer
Civil EngineerCivil Engineer
Civil Engineer
 
Civil Engineer
Civil EngineerCivil Engineer
Civil Engineer
 
659193
659193659193
659193
 
T.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsT.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy ts
 
CV M.Ilyas - 1
CV M.Ilyas - 1CV M.Ilyas - 1
CV M.Ilyas - 1
 
Curriculum Vitae (Muzzafar)
Curriculum Vitae (Muzzafar)Curriculum Vitae (Muzzafar)
Curriculum Vitae (Muzzafar)
 
shishir_cv
shishir_cvshishir_cv
shishir_cv
 
Abhishek Resume
Abhishek ResumeAbhishek Resume
Abhishek Resume
 
PIPING SUPERVISOR RESUME
PIPING SUPERVISOR RESUME  PIPING SUPERVISOR RESUME
PIPING SUPERVISOR RESUME
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
Naresh Resume
Naresh Resume Naresh Resume
Naresh Resume
 
Resume pritam
Resume  pritamResume  pritam
Resume pritam
 
Mudasar Resume-
Mudasar Resume-Mudasar Resume-
Mudasar Resume-
 

resume frfcf murgi

  • 1. MURUGESAN VELUSAMY 74. FIRST STREET, DAE TOWNSHIP, KALPAKKAM=603102 Tamil Nadu. INDIA Mobile no: 8098719798 E-mail: murgi_velu@yahoo.com murgijessi@gmail.com Objective ♦ Seeking a challenging position in Construction Engineering & Project Engineering, in industrial & infrastructure & Building construction firm Executions, Planning & Construction to render the possessed skills ♦ SKILLS • Project Management • Civil Construction Site Management • Resource Management • Relationship Management • Project Planning & Control •Bill of Quantity & Billing & Planning & Contract • Operations Management • Scheduling • Material Management • Tendering Bill of Quantity & Contracting - Rate analysis • Team Management.QA/QC Specification & Quality Assurance. Project Tracking Management. Experience Summary • 19 years’ experience in civil constructions in Railway Track laying, Construction of major bridges, Industrial Pre-engineered steel structures, Railway station buildings & Roads, bridges , laying of under water drainage works ,laying Highway Roads(Bahrain Roads Directorate)&Construction Residential Buildings, Villas(Annai velu Pvt Co) . • My core expertise centres on Construction like Industrial, Infrastructure, Building construction • Execution with Quality Assurance and Quality Control, Planning, Project Monitoring and Progress Review. Contractor billing and Rate Analysis of Quantity according to actual job and approved rate or market rate. Rate Analysis according PWD and CPWD Rate and MES Rate schedule rate. • I have execution knowledge across heavy Industrial Rcc work, heavy infrastructure construction • Precast erections Slab, I Girder, Box Girder, Pier Cap, U Girder and its fixing. Formwork & scaffolding work for diaphragm beam, Pier, Earth work for pile cap utility etc. Personal Details • Date of Birth - 02nd April 1966 • Sex - Male • Marital Status - Married • Nationality - Indian • Passport - Academic ♦ Trained in Staad pro v8i ♦ Master of Technology (M.Tech in Structural Engg) from IIT Madras in 2000 Bachelor of Engineering (B.E.) in Civil from Madurai Kamaraj University Madurai in 1983-87 ♦ Higher Secondary Examination from TN H.S.E. with 73% in 1983. ♦ Secondary Examination from TN S.S.L.C. with 69% in 1981. Page 1 of 6
  • 2. Technical Skills • Pilling work- Bored pile (up to 1200mm diameter) under major bridges in Gauge Conversion works for railway Track. Pile testing, pile concreting.  RCC Mass Concreting- Abutment, Pile cap, piling work for railway bridges. RCC raft foundation, well foundation etc. piers pile cap work, bow string arch bridges in gauge conversion rail work.  I Girder, box girder, composite girder for super structure for railway bridges.  RCC Frame Structure- Residential & commercial building, Pump house, Compressor House, bridge piers and piles caps work in railway track and Rail station Buildings,  Planning & Billing –Contract or billing ,Rate analysis, Bill of quantity, Quantity Survey, Tendering Document, Specification analysis rate schedule analysis for back to back contracting, according, rate schedule SR .  Geotechnical Investigation- NDT, SAND REPLACEMENT TEST PLATE LOAD TEST.all test related Rcc and soil.  Site Management- Design of temporary structure & false work (Staging & Scaffolding), Barricading, Road sign board fixing. Career Profile Organisation Period Designation Annai Velu Builders, Madurai. 2014(Mar) – Till Date Project Manager Southern Railway (Govt of India) 2010(Apr)-2013(Dec) Senior Section Engineer Habib Ali Awachi Ltd, Bahrain 2008(Feb) -2009(Dec) Project Engineer Southern Railway (Govt of India) 1993(June)-2007(Dec) Section Engineer Project Title 1 Construction of residential buildings and villas at Madurai (Annai Velu Builders Pvt Ltd.) Client Indivuvals Company Annai Velu Pvt.Ltd. Responsibilities • Coordination among Owner, Client, Consultant for acquiring land(Execution Section) • Continuous progress review (Weekly) to forecast the upcoming activities, resources requirement (like man power, plant involvement, machineries requirement etc.) • Preparing layout plan and required house plan and structural drawings. • monitoring labour and supervisor output and quality and quantity control • Inspection for activities (survey, pre & post concrete supervision) with a team of junior engineers. Page 2 of 6
  • 3. Planning Execution activity with regular construction methods. Recourse planning ,Work management planning for achieving monthly target • Work schedule preparations for achieving weekly targets Duration March2014 – PRESENT Role Project Manager Project Title 2 Gauge Conversion works of MG to BG from Chennai Beach to Tambaram Client Govt of India Company SOUTHERN RAILWAY Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section) • Continuous progress review (Monthly) to forecast the upcoming activities, resources requirement (like release of GAD drawings, man power, plant involvement, machineries requirement etc.) • Analysis to find out lag and lead time for different activities to achieve different milestones and identification of parallel activities to minimize the lag. • Civil QA & OC at site • Designing and review of different temporary, Building slab, and plate load test. • Inspection for activities (survey, pre & post concrete supervision) with a team of junior engineers. Functional Area • MINOR/MAJOR BRIDGE FOUNDATION /piling work/PILE CAP RCC/COLUMN RCC WORK- Supervision at pile cap work and column piers work and piers cap work work rcc work M35 TO M45 utility verification, survey site investigation, shifting • Rcc raft- Supervision at & its Pcc Rcc box minor bridge cast in situ RENFORCEMENT- BBS guiding & planning the reinforcement fixing Approved GAD of Minor bridge, RUB,. Road diversion plan its approval, Ground improvement for minor bridge and major bridge, with soil test. • Formwork & executions planning- for minor bridge • Collect drawing, making contractor bills, equipment planning etc . • QA&QC- plate load test, sand replacement test slump test SPT test, Plate load test for ground. • Material requirement and labour planning • Work schedule preparations • Utility survey shifting soil & site investigation survey, alignment checking etc. Duration April 2010 – Dec 2013 Role Senior Section Engineer Page 3 of 6
  • 4. Project Title 3 Laying of avenue highway roads, providing storm water drainage works at Galali and Improve ments to Highway Road between Bustain And Bahrain Airport. Client Roads Directorate , Kingdom Of Bahrain Company HABIB ALI AWACHI WLL, Bahrain. Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section) • Continuous progress review (Weekly) to forecast the upcoming activities, resources requirement (like release of approved drawings, man power, plant involvement, machineries requirement etc.) • Civil QA & OC at site • Inspection for activities (survey, pre & post concrete supervision) with a team of senior foremen and land surveyors Functional Area • Excavation work/laying protection PCC/laying of UPVC pipes for storm water drainage. STORM WATER DRAINAGE- Pipe laying ,Connecting Road gullies at road ends • Removing existing Road surface • Laying road base for sub grade surface etc. • QA&QC- sub grade load test coordinating with directorate etc. • Work management planning according to directorate norms. • Preparation of bill according to BOQ and codes. • Preparing monthly programme using MS PROJECT Duration Feb,2008 – Dec 2009 Role Project Engineer Project Title 4 Gauge Conversion works of MG to BG from Villupuram to Pondicherry Client Govt of India Company SOUTHERN RAILWAY Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section) • Continuous progress review (Weekly) to forecast the upcoming activities, resources requirement (like release of GAD drawings, man power, plant involvement, machineries requirement etc.) • Analysis to find out lag and lead time for different activities to achieve different milestones and identification of parallel activities to minimize the lag. • Civil QA & OC at site • Designing and review of different temporary, Building slab, and plate load test. • Inspection for activities (survey, pre & post concrete supervision) with a team of junior engineers. Page 4 of 6
  • 5. Functional Area • PILE CAP RCC/COLUMN RCC WORK- Supervision at pile cap work and PIERSCAP AND PIER and Portal structure AND STATION WORK OF RAIL work rcc work M35 TO M60 • Rcc raft- Supervision at & its Pcc like pile cap & pile, RENFORCEMENT- Planning the reinforcement fixing of pier And pier cap • Formwork & executions planning- for pile cap, pier, pier cap Pranav shutter. • Collect drawing, making contractor bills, equipment planning etc . • QA&QC- plate load test, sand replacement test slump test making work method • Work management planning for concreting according city traffic • Work schedule preparations according site condition. Duration Mar,2003 – Dec2007 Role Section engineer Project Title 5 Doubling of track works from Chengal pet to Tindivanam Client Govt of India Company SOUTHERN RAILWAY Responsibilities • Coordination among Contractor, Client, Consultant (Execution Section) • Continuous progress review (Weekly) to forecast the upcoming activities, resources requirement (like release of GAD drawings, man power, plant involvement, machineries requirement etc.) • Time frame analysis to find out lag and lead time for different activities to achieve different milestones and identification of parallel activities to minimize the lag. • Civil QA & OC at site • Designing and review of different temporary, Building slab, and plate load test. • Inspection for activities (survey, pre & post concrete supervision) with a team of junior engineers. Functional Area • Main embankment- Supervision development earth cutting filling gravel filling wbm filling etc • Formwork & execution’s planning & Precast Erection like I Girder and slab for ship lift platform over the sea and its concreting diaphragm wall etc. • Collect drawing, making contractor bills, equipment planning etc . • QA&QC- plate load test, sand replacement test slump test etc. • Work management planning for precast erection of Girder and slab for pier lift. • Work schedule preparations For Concreting of pier lift foundation.in Duration Mar,1999 – Feb 2003 Role Section Engineer Page 5 of 6
  • 6. Project Title 6 Additional line works of MG to BG from Chennai Egmore to Tambaram Client Govt of India Company SOUTHERN RAILWAY Responsibilities • Coordination among Contractor, Client, Consultant (Design Section) • Continuous progress review (Weekly) to forecast the upcoming activities, resources requirement (like release of GAD drawings, man power, plant involvement, machineries requirement etc.) • Time frame analysis to find out lag and lead time for different activities to achieve different milestones and identification of parallel activities to minimize the lag. • Civil QA & OC at site • Designing and review of different temporary structure , Building slab, Inspection for activities (survey, pre & post concrete supervision) with a team of junior engineers. Functional Area • EARH WORK- Sand cutting filling at 300mm layer for embankment and compaction • Temporary structure- Supervision at initial setting structure like cabin, office building, Batching plant structure. • Precast erections- Supervision at 3km precast boundary wall within 60 days • Hanging scaffolding Supervision of all terminal hanging scaffold activities. Gradation of CA & FA, Compressive strength, Setting time & Consistency of cement, Compressive strength of Concrete, Compaction testing of Soil, NDT witness, QC documentation etc. • Reconciliations- Progress review, monitoring making bills , meeting with client Duration May1996 – Mar,1999 Role Section Engineer Project Title 7 Gauge Conversion works of MG to BG from Bangalore to Hubli Client Govt of India Company SOUTHERN RAILWAY Responsibilities • Coordination with Client , Contractor and Design consultant • Follow and Implementation of International Safety Norms • Preparation and modification of as built drawings • Inspection of activities (Survey, Pre & Post concreting supervision) Functional Area • Earth work embankment planning- work planning according schedule • Making arrangement planning- Site supervision with progress review, resource planning for different activity of construction raft, pile foundation, client checking • Execution management at site level as Form work,Rcc ,for Industrial construction insert palate,staging,raft foundation, alignment for major bridge align ment Duration June 1993- May, 1996 Role Section Engineer Soft Skill ♦ Operating Platform- Windows 98,2000, NT, Vista window 7 ♦ Packages- MS Office, Working knowledge, internet uses. Excel MS Project, Present Packages ♦ Rs.5.0 lac per annum with accommodation, Conveyance, Health Insurances ♦ Notice period- 10- days for joining Expected Packages ♦ Negotiable. No Family accommodation is required, Conveyance, Health Insurances & Group Linked Medical claim Scheme and other facilities as per company rules. Page 6 of 6