SlideShare a Scribd company logo
1 of 36
Anthony Fang
Kirsten Rice
Viv Pitter
Ryan Williams
Jeremy Molayem
WATER SUPPLY AND
SEWER SYSTEM DESIGN
ZONE
AREAS
A
 Residential
 Area: 66.281 acres
 Population Density: 40 people/acre
 Population: 2652 people
 Industrial
 Area: 3.2881 acres
 Population Density: 20 people/acre
 Population: 66 people
 Commercial
 Area: 5.3375 acres
 Use: 10 hours per weekday
ZONE POPULATION
I. WATER SUPPLY
SYSTEM
 Residential
 Average consumption: 2.652 x 105 gpd
 Peak day consumption: 5.304 x 105 gpd
 Peak hour consumption: 1.608 x 106 gpd
 Industrial
 Weekday consumption: 1.44 x 106 gal/day
 Peak hour consumption:1.8 x 105 gal/hr
 Commercial
 Average flow rate: 17.5 gpm
 Peak day flow rate: 35 gpm
DEMAND
 Fire flow is calculated based on the equation
NFF=(Oi)(Ci)[1.0+(X+P)i]
Q = 5200 gpm (10 hour duration) = 3.124 x 106 gpd
 Total flow for max day and Fire flow
Qtotal = 2.38x106 + 3.124x106 = 5.50 x 106 gpd
FIRE FLOW
WATER DISTRIBUTION MAP WITH OUTFALLS
DISTRIBUTION LAYOUT
 System B – Pumping station to major center of demand with
an elevated storage tank between the supply and demand
 Average Day = 1.7 mgd.
 Max Day = 1.7 mgd x 1.5 = 2.55 mgd
 Peak hour = 2.55 mgd x 1.5 = 3.83 mgd
 Max day + Fire flow = 5.5 mgd
DISTRIBUTION STORAGE
DISTRIBUTION STORAGE
Demand Rate Calculation Pumping Head
Average Day (1.7 mgd) 115 + (0.67 x 19) 128 ft
Max. Day. (2.55 mgd) 115 + (1.42 x 19) 142 ft
Max. Hour. (3.83 mgd) 115 + (3.0 x 19) 172 ft
Max day + fire = (5.5
mgd)
115 + (6.1 x 19) 231 ft
 Total Length of Pipe ~ 19,000 feet
 Pipe Material = ductile iron (C = 140)
 Diameter: 12-14 in
 Water Tower Head – 310 ft
 Pump Head – 305 ft
 Worst Case: Pump Failure
 Pressure low: 28.84 psi, high: 40.21 psi
PIPING SYSTEM INFORMATION
 HP=QxH/(3960*n)
 Q= 3606 GPM
 H=305ft
 n=65%
 HP=427.28
 500 HP pump needed.
 Two pumps (one standby)
PUMP DESIGN
 Fire hydrants are to be located 300 feet apart on each street
and 150 feet apart in high value zones.
FIRE HYDRANT LOCATIONS
II. SEWER SYSTEM
SEWER DESIGN
 For Commercial and Residential
 25 F.U. => 40 gpm x 3 (Restaurants) = 120 gpm
 10 F.U. => 30 gpm x 2 (Offices) = 60 gpm
 Total = 180 gpm
 For Industry = (3000gpm) x (70%) = 2100 gpm
 For Residential = (Max Hourly Use) x 70% = Sewage Flow
SEWER DESIGN
 Summary
SEWER DESIGN
Pipe Material PVC
Min. Velocity 2 ft/s
Max Velocity 10 ft/s
Roughness (n) 0.015
Min Ground Cover 6 ft
Percentage Full 50%
Min. Pipe Diameter 8 in.
Max Pipe Diameter 50 in
Max Velocity (Actual) 7.7 ft/s
Max Depth 22 ft.
III. STORMWATER
SYSTEM
STORM DATA
Duration, Min Intensity, In/Hr
5 7
10 5.5
15 5
20 4.3
25 3.9
30 3.75
35 3.5
40 3.35
45 3.2
50 3.15
55 3.125
60 3.1
STORM SEWER DESIGN
Design Criteria Value (Minimum) Value (Maximum)
Flow Velocity 3 ft/s 15 ft/s
Slope 0.02% 10%
Depth of Cover 5 ft below surface N/A
Diameter 1 ft N/A
Roughness Coefficient N/A N = 0.013
Capacity* N/A ¾, 0.75
Horizontal Distance from
Drinking Water Lines**
10 ft N/A
Vertical Distance from
Utilities**
1 ft
Pipe Material PVC for Diameter les
*ratio of flow depth to full depth
**from Haestad Methods, Stormwater Conveyance Modeling and Design
Design Restrictions
•Hydraulic Gradient Line should be below surface elevation at all times.
•Curved Storm Sewers are unacceptable (maintenance problems)
Depth of cover should be at least 5 ft in order to prevent crushing of pipes due to loads.
CONDUITS EXCEEDING DESIGN CAPACITY
CONDUITS OVERCAPACITY AT 21 INCHES
CONDUITS OVERCAPACITY AT 24 INCHES
CONDUITS OVERCAPACITY AT 27 INCHES
DESIGN SATISFIED, ALL CAPACITY < 0.75
DESIGN CRITERION: 3FPS < VELOCITY <15FPS
DESIGN CRITERION, 0.2% < SLOPE <10%
CONDUIT DIAMETER
CONDUIT FLOW
HYDRAULIC PROFILES
HYDRAULIC PROFILES
HYDRAULIC PROFILES
SUMMARY
Pipe Material PVC or Reinforced Concrete (D>1ft)
Min. Velocity 3.72fps
Max. Velocity 12.3fps
Roughness n=0.013
Min Ground Cover 5ft
Max Capacity 75% fullness
Min. Pipe Diameter 12inches
Max. Pipe Diameter 27inches
Max Depth 22ft
 Worst Case Scenario
 Pump Failure, distribution only from water tower
 Water tower height 310 ft
 Pump head = 0 ft
 Pressure
 High- 40.21 psi
 Low- 28.84 psi
DISTRIBUTION DESIGN (SCENARIO 1)
 Water Tower Failure, supply only from pump
 Water tower head = 0 ft
 Pump head = 305 ft
 Pressure
 High: 44.99 psi
 Low: 30.52 psi
DISTRIBUTION DESIGN (SCENARIO 2)
 Best Case
 Elevated Storage Tank -310 ft
 Pumping Reservoir- Total head about 305 ft
 Pressure-
 High- 45.89 psi
 Low- 33.01 psi
DISTRIBUTION DESIGN (SCENARIO 3)

More Related Content

What's hot

sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
Manish Goyal
 
House connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipesHouse connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipes
krishnacp
 

What's hot (20)

Collection of sewage, Types,Components & Layout
Collection of sewage, Types,Components & LayoutCollection of sewage, Types,Components & Layout
Collection of sewage, Types,Components & Layout
 
Laying, jointing and testing of pipes
Laying, jointing and testing of pipesLaying, jointing and testing of pipes
Laying, jointing and testing of pipes
 
L 2 sources and water supply schemes
L 2 sources and water supply schemesL 2 sources and water supply schemes
L 2 sources and water supply schemes
 
Types of traps
Types of trapsTypes of traps
Types of traps
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage system
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Water demand/Waterrequirements
Water demand/Waterrequirements Water demand/Waterrequirements
Water demand/Waterrequirements
 
Building services water supply
Building services   water supplyBuilding services   water supply
Building services water supply
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
TRAPS AND ITS TYPES USED IN A BUILDING
TRAPS AND ITS TYPES USED IN A  BUILDING TRAPS AND ITS TYPES USED IN A  BUILDING
TRAPS AND ITS TYPES USED IN A BUILDING
 
Ee 2
Ee 2Ee 2
Ee 2
 
Sewer joint
Sewer jointSewer joint
Sewer joint
 
Transmission of water
Transmission of waterTransmission of water
Transmission of water
 
Storm water drainage
Storm water drainageStorm water drainage
Storm water drainage
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
House connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipesHouse connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipes
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
 
SEWERAGE SYSTEMS ppt by mayank oza
SEWERAGE SYSTEMS ppt by mayank ozaSEWERAGE SYSTEMS ppt by mayank oza
SEWERAGE SYSTEMS ppt by mayank oza
 
Water supply final
Water supply finalWater supply final
Water supply final
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design report
 

Viewers also liked

Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimation
Vijay Kumar
 
Dm p lhosp(1)
Dm p lhosp(1)Dm p lhosp(1)
Dm p lhosp(1)
bhattbhai
 
Cold water supply
Cold water supplyCold water supply
Cold water supply
Ar Eyla
 
CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)
KYUYOUNG HAN
 
What is the difference between sewage and drainage
What is the difference between sewage and drainageWhat is the difference between sewage and drainage
What is the difference between sewage and drainage
Naresh Kuruba
 

Viewers also liked (20)

Sewerage design
Sewerage designSewerage design
Sewerage design
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Sewerage network
Sewerage networkSewerage network
Sewerage network
 
WATER SUPPLY SYSTEM
WATER SUPPLY SYSTEM WATER SUPPLY SYSTEM
WATER SUPPLY SYSTEM
 
Sewrage
Sewrage Sewrage
Sewrage
 
02 water demand
02 water demand02 water demand
02 water demand
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage discharge
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimation
 
Water demand forecasting
Water demand forecastingWater demand forecasting
Water demand forecasting
 
Plumbing training
Plumbing training Plumbing training
Plumbing training
 
Sewage Conveyance and Pumping
Sewage Conveyance and PumpingSewage Conveyance and Pumping
Sewage Conveyance and Pumping
 
Cold water supply and pipe sizing
Cold water supply and pipe sizingCold water supply and pipe sizing
Cold water supply and pipe sizing
 
plumber
plumberplumber
plumber
 
Dm p lhosp(1)
Dm p lhosp(1)Dm p lhosp(1)
Dm p lhosp(1)
 
Cold water supply
Cold water supplyCold water supply
Cold water supply
 
Sewerage Infrastructure under Greater Kuala Lumpur / Klang Valley Initiatives
Sewerage Infrastructure under Greater Kuala Lumpur / Klang Valley InitiativesSewerage Infrastructure under Greater Kuala Lumpur / Klang Valley Initiatives
Sewerage Infrastructure under Greater Kuala Lumpur / Klang Valley Initiatives
 
PLUMBING YSTEM
PLUMBING YSTEMPLUMBING YSTEM
PLUMBING YSTEM
 
CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)
 
What is the difference between sewage and drainage
What is the difference between sewage and drainageWhat is the difference between sewage and drainage
What is the difference between sewage and drainage
 
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
 

Similar to Water Supply and Sewerage Design

Protec zld based on ltd system 2
Protec zld based on ltd system 2Protec zld based on ltd system 2
Protec zld based on ltd system 2
mohager4a
 
Apec workshop 2 presentation 6 1 compression and transport apec
Apec workshop 2 presentation 6 1  compression and transport apecApec workshop 2 presentation 6 1  compression and transport apec
Apec workshop 2 presentation 6 1 compression and transport apec
Global CCS Institute
 
TECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITY
TECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITYTECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITY
TECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITY
iQHub
 
334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx
BatuhanKse1
 
Landscape Irrigation
Landscape Irrigation Landscape Irrigation
Landscape Irrigation
wademurray7
 

Similar to Water Supply and Sewerage Design (20)

Protec zld based on ltd system 2
Protec zld based on ltd system 2Protec zld based on ltd system 2
Protec zld based on ltd system 2
 
Final presentation
Final presentationFinal presentation
Final presentation
 
Pseudo Dry Gas System
Pseudo Dry Gas SystemPseudo Dry Gas System
Pseudo Dry Gas System
 
Apec workshop 2 presentation 6 1 compression and transport apec
Apec workshop 2 presentation 6 1  compression and transport apecApec workshop 2 presentation 6 1  compression and transport apec
Apec workshop 2 presentation 6 1 compression and transport apec
 
TECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITY
TECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITYTECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITY
TECHNOLOGY FOR HIGH YIELD IMPROVEMENT IN PRODUCED WATER QUALITY
 
334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx
 
BerbariGeorge.pdf
BerbariGeorge.pdfBerbariGeorge.pdf
BerbariGeorge.pdf
 
Designing of sprinkler irrigation system
Designing of sprinkler irrigation systemDesigning of sprinkler irrigation system
Designing of sprinkler irrigation system
 
Covertura Jumbo DL 320.pdf
Covertura Jumbo DL 320.pdfCovertura Jumbo DL 320.pdf
Covertura Jumbo DL 320.pdf
 
HYPER-X sludge evaporating dryer
HYPER-X sludge evaporating dryerHYPER-X sludge evaporating dryer
HYPER-X sludge evaporating dryer
 
11wiik
11wiik11wiik
11wiik
 
Kelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in ColomboKelani River Water Treatment Plant in Colombo
Kelani River Water Treatment Plant in Colombo
 
Senior Capstone Final
Senior Capstone FinalSenior Capstone Final
Senior Capstone Final
 
TIM SERIES Paddle Wheel Flow Meter & Totalizer
TIM SERIES Paddle Wheel Flow Meter & TotalizerTIM SERIES Paddle Wheel Flow Meter & Totalizer
TIM SERIES Paddle Wheel Flow Meter & Totalizer
 
Screw press.pptx
Screw press.pptxScrew press.pptx
Screw press.pptx
 
Water Mist Systems - Akshay Jangam.
Water Mist Systems - Akshay Jangam. Water Mist Systems - Akshay Jangam.
Water Mist Systems - Akshay Jangam.
 
TIP SERIES Flow Rate Meter & Flow Total Meter with RS-485
TIP SERIES Flow Rate Meter & Flow Total Meter with RS-485TIP SERIES Flow Rate Meter & Flow Total Meter with RS-485
TIP SERIES Flow Rate Meter & Flow Total Meter with RS-485
 
Drip design ppt.
Drip design ppt.Drip design ppt.
Drip design ppt.
 
Landscape Irrigation
Landscape Irrigation Landscape Irrigation
Landscape Irrigation
 
The Value of Air Leakage Testing in Large Commercial Buildings
The Value of Air Leakage Testing in Large Commercial BuildingsThe Value of Air Leakage Testing in Large Commercial Buildings
The Value of Air Leakage Testing in Large Commercial Buildings
 

Recently uploaded

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

Water Supply and Sewerage Design

  • 1. Anthony Fang Kirsten Rice Viv Pitter Ryan Williams Jeremy Molayem WATER SUPPLY AND SEWER SYSTEM DESIGN
  • 3.  Residential  Area: 66.281 acres  Population Density: 40 people/acre  Population: 2652 people  Industrial  Area: 3.2881 acres  Population Density: 20 people/acre  Population: 66 people  Commercial  Area: 5.3375 acres  Use: 10 hours per weekday ZONE POPULATION
  • 5.  Residential  Average consumption: 2.652 x 105 gpd  Peak day consumption: 5.304 x 105 gpd  Peak hour consumption: 1.608 x 106 gpd  Industrial  Weekday consumption: 1.44 x 106 gal/day  Peak hour consumption:1.8 x 105 gal/hr  Commercial  Average flow rate: 17.5 gpm  Peak day flow rate: 35 gpm DEMAND
  • 6.  Fire flow is calculated based on the equation NFF=(Oi)(Ci)[1.0+(X+P)i] Q = 5200 gpm (10 hour duration) = 3.124 x 106 gpd  Total flow for max day and Fire flow Qtotal = 2.38x106 + 3.124x106 = 5.50 x 106 gpd FIRE FLOW
  • 7. WATER DISTRIBUTION MAP WITH OUTFALLS
  • 9.  System B – Pumping station to major center of demand with an elevated storage tank between the supply and demand  Average Day = 1.7 mgd.  Max Day = 1.7 mgd x 1.5 = 2.55 mgd  Peak hour = 2.55 mgd x 1.5 = 3.83 mgd  Max day + Fire flow = 5.5 mgd DISTRIBUTION STORAGE
  • 10. DISTRIBUTION STORAGE Demand Rate Calculation Pumping Head Average Day (1.7 mgd) 115 + (0.67 x 19) 128 ft Max. Day. (2.55 mgd) 115 + (1.42 x 19) 142 ft Max. Hour. (3.83 mgd) 115 + (3.0 x 19) 172 ft Max day + fire = (5.5 mgd) 115 + (6.1 x 19) 231 ft
  • 11.  Total Length of Pipe ~ 19,000 feet  Pipe Material = ductile iron (C = 140)  Diameter: 12-14 in  Water Tower Head – 310 ft  Pump Head – 305 ft  Worst Case: Pump Failure  Pressure low: 28.84 psi, high: 40.21 psi PIPING SYSTEM INFORMATION
  • 12.  HP=QxH/(3960*n)  Q= 3606 GPM  H=305ft  n=65%  HP=427.28  500 HP pump needed.  Two pumps (one standby) PUMP DESIGN
  • 13.  Fire hydrants are to be located 300 feet apart on each street and 150 feet apart in high value zones. FIRE HYDRANT LOCATIONS
  • 16.  For Commercial and Residential  25 F.U. => 40 gpm x 3 (Restaurants) = 120 gpm  10 F.U. => 30 gpm x 2 (Offices) = 60 gpm  Total = 180 gpm  For Industry = (3000gpm) x (70%) = 2100 gpm  For Residential = (Max Hourly Use) x 70% = Sewage Flow SEWER DESIGN
  • 17.  Summary SEWER DESIGN Pipe Material PVC Min. Velocity 2 ft/s Max Velocity 10 ft/s Roughness (n) 0.015 Min Ground Cover 6 ft Percentage Full 50% Min. Pipe Diameter 8 in. Max Pipe Diameter 50 in Max Velocity (Actual) 7.7 ft/s Max Depth 22 ft.
  • 19. STORM DATA Duration, Min Intensity, In/Hr 5 7 10 5.5 15 5 20 4.3 25 3.9 30 3.75 35 3.5 40 3.35 45 3.2 50 3.15 55 3.125 60 3.1
  • 20. STORM SEWER DESIGN Design Criteria Value (Minimum) Value (Maximum) Flow Velocity 3 ft/s 15 ft/s Slope 0.02% 10% Depth of Cover 5 ft below surface N/A Diameter 1 ft N/A Roughness Coefficient N/A N = 0.013 Capacity* N/A ¾, 0.75 Horizontal Distance from Drinking Water Lines** 10 ft N/A Vertical Distance from Utilities** 1 ft Pipe Material PVC for Diameter les *ratio of flow depth to full depth **from Haestad Methods, Stormwater Conveyance Modeling and Design Design Restrictions •Hydraulic Gradient Line should be below surface elevation at all times. •Curved Storm Sewers are unacceptable (maintenance problems) Depth of cover should be at least 5 ft in order to prevent crushing of pipes due to loads.
  • 25. DESIGN SATISFIED, ALL CAPACITY < 0.75
  • 26. DESIGN CRITERION: 3FPS < VELOCITY <15FPS
  • 27. DESIGN CRITERION, 0.2% < SLOPE <10%
  • 33. SUMMARY Pipe Material PVC or Reinforced Concrete (D>1ft) Min. Velocity 3.72fps Max. Velocity 12.3fps Roughness n=0.013 Min Ground Cover 5ft Max Capacity 75% fullness Min. Pipe Diameter 12inches Max. Pipe Diameter 27inches Max Depth 22ft
  • 34.  Worst Case Scenario  Pump Failure, distribution only from water tower  Water tower height 310 ft  Pump head = 0 ft  Pressure  High- 40.21 psi  Low- 28.84 psi DISTRIBUTION DESIGN (SCENARIO 1)
  • 35.  Water Tower Failure, supply only from pump  Water tower head = 0 ft  Pump head = 305 ft  Pressure  High: 44.99 psi  Low: 30.52 psi DISTRIBUTION DESIGN (SCENARIO 2)
  • 36.  Best Case  Elevated Storage Tank -310 ft  Pumping Reservoir- Total head about 305 ft  Pressure-  High- 45.89 psi  Low- 33.01 psi DISTRIBUTION DESIGN (SCENARIO 3)