SlideShare a Scribd company logo
1 of 17
Download to read offline
NOV Devin
Number
DVN-QCP-201-01
BHP
Number
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
1.1.1 Receive and review
RFQ from Company Rep
Deepwater Coordinator/Sales
Contract
SQP-5.1
Section 7.2 of MSM-1
Contract acceptance Contract acceptance N/A
1.1.2 Review site survey
document
Deepwater Coordinator/Sales Site survey checklist N/A N/A N/A
1.1.3 Check equipment
availability
Shop Foreman COM-ADM-SOP-07
Availability of
equipment
N/A N/A
This is checked in RTMS and no record is
generated
1.1.4 Enter job into RTMS Dispatcher COM-ADM-SOP-07
Ensure that delivery
ticket matches the MRF
/ customer contract
Delivery ticket N/A
1.1.5 Assigning appropriate
equipment
Deepwater Coordinator COM-ADM-SOP-07
Ensure that delivery
ticket matches the
quote / customer
contract
Delivery ticket N/A
1.1.6 Assigning qualified
personnel
Personnel Development
Coordinator
Qualification &
Training Matrix
SQP-6.2
Qualification &
Training Matrix
SQP-6.2
Qualification & Training
Matrix SQP-6.2
N/A
1.2 Logisitics
1.2.1 Obtain necessary
shipping information
Dispatcher / Company Rep N/A MRF MRF / Email confirmation N/A Permit must be verified by dispatcher.
CUSTOMER : BHP Billiton
LOCATION : Lafayette, LA SERVICE SECTOR: GOM - Deepwater Version 3.0
1.0 PLANNING TABLE This section will identify the project objectives, inputs and management responsibility for project realization.
PLANNING/SCHEDULING
1.1 Planning /
Scheduling
QUALITY CONTROL PLAN
WELL CONTROL EQUIPMENT / HANDLING EQUIPMENT
PURPOSE / SCOPE: This document identifies the minimum quality assurance requirements and guidelines for the preparation, ass embly and testing for the NOV Devin product lines. The below listed sequence of activities shall be followed by NOV Devin with
representation from the assigned (Customer) Third Party and/or the (Customer ) Drilling Department representative. This plan shall be an active part of the operational, inspection, assembly, and testing sequences.
Prepared by NOV/Devin Quality Group Page 1 of 17
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
2.1.1 Review order TPI
Equipment specific
procedures
Equipment specific
procedures
Contract acceptance H / D
2.1.2 Verify all
documentation and
inspections are current
Quality Coordinator / Deepwater
Coordinator / TPI
Equipment specific
procedures / SQP-
4.4.3, SQP -7.5.3
Equipment specific
procedures
Data books, Maintenance
records, Inspection records,
MTR's
H / D
2.0 Document Review This section will identify the project identification and traceability records; control of records (product history records, data books, inspection records).
2.1 Review
Equipment
List/Data Books
- BHP Billiton QA/QC- BHP Billiton QA/QCDevin Int'l Inc. Quality PlanDevin Rental Tools Quality Plan
AR-1. Any non-conformance to any or BHPB process shall be recorded on a formal or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 2 of 17
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
3.1.1 Inspections, assembly
and testing are performed
according to the customer
requirements and equipment
specific procedures. Initials
of the supervisor and quality
department on the
maintenance documents
signify release.
Quality Coordinator
Equipment specific
procedures /
Customer contract /
PHSE-14-P01
Equipment specific
procedures / Customer
contract
Inspection records,
Maintenance documents, Test
charts
W
3.1.2 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
3.1.3 Prepare tool for
inspection
Shop Foreman
COM-SHO-FRM-15 /
Stabilizer
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
3.1.4 Perform NDT
inspections if applicable
Third Party Contractors
COM-SHO-FRM-15 /
Contractor procedures
/ Inspection Procedure
AWS D1.1 / Contractor
procedures
Inspection records W
3.1.5 Pressure Test of
Equipment
Shop Foreman
COM-SHO-FRM-15 /
Work Order, DVN-
SHO-SOP-05
Unit Pressure Test
properly, DVN-SHO-
SOP-05
COM-SHO-FRM-15 /
Signature, DVN-SHO-FRM-12
W Refer to Dev-10
3.1.6 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Completion of required
repairs / Contractor
procedures
Repair / Inspection reports W W-Reinspection
3.1.7 Prepare tool for
staging
Shop Foreman COM-SHO-FRM-15 COM-SHO-FRM-15 MIR / PreDispatch Sheet W
3.1.8 Engineering, Revision,
Application
GOM Coordinator / BHP / Sales
Project Specific /
Drawing Number
BHP Signature
Project Specific / Drawing
Number
H Review / Confirm
3.1.9 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
3.0 INSPECTION/ASSEMBLY
3.1 Equipment
Inspection
This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements.
HANGOFF SUB - BHP Billiton QA/QC- BHP Billiton QA/QCDevin Int'l Inc. Quality PlanDevin Rental Tools Quality Plan
AR-1. Any non-conformance to any or BHPB process shall be recorded on a formal or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 3 of 17
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
4.1.1 Applicable testing
inspections (NDT/Pull)
Third Party Contractors
Contractor supplied
procedures
Equipment specific
procedures / Contractor
procedures
Inspection records W
4.1.2 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
4.1.3 Prepare tool for
inspection
Shop Foreman
COM-SHO-FRM-15 /
Stabilizer
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
4.1.4 Perform NDT
inspections if applicable
Third Party Contractors
COM-SHO-FRM-15 /
Contractor procedures
/ Inspection Procedure
AWS D1.1 / Contractor
procedures
Inspection records W W-Reinspection
4.1.5 Pressure Test of
Equipment
Shop Foreman
COM-SHO-FRM-15 /
Work Order, DVN-
SHO-SOP-05
Unit Pressure Test
properly, DVN-SHO-
SOP-05
COM-SHO-FRM-15 /
Signature, DVN-SHO-FRM-12
W Refer to Dev-10
4.1.6 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Completion of required
repairs / Contractor
procedures
Repair / Inspection reports W
4.1.7 Perform function
testing
Shop Foreman
COM-SHO-FRM-15 /
Work Order
Unit functions properly
COM-SHO-FRM-15 /
Signature
W
4.1.8 Prepare tool for
staging
Shop Foreman COM-SHO-FRM-15 COM-SHO-FRM-15 MIR / PreDispatch Sheet W
4.1.9 Engineering, Revision,
Application
GOM Coordinator / BHP / Sales
Project Specific /
Drawing Number
BHP Signature
Project Specific / Drawing
Number
H Review / Confirm
4.2.0 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
DUAL MINI
4.1 Equipment
Inspection
4.0 INSPECTION/ASSEMBLY This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements.
Prepared by NOV/Devin Quality Group Page 4 of 17
5.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
5.1.1 Applicable testing and
inspections for STT Stand
(NDT/Pull)
Client/Customer
Contractor supplied
procedures
Well Map, Equipment
specific procedure /
Contractor procedures
Inspection records W
5.1.2 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
5.1.3 Prepare tool for
inspection
Shop Foreman
COM-SHO-FRM-15 /
Stabilizer
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
5.1.4 Perform NDT
inspections if applicable
Third Party Contractors
COM-SHO-FRM-15 /
Contractor procedures
/ Inspection Procedure
AWS D1.1 / Contractor
procedures
Inspection records W
5.1.5 Perform Pressure
Testing if applicable
Shop Foreman DVN-SHO-SOP-05
DVN-SHO-SOP-05 /
TPI
DVN-SHO-FRM-12 W Refer to Dev-10
5.1.6 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Completion of required
repairs / Contractor
procedures
Repair / Inspection reports W W-Reinspection
5.1.7 Perform function
testing
Shop Foreman
COM-SHO-FRM-15 /
Work Order
Unit functions properly
COM-SHO-FRM-15 /
Signature
W
5.1.8 Prepare tool for
staging
Shop Foreman COM-SHO-FRM-15 COM-SHO-FRM-15 MIR / PreDispatch Sheet W
5.1.9 Engineering, Revision,
Application
GOM Coordinator / BHP / Sales
Project Specific /
Drawing Number
BHP Signature
Project Specific / Drawing
Number
H Review / Confirm
5.2.0 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
5.1 Equipment
Inspection
This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements.
SURFACE TEST TREE
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality PlanPrepared by NOV/Devin Quality Group Page 5 of 17
6.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
6.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
6.1.2 Prepare tool for
inspection (as per
procedure)
Shop Foreman
Equipment specific
procedure / Quality
Plan
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
6.1.3 Perform NDT
inspections if applicable
Third Party Contractors
Equipment specific
procedures /
Contractor procedures
/ Quality Plan
Equipment specific
procedures / Contractor
procedures
Inspection records W Bolts Require Visual Inspection Only
6.1.4 Applicable pressure
testing of Hang-Off Sub
Third Party Contractors
Contractor supplied
procedures
Equipment specific
procedures / Contractor
procedures
Inspection records W Refer to Dev-10
6.1.5 Repair & Re-
inspection
Repair Facility / NDT
Contractors / Quality
Coordinator
Repair facility
procedures / NDT
contractor procedures
Equipment specific
procedures / Contractor
procedures
Repair / Inspection reports W W-Reinspection
6.1.6 Perform function /
pressure testing
Shop Foreman / Deepwater
Coordinator
Equipment specific
procedure
Unit functions properly /
pressure testing
requirements
Pressure test charts W Refer to Dev-10
6.1.7 Prepare tool for
staging
Shop Foreman / Dispatch
Equipment specific
procedure
Equipment specific
procedure
Completed maintenance
record
W
6.1.8 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
HANDLING TOOLS
6.1 Equipment
Inspection and
Assembly
This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 6 of 17
7.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
7.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
7.1.2 Prepare tool for
inspection (as per
procedure)
Shop Foreman DVN-CLF-MIP-02
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
7.1.3 Perform NDT
inspections if applicable
Third Party Contractors
DVN-CLF-MIP-02 /
Contractor procedures
AWS D1.1 / Contractor
procedures
Inspection records W
7.1.4 Repair & Re-
inspection
Repair Facility / NDT
Contractors
Repair facility
procedures / NDT
contractor procedures
COM-SHO-SMP-15 /
Contractor procedures
Repair / Inspection reports W W-Reinspection
7.1.5 Perform function
testing
Shop Foreman DVN-CLF-IOP-01 MIR / Workorder COM-SHO-FRM-60 W
7.1.6 Prepare tool for
staging
Shop Foreman / Dispatch COM-OPE-SOP-33 COM-OPE-SOP-33
Completed maintenance
record /MIR / PreDispatch
Sheet
W
7.1.7 Engineering, Revision,
Application
GOM Coordinator / BHP / Sales
Project Specific /
Drawing Number
BHP Signature
Project Specific / Drawing
Number
H Review / Confirm
7.1.8 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
COILED TUBING LIFT
FRAME
7.1 Equipment
Inspection
This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 7 of 17
8.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
8.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
8.1.2 Prepare tool for
inspection
Shop Foreman / Dispatch COM-OPE-SOP-33
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
Swing Arm Crane is covered in the CTLF
procedures
8.1.3 Perform NDT
inspections if applicable
Third Party Contractors Contractor procedures
AWS D1.1 Welding
Procedures /
Contractor procedures
Inspection records W
8.1.4 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Completion of required
repairs / Contractor
procedures
Repair / Inspection reports W W-Reinspection
8.1.5 Perform function
testing
Shop Foreman COM-OPE-SOP-33 Unit functions properly COM-ADM-SOP-07 W
8.1.6 Prepare tool for
staging
Shop Foreman / Dispatch COM-ADM-SOP-07 COM-ADM-SOP-07
Signature / PreDispatch
Forms
W
8.1.7 Engineering, Revision,
Application
GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm
8.1.8 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
SWING ARM CRANE
8.1 Equipment
Inspection
Devin Int'l Inc. Quality PlanOffshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 8 of 17
9.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
9.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
9.1.2 Prepare tool for
inspection
Shop Foreman NA
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
9.1.3 Perform NDT
inspections if applicable
Third Party Contractors Contractor procedures
AWS D1.1 / Contractor
procedures
Inspection records W
Full Body Inspection shall be performed every
(2) years
9.1.4 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Completion of required
repairs / Contractor
procedures
Repair / Inspection reports W W-Reinspection
9.1.5 Perform function
testing
Shop Foreman NA Unit functions properly NA W
9.1.6 Prepare tool for
staging
Shop Foreman NA COM-ADM-SOP-07
Completed maintenance
record
W
9.1.7 Engineering, Revision,
Application
GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm
9.1.8 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
MINI TRACK
9.1 Equipment
Inspection
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 9 of 17
10.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
10.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D
10.1.2 Prepare tool for
inspection (as per
procedure)
Shop Foreman
BASS procedure DVN-
BAS-IOP-01 - DVN-
BAS-SOP-01
Dictated by the level of
maintenance /
Customer
Requirements
Inspection / Maintenance
records
D
10.1.3 Perform NDT
inspections if applicable
Third Party Contractors
BASS procedure /
Contractor procedures
AWS D1.1 / Contractor
procedures
Inspection records W
10.1.4 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Contractor procedures Repair / Inspection reports W W-Reinspection
10.1.5 Perform function
testing
Shop Foreman DEV-BAS-MIR-03 Unit functions properly Complete maintenance record W
10.1.6 Prepare tool for
staging
Shop Foreman DNV-BAS-MIR-03 COM-ADM-SOP-07 Complete maintenance record W
10.1.7 Engineering,
Revision, Application
GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm
10.1.8 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
BAIL ASSEMBLY
SPREADER SYSTEM
(BASS)
10.1 Equipment
Inspection
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 10 of 17
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
11.1.1 Verify equipment Shop Foreman / TPI
Delivery Ticket / Load
out list
Customer contract RTMS D
11.1.2 Prepare tool for
inspection
Shop Foreman N/A
Customer
Requirements
Inspection / Maintenance
records
D
11.1.3 Perform NDT
inspections if applicable
Third Party Contractors Contractor procedures
AWS D1.1 / Contractor
procedures
Inspection records W
HPU pad eyes are pull tested every (5) years,
MPI annually.
11.1.4 Repair & Re-
inspection
Shop Foreman / Repair Facility
/ NDT Contractors
Repair facility
procedures / NDT
contractor procedures
Completion of required
repairs / Contractor
procedures
Repair / Inspection reports W W-Reinspection
11.1.5 Perform function
testing
Shop Foreman DVN-HPU-MIR-02 Unit functions properly DVN-HPU-MIR-02 W
11.1.6 Prepare tool for
staging
Shop Foreman DVN-HPU-MIR-02 DVN-HPU-MIR-02 Complete maintenance record W
11.1.7 Engineering,
Revision, Application
GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm
11.1.8 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
11.1 Equipment
Inspection
HYDRAULIC POWER
UNIT
11.0 INSPECTION / ASSEMBLY
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 11 of 17
12.0 INSPECTION / ASSEMBLY
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
12.1.1 Source equipment Shop Foreman / Dispatcher Load out list Customer contract
Availibility / Delivery Ticket /
Sub Contractor
N/A
12.1.2 Equipment
Inspection
Shop Foreman PO / Requisition
Customer
Requirements
N/A D/W
Only if not previously performed and release
note was not provided.
12.1.3 Document review Quality Coordinator
Customer provided
certifications
Valid certifications
Customer provided
certifications
D
Customer to provide a release note stating
equipment is fit for use
12.1.4 Prepare tool for
staging
Shop Foreman NA CCU Checklist NA D/M/W
Check while on Job. Do not call out for only
CCU.
12.1.5 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
12.1 Equipment
Inspection
THIRD PARTY
EQUIPMENT
Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan
AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR.
Devin Int'l Inc. Quality Plan
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 12 of 17
13.0 MOBILIZATION
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
13.1.1 NDT / Pull testing
Shop Foreman / Third Party
Contractors
PHSE-14-P01
Equipment specific
procedures / PHSE-14-
P01
Inspection records D
13.1.2 Basket Structural Dispatcher / TPI
PHSE-14-P01 / CCU
Checklist
PHSE-14-P01 / CCU
Checklist
NA D
13.1.3 Loading Equipment Shop Foreman NA NA NA W See DEV-6 in the General Information section
13.2 Load Out
13.2.1 Verify equipment
before loading on truck
Dispatcher COM-ADM-SOP-07
Delivery ticket /
Predispatch
NA W
13.3 Release of
Material
13.3.1 Ensure correct
equipment is released
Dispatcher / BHP TPI /
Deepwater Coordinator
COM-ADM-SOP-07 /
Final Document
Checklist
TPI release notification
/ signature
NA H
TRANSPORTATION
13.1 Baskets /
Containers
Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan
Devin Int'l Inc. Quality Plan
Prepared by NOV/Devin Quality Group Page 13 of 17
DESCRIPTION TASK RESPONSIBLE PERSON
REFERENCE
DOCUMENT /
PROCEDURE
ACCEPTANCE
CRITERIA
VERIFYING DOCUMENT BHP ACTIVITY
TPI
ACTIVITY
COMMENTS
Ensure the return of correct
and complete equipment
Dispatcher COM-ADM-SOP-07
Delivery ticket / Load
out list
Delivery ticket / Load out list N/A
Return of defective
equipment
Dispatcher / Shop Foreman
COM-ADM-SOP-07
SQP-8.3,
N/A Delivery ticket W If anything fails, revert to OEM. .
5.2.0 Non-Conformance
Shop Foreman / Quaity
Coordinator / HSE Specialist /
BHP
SQP-5.10
SQP-6.4.2
CAR/PAR;Objective
Evidence;NCR Report -
DVN-ADM-FRM-18
Root Cause;Objective
evidence;NCN Report-DVN-
ADM-FRM-18
H Review / Confirm
GENERAL REQUIREMENTS
DEVIN
RETURNS
This section will identify the requirements of equipment returns and handling of non conforming products.
Prepared by NOV/Devin Quality Group Page 14 of 17
Quality
Coordinator
Dennis Morgan
BHP Engineering Subsea
Supervisor
Yen Dang
Deepwater
Coordinator
Matt Miguez BHP Subsea Engineer Andy Thompson
Special
Operations
Coordinator
Maka Borja BHP Subsea Engineer Anthony Smith
Personnel
Development
Coordinator
Kevin Killworth Quality Manager Stuart Barrowman
Regional
Manager
Craig Latch
WWD Quality Assurance
Engineer
John Warmuth
Dispatcher
Steve Broussard / Brian
Edwards
GENERAL INFORMATION
D- TPI Document Review
R- Released
DEVIN Contacts: 337-233-3846
APPROVED SPECIFICATIONS
AWS D1.1
Customer Contacts:
Devin
API
ASNT (American Society Of Non- destructive
Testing)
H- Hold for TPI Witness / BHP Activity
M- TPI Monitor Required
W- TPI Witness Required
DEV-1. Any non-conformance to NOV / DEVIN or process shall be recorded on a formal NOV / DEVIN NCR (QF-8.5.1) or NCR.
DEV-2. All equipment and tools to be serviced, maintained, and inspected shall be done in accordance with all DEV / OEM requirements.
DEV-3. All verifying documents, e.g., test charts, torque charts, make up records, inspection reports, etc. must clearly show the name of the individual performing the activity with
DEV-3. sign off.
DEV-4. All NOV / DEVIN rental tool assemblies must have full maintenance and inspection history up to 5 years.
DEV-5. Full traceability to raw material certifications shall be made available when requested by customer. In absence of full traceability, a Rockwell, BrInell hardness reading of the
DEV-5. component missing the documents can be performed and must meet NOV / DEV or the OEM requirements.
DEV-6. No tools shall be shipped without an MRF and release note. All equipment baskets must meet the minimum requirements of the GOM - Transit Container Code (TCC)
DEV-7. TPI SHALL fill in the appropriate part number/serial numbers on the Rig MRF & QA release note prior to shipping.
DEV-8. Devin shall insure that the latest revisions are in service and available for all processes.
DEV-9. Adherence to all HSSE policies and procedures are followed prior to the start of each task.
Dev-10. Test are to be conducted at working pressure and held for period of 15 minutes after stabilization. To qualify as an acceptable test the final 15 minutes after stabilization
must demonstrate zero drop and/or zero gain. In other words a straight line test; this assumes that a standard chart recorder is being utlized (Barton or similar mechanical
chart recorder). If the test is being conducted with a data acquisition system (computer linked to an electrical transducer) a change of +/- 5 PSIG is considered acceptable.
This pressure allowance cannot be in one direction only, either up or down, it must bobble in both directions. The allowance is there only to negate the inherent ambiguity
associated with analog to digital convesation.
Prepared by NOV/Devin Quality Group Page 15 of 17
MSM-1 Management System Manual
SQP-7.5.3
Determination of Requirements
SQP-4.3.2 Human Resources
SQP-4.4.3 Control of Documents
SQP 5.10
Dispatcher Procedures
Coiled Tubing Lift Frame Installation and Operations Procedure
Bass system work order
NCR Report
PHSE-14-P01
DVN-SHO-SOP-05
DVN-SHO-FRM-12 Hydrostatic Test Record
DVN-ADM-FRM-18
SQP-5.1, MSM-7.2.2
Identification, Traceability, Product Status
This document is in addition to the job specific drawing package, it is located at
the end of the drawing package
Lift Frame Disassembly / Reassembly Procedure
Control of Non Conforming Products / Services
BHP Lifting Operation Procedure (Petroleum CSG HSEC Management System
Procedure)
Lift Frame Function Testing and Maintenance Procedure -includes Swing Arm -
(DVN-DLF-FMP-02)
Coiled Tubing Lift Frame Maintenance, Inspection, and Repair (MIR)
REFERENCED PROCEDURES / DOCUMENTS
Surface Test Tree Hydrostatic Testing Procedure
DVN-CLF-IOP-01
COM-OPE-SOP-33
DVN-CLF-MIR-03
DVN-HPU-MIR-02
DALF Maintenance and Function Test (DVN-DLF-MIR-03)
DVN-BAS-MIR-03
COM-SHO-FRM-60
Lift Frame Stabilizer Work Order and Router
Hydraulic Power Unit Work Order and Router
COM-ADM-SOP-07
DVN -CLF-MIP-02
Final Document Checklist
COM-SHO-FRM-15
Prepared by NOV/Devin Quality Group Page 16 of 17
NOV / Devin Signature:
D
a
t
NOV / Devin Signature:
D
a
t
NOV / Devin Signature:
D
a
t
NOV / Devin Signature:
D
a
t
BHP Billiton Signature:
D
a
t
BHP Billiton Signature:
D
a
t
BHP Billiton Signature:
D
a
t
Location:
Operations Manager: Harold Touchet
Quality Manager: Stuart Barrowman
APPROVALS
Quality Engineer: John Warmuth
Engineering Manager/Supervisor: Mark Siler
Location:
Location:
Regional Manager: Craig LatchLocation: Lafayette, LA
Location: Lafayette, LA
Location: Lafayette, LA
Location:
This document represents the QA agreements between Customer and NOV / DEVIN for GOM deep water operations
Quality Manager: Dennis Morgan
Prepared by NOV/Devin Quality Group Page 17 of 17

More Related Content

What's hot

Change Control Process PowerPoint Presentation Slides
Change Control Process PowerPoint Presentation SlidesChange Control Process PowerPoint Presentation Slides
Change Control Process PowerPoint Presentation SlidesSlideTeam
 
Introduction to energy audit part 2
Introduction to energy audit part 2Introduction to energy audit part 2
Introduction to energy audit part 2ZAINI ABDUL WAHAB
 
Overpressure protection
Overpressure protectionOverpressure protection
Overpressure protectionWei Chiao Kuo
 
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Kevin Perry
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical CompletionsAndy Lang
 
Webinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycleWebinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycleStork
 
PID control for process safety.pdf
PID control for process safety.pdfPID control for process safety.pdf
PID control for process safety.pdfSMTauseef1
 
Rp e101 2012-01
Rp e101 2012-01Rp e101 2012-01
Rp e101 2012-01jpegd
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workthanhuce
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfMDAbdullah621330
 
Asset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyAsset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyChandrashekhar Kulkarni
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for pipingKhiem Vo Duy
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Storage tanks _emissions_and_emission_reductions_201312
Storage tanks _emissions_and_emission_reductions_201312Storage tanks _emissions_and_emission_reductions_201312
Storage tanks _emissions_and_emission_reductions_201312salah jallali
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Core tools apqp, ppap, fmea, spc and msa
Core tools   apqp, ppap, fmea, spc and msa Core tools   apqp, ppap, fmea, spc and msa
Core tools apqp, ppap, fmea, spc and msa Mouhcine Nahal
 
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...Pradeep Dhondi
 
NORSOK STANDARD_L-005.docx
NORSOK STANDARD_L-005.docxNORSOK STANDARD_L-005.docx
NORSOK STANDARD_L-005.docxKCMSpecialSteel
 

What's hot (20)

Change Control Process PowerPoint Presentation Slides
Change Control Process PowerPoint Presentation SlidesChange Control Process PowerPoint Presentation Slides
Change Control Process PowerPoint Presentation Slides
 
Introduction to energy audit part 2
Introduction to energy audit part 2Introduction to energy audit part 2
Introduction to energy audit part 2
 
Overpressure protection
Overpressure protectionOverpressure protection
Overpressure protection
 
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
Zablocki, Shawn, Olsson Associates, Mechanical Integrity Programs for MRP and...
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Webinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycleWebinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycle
 
PID control for process safety.pdf
PID control for process safety.pdfPID control for process safety.pdf
PID control for process safety.pdf
 
Rp e101 2012-01
Rp e101 2012-01Rp e101 2012-01
Rp e101 2012-01
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-work
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Asset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process SafetyAsset Integrity Management approach to achieve excellence in Process Safety
Asset Integrity Management approach to achieve excellence in Process Safety
 
API 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdfAPI 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdf
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
 
Ffs assessment
Ffs assessmentFfs assessment
Ffs assessment
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Storage tanks _emissions_and_emission_reductions_201312
Storage tanks _emissions_and_emission_reductions_201312Storage tanks _emissions_and_emission_reductions_201312
Storage tanks _emissions_and_emission_reductions_201312
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Core tools apqp, ppap, fmea, spc and msa
Core tools   apqp, ppap, fmea, spc and msa Core tools   apqp, ppap, fmea, spc and msa
Core tools apqp, ppap, fmea, spc and msa
 
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
Design Calculations of Venting in Atmospheric and Low-pressure Storage Tanks ...
 
NORSOK STANDARD_L-005.docx
NORSOK STANDARD_L-005.docxNORSOK STANDARD_L-005.docx
NORSOK STANDARD_L-005.docx
 

Viewers also liked

Form 12 accident report from employer
Form 12 accident report from employerForm 12 accident report from employer
Form 12 accident report from employersohanarunkumar
 
Quality Management System
Quality Management SystemQuality Management System
Quality Management SystemDennis J Morgan
 
Richard Brenner-CEO-Amarr
Richard Brenner-CEO-AmarrRichard Brenner-CEO-Amarr
Richard Brenner-CEO-AmarrDennis J Morgan
 
Accident report form
Accident report formAccident report form
Accident report formwirethehouse
 
Api q1 9th edition training program
Api q1 9th edition training programApi q1 9th edition training program
Api q1 9th edition training programapitrainings
 
BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1Dennis J Morgan
 
FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...
FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...
FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...Sephora Yao Harman
 

Viewers also liked (9)

Form 12 accident report from employer
Form 12 accident report from employerForm 12 accident report from employer
Form 12 accident report from employer
 
Quality Management System
Quality Management SystemQuality Management System
Quality Management System
 
Richard Brenner-CEO-Amarr
Richard Brenner-CEO-AmarrRichard Brenner-CEO-Amarr
Richard Brenner-CEO-Amarr
 
Accident report form
Accident report formAccident report form
Accident report form
 
Esic form
Esic formEsic form
Esic form
 
Web API HTTP Pipeline
Web API HTTP PipelineWeb API HTTP Pipeline
Web API HTTP Pipeline
 
Api q1 9th edition training program
Api q1 9th edition training programApi q1 9th edition training program
Api q1 9th edition training program
 
BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1
 
FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...
FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...
FWSVA Series_Referenced Handbook Water Storage Container Inspection Guide in ...
 

Similar to Example BHP QCP Revision 3

8.3 Control of Nonconforming Material
8.3 Control of Nonconforming Material8.3 Control of Nonconforming Material
8.3 Control of Nonconforming MaterialBrian McAuliffe
 
Supplier Requirements Specifications (SRS) Presentation
Supplier Requirements Specifications (SRS) PresentationSupplier Requirements Specifications (SRS) Presentation
Supplier Requirements Specifications (SRS) PresentationDennis J Morgan
 
SAEP-1151_inspection requirement.PDF
SAEP-1151_inspection requirement.PDFSAEP-1151_inspection requirement.PDF
SAEP-1151_inspection requirement.PDFMohammedZiauddin25
 
jabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfjabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfTraptiSharma28
 
Qualification & validation concept & terminology
Qualification & validation concept & terminologyQualification & validation concept & terminology
Qualification & validation concept & terminologyMuhammad Luqman Ikram
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptxsonutyagi20
 
Managed Pressure Drilling
Managed Pressure DrillingManaged Pressure Drilling
Managed Pressure DrillingKen Angus
 
Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)
Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)
Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)Kristipoom R-khubut
 
PerformanceAppraisal 2015
PerformanceAppraisal 2015PerformanceAppraisal 2015
PerformanceAppraisal 2015Stephen Martin
 
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxQIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxShubhamShukla221709
 
MADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMadan Kumar
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015Arun Jothilingam
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentationRanvijay Akela
 

Similar to Example BHP QCP Revision 3 (20)

8.3 Control of Nonconforming Material
8.3 Control of Nonconforming Material8.3 Control of Nonconforming Material
8.3 Control of Nonconforming Material
 
Supplier Requirements Specifications (SRS) Presentation
Supplier Requirements Specifications (SRS) PresentationSupplier Requirements Specifications (SRS) Presentation
Supplier Requirements Specifications (SRS) Presentation
 
PPAP
PPAPPPAP
PPAP
 
SAEP-1151_inspection requirement.PDF
SAEP-1151_inspection requirement.PDFSAEP-1151_inspection requirement.PDF
SAEP-1151_inspection requirement.PDF
 
jabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfjabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdf
 
Qa qc
Qa qcQa qc
Qa qc
 
Qualification & validation concept & terminology
Qualification & validation concept & terminologyQualification & validation concept & terminology
Qualification & validation concept & terminology
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptx
 
Managed Pressure Drilling
Managed Pressure DrillingManaged Pressure Drilling
Managed Pressure Drilling
 
Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)
Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)
Presentation offshore Audit WP22 -Closing meeting 12-March-2015 (3)
 
PerformanceAppraisal 2015
PerformanceAppraisal 2015PerformanceAppraisal 2015
PerformanceAppraisal 2015
 
Ppap training ppt
Ppap training   ppt Ppap training   ppt
Ppap training ppt
 
Training ppt
Training pptTraining ppt
Training ppt
 
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxQIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
 
Inspection and Test Plan_D.pdf
Inspection and Test Plan_D.pdfInspection and Test Plan_D.pdf
Inspection and Test Plan_D.pdf
 
MADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMADHAN RESUME - UPDATED
MADHAN RESUME - UPDATED
 
PROCUREMENT
PROCUREMENTPROCUREMENT
PROCUREMENT
 
CV_QC_Mahaboob khan (2)
CV_QC_Mahaboob khan (2)CV_QC_Mahaboob khan (2)
CV_QC_Mahaboob khan (2)
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentation
 

More from Dennis J Morgan

Office Manager Recommendation
Office Manager RecommendationOffice Manager Recommendation
Office Manager RecommendationDennis J Morgan
 
Joe Miller VP recommendation
Joe Miller VP recommendationJoe Miller VP recommendation
Joe Miller VP recommendationDennis J Morgan
 
Sales, Does It Really Make Sense, Part VII
Sales, Does It Really Make Sense, Part VIISales, Does It Really Make Sense, Part VII
Sales, Does It Really Make Sense, Part VIIDennis J Morgan
 
Sales, Does It Make Sense, Part VI
Sales, Does It Make Sense, Part VISales, Does It Make Sense, Part VI
Sales, Does It Make Sense, Part VIDennis J Morgan
 
Sales, Does It Really Make Sense, Part V
Sales, Does It Really Make Sense, Part VSales, Does It Really Make Sense, Part V
Sales, Does It Really Make Sense, Part VDennis J Morgan
 
Sales, Does It Really Make Sense, Part IV
Sales, Does It Really Make Sense, Part IVSales, Does It Really Make Sense, Part IV
Sales, Does It Really Make Sense, Part IVDennis J Morgan
 
Sales, Does It Really Make Sense, Part III
Sales, Does It Really Make Sense, Part IIISales, Does It Really Make Sense, Part III
Sales, Does It Really Make Sense, Part IIIDennis J Morgan
 
Sales, Does It Really Make Sense - Part II
Sales, Does It Really Make Sense - Part IISales, Does It Really Make Sense - Part II
Sales, Does It Really Make Sense - Part IIDennis J Morgan
 
Sales, Does It Really Make Sense, Part 1
Sales, Does It Really Make Sense, Part 1Sales, Does It Really Make Sense, Part 1
Sales, Does It Really Make Sense, Part 1Dennis J Morgan
 
"Don't Reinvent the Wheel, Just Realign It."
"Don't Reinvent the Wheel, Just Realign It.""Don't Reinvent the Wheel, Just Realign It."
"Don't Reinvent the Wheel, Just Realign It."Dennis J Morgan
 
EXXON-Deepwater Champion EB946
EXXON-Deepwater Champion EB946EXXON-Deepwater Champion EB946
EXXON-Deepwater Champion EB946Dennis J Morgan
 
A. Document control and record management
A. Document control and record managementA. Document control and record management
A. Document control and record managementDennis J Morgan
 
QMS Calibration Part ll Powerpoint
QMS Calibration Part ll PowerpointQMS Calibration Part ll Powerpoint
QMS Calibration Part ll PowerpointDennis J Morgan
 

More from Dennis J Morgan (20)

Manager+resume+ii
Manager+resume+iiManager+resume+ii
Manager+resume+ii
 
Josh recommendation
Josh recommendationJosh recommendation
Josh recommendation
 
Office Manager Recommendation
Office Manager RecommendationOffice Manager Recommendation
Office Manager Recommendation
 
Joe Miller VP recommendation
Joe Miller VP recommendationJoe Miller VP recommendation
Joe Miller VP recommendation
 
Time is an Illusion
Time is an IllusionTime is an Illusion
Time is an Illusion
 
Sales, Does It Really Make Sense, Part VII
Sales, Does It Really Make Sense, Part VIISales, Does It Really Make Sense, Part VII
Sales, Does It Really Make Sense, Part VII
 
Sales, Does It Make Sense, Part VI
Sales, Does It Make Sense, Part VISales, Does It Make Sense, Part VI
Sales, Does It Make Sense, Part VI
 
Sales, Does It Really Make Sense, Part V
Sales, Does It Really Make Sense, Part VSales, Does It Really Make Sense, Part V
Sales, Does It Really Make Sense, Part V
 
Sales, Does It Really Make Sense, Part IV
Sales, Does It Really Make Sense, Part IVSales, Does It Really Make Sense, Part IV
Sales, Does It Really Make Sense, Part IV
 
Sales, Does It Really Make Sense, Part III
Sales, Does It Really Make Sense, Part IIISales, Does It Really Make Sense, Part III
Sales, Does It Really Make Sense, Part III
 
Sales, Does It Really Make Sense - Part II
Sales, Does It Really Make Sense - Part IISales, Does It Really Make Sense - Part II
Sales, Does It Really Make Sense - Part II
 
Sales, Does It Really Make Sense, Part 1
Sales, Does It Really Make Sense, Part 1Sales, Does It Really Make Sense, Part 1
Sales, Does It Really Make Sense, Part 1
 
"Don't Reinvent the Wheel, Just Realign It."
"Don't Reinvent the Wheel, Just Realign It.""Don't Reinvent the Wheel, Just Realign It."
"Don't Reinvent the Wheel, Just Realign It."
 
Great job
Great jobGreat job
Great job
 
Mad Dog
Mad DogMad Dog
Mad Dog
 
DCR Presentation
DCR PresentationDCR Presentation
DCR Presentation
 
EXXON-Deepwater Champion EB946
EXXON-Deepwater Champion EB946EXXON-Deepwater Champion EB946
EXXON-Deepwater Champion EB946
 
Diamond Ocean Patriot
Diamond Ocean PatriotDiamond Ocean Patriot
Diamond Ocean Patriot
 
A. Document control and record management
A. Document control and record managementA. Document control and record management
A. Document control and record management
 
QMS Calibration Part ll Powerpoint
QMS Calibration Part ll PowerpointQMS Calibration Part ll Powerpoint
QMS Calibration Part ll Powerpoint
 

Example BHP QCP Revision 3

  • 1. NOV Devin Number DVN-QCP-201-01 BHP Number DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 1.1.1 Receive and review RFQ from Company Rep Deepwater Coordinator/Sales Contract SQP-5.1 Section 7.2 of MSM-1 Contract acceptance Contract acceptance N/A 1.1.2 Review site survey document Deepwater Coordinator/Sales Site survey checklist N/A N/A N/A 1.1.3 Check equipment availability Shop Foreman COM-ADM-SOP-07 Availability of equipment N/A N/A This is checked in RTMS and no record is generated 1.1.4 Enter job into RTMS Dispatcher COM-ADM-SOP-07 Ensure that delivery ticket matches the MRF / customer contract Delivery ticket N/A 1.1.5 Assigning appropriate equipment Deepwater Coordinator COM-ADM-SOP-07 Ensure that delivery ticket matches the quote / customer contract Delivery ticket N/A 1.1.6 Assigning qualified personnel Personnel Development Coordinator Qualification & Training Matrix SQP-6.2 Qualification & Training Matrix SQP-6.2 Qualification & Training Matrix SQP-6.2 N/A 1.2 Logisitics 1.2.1 Obtain necessary shipping information Dispatcher / Company Rep N/A MRF MRF / Email confirmation N/A Permit must be verified by dispatcher. CUSTOMER : BHP Billiton LOCATION : Lafayette, LA SERVICE SECTOR: GOM - Deepwater Version 3.0 1.0 PLANNING TABLE This section will identify the project objectives, inputs and management responsibility for project realization. PLANNING/SCHEDULING 1.1 Planning / Scheduling QUALITY CONTROL PLAN WELL CONTROL EQUIPMENT / HANDLING EQUIPMENT PURPOSE / SCOPE: This document identifies the minimum quality assurance requirements and guidelines for the preparation, ass embly and testing for the NOV Devin product lines. The below listed sequence of activities shall be followed by NOV Devin with representation from the assigned (Customer) Third Party and/or the (Customer ) Drilling Department representative. This plan shall be an active part of the operational, inspection, assembly, and testing sequences. Prepared by NOV/Devin Quality Group Page 1 of 17
  • 2. DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 2.1.1 Review order TPI Equipment specific procedures Equipment specific procedures Contract acceptance H / D 2.1.2 Verify all documentation and inspections are current Quality Coordinator / Deepwater Coordinator / TPI Equipment specific procedures / SQP- 4.4.3, SQP -7.5.3 Equipment specific procedures Data books, Maintenance records, Inspection records, MTR's H / D 2.0 Document Review This section will identify the project identification and traceability records; control of records (product history records, data books, inspection records). 2.1 Review Equipment List/Data Books - BHP Billiton QA/QC- BHP Billiton QA/QCDevin Int'l Inc. Quality PlanDevin Rental Tools Quality Plan AR-1. Any non-conformance to any or BHPB process shall be recorded on a formal or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 2 of 17
  • 3. DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 3.1.1 Inspections, assembly and testing are performed according to the customer requirements and equipment specific procedures. Initials of the supervisor and quality department on the maintenance documents signify release. Quality Coordinator Equipment specific procedures / Customer contract / PHSE-14-P01 Equipment specific procedures / Customer contract Inspection records, Maintenance documents, Test charts W 3.1.2 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 3.1.3 Prepare tool for inspection Shop Foreman COM-SHO-FRM-15 / Stabilizer Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 3.1.4 Perform NDT inspections if applicable Third Party Contractors COM-SHO-FRM-15 / Contractor procedures / Inspection Procedure AWS D1.1 / Contractor procedures Inspection records W 3.1.5 Pressure Test of Equipment Shop Foreman COM-SHO-FRM-15 / Work Order, DVN- SHO-SOP-05 Unit Pressure Test properly, DVN-SHO- SOP-05 COM-SHO-FRM-15 / Signature, DVN-SHO-FRM-12 W Refer to Dev-10 3.1.6 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Completion of required repairs / Contractor procedures Repair / Inspection reports W W-Reinspection 3.1.7 Prepare tool for staging Shop Foreman COM-SHO-FRM-15 COM-SHO-FRM-15 MIR / PreDispatch Sheet W 3.1.8 Engineering, Revision, Application GOM Coordinator / BHP / Sales Project Specific / Drawing Number BHP Signature Project Specific / Drawing Number H Review / Confirm 3.1.9 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm 3.0 INSPECTION/ASSEMBLY 3.1 Equipment Inspection This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements. HANGOFF SUB - BHP Billiton QA/QC- BHP Billiton QA/QCDevin Int'l Inc. Quality PlanDevin Rental Tools Quality Plan AR-1. Any non-conformance to any or BHPB process shall be recorded on a formal or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 3 of 17
  • 4. DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 4.1.1 Applicable testing inspections (NDT/Pull) Third Party Contractors Contractor supplied procedures Equipment specific procedures / Contractor procedures Inspection records W 4.1.2 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 4.1.3 Prepare tool for inspection Shop Foreman COM-SHO-FRM-15 / Stabilizer Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 4.1.4 Perform NDT inspections if applicable Third Party Contractors COM-SHO-FRM-15 / Contractor procedures / Inspection Procedure AWS D1.1 / Contractor procedures Inspection records W W-Reinspection 4.1.5 Pressure Test of Equipment Shop Foreman COM-SHO-FRM-15 / Work Order, DVN- SHO-SOP-05 Unit Pressure Test properly, DVN-SHO- SOP-05 COM-SHO-FRM-15 / Signature, DVN-SHO-FRM-12 W Refer to Dev-10 4.1.6 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Completion of required repairs / Contractor procedures Repair / Inspection reports W 4.1.7 Perform function testing Shop Foreman COM-SHO-FRM-15 / Work Order Unit functions properly COM-SHO-FRM-15 / Signature W 4.1.8 Prepare tool for staging Shop Foreman COM-SHO-FRM-15 COM-SHO-FRM-15 MIR / PreDispatch Sheet W 4.1.9 Engineering, Revision, Application GOM Coordinator / BHP / Sales Project Specific / Drawing Number BHP Signature Project Specific / Drawing Number H Review / Confirm 4.2.0 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm DUAL MINI 4.1 Equipment Inspection 4.0 INSPECTION/ASSEMBLY This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements. Prepared by NOV/Devin Quality Group Page 4 of 17
  • 5. 5.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 5.1.1 Applicable testing and inspections for STT Stand (NDT/Pull) Client/Customer Contractor supplied procedures Well Map, Equipment specific procedure / Contractor procedures Inspection records W 5.1.2 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 5.1.3 Prepare tool for inspection Shop Foreman COM-SHO-FRM-15 / Stabilizer Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 5.1.4 Perform NDT inspections if applicable Third Party Contractors COM-SHO-FRM-15 / Contractor procedures / Inspection Procedure AWS D1.1 / Contractor procedures Inspection records W 5.1.5 Perform Pressure Testing if applicable Shop Foreman DVN-SHO-SOP-05 DVN-SHO-SOP-05 / TPI DVN-SHO-FRM-12 W Refer to Dev-10 5.1.6 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Completion of required repairs / Contractor procedures Repair / Inspection reports W W-Reinspection 5.1.7 Perform function testing Shop Foreman COM-SHO-FRM-15 / Work Order Unit functions properly COM-SHO-FRM-15 / Signature W 5.1.8 Prepare tool for staging Shop Foreman COM-SHO-FRM-15 COM-SHO-FRM-15 MIR / PreDispatch Sheet W 5.1.9 Engineering, Revision, Application GOM Coordinator / BHP / Sales Project Specific / Drawing Number BHP Signature Project Specific / Drawing Number H Review / Confirm 5.2.0 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm 5.1 Equipment Inspection This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements. SURFACE TEST TREE Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality PlanPrepared by NOV/Devin Quality Group Page 5 of 17
  • 6. 6.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 6.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 6.1.2 Prepare tool for inspection (as per procedure) Shop Foreman Equipment specific procedure / Quality Plan Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 6.1.3 Perform NDT inspections if applicable Third Party Contractors Equipment specific procedures / Contractor procedures / Quality Plan Equipment specific procedures / Contractor procedures Inspection records W Bolts Require Visual Inspection Only 6.1.4 Applicable pressure testing of Hang-Off Sub Third Party Contractors Contractor supplied procedures Equipment specific procedures / Contractor procedures Inspection records W Refer to Dev-10 6.1.5 Repair & Re- inspection Repair Facility / NDT Contractors / Quality Coordinator Repair facility procedures / NDT contractor procedures Equipment specific procedures / Contractor procedures Repair / Inspection reports W W-Reinspection 6.1.6 Perform function / pressure testing Shop Foreman / Deepwater Coordinator Equipment specific procedure Unit functions properly / pressure testing requirements Pressure test charts W Refer to Dev-10 6.1.7 Prepare tool for staging Shop Foreman / Dispatch Equipment specific procedure Equipment specific procedure Completed maintenance record W 6.1.8 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm HANDLING TOOLS 6.1 Equipment Inspection and Assembly This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 6 of 17
  • 7. 7.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 7.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 7.1.2 Prepare tool for inspection (as per procedure) Shop Foreman DVN-CLF-MIP-02 Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 7.1.3 Perform NDT inspections if applicable Third Party Contractors DVN-CLF-MIP-02 / Contractor procedures AWS D1.1 / Contractor procedures Inspection records W 7.1.4 Repair & Re- inspection Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures COM-SHO-SMP-15 / Contractor procedures Repair / Inspection reports W W-Reinspection 7.1.5 Perform function testing Shop Foreman DVN-CLF-IOP-01 MIR / Workorder COM-SHO-FRM-60 W 7.1.6 Prepare tool for staging Shop Foreman / Dispatch COM-OPE-SOP-33 COM-OPE-SOP-33 Completed maintenance record /MIR / PreDispatch Sheet W 7.1.7 Engineering, Revision, Application GOM Coordinator / BHP / Sales Project Specific / Drawing Number BHP Signature Project Specific / Drawing Number H Review / Confirm 7.1.8 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm COILED TUBING LIFT FRAME 7.1 Equipment Inspection This section will identify the basic requirements for equipment inspection, assembly, and testing. Equipment specific procedures will dictate specific requirements. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 7 of 17
  • 8. 8.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 8.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 8.1.2 Prepare tool for inspection Shop Foreman / Dispatch COM-OPE-SOP-33 Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D Swing Arm Crane is covered in the CTLF procedures 8.1.3 Perform NDT inspections if applicable Third Party Contractors Contractor procedures AWS D1.1 Welding Procedures / Contractor procedures Inspection records W 8.1.4 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Completion of required repairs / Contractor procedures Repair / Inspection reports W W-Reinspection 8.1.5 Perform function testing Shop Foreman COM-OPE-SOP-33 Unit functions properly COM-ADM-SOP-07 W 8.1.6 Prepare tool for staging Shop Foreman / Dispatch COM-ADM-SOP-07 COM-ADM-SOP-07 Signature / PreDispatch Forms W 8.1.7 Engineering, Revision, Application GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm 8.1.8 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm SWING ARM CRANE 8.1 Equipment Inspection Devin Int'l Inc. Quality PlanOffshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 8 of 17
  • 9. 9.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 9.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 9.1.2 Prepare tool for inspection Shop Foreman NA Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 9.1.3 Perform NDT inspections if applicable Third Party Contractors Contractor procedures AWS D1.1 / Contractor procedures Inspection records W Full Body Inspection shall be performed every (2) years 9.1.4 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Completion of required repairs / Contractor procedures Repair / Inspection reports W W-Reinspection 9.1.5 Perform function testing Shop Foreman NA Unit functions properly NA W 9.1.6 Prepare tool for staging Shop Foreman NA COM-ADM-SOP-07 Completed maintenance record W 9.1.7 Engineering, Revision, Application GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm 9.1.8 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm MINI TRACK 9.1 Equipment Inspection Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 9 of 17
  • 10. 10.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 10.1.1 Verify equipment Shop Foreman / TPI Load out list Customer contract RTMS D 10.1.2 Prepare tool for inspection (as per procedure) Shop Foreman BASS procedure DVN- BAS-IOP-01 - DVN- BAS-SOP-01 Dictated by the level of maintenance / Customer Requirements Inspection / Maintenance records D 10.1.3 Perform NDT inspections if applicable Third Party Contractors BASS procedure / Contractor procedures AWS D1.1 / Contractor procedures Inspection records W 10.1.4 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Contractor procedures Repair / Inspection reports W W-Reinspection 10.1.5 Perform function testing Shop Foreman DEV-BAS-MIR-03 Unit functions properly Complete maintenance record W 10.1.6 Prepare tool for staging Shop Foreman DNV-BAS-MIR-03 COM-ADM-SOP-07 Complete maintenance record W 10.1.7 Engineering, Revision, Application GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm 10.1.8 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm BAIL ASSEMBLY SPREADER SYSTEM (BASS) 10.1 Equipment Inspection Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 10 of 17
  • 11. DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 11.1.1 Verify equipment Shop Foreman / TPI Delivery Ticket / Load out list Customer contract RTMS D 11.1.2 Prepare tool for inspection Shop Foreman N/A Customer Requirements Inspection / Maintenance records D 11.1.3 Perform NDT inspections if applicable Third Party Contractors Contractor procedures AWS D1.1 / Contractor procedures Inspection records W HPU pad eyes are pull tested every (5) years, MPI annually. 11.1.4 Repair & Re- inspection Shop Foreman / Repair Facility / NDT Contractors Repair facility procedures / NDT contractor procedures Completion of required repairs / Contractor procedures Repair / Inspection reports W W-Reinspection 11.1.5 Perform function testing Shop Foreman DVN-HPU-MIR-02 Unit functions properly DVN-HPU-MIR-02 W 11.1.6 Prepare tool for staging Shop Foreman DVN-HPU-MIR-02 DVN-HPU-MIR-02 Complete maintenance record W 11.1.7 Engineering, Revision, Application GOM Coordinator / BHP / Sales Drawing Number BHP Signature Drawing Number H Review/Confirm 11.1.8 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm 11.1 Equipment Inspection HYDRAULIC POWER UNIT 11.0 INSPECTION / ASSEMBLY Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 11 of 17
  • 12. 12.0 INSPECTION / ASSEMBLY DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 12.1.1 Source equipment Shop Foreman / Dispatcher Load out list Customer contract Availibility / Delivery Ticket / Sub Contractor N/A 12.1.2 Equipment Inspection Shop Foreman PO / Requisition Customer Requirements N/A D/W Only if not previously performed and release note was not provided. 12.1.3 Document review Quality Coordinator Customer provided certifications Valid certifications Customer provided certifications D Customer to provide a release note stating equipment is fit for use 12.1.4 Prepare tool for staging Shop Foreman NA CCU Checklist NA D/M/W Check while on Job. Do not call out for only CCU. 12.1.5 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm 12.1 Equipment Inspection THIRD PARTY EQUIPMENT Andergauge - BHP Billiton QA/QCAndergauge - BHP Billiton QA/QC AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality Plan AR-1. Any non-conformance to any Andergauge or BHPB process shall be recorded on a formal Andergauge or BHPB NCR. Devin Int'l Inc. Quality Plan Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 12 of 17
  • 13. 13.0 MOBILIZATION DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS 13.1.1 NDT / Pull testing Shop Foreman / Third Party Contractors PHSE-14-P01 Equipment specific procedures / PHSE-14- P01 Inspection records D 13.1.2 Basket Structural Dispatcher / TPI PHSE-14-P01 / CCU Checklist PHSE-14-P01 / CCU Checklist NA D 13.1.3 Loading Equipment Shop Foreman NA NA NA W See DEV-6 in the General Information section 13.2 Load Out 13.2.1 Verify equipment before loading on truck Dispatcher COM-ADM-SOP-07 Delivery ticket / Predispatch NA W 13.3 Release of Material 13.3.1 Ensure correct equipment is released Dispatcher / BHP TPI / Deepwater Coordinator COM-ADM-SOP-07 / Final Document Checklist TPI release notification / signature NA H TRANSPORTATION 13.1 Baskets / Containers Offshore Energy Services Quality PlanDevin Rental Tools Quality PlanAndergauge Quality PlanSpecialty Rental Tools & Supply Quality PlanDevin Int'l Inc. Quality Plan Devin Int'l Inc. Quality Plan Prepared by NOV/Devin Quality Group Page 13 of 17
  • 14. DESCRIPTION TASK RESPONSIBLE PERSON REFERENCE DOCUMENT / PROCEDURE ACCEPTANCE CRITERIA VERIFYING DOCUMENT BHP ACTIVITY TPI ACTIVITY COMMENTS Ensure the return of correct and complete equipment Dispatcher COM-ADM-SOP-07 Delivery ticket / Load out list Delivery ticket / Load out list N/A Return of defective equipment Dispatcher / Shop Foreman COM-ADM-SOP-07 SQP-8.3, N/A Delivery ticket W If anything fails, revert to OEM. . 5.2.0 Non-Conformance Shop Foreman / Quaity Coordinator / HSE Specialist / BHP SQP-5.10 SQP-6.4.2 CAR/PAR;Objective Evidence;NCR Report - DVN-ADM-FRM-18 Root Cause;Objective evidence;NCN Report-DVN- ADM-FRM-18 H Review / Confirm GENERAL REQUIREMENTS DEVIN RETURNS This section will identify the requirements of equipment returns and handling of non conforming products. Prepared by NOV/Devin Quality Group Page 14 of 17
  • 15. Quality Coordinator Dennis Morgan BHP Engineering Subsea Supervisor Yen Dang Deepwater Coordinator Matt Miguez BHP Subsea Engineer Andy Thompson Special Operations Coordinator Maka Borja BHP Subsea Engineer Anthony Smith Personnel Development Coordinator Kevin Killworth Quality Manager Stuart Barrowman Regional Manager Craig Latch WWD Quality Assurance Engineer John Warmuth Dispatcher Steve Broussard / Brian Edwards GENERAL INFORMATION D- TPI Document Review R- Released DEVIN Contacts: 337-233-3846 APPROVED SPECIFICATIONS AWS D1.1 Customer Contacts: Devin API ASNT (American Society Of Non- destructive Testing) H- Hold for TPI Witness / BHP Activity M- TPI Monitor Required W- TPI Witness Required DEV-1. Any non-conformance to NOV / DEVIN or process shall be recorded on a formal NOV / DEVIN NCR (QF-8.5.1) or NCR. DEV-2. All equipment and tools to be serviced, maintained, and inspected shall be done in accordance with all DEV / OEM requirements. DEV-3. All verifying documents, e.g., test charts, torque charts, make up records, inspection reports, etc. must clearly show the name of the individual performing the activity with DEV-3. sign off. DEV-4. All NOV / DEVIN rental tool assemblies must have full maintenance and inspection history up to 5 years. DEV-5. Full traceability to raw material certifications shall be made available when requested by customer. In absence of full traceability, a Rockwell, BrInell hardness reading of the DEV-5. component missing the documents can be performed and must meet NOV / DEV or the OEM requirements. DEV-6. No tools shall be shipped without an MRF and release note. All equipment baskets must meet the minimum requirements of the GOM - Transit Container Code (TCC) DEV-7. TPI SHALL fill in the appropriate part number/serial numbers on the Rig MRF & QA release note prior to shipping. DEV-8. Devin shall insure that the latest revisions are in service and available for all processes. DEV-9. Adherence to all HSSE policies and procedures are followed prior to the start of each task. Dev-10. Test are to be conducted at working pressure and held for period of 15 minutes after stabilization. To qualify as an acceptable test the final 15 minutes after stabilization must demonstrate zero drop and/or zero gain. In other words a straight line test; this assumes that a standard chart recorder is being utlized (Barton or similar mechanical chart recorder). If the test is being conducted with a data acquisition system (computer linked to an electrical transducer) a change of +/- 5 PSIG is considered acceptable. This pressure allowance cannot be in one direction only, either up or down, it must bobble in both directions. The allowance is there only to negate the inherent ambiguity associated with analog to digital convesation. Prepared by NOV/Devin Quality Group Page 15 of 17
  • 16. MSM-1 Management System Manual SQP-7.5.3 Determination of Requirements SQP-4.3.2 Human Resources SQP-4.4.3 Control of Documents SQP 5.10 Dispatcher Procedures Coiled Tubing Lift Frame Installation and Operations Procedure Bass system work order NCR Report PHSE-14-P01 DVN-SHO-SOP-05 DVN-SHO-FRM-12 Hydrostatic Test Record DVN-ADM-FRM-18 SQP-5.1, MSM-7.2.2 Identification, Traceability, Product Status This document is in addition to the job specific drawing package, it is located at the end of the drawing package Lift Frame Disassembly / Reassembly Procedure Control of Non Conforming Products / Services BHP Lifting Operation Procedure (Petroleum CSG HSEC Management System Procedure) Lift Frame Function Testing and Maintenance Procedure -includes Swing Arm - (DVN-DLF-FMP-02) Coiled Tubing Lift Frame Maintenance, Inspection, and Repair (MIR) REFERENCED PROCEDURES / DOCUMENTS Surface Test Tree Hydrostatic Testing Procedure DVN-CLF-IOP-01 COM-OPE-SOP-33 DVN-CLF-MIR-03 DVN-HPU-MIR-02 DALF Maintenance and Function Test (DVN-DLF-MIR-03) DVN-BAS-MIR-03 COM-SHO-FRM-60 Lift Frame Stabilizer Work Order and Router Hydraulic Power Unit Work Order and Router COM-ADM-SOP-07 DVN -CLF-MIP-02 Final Document Checklist COM-SHO-FRM-15 Prepared by NOV/Devin Quality Group Page 16 of 17
  • 17. NOV / Devin Signature: D a t NOV / Devin Signature: D a t NOV / Devin Signature: D a t NOV / Devin Signature: D a t BHP Billiton Signature: D a t BHP Billiton Signature: D a t BHP Billiton Signature: D a t Location: Operations Manager: Harold Touchet Quality Manager: Stuart Barrowman APPROVALS Quality Engineer: John Warmuth Engineering Manager/Supervisor: Mark Siler Location: Location: Regional Manager: Craig LatchLocation: Lafayette, LA Location: Lafayette, LA Location: Lafayette, LA Location: This document represents the QA agreements between Customer and NOV / DEVIN for GOM deep water operations Quality Manager: Dennis Morgan Prepared by NOV/Devin Quality Group Page 17 of 17