Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and
Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
โ€œSelection of suitable highway construction project
delivery method by multiple criteria decision-making
frameworkโ€
Thesis Supervisor: Dr. Khurram Iqbal Ahmad Khan
Department of Construction Engineering and Management
NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad
G.E.C. Members: 1. Dr. Abdur Rehman Nasir
Department of Construction Engineering and Management,
NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad.
2. Lect. Muhammad Hasnain
Department of Construction Engineering and Management,
NIT, National University of Sciences and Technology (NUST), Islamabad
Final Defense Presentation
by
Zeeshan Ul Hassan
NUST2016 MSCE&M00000170739
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Introduction of Student
1. Name Zeeshan Ul Hassan
2. Reg No. NUST 2016 MSCE&M 00000170739
3. Discipline /Department
Construction Engineering & Management
(NIT), SCEE
4. Date of Admission in MS Program September 2016
5. Coursework CGPA 3.33 / 4.00
6.
Previous Qualification
B.Sc. Civil Engineering 3.24/4.00 NUST, H-12
F.Sc. (Pre Engineering) 1st Div F.G Degree College Wah Cantt
Matric (Sciences) 1st Div Sir Syed College Wah Cantt
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method
by multiple criteria decision making framework
1. Introduction
2. Literature Review
3. Research Methodology
4. Data Analysis and Results
5. Conclusions & Recommendations
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Study background
โ€ข A project delivery system is the one in which owner and contractor
are contractually bound to have certain predetermined conditions
to carry forward the project (An et al., 2018).
โ€ข No absolute project delivery method is universally suitable for all
kind of projects and it depends on the condition and nature or
project (Mahdi and Alreshaid, 2005) .
โ€ข In one research it has been investigated that design-build method
offers greater price certainty and reduced cost growth than
design-bid-build (Shrestha et al., 2011).
โ€ข (Tran et al., 2013) found out from case study that the design-build
is optimal project delivery method for a bridge replacement
project
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Study background
โ€ข Most highway infrastructure projects in Australia, Canada, New
Zealand, Sweden, the UK and the US adopt a common delivery
model known as the โ€˜traditional modelโ€™, or Design-Bid Build (DBB)
(Pakkala, 2002).
โ€ข Other than cost growth, the entire schedule related merits of
DBB are superior than the DB project delivery method after
analyzing 67 globally construction projects. (Hale et al., 2009)
(Ibbs et al., 2003).
โ€ข In another research it has been cited that Design Build is
effective with comparative to Design Bid Build by analyzing
in eight different categories. (Hyun et al., 2008)
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Study background
โ€ข It has been set up that the construction speed per lane of Highway
project using design Build is faster than design bid build(Shrestha
et al., 2011).
โ€ข After analysis for risk assessment it has been found out that
traditional DBB is risk averse in comparison to other types of
project delivery method (Tran and Molenaar, 2015).
โ€ข Selection of projected delivery is perceived at the designing phase
so the selection should be appropriate for the project success.
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Problem statement
โ€ข Factors such as cost control, Risk allocation, and schedule
compression are effected by selection of project delivery
method (Touran et al. , 2011).
โ€ข Amongst the many reasons of project failures, selection of
inappropriate Project Delivery Method is one of them (Jaafari .,
2001) (Moon et al. , 2011) .
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Research objectives
โ€ข To identify the factors affecting selection of
project delivery method.
โ€ข To prioritize the project delivery methods for
highway projects using Multi Criteria Decision
Making approach
โ€ข Develop a framework for the selection of
appropriate project delivery methods
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Different project delivery methods
Four types of project delivery methods were found in the study are as follow;
โ€ข Design Bid/Build (DBB)
โ€ข Design/Build (DB)
โ€ข Public Private Partnership (PPP)
โ€ข Construction management at risk (CMA)
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Literature Review
โ€ข Majority of US highway projects are built by DBB delivery method (Beard et
al., 2001).
โ€ข The nature of project determines the appropriate project delivery method, like
for bridge construction DB is best and the same is horrible for its maintenance
(Park and Kwak, 2017).
โ€ข . Fuzzy numbers (FN) most often used are triangular FN, trapezoidal FN and
Gaussian FN.
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Factors Identification
โ€ข 38 factors are gathered from 24 research papers which are further
summarized from content analysis to have precise information.
โ€ข Google Survey Form
โ€ข Based on their analysis of literature and respondent from preliminary
questionnaire, significance of factors is calculated to develop final
questionnaire for data collection.
โ€ข The TOPSIS method uses n-dimensional Euclidean
distance to rank the alternatives on the basis
of their distance from ideal solution
(Opricovic and Tzeng, 2004).
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Factors
โ€ข Design characteristics
Regulatory
โ€ข Project size and
โ€ข Complexity.
โ€ข Coordination and
โ€ข Project Location
โ€ข Construction quality
โ€ข Complexity of decision
making
โ€ข Cost saving
โ€ข Contractor input in
design
โ€ข Contractor
characteristics
โ€ข Risk allocation
โ€ข Time reduction
โ€ข Design quality
โ€ข Technology availability
โ€ข Schedule
โ€ข Quality
โ€ข Risk
โ€ข Culture
โ€ข Uniqueness
โ€ข Size of Project
โ€ข Scope of Project
โ€ข Disputes
โ€ข Contractorโ€™s capability
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Preliminary
study
Detailed
Literature
Review
Research gap Problem statement Research objectives
Identification of factors
effecting selection of
project delivery method
Literature review
Data
Collection
Data
Analysis
and
Results
Content Analysis / Preliminary
Survey
Development of
questionnaire for survey
Data Analysis through
Fuzzy TOPSIS
Data collection
Development of
Framework for PDM
selection
Validation
Expert Opinion/
Sensitivity test
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Why TOPSISโ€ฆ
โ€ข TOPSIS method used linear normalization and consider the Euclidean distance from
positive and negative ideal solution (Opricovic and Tzeng, 2004).
โ€ข For Large scale project including so many number of factors and alternatives,
pairwise comparison like AHP is a cumbersome problem, where TOPSIS takes the
lead. (Junior et al. , 2014)
โ€ข In a case study on already constructed dams, TOPSIS was more reliable as compare
to AHP because the top four recommended locations for dam from AHP were never
constructed. (Jozaghi et al., 2018).
โ€ข Analysis with addition of another alternative of the same rating has changed the
order preference of supplier selection using Fuzzy AHP, while the results remains
same using Fuzzy TOPSIS (Junior et al., 2014)
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Fuzzy TOPSIS
1. Assigning alternatives and criteria corresponding to each
other in a matrix to correlate.
2. Normalization.
3. Assigning weightages to different project delivery methods
from user input.
4. Multiplication of normalized performance value and the
weightage criteria of that criteria.
5. Ideal best and ideal worst value is determined.
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Fuzzy TOPSIS
6. Euclidean distance of ideal best and ideal worst value.
๐‘†๐‘—+ =
๐‘—=1
๐‘š
๐‘‰๐‘–๐‘— โˆ’ ๐‘‰
๐‘—
+ 2
๐‘†๐‘—โˆ’ =
๐‘—=1
๐‘š
๐‘‰๐‘–๐‘— โˆ’ ๐‘‰
๐‘—
โˆ’ 2
7. Assign ranking to the available alternatives according to
their importance
๐‘ƒ๐‘– =
๐‘†๐‘–โˆ’
๐‘†๐‘–โˆ’+ ๐‘†๐‘–+
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Proposed framework approach:
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
Objectives Tools & Techniques Sources
โ€ข To identify the factors effecting
selection of project delivery method.
๏ƒผ Literature review
๏ƒผ Research papers
๏ƒผ Reports
๏ƒผ Articles
๏ƒผ Thesis
๏ƒผ Books
โ€ข To prioritize the project delivery
methods for highway projects using
MCDM approach
๏ฑ Questionnaire
survey
๏ฑ Expert opinion
๏ƒผ Research papers
๏ƒผ Thesis
๏ฑ Experts opinion
๏ฑ Technical professionals/
practitioners
โ€ข Develop a framework for the
selection of appropriate project
delivery methods
๏ฑ Fuzzy TOPSIS
๏ฑ Questionnaire
๏ฑ Expert opinion
๏ฑ Experts opinion
๏ฑ Technical professionals/
practitioners
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Research Methodology
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
โ€ข https://docs.google.com/forms/d/1z5sfO2tQ5ma5n4AP7iaIvOVRGIP_r
bN8giEoKolKCqE/edit
โ€ข Final Questionnaire consist of 12 factors and results shows the impact
of those factors for each type of 4 type project delivery method.
โ€ข Data Analysis
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Weightages of the Factors
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Weightages Factors
0.1145 Project Schedule and its Importance
0.1115 Project Complexity and Initial Risk
0.1097 Project Cost
0.0859 Project Construction Quality Assurance
0.0856 Owner Experience and Attribute
0.0839 Construction and Managerial Risk
0.0758 Scope of Project and its Clarity
0.0723 Owner Involvement and Control Over Design
0.0684 Design Quality
0.0653 Cost Variation Probability
0.0643 Experience and Capability of Contractor
0.0627 Client In-house Resources
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Distribution of Factors
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Cost Project Schedule and its Importance
Cost Project Complexity and Initial Risk
Cost Project Cost
Benefit Project Construction Quality Assurance
Benefit Owner Experience and Attribute
Cost Construction and Managerial Risk
Cost Scope of Project and its Clarity
Benefit Owner Involvement and Control Over Design
Benefit Design Quality
Cost Cost Variation Probability
Benefit Experience and Capability of Contractor
Benefit Client In-house Resources
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Fuzzy TOPSIS
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
โ€ข MCDM technique Fuzzy TOPSIS is applied on the
results obtained from the respondent.
โ€ข Normalization of Score
โ€ข Weighted Normalized Score
โ€ข Fuzzy Positive and Negative Ideal Solution
โ€ข Closeness coefficient
โ€ข Ranking of the alternatives
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Fuzzy TOPSIS
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Framework for the selection of Project Delivery method
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
Conclusions
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
โ€ข Based on the analysis and data collected from the
respondents Design Build is found to be most
relevant factor for the selection of Project Delivery
method specific to Highway Projects in Pakistan.
โ€ข Time duration for the project is the main
determining factor for choosing the type of project
delivery method for Highway Projects.
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
References:
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
โ€ข AN, X., WANG, Z., LI, H. & DING, J. 2018. Project Delivery System Selection with Interval-Valued Intuitionistic Fuzzy Set Group
Decision-Making Method. Group Decision and Negotiation, 27, 689-707.
โ€ข MAHDI, I. M. & ALRESHAID, K. 2005. Decision support system for selecting the proper project delivery method using analytical
hierarchy process (AHP). International journal of project management, 23, 564-572.
โ€ข SHRESTHA, P. P., Oโ€™CONNOR, J. T. & GIBSON JR, G. E. 2011. Performance comparison of large design-build and design-bid-build
highway projects. Journal of construction engineering and management, 138, 1-13.
โ€ข TRAN, D. Q., HARPER, C. M., MOLENAAR, K. R., HADDAD, N. F. & SCHOLFIELD, M. M. 2013. Project delivery selection matrix for
highway design and construction. Transportation Research Record, 2347, 3-10.
โ€ข OPRICOVIC, S. & TZENG, G.-H. 2004. Compromise solution by MCDM methods: A comparative analysis of VIKOR and TOPSIS. European
journal of operational research, 156, 445-455.
โ€ข PAKKALA, P. 2002. Innovative project delivery methods for infrastructure. Finnish Road Enterprise, Helsinki, 19.
โ€ข CREEDY, G. D., SKITMORE, M. & WONG, J. K. 2010. Evaluation of risk factors leading to cost overrun in delivery of highway
construction projects. Journal of construction engineering and management, 136, 528-537.
โ€ข HALE, D. R., SHRESTHA, P. P., GIBSON JR, G. E. & MIGLIACCIO, G. C. 2009. Empirical comparison of design/build and design/bid/build
project delivery methods. Journal of construction engineering and management, 135, 579-587.
โ€ข IBBS, C. W., KWAK, Y. H., NG, T. & ODABASI, A. M. 2003. Project delivery systems and project change: Quantitative analysis. Journal of
construction engineering and management, 129, 382-387.
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
Selection of suitable highway construction project delivery method by multiple criteria decision
making framework
References:
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering
(SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.
โ€ข HYUN, C., CHO, K., KOO, K., HONG, T. & MOON, H. 2008. Effect of delivery methods on design performance in multifamily housing
projects. Journal of construction engineering and management, 134, 468-482.
โ€ข PARK, J. & KWAK, Y. H. 2017. Design-bid-build (DBB) vs. design-build (DB) in the US public transportation projects: The choice and
consequences. International Journal of Project Management, 35, 280-295.
โ€ข BEARD, J., LOULAKIS, E. M. & WUNDRAM, E. 2001. Design-build: Planning through development, McGraw Hill Professional.
โ€ข TRAN, D. Q. & MOLENAAR, K. R. 2015. Risk-based project delivery selection model for highway design and construction. Journal of
construction engineering and management, 141, 04015041.
โ€ข JOZAGHI, A., ALIZADEH, B., HATAMI, M., FLOOD, I., KHORRAMI, M., KHODAEI, N. & GHASEMI TOUSI, E. 2018. A Comparative Study of
the AHP and TOPSIS Techniques for Dam Site Selection Using GIS: A Case Study of Sistan and Baluchestan Province, Iran. Geosciences,
8, 494.
โ€ข JUNIOR, F. R. L., OSIRO, L. & CARPINETTI, L. C. R. 2014. A comparison between Fuzzy AHP and Fuzzy TOPSIS methods to supplier
selection. Applied Soft Computing, 21, 194-209.
โ€ข Jaafari, A. (2001). Management of risks, uncertainties and opportunities on projects: time for a fundamental shift. International
journal of project management, 19(2), 89-101.
โ€ข Whitaker, R. (2007). Validation examples of the analytic hierarchy process and analytic network process. Mathematical and Computer
Modelling, 46(7-8), 840-859.
โ€ข Moon, H., Cho, K., Hong, T., & Hyun, C. (2011). Selection model for delivery methods for multifamily-housing construction
projects. Journal of Management in Engineering, 27(2), 106-115.
โ€ข Touran, A., Gransberg, D. D., Molenaar, K. R., & Ghavamifar, K. (2011). Selection of project delivery method in transit: Drivers and
objectives. Journal of Management in Engineering, 27(1), 21-27
Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE),
National University of Sciences and Technology (NUST), Islamabad, Pakistan
THANK YOU

More Related Content

Similar to presentation.pptx

Chi Yao Resume (construction Management)
Chi Yao Resume (construction Management)Chi Yao Resume (construction Management)
Chi Yao Resume (construction Management)
Chi (Claire) Yao
ย 
Modeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projectsModeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projects
Gafel Kareem
ย 
Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...
Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...
Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...
ijtsrd
ย 
CV-toLinkedIn
CV-toLinkedInCV-toLinkedIn
CV-toLinkedIn
Dr Pandey
ย 
Project Research Proposal Design of 4.5km road
Project Research Proposal  Design of 4.5km  roadProject Research Proposal  Design of 4.5km  road
Project Research Proposal Design of 4.5km road
Syed Hazoor Ali Shah
ย 
FWD_paper_IJPEfinal
FWD_paper_IJPEfinalFWD_paper_IJPEfinal
FWD_paper_IJPEfinal
omar elbagalati
ย 
project poster presentation
project poster presentationproject poster presentation
project poster presentation
Hafiz Ahmed Waqas
ย 

Similar to presentation.pptx (20)

20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
ย 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
ย 
A review of Design and Construction Parameters of Pavements
A review of Design and Construction Parameters of PavementsA review of Design and Construction Parameters of Pavements
A review of Design and Construction Parameters of Pavements
ย 
Faisalcv1
Faisalcv1Faisalcv1
Faisalcv1
ย 
Analysis and Design of Box Underpass Bridge Using Software
Analysis and Design of Box Underpass Bridge Using SoftwareAnalysis and Design of Box Underpass Bridge Using Software
Analysis and Design of Box Underpass Bridge Using Software
ย 
Resume msr amin
Resume msr aminResume msr amin
Resume msr amin
ย 
Chi Yao Resume (construction Management)
Chi Yao Resume (construction Management)Chi Yao Resume (construction Management)
Chi Yao Resume (construction Management)
ย 
" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "
ย 
Muhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CVMuhammad Asad Shaheen - CV
Muhammad Asad Shaheen - CV
ย 
Modeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projectsModeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projects
ย 
Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...
Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...
Design and Analysis of Pre Cast Box Segment using Limit State Method Manually...
ย 
CV-toLinkedIn
CV-toLinkedInCV-toLinkedIn
CV-toLinkedIn
ย 
Fuel assessment and design of public transportation model by using movement b...
Fuel assessment and design of public transportation model by using movement b...Fuel assessment and design of public transportation model by using movement b...
Fuel assessment and design of public transportation model by using movement b...
ย 
20320140507006 2-3
20320140507006 2-320320140507006 2-3
20320140507006 2-3
ย 
20320140507006
2032014050700620320140507006
20320140507006
ย 
Sensor Placement based on FE Modal Analysis: Dynamic Characteristic of Cable ...
Sensor Placement based on FE Modal Analysis: Dynamic Characteristic of Cable ...Sensor Placement based on FE Modal Analysis: Dynamic Characteristic of Cable ...
Sensor Placement based on FE Modal Analysis: Dynamic Characteristic of Cable ...
ย 
IRJET- A Review: Design, Analysis & Optimization of Drag Chain Conveyer
IRJET- A Review: Design, Analysis & Optimization of Drag Chain ConveyerIRJET- A Review: Design, Analysis & Optimization of Drag Chain Conveyer
IRJET- A Review: Design, Analysis & Optimization of Drag Chain Conveyer
ย 
Project Research Proposal Design of 4.5km road
Project Research Proposal  Design of 4.5km  roadProject Research Proposal  Design of 4.5km  road
Project Research Proposal Design of 4.5km road
ย 
FWD_paper_IJPEfinal
FWD_paper_IJPEfinalFWD_paper_IJPEfinal
FWD_paper_IJPEfinal
ย 
project poster presentation
project poster presentationproject poster presentation
project poster presentation
ย 

More from IrfanAwan25

cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
IrfanAwan25
ย 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
IrfanAwan25
ย 
Progress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxProgress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptx
IrfanAwan25
ย 
Progress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxProgress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptx
IrfanAwan25
ย 
product-development-roadmap-template.pptx
product-development-roadmap-template.pptxproduct-development-roadmap-template.pptx
product-development-roadmap-template.pptx
IrfanAwan25
ย 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
IrfanAwan25
ย 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
ย 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
IrfanAwan25
ย 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
IrfanAwan25
ย 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
ย 

More from IrfanAwan25 (11)

cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
ย 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
ย 
Progress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxProgress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptx
ย 
Das HSE.ppt
Das HSE.pptDas HSE.ppt
Das HSE.ppt
ย 
Progress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxProgress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptx
ย 
product-development-roadmap-template.pptx
product-development-roadmap-template.pptxproduct-development-roadmap-template.pptx
product-development-roadmap-template.pptx
ย 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
ย 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
ย 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
ย 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
ย 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
ย 

Recently uploaded

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
sivaprakash250
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 

Recently uploaded (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
ย 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
ย 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
ย 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
ย 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
ย 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
ย 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
ย 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
ย 

presentation.pptx

  • 1. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. โ€œSelection of suitable highway construction project delivery method by multiple criteria decision-making frameworkโ€ Thesis Supervisor: Dr. Khurram Iqbal Ahmad Khan Department of Construction Engineering and Management NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad G.E.C. Members: 1. Dr. Abdur Rehman Nasir Department of Construction Engineering and Management, NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad. 2. Lect. Muhammad Hasnain Department of Construction Engineering and Management, NIT, National University of Sciences and Technology (NUST), Islamabad Final Defense Presentation by Zeeshan Ul Hassan NUST2016 MSCE&M00000170739 Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 2. Introduction of Student 1. Name Zeeshan Ul Hassan 2. Reg No. NUST 2016 MSCE&M 00000170739 3. Discipline /Department Construction Engineering & Management (NIT), SCEE 4. Date of Admission in MS Program September 2016 5. Coursework CGPA 3.33 / 4.00 6. Previous Qualification B.Sc. Civil Engineering 3.24/4.00 NUST, H-12 F.Sc. (Pre Engineering) 1st Div F.G Degree College Wah Cantt Matric (Sciences) 1st Div Sir Syed College Wah Cantt Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 3. Selection of suitable highway construction project delivery method by multiple criteria decision making framework 1. Introduction 2. Literature Review 3. Research Methodology 4. Data Analysis and Results 5. Conclusions & Recommendations Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 4. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Study background โ€ข A project delivery system is the one in which owner and contractor are contractually bound to have certain predetermined conditions to carry forward the project (An et al., 2018). โ€ข No absolute project delivery method is universally suitable for all kind of projects and it depends on the condition and nature or project (Mahdi and Alreshaid, 2005) . โ€ข In one research it has been investigated that design-build method offers greater price certainty and reduced cost growth than design-bid-build (Shrestha et al., 2011). โ€ข (Tran et al., 2013) found out from case study that the design-build is optimal project delivery method for a bridge replacement project Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 5. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Study background โ€ข Most highway infrastructure projects in Australia, Canada, New Zealand, Sweden, the UK and the US adopt a common delivery model known as the โ€˜traditional modelโ€™, or Design-Bid Build (DBB) (Pakkala, 2002). โ€ข Other than cost growth, the entire schedule related merits of DBB are superior than the DB project delivery method after analyzing 67 globally construction projects. (Hale et al., 2009) (Ibbs et al., 2003). โ€ข In another research it has been cited that Design Build is effective with comparative to Design Bid Build by analyzing in eight different categories. (Hyun et al., 2008) Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 6. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Study background โ€ข It has been set up that the construction speed per lane of Highway project using design Build is faster than design bid build(Shrestha et al., 2011). โ€ข After analysis for risk assessment it has been found out that traditional DBB is risk averse in comparison to other types of project delivery method (Tran and Molenaar, 2015). โ€ข Selection of projected delivery is perceived at the designing phase so the selection should be appropriate for the project success. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 7. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Problem statement โ€ข Factors such as cost control, Risk allocation, and schedule compression are effected by selection of project delivery method (Touran et al. , 2011). โ€ข Amongst the many reasons of project failures, selection of inappropriate Project Delivery Method is one of them (Jaafari ., 2001) (Moon et al. , 2011) . Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 8. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Research objectives โ€ข To identify the factors affecting selection of project delivery method. โ€ข To prioritize the project delivery methods for highway projects using Multi Criteria Decision Making approach โ€ข Develop a framework for the selection of appropriate project delivery methods Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan Selection of suitable highway construction project delivery method by multiple criteria decision making framework
  • 9. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Different project delivery methods Four types of project delivery methods were found in the study are as follow; โ€ข Design Bid/Build (DBB) โ€ข Design/Build (DB) โ€ข Public Private Partnership (PPP) โ€ข Construction management at risk (CMA) Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 10. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Literature Review โ€ข Majority of US highway projects are built by DBB delivery method (Beard et al., 2001). โ€ข The nature of project determines the appropriate project delivery method, like for bridge construction DB is best and the same is horrible for its maintenance (Park and Kwak, 2017). โ€ข . Fuzzy numbers (FN) most often used are triangular FN, trapezoidal FN and Gaussian FN. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 11. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Factors Identification โ€ข 38 factors are gathered from 24 research papers which are further summarized from content analysis to have precise information. โ€ข Google Survey Form โ€ข Based on their analysis of literature and respondent from preliminary questionnaire, significance of factors is calculated to develop final questionnaire for data collection. โ€ข The TOPSIS method uses n-dimensional Euclidean distance to rank the alternatives on the basis of their distance from ideal solution (Opricovic and Tzeng, 2004). Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 12. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Factors โ€ข Design characteristics Regulatory โ€ข Project size and โ€ข Complexity. โ€ข Coordination and โ€ข Project Location โ€ข Construction quality โ€ข Complexity of decision making โ€ข Cost saving โ€ข Contractor input in design โ€ข Contractor characteristics โ€ข Risk allocation โ€ข Time reduction โ€ข Design quality โ€ข Technology availability โ€ข Schedule โ€ข Quality โ€ข Risk โ€ข Culture โ€ข Uniqueness โ€ข Size of Project โ€ข Scope of Project โ€ข Disputes โ€ข Contractorโ€™s capability Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 13. Preliminary study Detailed Literature Review Research gap Problem statement Research objectives Identification of factors effecting selection of project delivery method Literature review Data Collection Data Analysis and Results Content Analysis / Preliminary Survey Development of questionnaire for survey Data Analysis through Fuzzy TOPSIS Data collection Development of Framework for PDM selection Validation Expert Opinion/ Sensitivity test Selection of suitable highway construction project delivery method by multiple criteria decision making framework
  • 14. Why TOPSISโ€ฆ โ€ข TOPSIS method used linear normalization and consider the Euclidean distance from positive and negative ideal solution (Opricovic and Tzeng, 2004). โ€ข For Large scale project including so many number of factors and alternatives, pairwise comparison like AHP is a cumbersome problem, where TOPSIS takes the lead. (Junior et al. , 2014) โ€ข In a case study on already constructed dams, TOPSIS was more reliable as compare to AHP because the top four recommended locations for dam from AHP were never constructed. (Jozaghi et al., 2018). โ€ข Analysis with addition of another alternative of the same rating has changed the order preference of supplier selection using Fuzzy AHP, while the results remains same using Fuzzy TOPSIS (Junior et al., 2014) Selection of suitable highway construction project delivery method by multiple criteria decision making framework
  • 15. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Fuzzy TOPSIS 1. Assigning alternatives and criteria corresponding to each other in a matrix to correlate. 2. Normalization. 3. Assigning weightages to different project delivery methods from user input. 4. Multiplication of normalized performance value and the weightage criteria of that criteria. 5. Ideal best and ideal worst value is determined. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 16. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Fuzzy TOPSIS 6. Euclidean distance of ideal best and ideal worst value. ๐‘†๐‘—+ = ๐‘—=1 ๐‘š ๐‘‰๐‘–๐‘— โˆ’ ๐‘‰ ๐‘— + 2 ๐‘†๐‘—โˆ’ = ๐‘—=1 ๐‘š ๐‘‰๐‘–๐‘— โˆ’ ๐‘‰ ๐‘— โˆ’ 2 7. Assign ranking to the available alternatives according to their importance ๐‘ƒ๐‘– = ๐‘†๐‘–โˆ’ ๐‘†๐‘–โˆ’+ ๐‘†๐‘–+ Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 17. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Proposed framework approach: Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Objectives Tools & Techniques Sources โ€ข To identify the factors effecting selection of project delivery method. ๏ƒผ Literature review ๏ƒผ Research papers ๏ƒผ Reports ๏ƒผ Articles ๏ƒผ Thesis ๏ƒผ Books โ€ข To prioritize the project delivery methods for highway projects using MCDM approach ๏ฑ Questionnaire survey ๏ฑ Expert opinion ๏ƒผ Research papers ๏ƒผ Thesis ๏ฑ Experts opinion ๏ฑ Technical professionals/ practitioners โ€ข Develop a framework for the selection of appropriate project delivery methods ๏ฑ Fuzzy TOPSIS ๏ฑ Questionnaire ๏ฑ Expert opinion ๏ฑ Experts opinion ๏ฑ Technical professionals/ practitioners Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 18. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Research Methodology Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan โ€ข https://docs.google.com/forms/d/1z5sfO2tQ5ma5n4AP7iaIvOVRGIP_r bN8giEoKolKCqE/edit โ€ข Final Questionnaire consist of 12 factors and results shows the impact of those factors for each type of 4 type project delivery method. โ€ข Data Analysis
  • 19. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Weightages of the Factors Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan Weightages Factors 0.1145 Project Schedule and its Importance 0.1115 Project Complexity and Initial Risk 0.1097 Project Cost 0.0859 Project Construction Quality Assurance 0.0856 Owner Experience and Attribute 0.0839 Construction and Managerial Risk 0.0758 Scope of Project and its Clarity 0.0723 Owner Involvement and Control Over Design 0.0684 Design Quality 0.0653 Cost Variation Probability 0.0643 Experience and Capability of Contractor 0.0627 Client In-house Resources
  • 20. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Distribution of Factors Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan Cost Project Schedule and its Importance Cost Project Complexity and Initial Risk Cost Project Cost Benefit Project Construction Quality Assurance Benefit Owner Experience and Attribute Cost Construction and Managerial Risk Cost Scope of Project and its Clarity Benefit Owner Involvement and Control Over Design Benefit Design Quality Cost Cost Variation Probability Benefit Experience and Capability of Contractor Benefit Client In-house Resources
  • 21. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Fuzzy TOPSIS Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan โ€ข MCDM technique Fuzzy TOPSIS is applied on the results obtained from the respondent. โ€ข Normalization of Score โ€ข Weighted Normalized Score โ€ข Fuzzy Positive and Negative Ideal Solution โ€ข Closeness coefficient โ€ข Ranking of the alternatives
  • 22. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Fuzzy TOPSIS Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 23. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Framework for the selection of Project Delivery method Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 24. Selection of suitable highway construction project delivery method by multiple criteria decision making framework Conclusions Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan โ€ข Based on the analysis and data collected from the respondents Design Build is found to be most relevant factor for the selection of Project Delivery method specific to Highway Projects in Pakistan. โ€ข Time duration for the project is the main determining factor for choosing the type of project delivery method for Highway Projects.
  • 25. Selection of suitable highway construction project delivery method by multiple criteria decision making framework References: Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. โ€ข AN, X., WANG, Z., LI, H. & DING, J. 2018. Project Delivery System Selection with Interval-Valued Intuitionistic Fuzzy Set Group Decision-Making Method. Group Decision and Negotiation, 27, 689-707. โ€ข MAHDI, I. M. & ALRESHAID, K. 2005. Decision support system for selecting the proper project delivery method using analytical hierarchy process (AHP). International journal of project management, 23, 564-572. โ€ข SHRESTHA, P. P., Oโ€™CONNOR, J. T. & GIBSON JR, G. E. 2011. Performance comparison of large design-build and design-bid-build highway projects. Journal of construction engineering and management, 138, 1-13. โ€ข TRAN, D. Q., HARPER, C. M., MOLENAAR, K. R., HADDAD, N. F. & SCHOLFIELD, M. M. 2013. Project delivery selection matrix for highway design and construction. Transportation Research Record, 2347, 3-10. โ€ข OPRICOVIC, S. & TZENG, G.-H. 2004. Compromise solution by MCDM methods: A comparative analysis of VIKOR and TOPSIS. European journal of operational research, 156, 445-455. โ€ข PAKKALA, P. 2002. Innovative project delivery methods for infrastructure. Finnish Road Enterprise, Helsinki, 19. โ€ข CREEDY, G. D., SKITMORE, M. & WONG, J. K. 2010. Evaluation of risk factors leading to cost overrun in delivery of highway construction projects. Journal of construction engineering and management, 136, 528-537. โ€ข HALE, D. R., SHRESTHA, P. P., GIBSON JR, G. E. & MIGLIACCIO, G. C. 2009. Empirical comparison of design/build and design/bid/build project delivery methods. Journal of construction engineering and management, 135, 579-587. โ€ข IBBS, C. W., KWAK, Y. H., NG, T. & ODABASI, A. M. 2003. Project delivery systems and project change: Quantitative analysis. Journal of construction engineering and management, 129, 382-387. Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • 26. Selection of suitable highway construction project delivery method by multiple criteria decision making framework References: Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. โ€ข HYUN, C., CHO, K., KOO, K., HONG, T. & MOON, H. 2008. Effect of delivery methods on design performance in multifamily housing projects. Journal of construction engineering and management, 134, 468-482. โ€ข PARK, J. & KWAK, Y. H. 2017. Design-bid-build (DBB) vs. design-build (DB) in the US public transportation projects: The choice and consequences. International Journal of Project Management, 35, 280-295. โ€ข BEARD, J., LOULAKIS, E. M. & WUNDRAM, E. 2001. Design-build: Planning through development, McGraw Hill Professional. โ€ข TRAN, D. Q. & MOLENAAR, K. R. 2015. Risk-based project delivery selection model for highway design and construction. Journal of construction engineering and management, 141, 04015041. โ€ข JOZAGHI, A., ALIZADEH, B., HATAMI, M., FLOOD, I., KHORRAMI, M., KHODAEI, N. & GHASEMI TOUSI, E. 2018. A Comparative Study of the AHP and TOPSIS Techniques for Dam Site Selection Using GIS: A Case Study of Sistan and Baluchestan Province, Iran. Geosciences, 8, 494. โ€ข JUNIOR, F. R. L., OSIRO, L. & CARPINETTI, L. C. R. 2014. A comparison between Fuzzy AHP and Fuzzy TOPSIS methods to supplier selection. Applied Soft Computing, 21, 194-209. โ€ข Jaafari, A. (2001). Management of risks, uncertainties and opportunities on projects: time for a fundamental shift. International journal of project management, 19(2), 89-101. โ€ข Whitaker, R. (2007). Validation examples of the analytic hierarchy process and analytic network process. Mathematical and Computer Modelling, 46(7-8), 840-859. โ€ข Moon, H., Cho, K., Hong, T., & Hyun, C. (2011). Selection model for delivery methods for multifamily-housing construction projects. Journal of Management in Engineering, 27(2), 106-115. โ€ข Touran, A., Gransberg, D. D., Molenaar, K. R., & Ghavamifar, K. (2011). Selection of project delivery method in transit: Drivers and objectives. Journal of Management in Engineering, 27(1), 21-27 Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan

Editor's Notes

  1. ANOVA test and t-test would validate the results.
  2. ANOVA test and t-test would validate the results.