SlideShare a Scribd company logo
1 of 10
Download to read offline
CLOSING MEETING
OFFSHORE PROJECT QUALITY AUDIT AT (WP22)
BONGKOT FIELD DEVELOPMENT PROJECT
BONGKOT WELLHEAD BOOSTER COMPRESSOR
PHASE IV (WP2, WP15, WP16, WP22)
SUMMARY AUDIT
NO NON -COMPLIANCE CAR OBSERVATION TARGET
1 Finding that STR WPS Procedure is old revision for
THAI-BC4-GEN-09-11-4001 Rev. 17B at Quality
Board, but latest revision is 21C which not
according with MDDR Rev.28B
- To be rechecked and
replaced the latest revision
on board for this
procedure.
3 Days
2 The Quality board don’t have posted related WPS
of Excavation for STR & Piping work at deck.
- To be provided the WPS of
Excavation of STR and
Piping at Quality Board.
Today
3 Drawing doesn’t identified the weld joint at
offshore site, as refer to drawing no# BC4-WP22-
- Immediately communicate
with responsible persons
1 Week
offshore site, as refer to drawing no# BC4-WP22-
ST-WM-0002-01-2 Rev.13
with responsible persons
for solving on this matter.
4 Painting material has been issued certificated on
Feb, 2014, which it can’t using to work because
not according with project procedure no# THAI-
BC4-GEN-09-01-1024 Rev16C
- Immediately discussion
with related persons for
solving on this matter.
1 Week
5 Finding that calibration tag of Pressure gauge
have been swopped from Range 300 Psi to Range
10000 Psi, which it is not according with Pressure
gauge certificate.
- To be ensured and check
to all pressure gauges and
must be complied with
certificate before using to
work.
3 Days
SUMMARY AUDIT
NO NON COMPLIANCE CAR OBSERVATION TARGET
6 Finding that QA/QC organization chart (offshore) doesn't
have Khun Preecha Jumnongrit for work related PT &
MT, RT methods Level II under BC4 Project, which this
procedure still not update and approval by client as refer
to THAI-BC4-GEN-09-11-4002 Rev.24C
- Immediately submit
the QA/QC
organization chart
(offshore) to client for
review and approval
to according with
Procedure.
1 Week
OBSERVATION NO# 1
See the Excel file as shownSee the Excel file as shown
OBSERVATION NO# 2
OBSERVATION NO# 3
OBSERVATION NO# 4
OBSERVATION NO# 5
OBSERVATION NO# 6
Follow up and Validate to continuous
improvement from previously audit at WP2
No Audit Finding / OBS Improvement Action Validate Status
1 Observation for improvement was
found when Electrode Quiver (ID 2594)
was without a calibration label tag at
welding consumable control area.
During the audit at WP2, it also found
that Electrode Quiver (ID 1089) does
not have calibration sticker
To be used the temporary
sticker calibration tag is “Pink
Color” after ensure the
tooling and equipments within
calibration certificate
Already done and
closed at WP22
2 Observation for improvement on Must be checked certificate Already done and2 Observation for improvement on
calibration tag for vertical lifting was
expired but proof load test certificate
is still valid
Must be checked certificate
before sending to offshore site
in according project period.
Already done and
closed at WP22
3 Observation for Improvement on
sticker tag identification or box
identification on weld joints for
traceability was not practiced.
To be used the sticker tags
identify or box identify for
weld joint traceability.
Already done and
closed at WP22
4 Observation for Improvement on weld
face was grinded after accepting by
QC, because lack miscommunication.
After re-checked and accepted RT
result on that welded.
Toolbox meeting on this
matter with QC and
Production teams for
understanding and awareness
to process control.
Already done and
closed at WP22

More Related Content

What's hot

CV : Inspection Engineer ( With SABIC Experience )
CV : Inspection Engineer ( With SABIC Experience )CV : Inspection Engineer ( With SABIC Experience )
CV : Inspection Engineer ( With SABIC Experience )Ganesan Sivam
 
M.Nouman Aramco Format CV
M.Nouman Aramco Format CVM.Nouman Aramco Format CV
M.Nouman Aramco Format CVMuhammad Nouman
 
E&I QA QC SUPERVISOR....ORGINAL 2
E&I QA QC  SUPERVISOR....ORGINAL 2E&I QA QC  SUPERVISOR....ORGINAL 2
E&I QA QC SUPERVISOR....ORGINAL 2mohammad tanweer
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan
 
Certified Welding Inspector - LAWAL IDRIS DARAMOLA CV
Certified Welding Inspector - LAWAL IDRIS DARAMOLA CVCertified Welding Inspector - LAWAL IDRIS DARAMOLA CV
Certified Welding Inspector - LAWAL IDRIS DARAMOLA CVidris lawal
 
Qa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi welding inspector
Qa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi  welding inspectorQa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi  welding inspector
Qa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi welding inspectorWael Mahmoud alkilany
 
Arnel Moncada Resume
Arnel Moncada ResumeArnel Moncada Resume
Arnel Moncada Resumearnel moncada
 
Vijay konathala Resume
Vijay konathala ResumeVijay konathala Resume
Vijay konathala Resumevijay kumar
 
QC INSPECTOR E&I
QC INSPECTOR E&IQC INSPECTOR E&I
QC INSPECTOR E&INASIM NEZAM
 
RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORMohsin Iqubal
 
Ganesan Selvakumar CV 151116_M+W
Ganesan Selvakumar CV 151116_M+WGanesan Selvakumar CV 151116_M+W
Ganesan Selvakumar CV 151116_M+WGanesan Selvakumar
 

What's hot (19)

CV : Inspection Engineer ( With SABIC Experience )
CV : Inspection Engineer ( With SABIC Experience )CV : Inspection Engineer ( With SABIC Experience )
CV : Inspection Engineer ( With SABIC Experience )
 
M.Nouman Aramco Format CV
M.Nouman Aramco Format CVM.Nouman Aramco Format CV
M.Nouman Aramco Format CV
 
E&I QA QC SUPERVISOR....ORGINAL 2
E&I QA QC  SUPERVISOR....ORGINAL 2E&I QA QC  SUPERVISOR....ORGINAL 2
E&I QA QC SUPERVISOR....ORGINAL 2
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16
 
Certified Welding Inspector - LAWAL IDRIS DARAMOLA CV
Certified Welding Inspector - LAWAL IDRIS DARAMOLA CVCertified Welding Inspector - LAWAL IDRIS DARAMOLA CV
Certified Welding Inspector - LAWAL IDRIS DARAMOLA CV
 
Qa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi welding inspector
Qa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi  welding inspectorQa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi  welding inspector
Qa qc mechanical engineer ,api 510,api 570 ,api 653 & cwi welding inspector
 
RESUME UPDATED 2015
RESUME UPDATED 2015RESUME UPDATED 2015
RESUME UPDATED 2015
 
Cv ardiansyah t.a cswip 3.1
Cv ardiansyah t.a cswip 3.1Cv ardiansyah t.a cswip 3.1
Cv ardiansyah t.a cswip 3.1
 
Arnel Moncada Resume
Arnel Moncada ResumeArnel Moncada Resume
Arnel Moncada Resume
 
PRINCE CV -
PRINCE CV - PRINCE CV -
PRINCE CV -
 
Vijay konathala Resume
Vijay konathala ResumeVijay konathala Resume
Vijay konathala Resume
 
QC INSPECTOR E&I
QC INSPECTOR E&IQC INSPECTOR E&I
QC INSPECTOR E&I
 
RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTOR
 
Ganesan Plant Inspector_CV
Ganesan Plant Inspector_CVGanesan Plant Inspector_CV
Ganesan Plant Inspector_CV
 
Vuong Tatthang
Vuong TatthangVuong Tatthang
Vuong Tatthang
 
Ganesan Selvakumar CV 151116_M+W
Ganesan Selvakumar CV 151116_M+WGanesan Selvakumar CV 151116_M+W
Ganesan Selvakumar CV 151116_M+W
 
CVMA_-_QA_Manager_-_Apr 2015
CVMA_-_QA_Manager_-_Apr 2015CVMA_-_QA_Manager_-_Apr 2015
CVMA_-_QA_Manager_-_Apr 2015
 
Welding Inspector - QC Inspector
Welding Inspector - QC InspectorWelding Inspector - QC Inspector
Welding Inspector - QC Inspector
 
Updated cv
Updated cvUpdated cv
Updated cv
 

Viewers also liked

Offshore Project Report
Offshore Project ReportOffshore Project Report
Offshore Project ReportSergey Makeev
 
Sustaining Nuclear Infrastructure Wna China Nov10
Sustaining Nuclear Infrastructure   Wna China   Nov10Sustaining Nuclear Infrastructure   Wna China   Nov10
Sustaining Nuclear Infrastructure Wna China Nov10Jean-Baptiste MONNIER, PhD
 
Implementing people-driven mobile technology to improve offshore project know...
Implementing people-driven mobile technology to improve offshore project know...Implementing people-driven mobile technology to improve offshore project know...
Implementing people-driven mobile technology to improve offshore project know...Gerrit Brouwer (格里特)
 
ISO 15926 series standard and its business value
ISO 15926 series standard and its business valueISO 15926 series standard and its business value
ISO 15926 series standard and its business valueHiroshi Okada
 
Corporate presentation (short with examples)
Corporate presentation (short with examples)Corporate presentation (short with examples)
Corporate presentation (short with examples)PCA Services
 
Solve It Labs Offshore Project Management
Solve It Labs Offshore Project ManagementSolve It Labs Offshore Project Management
Solve It Labs Offshore Project ManagementRafael Sultanov
 

Viewers also liked (9)

Offshore Project Report
Offshore Project ReportOffshore Project Report
Offshore Project Report
 
Sustaining Nuclear Infrastructure Wna China Nov10
Sustaining Nuclear Infrastructure   Wna China   Nov10Sustaining Nuclear Infrastructure   Wna China   Nov10
Sustaining Nuclear Infrastructure Wna China Nov10
 
Implementing people-driven mobile technology to improve offshore project know...
Implementing people-driven mobile technology to improve offshore project know...Implementing people-driven mobile technology to improve offshore project know...
Implementing people-driven mobile technology to improve offshore project know...
 
ISO 15926 series standard and its business value
ISO 15926 series standard and its business valueISO 15926 series standard and its business value
ISO 15926 series standard and its business value
 
An Offshore Project Portfolio Management Organizational Chart
An Offshore Project Portfolio Management Organizational ChartAn Offshore Project Portfolio Management Organizational Chart
An Offshore Project Portfolio Management Organizational Chart
 
CS Offshore Project
CS Offshore ProjectCS Offshore Project
CS Offshore Project
 
ISO 15926 standard for Nuclear Power
ISO 15926 standard for Nuclear PowerISO 15926 standard for Nuclear Power
ISO 15926 standard for Nuclear Power
 
Corporate presentation (short with examples)
Corporate presentation (short with examples)Corporate presentation (short with examples)
Corporate presentation (short with examples)
 
Solve It Labs Offshore Project Management
Solve It Labs Offshore Project ManagementSolve It Labs Offshore Project Management
Solve It Labs Offshore Project Management
 

Similar to Offshore Project Quality Audit Summary

Example BHP QCP Revision 3
Example BHP QCP Revision 3 Example BHP QCP Revision 3
Example BHP QCP Revision 3 Dennis J Morgan
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013leo040490
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007Tonni Bruce
 
Draft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxDraft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxArshadMahmood155695
 
Aramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeAramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeRobin Parayil
 
ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)Aravinth Jai
 
KVPS HO walkdown Punch control procedure_Rev A.pptx
KVPS HO walkdown  Punch control procedure_Rev A.pptxKVPS HO walkdown  Punch control procedure_Rev A.pptx
KVPS HO walkdown Punch control procedure_Rev A.pptxKien King
 
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxQIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxShubhamShukla221709
 
Mohamad Elyaas CV & Certf
Mohamad Elyaas CV & CertfMohamad Elyaas CV & Certf
Mohamad Elyaas CV & CertfMohamad Elyaas
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineIEI GSC
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works Shaik Mohsin
 
Welding Construction Mngmt_revert
Welding Construction Mngmt_revertWelding Construction Mngmt_revert
Welding Construction Mngmt_revertMike Lewin
 
2 mcs cert process
2 mcs cert process2 mcs cert process
2 mcs cert processedge7557
 
New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105Safe Rise
 
Cqi 11 plating system assessment process table b - surface conditioning of me...
Cqi 11 plating system assessment process table b - surface conditioning of me...Cqi 11 plating system assessment process table b - surface conditioning of me...
Cqi 11 plating system assessment process table b - surface conditioning of me...Paco Miró
 
MD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalMD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalM.Nafis Haque
 

Similar to Offshore Project Quality Audit Summary (20)

Example BHP QCP Revision 3
Example BHP QCP Revision 3 Example BHP QCP Revision 3
Example BHP QCP Revision 3
 
Qa qc
Qa qcQa qc
Qa qc
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
 
PALANIIAPPAN CV (1)
PALANIIAPPAN CV (1)PALANIIAPPAN CV (1)
PALANIIAPPAN CV (1)
 
Draft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxDraft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docx
 
Aramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeAramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector Resume
 
ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)ARAVINTH(CV Aramco Approved)
ARAVINTH(CV Aramco Approved)
 
KVPS HO walkdown Punch control procedure_Rev A.pptx
KVPS HO walkdown  Punch control procedure_Rev A.pptxKVPS HO walkdown  Punch control procedure_Rev A.pptx
KVPS HO walkdown Punch control procedure_Rev A.pptx
 
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxQIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
 
Mohamad Elyaas CV & Certf
Mohamad Elyaas CV & CertfMohamad Elyaas CV & Certf
Mohamad Elyaas CV & Certf
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Welding Construction Mngmt_revert
Welding Construction Mngmt_revertWelding Construction Mngmt_revert
Welding Construction Mngmt_revert
 
2 mcs cert process
2 mcs cert process2 mcs cert process
2 mcs cert process
 
New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105
 
Cqi 11 plating system assessment process table b - surface conditioning of me...
Cqi 11 plating system assessment process table b - surface conditioning of me...Cqi 11 plating system assessment process table b - surface conditioning of me...
Cqi 11 plating system assessment process table b - surface conditioning of me...
 
kiruba new resume
kiruba new resumekiruba new resume
kiruba new resume
 
MD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalMD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_original
 

Offshore Project Quality Audit Summary

  • 1. CLOSING MEETING OFFSHORE PROJECT QUALITY AUDIT AT (WP22) BONGKOT FIELD DEVELOPMENT PROJECT BONGKOT WELLHEAD BOOSTER COMPRESSOR PHASE IV (WP2, WP15, WP16, WP22)
  • 2. SUMMARY AUDIT NO NON -COMPLIANCE CAR OBSERVATION TARGET 1 Finding that STR WPS Procedure is old revision for THAI-BC4-GEN-09-11-4001 Rev. 17B at Quality Board, but latest revision is 21C which not according with MDDR Rev.28B - To be rechecked and replaced the latest revision on board for this procedure. 3 Days 2 The Quality board don’t have posted related WPS of Excavation for STR & Piping work at deck. - To be provided the WPS of Excavation of STR and Piping at Quality Board. Today 3 Drawing doesn’t identified the weld joint at offshore site, as refer to drawing no# BC4-WP22- - Immediately communicate with responsible persons 1 Week offshore site, as refer to drawing no# BC4-WP22- ST-WM-0002-01-2 Rev.13 with responsible persons for solving on this matter. 4 Painting material has been issued certificated on Feb, 2014, which it can’t using to work because not according with project procedure no# THAI- BC4-GEN-09-01-1024 Rev16C - Immediately discussion with related persons for solving on this matter. 1 Week 5 Finding that calibration tag of Pressure gauge have been swopped from Range 300 Psi to Range 10000 Psi, which it is not according with Pressure gauge certificate. - To be ensured and check to all pressure gauges and must be complied with certificate before using to work. 3 Days
  • 3. SUMMARY AUDIT NO NON COMPLIANCE CAR OBSERVATION TARGET 6 Finding that QA/QC organization chart (offshore) doesn't have Khun Preecha Jumnongrit for work related PT & MT, RT methods Level II under BC4 Project, which this procedure still not update and approval by client as refer to THAI-BC4-GEN-09-11-4002 Rev.24C - Immediately submit the QA/QC organization chart (offshore) to client for review and approval to according with Procedure. 1 Week
  • 4. OBSERVATION NO# 1 See the Excel file as shownSee the Excel file as shown
  • 10. Follow up and Validate to continuous improvement from previously audit at WP2 No Audit Finding / OBS Improvement Action Validate Status 1 Observation for improvement was found when Electrode Quiver (ID 2594) was without a calibration label tag at welding consumable control area. During the audit at WP2, it also found that Electrode Quiver (ID 1089) does not have calibration sticker To be used the temporary sticker calibration tag is “Pink Color” after ensure the tooling and equipments within calibration certificate Already done and closed at WP22 2 Observation for improvement on Must be checked certificate Already done and2 Observation for improvement on calibration tag for vertical lifting was expired but proof load test certificate is still valid Must be checked certificate before sending to offshore site in according project period. Already done and closed at WP22 3 Observation for Improvement on sticker tag identification or box identification on weld joints for traceability was not practiced. To be used the sticker tags identify or box identify for weld joint traceability. Already done and closed at WP22 4 Observation for Improvement on weld face was grinded after accepting by QC, because lack miscommunication. After re-checked and accepted RT result on that welded. Toolbox meeting on this matter with QC and Production teams for understanding and awareness to process control. Already done and closed at WP22