CONSTRUCTION PLANNING
AND SCHEDULING
MODULE 1
CONSTRUCTION PLANNING
• Planning in construction is necessary to ensure
proper utilisation of humans and material
resources to achieve the objectives of the
project.
• Plan includes the estimates, budget, time
schedule, sequence of completion of each part
of the project, manpower planning , plant and
equipments.
Object of Planning
• To execute work in an organised and structured
manner.
• Proper design of each elements of the project.
• To reduce rework.
• To establish quality standards.
• To provide basis for monitoring and control of
project work.
• To know the duration of each activity.
Object of Planning
• To know the cost associated with each activity.
• To know responsibility and authority of people
involved in the project.
• Proper selection of equipment and machinery.
• Proper arrangement of repair of equipment and
machinery near the site of work.
• Procurement of material well in advance.
• To provide welfare schemes for the staff and workers
such as medical and recreational facilities.
• To arrange proper safety measures such as proper
ventilation, proper arrangement of light and water.
Principles of Planning
• The plan should provide information in readily
understandable form.
• The plan should be realistic.
• The plan should be flexible.
• The plan should serve as a basis for project
monitoring and control.
• The plan should be comprehensive.
Construction Project Planning
Project planning is a logical process to ensure
that the work of project is carried out:
• In an organised and structured manner.
• By reducing uncertainties to minimum.
• By reducing risk to minimum.
• By establishing quality standards.
• By achieving results within budget and
schedule time.
Steps to prepare Project Plan
• The first step of project planning is to clearly
define the problem to be solved by the project.
• Once the problem is clearly defined, the next
step is to define the project objectives or goals.
• Developing schedule and cost.
• Identify project deliverables.
• After identifying the deliverables, these are
subdivided into smaller activities to enable
developing schedule and cost estimates.
Steps to prepare Project Plan
• Step to estimate activity resources, activity duration and
develop schedule.
• Step to estimate cost and develop budget based on
project deliverable and schedule.
• Supporting plans such as quality management, human
resources, communication, risk management and
procurement/ supply management are simultaneously
developed.
• Steps to compare the plan compliance with original
project objectives.
• The plan is updated to meet original objectives/ goals.
• The project is launched based on this plan.
Activities involved in Construction
Planning
• Defining the scope of Work.
• Identifying activities involved.
• Establishing Project duration.
• Defining procedure for controlling and
assigning resources.
• Developing appropriate interfaces.
• Updating and revising plans.
Types of Plans
Different types of Plans
1. Project Conceptual Plan
2. Project Preliminary Plan
3. Detailed construction Plan
4. Time Plan
5. Manpower Plan
6. Material Plan
7. Construction Equipment Plan
8. Finance Plan
Scheduling
4 important Resources for all Work
• Materials
• Man
• Machinery
• Money
Scheduling is a mechanical process for setting the
various planned activities in order by fixing the
starting and finishing date of each activity of the
work .
Uses of Scheduling
• It gives quantity of work involved, labour,
materials and equipment of each work.
• The actual progress of the work can be
checked.
• The project can be carried out in a systematic
manner using the scheduling.
Advantages of Scheduling
• Alternate method of construction can be examined at
the planning stage and most economical methods can
be chosen.
• It gives clear idea regarding the required men, materials
and equipment at different stages of the work.
• Cost control study.
• Arrangement of different materials.
• Actual Progress schedule.
• Requirements of Funds during various stages of work.
• Total time required for completion of project is known.
Types of Schedule
• Construction Schedule
• Material Schedule
• Labour Schedule
• Equipment Schedule
• Expenditure Schedule.
The Work Break Down Structure
(WBS)
• An organizational tool for complex projects
– A first step in creating a schedule
– Useful for defining the Scope of Work
• After decided how to do the work
• Consists of:
– Goal statement for project
– Subdividing goal into smaller & smaller portions
Example of WBS
Warehouse WBS
Site Boundaries Elevation
Data Points
Building
Footprints
Locate
Buried Services
Survey Soils Analysis Excavate Soil Backfill & Compact
Site Preparation Foundation Structural Systems Finishing
To construct a 5-unit
warehouse for light industry
Complex
Methods Of Scheduling
Scheduling can be done by different methods
depending on the size of the project.
The methods used are:
1. Gantt Charts or Bar Charts
2. Milestone Charts
3. Network Analysis
Gantt Chart
• Gantt chart is a matrix of rows and columns.
The time scale is indicated along the horizontal
axis. Activities are arranged along the vertical
axis.
• Gantt charts are usually used to represent the
project schedule. Gantt charts should be
updated periodically.
Gantt Chart
• Henry L Gantt (1861 – 1919) around 1917
developed a system of bar charts for scheduling
and reporting progress of a project. These charts
latter were known as Gantt Charts.
• Gantt chart is a matrix of rows and columns. The
time scale is indicated along the horizontal axis.
Activities are arranged along the vertical axis.
• Gantt charts are usually used to represent the
project schedule.
• Gantt charts should be updated periodically.
Gantt Chart
• For example,
“Task A” is land preparation,
“Task B” is procurement of inputs etc.
Land preparation (Task A) takes five days
starting from day one.
However in practice the time scale is
superimposed on a calendar i.e., if land
preparation starts on 1st March it would be
completed by 5 th March.
Figure: Gantt Chart
Limitation of Bar Charts
• They can be used only for small projects.
• It does not show the inter dependence between the
various activities in the projects.
• The progress of the works in the project cannot be
monitored scientifically.
• Delays in the works cannot be detected.
• It does not indicate the critical activities of the project.
• It gives some ideas about the physical progress of the
project, but financial aspects involved is not known.
• It cannot be used as a controlling device by the project
manager to take any timely action.
Mile Stone
• Milestone chart is a modification over the
original bar chart.
• The beginning and end of the activities or tasks
are termed as milestone.
Mile Stone
Figure: Milestone
Network Analysis
• Network analysis is the synthesis of two most useful
techniques of project management i.e P.E.R.T and
C.P.M.
• PERT was developed as a management tool for
coordination and early completion of Polaris Ballistic
Missile Project in U.S.A, resulting in reduction of 30%
time in project execution.
• A contemporary of PERT is CPM and was developed
in connection with maintenance and construction work.
• Both CPM and PERT describe the work plan of project
where arrows and circles respectively indicate the
activities and events in the project.
Difference between PERT and CPM
PERT CPM
1. PERT is event oriented.. 1. CPM is activity oriented.
2. PERT is probabilistic. 2. CPM is deterministic.
3. PERT is primarily concerned with time
only
3. CPM places dual emphasis on project
time as well cost.
4. PERT is generally used for projects
where time required to complete the
activities is not known a priori. Thus
PERT is used for large, R&D type of
projects
4. CPM is used for projects which are
repetitive in nature and comparatively
small in size.
5. Three time estimates are possible for
activities linking up two events.
5.One time estimate is possible for
activities
Benefits of CPM/PERT
1) Useful at many stages of project management.
2) Mathematically simple.
3) Give critical path and slack time.
4) Provide project documentation.
5) Useful in monitoring costs.
Two types of notations used in the
network diagram.
They are as under,
1. Activity-on-Arrow (AOA), and
2.Activity-on-Node (AON).
Activity-on-Arrow (AOA)
• In AOA notation, the arrow represents the
work to be done and the circle represents an
event – either the beginning of another activity
or completion of previous one.
Activity-on-Node (AON).
• For AON notation, a box (or node) is used to
show the task itself and the arrow simply show
the sequence in which work is done
Comparison of AON and AOA
Components of PERT and CPM
Components of PERT and CPM
Merge and Burst Event
Activities A and B Precede activities C and D.
• Dummy Activity
Errors to be Avoided in Constructing Network
• Two activities starting from a
tail event must not have a same
end event. To ensure this, it is
absolutely necessary to
introduce a dummy activity, as
shown in figure,
• Looping error should not be
formed in a network, as it
represents performance of
activities repeatedly in a cyclic
manner.
• In a network, there
should be only one start
event and one ending
event.
• The direction of arrows
should flow from left to
right avoiding mixing of
direction.
RULES IN CONSTRUCTING A NETWORK
• No single activity can be represented more than once in a
network. The length of an arrow has no significance.
• The event numbered 1 is the start event and an event with
highest number is the end event. Before an activity can be
undertaken, all activities preceding it must be completed.
That is, the activities must follow a logical sequence (or –
interrelationship) between activities.
• In assigning numbers to events, there should not be any
duplication of event numbers in a network.
• Dummy activities must be used only if it is necessary to
reduce the complexity of a network.
• A network should have only one start event and one end
event.
Consider the project given in Table and construct a network
diagram
Determining the Critical Path
• Step 1: Make a forward pass through the network
as follows: For each activity i beginning at the Start
node, compute:
– Earliest Start Time (ES) = the maximum of the earliest
finish times of all activities immediately preceding activity
i. (This is 0 for an activity with no predecessors.). This is
the earliest time an activity can begin without violation of
immediate predecessor requirements.
– Earliest Finish Time (EF) = (Earliest Start Time) + (Time to
complete activity i. This represent the earliest time at
which an activity can end.
The project completion time is the maximum of the
Earliest Finish Times at the Finish node.
Determining the Critical Path
• Step 2: Make a backwards pass through the network as
follows: Move sequentially backwards from the Finish node
to the Start node. At a given node, j, consider all activities
ending at node j. For each of these activities, (i,j), compute:
– Latest Finish Time (LF) = the minimum of the latest start
times beginning at node j. (For node N, this is the project
completion time.). This is the latest time an activity can
end without delaying the entire project.
– Latest Start Time (LS) = (Latest Finish Time) - (Time to
complete activity (i,j)). This is the latest time an activity
can begin without delaying the entire project.
Determining the Critical Path
• Step 3: Calculate the slack time for each
activity by:
Slack = (Latest Start) - (Earliest Start),
or
= (Latest Finish) - (Earliest Finish).
A critical path is a path of activities, from
the Start node to the Finish node, with 0
slack times.
Example: ABC Associates
• Consider the following project:
Immediate
Activity Predecessor time (days)
A -- 6
B -- 4
C A 3
D A 5
E A 1
F B,C 4
G B,C 2
H E,F 6
I E,F 5
J D,H 3
K G,I 5
Example: network
A
B
C
D
E
F
G
H
I
J
K
1
2
3
4
5
6
7
6
4
3
5
1
4
2
6
5
3
5
0
6
9
13
19
18
23
23
18
20
13
9
6
0
ES
LF
Forward
Backward
Activity Duration EST EFT LST LFT SLACK Remarks
A 6 0 6 0 6 0 CA
B 4 0 4 5 9 5
C 3 6 9 6 9 0 CA
D 5 6 11 15 20 9
E 1 6 7 12 13 6
F 4 9 13 9 13 0 CA
G 2 9 11 16 18 7
H 6 13 19 14 20 1
I 5 13 18 13 18 0 CA
J 3 19 22 20 23 1
K 5 18 23 18 23 0 CA
EF = ES + t
LS = LF – t
Where t is the
Activity time
Slack = LF – EF
= LS - ES
The estimated project completion time is the Max EF at node 7 = 23
THANK YOU

More Related Content

What's hot

CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industryRubnawaz Bhatti
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptssuserb4074f
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxRaoAnkitYadav1
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project managementreachfirst01
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of constructionSANJEEV Wazir
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture) Muhammad Aljalali
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 

What's hot (20)

CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project management
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Construction management
Construction managementConstruction management
Construction management
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Contracts
ContractsContracts
Contracts
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 

Similar to CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx

project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 
Project management techniques
Project management techniquesProject management techniques
Project management techniquesRagjni Govindaraju
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptxssuserbc5970
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfGagandeepKaur617299
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
L6.2 planing&scheduling
L6.2 planing&schedulingL6.2 planing&scheduling
L6.2 planing&schedulingmanusug
 
PROJECT CONTROL.pptx
PROJECT CONTROL.pptxPROJECT CONTROL.pptx
PROJECT CONTROL.pptxANANDChavan56
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesvideoaakash15
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdfAhmedshayor
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 

Similar to CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx (20)

project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Scheduling.pptx
Scheduling.pptxScheduling.pptx
Scheduling.pptx
 
L6.2 planing&scheduling
L6.2 planing&schedulingL6.2 planing&scheduling
L6.2 planing&scheduling
 
PROJECT CONTROL.pptx
PROJECT CONTROL.pptxPROJECT CONTROL.pptx
PROJECT CONTROL.pptx
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 

More from surekha1287

Module 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptxModule 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptxsurekha1287
 
LIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptxLIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptxsurekha1287
 
Drone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptxDrone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptxsurekha1287
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxsurekha1287
 
MS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptxMS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptxsurekha1287
 
Runoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation EngineeringRunoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation Engineeringsurekha1287
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxsurekha1287
 
Ethics.ppt
Ethics.pptEthics.ppt
Ethics.pptsurekha1287
 
Module-2.pptx
Module-2.pptxModule-2.pptx
Module-2.pptxsurekha1287
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxsurekha1287
 
Economy.pptx
Economy.pptxEconomy.pptx
Economy.pptxsurekha1287
 
unionexecutive-.pptx
unionexecutive-.pptxunionexecutive-.pptx
unionexecutive-.pptxsurekha1287
 
Module-5.pptx
Module-5.pptxModule-5.pptx
Module-5.pptxsurekha1287
 
unionexecutive-Module 3.pptx
unionexecutive-Module 3.pptxunionexecutive-Module 3.pptx
unionexecutive-Module 3.pptxsurekha1287
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptxsurekha1287
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptxsurekha1287
 
MODULE 1 continuation .pptx
MODULE 1 continuation .pptxMODULE 1 continuation .pptx
MODULE 1 continuation .pptxsurekha1287
 
Hydrology.pptx
Hydrology.pptxHydrology.pptx
Hydrology.pptxsurekha1287
 
module-1 CME.pptx
module-1 CME.pptxmodule-1 CME.pptx
module-1 CME.pptxsurekha1287
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptxsurekha1287
 

More from surekha1287 (20)

Module 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptxModule 5 Remote Sensing in Civil Engineering.pptx
Module 5 Remote Sensing in Civil Engineering.pptx
 
LIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptxLIDAR- Modern techniques in Surveying.pptx
LIDAR- Modern techniques in Surveying.pptx
 
Drone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptxDrone Surveying in Civil Engineering pptx
Drone Surveying in Civil Engineering pptx
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptx
 
MS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptxMS Excel and Visual Basic Applications.pptx
MS Excel and Visual Basic Applications.pptx
 
Runoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation EngineeringRunoff - Hydrology and Irrigation Engineering
Runoff - Hydrology and Irrigation Engineering
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptx
 
Ethics.ppt
Ethics.pptEthics.ppt
Ethics.ppt
 
Module-2.pptx
Module-2.pptxModule-2.pptx
Module-2.pptx
 
Introduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptxIntroduction to Hydrology & Precipitation - Module - 1.pptx
Introduction to Hydrology & Precipitation - Module - 1.pptx
 
Economy.pptx
Economy.pptxEconomy.pptx
Economy.pptx
 
unionexecutive-.pptx
unionexecutive-.pptxunionexecutive-.pptx
unionexecutive-.pptx
 
Module-5.pptx
Module-5.pptxModule-5.pptx
Module-5.pptx
 
unionexecutive-Module 3.pptx
unionexecutive-Module 3.pptxunionexecutive-Module 3.pptx
unionexecutive-Module 3.pptx
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptx
 
Module 2 dSp.pptx
Module 2 dSp.pptxModule 2 dSp.pptx
Module 2 dSp.pptx
 
MODULE 1 continuation .pptx
MODULE 1 continuation .pptxMODULE 1 continuation .pptx
MODULE 1 continuation .pptx
 
Hydrology.pptx
Hydrology.pptxHydrology.pptx
Hydrology.pptx
 
module-1 CME.pptx
module-1 CME.pptxmodule-1 CME.pptx
module-1 CME.pptx
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 

Recently uploaded

💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsArindam Chakraborty, Ph.D., P.E. (CA, TX)
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 

Recently uploaded (20)

💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 

CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx

  • 2. CONSTRUCTION PLANNING • Planning in construction is necessary to ensure proper utilisation of humans and material resources to achieve the objectives of the project. • Plan includes the estimates, budget, time schedule, sequence of completion of each part of the project, manpower planning , plant and equipments.
  • 3. Object of Planning • To execute work in an organised and structured manner. • Proper design of each elements of the project. • To reduce rework. • To establish quality standards. • To provide basis for monitoring and control of project work. • To know the duration of each activity.
  • 4. Object of Planning • To know the cost associated with each activity. • To know responsibility and authority of people involved in the project. • Proper selection of equipment and machinery. • Proper arrangement of repair of equipment and machinery near the site of work. • Procurement of material well in advance. • To provide welfare schemes for the staff and workers such as medical and recreational facilities. • To arrange proper safety measures such as proper ventilation, proper arrangement of light and water.
  • 5. Principles of Planning • The plan should provide information in readily understandable form. • The plan should be realistic. • The plan should be flexible. • The plan should serve as a basis for project monitoring and control. • The plan should be comprehensive.
  • 6. Construction Project Planning Project planning is a logical process to ensure that the work of project is carried out: • In an organised and structured manner. • By reducing uncertainties to minimum. • By reducing risk to minimum. • By establishing quality standards. • By achieving results within budget and schedule time.
  • 7. Steps to prepare Project Plan • The first step of project planning is to clearly define the problem to be solved by the project. • Once the problem is clearly defined, the next step is to define the project objectives or goals. • Developing schedule and cost. • Identify project deliverables. • After identifying the deliverables, these are subdivided into smaller activities to enable developing schedule and cost estimates.
  • 8. Steps to prepare Project Plan • Step to estimate activity resources, activity duration and develop schedule. • Step to estimate cost and develop budget based on project deliverable and schedule. • Supporting plans such as quality management, human resources, communication, risk management and procurement/ supply management are simultaneously developed. • Steps to compare the plan compliance with original project objectives. • The plan is updated to meet original objectives/ goals. • The project is launched based on this plan.
  • 9. Activities involved in Construction Planning • Defining the scope of Work. • Identifying activities involved. • Establishing Project duration. • Defining procedure for controlling and assigning resources. • Developing appropriate interfaces. • Updating and revising plans.
  • 10. Types of Plans Different types of Plans 1. Project Conceptual Plan 2. Project Preliminary Plan 3. Detailed construction Plan 4. Time Plan 5. Manpower Plan 6. Material Plan 7. Construction Equipment Plan 8. Finance Plan
  • 11. Scheduling 4 important Resources for all Work • Materials • Man • Machinery • Money Scheduling is a mechanical process for setting the various planned activities in order by fixing the starting and finishing date of each activity of the work .
  • 12. Uses of Scheduling • It gives quantity of work involved, labour, materials and equipment of each work. • The actual progress of the work can be checked. • The project can be carried out in a systematic manner using the scheduling.
  • 13. Advantages of Scheduling • Alternate method of construction can be examined at the planning stage and most economical methods can be chosen. • It gives clear idea regarding the required men, materials and equipment at different stages of the work. • Cost control study. • Arrangement of different materials. • Actual Progress schedule. • Requirements of Funds during various stages of work. • Total time required for completion of project is known.
  • 14. Types of Schedule • Construction Schedule • Material Schedule • Labour Schedule • Equipment Schedule • Expenditure Schedule.
  • 15. The Work Break Down Structure (WBS) • An organizational tool for complex projects – A first step in creating a schedule – Useful for defining the Scope of Work • After decided how to do the work • Consists of: – Goal statement for project – Subdividing goal into smaller & smaller portions
  • 16. Example of WBS Warehouse WBS Site Boundaries Elevation Data Points Building Footprints Locate Buried Services Survey Soils Analysis Excavate Soil Backfill & Compact Site Preparation Foundation Structural Systems Finishing To construct a 5-unit warehouse for light industry Complex
  • 17. Methods Of Scheduling Scheduling can be done by different methods depending on the size of the project. The methods used are: 1. Gantt Charts or Bar Charts 2. Milestone Charts 3. Network Analysis
  • 18. Gantt Chart • Gantt chart is a matrix of rows and columns. The time scale is indicated along the horizontal axis. Activities are arranged along the vertical axis. • Gantt charts are usually used to represent the project schedule. Gantt charts should be updated periodically.
  • 19. Gantt Chart • Henry L Gantt (1861 – 1919) around 1917 developed a system of bar charts for scheduling and reporting progress of a project. These charts latter were known as Gantt Charts. • Gantt chart is a matrix of rows and columns. The time scale is indicated along the horizontal axis. Activities are arranged along the vertical axis. • Gantt charts are usually used to represent the project schedule. • Gantt charts should be updated periodically.
  • 20. Gantt Chart • For example, “Task A” is land preparation, “Task B” is procurement of inputs etc. Land preparation (Task A) takes five days starting from day one. However in practice the time scale is superimposed on a calendar i.e., if land preparation starts on 1st March it would be completed by 5 th March.
  • 22. Limitation of Bar Charts • They can be used only for small projects. • It does not show the inter dependence between the various activities in the projects. • The progress of the works in the project cannot be monitored scientifically. • Delays in the works cannot be detected. • It does not indicate the critical activities of the project. • It gives some ideas about the physical progress of the project, but financial aspects involved is not known. • It cannot be used as a controlling device by the project manager to take any timely action.
  • 23. Mile Stone • Milestone chart is a modification over the original bar chart. • The beginning and end of the activities or tasks are termed as milestone.
  • 25. Network Analysis • Network analysis is the synthesis of two most useful techniques of project management i.e P.E.R.T and C.P.M. • PERT was developed as a management tool for coordination and early completion of Polaris Ballistic Missile Project in U.S.A, resulting in reduction of 30% time in project execution. • A contemporary of PERT is CPM and was developed in connection with maintenance and construction work. • Both CPM and PERT describe the work plan of project where arrows and circles respectively indicate the activities and events in the project.
  • 26. Difference between PERT and CPM PERT CPM 1. PERT is event oriented.. 1. CPM is activity oriented. 2. PERT is probabilistic. 2. CPM is deterministic. 3. PERT is primarily concerned with time only 3. CPM places dual emphasis on project time as well cost. 4. PERT is generally used for projects where time required to complete the activities is not known a priori. Thus PERT is used for large, R&D type of projects 4. CPM is used for projects which are repetitive in nature and comparatively small in size. 5. Three time estimates are possible for activities linking up two events. 5.One time estimate is possible for activities
  • 27. Benefits of CPM/PERT 1) Useful at many stages of project management. 2) Mathematically simple. 3) Give critical path and slack time. 4) Provide project documentation. 5) Useful in monitoring costs.
  • 28. Two types of notations used in the network diagram. They are as under, 1. Activity-on-Arrow (AOA), and 2.Activity-on-Node (AON).
  • 29. Activity-on-Arrow (AOA) • In AOA notation, the arrow represents the work to be done and the circle represents an event – either the beginning of another activity or completion of previous one.
  • 30. Activity-on-Node (AON). • For AON notation, a box (or node) is used to show the task itself and the arrow simply show the sequence in which work is done
  • 31. Comparison of AON and AOA
  • 34. Merge and Burst Event Activities A and B Precede activities C and D.
  • 36. Errors to be Avoided in Constructing Network • Two activities starting from a tail event must not have a same end event. To ensure this, it is absolutely necessary to introduce a dummy activity, as shown in figure, • Looping error should not be formed in a network, as it represents performance of activities repeatedly in a cyclic manner.
  • 37. • In a network, there should be only one start event and one ending event. • The direction of arrows should flow from left to right avoiding mixing of direction.
  • 38. RULES IN CONSTRUCTING A NETWORK • No single activity can be represented more than once in a network. The length of an arrow has no significance. • The event numbered 1 is the start event and an event with highest number is the end event. Before an activity can be undertaken, all activities preceding it must be completed. That is, the activities must follow a logical sequence (or – interrelationship) between activities. • In assigning numbers to events, there should not be any duplication of event numbers in a network. • Dummy activities must be used only if it is necessary to reduce the complexity of a network. • A network should have only one start event and one end event.
  • 39. Consider the project given in Table and construct a network diagram
  • 40. Determining the Critical Path • Step 1: Make a forward pass through the network as follows: For each activity i beginning at the Start node, compute: – Earliest Start Time (ES) = the maximum of the earliest finish times of all activities immediately preceding activity i. (This is 0 for an activity with no predecessors.). This is the earliest time an activity can begin without violation of immediate predecessor requirements. – Earliest Finish Time (EF) = (Earliest Start Time) + (Time to complete activity i. This represent the earliest time at which an activity can end. The project completion time is the maximum of the Earliest Finish Times at the Finish node.
  • 41. Determining the Critical Path • Step 2: Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Start node. At a given node, j, consider all activities ending at node j. For each of these activities, (i,j), compute: – Latest Finish Time (LF) = the minimum of the latest start times beginning at node j. (For node N, this is the project completion time.). This is the latest time an activity can end without delaying the entire project. – Latest Start Time (LS) = (Latest Finish Time) - (Time to complete activity (i,j)). This is the latest time an activity can begin without delaying the entire project.
  • 42. Determining the Critical Path • Step 3: Calculate the slack time for each activity by: Slack = (Latest Start) - (Earliest Start), or = (Latest Finish) - (Earliest Finish). A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times.
  • 43. Example: ABC Associates • Consider the following project: Immediate Activity Predecessor time (days) A -- 6 B -- 4 C A 3 D A 5 E A 1 F B,C 4 G B,C 2 H E,F 6 I E,F 5 J D,H 3 K G,I 5
  • 45. Activity Duration EST EFT LST LFT SLACK Remarks A 6 0 6 0 6 0 CA B 4 0 4 5 9 5 C 3 6 9 6 9 0 CA D 5 6 11 15 20 9 E 1 6 7 12 13 6 F 4 9 13 9 13 0 CA G 2 9 11 16 18 7 H 6 13 19 14 20 1 I 5 13 18 13 18 0 CA J 3 19 22 20 23 1 K 5 18 23 18 23 0 CA EF = ES + t LS = LF – t Where t is the Activity time Slack = LF – EF = LS - ES The estimated project completion time is the Max EF at node 7 = 23