The document provides an overview of project management using MS Project 2007. It discusses key aspects of project planning including defining tasks, task relationships, resources and timelines. The summary focuses on the high-level steps for setting up a project plan in MS Project:
1. Define the project calendar and properties.
2. Identify and break down the project goals and tasks.
3. Determine task sequences and relationships such as finish-to-start.
4. Assign resources and time estimates to each task.
5. Review the full project plan for accuracy.
3. WHAT IS A PROJECT?
A project is a well-defined sequence of events with an
identifiable beginning, deliverables and ending
4. PROJECT MANAGEMENT
Project management is the planning, organizing and
managing of tasks and resources to accomplish a
defined objective, usually with the constraint of time and
cost.
(ግዜ ከተሰጣት ግመል በመርፌ ቀዳዳ ታልፋለች!)
Project Management Helps you to answer
How long the project Will take
the impact on the overall project if a task is delayed.
Which tasks are critical
Are sufficient resources allocated to the project to complete
on time?
The resource costs of the project
Is the project on schedule?
5. PROJECT MANAGEMENT CONT.
Project management can be broken down in to
three Phases
Creating the project plan (identify task, resource, time)
Managing the project (ensuring completion of tasks with
in schedule & budget)
Progress reporting (communicating project status)
6. CREATING THE PROJECT PLAN
The steps involved in setting up a project plan
Define calendar (Create a work day & holiday schedule)
Define the project goals and determine what needs to
be done.
break the project in to phases & sub divide phases into tasks,
identify project milestones ,
estimate the duration of each task
Determine the sequence of tasks (which tasks can be completed
before others?, which tasks can be completed at the same time ?, define task constraints)
Assign Resources
Who is needed for each task
What equipment is needed for each task
What facilities are necessary.
What materials are necessary.
Review the plan (Verify the accuracy and completeness circulate the plan for
review)
Additional planning issues
Budget and cost constraints
Who else needs the project staffs information
What are the consequences of missing deadlines
7. IMPLEMENT PROJECT MANAGEMENT
Tracking
Follow tasks to be done each day
Follow supply of resources as per the planning
document
Update planning with actual data
Comparing Baseline data to actual data
Monitor, control and analyze actual executions with
original planning
Modify and devise method to avoid critical delays
Splitting Tasks
Manage over allocations
8. PROGRESS REPORTING & PROJECT COMMUNICATIONS
Identify project stake holders
Identify parties project execution status knowledge
is important to
Report task execution, Resource Utilization status
and cost to the parties identified above
10. START A NEW PROJECT
There are two activities that need to be completed
before starting the planning task
Setting Project properties
Setting File properties
19. PROJECT PLANNING
Define calendar
Define the project goals and
determine what needs to be done.
Determine the sequence of tasks
Assign Resources
Review the plan
Additional planning issues
20. Define calendar
Entering the project working this cronies setting the
options and working times in the standard
calendar that all other calendar use as a definite.
25. DEFINE CALENDAR
you can also define important parameters of calendar like hour of work a day,
hours per week, days month, start of a week &start of a year.
Click options - enter parameter of interest -
ok.
26. PROJECT GOALS
Project goals
Develop A residential facility with one Modern three
bedroom house with a service quarter, five buildings
with associated service quarters each with two two bed
room modern house and six buildings to be used as
Guest house each having two guest rooms.
27. WHAT NEEDS TO BE DONE
Define tasks
Define task relationships
Define task durations
Define and Assign project resources
Define cost resources
29. PROJECT TASKS
Tasks are activities in a project that need a start
and end time with a deliverable
One needs to identify between the following naming
of tasks to work with MPP
Summary Task
Sub tasks
Critical tasks
Milestone
Recurring tasks
Predecessor tasks
Successor tasks
30. PROJECT TASKS CONT.
Summary tasks:- these tasks define and include same
nature works or sub tasks to be defined.
The summary tasks for instance in our project are
Excavation and earth work
Concrete work (subs structure)
Concrete work (super structure)
Masonry work
Block work
Carpentry
Roof work
Metal work
Steel structures
Finishing work
Glazing
Electric work
Seminary work
Site work
Fence work
31. PROJECT TASKS CONT.
sub tasks – tasks under logical grouping of
summary tasks .It is a good practice in project to
break down tasks into manageable portions
These smaller manageable portions under
summary tasks are the sub- tasks
for instance let us breakdown our summary tasks
into sub tasks
(we consider a residential development project with
three group of buildings administrator residences (3-
bedroom) , Officials Residences(2-Bed rooms) ,
Guest houses and the site work)
32. PROJECT TASKS CONT.
Excavation & earth work
Site clearing
-Site clearing- Administrator Residence
- Site clearing-officials residence
-Site clearing –guest house
Bulk excavation
-Bulk excavation -administration residence
-Bulk excavation – officials residence
-Bulk excavation- guest house
Trench excavation
-Trench excavation- administration
-Trench excavation- officials
-Trench excavation- guest house
Back fill around trench & under hard core
- Back fill- administration residence
- Back fill-– officials residence
-- Back fill - guest house.
Cart away surplus excavated material
Hard care
Hardcore - administration residence
Hardcore - officials residence
Hardcore - guest house
33. PROJECT TASKS CONT.
Concrete work (substructure)
Lean Concrete
Lean Concrete -officials residence
Lean Concrete- administration residence
Lean Concrete- guest house
Grade Beam Concrete
Bar bending
Bar bending -administration residence
Bar bending- officials residence
Bar bending- guest house
Form work
Form work- administration residence
Form work- officials residence
Form work- guest house
Casting
Casting- administration
Casting- officials
Casting- guest
Slab concrete
Reinforcement
- administration
- officials
-- guest
Concrete casting
- administration
- officials
-- guest
34. PROJECT TASKS CONT.
Concrete work superstructure
Column
Reinforcement
administration
officials
guest
Form work
administration
officials
guest
Concrete cast
administration
officials
guest house
Top tie
Reinforcement
administration
officials
guest hawse
Form work
administration
officials
guest house
Concrete casting
- administration
- officials
- guest house
40. PROJECT TASKS CONT.
Electrical installation
Point installation
administration
officials
guest house
Fixture
administration
officials
guest house
Site work
Site sanitary installation
Elevated water task
Earth work
Concrete work
Perforation
Steel structure
41. PROJECT TASKS CONT.
Septic tank
Earth work
Concrete work
Masonry work
Block work
Finishing
Pipe work
Fence work
Excavation &Earth work
Concrete work
Masonry work
Finishing work
Metal work
46. PROJECT TASKS CONT.
critical tasks
A critical tasks is defined as a task which if delayed will delay
the end date and time of the project
critical tasks are shown as a red bar on the gantt chart.
Non- critical tasks
A non critical task is defined as a task. Which if delayed, will
not have an effect on the project end date.
Milestone
tasks with duration of zero are set as mile stores.
milestones usually represent the completion of an event,
phase or other manageable goal with in the project
when duration is entered zero the Gantt bar charges to a
diamond shaped mark
47. DEFINING CRITICAL TASKS ON MSP 2007
Microsoft schedule will define tasks critical or non
critical depending their position and property in the
schedule .
We can make the following so that microsoft project
can highlight its critical tasks so that we can give
attention to the tasks.
54. PROJECT TASKS CONT.
Recurring Tasks
Recurring task is a task that occurs repeatedly with is a
project
This could be a weekly meeting, a status report or regular
inspections
instead Of typing the task repeatedly with in a schedule a
recurring task needs only be entered once
A recurring task can be set to repeat daily ,weekly, monthly or
yearly
click task name---- select (insert, recurring one) ----Recurring
task----- fill in the appropriate details.
Predecessor task
a task that must be started or finished before task can begin
Successor task
A task that can only start or finish after another task has
finished is called successor task.
60. DEFINE TASK RELATIONSHIPS
Any two tasks if have relations then their relation
ship can lie under one of the folowing
Finish to start task relation
Start to start task relations
Finish to finish task relations
Start to finish task relations
61. FS –FINISH TO START TASK RELATIONS
lets defile most finish to start tasks .
layout drawing should be approved before carrying out setting out.
setting out should be complete before site clearing & bulk excavation.
Bulk should be done before formations & trench excavations.
Trench should finish before lean concrete under masonry .
Back fill under hard core should be complete before hard core.
formwork and reinforcement should be complete before concreting.
rooting carpentry should finish before roof covering.
super structures concrete work should complete before block work.
Block work should complete before door and window metal work
Block work should finish before plastering
plastering should finish before painting concretes.
sanitary line installation should finish before wall ceramic.
floor tiles should be finished before wooden door carpentry.
Glazing should finish before electrical & sanitary fixtures fixing.
roofing work should complete before plastering.
62. DEFINE FS TASK RELATIONS WITH MSP-2007
Linking tasks with a finish to start relation ships
Select the tasks to be linked -- Edit -- link tasks.
This links the tasks with a finish to start relationships.
In a finish to start relationship, an overlap or time
delay between two task is called a lag, Lead times
are entered as negative numbers.
To enter task relationships in the task form fields
double click on task-- select predecessor --- define
lag.
63. DEFINE FS TASK RELATIONS WITH MSP 2007
Select the two tasks having finish to start relation –click link button on task bar
This is the quickest
65. DEFINE FS TASK RELATIONS WITH MSP 2007
Select the task—double click task—task information dialog appears—select
predecessor-select task name from drop down—select Finish to start from type –
enter lag time—ok
66. SS –START TO START TASK RELATIONS
To start a task if some other task needs to start then
these two tasks need to have a start to start relation
between them
Lets defile most to start tasks
Lean concreting should start for masonry to start .
Blok work should start for plastering to start.
reinforcement should start for form work to start.
masonry should start for sanitary drainage to start.
linking tasks with start to start relation
Select the tasks to be linked—Click edit –click tasks—double
click arrow –change type to start to start—ok .
69. FF –FINISH TO FINISH TASK RELATIONS
Refer slides above
SF –START TO FINISH TASK RELATIONS
Refer slides above
70. TASK DURATION
Task Duration is the time factor that is needed to get the
job done
The task duration is usually done on to basis
When delivery date is known and more important and
resource is assumed to be available
When delivery date is less important and Resource
constraint exists
In construction during defining tasks the following has to
be strictly followed
We should always follow recommended curing times And
waiting times
We should always follow Finish to start relations.
When setting duration always proportionate with the real
production efficiency
71. SETTING TASK DURATION IN MS PROJECT
Select task—Go to duration –Enter Duration of task—Press Enter
72. TASK CONSTRAINTS
When a task is first entered in to project the task
start date is project start date
After tasks are linked and resource are assigned
project sets start and finish dates based on task
dependencies and resource availability
A constraint is a restriction imposed on the start or
finish data.
73. DEFINE A TASK CONSTRAINT
Double click task—select advanced on summary
task information dialog box—select constraint
select constraint date –ok .
74. CONSTRAINT TYPES
Constraints are of two kind in nature
Flexible constraints
Such constraints are not tied to specific dates and gives the
schedule flexibility
Inflexible constraints
Such constraints are tied to a particular date and should be
used less of them because they take flexibility away from the
schedule.
75. FLEXIBLE CONSTRAINTS
Constraint description Flexible for
As soon as possible Starts the task as late as possible based on
other constraints and depending
All projects
As later as possible Starts the task as soon as possible based on
other constraints and depending
All projects
Finish no earlier
than
Finish the task on or after an entered date Projects scheduled from a start
date
Start no earlier than Starts the task on or after an entered date Projects scheduled from a start
date
Finish no later than Finishes the task on or before an entered date Projects scheduled from a finish
date
Start no later than Starts the task on or before an entered date Projects scheduled from a finish
date
76. INFLEXIBLE CONSTRAINTS
constraint description Inflexible for
Finish no earlier than Finish the task an or after an entered
date
Projects scheduled with a finish date
Start no earlier than start the task an or after an entered date Projects scheduled from a finish date
Finish no earlier than Finish the task an or before an entered
date
Projects scheduled from a start date
Start no earlier than Start the task an or before an entered
date
Projects scheduled from a start date
Must finish on Finishes the task or an entered date All projects
Must start on starts the task or an entered date All projects
77. TASK DEADLINES
A dead line is a date that you want or need the task
completed by
Setting a dead line does not affect the task
scheduling in any way but project places a down
ward projecting allow on the Gantt chart to indicate
the dead line and an indicator when the dead line is
exceeded
78. SETTING A DEADLINE
Select the task you want to assign deadline—double click task –information dialog
appears—select advanced—select dead line –enter deadline—ok .
82. DEFINE
A resource can be any
item or material (brick, cement, water etc),
Place (shades, storage etc)
Equipment (dump truck, mixer etc
persons (human being)
necessary to complete the task.
A task might require a single resource or multiple
recourse to be completed.
In naming resource we should be consistent
enough.
There are three types of resources in Ms project
Work resource
Material resource and
Cost resource
83. DEFINE
Work resources are people and machines, and they
need time (hours, days, weeks etc.) to perform the
tasks
Material resources are consumables like bricks,
stones, sand ,concrete, etc. material resources are
time independent
Cost Resources are time independent resources
like advance bond guarantee, performance
guarantee.
84. IDENTIFY
Tasks are identified and now it is time for identifying what is needed to
get the task done
Task Unit Quantity Duratio
n
(days)
List of Resource Unit Qua
ntity
Concrete m3 4 1 Gravel m3
Sand M3
Cement Qtal
Water m3
Mixer Pc
DL No
Forman No
Site
clearing
m2 10 1 Bachhoe loader
forman
Loader operator
85. RESOURCES FOR THE EXAMPLE PROJECT
No Item of work material Equipment & tools resource
1 Site cleaning Back hoe loader spandex doula -operators
-DL
-forman
-engineer
-PM
2 Bulk excavation Back hoe water excavator for spade ,down -operators
-DL
-forman
-engineer
-PM
3 Trench excavation Back hoe loader spade, doma -operators
-DL
-forman
-engineer
-PM
4 Back fill -selected material
-water
Compactor spade doma
Back hoe lands compaction tools
-Dmp truck Drive -
operators
-DL
-forman
-engineer
-PM
5 Cart away Drip truck
-back hoe loader
-Dmp truck Drive
-DL
-forman
-engineer
-PM
86. RESOURCES FOR THE EXAMPLE PROJECT
No Item of work material Equipment & tools resource
6 Hard core -basaltic stone -sundry humane -DL
-Forman
-engineer
-PM
7 Lean concrete -gravel 02’
-concrete
-sand
-black wire
-mixer -DL
-Forman
-engineer
-PM
-Mixer operator
8 Bar bending -reinforced bars
-black wire
-bar cutter(Grinder)
-bar bending tools
-gutet(wire cutter)
-DL
-bar man
-foreman
-engineer
-PM
9 Form work timber(euclyptus)
timber –tawela
-panels
-nails
-carpentar
-DL
-foreman
-engineer
-PM
87. RESOURCES FOR THE EXAMPLE PROJECT
No Item of work material Equipment & tools resource
10
Concrete cast -gravel 02’
-sand
-cement
-water
-vibrator
-mixer
-mixer operator
-DL
-forma
-engineer
-PM
11 masonry -basaltic stone
-sand
-cement
-water
-mixer mason
-DL
-forma
-engineer
-PM
12 Block work
-HCB_20
-HCB_15
HCB_10
-sand
-cement
-water
-level
-mixer
-Carpenter
-DL
-forma
-engineer
-PM
13 Root covers -nail
-roof cover of
specification
-Carpenter
-DL
-forma
-engineer
-PM
14 gutter & down pipe -steel sheet
-lead
-nail
-Acid
-puc clamp
-Ria to
-PVC pipes
-welder -Gutter man
-DL
-forma
-engineer
88. RESOURCES FOR THE EXAMPLE PROJECT
No Item of work material Equipment & tools resource
15 Roof carpentry -timber
-purl in 5x7
-chip wood
-purling 4x5
-nail
- scaffolding -Carpenter
-DL
-forman
-engineer
-PM
16 Woods doors -timber
-keys
-adhesives
-pairts
(manufactured door)
-sealing machines (tools)
-painting nadir
-Carpenter (wood work)
-DL
-forman
17 Metal work -steel profiles
-paint
-lead
-black wire
-key
-accessories
Welding machine
Cutting machine
compressor
-welder
-DL
-forman
-engineer
-carpenter
-mason
18 Cement plastering -cement
-sand
-water
plasterer
-DL
-forman
-engineer
19 Gypsum plastering Gypsum
-water
tools Gypsm plasterer
-DL
-forman
-engineer
-PM
89. RESOURCES FOR THE EXAMPLE PROJECT
No Item of work material Equipment & tools resource
20 Floor finish & skirting -tile of spec
-skirting of sped
-sand
-cement
-water
Tiller (mason)
-DL
-forman
-PM
-engineer
21 Wall ceramic -ceramics
-sand
-cement
-water
Tiller (mason)
-DL
-forman
-PM
-engineer
22 Window sill & edpe work -window sill material
-sand
-cement
-water
-angle iron profile
-grinding (cutter) machine plasterer
-DL
-forman
-engineer
-PM
-carpeting
23 Pavement & half ditch -ceramics
-sand
-cement
-water
-halfdifen manufactory
-mixer
-DL
-forman
-engineer
-carpenter
24 glazing -glasses
-stucco
-screw driving
-glass cutter
-glazer
-DL
-forman
90. RESOURCES FOR THE EXAMPLE PROJECT
No Item of work material Equipment & tools resource
25 painting -paint
-accessories
-painter
-Forman
26 Electrical
installation
-electrical cables
Electrical wires
-electrical
distribution boxy
-electrical tool box -electrical
-DL
-Forman
27 sanitary
installation
-sanitary pipes
-sanitary joints
-sanitary filets
-sanitary
accessing
-sanitary tool box -sanitary mason
-DL
-forma
91. ASSIGN RESOURCES
The two most common location to enter recourses
are
The Assigning resource dialog box.
The resource sheet.
Assign resource dialog box
Click on the Assign resource button and the Assign
resource Dialog box appears.
Type the name of the resource in the name box and
enter.
The resources sheet
Click view click Resource sheet
Enter the name and details of resource
92. ASSIGN RESOURCE DIALOG BOX
Click on the Assign resource button and the Assign resource Dialog box
appears.
Type the name of the resource in the name box and enter.
93. THE RESOURCE SHEET
Click view --- click Resource sheet--- Enter the name and details of
resource
94. THE RESOURCE SHEET
Click view --- click Resource sheet--- Enter the name and details of
resource
95. THE RESOURCE SHEET
name The name of the resource.
type The type of resource work or material.
Material label The units of management for a material resource tons , pouds, tons , gross etc
initials The abbreviated name of the resource.
Group A name that is useful for grouping resources that can be hand for sorting & filtering
Max. Units The total number of resource unite available
Std rate Standard wage, salary or gate for the resource
Ovt rate Over .time rate for the resource
Cost/use Cost amount per use of each resource unit
Accrue At Accrual method for costs;
Start, end/or prorated
Base calendar Choose a calendar from the calendars available
code An identification code, such as an accounting code that you night
Want to use for sorting, filtering or reporting
96. ASSIGNING WORK RESOURCES
Assigning work resources
Select the task you want to assigning a resource of
resource to
Click on the assign resources button and the
assigning resource dialog box appears.
Select the required resource & click assign.
(100% that resource is assigned out unit .you can
change the percentage assignment if you wish in
the units field)
Select all the tasks to assign one resource common
to all
Select all resources to assign to a task is also
possible.
97. ASSIGNING MATERIAL RESOURCES
Material resources are either variable, or fixed
Variable material resource are resources whose consumption
varies with time
Fixed material resource are resources despite duration of
tasks the consumption doesn’t change
Assigning variable material resources.
Select task
Click assign resource button
Select material
Enter gate in units field like 2/h
Assigning fixed material consumption
Select task
Click assign resource
Select material
Enter the number of units needed for the task.(the material the
task consumes)
99. ASSIGN COSTS RESOURCE.
There are two types of costs in MP project,
Resource costs
Fixed costs
Each resource of task can have a costs associated
with it.
The resource sheet can be used to enter basic cost
information.
101. OVER ALLOCATION & CONFLICT OF RESOURCES
During Planning phase if resource planning is not
carefully done
Conflict of interest happens when a single resource is
assigned to two or more tasks at the same time
Over allocations – when resources are short over
allocations happens (for instance for a task which
needs 2x amount of a resource and the maximum
resource defined is x then the resource is said to be
over allocated
Usually fixing resource planning exactly the way it
should be we can avoid this.
102. GETTING DONE WITH PLANNING
Presenting project plan to the technical project
team, defend and modify
Present project to company management , defend
and modify
Present the plan to client and consultant, defend,
modify and finalize
Get approval or acceptance signatures from
authorized signatories of each party (contractor
(Gugetech Engineering), client, consultant
105. IMPLEMENT THE PROJECT
Baseline
Setting Baseline
Saving Baseline
Deleting baseline
Tracking
Follow tasks to be done each day
Follow supply of resources as per the planning document
Update planning with actual data
Comparing Baseline data to actual data
Monitor, control and analyze actual executions with original
planning
Modify and devise method to avoid critical delays
Splitting Tasks
Manage over allocations
106. BASELINE
Before the first task begins a base line should be
set . (A base line is a schedule confirmed and free
of conflicts)
For construction projects a baseline is the schedule
accepted by the client as well as the consultant.
That should be a schedule with approval from all
parties
Setting a base line is a critical step in the
scheduling process
As a project progresses, assignments will change.
A base line is useful for comparing the planned
schedule with later version of the schedule to see
what changes have occurred.
108. SAVING A BASELINE
When a baseline is set the data in the schedule
fields is copied over to the baseline fields.
If a baseline is saved before the schedule planning
is finished , a new base line can be saved over the
existing baseline.
Select tools—tracking –set baseline—ok .
112. TRACKING THE PROJECT
Tracking is the process of gathering and entering task
information in to the schedules.
Before the first task in the project can begin the project
schedule should be fully developed and baseline should
be set.
When actual task progress is entered ,the project is
automatically recalculated and subsequent tasks are
scheduled based on the actual data, task
dependencies, resources and constraints.
Task progress should be entered chronologically so that
the remainder of the project can be evaluated and both
positive and negative impacts can be dealt with on
proactive basis rather than a reactive basis (controlling
or clearing a situation rather than just responding to it).
113. ENTERING ACTUAL PROGRESS
There are five types of actual data that can be
entered in project
Actual start & finish dates
Percentage complete
Actual duration & remaining duration
Actual & remaining work.
Actual and remaining cost
Actual task data can be entered using one of the
following feature
The update task dialog box
The tracking tool bar
118. TRACKING THE DAY TO DAY STATISTICS
To find statistical data about the project anytime you can go to tracking tool bar
and select project statistics
119. FILTERING TO DO LISTS
You can trace to do lists for a day or aperiod of time
Select project—filtered for –Date Range—Enter start
time—Enter End time –ok
124. SPLITTING TASKS
A task can be split or rescheduled to interrupt the
work and ten resume the remainder of the work at a
later point in the schedule
View –Gantt chart –select required task—click the
split task button on the Standard toolbar –position the
mouse at the point of split need and left click—hold and
move the splitter part to the point of restart
129. MANAGE OVER ALLOCATIONS
When a resource is short of what is needed
resource is over allocated
The resource over allocated is highlighted red in the
resource sheet
To manage over allocation
Split tasks
Increase maximum resources available or defined
Reschedule
130. COMPARING BASELINE TO ACTUAL DATA
The project baseline provides the basis for
comparing costs, work and dates for all tasks and
resources.
By comparing the project progress to the baseline,
the project can be monitored to ensure
tasks are on schedule,
resources ,are completing their work and
costs are not exceeding the budget.
The following table describes the tools in project to
analyzes and compare baseline, actual and
scheduled data.
131. COMPARING BASELINE TO ACTUAL DATA
tool type description
Tracking Gantt chart Displays actual & base line information
Variance table Displays the difference between the actual information & base line
information
work table Displays the actual &base line costs and shows the variances
cost table Displays the actual &base line costs and shows the variances
Cost over budget Task filter Displays all tasks with a cost greater than the base line cost
Slipping tasks Task filter Display all tasks that are bleared schedule
Work over budget Resource filter Displays all resource with scheduled work greater than the base line
work
132. THE TRACKING GANTT
Select view—tracking Gantt.
Patterned Gantt bars represent the update schedule
for tasks that have not been started or are in
progress
Double click on any white area on the Gantt chart to
view the bar styles definition dialog box to find out
what each bar represents.
135. THE PROGRESS LINE
A progress line represents the tasks progress
The progress can be drawn on the Gantt chart view
and tracking Gantt view
The progress line create peaks. Peaks point to the
left for work that is behind schedule and to the right
for work that is a head of schedule.
Progress line can be automatically displayed of the
current date, at recurring intervals and on specific
dates.
Select tool—tracking –click progress line –select the
appropriate progress line options & click ok.
140. THE PROJECT DATA TABLE
Select view—view bar—more views—Select task
sheet—apply
select view—table cost—the cost table is
displayed.
All task cost information , including variances, is
displayed.
145. PROGRESS REPORTING
Progress reporting is an important tool in project
management.
The management evaluates , monitors and control
the project using the reports
Reports should always be done always in a manner
that proactive responses are actionable.( i.e. they
should be timely and to the correct person or unit)
Ms project comes with 26 pre defined views and 25
predefined reports that can be printed.
146. PROGRESS REPORTING
Select Report –Reports –Report Dialog Box—select
category—Click on desired report—print it out—
distribute (if neessary)