SlideShare a Scribd company logo
1 of 19
Download to read offline
Running head: TEAM 3 FINAL PROJECT PAPER 1
Sim4Project Simulation
Auto Supply, Inc. (ASI) – A Complete Redesigned Information System
Connie R. Himebaugh, Ashley Jackson & Justin Hughes
Davenport University
August 15th
, 2019
Author Note
GPMT287 Principles of Project Management
TEAM 3 FINAL PROJECT PAPER 2
Abstract
The duration of this Sim4Project simulation, demonstrates how a fictitious company, the case of
Auto Supply, Inc. (ASI), redesigned their IT Information Technology System to a better, more
functional system for them and for their customers. This company is a regional automotive part
supplier whose business has been steadily growing over the past decade, with annual sales of $80
million, ASI discovered that their information system was badly outdated. Team 3 stepped in and
in 8 periods, developed a project plan to resolve the issues and set a new IT information in place.
TEAM 3 FINAL PROJECT PAPER 3
Table of Contents
Abstract............................................................................................................................................2
Auto Supply, Inc. – Project Management Concepts........................................................................5
Project Life Cycle............................................................................................................................5
Initiating.......................................................................................................................................5
Planning/Scheduling....................................................................................................................5
Executing.....................................................................................................................................6
Schedule Management.............................................................................................................6
Triple Constraint......................................................................................................................7
Monitoring and Controlling.........................................................................................................7
Decision-Making.........................................................................................................................8
Conflict Resolution......................................................................................................................9
Cost Variance...............................................................................................................................9
Analysis.....................................................................................................................................10
Team Dynamics.....................................................................................................................10
Functionality..................................................................................................................................11
Organization...............................................................................................................................11
Resource Allocation.......................................................................................................................12
Time Management Skills...........................................................................................................12
TEAM 3 FINAL PROJECT PAPER 4
Effective Time Management......................................................................................................12
Stakeholder Satisfaction................................................................................................................12
Period One Results....................................................................................................................14
Worst Period Results..................................................................................................................14
Best Period Results....................................................................................................................14
Last Period Results....................................................................................................................14
Conclusion.....................................................................................................................................15
References......................................................................................................................................15
Appendix........................................................................................................................................18
Tables.........................................................................................................................................19
Graphs........................................................................................................................................19
TEAM 3 FINAL PROJECT PAPER 5
Auto Supply, Inc. – Project Management Concepts
The GPMT287 Project Management students from Team 3, organized and produced a
project plan life cycle which provided selecting and initiating resources for work in the
simulation. Planned each period, selected workers to the appropriate tasks, submitted in Sims for
status results compared to 5 other teams, constructed charts, graphs, and reports, then finalized
the project with statistical recognition and observation, and closed the IT project at completion.
Project Life Cycle
Initiating
Team 3 sat down and discussed the problems that Auto Supply Inc. lacked in the IT
Information System that was not satisfactorily producing adequate results. The customers were
complaining that their order were getting mixed up from paper copies, and that they never
received a revised fax if the order changed. To construct a more efficient system, a computer
information system that allowed invoicing at the time of call in intake, packaging, organizing and
storing, down to the loading the trucks and deliveries. Quality assurance and a more efficient
way of processing these orders in a timely fashion was desperately needed. Therefore, Team 3
agreed and signed a contract including these measures and it was signed. Selecting and initiating
begins when the idea for a project first develops and the project is selected and planned with the
team committed to the project and its stages (Kloppenborg, Anantatmuia, & Wells, 2019, p. 7).
Planning/Scheduling
Scheduling is the process of managing the time constraints of the project from beginning
to end. It takes teamwork, identification of the problem, then defining the problem and selecting
a project manager to get the scope in perspective. It is planning and processing that a whole team
TEAM 3 FINAL PROJECT PAPER 6
gets involved with. Therefore, the project manager hires a team of professionals to do their part
in the overall steps that it takes to get the job done. Planning begins right after the initial
obligation by the members and includes the detail plans, and ends when all the members have
accepted the entire detailed plan as discussed in the meetings (Kloppenborg, Anantatmuia, &
Wells, 2019, p. 8). Team three did a Sim4Project pre-play and this allowed our team to get
familiar with the Sims simulation and how it works.
Executing
After thoughtful considerations, our team 3 worked together and hired simulated workers
throughout our simulation that consisted of these 9 resource categories: Hardware Analyst, Jr.
Systems Analyst, MIS Manager, Network Design Consultant, Office Engineer, Programmer,
Project Manager, Sr. Systems Analyst, and Systems Software Engineer. To execute the plan after
acceptance, the plan includes authorizing, executing, monitoring, and controlling work until the
customers or the project purpose has been accepted and is approved to move forward with the
budget in mind (Kloppenborg, Anantatmuia, & Wells, 2019, p. 8). Each period 1-8, an updated
project plan was posted to gain knowledge of what the current stats were and how to proceed
choosing the tasks for the next period and for which workers. A timeline shows which worker
had what job to do, how long the job is to take, and an expected finish date.
Schedule Management
Our class participation as a team, consisting of two girls and one boy, worked to achieve
making Sim4Project selections by reading each task for that period and hiring one of the workers
from the project to complete that task within a specified time frame, not to go over budget. Some
workers had to be fired due to too many hired for the same purpose and title, and for cost
reasons. Did not need them for that amount of money. We started out with a beginning balance of
TEAM 3 FINAL PROJECT PAPER 7
$270,000 in pre-play and within each end period results, we could see the report results and what
place we came in comparted to that of the other 5 teams.
Triple Constraint
It is the combination of the three most significant restrictions in this project that includes
scope, schedule, and cost – such a addressing the “triple constraint” and why this concept
imposes a higher level of accountability than most jobs (Kloppenborg, Anantatmuia, & Wells,
2019, p. 14). Therefore, as what team three did, to review all aspects of project of Auto Supply,
Inc. (ASI), as a project manager, it is imperative to understand the performance levels of these
constraints including quality, time, and budget to take precedence and to make a strong
commitment to (Kloppenborg, Anantatmuia, & Wells, 2019, p. 15). Team three review the
instructions, downloaded the appetitive software needed, reviewed requirements, instructions,
and started team building skills right away. Sim4Project simulation is a competitive software that
enables a group to compete with other teams. From there, we signed a team contract committed
to the project, appendix¹.
Monitoring and Controlling
This step aligns the activities in a project in a series to help track, review, and document
the continued progress and making sure it meets performance objectives as outlined in the plan
(Kloppenborg, Anantatmuia, & Wells, 2019, p. 460). When we think of monitoring, this refers to
review the progress and capture project performance data along with referencing the project plan
(Kloppenborg, Anantatmuia, & Wells, 2019, p. 460). The objective is to see how the
development and performance measures and that of good communication during that time, to
have control assessing the actual performance (Kloppenborg, Anantatmuia, & Wells, 2019, p.
460). A project manager keeps the project under control with an action and keeping that revised
TEAM 3 FINAL PROJECT PAPER 8
at each meeting, that way those meeting minutes and posted revisions can be viewed by each
member at any given time between meetings.
Closing
Closing a project is the very last step in the project and is a very important one. It is the
final phase, or the administration phase, and cannot be completed until everything else in the
project tasks has taken place (Kloppenborg, Anantatmuia, & Wells, 2019, p. 515). To do so,
gathering and storing lessons learned, writing reports, and updating project documents, even
though it is a possibility that a conclusion has been reached or not (Kloppenborg, Anantatmuia,
& Wells, 2019, p. 515). The project manager is usually the one to close the project with said date
and time.
Project Budget
Decision-Making
What went well was decision making for the tasks. What didn’t work well was not
everyone in the team participated at all times and the important decisions were not made by all
involved that hurt the team. It is important that all team members work equally and not rely on
other team members to do all the work while they sit back and do absolutely nothing. Managerial
Actions were taken throughout the simulation, and these affected the project in significant ways
and those that were associated to them as team three went along during the project. The
beginning budget was $270,000 to start knowing that we had to stretch that over 8 period worth
of planning and executing. The decisions were amongst three team members deciding which
worker to be appointed to which task for that period. We conversed through our team discussion
board, or by email, phone, or cell texting for an adequate decision before that particular period
TEAM 3 FINAL PROJECT PAPER 9
tasks were selected and then submitted. For each period, a team leader, which Connie took
charge of and made sure that all decisions were in, and that the Sims and Stats were submitted on
time. Connie planned meetings in the beginning of the project to make sure everyone was on
board and that we understood what was to be expected of each of us. Making task decisions in
Sims was probably the most difficult because it determined how it would affect the progress of
the team company and making sure that all the workers’ jobs were done in a timely fashion. Our
budget report indicated our period report for each period, Appendix².
Conflict Resolution
Once a project manager sees that there is a conflict within the project, he or she might try
and find a better solution before it escalates into a bigger problem (Kloppenborg, Anantatmuia,
& Wells, 2019, p. 163). One of the situations within this team is not seeing that all members of
the team were on board initially and that caused stress and uncertainties to the members that
were a tentative. The project coordinator, Connie sent out emails to the other member asking if
they have received any emails from the group and to check and make sure that in fact they were
viewing the correct email inbox and included the instructor on the email. That did help getting
the non-participant’s attention and their participation began shortly thereafter.
Cost Variance
As stated above the beginning budget for this project was $270,000 by the end of period
8, we had exceeded that budget by $34,406. A few things contributed to this. In period 1 we
mistakenly spent $55,616 on training and $290 on managerial actions, this brought our total cost
to $85,603, that was 31% of our budget gone. We learned from that and didn’t spend money on
training or managerial actions for the remaining periods. From there our money problems went
towards unallocated cost and work overage. Because our actual work hours were so much more
TEAM 3 FINAL PROJECT PAPER 10
than the estimated work, we ended up spending even more money. Cost variance is the difference
between earned value and actual cost, which reflects performance (Kloppenborg, Anantatmuia,
& Wells, 2019, p. 478). Based on our cost variance, we did poorly in this regard. We tried to
lower the cost by having our resources work only half the time. However, this proved to be
fruitless as we still did not make up the budget. That being said, even with the cost variance
being so high we would have remained in budget if did not spend the $55, 616 on training,
actually leaving us with $21, 500 in the budget, graph¹.
Analysis
Reporting is essential within this project as each period contains analysis with live data
pertaining to the team as a result of the end of a period simulation. The stats report indicates how
we did each period in comparison to the other teams, appendix³.
Team Dynamics
The virtual team in Sims allowed us to really experience what it is like to do a project as
a team. It allowed us to use managerial skills, perception skills, team building skills, ethical
behaviors utilized, and analytical thinking. It takes a lot of organizational skills to keep everyone
on track to get the project done and to stay focused. Six reasons why team participation is so
important is: Your opinion is important, More perspectives, New information, Community
benefit/ownership, It feels good, and A Numbers game, meaning the total number of members in
the project (Connell, 2017). Definitely time management skills were needed and affective to keep
up with the simulation and what workers to hire, who to fire, who to do what job and for how
long, sometimes a worker was given half, 50% the allotted time to complete the job, splitting that
very same job with another worker so that they can also work as a team. Striving for more
TEAM 3 FINAL PROJECT PAPER 11
efficiency was the goal in that and to meet our milestones and deadlines at the same time. Both
keeping cost down and meeting our milestones was our main focus in this project.
Functionality
Functionality organization in an organization and in a project structure is which a staff is
grouped by areas of specialization, the project manager has limited authority to assign work and
apply resources (Kloppenborg, Anantatmuia, & Wells, 2019, p. 103). The function manager
controls the project budget, makes most of the decisions, and is primarily the one coordinating
project communication amongst the other team members (Kloppenborg, Anantatmuia, & Wells,
2019, p. 103).
The functionality in project management is whether or not the team is achieving its
attended purpose. To figure this out you take the estimated time and divided it by the actual time.
The higher the percentage the better the chance of the project doing what it is intended. By the
end of period 8 our teams’ functionality was at 35%, this means our project has a low chance of
completing its task. Our best performance was in period 5 where the functionality was at 82%.
The difference in these two performances has to do with the work variance. For period 8 we
went over our estimated hours of work by 72 hours, in period 5 we went over by 66 hours.
Organization
Unity comes to mind when thinking of organization. Team three has unity when all team
members show equal interest and participates in an equal manner of all work involved. In the
Sims project, allocating other virtual team members allowed us to gain more people within our
team, even though they could not communicate with us, it was realistic enough to assume they
were present and getting their work done accordingly. The organizational needs assessment table
shows the system breakdown, table¹.
TEAM 3 FINAL PROJECT PAPER 12
Resource Allocation
Resource allocation is defined in MS Project that allows us to understand of who and
what resources are being used that includes five steps: Defining resources, Setting up a resource
calendar, Assigning resources, Identifying over allocated resources, Dealing with over
allocations (Kloppenborg, Anantatmuia, & Wells, 2019, p. 311).
Time Management Skills
The importance of time management is the capability to organize and plan the amount of
time to spend in an activity or activities in one given day. The result of that is good time
management. It could increase effectiveness and the overall productivity, and by planning ahead
and setting goals your overall performance will be more rewarding. Prioritizing is best in this
situation.
Effective Time Management
To work more efficiently that if at all, utilize work that can be done in less time without
stress of the project. Some suggestions are: Avoid distractions, Make a task list of priorities,
Estimate and track time accordingly, and create and follow a schedule (Tran, 2015).
Stakeholder Satisfaction
Stakeholders are groups or people that have a certain level of investment in a project.
These can include people who work on the project, people who provide the resources, customers
and even local, state or federal governments who may be affected. “To ensure the success of their
projects, project managers should initially identify all the people or groups that have the potential
TEAM 3 FINAL PROJECT PAPER 13
to affect the work in progress, either positively or negatively” [ CITATION Dug19 l 1033 ]One
of the best ways to identify stakeholders is to ask the simple questions, “who will use, will be
affected by, or could impact this project. For this simulation team 3 had to oversee the project for
Auto Supply, Inc in redesigning their information technology system to better communicate. In
this case the stakeholders would be the owners, managers, the employees, the vendors, software
and hardware engineers, IT specialist, and the customers. Team 3 started period 1 with a
stakeholder satisfaction of 59%. This score depends on several things, the time, cost and
functionality scores as well the skills and management style of the team and whether the
milestones were met. At the end of period 8 the score had dropped to 34%.
Table 1
Period 1 Statistics
Name Time Cost Functionality Stakeholder Overall Rank
Team
3
81 0 46 59 5 5
Table 2
Period 8 Statistics
Name Time Cost Functionality Stakeholder Overall Rank
Team
3
56 17 35 34 16 4
Looking at these two tables you can see how the time and functionality scores affected
the stakeholders. Because we weren’t keeping good time and functioning less as a team the
satisfaction of the stakeholders decreased. Having more than one stakeholder means that there
are many voices that are involved in a project. This can become complicated. Project managers
TEAM 3 FINAL PROJECT PAPER 14
need to establish which stakeholders’ interest are the most important. Categories such as power,
influence, impact and urgency are weighted among the stakeholders to see who carries more
weight. This helps the project team to prioritize and establish a clear direction as well as
relationships.
Period One Results
For period one results we sent our team to training resulting in us going over budget so
our score in cost was 0%. Our score for time was good at 81% however our functionality was
only at 46%. We did not meet the milestone this period.
Worst Period Results
This can be a tossup between period 1 and period 8. The milestones were not met for
either period. Although we rank 4th
in period 8 our team score was 56% and functionality was
34%. In period 1 we ranked 5th
but our cost was 0% and functionality was at 46% but time was
better at 81%.
Best Period Results
Period 5 was our best period. The milestone was achieved this period. It was our best
performance in time at 74%, functionality at 82%, stakeholders at 32%, and our best overall
score.
Last Period Results
For the last period we did not meet our milestone. Our functionality and time scores
were low. We consistently did not complete task in the estimated time frame and went over.
Although not our best performance we did managed to move up to rank 4 and we received our
best percentage in cost at 17%
TEAM 3 FINAL PROJECT PAPER 15
Conclusion
There is a lot that goes into project management. Throughout the process we have learned
various things about the planning process and hiring resources as well as what it takes to work as
a team. When closing a project, the team captures the lessons learned. “Lessons learned can be
considered as a useful knowledge gained by project team members as they perform a project and
then reflect on both the process of doing the work and the results that transpired.”[ CITATION
Ana192 l 1033 ]. The biggest learned lesson was the ways to manage the budget. When deciding
the resources, we focused a lot on the skill, experience and education. The rate at which they
would cost and how it might affect the budget was not discussed so much. Had we taking that
into more consideration, we may have done better on the budget. Another lesson learned was in
spending the part of the budget taking managerial actions and on training. Although a mistake,
we underestimated the effect that it would have the budget and ultimately it did not need to be
done. The unallocated resources were another thing that ate away at our budget. We hired
everybody we thought we needed for the project in the beginning instead of hiring them and
letting them as we needed them. This simulation was something knew that neither of us has
done. At our first meeting we were unsure of how to even do it. We all had our strengths and
weaknesses, but we asked questions and relied on one another to see this through. The biggest
lesson learned was gathering an appreciation of the value of teamwork.
References
Anantatmula, V., Kloppenborg, T. J., & Wells, K. N. (2019). Contemporary Project
Management. Boston: Cengage Learning.
Connell, C. (2017). 6 reasons why participation is important [Benefits of
community engagement]. Retrieved July 26, 2019, from social pinpoint
TEAM 3 FINAL PROJECT PAPER 16
website: https://www.socialpinpoint.com/blog/
6-reasons-to-participate-community-engagement/
Duggan, T. (n.d.). What Are the Methods of Measuring Stakeholder Satisfaction. Retrieved
August 15, 2019, from Bright Hub Project Management:
https://www.brighthubpm.com/project-planning/93575-methods-of-measuring-
stakeholder-satisfaction/
Jacoby, J. (2011). How to prioritize stakeholders to ensure a successful change
program. EJ Emergent Journal. Retrieved from
http://blog.emergentconsultants.com/2011/04/18/
how-to-prioritize-stakeholders-to-ensure-a-successful-change-program/
Kloppenborg, T. J., Anantatmuia, V., & Wells, K. N. (2019). Contemporary project
management (4th ed.). Boston, MA: Cengage Learning.
Lucidchart Content Team. (2017, August 28). The 4 phases of the project
management life cycle [Blog post]. Retrieved from Lucidchart website:
https://www.lucidchart.com/blog/
the-4-phases-of-the-project-management-life-cycle
TEAM 3 FINAL PROJECT PAPER 17
Plan risk responses. (2019). Retrieved August 1, 2019, from Project Management
Professional (PMP) website: https://www.greycampus.com/opencampus/
project-management-professional/plan-risk-responses
Tran, L. (2015, April 10). The importance of time management (Aspects of time
management part 1) [Blog post]. Retrieved from InLoox website:
https://www.inloox.com/company/blog/articles/
the-importance-of-time-management-aspects-of-project-management-part-1/
TEAM 3 FINAL PROJECT PAPER 18
Appendix
1. Team 3 Contract
2. Project Schedule – all project activities with all matching WBS numbers
3. Budget Report – with all matching WBS numbers
4. Team Stats Report – Periods 1-8
5. Simulation Report
6. First Period Report
7. Last Period Report
8. Best Period Report
9. Worst Period Report
10. Work Breakdown Structure (WBS) Report – all project activities with WBS numbers
11. Resource Assignment Report
12. Five Clip Art Pieces
TEAM 3 FINAL PROJECT PAPER 19
Tables
Table 1
Organizational Needs
Assessment
$0.00 $20,337.00 $0.00 $20,337.00 $10,540.00 $9,797.00
Identify Consultants $0.00 $14,880.00 $0.00 $14,880.00 $7,040.00 $7,840.00
Hire Consultants $0.00 $14,884.00 $0.00 $14,884.00 $10,800.00 $4,084.00
System Planning $0.00 $3,256.00 $0.00 $3,256.00 $3,120.00 $136.00
Design / Configure
System
$0.00 $18,000.00 $0.00 $18,000.00 $12,720.00 $5,280.00
Implementation $0.00 $60,802.00 $0.00 $60,802.00 $73,520.00 ($12,718.00)
Post Evaluation $0.00 $0.00 $0.00 $0.00 $4,800.00 ($4,800.00)
Project Management $0.00 $68,760.00 $0.00 $68,760.00 $112,000.00 ($43,240.00)
Milestones $0.00 $103,487.00 $0.00 $103,487.00 $25,000.00 $78,487.00
Graphs
Graph 1

More Related Content

What's hot

Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavorImad Alsadeq
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesProject Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesSlideTeam
 
The Role of an Architect
The Role of an ArchitectThe Role of an Architect
The Role of an ArchitectRajesh Raheja
 
Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)pankajsh10
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Supply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in ConstructionSupply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in ConstructionKogan Page
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008ITVAMP, LLC
 
Human Analytics and The Predictive Index May 2010
Human Analytics and The Predictive Index May 2010Human Analytics and The Predictive Index May 2010
Human Analytics and The Predictive Index May 2010Robert Friday
 
PM Notebook - Chapter 8: Quality Management
PM Notebook - Chapter 8: Quality ManagementPM Notebook - Chapter 8: Quality Management
PM Notebook - Chapter 8: Quality ManagementMohammad Elsheimy
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project ManagementKashiff Naveed
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication managementejlp12
 
10.3 Monitor Communication
10.3 Monitor Communication10.3 Monitor Communication
10.3 Monitor CommunicationDavidMcLachlan1
 

What's hot (20)

Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavor
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesProject Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
 
The Role of an Architect
The Role of an ArchitectThe Role of an Architect
The Role of an Architect
 
Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Opm3 050607 hkcs
Opm3 050607 hkcsOpm3 050607 hkcs
Opm3 050607 hkcs
 
Supply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in ConstructionSupply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in Construction
 
Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008Pmo Gap Analysis Sample Itvamp 2008
Pmo Gap Analysis Sample Itvamp 2008
 
Human Analytics and The Predictive Index May 2010
Human Analytics and The Predictive Index May 2010Human Analytics and The Predictive Index May 2010
Human Analytics and The Predictive Index May 2010
 
PM Notebook - Chapter 8: Quality Management
PM Notebook - Chapter 8: Quality ManagementPM Notebook - Chapter 8: Quality Management
PM Notebook - Chapter 8: Quality Management
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
 
10.3 Monitor Communication
10.3 Monitor Communication10.3 Monitor Communication
10.3 Monitor Communication
 

Similar to Final_Team_Project_Simulation_Paper.docx.pdf

The changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docxThe changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docxmattinsonjanel
 
Capstone Using Time Effectively
Capstone Using Time EffectivelyCapstone Using Time Effectively
Capstone Using Time EffectivelyBetty K. Simpson
 
Time Management
Time ManagementTime Management
Time ManagementHKA
 
2014 DeltaV life sciences booth at emerson exchange
2014 DeltaV life sciences booth at emerson exchange2014 DeltaV life sciences booth at emerson exchange
2014 DeltaV life sciences booth at emerson exchangeK. David McKee
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration EstimationHarsh Behl
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET Journal
 
Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016Clint Britt
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Greg Eskridge
 
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...Dr. Amarjeet Singh
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningAmr E. Mohamed
 
Risk Response Plan Paper Grading GuideCPMGT300 Version 10.docx
Risk Response Plan Paper Grading GuideCPMGT300 Version 10.docxRisk Response Plan Paper Grading GuideCPMGT300 Version 10.docx
Risk Response Plan Paper Grading GuideCPMGT300 Version 10.docxSUBHI7
 
Running head REVISION .docx
Running head REVISION                                          .docxRunning head REVISION                                          .docx
Running head REVISION .docxtoltonkendal
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 
12 steps to initiate and plan a successful project
12 steps to initiate and plan a successful project12 steps to initiate and plan a successful project
12 steps to initiate and plan a successful projectProjectPractical.com
 
BUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docx
BUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docxBUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docx
BUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docxjasoninnes20
 
Managing Technical Debt
Managing Technical DebtManaging Technical Debt
Managing Technical DebtAndre Perkins
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET Journal
 

Similar to Final_Team_Project_Simulation_Paper.docx.pdf (20)

The changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docxThe changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docx
 
Capstone Using Time Effectively
Capstone Using Time EffectivelyCapstone Using Time Effectively
Capstone Using Time Effectively
 
Time Management
Time ManagementTime Management
Time Management
 
Time management (sb)
Time management (sb)Time management (sb)
Time management (sb)
 
2014 DeltaV life sciences booth at emerson exchange
2014 DeltaV life sciences booth at emerson exchange2014 DeltaV life sciences booth at emerson exchange
2014 DeltaV life sciences booth at emerson exchange
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites Progress
 
Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08
 
Team Contract
Team ContractTeam Contract
Team Contract
 
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
 
Project Management
Project ManagementProject Management
Project Management
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
Risk Response Plan Paper Grading GuideCPMGT300 Version 10.docx
Risk Response Plan Paper Grading GuideCPMGT300 Version 10.docxRisk Response Plan Paper Grading GuideCPMGT300 Version 10.docx
Risk Response Plan Paper Grading GuideCPMGT300 Version 10.docx
 
Running head REVISION .docx
Running head REVISION                                          .docxRunning head REVISION                                          .docx
Running head REVISION .docx
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
12 steps to initiate and plan a successful project
12 steps to initiate and plan a successful project12 steps to initiate and plan a successful project
12 steps to initiate and plan a successful project
 
BUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docx
BUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docxBUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docx
BUSINESS CASE CAPSTONE2BUSINESS CASE CAPSTONE3.docx
 
Managing Technical Debt
Managing Technical DebtManaging Technical Debt
Managing Technical Debt
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 

More from JomaraCeliaRosellRos

More from JomaraCeliaRosellRos (7)

Final Project presentation.pptx
Final Project presentation.pptxFinal Project presentation.pptx
Final Project presentation.pptx
 
Creatividad Desafío 04 Grupo 04_revJLZO.pdf
Creatividad Desafío 04 Grupo 04_revJLZO.pdfCreatividad Desafío 04 Grupo 04_revJLZO.pdf
Creatividad Desafío 04 Grupo 04_revJLZO.pdf
 
2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf
2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf
2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf
 
Week 2.pptx
Week 2.pptxWeek 2.pptx
Week 2.pptx
 
Week 1.pptx
Week 1.pptxWeek 1.pptx
Week 1.pptx
 
2_2_Event_Mechanism_Chapter_2.pdf
2_2_Event_Mechanism_Chapter_2.pdf2_2_Event_Mechanism_Chapter_2.pdf
2_2_Event_Mechanism_Chapter_2.pdf
 
2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf
2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf
2_1_Fundamentals_Event_Mechanism_Chapter_2.pdf
 

Recently uploaded

Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Toolssoginsider
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.benjamincojr
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdfAlexander Litvinenko
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptjigup7320
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfEr.Sonali Nasikkar
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfSkNahidulIslamShrabo
 
Basics of Relay for Engineering Students
Basics of Relay for Engineering StudentsBasics of Relay for Engineering Students
Basics of Relay for Engineering Studentskannan348865
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligencemahaffeycheryld
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksIJECEIAES
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docxrahulmanepalli02
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxMustafa Ahmed
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New HorizonMorshed Ahmed Rahath
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashidFaiyazSheikh
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxMustafa Ahmed
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024EMMANUELLEFRANCEHELI
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...archanaece3
 
What is Coordinate Measuring Machine? CMM Types, Features, Functions
What is Coordinate Measuring Machine? CMM Types, Features, FunctionsWhat is Coordinate Measuring Machine? CMM Types, Features, Functions
What is Coordinate Measuring Machine? CMM Types, Features, FunctionsVIEW
 

Recently uploaded (20)

Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdf
 
Basics of Relay for Engineering Students
Basics of Relay for Engineering StudentsBasics of Relay for Engineering Students
Basics of Relay for Engineering Students
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
What is Coordinate Measuring Machine? CMM Types, Features, Functions
What is Coordinate Measuring Machine? CMM Types, Features, FunctionsWhat is Coordinate Measuring Machine? CMM Types, Features, Functions
What is Coordinate Measuring Machine? CMM Types, Features, Functions
 

Final_Team_Project_Simulation_Paper.docx.pdf

  • 1. Running head: TEAM 3 FINAL PROJECT PAPER 1 Sim4Project Simulation Auto Supply, Inc. (ASI) – A Complete Redesigned Information System Connie R. Himebaugh, Ashley Jackson & Justin Hughes Davenport University August 15th , 2019 Author Note GPMT287 Principles of Project Management
  • 2. TEAM 3 FINAL PROJECT PAPER 2 Abstract The duration of this Sim4Project simulation, demonstrates how a fictitious company, the case of Auto Supply, Inc. (ASI), redesigned their IT Information Technology System to a better, more functional system for them and for their customers. This company is a regional automotive part supplier whose business has been steadily growing over the past decade, with annual sales of $80 million, ASI discovered that their information system was badly outdated. Team 3 stepped in and in 8 periods, developed a project plan to resolve the issues and set a new IT information in place.
  • 3. TEAM 3 FINAL PROJECT PAPER 3 Table of Contents Abstract............................................................................................................................................2 Auto Supply, Inc. – Project Management Concepts........................................................................5 Project Life Cycle............................................................................................................................5 Initiating.......................................................................................................................................5 Planning/Scheduling....................................................................................................................5 Executing.....................................................................................................................................6 Schedule Management.............................................................................................................6 Triple Constraint......................................................................................................................7 Monitoring and Controlling.........................................................................................................7 Decision-Making.........................................................................................................................8 Conflict Resolution......................................................................................................................9 Cost Variance...............................................................................................................................9 Analysis.....................................................................................................................................10 Team Dynamics.....................................................................................................................10 Functionality..................................................................................................................................11 Organization...............................................................................................................................11 Resource Allocation.......................................................................................................................12 Time Management Skills...........................................................................................................12
  • 4. TEAM 3 FINAL PROJECT PAPER 4 Effective Time Management......................................................................................................12 Stakeholder Satisfaction................................................................................................................12 Period One Results....................................................................................................................14 Worst Period Results..................................................................................................................14 Best Period Results....................................................................................................................14 Last Period Results....................................................................................................................14 Conclusion.....................................................................................................................................15 References......................................................................................................................................15 Appendix........................................................................................................................................18 Tables.........................................................................................................................................19 Graphs........................................................................................................................................19
  • 5. TEAM 3 FINAL PROJECT PAPER 5 Auto Supply, Inc. – Project Management Concepts The GPMT287 Project Management students from Team 3, organized and produced a project plan life cycle which provided selecting and initiating resources for work in the simulation. Planned each period, selected workers to the appropriate tasks, submitted in Sims for status results compared to 5 other teams, constructed charts, graphs, and reports, then finalized the project with statistical recognition and observation, and closed the IT project at completion. Project Life Cycle Initiating Team 3 sat down and discussed the problems that Auto Supply Inc. lacked in the IT Information System that was not satisfactorily producing adequate results. The customers were complaining that their order were getting mixed up from paper copies, and that they never received a revised fax if the order changed. To construct a more efficient system, a computer information system that allowed invoicing at the time of call in intake, packaging, organizing and storing, down to the loading the trucks and deliveries. Quality assurance and a more efficient way of processing these orders in a timely fashion was desperately needed. Therefore, Team 3 agreed and signed a contract including these measures and it was signed. Selecting and initiating begins when the idea for a project first develops and the project is selected and planned with the team committed to the project and its stages (Kloppenborg, Anantatmuia, & Wells, 2019, p. 7). Planning/Scheduling Scheduling is the process of managing the time constraints of the project from beginning to end. It takes teamwork, identification of the problem, then defining the problem and selecting a project manager to get the scope in perspective. It is planning and processing that a whole team
  • 6. TEAM 3 FINAL PROJECT PAPER 6 gets involved with. Therefore, the project manager hires a team of professionals to do their part in the overall steps that it takes to get the job done. Planning begins right after the initial obligation by the members and includes the detail plans, and ends when all the members have accepted the entire detailed plan as discussed in the meetings (Kloppenborg, Anantatmuia, & Wells, 2019, p. 8). Team three did a Sim4Project pre-play and this allowed our team to get familiar with the Sims simulation and how it works. Executing After thoughtful considerations, our team 3 worked together and hired simulated workers throughout our simulation that consisted of these 9 resource categories: Hardware Analyst, Jr. Systems Analyst, MIS Manager, Network Design Consultant, Office Engineer, Programmer, Project Manager, Sr. Systems Analyst, and Systems Software Engineer. To execute the plan after acceptance, the plan includes authorizing, executing, monitoring, and controlling work until the customers or the project purpose has been accepted and is approved to move forward with the budget in mind (Kloppenborg, Anantatmuia, & Wells, 2019, p. 8). Each period 1-8, an updated project plan was posted to gain knowledge of what the current stats were and how to proceed choosing the tasks for the next period and for which workers. A timeline shows which worker had what job to do, how long the job is to take, and an expected finish date. Schedule Management Our class participation as a team, consisting of two girls and one boy, worked to achieve making Sim4Project selections by reading each task for that period and hiring one of the workers from the project to complete that task within a specified time frame, not to go over budget. Some workers had to be fired due to too many hired for the same purpose and title, and for cost reasons. Did not need them for that amount of money. We started out with a beginning balance of
  • 7. TEAM 3 FINAL PROJECT PAPER 7 $270,000 in pre-play and within each end period results, we could see the report results and what place we came in comparted to that of the other 5 teams. Triple Constraint It is the combination of the three most significant restrictions in this project that includes scope, schedule, and cost – such a addressing the “triple constraint” and why this concept imposes a higher level of accountability than most jobs (Kloppenborg, Anantatmuia, & Wells, 2019, p. 14). Therefore, as what team three did, to review all aspects of project of Auto Supply, Inc. (ASI), as a project manager, it is imperative to understand the performance levels of these constraints including quality, time, and budget to take precedence and to make a strong commitment to (Kloppenborg, Anantatmuia, & Wells, 2019, p. 15). Team three review the instructions, downloaded the appetitive software needed, reviewed requirements, instructions, and started team building skills right away. Sim4Project simulation is a competitive software that enables a group to compete with other teams. From there, we signed a team contract committed to the project, appendix¹. Monitoring and Controlling This step aligns the activities in a project in a series to help track, review, and document the continued progress and making sure it meets performance objectives as outlined in the plan (Kloppenborg, Anantatmuia, & Wells, 2019, p. 460). When we think of monitoring, this refers to review the progress and capture project performance data along with referencing the project plan (Kloppenborg, Anantatmuia, & Wells, 2019, p. 460). The objective is to see how the development and performance measures and that of good communication during that time, to have control assessing the actual performance (Kloppenborg, Anantatmuia, & Wells, 2019, p. 460). A project manager keeps the project under control with an action and keeping that revised
  • 8. TEAM 3 FINAL PROJECT PAPER 8 at each meeting, that way those meeting minutes and posted revisions can be viewed by each member at any given time between meetings. Closing Closing a project is the very last step in the project and is a very important one. It is the final phase, or the administration phase, and cannot be completed until everything else in the project tasks has taken place (Kloppenborg, Anantatmuia, & Wells, 2019, p. 515). To do so, gathering and storing lessons learned, writing reports, and updating project documents, even though it is a possibility that a conclusion has been reached or not (Kloppenborg, Anantatmuia, & Wells, 2019, p. 515). The project manager is usually the one to close the project with said date and time. Project Budget Decision-Making What went well was decision making for the tasks. What didn’t work well was not everyone in the team participated at all times and the important decisions were not made by all involved that hurt the team. It is important that all team members work equally and not rely on other team members to do all the work while they sit back and do absolutely nothing. Managerial Actions were taken throughout the simulation, and these affected the project in significant ways and those that were associated to them as team three went along during the project. The beginning budget was $270,000 to start knowing that we had to stretch that over 8 period worth of planning and executing. The decisions were amongst three team members deciding which worker to be appointed to which task for that period. We conversed through our team discussion board, or by email, phone, or cell texting for an adequate decision before that particular period
  • 9. TEAM 3 FINAL PROJECT PAPER 9 tasks were selected and then submitted. For each period, a team leader, which Connie took charge of and made sure that all decisions were in, and that the Sims and Stats were submitted on time. Connie planned meetings in the beginning of the project to make sure everyone was on board and that we understood what was to be expected of each of us. Making task decisions in Sims was probably the most difficult because it determined how it would affect the progress of the team company and making sure that all the workers’ jobs were done in a timely fashion. Our budget report indicated our period report for each period, Appendix². Conflict Resolution Once a project manager sees that there is a conflict within the project, he or she might try and find a better solution before it escalates into a bigger problem (Kloppenborg, Anantatmuia, & Wells, 2019, p. 163). One of the situations within this team is not seeing that all members of the team were on board initially and that caused stress and uncertainties to the members that were a tentative. The project coordinator, Connie sent out emails to the other member asking if they have received any emails from the group and to check and make sure that in fact they were viewing the correct email inbox and included the instructor on the email. That did help getting the non-participant’s attention and their participation began shortly thereafter. Cost Variance As stated above the beginning budget for this project was $270,000 by the end of period 8, we had exceeded that budget by $34,406. A few things contributed to this. In period 1 we mistakenly spent $55,616 on training and $290 on managerial actions, this brought our total cost to $85,603, that was 31% of our budget gone. We learned from that and didn’t spend money on training or managerial actions for the remaining periods. From there our money problems went towards unallocated cost and work overage. Because our actual work hours were so much more
  • 10. TEAM 3 FINAL PROJECT PAPER 10 than the estimated work, we ended up spending even more money. Cost variance is the difference between earned value and actual cost, which reflects performance (Kloppenborg, Anantatmuia, & Wells, 2019, p. 478). Based on our cost variance, we did poorly in this regard. We tried to lower the cost by having our resources work only half the time. However, this proved to be fruitless as we still did not make up the budget. That being said, even with the cost variance being so high we would have remained in budget if did not spend the $55, 616 on training, actually leaving us with $21, 500 in the budget, graph¹. Analysis Reporting is essential within this project as each period contains analysis with live data pertaining to the team as a result of the end of a period simulation. The stats report indicates how we did each period in comparison to the other teams, appendix³. Team Dynamics The virtual team in Sims allowed us to really experience what it is like to do a project as a team. It allowed us to use managerial skills, perception skills, team building skills, ethical behaviors utilized, and analytical thinking. It takes a lot of organizational skills to keep everyone on track to get the project done and to stay focused. Six reasons why team participation is so important is: Your opinion is important, More perspectives, New information, Community benefit/ownership, It feels good, and A Numbers game, meaning the total number of members in the project (Connell, 2017). Definitely time management skills were needed and affective to keep up with the simulation and what workers to hire, who to fire, who to do what job and for how long, sometimes a worker was given half, 50% the allotted time to complete the job, splitting that very same job with another worker so that they can also work as a team. Striving for more
  • 11. TEAM 3 FINAL PROJECT PAPER 11 efficiency was the goal in that and to meet our milestones and deadlines at the same time. Both keeping cost down and meeting our milestones was our main focus in this project. Functionality Functionality organization in an organization and in a project structure is which a staff is grouped by areas of specialization, the project manager has limited authority to assign work and apply resources (Kloppenborg, Anantatmuia, & Wells, 2019, p. 103). The function manager controls the project budget, makes most of the decisions, and is primarily the one coordinating project communication amongst the other team members (Kloppenborg, Anantatmuia, & Wells, 2019, p. 103). The functionality in project management is whether or not the team is achieving its attended purpose. To figure this out you take the estimated time and divided it by the actual time. The higher the percentage the better the chance of the project doing what it is intended. By the end of period 8 our teams’ functionality was at 35%, this means our project has a low chance of completing its task. Our best performance was in period 5 where the functionality was at 82%. The difference in these two performances has to do with the work variance. For period 8 we went over our estimated hours of work by 72 hours, in period 5 we went over by 66 hours. Organization Unity comes to mind when thinking of organization. Team three has unity when all team members show equal interest and participates in an equal manner of all work involved. In the Sims project, allocating other virtual team members allowed us to gain more people within our team, even though they could not communicate with us, it was realistic enough to assume they were present and getting their work done accordingly. The organizational needs assessment table shows the system breakdown, table¹.
  • 12. TEAM 3 FINAL PROJECT PAPER 12 Resource Allocation Resource allocation is defined in MS Project that allows us to understand of who and what resources are being used that includes five steps: Defining resources, Setting up a resource calendar, Assigning resources, Identifying over allocated resources, Dealing with over allocations (Kloppenborg, Anantatmuia, & Wells, 2019, p. 311). Time Management Skills The importance of time management is the capability to organize and plan the amount of time to spend in an activity or activities in one given day. The result of that is good time management. It could increase effectiveness and the overall productivity, and by planning ahead and setting goals your overall performance will be more rewarding. Prioritizing is best in this situation. Effective Time Management To work more efficiently that if at all, utilize work that can be done in less time without stress of the project. Some suggestions are: Avoid distractions, Make a task list of priorities, Estimate and track time accordingly, and create and follow a schedule (Tran, 2015). Stakeholder Satisfaction Stakeholders are groups or people that have a certain level of investment in a project. These can include people who work on the project, people who provide the resources, customers and even local, state or federal governments who may be affected. “To ensure the success of their projects, project managers should initially identify all the people or groups that have the potential
  • 13. TEAM 3 FINAL PROJECT PAPER 13 to affect the work in progress, either positively or negatively” [ CITATION Dug19 l 1033 ]One of the best ways to identify stakeholders is to ask the simple questions, “who will use, will be affected by, or could impact this project. For this simulation team 3 had to oversee the project for Auto Supply, Inc in redesigning their information technology system to better communicate. In this case the stakeholders would be the owners, managers, the employees, the vendors, software and hardware engineers, IT specialist, and the customers. Team 3 started period 1 with a stakeholder satisfaction of 59%. This score depends on several things, the time, cost and functionality scores as well the skills and management style of the team and whether the milestones were met. At the end of period 8 the score had dropped to 34%. Table 1 Period 1 Statistics Name Time Cost Functionality Stakeholder Overall Rank Team 3 81 0 46 59 5 5 Table 2 Period 8 Statistics Name Time Cost Functionality Stakeholder Overall Rank Team 3 56 17 35 34 16 4 Looking at these two tables you can see how the time and functionality scores affected the stakeholders. Because we weren’t keeping good time and functioning less as a team the satisfaction of the stakeholders decreased. Having more than one stakeholder means that there are many voices that are involved in a project. This can become complicated. Project managers
  • 14. TEAM 3 FINAL PROJECT PAPER 14 need to establish which stakeholders’ interest are the most important. Categories such as power, influence, impact and urgency are weighted among the stakeholders to see who carries more weight. This helps the project team to prioritize and establish a clear direction as well as relationships. Period One Results For period one results we sent our team to training resulting in us going over budget so our score in cost was 0%. Our score for time was good at 81% however our functionality was only at 46%. We did not meet the milestone this period. Worst Period Results This can be a tossup between period 1 and period 8. The milestones were not met for either period. Although we rank 4th in period 8 our team score was 56% and functionality was 34%. In period 1 we ranked 5th but our cost was 0% and functionality was at 46% but time was better at 81%. Best Period Results Period 5 was our best period. The milestone was achieved this period. It was our best performance in time at 74%, functionality at 82%, stakeholders at 32%, and our best overall score. Last Period Results For the last period we did not meet our milestone. Our functionality and time scores were low. We consistently did not complete task in the estimated time frame and went over. Although not our best performance we did managed to move up to rank 4 and we received our best percentage in cost at 17%
  • 15. TEAM 3 FINAL PROJECT PAPER 15 Conclusion There is a lot that goes into project management. Throughout the process we have learned various things about the planning process and hiring resources as well as what it takes to work as a team. When closing a project, the team captures the lessons learned. “Lessons learned can be considered as a useful knowledge gained by project team members as they perform a project and then reflect on both the process of doing the work and the results that transpired.”[ CITATION Ana192 l 1033 ]. The biggest learned lesson was the ways to manage the budget. When deciding the resources, we focused a lot on the skill, experience and education. The rate at which they would cost and how it might affect the budget was not discussed so much. Had we taking that into more consideration, we may have done better on the budget. Another lesson learned was in spending the part of the budget taking managerial actions and on training. Although a mistake, we underestimated the effect that it would have the budget and ultimately it did not need to be done. The unallocated resources were another thing that ate away at our budget. We hired everybody we thought we needed for the project in the beginning instead of hiring them and letting them as we needed them. This simulation was something knew that neither of us has done. At our first meeting we were unsure of how to even do it. We all had our strengths and weaknesses, but we asked questions and relied on one another to see this through. The biggest lesson learned was gathering an appreciation of the value of teamwork. References Anantatmula, V., Kloppenborg, T. J., & Wells, K. N. (2019). Contemporary Project Management. Boston: Cengage Learning. Connell, C. (2017). 6 reasons why participation is important [Benefits of community engagement]. Retrieved July 26, 2019, from social pinpoint
  • 16. TEAM 3 FINAL PROJECT PAPER 16 website: https://www.socialpinpoint.com/blog/ 6-reasons-to-participate-community-engagement/ Duggan, T. (n.d.). What Are the Methods of Measuring Stakeholder Satisfaction. Retrieved August 15, 2019, from Bright Hub Project Management: https://www.brighthubpm.com/project-planning/93575-methods-of-measuring- stakeholder-satisfaction/ Jacoby, J. (2011). How to prioritize stakeholders to ensure a successful change program. EJ Emergent Journal. Retrieved from http://blog.emergentconsultants.com/2011/04/18/ how-to-prioritize-stakeholders-to-ensure-a-successful-change-program/ Kloppenborg, T. J., Anantatmuia, V., & Wells, K. N. (2019). Contemporary project management (4th ed.). Boston, MA: Cengage Learning. Lucidchart Content Team. (2017, August 28). The 4 phases of the project management life cycle [Blog post]. Retrieved from Lucidchart website: https://www.lucidchart.com/blog/ the-4-phases-of-the-project-management-life-cycle
  • 17. TEAM 3 FINAL PROJECT PAPER 17 Plan risk responses. (2019). Retrieved August 1, 2019, from Project Management Professional (PMP) website: https://www.greycampus.com/opencampus/ project-management-professional/plan-risk-responses Tran, L. (2015, April 10). The importance of time management (Aspects of time management part 1) [Blog post]. Retrieved from InLoox website: https://www.inloox.com/company/blog/articles/ the-importance-of-time-management-aspects-of-project-management-part-1/
  • 18. TEAM 3 FINAL PROJECT PAPER 18 Appendix 1. Team 3 Contract 2. Project Schedule – all project activities with all matching WBS numbers 3. Budget Report – with all matching WBS numbers 4. Team Stats Report – Periods 1-8 5. Simulation Report 6. First Period Report 7. Last Period Report 8. Best Period Report 9. Worst Period Report 10. Work Breakdown Structure (WBS) Report – all project activities with WBS numbers 11. Resource Assignment Report 12. Five Clip Art Pieces
  • 19. TEAM 3 FINAL PROJECT PAPER 19 Tables Table 1 Organizational Needs Assessment $0.00 $20,337.00 $0.00 $20,337.00 $10,540.00 $9,797.00 Identify Consultants $0.00 $14,880.00 $0.00 $14,880.00 $7,040.00 $7,840.00 Hire Consultants $0.00 $14,884.00 $0.00 $14,884.00 $10,800.00 $4,084.00 System Planning $0.00 $3,256.00 $0.00 $3,256.00 $3,120.00 $136.00 Design / Configure System $0.00 $18,000.00 $0.00 $18,000.00 $12,720.00 $5,280.00 Implementation $0.00 $60,802.00 $0.00 $60,802.00 $73,520.00 ($12,718.00) Post Evaluation $0.00 $0.00 $0.00 $0.00 $4,800.00 ($4,800.00) Project Management $0.00 $68,760.00 $0.00 $68,760.00 $112,000.00 ($43,240.00) Milestones $0.00 $103,487.00 $0.00 $103,487.00 $25,000.00 $78,487.00 Graphs Graph 1