Submit Search
Upload
Term project "Design of Slab Formwork"
•
0 likes
•
112 views
E
Esraa Hussein
Follow
Design of Slab Formwork
Read less
Read more
Engineering
Report
Share
Report
Share
1 of 11
Download now
Download to read offline
Recommended
MERENCANAKAN BALOK BETON PRATEGANG
MERENCANAKAN BALOK BETON PRATEGANG
Mira Pemayun
Design report
Design report
Harshana Prabhath
Design report
Design report
Harshana Prabhath
Preliminary design of beam
Preliminary design of beam
ila vamsi krishna
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
Sumarno Feriyal
Preliminary design of slab
Preliminary design of slab
ila vamsi krishna
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
design of stair case
design of stair case
ila vamsi krishna
Recommended
MERENCANAKAN BALOK BETON PRATEGANG
MERENCANAKAN BALOK BETON PRATEGANG
Mira Pemayun
Design report
Design report
Harshana Prabhath
Design report
Design report
Harshana Prabhath
Preliminary design of beam
Preliminary design of beam
ila vamsi krishna
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
Sumarno Feriyal
Preliminary design of slab
Preliminary design of slab
ila vamsi krishna
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
design of stair case
design of stair case
ila vamsi krishna
1 perhitungan-balok
1 perhitungan-balok
eidhy setiawan eidhy Edy
Water tank design ppt
Water tank design ppt
Vibhanshu Singh
Harshal
Harshal
Harshal Patil Warade
Desain sengkang struktur beton bertulang
Desain sengkang struktur beton bertulang
Shaleh Afif Hasibuan
Muro contension raul1
Muro contension raul1
Diego Rodriguez
Design of toggle jack
Design of toggle jack
hemant Kuralkar
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
Akshika Mahanama
Steel Plate Girder Bridge Design
Steel Plate Girder Bridge Design
Venkatesh A
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
Yongsheng (Jack) Jiao
MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1
Yongsheng (Jack) Jiao
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
Hossam Shafiq II
Footing Design
Footing Design
Sagnik Bhattacharjee
X10703 (me8593)
X10703 (me8593)
BIBIN CHIDAMBARANATHAN
131445983 jembatan-balok-t
131445983 jembatan-balok-t
agustinamanru
C09 m-403032016 som
C09 m-403032016 som
vinodh kumar
Diseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigas
David Chavez Huerto
Final Design Report
Final Design Report
Ashutosh Khushu
Design of isolated footing by ACI code
Design of isolated footing by ACI code
Mahmoud Al-Sharawi
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
Hossam Shafiq II
Baja - Base Plate
Baja - Base Plate
Yasmin Rosyad
Term project " Design of formwork "
Term project " Design of formwork "
Esraa Hussein
Design and analysis of school building
Design and analysis of school building
Raghav Sankar
More Related Content
What's hot
1 perhitungan-balok
1 perhitungan-balok
eidhy setiawan eidhy Edy
Water tank design ppt
Water tank design ppt
Vibhanshu Singh
Harshal
Harshal
Harshal Patil Warade
Desain sengkang struktur beton bertulang
Desain sengkang struktur beton bertulang
Shaleh Afif Hasibuan
Muro contension raul1
Muro contension raul1
Diego Rodriguez
Design of toggle jack
Design of toggle jack
hemant Kuralkar
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
Akshika Mahanama
Steel Plate Girder Bridge Design
Steel Plate Girder Bridge Design
Venkatesh A
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
Yongsheng (Jack) Jiao
MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1
Yongsheng (Jack) Jiao
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
Hossam Shafiq II
Footing Design
Footing Design
Sagnik Bhattacharjee
X10703 (me8593)
X10703 (me8593)
BIBIN CHIDAMBARANATHAN
131445983 jembatan-balok-t
131445983 jembatan-balok-t
agustinamanru
C09 m-403032016 som
C09 m-403032016 som
vinodh kumar
Diseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigas
David Chavez Huerto
Final Design Report
Final Design Report
Ashutosh Khushu
Design of isolated footing by ACI code
Design of isolated footing by ACI code
Mahmoud Al-Sharawi
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
Hossam Shafiq II
Baja - Base Plate
Baja - Base Plate
Yasmin Rosyad
What's hot
(20)
1 perhitungan-balok
1 perhitungan-balok
Water tank design ppt
Water tank design ppt
Harshal
Harshal
Desain sengkang struktur beton bertulang
Desain sengkang struktur beton bertulang
Muro contension raul1
Muro contension raul1
Design of toggle jack
Design of toggle jack
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
Steel Plate Girder Bridge Design
Steel Plate Girder Bridge Design
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
Footing Design
Footing Design
X10703 (me8593)
X10703 (me8593)
131445983 jembatan-balok-t
131445983 jembatan-balok-t
C09 m-403032016 som
C09 m-403032016 som
Diseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigas
Final Design Report
Final Design Report
Design of isolated footing by ACI code
Design of isolated footing by ACI code
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
Baja - Base Plate
Baja - Base Plate
Similar to Term project "Design of Slab Formwork"
Term project " Design of formwork "
Term project " Design of formwork "
Esraa Hussein
Design and analysis of school building
Design and analysis of school building
Raghav Sankar
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
EngGalaydh Farah Axmed
materi kuliah it pln perhitungan plat balok
materi kuliah it pln perhitungan plat balok
IlhamPutera2
Week 9 Lecture Material_watermark.pdf
Week 9 Lecture Material_watermark.pdf
ssuser021946
Shallow and Deep Founation Design Calucations
Shallow and Deep Founation Design Calucations
Tyler Edgington
Concreto armado
Concreto armado
Leonidas Gil Arroyo
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
Hamza Waheed
Term project estimate no. of pieces for elements part 1
Term project estimate no. of pieces for elements part 1
Esraa Hussein
Planing,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALL
Arshana Anu
final internship ppt.pptx
final internship ppt.pptx
KiranKr32
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
RifQii6
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
RifQii6
Diesel Production: Equipments Design
Diesel Production: Equipments Design
Pratik Patel
NAME 338 , Presentation 1
NAME 338 , Presentation 1
Kifayath Chowdhury
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
subhashini214160
2nd Presentation NAME 338
2nd Presentation NAME 338
Kifayath Chowdhury
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
Harsh Shani
Puentes
Puentes
KhenyiClementeChahua
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
Robin Arthur Flores
Similar to Term project "Design of Slab Formwork"
(20)
Term project " Design of formwork "
Term project " Design of formwork "
Design and analysis of school building
Design and analysis of school building
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
materi kuliah it pln perhitungan plat balok
materi kuliah it pln perhitungan plat balok
Week 9 Lecture Material_watermark.pdf
Week 9 Lecture Material_watermark.pdf
Shallow and Deep Founation Design Calucations
Shallow and Deep Founation Design Calucations
Concreto armado
Concreto armado
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
Term project estimate no. of pieces for elements part 1
Term project estimate no. of pieces for elements part 1
Planing,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALL
final internship ppt.pptx
final internship ppt.pptx
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
04.PER PLAT 1 ARAH 3 TUMPUAN 8-9.ppt
Diesel Production: Equipments Design
Diesel Production: Equipments Design
NAME 338 , Presentation 1
NAME 338 , Presentation 1
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
2nd Presentation NAME 338
2nd Presentation NAME 338
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
Puentes
Puentes
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
More from Esraa Hussein
Noise Pollution
Noise Pollution
Esraa Hussein
Term project "Bill Of Quantity"
Term project "Bill Of Quantity"
Esraa Hussein
Term project estimate no. of element part 2
Term project estimate no. of element part 2
Esraa Hussein
Concrete production
Concrete production
Esraa Hussein
Design of bracing
Design of bracing
Esraa Hussein
Air pollution.
Air pollution.
Esraa Hussein
Microbial fuel cell
Microbial fuel cell
Esraa Hussein
Aqua, hydra, aeroponics
Aqua, hydra, aeroponics
Esraa Hussein
Noise pollution
Noise pollution
Esraa Hussein
Soil.pptx
Soil.pptx
Esraa Hussein
More from Esraa Hussein
(10)
Noise Pollution
Noise Pollution
Term project "Bill Of Quantity"
Term project "Bill Of Quantity"
Term project estimate no. of element part 2
Term project estimate no. of element part 2
Concrete production
Concrete production
Design of bracing
Design of bracing
Air pollution.
Air pollution.
Microbial fuel cell
Microbial fuel cell
Aqua, hydra, aeroponics
Aqua, hydra, aeroponics
Noise pollution
Noise pollution
Soil.pptx
Soil.pptx
Recently uploaded
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
Extrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
120cr0395
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Christo Ananth
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
ranjana rawat
NFPA 5000 2024 standard .
NFPA 5000 2024 standard .
DerechoLaboralIndivi
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
sivaprakash250
Thermal Engineering Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
DineshKumar4165
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
roncy bisnoi
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
roncy bisnoi
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
Call Girls in Nagpur High Profile Call Girls
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
JiananWang21
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
fenichawla
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
simmis5
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
timesproduction05
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
Call Girls in Nagpur High Profile Call Girls
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
KreezheaRecto
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
RagavanV2
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
DineshKumar4165
Recently uploaded
(20)
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
Extrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
NFPA 5000 2024 standard .
NFPA 5000 2024 standard .
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
Thermal Engineering Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
Term project "Design of Slab Formwork"
1.
CB523 TERM PROJECT ENG. ESRAA
HUSSEIN MOHAMED
2.
Addextra(X*10)cmtoeachdimensionforall spacingbetweenX-Axis. Add extra (Y*10)
cm to each dimension for all spacing between Y-Axis W2 W1 C1 C1 C1 C2 C2C3C2 C2 C3 C3 C3 C3 ID: 14104622 X Y Z M4.3 4.14.24.4 3.89 2.06 2.79 1.72 3.25
3.
• W =
2300 + (10 * M) = 2300 + (10 * 2) = 2320 Kg/m3 • W1= w * ts = 2320*10-2 *20 * 10-2 = 4.64 KPa • W2= 15 PSF * 0.048 = 0.72 KPa • W3= 50 PSF *0.048 = 2.4 KPa • Design load (WT) = W1+ W2+ W3 = 4.64 + 0.72 + 2.4 = 7.76 KPa > 4.8 KPa (100 PSF*0.048) • Sheathing load = Design load * 1m = 7.76 * 1= 7.76 KN/m • Plywood thickness if (M< = 4) = ( 4 + M ) / 8 if (M> 4) = ( M ) / 8 M= 2 à Plywood thickness ( 4 + 2 ) / 8 Plywood thickness 6/ 8 = ¾ Plywood thickness 6/ 8 = ¾ *2.54 cm *10 mm = 19.05 mm ID: 14104622 X Y Z M
4.
Plywood thickness =19.05
mm , Sheathing load = 7.76 KN/m • FbKS = 326 * 103 • Fslb/Q = 7.55 * 103 • EI = 2810 * 109 • Lbending = 3.16( FbKS ! )1/2 = 3.16( 326 ∗ 103 !.!# )1/2 = 647.69 mm • Lshear = 1.67( Fslb/Q ! ) + 2d = 1.67( 7.55 ∗ 103 !.!# ) + (2*19.05) = 1662.91 mm • Ldefection = "#.% &''' ( EI ! )1/3 = "#.% &''' ( 2810 ∗ 109 !.!# )1/3 = 526.02 mm • Ljoist = 526.02 mm /10 = 52.6 cm = 50 cm Design of Sheathing
5.
• Joist load
= 7.76 * 0.5 = 3.88 KN/m • Lbending = &'' &''' ( FbS ! )1/2 = &'' &''' ( 9998∗123900 $.%% )1/2 = 1786.8 mm • Lshear = &.&& &''' ( Fv A ! ) + 2d = &.&& &''' ( 1276 ∗ 5323 $.%% ) + (2*140) = 2223.11 mm • Ldefection = "#.% &''' ( EI ! )1/3 = "#.% &''' ( 11.7∗106 ∗ 8.656∗106 $.%% )1/3 = 2189.17 mm • Lstringer= 1786.17 mm /10 = 178.62 cm = 175 cm Design of Joist 2”*6” Douglas Fir B= 38mm D=140mm
6.
• Stringer load
= 7.76 * 1.75 = 13.58 KN/m • Lbending = &'' &''' ( FbS ! )1/2 = &'' &''' ( 9998∗215300 &$.'% )1/2 = 1259.01 mm • Lshear = &.&& &''' ( Fv A ! ) + 2d = &.&& &''' ( 1276 ∗ 7016 &$.'% ) + (2*184) = 1099.75 mm • Ldefection = "#.% &''' ( EI ! )1/3 = "#.% &''' ( 11.7∗106 ∗ 19.83∗106 &$.'% )1/3 = 1900.75 mm • Lshore = 1099.75 mm /10 = 109.975 cm = 105 cm Design of Stringer 2”*8” Douglas Fir B= 38mm D=184mm
7.
Ljoist =50 cm
Lstringer= 175 cm Lshore = 105 cm Check of bearing 1. Between Joist and Stringer : Load= Design load * LJoist * Lstringer = 7.76 * 0.5 * 1.75= 6.79 KN Area= BJoist * Bstringer = 38 * 38 = 1444 mm2 Stress = Load / Area = 6.79/ (1444*10-6) = 4702.22 KPa > Fc⏊= 2655 KN/m2 “ Un safe ” Lstringer new= 0.95 m
8.
• Stringer load
= 7.76 * 0.95 = 7.372 KN/m • Lbending = &'' &''' ( FbS ! )1/2 = &'' &''' ( 9998∗215300 !.$!( )1/2 = 1708.78 mm • Lshear = &.&& &''' ( Fv A ! ) + 2d = &.&& &''' ( 1276 ∗ 7016 !.$!( ) + (2*184) = 1715.96 mm • Ldefection = "#.% &''' ( EI ! )1/3 = "#.% &''' ( 11.7∗106 ∗ 19.83∗106 !.$!( )1/3 = 2330.04 mm • Lshore = 1708.78 mm /10 = 170.88 cm = 170 cm Design of Stringer 2”*8” Douglas Fir B= 38mm D=184mm
9.
Check of bearing 2.
Between Stringer and Shore : Load= Design load * Lstringer* Lshore = 7.76 * 0.95 * 1.7 = 12.53 KN Area= Bstringer * Bshore = 38 *89 = 3382 mm2 Stress = Load / Area = 12.53 / (3382*10-6) = 3704.91 KPa > Fc⏊= 2655 KN/m2 “ Un safe ” Lshore new= 1.2 m
10.
Ljoist = 50
cm Lstringer= 95 cm Lshore = 120 cm Check shore safety Load= Design load * Lstringer * Lshore = 7.76 * 0.95 * 1.2= 8.85 KN Area= Bshore * Bshore = 89 *89 = 7921 mm2 Stress = Load / Area = 8.85/ (7921*10-6) = 1117.28 KPa < Fc = 6895 KN/m2 “ safe ” Final Design:-