International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–1
A STUDY ON THE IMPLEMENTATION OF PRE-
CONSTRUCTION HEALTH AND SAFETY PLANNING
IN THE CONSTRUCTION PROJECTS IN UNIVERSITAS
NEGERI SEMARANG IN 2018
Tugino*
Civil Engineering Department, Universitas Negeri Semarang, INDONESIA
tugino60@gmail.com
Aris Widodo
Civil Engineering Department, Universitas Negeri Semarang, INDONESIA
ariswidodo71@mail.unnes.ac.id
Harijadi Gunawan Buntoro Wahyono
Civil Engineering Department, Universitas Negeri Semarang, INDONESIA
hariyadi_gbw@mail.unnes.ac.id
Bambang Endroyo
Civil Engineering Department, Universitas Negeri Semarang, INDONESIA
bb.endroyo@gmail.com
Manuscript History
Number: IJIRAE/RS/Vol.06/Issue01/JAAE10080
Received: 22, December 2018
Final Correction: 03, January 2019
Final Accepted: 12, January 2019
Published: January 2019
Citation:
Editor: Dr.A.Arul L.S, Chief Editor, IJIRAE, AM Publications, India
Copyright: ©2019 This is an open access article distributed under the terms of the Creative Commons Attribution
License, Which Permits unrestricted use, distribution, and reproduction in any medium, provided the original author
and source are credited
Abstract— The construction sector in Indonesia is still having a high number of fatal accidents nationwide
approximately 32% of all accidents and lately tends to increase. Reducing the number of accidents required a
comprehensive understanding of how and why the event occurred. From the management process, one of the
ways to reduce the number of accidents is by conducting safety planning during pre-construction phase. In
construction projects, costs, and building structures have been planned since the pre-construction phase.
However, the safety aspects are generally planned at the stage of construction by contractors. According to
recommendations from several experts [2] ; [14]; [11]; and [18], construction safety planning should be carried
out as early as possible (called pre-construction safety planning), as well as structural planning and costs.
Furthermore, to be able to find out whether a pre-construction safety plan has been sufficient or not, an
assessment tool is needed. The assessment tool must meet the requirements, which are valid, reliable and easy to
use. Pre – construction safety planning assessment model used in this study was Maturity Index of Pre-
construction Safety Planning (MISAP) by [9]. This model has adequate numbers of validity and reliability.
However, it still requires further verification in its usage. Therefore, this study was proposed to verify the MISAP
to construction projects in Universitas Negeri Semarang (UNNES). The results of this study are expected to
calculate the validity and reliability of the instrument (MISAP). In addition, it could assess the quality of the
project safety planning at UNNES.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–2
The validity and reliability of the instrument (MISAP) and the project safety-planning index for the construction
projects at UNNES could be obtained. If the index is low, it can provide input or suggestions to improve pre –
construction safety planning. Therefore, the potential for accidents is smaller and it is expected that that
construction accidents do not occur. Other benefits are to increase in Indonesia's image in the international forum
in terms of safety planning. The results of this study showed that: (a) The maturity of the pre-construction safety
planning of projects in 2018 in UNNES was categorized as under developed, (b) The content validity of the
previous research instruments still required improvement from new regulations, (c) the reliability of previous
research instruments can categorized as sufficient.
Keywords— implementation; planning; safety; pre-construction; UNNES project;
I. INTRODUCTION
The construction project is a complex and unique project involving various parties such as the owner, a consultant,
a contractor and a sub-contractor, supplier, and government who have an interest in the results. The construction
parties based on their skills consist of construction experts, mid-level staff and labor, the last two parties mostly
have inadequate competencies. Project locations are mostly in the open area, which are very directly affected by
nature such as heat, rain, day and night, wind, floods and the like which means it is difficult to be fully controlled.
In terms of time, many projects must be completed in a limited duration so that it requires extra-strict
management.
The construction sector still has poor performance in terms of occupational health and safety (OHS). The
occupational Health and Safety in Indonesia occupy the fifth position, or the worst in Asean (Bali Post,
13/05/2004). The position until the end of 2008 did not change much by referring to [1]. [1] states that the
number of occupational accidents in Indonesia is the 52nd position out of 53 countries surveyed with accident
rates in the construction sector. Therefore, accident prevention construction requires serious attention to
decrease the number of accidents in Indonesia and improve Indonesia's image in terms of occupational health and
safety.
A good construction safety requires a safety plan that has been prepared before the construction phase, which is
often called pre-construction safety planning. In Indonesia, this pre-construction safety planning is not yet
common. A number of frequent accidents are allegedly due to the absence of pre - construction safety planning.
The recommendation from [2], [14], [11], and [18] is to conduct construction safety planning as early as possible.
Furthermore, the safety plan must be conducted during the construction / operation stage [12]. In its
implementation, the construction safety must also be controlled so that the pre – construction safety planned is
really carried out.
In 2008, the Ministry of Public Works issued the Ministry Regulation No. 09 / PER / M / 2008 which regulates that
a safety plan must be made by participants in the auction of a construction project. At present, the regulation has
started to be implemented. The regulation was then refined with the Ministry Regulation No. 05 / PRT / M / 2014.
Through the regulation, the government has indeed required the Occupational Safety Plan Contract (RK3K) since
the pre-construction stage. However, its implementation requires more monitoring. As in Article 4 paragraph 3,
the implementation of construction safety is conducted during pre-construction phase includes conceptual design,
feasibility studies, surveys, investigations, DED, and the selection of service providers (ISC). The regulations have
been ready.
The problems in this study were formulated as follows: How to assess the readiness of the pre-construction safety
plan? Has construction safety plan been implemented properly? Current assessment issues play an important role
in every activity. To assess the pre-construction safety planning maturity, there must be an instrument / model of
assessment. The valuation model must meet the requirements: valid and reliable. At overseas, CDM (Construction
Design Management) and Process Protocol are implemented to assess to maturity of the preconstruction safety
planning. In Indonesia, [7] has developed a pre-construction safety planning maturity assessment model. This
model was refined several times and has been validated on construction projects in the Central Java. The model
was named Maturity Index of Pre-construction Safety Planning (MISAP). In this study, review of MISAP was
conducted to investigate its validity and reliability and whether the indicators were still relevant to the current
situation. Then the instrument was implemented for medium-rise construction projects (one to four floors).
The problems of this study were: (1) How is the content validity of the preconstruction safety planning maturity
assessment instrument? (reviewing key factors and variables) (2) How is the reliability of the preconstruction
safety planning maturity assessment instrument? (3) What is the maturity level of pre-construction safety
planning for projects at Universitas Negeri Semarang in 2018?
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–3
II. PLANNING, PLANNING MATURITY, AND ASSESSMENT
One effort to ensure the implementation of occupational health and safety is a good / mature pre-construction
safety plan. Furthermore, assessing the pre - construction safety plan requires a good assessment instrument.
According to [13], a good assessment tool is valid, reliable, and practical. In this modern age, systematic
assessment is required [16]. A quality management system based on a continuous improvement process involves
assessment-analysis-improvement [19]. [10] argues that decision making must be based on facts / data and not
based on opinion, while data can be obtained from assessments. Assessment is a systematic and sustainable
method of collecting and analysing information from various sources about a program and assessing program
results [17]. Assessment is performed to find out the level of performance or achievements of the subjects
assessed. With the results of the assessment, it will be able to know which ones are good / mature and which ones
have not. Ward (1980) states that an assessment process must be accountable for its validity and reliability.
Validity is an ability of a test instrument that can measure what is meant to measure, and reliability is the
regularity of assessment in measuring what will be measured. The validity of the assessment instrument consists
of face validity, content validity, construct validity, concurrent validity, and predictive validity [15].
Maturity, according to the dictionary (dictionary.reference.com), is development of a full, perfect condition, and
mature consideration to bring a plan, status or quality which has developed. According to [5], maturity plans are
plans that have been carefully considered. In this study, maturity was interpreted as a statement of the perfection
of a pre – construction safety plan. Index is a numerical or mathematical symbol that describes the level or
position of a variable. A variable is a phenomenon or phenomenon under study. Index means the degree of
strength of a variable, which starts from a basic level constructed in a way that the it is easy to understand and
compare. The index is used for various variables, such as salaries and prices, ultra violet levels of sunlight,
intelligence index, growth index, and so on. Indexes can be arranged in a variety of ways, ranging from 0 to 10 and
starting from 0 to 100. The index used in this study started from 0% to 100% because it is easy to use and in line
with the scores of other similar assessments. Therefore, the relationship and comparison can be analyzed.
Previous studies in Indonesia on the model of pre-construction safety planning maturity assessment instruments
were carried out by [7] (2009, 2011, and 2013) and has produced the pre-construction safety planning maturity
assessment instrument which were named MISAP. This model has been validated by involving 74 construction
projects and the results are: (a) the model has content validity, with the involvement of academics and
practitioners through three phases of Delphi method, (b). this model has construct validity analyzed by PLS, 27
items out of 40 item were valid, (c ) the model has fulfilled the reliability requirements of the instrument with the
reliability of 0.856 (for owner factors), 0.867 (for consultant factors), 0.892 (for the contractor factor ), and 0.891
(for the stakeholder factor), (d) the assessment was performed manually or by using computer.
In this study, the MISAP model was reviewed and then used to assess the level of maturity of pre-construction
planning on projects at UNNES in 2018. The results of the research were used to improve the management of
projects in the UNNES to comply with safety requirements. With the issue of Public Work Ministry Regulation
No.05 / PRT / M / 2014, it is necessary to update the MISAP indicators according to the new regulation.
III.METHOD OF THE STUDY
This study was an applied research because the focus was on practical needs. This study applied an existing
assessment instrument and adjusted it to the enactment of government regulations (in this case Public Work
Ministry Regulation PU no. 05 / PRT / M / 2014). In its implementation, this study employed a mixed approach.
According to [3], mixed approach is a research approach that uses both quantitative and qualitative methods. The
study took place on the construction projects in Universitas Negeri Semarang in the 2018 fiscal year. All projects
were used as a sample (total sampling) considering its small amount. The procedures of the study consisted of 5
stages: (1) information-gathering phase, (2) the stage of developing the instrument (3) the stage of collecting data
through observation and documentation (4) data analysis stage (5) the stage of preparation of the research
results.
The variable in this study was the maturity of pre- construction safety planning. This variable was a mono variable
which can then be grouped into these following key factors that played a role in pre-construction safety planning:
1) The role of owner (OW ) which includes various variables from the Owner. . These aspects are coded:
OW1, OW2 , OW3, and etc.
2) The role of the consultant (KS) which includes various variables from the consultant. These aspects are
coded: KS 1, KS 2 , KS 3 , and etc.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–4
3) The role of the contractor (KN) which includes various variables from the contractor. These aspects are
coded: KN1, KN2 , KN3 , and etc.
4) The role of stakeholders (ST ) which includes various variables from Stakeholder both physical and non-
physical. These aspects are given code: ST 1, ST 2, ST 3 , and etc.
Data collection employed documentation, observation, and the Delphi method. Documentation was used to
revealed the background of the project / samples and review regulation relevant to the topic of research.
Observation was used to assess the maturity of the pre-construction safety planning at the projects in UNNES. The
Delphi method was a method that revealed subjective considerations about the possibility of occurrences of future
events on the basis of related events (Dunn, 1981). It involved a structured process for gathering and filtering
knowledge from a group of experts for the help of a series of question lists with controlled feedback [21]. This
technique was used to ask experts to discuss systematically a complex problem with a series of questionnaires
sent by post or by computer system to a select group of experts. Generally, the number of stages is between two
and seven and the number of participants are between two and fifteen people (Yueng, 2009). In this study, two
Delphi methods were used with four participants, all participants were doctors in the field of Construction
Management who were relevant to the topic of this study.
Quantitative data analysis used mathematical analysis and statistical analysis. The formula to calculate the
maturity of the pre-construction planning of projects at UNNES in 2018 was called MISAP. MISAP was an index
calculation method generated from [9].
MISAP = 0,9 

6
1n
OWi + 0,6875 

8
1n
KSi + 0,7 

9
1n
KNi + 0,7 

4
1n
STi
The pre-construction safety planning maturity criteria (MISAP) are as follows:
0% < MISAP <20% is undeveloped,
20% <MISAP <40% is under developed,
40% <MISAP <60% is less developed,
60% <MISAP <80% is developed, and
80% <MISAP <100% is really developed.
The mathematical calculation formula above can be made into forms that can be used manually, can also be
created using EXCEL program so that it can be operated with a computer.
IV. THE RESULTS OF THE STUDY
A. Text Font of Entire Document
The study was conducted from May to September in 2018. The study was conducted at the projects in UNNES in
2018. The scope of the study was limited to the pre-construction project stage ( upstream ), that was the stage
between of conception and auction (procurement), as well as in projects with the conventional delivery patterns:
DBB (design-bid- built). The names of the projects on this study are shown in Table 1.
TABLE I - Lists of Projects in Universitas Negeri Semarang in 2018
No. The project name Contract value (Rp) Service Provider Information
1.a. 3rd Phase of Library Building
Construction at Unnes
Rp. 25,324,016,000
Procurement Document No:
1.4.6/UN37.7.11/TU/2018 June 4, 2008
PT Sumber Alam
Sejahtera
ed?
The next project is
called PSTa
1.b 3rd Phase of Construction
Management of Library
Building at Unnes
Rp. 587,537,500
Procurement Document No.
1.9.4/UN37.7.1.6/TU/2018,April 9, 2018
PT Bina Karya The next project is
called PSTb
2 2nd Phase of the Badminton
Building Renovation at
Pegandan Campus of
Universitas Negeri Semarang
Rp. 1,409,500,000
Procurement Document No:
1.27.4/UN37.7.11/TU/2018,17,April 2018
CV Insan Mandiri The new project is
then called PGD
3 Construction of roof of futsal
building, Universitas Negeri
Semarang
Rp. 6,731,840,000
Procurement Document No.
1.5.6/UN37.7.11/TU/2018 June 5, 2018
PT Harmony
International
Technology
The next project is
called PIK
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–5
The results of the observation on the occupational health and safety at the construction projects at UNNES in 2018
can be summarized as follows. In the PST project, this project was a continuation project from the previous year.
The parts of the building which was being constructed were not the structures but was located at a certain height.
From observing procurement documents No. 1.4.6 / UN37.7.11 / TU / 2018 dated June 4th, 2008, there is a clause
on Occupational Health and Safety Construction. However, it still did not comply with Ministry of Public Work
Regulation number 05 / PRT / M / 2014 regarding OHS construction, preparation of hazard identification in DED,
the inclusion of potential hazards and assessment criteria to fulfil OHS construction requirements. In addition, the
owner in selecting consultants and contractors have not included the performance of OHS in construction. There
was no schedule for the owner to review and monitor the implementation of OHS in the construction site.
Furthermore, a perimeter fence has been built around the construction site. However, it appears that the
obligation to use Personal Protection Equipment (PPE) has not been obeyed by workers. Horizontal and vertical
net were absent. Safety briefing and patrol were not performed. OHS planning by consultants and contractors
were not performed due to the project owner's lack of control. In the PGD project, this project was also a follow-up
project from last year. The parts of the building that were being constructed are not structures. Based on the
procurement document No. 1.27.4 / UN37.7.11 / TU / 17th of April 2018, there is a clause about Construction OHS.
However, it is not in line with the Ministry of Public Work Regulation number 05 / PRT / M / 2014 concerning
construction OHS staffs, preparation of hazard identification in DED, the inclusion of potential hazards and
assessment criteria to fulfil OHS construction requirements. In addition, the owner in selecting consultants and
contractors have not included the performance of OHS in construction. There was no schedule for the owner to
review and monitor the implementation of OHS in the construction site. Furthermore, a perimeter fence has been
built around the construction site. However, it appears that the obligation to use Personal Protection Equipment
(PPE) has not been obeyed by workers. This building only has one floor, but because it is building for physical
exercise and meeting, the potential danger can be included in the two-storey building.
The PIK Project is a continuation of the previous year project. The part of the building that was being constructed
was the making / connecting of columns and the construction of the roof. It was a structural work and was located
at a certain height. Based on the procurement document No. 1.5.6 / UN37.7.11 / TU / 2018 dated June 5th, 2018,
there is a clause about Construction OHS. However, it is not in line with the Ministry of Public Work Regulation
number 05 / PRT / M / 2014 concerning construction OHS staffs, preparation of hazard identification in DED, the
inclusion of potential hazards and assessment criteria to fulfil OHS construction requirements. The results of
assessment recapitulation of the development of the pre- construction safety planning on projects in UNNES in
2018 can be illustrated in figure 1.
100
80
60
50
40
20
0
PROYEK PST PGD PIF
Fig. 1 Maturity pre- construction safety planning at UNNES projects in 2018
The results showed these following: MISAP for PST = 55,425; MISAP for PGD = 41,625; and MISAP for PIK =
42,745 with mean = 46,56. All of them are in the underdeveloped category.
55,425
42,745
Mean: 46,56
80% < MISAP < 100% Really developed
60% < MISAP < 80% developed
40% < MISAP < 60% Less developed
20% < MISAP < 40% Under developed
0% < MISAP < 20% Undeveloped
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–6
In addition, the owner in selecting consultants and contractors have not included the performance of OHS in
construction. There was no schedule for the owner to review and monitor the implementation of OHS in the
construction site. Furthermore, a perimeter fence has been built around the construction site. However, it appears
that the obligation to use Personal Protection Equipment (PPE) has not been obeyed by workers. This shows that
OHS planning by consultants and contractors were not performed due to the project owner's lack of control.
V. THE REVIEW OF THE PREVIOUS INSTRUMENT BASED ON THE DEVELOPMENT OF REGULATION
The instrument used in this study was the Maturity Index of Safety Planning (MISAP) by [9]. Some quality
components of the instrument are: a. Content validity: based on the review of Minister of Public Works Regulation
number 05 / PRT / M / 2014 and a circular letter from the Minister of Public Works number 66 / SE / M / 2015
dated December 3, 2015, then the content validity of the instruments need to be evaluated again. To summarize
the additional points of regulation, the Delphi method was carried out by giving a questionnaire to the
participants in the first round. Based on the responses on the first round, the answers were summarized and then
sent back to the participants for the second round. The results of the second round were expected to have points
agreed upon by all participants. Some variables that need to be added to improve the previous instrument, from
the results of the Delphi method are: (1) the necessity of calculating OHS costs on project cost proposal included
in general costs (Circular of Public Work Ministry No. 66 / SE / M / 2015). And (2) Occupational Safety Plan
Contract preparation and presentation by contractors (Ministry Regulation No. 05 / / PRT / M / 2014).
b. Construct validity. The number of projects was three, construct validity calculation is not sufficient. Therefore,
the validity used in this study was from the previous study such as: Owner Role Validity = 0.599; Validity of the
Consultant Role = 0.723; Contractor Role Validity = 0.763; Validity of Stakeholder Roles = 0.576. The calculation
was performed using SEM-PLS program (Structural Equation Model - Partial Least Square). The basis for decision-
making validity tests was that the correlation value was greater than 0.70. However, on the research and the
development design, the scale of loading factors from 0.50 - 0.60 is still acceptable [20]. Because all validity scores
above 0.50, the instruments were categorized as valid.
c. Reliability. The composite Reliability and Cronbach Alpha of instrument on the previous study were as follows:
the role owner reliability = 0.846; reliability of the consultant role = 0.835; contractor role reliability = 0.891;
stakeholder role reliability = 0.891. According to [20], a construct is categorized as reliable if the value of
composite reliability and cronbach alpha is above 0.70. Because all reliability scores above 0.70, the instrument
was categorized as reliable.
VI. DISCUSSION
The following is a discussion of the results of the study. a. The maturity of the pre-construction safety planning for
UNNES projects in 2018 on average is categorized as under - developed categories (score 46.56). This shows that
improvement is required on the safety planning at the pre- construction stage, both for the Owner, Consultants,
Contractors and Stakeholders. The Owners, Consultants, and Contractors need to learn the newly issued
regulations to be implemented immediately. These regulations include Public Work Ministry Regulation No. 05 / /
PRT / M / 2014) and Circular Letter of Public Work Ministry Regulation No. 66 / SE / M / 2015. The role of the
Owner and Consultant still seems minimal. The owner can make a decision to improve construction safety from
the conception stage. Fink (1997) argues that the owner can participate in controlling through the proposal
submitted by contractors. Next, the architects and planning engineers can improve the construction safety in the
design process. In the UK, although the Construction Design Management has been implemented for more than 10
years, until 2006 planners still lacked in utilizing their potential to eliminate and reduce risk in the workplace
(www.hse.Gov.uk downloaded 20/09/2006). In USA, there is less motivation from professional designers to adopt
safe design concepts because they assume that safety is included as the job of contractor according to Behm
(2005). Behm (2005) also states that the effect of planning on construction safety is lost if planning are not carried
out until the construction phase takes place.
b. The validity of the assessment instrument: the following variables must be added on the content validity: the
compulsory calculation of OHS costs on project cost proposal included in general costs (Circular of Public Work
Ministry No. 66 / SE / M / 2015), and Occupational Safety Plan Contract Preparation & presentation by
contractors (Ministry Regulation No. 05 / PRT / / M / 2014). In construct validity, the instrument of this study has
sufficient numbers of construct validity which was above 0.50 (>0.50). With sufficient numbers of validity, this
instrument can be used to measure what should be measured. c. Reliability of the instrument, the reliability of this
assessment instrument has sufficient reliability value, which is above 0,70 (> 0.70). With sufficient reliability
value, this instrument can be used consistently, meaning that it is used at various times and used by various
people when tested on one object, the results are relatively similar.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–7
d. Occupational health and safety at construction in general, pre – construction safety planning is an accident
prevention efforts using the upstream approach. The prevention of accidents in construction projects in Indonesia
are mostly conducted using the downstream approach. This phenomenon occurs in both developing countries and
countries that have implemented construction safety. Construction Occupational Health and Safety in Indonesia is
still a concern. The number of fatal accidents tends to increase annually as shown in Table 2
TABLE III - FATAL WORKPLACE ACCIDENTS IN INDONESIA
Year 2001 2003 2005 2011 2015 2016
Total cases 104,774 105,846 99,203 108,696 105,182 101,367
Fatality 1,768 1,748 2,045 31,195 2,375 2,382
Percentage of fatality to total case (p) 1.69% 1.65% 2.07% 2.87% 2.16% 2.35%
It implies that there is a need for socialization to all parties in construction safety regarding the importance of safe
design and pre-construction safety planning. Ways of socialization are by submitting the results of this study to
the various stakeholders, writing in professional journals and at seminars, and can also conduct training. It
implies that there is a need for socialization to all parties in construction safety regarding the importance of safe
design and pre-construction safety planning. Ways of socialization are by submitting the results of this study to
the various stakeholders, writing in professional journals and at seminars, and can also organize training or
workshops in collaboration with relevant agencies and institutions. The further effect that can be expected is the
decline in the number of construction accidents in Indonesia and the increasing image of Indonesia in terms of
work safety.
VII. CONCLUSION AND SUGGESTION
The conclusions of this study are:
a. Construction safety in Indonesia is still low and some efforts are needed to improve it.
b. Pre-construction safety planning for projects in UNNES in 2018 was categorized as underdeveloped
c. With the new regulation, the content validity of the pre-construction safety assessment instruments still
needs to be refined. Improvements were made with the addition of the regulations listed in Ministry of Public
Work Regulation number 05 / PRT / M / 2014 and Circular Letter of Ministry of Public Work No. No. 66 / SE
/ M / 2015.
d. The reliability of the pre-construction safety assessment instrument currently in use is still usable.
The following are the suggestions based on the results of the study:
a. Pre-construction safety planning for projects at UNNES in 2018 needs to be improved. Improvement can be
performed by entering OHS clauses in the auction document. Consultants need to be more professional in
making technical specifications by incorporating specific OHS aspects.
b. It is necessary to provide sufficient funds for the implementation of OHS construction in accordance with the
mandate of Ministry of Public Work Regulation number 05 / PRT / M / 2014 and Circular Letter of Ministry
of Public Work No. No.66 / SE / M / 2015.
c. It is recommended to carry out further validation of the pre-construction safety assessment instrument.
d. It is recommended that Unnes provides personnel who handle OHS construction problems in the UNNES
environment, which will be able to help direct the realization of OHS regulations on UNNES projects, or even
on some projects outside the UNNES
REFERENCES
[1] Arka, Bahan – bahan Lokakarya K3 Konstruksi, 2008
[2] Barrie, Donald S. et. al., Manajemen Konstruksi Profesional, Terjemahan oleh Sudinarto, Jakarta, Penerbit
Erlangga, 1990.
[3] Creswell, Research Design: Qualitative, Quantitative, and Mixed Methods Approaches, London, SAGE
Publication, 2003.
[4] Davies, V J and K. Tomasin, Construction safety Handbook, London, Thomas Telford Publishing, 1996.
[5] Echols, John M dan Hassan Shadily, Kamus Inggris-Indonesia, Jakarta, PT Gramedia, Hal. 375, 1990.
[6] Efansyah, M. Noor, OHSAS 18001:1999- Sistem Manajemen Kesehatan dan Keselamatan Kerja (Modul
Pelatihan), Yogyakarta, Deras Training Center, 2007.
[7] Endroyo, Bambang, Studi Tentang Model Penilaian Kematangan Perencanaan Keselamatan Pada Tahap Pra
Konstruksi, Untuk Mitigasi Kecelakaan Konstruksi, Laporan Penelitian, Semarang: UNNES, 2009.
[8] Endroyo, Bambang, Verifikasi-Validasi Lanjut Model Penilaian Kematangan
Perencanaan Keselamatan Pra Konstruksi, Laporan Penelitian, Semarang: UNNES, 2011.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163
Issue 01, Volume 6 (January 2019) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco
(2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35
IJIRAE © 2014- 19, All Rights Reserved Page–8
[9] Endroyo, Bambang, Pengembangan Model Penilaian Perencanaan Keselamatan Pra konstruksi Dengan
Pendekatan matematik dan Penerapan Diagram Radar, Laporan Penelitian. Semarang, UNNES, 2013.
[10] Gaspersz, Vincent, Total Quality Management, Jakarta: Gramedia Pustaka Utama, 2003.
[11] Hinze, W Jimmie., Construction Safety. Prentice-Hall, Inc, 1997.
[12] Koehn, Enno et. al. Safety in Developing Countries: Professional and Bureaucratic Problems. Journal of
Construction Engineering and Management, September 1995 hal. 261 – 265, 1995
[13] Mardapi, Djemari., Teknik Penyusunan Instrumen Tes dan Non Tes. Yogyakarta: Penerbit Mitra Cendikia,
2008.
[14] Oberlender, Garold D., Project Management. 2000
[15] Purwanto., Evaluasi Program Diklat. Jakarta: Sekolah Tinggi Ilmu Administrasi Negara, 1999
[16] Rossi, Peter H and Howard E. Freeman., California: Evaluation, A Systematic Approach. SAGE Publication, Inc,
1985.
[17] Selim, Bisma R and Julia Pet-Armacost., Program Assessment Handbook. Florida: University of Central, 2004.
[18] Suraji, Akhmad and A. Roy Duff., Constraint-Response Theory of Construction Accident Causation, The
International Conference on Designing for Safety, ECI/CIB/HSE, London, 2000
[19] Suardi, Rudi (2005). Sistem Manajemen Keselamatan & Kesehatan Kerja. Jakarta: Penerbit PPM.
[20] Ghozali, I., Structural equation modeling: Metode alternatif dengan partial least square (pls). Badan Penerbit
Universitas Diponegoro, 2008.
[21] Adler, M., & Ziglio., Gazing into the oracle: The Delphi method and its application to social policy and public
health. Jessica Kingsley Publishers, 1996.

More Related Content

What's hot

STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRYSTUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
IAEME Publication
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
ijtsrd
 
Final Report- Betterment of EHS Conditions- Daniyal
Final Report- Betterment of EHS Conditions- DaniyalFinal Report- Betterment of EHS Conditions- Daniyal
Final Report- Betterment of EHS Conditions- Daniyal
Muhammad Daniyal
 
Ijmet 10 01_190
Ijmet 10 01_190Ijmet 10 01_190
Ijmet 10 01_190
IAEME Publication
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
IAEME Publication
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
Rifan Fhazi
 

What's hot (19)

Amelioration of safety management in infrastructure projects
Amelioration of safety management in infrastructure projectsAmelioration of safety management in infrastructure projects
Amelioration of safety management in infrastructure projects
 
50120140507007
5012014050700750120140507007
50120140507007
 
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
 
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRYSTUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
STUDY ON ENHANCEMENT OF HUMAN SAFETY PROTECTION FACTORS IN CONSTRUCTION INDUSTRY
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
 
IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET- Study of Innovative Technologies for Effective Construction and Manage...IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET- Study of Innovative Technologies for Effective Construction and Manage...
 
Final Report- Betterment of EHS Conditions- Daniyal
Final Report- Betterment of EHS Conditions- DaniyalFinal Report- Betterment of EHS Conditions- Daniyal
Final Report- Betterment of EHS Conditions- Daniyal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
Ijmet 10 01_190
Ijmet 10 01_190Ijmet 10 01_190
Ijmet 10 01_190
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 

Similar to A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING IN THE CONSTRUCTION PROJECTS IN UNIVERSITAS NEGERI SEMARANG IN 2018

Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
A Makwana
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
Sibo Kanyambari Aimable
 

Similar to A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING IN THE CONSTRUCTION PROJECTS IN UNIVERSITAS NEGERI SEMARANG IN 2018 (20)

Health and Safety Framework Using Analytic Hierarchy Process For Construction...
Health and Safety Framework Using Analytic Hierarchy Process For Construction...Health and Safety Framework Using Analytic Hierarchy Process For Construction...
Health and Safety Framework Using Analytic Hierarchy Process For Construction...
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Occupational health and safety (ohs) management vis à-vis different phases of...
Occupational health and safety (ohs) management vis à-vis different phases of...Occupational health and safety (ohs) management vis à-vis different phases of...
Occupational health and safety (ohs) management vis à-vis different phases of...
 
Site Safety Management and planning for Building Construction
Site Safety Management and planning for Building ConstructionSite Safety Management and planning for Building Construction
Site Safety Management and planning for Building Construction
 
Riskanalysisin housingindustry (1)
Riskanalysisin housingindustry (1)Riskanalysisin housingindustry (1)
Riskanalysisin housingindustry (1)
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Ijertv7 is090066
Ijertv7 is090066Ijertv7 is090066
Ijertv7 is090066
 
The Impact of Skilled and Unskilled Labour in Construction Industry in India
The Impact of Skilled and Unskilled Labour in Construction Industry in IndiaThe Impact of Skilled and Unskilled Labour in Construction Industry in India
The Impact of Skilled and Unskilled Labour in Construction Industry in India
 
BIM as a Design and Safety Tool for Construction Projects
BIM as a Design and Safety Tool for Construction ProjectsBIM as a Design and Safety Tool for Construction Projects
BIM as a Design and Safety Tool for Construction Projects
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
C1303032126
C1303032126C1303032126
C1303032126
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
 
Construction health and safety model towards adoption | IJB 2022
Construction health and safety model towards adoption | IJB 2022Construction health and safety model towards adoption | IJB 2022
Construction health and safety model towards adoption | IJB 2022
 
Case Study on Health and Safety Knowledge and Compliance on Construction Site
Case Study on Health and Safety Knowledge and Compliance on Construction SiteCase Study on Health and Safety Knowledge and Compliance on Construction Site
Case Study on Health and Safety Knowledge and Compliance on Construction Site
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 

More from AM Publications

ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISESANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
AM Publications
 
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENTSIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
AM Publications
 

More from AM Publications (20)

DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
 
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
 
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGNTHE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
 
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
 
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
 
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISESANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
 
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
 
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
 
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITIONHMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
 
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
 
INTELLIGENT BLIND STICK
INTELLIGENT BLIND STICKINTELLIGENT BLIND STICK
INTELLIGENT BLIND STICK
 
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
 
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
 
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
 
OPTICAL CHARACTER RECOGNITION USING RBFNN
OPTICAL CHARACTER RECOGNITION USING RBFNNOPTICAL CHARACTER RECOGNITION USING RBFNN
OPTICAL CHARACTER RECOGNITION USING RBFNN
 
DETECTION OF MOVING OBJECT
DETECTION OF MOVING OBJECTDETECTION OF MOVING OBJECT
DETECTION OF MOVING OBJECT
 
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENTSIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
 
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
 
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
 
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
 

Recently uploaded

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Recently uploaded (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING IN THE CONSTRUCTION PROJECTS IN UNIVERSITAS NEGERI SEMARANG IN 2018

  • 1. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–1 A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING IN THE CONSTRUCTION PROJECTS IN UNIVERSITAS NEGERI SEMARANG IN 2018 Tugino* Civil Engineering Department, Universitas Negeri Semarang, INDONESIA tugino60@gmail.com Aris Widodo Civil Engineering Department, Universitas Negeri Semarang, INDONESIA ariswidodo71@mail.unnes.ac.id Harijadi Gunawan Buntoro Wahyono Civil Engineering Department, Universitas Negeri Semarang, INDONESIA hariyadi_gbw@mail.unnes.ac.id Bambang Endroyo Civil Engineering Department, Universitas Negeri Semarang, INDONESIA bb.endroyo@gmail.com Manuscript History Number: IJIRAE/RS/Vol.06/Issue01/JAAE10080 Received: 22, December 2018 Final Correction: 03, January 2019 Final Accepted: 12, January 2019 Published: January 2019 Citation: Editor: Dr.A.Arul L.S, Chief Editor, IJIRAE, AM Publications, India Copyright: ©2019 This is an open access article distributed under the terms of the Creative Commons Attribution License, Which Permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited Abstract— The construction sector in Indonesia is still having a high number of fatal accidents nationwide approximately 32% of all accidents and lately tends to increase. Reducing the number of accidents required a comprehensive understanding of how and why the event occurred. From the management process, one of the ways to reduce the number of accidents is by conducting safety planning during pre-construction phase. In construction projects, costs, and building structures have been planned since the pre-construction phase. However, the safety aspects are generally planned at the stage of construction by contractors. According to recommendations from several experts [2] ; [14]; [11]; and [18], construction safety planning should be carried out as early as possible (called pre-construction safety planning), as well as structural planning and costs. Furthermore, to be able to find out whether a pre-construction safety plan has been sufficient or not, an assessment tool is needed. The assessment tool must meet the requirements, which are valid, reliable and easy to use. Pre – construction safety planning assessment model used in this study was Maturity Index of Pre- construction Safety Planning (MISAP) by [9]. This model has adequate numbers of validity and reliability. However, it still requires further verification in its usage. Therefore, this study was proposed to verify the MISAP to construction projects in Universitas Negeri Semarang (UNNES). The results of this study are expected to calculate the validity and reliability of the instrument (MISAP). In addition, it could assess the quality of the project safety planning at UNNES.
  • 2. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–2 The validity and reliability of the instrument (MISAP) and the project safety-planning index for the construction projects at UNNES could be obtained. If the index is low, it can provide input or suggestions to improve pre – construction safety planning. Therefore, the potential for accidents is smaller and it is expected that that construction accidents do not occur. Other benefits are to increase in Indonesia's image in the international forum in terms of safety planning. The results of this study showed that: (a) The maturity of the pre-construction safety planning of projects in 2018 in UNNES was categorized as under developed, (b) The content validity of the previous research instruments still required improvement from new regulations, (c) the reliability of previous research instruments can categorized as sufficient. Keywords— implementation; planning; safety; pre-construction; UNNES project; I. INTRODUCTION The construction project is a complex and unique project involving various parties such as the owner, a consultant, a contractor and a sub-contractor, supplier, and government who have an interest in the results. The construction parties based on their skills consist of construction experts, mid-level staff and labor, the last two parties mostly have inadequate competencies. Project locations are mostly in the open area, which are very directly affected by nature such as heat, rain, day and night, wind, floods and the like which means it is difficult to be fully controlled. In terms of time, many projects must be completed in a limited duration so that it requires extra-strict management. The construction sector still has poor performance in terms of occupational health and safety (OHS). The occupational Health and Safety in Indonesia occupy the fifth position, or the worst in Asean (Bali Post, 13/05/2004). The position until the end of 2008 did not change much by referring to [1]. [1] states that the number of occupational accidents in Indonesia is the 52nd position out of 53 countries surveyed with accident rates in the construction sector. Therefore, accident prevention construction requires serious attention to decrease the number of accidents in Indonesia and improve Indonesia's image in terms of occupational health and safety. A good construction safety requires a safety plan that has been prepared before the construction phase, which is often called pre-construction safety planning. In Indonesia, this pre-construction safety planning is not yet common. A number of frequent accidents are allegedly due to the absence of pre - construction safety planning. The recommendation from [2], [14], [11], and [18] is to conduct construction safety planning as early as possible. Furthermore, the safety plan must be conducted during the construction / operation stage [12]. In its implementation, the construction safety must also be controlled so that the pre – construction safety planned is really carried out. In 2008, the Ministry of Public Works issued the Ministry Regulation No. 09 / PER / M / 2008 which regulates that a safety plan must be made by participants in the auction of a construction project. At present, the regulation has started to be implemented. The regulation was then refined with the Ministry Regulation No. 05 / PRT / M / 2014. Through the regulation, the government has indeed required the Occupational Safety Plan Contract (RK3K) since the pre-construction stage. However, its implementation requires more monitoring. As in Article 4 paragraph 3, the implementation of construction safety is conducted during pre-construction phase includes conceptual design, feasibility studies, surveys, investigations, DED, and the selection of service providers (ISC). The regulations have been ready. The problems in this study were formulated as follows: How to assess the readiness of the pre-construction safety plan? Has construction safety plan been implemented properly? Current assessment issues play an important role in every activity. To assess the pre-construction safety planning maturity, there must be an instrument / model of assessment. The valuation model must meet the requirements: valid and reliable. At overseas, CDM (Construction Design Management) and Process Protocol are implemented to assess to maturity of the preconstruction safety planning. In Indonesia, [7] has developed a pre-construction safety planning maturity assessment model. This model was refined several times and has been validated on construction projects in the Central Java. The model was named Maturity Index of Pre-construction Safety Planning (MISAP). In this study, review of MISAP was conducted to investigate its validity and reliability and whether the indicators were still relevant to the current situation. Then the instrument was implemented for medium-rise construction projects (one to four floors). The problems of this study were: (1) How is the content validity of the preconstruction safety planning maturity assessment instrument? (reviewing key factors and variables) (2) How is the reliability of the preconstruction safety planning maturity assessment instrument? (3) What is the maturity level of pre-construction safety planning for projects at Universitas Negeri Semarang in 2018?
  • 3. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–3 II. PLANNING, PLANNING MATURITY, AND ASSESSMENT One effort to ensure the implementation of occupational health and safety is a good / mature pre-construction safety plan. Furthermore, assessing the pre - construction safety plan requires a good assessment instrument. According to [13], a good assessment tool is valid, reliable, and practical. In this modern age, systematic assessment is required [16]. A quality management system based on a continuous improvement process involves assessment-analysis-improvement [19]. [10] argues that decision making must be based on facts / data and not based on opinion, while data can be obtained from assessments. Assessment is a systematic and sustainable method of collecting and analysing information from various sources about a program and assessing program results [17]. Assessment is performed to find out the level of performance or achievements of the subjects assessed. With the results of the assessment, it will be able to know which ones are good / mature and which ones have not. Ward (1980) states that an assessment process must be accountable for its validity and reliability. Validity is an ability of a test instrument that can measure what is meant to measure, and reliability is the regularity of assessment in measuring what will be measured. The validity of the assessment instrument consists of face validity, content validity, construct validity, concurrent validity, and predictive validity [15]. Maturity, according to the dictionary (dictionary.reference.com), is development of a full, perfect condition, and mature consideration to bring a plan, status or quality which has developed. According to [5], maturity plans are plans that have been carefully considered. In this study, maturity was interpreted as a statement of the perfection of a pre – construction safety plan. Index is a numerical or mathematical symbol that describes the level or position of a variable. A variable is a phenomenon or phenomenon under study. Index means the degree of strength of a variable, which starts from a basic level constructed in a way that the it is easy to understand and compare. The index is used for various variables, such as salaries and prices, ultra violet levels of sunlight, intelligence index, growth index, and so on. Indexes can be arranged in a variety of ways, ranging from 0 to 10 and starting from 0 to 100. The index used in this study started from 0% to 100% because it is easy to use and in line with the scores of other similar assessments. Therefore, the relationship and comparison can be analyzed. Previous studies in Indonesia on the model of pre-construction safety planning maturity assessment instruments were carried out by [7] (2009, 2011, and 2013) and has produced the pre-construction safety planning maturity assessment instrument which were named MISAP. This model has been validated by involving 74 construction projects and the results are: (a) the model has content validity, with the involvement of academics and practitioners through three phases of Delphi method, (b). this model has construct validity analyzed by PLS, 27 items out of 40 item were valid, (c ) the model has fulfilled the reliability requirements of the instrument with the reliability of 0.856 (for owner factors), 0.867 (for consultant factors), 0.892 (for the contractor factor ), and 0.891 (for the stakeholder factor), (d) the assessment was performed manually or by using computer. In this study, the MISAP model was reviewed and then used to assess the level of maturity of pre-construction planning on projects at UNNES in 2018. The results of the research were used to improve the management of projects in the UNNES to comply with safety requirements. With the issue of Public Work Ministry Regulation No.05 / PRT / M / 2014, it is necessary to update the MISAP indicators according to the new regulation. III.METHOD OF THE STUDY This study was an applied research because the focus was on practical needs. This study applied an existing assessment instrument and adjusted it to the enactment of government regulations (in this case Public Work Ministry Regulation PU no. 05 / PRT / M / 2014). In its implementation, this study employed a mixed approach. According to [3], mixed approach is a research approach that uses both quantitative and qualitative methods. The study took place on the construction projects in Universitas Negeri Semarang in the 2018 fiscal year. All projects were used as a sample (total sampling) considering its small amount. The procedures of the study consisted of 5 stages: (1) information-gathering phase, (2) the stage of developing the instrument (3) the stage of collecting data through observation and documentation (4) data analysis stage (5) the stage of preparation of the research results. The variable in this study was the maturity of pre- construction safety planning. This variable was a mono variable which can then be grouped into these following key factors that played a role in pre-construction safety planning: 1) The role of owner (OW ) which includes various variables from the Owner. . These aspects are coded: OW1, OW2 , OW3, and etc. 2) The role of the consultant (KS) which includes various variables from the consultant. These aspects are coded: KS 1, KS 2 , KS 3 , and etc.
  • 4. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–4 3) The role of the contractor (KN) which includes various variables from the contractor. These aspects are coded: KN1, KN2 , KN3 , and etc. 4) The role of stakeholders (ST ) which includes various variables from Stakeholder both physical and non- physical. These aspects are given code: ST 1, ST 2, ST 3 , and etc. Data collection employed documentation, observation, and the Delphi method. Documentation was used to revealed the background of the project / samples and review regulation relevant to the topic of research. Observation was used to assess the maturity of the pre-construction safety planning at the projects in UNNES. The Delphi method was a method that revealed subjective considerations about the possibility of occurrences of future events on the basis of related events (Dunn, 1981). It involved a structured process for gathering and filtering knowledge from a group of experts for the help of a series of question lists with controlled feedback [21]. This technique was used to ask experts to discuss systematically a complex problem with a series of questionnaires sent by post or by computer system to a select group of experts. Generally, the number of stages is between two and seven and the number of participants are between two and fifteen people (Yueng, 2009). In this study, two Delphi methods were used with four participants, all participants were doctors in the field of Construction Management who were relevant to the topic of this study. Quantitative data analysis used mathematical analysis and statistical analysis. The formula to calculate the maturity of the pre-construction planning of projects at UNNES in 2018 was called MISAP. MISAP was an index calculation method generated from [9]. MISAP = 0,9   6 1n OWi + 0,6875   8 1n KSi + 0,7   9 1n KNi + 0,7   4 1n STi The pre-construction safety planning maturity criteria (MISAP) are as follows: 0% < MISAP <20% is undeveloped, 20% <MISAP <40% is under developed, 40% <MISAP <60% is less developed, 60% <MISAP <80% is developed, and 80% <MISAP <100% is really developed. The mathematical calculation formula above can be made into forms that can be used manually, can also be created using EXCEL program so that it can be operated with a computer. IV. THE RESULTS OF THE STUDY A. Text Font of Entire Document The study was conducted from May to September in 2018. The study was conducted at the projects in UNNES in 2018. The scope of the study was limited to the pre-construction project stage ( upstream ), that was the stage between of conception and auction (procurement), as well as in projects with the conventional delivery patterns: DBB (design-bid- built). The names of the projects on this study are shown in Table 1. TABLE I - Lists of Projects in Universitas Negeri Semarang in 2018 No. The project name Contract value (Rp) Service Provider Information 1.a. 3rd Phase of Library Building Construction at Unnes Rp. 25,324,016,000 Procurement Document No: 1.4.6/UN37.7.11/TU/2018 June 4, 2008 PT Sumber Alam Sejahtera ed? The next project is called PSTa 1.b 3rd Phase of Construction Management of Library Building at Unnes Rp. 587,537,500 Procurement Document No. 1.9.4/UN37.7.1.6/TU/2018,April 9, 2018 PT Bina Karya The next project is called PSTb 2 2nd Phase of the Badminton Building Renovation at Pegandan Campus of Universitas Negeri Semarang Rp. 1,409,500,000 Procurement Document No: 1.27.4/UN37.7.11/TU/2018,17,April 2018 CV Insan Mandiri The new project is then called PGD 3 Construction of roof of futsal building, Universitas Negeri Semarang Rp. 6,731,840,000 Procurement Document No. 1.5.6/UN37.7.11/TU/2018 June 5, 2018 PT Harmony International Technology The next project is called PIK
  • 5. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–5 The results of the observation on the occupational health and safety at the construction projects at UNNES in 2018 can be summarized as follows. In the PST project, this project was a continuation project from the previous year. The parts of the building which was being constructed were not the structures but was located at a certain height. From observing procurement documents No. 1.4.6 / UN37.7.11 / TU / 2018 dated June 4th, 2008, there is a clause on Occupational Health and Safety Construction. However, it still did not comply with Ministry of Public Work Regulation number 05 / PRT / M / 2014 regarding OHS construction, preparation of hazard identification in DED, the inclusion of potential hazards and assessment criteria to fulfil OHS construction requirements. In addition, the owner in selecting consultants and contractors have not included the performance of OHS in construction. There was no schedule for the owner to review and monitor the implementation of OHS in the construction site. Furthermore, a perimeter fence has been built around the construction site. However, it appears that the obligation to use Personal Protection Equipment (PPE) has not been obeyed by workers. Horizontal and vertical net were absent. Safety briefing and patrol were not performed. OHS planning by consultants and contractors were not performed due to the project owner's lack of control. In the PGD project, this project was also a follow-up project from last year. The parts of the building that were being constructed are not structures. Based on the procurement document No. 1.27.4 / UN37.7.11 / TU / 17th of April 2018, there is a clause about Construction OHS. However, it is not in line with the Ministry of Public Work Regulation number 05 / PRT / M / 2014 concerning construction OHS staffs, preparation of hazard identification in DED, the inclusion of potential hazards and assessment criteria to fulfil OHS construction requirements. In addition, the owner in selecting consultants and contractors have not included the performance of OHS in construction. There was no schedule for the owner to review and monitor the implementation of OHS in the construction site. Furthermore, a perimeter fence has been built around the construction site. However, it appears that the obligation to use Personal Protection Equipment (PPE) has not been obeyed by workers. This building only has one floor, but because it is building for physical exercise and meeting, the potential danger can be included in the two-storey building. The PIK Project is a continuation of the previous year project. The part of the building that was being constructed was the making / connecting of columns and the construction of the roof. It was a structural work and was located at a certain height. Based on the procurement document No. 1.5.6 / UN37.7.11 / TU / 2018 dated June 5th, 2018, there is a clause about Construction OHS. However, it is not in line with the Ministry of Public Work Regulation number 05 / PRT / M / 2014 concerning construction OHS staffs, preparation of hazard identification in DED, the inclusion of potential hazards and assessment criteria to fulfil OHS construction requirements. The results of assessment recapitulation of the development of the pre- construction safety planning on projects in UNNES in 2018 can be illustrated in figure 1. 100 80 60 50 40 20 0 PROYEK PST PGD PIF Fig. 1 Maturity pre- construction safety planning at UNNES projects in 2018 The results showed these following: MISAP for PST = 55,425; MISAP for PGD = 41,625; and MISAP for PIK = 42,745 with mean = 46,56. All of them are in the underdeveloped category. 55,425 42,745 Mean: 46,56 80% < MISAP < 100% Really developed 60% < MISAP < 80% developed 40% < MISAP < 60% Less developed 20% < MISAP < 40% Under developed 0% < MISAP < 20% Undeveloped
  • 6. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–6 In addition, the owner in selecting consultants and contractors have not included the performance of OHS in construction. There was no schedule for the owner to review and monitor the implementation of OHS in the construction site. Furthermore, a perimeter fence has been built around the construction site. However, it appears that the obligation to use Personal Protection Equipment (PPE) has not been obeyed by workers. This shows that OHS planning by consultants and contractors were not performed due to the project owner's lack of control. V. THE REVIEW OF THE PREVIOUS INSTRUMENT BASED ON THE DEVELOPMENT OF REGULATION The instrument used in this study was the Maturity Index of Safety Planning (MISAP) by [9]. Some quality components of the instrument are: a. Content validity: based on the review of Minister of Public Works Regulation number 05 / PRT / M / 2014 and a circular letter from the Minister of Public Works number 66 / SE / M / 2015 dated December 3, 2015, then the content validity of the instruments need to be evaluated again. To summarize the additional points of regulation, the Delphi method was carried out by giving a questionnaire to the participants in the first round. Based on the responses on the first round, the answers were summarized and then sent back to the participants for the second round. The results of the second round were expected to have points agreed upon by all participants. Some variables that need to be added to improve the previous instrument, from the results of the Delphi method are: (1) the necessity of calculating OHS costs on project cost proposal included in general costs (Circular of Public Work Ministry No. 66 / SE / M / 2015). And (2) Occupational Safety Plan Contract preparation and presentation by contractors (Ministry Regulation No. 05 / / PRT / M / 2014). b. Construct validity. The number of projects was three, construct validity calculation is not sufficient. Therefore, the validity used in this study was from the previous study such as: Owner Role Validity = 0.599; Validity of the Consultant Role = 0.723; Contractor Role Validity = 0.763; Validity of Stakeholder Roles = 0.576. The calculation was performed using SEM-PLS program (Structural Equation Model - Partial Least Square). The basis for decision- making validity tests was that the correlation value was greater than 0.70. However, on the research and the development design, the scale of loading factors from 0.50 - 0.60 is still acceptable [20]. Because all validity scores above 0.50, the instruments were categorized as valid. c. Reliability. The composite Reliability and Cronbach Alpha of instrument on the previous study were as follows: the role owner reliability = 0.846; reliability of the consultant role = 0.835; contractor role reliability = 0.891; stakeholder role reliability = 0.891. According to [20], a construct is categorized as reliable if the value of composite reliability and cronbach alpha is above 0.70. Because all reliability scores above 0.70, the instrument was categorized as reliable. VI. DISCUSSION The following is a discussion of the results of the study. a. The maturity of the pre-construction safety planning for UNNES projects in 2018 on average is categorized as under - developed categories (score 46.56). This shows that improvement is required on the safety planning at the pre- construction stage, both for the Owner, Consultants, Contractors and Stakeholders. The Owners, Consultants, and Contractors need to learn the newly issued regulations to be implemented immediately. These regulations include Public Work Ministry Regulation No. 05 / / PRT / M / 2014) and Circular Letter of Public Work Ministry Regulation No. 66 / SE / M / 2015. The role of the Owner and Consultant still seems minimal. The owner can make a decision to improve construction safety from the conception stage. Fink (1997) argues that the owner can participate in controlling through the proposal submitted by contractors. Next, the architects and planning engineers can improve the construction safety in the design process. In the UK, although the Construction Design Management has been implemented for more than 10 years, until 2006 planners still lacked in utilizing their potential to eliminate and reduce risk in the workplace (www.hse.Gov.uk downloaded 20/09/2006). In USA, there is less motivation from professional designers to adopt safe design concepts because they assume that safety is included as the job of contractor according to Behm (2005). Behm (2005) also states that the effect of planning on construction safety is lost if planning are not carried out until the construction phase takes place. b. The validity of the assessment instrument: the following variables must be added on the content validity: the compulsory calculation of OHS costs on project cost proposal included in general costs (Circular of Public Work Ministry No. 66 / SE / M / 2015), and Occupational Safety Plan Contract Preparation & presentation by contractors (Ministry Regulation No. 05 / PRT / / M / 2014). In construct validity, the instrument of this study has sufficient numbers of construct validity which was above 0.50 (>0.50). With sufficient numbers of validity, this instrument can be used to measure what should be measured. c. Reliability of the instrument, the reliability of this assessment instrument has sufficient reliability value, which is above 0,70 (> 0.70). With sufficient reliability value, this instrument can be used consistently, meaning that it is used at various times and used by various people when tested on one object, the results are relatively similar.
  • 7. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–7 d. Occupational health and safety at construction in general, pre – construction safety planning is an accident prevention efforts using the upstream approach. The prevention of accidents in construction projects in Indonesia are mostly conducted using the downstream approach. This phenomenon occurs in both developing countries and countries that have implemented construction safety. Construction Occupational Health and Safety in Indonesia is still a concern. The number of fatal accidents tends to increase annually as shown in Table 2 TABLE III - FATAL WORKPLACE ACCIDENTS IN INDONESIA Year 2001 2003 2005 2011 2015 2016 Total cases 104,774 105,846 99,203 108,696 105,182 101,367 Fatality 1,768 1,748 2,045 31,195 2,375 2,382 Percentage of fatality to total case (p) 1.69% 1.65% 2.07% 2.87% 2.16% 2.35% It implies that there is a need for socialization to all parties in construction safety regarding the importance of safe design and pre-construction safety planning. Ways of socialization are by submitting the results of this study to the various stakeholders, writing in professional journals and at seminars, and can also conduct training. It implies that there is a need for socialization to all parties in construction safety regarding the importance of safe design and pre-construction safety planning. Ways of socialization are by submitting the results of this study to the various stakeholders, writing in professional journals and at seminars, and can also organize training or workshops in collaboration with relevant agencies and institutions. The further effect that can be expected is the decline in the number of construction accidents in Indonesia and the increasing image of Indonesia in terms of work safety. VII. CONCLUSION AND SUGGESTION The conclusions of this study are: a. Construction safety in Indonesia is still low and some efforts are needed to improve it. b. Pre-construction safety planning for projects in UNNES in 2018 was categorized as underdeveloped c. With the new regulation, the content validity of the pre-construction safety assessment instruments still needs to be refined. Improvements were made with the addition of the regulations listed in Ministry of Public Work Regulation number 05 / PRT / M / 2014 and Circular Letter of Ministry of Public Work No. No. 66 / SE / M / 2015. d. The reliability of the pre-construction safety assessment instrument currently in use is still usable. The following are the suggestions based on the results of the study: a. Pre-construction safety planning for projects at UNNES in 2018 needs to be improved. Improvement can be performed by entering OHS clauses in the auction document. Consultants need to be more professional in making technical specifications by incorporating specific OHS aspects. b. It is necessary to provide sufficient funds for the implementation of OHS construction in accordance with the mandate of Ministry of Public Work Regulation number 05 / PRT / M / 2014 and Circular Letter of Ministry of Public Work No. No.66 / SE / M / 2015. c. It is recommended to carry out further validation of the pre-construction safety assessment instrument. d. It is recommended that Unnes provides personnel who handle OHS construction problems in the UNNES environment, which will be able to help direct the realization of OHS regulations on UNNES projects, or even on some projects outside the UNNES REFERENCES [1] Arka, Bahan – bahan Lokakarya K3 Konstruksi, 2008 [2] Barrie, Donald S. et. al., Manajemen Konstruksi Profesional, Terjemahan oleh Sudinarto, Jakarta, Penerbit Erlangga, 1990. [3] Creswell, Research Design: Qualitative, Quantitative, and Mixed Methods Approaches, London, SAGE Publication, 2003. [4] Davies, V J and K. Tomasin, Construction safety Handbook, London, Thomas Telford Publishing, 1996. [5] Echols, John M dan Hassan Shadily, Kamus Inggris-Indonesia, Jakarta, PT Gramedia, Hal. 375, 1990. [6] Efansyah, M. Noor, OHSAS 18001:1999- Sistem Manajemen Kesehatan dan Keselamatan Kerja (Modul Pelatihan), Yogyakarta, Deras Training Center, 2007. [7] Endroyo, Bambang, Studi Tentang Model Penilaian Kematangan Perencanaan Keselamatan Pada Tahap Pra Konstruksi, Untuk Mitigasi Kecelakaan Konstruksi, Laporan Penelitian, Semarang: UNNES, 2009. [8] Endroyo, Bambang, Verifikasi-Validasi Lanjut Model Penilaian Kematangan Perencanaan Keselamatan Pra Konstruksi, Laporan Penelitian, Semarang: UNNES, 2011.
  • 8. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2163 Issue 01, Volume 6 (January 2019) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value – Mendeley (Elsevier Indexed); Citefactor 1.9 (2017) ; SJIF: Innospace, Morocco (2016): 3.916 | PIF: 2.469 | Jour Info: 4.085 | ISRAJIF (2017): 4.011 | Indexcopernicus: (ICV 2016): 64.35 IJIRAE © 2014- 19, All Rights Reserved Page–8 [9] Endroyo, Bambang, Pengembangan Model Penilaian Perencanaan Keselamatan Pra konstruksi Dengan Pendekatan matematik dan Penerapan Diagram Radar, Laporan Penelitian. Semarang, UNNES, 2013. [10] Gaspersz, Vincent, Total Quality Management, Jakarta: Gramedia Pustaka Utama, 2003. [11] Hinze, W Jimmie., Construction Safety. Prentice-Hall, Inc, 1997. [12] Koehn, Enno et. al. Safety in Developing Countries: Professional and Bureaucratic Problems. Journal of Construction Engineering and Management, September 1995 hal. 261 – 265, 1995 [13] Mardapi, Djemari., Teknik Penyusunan Instrumen Tes dan Non Tes. Yogyakarta: Penerbit Mitra Cendikia, 2008. [14] Oberlender, Garold D., Project Management. 2000 [15] Purwanto., Evaluasi Program Diklat. Jakarta: Sekolah Tinggi Ilmu Administrasi Negara, 1999 [16] Rossi, Peter H and Howard E. Freeman., California: Evaluation, A Systematic Approach. SAGE Publication, Inc, 1985. [17] Selim, Bisma R and Julia Pet-Armacost., Program Assessment Handbook. Florida: University of Central, 2004. [18] Suraji, Akhmad and A. Roy Duff., Constraint-Response Theory of Construction Accident Causation, The International Conference on Designing for Safety, ECI/CIB/HSE, London, 2000 [19] Suardi, Rudi (2005). Sistem Manajemen Keselamatan & Kesehatan Kerja. Jakarta: Penerbit PPM. [20] Ghozali, I., Structural equation modeling: Metode alternatif dengan partial least square (pls). Badan Penerbit Universitas Diponegoro, 2008. [21] Adler, M., & Ziglio., Gazing into the oracle: The Delphi method and its application to social policy and public health. Jessica Kingsley Publishers, 1996.