International
OPEN ACCESS Journal
Of Modern Engineering Research (IJMER)
| IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss. 3 | Mar. 2014 | 45 |
Line of Balance
P. A. Badukale1
, Prof. Syed. Sabihuddin2
I. Introduction
In different types of construction companies different methods are used for different projects. As the
requirement of a project the method like critical path method (CPM), linear scheduling method (LSM), and line
of balance (LOB) are applied on it.
The construction industry currently utilizes the Critical Path Method scheduling technique (CPM) to
plan and manage most construction projects. This phenomenon is depicted in a study conducted by Tavakoli and
Riachi in 1990. In their study, they surveyed the use of CPM scheduling in the top ENR 400 contractors.
For the past three decades, numerous researchers have identified the various intrinsic advantages of the
Line of Balance scheduling technique (LOB) in comparison to the CPM. The concept of finding a critical path is
another major fundamental difference between LOB and CPM scheduling. Arditi, Tokdemir, and Suh (2001)
explained how “In network analysis, at least one critical path exists. Activities which are on the critical path
have to be started and completed by their assigned times if the total project duration is not to be extended.” The
LOB scheduling methods criticalness is based on time and resources, unlike network scheduling where it is only
based on time.
The LOB method allows the team to deliver at its maximum speed, by helping balance the different
activities in the production chain. In keeping with the idea of using the team‟s actual performance, we also
propose to derive the lead-times for the so called “control points”, not from an activity network as in the
original LOB formulation, but from the team‟s “velocity”. Line of Balance (LOB) is a method of showing the
repetitive work that may exist in a project as a single line on a graph. Unlike a Bar Chart, which shows the
duration of a particular activity, a LOB Chart shows the rate at which the work that makes up all of the activities
has to be undertaken to stay on schedule, the relationship of one trade or process to the subsequent trade or
process is defined by the space between the lines. If one group is running behind schedule, it will impact on the
following group and this is shown by the lines intersecting.
The Line-of-Balance then would have a series of stair step offsets. Making those decisions is the job of
the management team. Once the Bedding, Laying of Pipe, and Testing of the 1st segment to done, then the
Backfill can begin and work continuously. However, the difficulties in using the LOB for scheduling projects
have been stripped off from the method when authors have downplayed problems that surround the definition of
task durations, the choice of the repetitive unit or batch size, cycle time, and the definition of buffers between
tasks.
II. Line Of Balance
A simple diagram in which line shows location and time at which a certain crew will be working on a
given operation is known as LOB. it is used on repetitive work such as constructing multiple dwelling units,
when used on linear work such as roads and railways the technique is more accurately called Time/Location
Charts or Chainage Charts which include „blocks‟ to mark out chainages such as bridges and culverts that
require substantial time to build and interrupt the general flow of work.
Abstract: Now-a-days whole world facing competition in every fields, including construction industry.
Large construction companies carry out big projects, according to the need of that project, they uses
different methods of construction and management. Critical Path Method (CPM), Linear Scheduling Method
(LSM), and Line Of Balance (LOB) are the different methods of construction project management. All the
construction companies utilize these methods according their utilities and requirement of project. In this
report, Line of balance method is explained with its different component on the basis of some related works
discussed different alternatives and strategies to sequence activities in the long run. This report contains a
study carried out in a construction company in which LOB concept is used in the initial planning phase of a
high-rise residential project. Based on the information provided by different LOBs, representing different
scenarios, It is further discussed with projects managers, superintendents, and crews the advantages and
disadvantages of each scenario regarding the project’s lead time, activities cycle time, gang sizes, batch
sizes, buffers, sequencing and interferences between activities .
Keywords: 1 Line of Balance, Preplanning methods of LOB, Advantages, Disadvantages.
Line of Balance
| IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss. 3 | Mar. 2014 | 46 |
The purpose of the LOB method is to ensure that the many activities of a repetitive production process
stay “in balance” that is, they are producing at a pace which allows an even flow of the items produced through
a process and at a speed compatible with the goals set forth in a plan. The method does this by calculating how
many items should have passed through a given operation or control point, and showing these figures alongside
the number that actually did.
The LOB technique is very suitable for repetitive projects like residential buildings, however it may be
adapted for non-repetitive projects as well. The main advantages of LOB schedule are its graphical presentation,
easy understanding of the schedule and the goals of planning used in it. The research conducted by the authors
aims to improve the LOB concepts on building construction and prove its usefulness.
The LOB method helps project managers take corrective actions such as allocating more resources or
prioritizing the work when there is still time to do it. In terms of the data required to implement the LOB
technique, most of it should be readily available from your defect tracking system or could be derived from it
with a few calculations implemented in Excel or any other spreadsheet. Preplanning using the line of balance
technique attempts to solve planning problems by making production process clearer and simpler. A preplanning
method is presented which needs little detailed information about productivities and work volumes and may be
rapidly produced. The plan brings an overall view of the project by grouping the main activities that are highly
interdependent. The concept on the best rhythm for each group of activities focus on the sequencie of work,
continuity of labor team working and completeness rather than on pure schedule goals. Many characteristics of
the method support lean construction concepts, such as waste elimination, variances minimization, flexible
planning and scheduling sequencing. Using line of balance concepts also suggests some control tools which are
being experimented on aplication cases and are briefly described.
LOB scheduling is superior to the CPM when scheduling projects of a repetitive nature; and these
projects capitalize and make use of many of LOB scheduling benefits, and explained how in repetitive projects,
LOB scheduling is more beneficial in areas like managing the project resources, visualization of the project
schedule, creating schedules more efficiently, managing and updating the schedule, and decreasing the chance
of scheduling errors.
The lessons learned from the first jobs helped the efficient use of the developed tools for the planning of
new projects and the development of the second stage of the work, which is the LOB application on multi-story
building sites as a medium term planning and control tool. The LOB application is imbedded into a new model
of planning and control which attempts to solve planning problems by making production control process
clearer and simpler. The main idea would be: “let everybody manage his own problems and do not create new
problems by managing other people‟s problems”. The line of balance technique has many concepts close to this
new model and the research is investigating them on practical site applications.
III. Preplanning Method
Repetitive projects such as multi-story building allow working with rhythmic planning. In this case, in
order to find the optimum use of resources, a different type of planning is typically used. Crews and equipment
are designed to yield the same production rate, in terms of construction units (i.e., one floor/week, one
apartment/week, etc.). If activities are planned to be built in this way, all activities could become critical.
Nevertheless, most building projects (even simple building construction projects) are not repetitive ones in all
their extent. Thus, an “all activities critical” planning might not be applicable for the whole project. When
planning is based in construction units (floors or apartments) and production velocities, fairly repetitive
construction subdivisions can be developed. In this case the schedule is developed based on the production
velocity, in such a way to generate the same work rhythm for all the involved crews. The number of optimum
crews is selected so that all crews will perform the same amount of construction units in the same period of
time. This approach is essentially the line of balance concept and was proved successful in the applications
described in this paper and by others.
Detailed construction procedures were developed for major construction activities. The fact of working with a
repetitive apartment building project eased the work and allowed development of a significant level of detail for
the majority of activities on site.
The construction procedures included:
I) Crew composition
II) Daily construction volume
III) Crew sizes
IV) Required tools and equipment
Line of Balance
| IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss. 3 | Mar. 2014 | 47 |
IV. Advantages
The Advantages of Line Of Balance is as :
1) Clearly shows the amount of work taking place in a certain area at a specific time of the project.
2) Has the ability to show and optimize the resources used for large number of repeated
activities, executed in several zones or locations.
3) Easier cost and time optimization analysis because of all the information available for
each activity in the project.
4) Ease of setup and its superior presentation and visualization.
5) Easier to modify, update and change the schedule.
6) Better managing of all the various sub-contractors in the project.
7) Allows for simpler and clearer resource management and resource optimization
functions.
8) Visualization of productivity and location of crews.
9) It allows project managers to see, in the middle of a project, whether they can meet the schedule if
they continue working as they have been.
V. DISADVANTAGES
1) Inability to generate a clear critical path of the project schedule, relative to the one
provided by CPM schedules.
2) Could only be divided by location.
3) In CPM scheduling the user could divide project by location and other systems like
trades, in LOB only location.
4) Productivity rates in LOB schedule do not include the effect of crews‟ learning curve, or if the
individuals working in the crews changed.
5)
V. Conclusion
As the Line Of Balance is more suitable than other methods and the study shows the use of LOB as a
means to simulate and discuss decisions related to the design of a production system for a multi-storey building
and its impacts on daily operations. As the LOBs presented to the Company, project managers, different cultural
aspects surfaced regarding the adoption of Lean Construction concepts and presentation of LOB for the purpose
of easy understanding is convenient.
Therefore now a days Line Of Balance is more popular method in construction management and
adopted by most companies.
References
[1] Ballard, G. (1995). “Toward construction JIT.” Proc. 3rd Workshop on Lean Construction, Albuquerque, ed. Luis
Alárcon, Santiago, 1997, Chile: Catholic University of Chile, pp. 291 300.
[2] Ballard, G. (1997). “Lookahead planning: the missing link in production control.” Proc. 5th Conf. of Lean
Construction, pp. 13-25, http://www.vtt.fi/rte/lean/
[3] Lutz, J.D. and Hijazi, A. (1993). “Planning repetitive construction current practice.” Construction Management and
Economics, 11:99-110.
[4] Melles, B. and Welling, D.T. (1996). “Towards a different view on production control in construction.” Proc. 4th
Conference on Lean Construction, http://www.vtt.fi/rte/lean/
[5] Mendes Jr., R. (1998). “Modelo em planilha eletrônica para programação de edifícios— novos desenvolvimentos”
(in Portuguese), Encontro Nacional de Tecnologia do Ambiente Construído—ENTAC 98, Proc., April, Florianópolis:
UFSC, pp. 671-678.
[6] Kemmer, S. L. (2006) “Análise de diferentes tempos de ciclo na formulação de planos de ataque de edifícios de
múltiplos pavimentos.” (in Portuguese) Master‟s thesis. Programa de Pós-Graduação em Engenharia Civil. Federal
University of Santa Catarina, Florianópolis. 122pp.

More Related Content

What's hot

construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxsurekha1287
 
Construction administration
Construction administrationConstruction administration
Construction administrationKarim El-Dash
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & EquipmentsGAURAV. H .TANDON
 
lean construction and integrated project delivery
lean construction and integrated project delivery lean construction and integrated project delivery
lean construction and integrated project delivery Mahendra Bhuva
 
050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction 050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction Dr Fereidoun Dejahang
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 

What's hot (20)

Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
construction project planing
 construction project planing construction project planing
construction project planing
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
 
Construction administration
Construction administrationConstruction administration
Construction administration
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Lean Construction
Lean ConstructionLean Construction
Lean Construction
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
lean construction and integrated project delivery
lean construction and integrated project delivery lean construction and integrated project delivery
lean construction and integrated project delivery
 
050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction 050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Gcc vs scc
Gcc vs sccGcc vs scc
Gcc vs scc
 

Viewers also liked

Lecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMINGLecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMINGJB Nartey
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations Felipe Moreira
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulationavijit biswas
 
Assembly Line Balancing -Example
Assembly Line Balancing -ExampleAssembly Line Balancing -Example
Assembly Line Balancing -ExampleJoseph Konnully
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsScheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsRicardo Viana Vargas
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementAditi Shah
 
Anne+Dennis
Anne+DennisAnne+Dennis
Anne+DennisANNE138
 
Modelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish RelationshipsModelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish RelationshipsFelipe Moreira
 
Project management and control
Project management and controlProject management and control
Project management and controlShruti Pendharkar
 
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Ricardo Viana Vargas
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Scheduleellefsonj
 
waste minimization techniques
waste minimization techniqueswaste minimization techniques
waste minimization techniquesAbuzer Ansari
 
Milestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - FundamentalsMilestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - FundamentalsRicardo Viana Vargas
 
Materi mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopoMateri mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopoHarper's Bazaar Magazine
 

Viewers also liked (20)

Line balancing
Line balancingLine balancing
Line balancing
 
Lecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMINGLecture slides5; LINE OF BALANCE PROGRAMMING
Lecture slides5; LINE OF BALANCE PROGRAMMING
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Assembly Line Balancing -Example
Assembly Line Balancing -ExampleAssembly Line Balancing -Example
Assembly Line Balancing -Example
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish RelationsScheduling Optimization with Line of Balance and Start-to-Finish Relations
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
6. Mr V Smith
6. Mr V Smith6. Mr V Smith
6. Mr V Smith
 
Anne+Dennis
Anne+DennisAnne+Dennis
Anne+Dennis
 
Linear scheduling LSM
Linear scheduling LSMLinear scheduling LSM
Linear scheduling LSM
 
Modelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish RelationshipsModelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish Relationships
 
Project management and control
Project management and controlProject management and control
Project management and control
 
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...Lessons from 40 PPM Experts on Making the Transition from Project Management ...
Lessons from 40 PPM Experts on Making the Transition from Project Management ...
 
Session 10 leb
Session 10 lebSession 10 leb
Session 10 leb
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
waste minimization techniques
waste minimization techniqueswaste minimization techniques
waste minimization techniques
 
Milestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - FundamentalsMilestones Trend Analysis (MTA) - Fundamentals
Milestones Trend Analysis (MTA) - Fundamentals
 
Materi mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopoMateri mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopo
 

Similar to Line of Balance

Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
 
Literature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesLiterature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesObi-Ugbo Alex
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteDawn Cook
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...Dr. Amarjeet Singh
 
The changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docxThe changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docxmattinsonjanel
 
Simulasi lean contractor
Simulasi lean contractorSimulasi lean contractor
Simulasi lean contractorRifki Rizal
 
Service Oriented Unified Process
Service Oriented Unified ProcessService Oriented Unified Process
Service Oriented Unified Processhazimalghalayini
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Surajkumar Sonar
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionIJERA Editor
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...Nat Rice
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 

Similar to Line of Balance (20)

Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
 
Literature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesLiterature Review in Project Scheduling Techniques
Literature Review in Project Scheduling Techniques
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
 
The changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docxThe changes required in the IT project plan for Telecomm Ltd would.docx
The changes required in the IT project plan for Telecomm Ltd would.docx
 
Simulasi lean contractor
Simulasi lean contractorSimulasi lean contractor
Simulasi lean contractor
 
Service Oriented Unified Process
Service Oriented Unified ProcessService Oriented Unified Process
Service Oriented Unified Process
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building Construction
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
 
Case study(i)
Case study(i)Case study(i)
Case study(i)
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 

More from IJMER

A Study on Translucent Concrete Product and Its Properties by Using Optical F...
A Study on Translucent Concrete Product and Its Properties by Using Optical F...A Study on Translucent Concrete Product and Its Properties by Using Optical F...
A Study on Translucent Concrete Product and Its Properties by Using Optical F...IJMER
 
Developing Cost Effective Automation for Cotton Seed Delinting
Developing Cost Effective Automation for Cotton Seed DelintingDeveloping Cost Effective Automation for Cotton Seed Delinting
Developing Cost Effective Automation for Cotton Seed DelintingIJMER
 
Study & Testing Of Bio-Composite Material Based On Munja Fibre
Study & Testing Of Bio-Composite Material Based On Munja FibreStudy & Testing Of Bio-Composite Material Based On Munja Fibre
Study & Testing Of Bio-Composite Material Based On Munja FibreIJMER
 
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)IJMER
 
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...IJMER
 
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...IJMER
 
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...IJMER
 
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...IJMER
 
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
Static Analysis of Go-Kart Chassis by Analytical and Solid Works SimulationStatic Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
Static Analysis of Go-Kart Chassis by Analytical and Solid Works SimulationIJMER
 
High Speed Effortless Bicycle
High Speed Effortless BicycleHigh Speed Effortless Bicycle
High Speed Effortless BicycleIJMER
 
Integration of Struts & Spring & Hibernate for Enterprise Applications
Integration of Struts & Spring & Hibernate for Enterprise ApplicationsIntegration of Struts & Spring & Hibernate for Enterprise Applications
Integration of Struts & Spring & Hibernate for Enterprise ApplicationsIJMER
 
Microcontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation SystemMicrocontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation SystemIJMER
 
On some locally closed sets and spaces in Ideal Topological Spaces
On some locally closed sets and spaces in Ideal Topological SpacesOn some locally closed sets and spaces in Ideal Topological Spaces
On some locally closed sets and spaces in Ideal Topological SpacesIJMER
 
Intrusion Detection and Forensics based on decision tree and Association rule...
Intrusion Detection and Forensics based on decision tree and Association rule...Intrusion Detection and Forensics based on decision tree and Association rule...
Intrusion Detection and Forensics based on decision tree and Association rule...IJMER
 
Natural Language Ambiguity and its Effect on Machine Learning
Natural Language Ambiguity and its Effect on Machine LearningNatural Language Ambiguity and its Effect on Machine Learning
Natural Language Ambiguity and its Effect on Machine LearningIJMER
 
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcess
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcessEvolvea Frameworkfor SelectingPrime Software DevelopmentProcess
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcessIJMER
 
Material Parameter and Effect of Thermal Load on Functionally Graded Cylinders
Material Parameter and Effect of Thermal Load on Functionally Graded CylindersMaterial Parameter and Effect of Thermal Load on Functionally Graded Cylinders
Material Parameter and Effect of Thermal Load on Functionally Graded CylindersIJMER
 
Studies On Energy Conservation And Audit
Studies On Energy Conservation And AuditStudies On Energy Conservation And Audit
Studies On Energy Conservation And AuditIJMER
 
An Implementation of I2C Slave Interface using Verilog HDL
An Implementation of I2C Slave Interface using Verilog HDLAn Implementation of I2C Slave Interface using Verilog HDL
An Implementation of I2C Slave Interface using Verilog HDLIJMER
 
Discrete Model of Two Predators competing for One Prey
Discrete Model of Two Predators competing for One PreyDiscrete Model of Two Predators competing for One Prey
Discrete Model of Two Predators competing for One PreyIJMER
 

More from IJMER (20)

A Study on Translucent Concrete Product and Its Properties by Using Optical F...
A Study on Translucent Concrete Product and Its Properties by Using Optical F...A Study on Translucent Concrete Product and Its Properties by Using Optical F...
A Study on Translucent Concrete Product and Its Properties by Using Optical F...
 
Developing Cost Effective Automation for Cotton Seed Delinting
Developing Cost Effective Automation for Cotton Seed DelintingDeveloping Cost Effective Automation for Cotton Seed Delinting
Developing Cost Effective Automation for Cotton Seed Delinting
 
Study & Testing Of Bio-Composite Material Based On Munja Fibre
Study & Testing Of Bio-Composite Material Based On Munja FibreStudy & Testing Of Bio-Composite Material Based On Munja Fibre
Study & Testing Of Bio-Composite Material Based On Munja Fibre
 
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
Hybrid Engine (Stirling Engine + IC Engine + Electric Motor)
 
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
Fabrication & Characterization of Bio Composite Materials Based On Sunnhemp F...
 
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
Geochemistry and Genesis of Kammatturu Iron Ores of Devagiri Formation, Sandu...
 
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
Experimental Investigation on Characteristic Study of the Carbon Steel C45 in...
 
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
 
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
Static Analysis of Go-Kart Chassis by Analytical and Solid Works SimulationStatic Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
 
High Speed Effortless Bicycle
High Speed Effortless BicycleHigh Speed Effortless Bicycle
High Speed Effortless Bicycle
 
Integration of Struts & Spring & Hibernate for Enterprise Applications
Integration of Struts & Spring & Hibernate for Enterprise ApplicationsIntegration of Struts & Spring & Hibernate for Enterprise Applications
Integration of Struts & Spring & Hibernate for Enterprise Applications
 
Microcontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation SystemMicrocontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation System
 
On some locally closed sets and spaces in Ideal Topological Spaces
On some locally closed sets and spaces in Ideal Topological SpacesOn some locally closed sets and spaces in Ideal Topological Spaces
On some locally closed sets and spaces in Ideal Topological Spaces
 
Intrusion Detection and Forensics based on decision tree and Association rule...
Intrusion Detection and Forensics based on decision tree and Association rule...Intrusion Detection and Forensics based on decision tree and Association rule...
Intrusion Detection and Forensics based on decision tree and Association rule...
 
Natural Language Ambiguity and its Effect on Machine Learning
Natural Language Ambiguity and its Effect on Machine LearningNatural Language Ambiguity and its Effect on Machine Learning
Natural Language Ambiguity and its Effect on Machine Learning
 
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcess
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcessEvolvea Frameworkfor SelectingPrime Software DevelopmentProcess
Evolvea Frameworkfor SelectingPrime Software DevelopmentProcess
 
Material Parameter and Effect of Thermal Load on Functionally Graded Cylinders
Material Parameter and Effect of Thermal Load on Functionally Graded CylindersMaterial Parameter and Effect of Thermal Load on Functionally Graded Cylinders
Material Parameter and Effect of Thermal Load on Functionally Graded Cylinders
 
Studies On Energy Conservation And Audit
Studies On Energy Conservation And AuditStudies On Energy Conservation And Audit
Studies On Energy Conservation And Audit
 
An Implementation of I2C Slave Interface using Verilog HDL
An Implementation of I2C Slave Interface using Verilog HDLAn Implementation of I2C Slave Interface using Verilog HDL
An Implementation of I2C Slave Interface using Verilog HDL
 
Discrete Model of Two Predators competing for One Prey
Discrete Model of Two Predators competing for One PreyDiscrete Model of Two Predators competing for One Prey
Discrete Model of Two Predators competing for One Prey
 

Recently uploaded

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Line of Balance

  • 1. International OPEN ACCESS Journal Of Modern Engineering Research (IJMER) | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss. 3 | Mar. 2014 | 45 | Line of Balance P. A. Badukale1 , Prof. Syed. Sabihuddin2 I. Introduction In different types of construction companies different methods are used for different projects. As the requirement of a project the method like critical path method (CPM), linear scheduling method (LSM), and line of balance (LOB) are applied on it. The construction industry currently utilizes the Critical Path Method scheduling technique (CPM) to plan and manage most construction projects. This phenomenon is depicted in a study conducted by Tavakoli and Riachi in 1990. In their study, they surveyed the use of CPM scheduling in the top ENR 400 contractors. For the past three decades, numerous researchers have identified the various intrinsic advantages of the Line of Balance scheduling technique (LOB) in comparison to the CPM. The concept of finding a critical path is another major fundamental difference between LOB and CPM scheduling. Arditi, Tokdemir, and Suh (2001) explained how “In network analysis, at least one critical path exists. Activities which are on the critical path have to be started and completed by their assigned times if the total project duration is not to be extended.” The LOB scheduling methods criticalness is based on time and resources, unlike network scheduling where it is only based on time. The LOB method allows the team to deliver at its maximum speed, by helping balance the different activities in the production chain. In keeping with the idea of using the team‟s actual performance, we also propose to derive the lead-times for the so called “control points”, not from an activity network as in the original LOB formulation, but from the team‟s “velocity”. Line of Balance (LOB) is a method of showing the repetitive work that may exist in a project as a single line on a graph. Unlike a Bar Chart, which shows the duration of a particular activity, a LOB Chart shows the rate at which the work that makes up all of the activities has to be undertaken to stay on schedule, the relationship of one trade or process to the subsequent trade or process is defined by the space between the lines. If one group is running behind schedule, it will impact on the following group and this is shown by the lines intersecting. The Line-of-Balance then would have a series of stair step offsets. Making those decisions is the job of the management team. Once the Bedding, Laying of Pipe, and Testing of the 1st segment to done, then the Backfill can begin and work continuously. However, the difficulties in using the LOB for scheduling projects have been stripped off from the method when authors have downplayed problems that surround the definition of task durations, the choice of the repetitive unit or batch size, cycle time, and the definition of buffers between tasks. II. Line Of Balance A simple diagram in which line shows location and time at which a certain crew will be working on a given operation is known as LOB. it is used on repetitive work such as constructing multiple dwelling units, when used on linear work such as roads and railways the technique is more accurately called Time/Location Charts or Chainage Charts which include „blocks‟ to mark out chainages such as bridges and culverts that require substantial time to build and interrupt the general flow of work. Abstract: Now-a-days whole world facing competition in every fields, including construction industry. Large construction companies carry out big projects, according to the need of that project, they uses different methods of construction and management. Critical Path Method (CPM), Linear Scheduling Method (LSM), and Line Of Balance (LOB) are the different methods of construction project management. All the construction companies utilize these methods according their utilities and requirement of project. In this report, Line of balance method is explained with its different component on the basis of some related works discussed different alternatives and strategies to sequence activities in the long run. This report contains a study carried out in a construction company in which LOB concept is used in the initial planning phase of a high-rise residential project. Based on the information provided by different LOBs, representing different scenarios, It is further discussed with projects managers, superintendents, and crews the advantages and disadvantages of each scenario regarding the project’s lead time, activities cycle time, gang sizes, batch sizes, buffers, sequencing and interferences between activities . Keywords: 1 Line of Balance, Preplanning methods of LOB, Advantages, Disadvantages.
  • 2. Line of Balance | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss. 3 | Mar. 2014 | 46 | The purpose of the LOB method is to ensure that the many activities of a repetitive production process stay “in balance” that is, they are producing at a pace which allows an even flow of the items produced through a process and at a speed compatible with the goals set forth in a plan. The method does this by calculating how many items should have passed through a given operation or control point, and showing these figures alongside the number that actually did. The LOB technique is very suitable for repetitive projects like residential buildings, however it may be adapted for non-repetitive projects as well. The main advantages of LOB schedule are its graphical presentation, easy understanding of the schedule and the goals of planning used in it. The research conducted by the authors aims to improve the LOB concepts on building construction and prove its usefulness. The LOB method helps project managers take corrective actions such as allocating more resources or prioritizing the work when there is still time to do it. In terms of the data required to implement the LOB technique, most of it should be readily available from your defect tracking system or could be derived from it with a few calculations implemented in Excel or any other spreadsheet. Preplanning using the line of balance technique attempts to solve planning problems by making production process clearer and simpler. A preplanning method is presented which needs little detailed information about productivities and work volumes and may be rapidly produced. The plan brings an overall view of the project by grouping the main activities that are highly interdependent. The concept on the best rhythm for each group of activities focus on the sequencie of work, continuity of labor team working and completeness rather than on pure schedule goals. Many characteristics of the method support lean construction concepts, such as waste elimination, variances minimization, flexible planning and scheduling sequencing. Using line of balance concepts also suggests some control tools which are being experimented on aplication cases and are briefly described. LOB scheduling is superior to the CPM when scheduling projects of a repetitive nature; and these projects capitalize and make use of many of LOB scheduling benefits, and explained how in repetitive projects, LOB scheduling is more beneficial in areas like managing the project resources, visualization of the project schedule, creating schedules more efficiently, managing and updating the schedule, and decreasing the chance of scheduling errors. The lessons learned from the first jobs helped the efficient use of the developed tools for the planning of new projects and the development of the second stage of the work, which is the LOB application on multi-story building sites as a medium term planning and control tool. The LOB application is imbedded into a new model of planning and control which attempts to solve planning problems by making production control process clearer and simpler. The main idea would be: “let everybody manage his own problems and do not create new problems by managing other people‟s problems”. The line of balance technique has many concepts close to this new model and the research is investigating them on practical site applications. III. Preplanning Method Repetitive projects such as multi-story building allow working with rhythmic planning. In this case, in order to find the optimum use of resources, a different type of planning is typically used. Crews and equipment are designed to yield the same production rate, in terms of construction units (i.e., one floor/week, one apartment/week, etc.). If activities are planned to be built in this way, all activities could become critical. Nevertheless, most building projects (even simple building construction projects) are not repetitive ones in all their extent. Thus, an “all activities critical” planning might not be applicable for the whole project. When planning is based in construction units (floors or apartments) and production velocities, fairly repetitive construction subdivisions can be developed. In this case the schedule is developed based on the production velocity, in such a way to generate the same work rhythm for all the involved crews. The number of optimum crews is selected so that all crews will perform the same amount of construction units in the same period of time. This approach is essentially the line of balance concept and was proved successful in the applications described in this paper and by others. Detailed construction procedures were developed for major construction activities. The fact of working with a repetitive apartment building project eased the work and allowed development of a significant level of detail for the majority of activities on site. The construction procedures included: I) Crew composition II) Daily construction volume III) Crew sizes IV) Required tools and equipment
  • 3. Line of Balance | IJMER | ISSN: 2249–6645 | www.ijmer.com | Vol. 4 | Iss. 3 | Mar. 2014 | 47 | IV. Advantages The Advantages of Line Of Balance is as : 1) Clearly shows the amount of work taking place in a certain area at a specific time of the project. 2) Has the ability to show and optimize the resources used for large number of repeated activities, executed in several zones or locations. 3) Easier cost and time optimization analysis because of all the information available for each activity in the project. 4) Ease of setup and its superior presentation and visualization. 5) Easier to modify, update and change the schedule. 6) Better managing of all the various sub-contractors in the project. 7) Allows for simpler and clearer resource management and resource optimization functions. 8) Visualization of productivity and location of crews. 9) It allows project managers to see, in the middle of a project, whether they can meet the schedule if they continue working as they have been. V. DISADVANTAGES 1) Inability to generate a clear critical path of the project schedule, relative to the one provided by CPM schedules. 2) Could only be divided by location. 3) In CPM scheduling the user could divide project by location and other systems like trades, in LOB only location. 4) Productivity rates in LOB schedule do not include the effect of crews‟ learning curve, or if the individuals working in the crews changed. 5) V. Conclusion As the Line Of Balance is more suitable than other methods and the study shows the use of LOB as a means to simulate and discuss decisions related to the design of a production system for a multi-storey building and its impacts on daily operations. As the LOBs presented to the Company, project managers, different cultural aspects surfaced regarding the adoption of Lean Construction concepts and presentation of LOB for the purpose of easy understanding is convenient. Therefore now a days Line Of Balance is more popular method in construction management and adopted by most companies. References [1] Ballard, G. (1995). “Toward construction JIT.” Proc. 3rd Workshop on Lean Construction, Albuquerque, ed. Luis Alárcon, Santiago, 1997, Chile: Catholic University of Chile, pp. 291 300. [2] Ballard, G. (1997). “Lookahead planning: the missing link in production control.” Proc. 5th Conf. of Lean Construction, pp. 13-25, http://www.vtt.fi/rte/lean/ [3] Lutz, J.D. and Hijazi, A. (1993). “Planning repetitive construction current practice.” Construction Management and Economics, 11:99-110. [4] Melles, B. and Welling, D.T. (1996). “Towards a different view on production control in construction.” Proc. 4th Conference on Lean Construction, http://www.vtt.fi/rte/lean/ [5] Mendes Jr., R. (1998). “Modelo em planilha eletrônica para programação de edifícios— novos desenvolvimentos” (in Portuguese), Encontro Nacional de Tecnologia do Ambiente Construído—ENTAC 98, Proc., April, Florianópolis: UFSC, pp. 671-678. [6] Kemmer, S. L. (2006) “Análise de diferentes tempos de ciclo na formulação de planos de ataque de edifícios de múltiplos pavimentos.” (in Portuguese) Master‟s thesis. Programa de Pós-Graduação em Engenharia Civil. Federal University of Santa Catarina, Florianópolis. 122pp.