Performance Service Level Agreement – Professional Services – Technical Services: Project Management
SERVICE LEVEL AGREEMENT
PROFESSIONAL SERVICES – PERFORMANCE – CIVIL
& BUILDING WORKS
BETEWEEN
SENQU MUNICIPALITY
(Hereafter referred to as SM)
AND
(Hereafter referred to as the “Consultant”)
DATE:_________________
PROJECT NAME
NOTICE #: _________________________
2 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
1. PURPOSE
The purpose of this Service Level Agreement is to enforce certain guidelines that the appointed consultant
must consider and enforce throughout the project lifespan and responsibility period as defined within this
agreement, and performance measurement and penalties of the consultant, as stipulated within this
agreement. It is accepted that the Consultant is aware and understands all terms and abbreviations used
within this SLA.
2. GENERAL
The following general terms and conditions have been laid down for all construction or similar
appointments.
1. Where such special conditions or procedures are in conflict with this SLA, the said special
conditions or procedures shall apply but must be incorporated into the standard SLA (SAICE).
2. These SLA terms and conditions, may at SM’s sole discretion, be amended or supplemented and
the service provider notified in writing within 5 working days thereof. The service provider will have a
further 5 working days to accept/respond to such changes.
3. For purpose of this agreement the word “appointment” will be considered as the contract for
professional services as required and tendered for by the Consultant, to the SM, in order to achieve
construction completion in terms of objectives, budget, quality and quantity as per the successful
construction bidders contract.
4. Reference to the GCC will include any other sector related contracts in common use. (eg JBCC)
and terms identified within this contract related to the GCC will be replaced with the terms of the
sector contract but conditions and penalties will remain the same.
5. Contract length will be from date of appointment to one calendar month after Final Completion is
achieved, unless otherwise dictated in terms of this agreement or law.
6. The point of contact within the municipality will be the PMU manager, unless otherwise stated by the
SM, in writing.
7. Principle Agent/ Team shall be considered to refer to Consultant, both being considered the same in
terms of this Service Level Agreement.
3. CORRESPONDENCE
All signed written correspondence, including faxes and e-mail received from the Consultant or the SM will
be regarded as binding to the party and company whom he / she represents. Certain critical
correspondences will be required on official letterhead from both parties.
4. REFERENCE DOCUMENTS
Where the need arises to obtain reference/specification documents, the Consultant will do so from the
relevant authority, at own cost.
5. PERIOD OF RESPONSIBILITY
The period within which the total responsibility/accountability of the Consultants appointment is to remain
valid and binding on the Consultant will be from the date of the signed letter of acceptance for the tender
submitted, returned to SM, until 31 calendar days after the issue of the Final Completion Certificate date.
The consultant will remain liable for design and construction for any further period as identified by the
industry or law. This applies to the Works that the Consultant was appointed for in terms of the
appointment. The SM retains the right to extend such period of contract accountability if there is any doubt
on the quality of the Works or any associated matter, for any reasonable amount of time, at no cost to the
SM, until the matter has been dealt with fully and in all respects, in terms of this agreement. Consultants
will be required to attend any meeting considered as reasonable, requested by the SM, even after Final
Completion, should any information be required for clarification.
3 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
6. PRICE
a) Tendered prices are fixed and considered as the total cost (Including disbursements etc.) and only
subject to adjustments in accordance with the actual increases resulting from the change of
rendering costs for the execution of the contract upon prior approval of Contingency expenditure or
a Variation Order, which may not exceed 20% of the total contract / tender value (Direct or Indirect
cost). Any such adjustment will be done on a pro-rata scale, calculated in percentage, and reduced
to figures (Including VAT). Any additional Works MUST be approved, in writing, by the SM BEFORE
instruction is given to the contractor to continue with such works.
b) The contract construction or management cost may not be exceeded by the Consultant without the
express written permission of the SM. Should this occur without prior written permission, the
Consultant will be held accountable for such costs.
c) In the event of a contractor being removed from site in terms of the GCC or any other legislation, the
Consultant may not retender the project without the express written permission of the SM. The
Consultant must ensure that the construction site is safe and usable to the public (where applicable)
at all times, until the SM has, in writing, issued further instructions. The Consultant will, within 10
working days, submit a revised construction cost to complete the project.
7. DESIGN
Dependent on the urgency or nature of the Works, the Consultant is to consider the following in the design
for the Works, without eroding quality or circumventing legislation:-
1. Labor intensive construction methods (LIC) using local labour/SMME’s
2. Sustainability of the project
3. Possible risks
4. Project objectives
5. Use of local suppliers where possible
6. Use of local registered contractors on the SM database as sub-contractors in order to develop
accession in the CIDB rating.
7. Possible alternatives
8. Price (Value for money)
9. Contingencies and criteria for use thereof.
10. Future maintenance and operational cost
11. Environmental and other legislative requirements
12. Time frames
13. Cash flow predictions
14. CIDB considerations
15. Community considerations in terms of buy in (ISD)
16. Client liaison and design approval
17. Establish and confirm that the Contractor has sufficient resources and capacity to complete the
project, aside from the CIDB rating.
8. DOCUMENTATION
The Consultant will ensure that advertisements are placed in at least 2 registered newspapers for contracts
under R 10 M and 3 registered newspapers if over R 10 M.
4 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
Minimum advertisement periods will be 21 days for values under R 10 m and 31 days for any value over R
10 M.
Copies of the original newspaper advertisements must be given to the PMU Manager within 5 working days
of their placement/publication.
The Consultant will ensure a compulsory tender site meeting on all projects, unless agreed otherwise with
the SM.
The Consultant will ensure that accurate minutes and attendance registers are kept of all official meetings
and distributed within 5 working days to all relevant parties as will be agreed upon at the first official site
meeting.
The Consultant (or representative) will be present at the official opening of tender documents (SM SCM
processes) and will sign for receipt of the documents (Annexure E), after processed, before removal from
the SM premises, for appraisal purposes.
The Consultant will submit a tender evaluation report within 15 working days of official opening of the
tender opening date, unless agreed otherwise with the PMU Manager. The capacity and the ability of the
contractor must be assessed to ensure ability to complete the contract. This must include a similar report
on all sub-contractors / SMEEs, including a background check on all parties for all responsive tenders.
All SM Procurement policy and regulations must be strictly adhered to at all times.
Construction Joint Venture agreements must be proven, verified and must be VAT registered in the name
of the JV (No payment will be made until the JV is VAT registered). Sub-contractor (Annexure F)
agreements and labour contracts (Annexure G) must be in place.
Upon receipt of a Commencement Letter, the Consultant shall, in writing, inform the successful contractor
and copy to the PMU Manager, to go ahead with the Works, within one working day of being instructed, in
writing, from the SM.
The Consultant will ensure that Site Establishment by the contractor takes place within 14 working days of
appointment letter to the contractor unless otherwise agreed with the PMU Manager.
The Consultant will ensure the following, but not limited to, is incorporated into the tender documentation:-
1. LIC – where possible
2. Risk will remain with the contractor until issue of the Final Completion Certificate and acceptance by
SM, in writing as stated in this SLA.
3. Training – accredited/non-accredited
4. SMME’s & Local labour (Use, contracts, responsibilities etc)
5. Verified Bill of quantities
6. Latest GCC/JBCC (The contractor must be aware of non-performance and grounds for blacklisting
at National Treasury)
7. Special Conditions of Contract – where required and in terms of this SLA.
8. Detailed description of the Works and specifications.
9. Legislative requirements
10. Appropriate penalty clauses (To be agreed upon by the SM – 0.0085 %/day based on total
tendered-Ex Vat)
11. Expected project outcomes
12. Expected quality & quantity
5 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
13. Insurance, guarantees & sureties before site occupation.
14. Contract contingencies allocation (5% Max - To be approved by the PMU Manager)
15. The contractor will be expected to be on site no later than 14 working days of appointment date
16. Provision must be made for the payment of PSC seating allowances, by the contractor.
17. A provisional sum of R 5 000 must be set aside for a project handover ceremony.
18. The employment of a Community Liaison Officer (CLO) must be accommodated.
19. See “PAYMENT FOR SERVICES”
20. 10% Retention on total contract price.
21. Penalties (Calendar day based).
22. If a JV is acceptable in terms of the construction contract, a clause must be inserted holding the
major JV holder liable in terms of the contract performance and financial impacts.
23. Ensure all workers are registered for UIF in terms of the Unemployment Insurance Act, 63 of 2001
and as amended.
24. Ensure workers are covered by IOD.
The Consultant understands that “contingencies” are only a part of the construction value, if approved by
the PMU Manager in writing, and the Consultant may not claim further expense on “contingencies” as in
terms of this SLA the total value of the project is the tendered value, including “contingencies”, with
exception of approved Variation Orders.
See “ PRICE”
The Consultant will ensure that the all surety, insurance, guarantee, acceptance letter, and relevant
documents are received from the appointed contractor within 14 working days of official appointment date
of the contractor, unless otherwise approved by the PMU Manager, in writing. The Consultant will ensure
the validity of such surety and insurance. Original documents will be kept by the Senqu Municipality.
The Consultant will ensure that the construction Tender Document is signed and witnessed by all parties
within 5 working days of the contractor’s official appointment date.
9. The original signed copy will be kept by the Senqu Municipality.
The consultant will ensure that the following documentation is supplied to the municipality, in hard and soft
copy, within 15 working days of practical completion of the project, which is described as” completion of all
practical works, including snag list and no further financial obligations to the SM other than final retention
payment in terms of the contract”. The SM reserves the right to retain payment of the Consultant, without
additional cost to the SM, until all required information as stipulated below is received.
 Final “as build” plans
 Final Bill of quantities
 Confirmation letter with regard to no further financial implications on the part of the SM, with
exception of final retention (5%) and the date payable of the retention.
 Close out report on the project, as defined in “CONSTRUCTION” S 22.
 A Structural Safety Certificate is required by the SM, issued by a competent registered structural
engineer, where public buildings and bridges are part of or are the full scope of the project. The
Structural Safety Certificate may be for an individual construction or a combination of constructions,
providing each is identified individually on the certificate. Exemption is given for pipe/culvert
crossings shorter than 25 meters or if in writing from the SM.
 Project File (hard & soft copies) with the above documentation but inclusive of the following:-
1. Official correspondence from the Consultant to the Contractor and SM (Include emails)
2. Official correspondence from the Contractor and client (include emails)
6 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
3. Any other relative correspondence (outside service providers etc)
4. PSC attendance registers/minutes
5. Site meeting attendance registers/minutes
6. Any other official meeting attendance registers/minutes
7. Variation orders approved
8. Changes in scope of works (where applicable) and reasons
9. Summary of financials including VO’s and/or contingencies and VAT
10. Performance summary in terms of cost against production (value for money)
11. Summary of Sub Contractor / SMEE performance & payment.
10. GROUNDS FOR BLACKLISTING
Failure to comply with any of the below will result in no final payment and possible National Treasury
“black listing”. [Details may be obtained from the Municipal Finance Management Act:
Circular 43 of 2007]
 Committing an irregular practice/s as defined above.
 Failing to achieve a specified goal as is stipulated in the tender document in terms of Regulation
15(1) of the Preferential Procurement Regulations.
 Committing of any offence as set out in section 12 and 13 of the Prevention and Combating of
Corrupt Activities Act 12 of 2004.
 Persistent non–performance.
 A conviction in respect of a related criminal activity, by a competent court of law, for which the
sentence is a term of imprisonment of not less than six (6) months.
Extract from MFMA Circular 43 of 2007:
The Preferential Procurement Regulations prescribe requirements for developing and applying evaluation
criteria and goals to achieve required outcomes. Should the municipality or entity discover that the bidder
obtained preference on a fraudulent basis or has failed to attain specified goals during the performance of
the contract then certain remedies are available to and need to be considered by the municipality or entity.
Regulation 15 of the Preferential Procurement Regulations reads as follows:
“15 (1) An organ of state must, upon detecting that a preference in terms of the Act and these regulations
has been obtained on a fraudulent basis, or any specified goals are not attained in the performance of the
contract, act against the person awarded the contract.
(2) An organ of state may, in addition to any other remedy it may have against the person contemplated
in sub-regulation (1) –
 recover all costs, losses or damage it has incurred or suffered as a result of that person’s conduct;
 cancel the contract and claim any damages which it has suffered as a result of having to make less
favourable arrangements due to such cancellation;
 impose a financial penalty more severe than the theoretical financial preference associated with the
claim which was made in the tender; and
 restrict the contractor, its shareholders and directors from obtaining business from any organ of
state for a period not exceeding 10 years.”
See attached circular : (Annexure H)
11. CONSTRUCTION
The Consultant is to ensure the following (but not limited to) are implemented timeously and in accordance
with legislation and required industry specifications, in order to achieve the highest quality for resources
available:
7 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
1. The contractor supplies and enforces the required safety measures and requirements (including
Health & Safety Plan)
2. The Consultant will ensure that the contractor takes all reasonable measures prescribed by law
and/or any other reasonable measures necessary for the prevention of accidents during
construction at Senqu Municipality premises or any other areas affected by the construction.
3. The Consultant must ensure that the contractor has adequate insurance cover at all times, and
this will include cover for any sub-contractor/SMME used. This shall also cover public liability
insurance. Proof thereof must be submitted in terms of the contractor’s tender document.
4. A site diary, with a triplicate carbon book specifically for instructions issued, must be
implemented and kept up to date and safely on site at all times. (All instructions must be
recorded in the triplicate book – original to consultant, copy to client) The SM will consider the
instruction as not ever have been given, if not in writing as specified above, and therefore the
Consultant will be liable for any cost that may be incurred if the Contractor implements such
further instruction (s). Also refer to “PRICE” S (a) & (b).
5. Rain fall records must be kept.
6. A site equipment register must be kept.
7. A labour register must be kept and contain the following information:-
a) Division in local and “imported” labour
b) Name of each person
c) Gender of each person
d) Race of each person
e) ID Number of each person
f) Copy of the ID of each person
g) UIF Payments
h) Pay Rate (per hour) of each person
i) Days worked per person
j) Category of work (Unskilled, Semi-Skilled, Operator, Driver, Skilled, Professional)
k) Total payment for local labour
l) Total payment for ‘imported” labour
m) Number of SMME’s used
n) Payment to SMME’s
o) Training (Number, type, length, cost and accredited or not)
p) Copy of contracts with labour and SMME’s.
8. Labour must be sourced from the ward where the project is taking place and done in conjunction
with the Ward Councilor through the CLO.
9. Labour rates paid must be in accordance to the amount stipulated by the Department of Labour,
which may vary from time to time.
10. The SM will not be held liable for any costs that may arise (direct & non-direct) due to the project
being shut down or delayed due to non-compliance of any construction, environmental, labour or
any other relevant legislation.
11. The Consultant must ensure that the contractor’s Site Establishment is done in an acceptable
manner, taking the local community and circumstances into consideration.
12. The Consultant will ensure that he / she have a representative on site at all times and that the
contractor has a mandated representative on site at all times.
13. The Consultant agrees to allow SM to obtain a third party professional opinion, at any time
during or after construction, in order to confirm quality / quantities, or any other part of the Works
or documentation related to the Works.
14. The Consultant will at all times ensure the quality and quantities of the Works/ Materials are
correct, within specifications and acceptable. Should it later emerge that this is not the case, the
8 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
municipality reserves the right to hold the Consultant fully accountable for the following and any
other appropriate action in terms of this agreement:-
a) All associated construction costs in correction Works to be done
b) All administrative and/or legal costs
c) Cost of any other professional opinion in order to evaluate works.
d) Should evaluation reports on quality / quantity prove to be acceptable; the SM will pay the cost
of such evaluation and if not, the Consultant will be liable for the costs.
15. The Consultant shall continually evaluate the performance of the contractor against established
timeframes, milestones, cash flows, quality and performance to expenditure.
16. The Consultant will ensure that monthly technical and site meetings are held and that a Project
Steering Committee is formed that includes the Ward Councillor. A seating allowance must be
payable by the contractor, of a minimum of R 300 / person /meeting in order to cover travelling
costs. This amount may be amended from time to time and the Consultant must request the
amount prior to project costing. The seating allowance will not apply to officials of the
municipality or any other government department or parastatal. All meetings will be held on site
unless otherwise required by the SM.
17. The Consultant will submit all appropriate required reports monthly no later than 2 working days
after calendar month end, in soft and hard copy to the PMU manager.
18. The Consultant must inform the PMU Manager and Ward Councillor immediately, in writing, in
the event any of the following occurring:-
a) Accidents/death on site
b) Major change in scope of the Works required
c) Any other change/incident that may affect the outcome or cost of the project.
d) Any labour related matters that may delay or negatively affect the project.
e) Any material supply matters that may delay or negatively affect the project.
f) Damage to existing services.
19. The Consultant will issue a Practical Completion Certificate and a Final Completion Certificate at
the appropriate stage of the construction contract. Any retention payment will be measured from
the date of the Practical Completion Certificate for a period of one calendar year unless
specified otherwise in the tender document.
20. The Consultant will ensure the implementation of the latest GCC/JBCC at all times.
21. The Consultant shall ensure return of all relevant contractual documentation to the contractor
within a reasonable period of construction contract completion. (Sureties, guarantee’s etc.)
22. The Consultant shall, upon issue of the Final Completion Certificate, within 15 working days,
provide the SM with a project “close out” report which will contain the following project
information:-
a) Back ground
b) Objectives
c) Budget (Payment certificates – Direct & Indirect – VOs- Contingencies etc.)
d) Cash flow
e) Milestones
f) Weather
g) Labour summary (numbers, payments, totals, man days, local, youth, sex etc.)
h) Training summary
i) Challenges/ targets
j) Lessons learnt
k) Photographs (before & after-date stamped with coordinates)
9 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
l) Recommendations
m) General comments
12. CONSTRUCTION CONTRACT PERIOD & PENALTIES
Failure by the Consultant to effect delivery of the construction contract within the specified period,
as tendered by the construction contractor (this includes extension of time in accordance with the
GCC), shall constitute a breach of contract, which breach shall entitle SM to:-
a) Implement penalty costs on a daily basis of 0.0085 % of the Consultants accepted tender value
(Before VAT – No VAT charged on penalties). This applies to calendar days.
b) If determined as poor performance, in terms of Annexure D, may cancel the contract with the
Consultant
c) Hold the Consultant liable for all professional costs related to completing the tender in
accordance with specifications; and should it be necessary, claim previous construction
rectification costs from the Consultant.
d) The Consultant will be blacklisted on the National Treasury database;
e) Exercise any of its rights in terms of this agreement or relevant legislation.
f) The SM will allow the Consultant an opportunity to mitigate their circumstances, in writing,
before a final decision is made.
13. INFORMATION
1. The Consultant understands that the SM holds full copyright and ownership on all project related
documentation, inclusive of designs, plans etc.
2. All information is to be considered as confidential.
The Consultant may retain such information but may only make use thereof by express written permission
of the SM. The information may be shared with other parties only with the express written permission of the
SM.
14. LEGAL COMPLIANCE
The Consultant hereby indemnifies and agrees to defend and hold SM harmless from any liability arising or
alleged to arise out of any failure of construction works / services or to conform to any laws, orders,
regulations, requirements or standards.
15. PERFORMANCE
KPI’s are weighted and scored to a maximum of 5 points. Performance will be rated monthly, with or
without the Consultant. The dates will be pre-arranged.
All scores will be done in terms of Annexure D and scores will be converted to percentage to determine a
total percentage based between compliance and satisfaction.
Score categories vs performance is as follows:-
PERFORMANCE RATING
0% 80% Unacceptable
81% 90% Poor
91% 92% Good
10 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
93% 96% Very Good
97% 100% Excellent
In terms of this agreement, the SM reserves the right to terminate the Consultants contract for poor
performance with regard to the above, should it become evident that the consultant cannot achieve at least
“good” status before the half way point of the construction contract.
In the event of termination due to non-performance of the service provider, no outstanding payment shall
be considered until such time the construction contract has reached Final Completion Certificate stage and
only then if there is funding available.
Should there be any financial loss for the SM due to contract termination for poor performance; the SM
reserves the right to recover such cost from the Consultant, with regard to professional and related costs,
as well as any cost on construction, that is due to the poor performance of the Consultant on the project.
16. AVAILABILITY
It is a condition of appointment that at any stage during the period of responsibility, the Consultant will
make him/herself available, all reasonable hours, for inspection of the works or meetings, at any location
deemed reasonable by the SM, at request of an authorized representative of SM or agent acting on behalf
of SM. A minimum notice period of 48 hours will be allowed with the exception of what the SM considers as
an emergency.
17. TRANSFER OF RISK
The SM will only accept risk on the project upon receipt of the Practical Completion Certificate, final Bill of
Quantities, final “as build” and letter of financial confirmation. [Refer ”DOCUMENTATION”]. Until the
Practical Completion Certificate is received, all insurance and other risk remains with the Consultant who
must ensure such in the Contractors tender document.
18. CESSION AGREEMENTS
No cession agreements will be entertained, by the Consultant or the contractor, without the prior written
consent of the municipality and these types of arrangements must be avoided if possible.
19. DESIGN & CONSTRUCT
If the Consultant is appointed on a Turnkey / Principle Agent (Design & Construct) basis, all the
requirements of this SLA will still apply to the Consultant but will also include the latest GCC/JBCC and
other construction matters as referred to in this agreement. The Consultant will then be considered as a
Contractor. Please see “PAYMENT”
The SM still retains its rights within any other law aside from and within this agreement, in the event of a
turnkey appointment.
20. PROFESSIONAL JOINT VENTURES
The Consultant is allowed to engage into a joint venture on the following conditions:-
 The JV partner (s) must also be a competent person in the same or other required discipline in
order to meet the completion of the contract works.
 No payment will be made unless the JV is VAT registered.
 The JV must have tendered in accordance with SM procurement regulations.
 The percentage value split must be indicated in the JV agreement. This percentage will determine
the split in responsibility/accountability between the JV partners in terms of this SLA and any other
recourse in terms of law.
11 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
 All JV partners must sign this SLA
 There must be a bank account in the name of the JV
21. PAYMENT FOR SERVICES
SM reserves the right to only pay for services, after verification by the PMU Manager, for both the
Consultant and the Contractor, and within 30 days of date of invoice. Where possible, this will be
shortened, in order to assist with cash flow.
The SM reserves the right to withhold/delay payment from the Consultant and the Contractor, for the next
Payment Certificate submitted, in the event that the labour and/or SMME’s on the project are not paid by
month end by the Contractor on the previous certificate. The delayed payment will be determined by the
number of days late payment to the labour and/or SMME’s after the stipulated month end. ie If only paid 6
days after month end, the Contractor payment for the next certificate will be intentionally delayed for 30
days plus 6 days etc.(30 + 6 = 36 days) Proof of timeous payment must be submitted to each Site Meeting
failing which it will be considered that labour and SMME’s have not been paid. This will include sub-
contractors. This must be included in the Construction tender document for the contractor.
The SM guarantees payment to the Consultant for verified services in accordance to the above.
The SM reserves the right not to pay the Consultant and the Contractor if Labour Reports (or any other
requested report) are not received timeously, without penalty to the municipality. This must be included
into the Construction tender document for the contractor.
The SM reserves the right not to process payment in the event of any possible conflict with performance of
the Consultant until such time that the matter is resolved or the SM has exercised its tights in terms of this
agreement or applicable legislation.
The SM will hold the Consultant liable for all costs that may occur due to inappropriate / mismatched /
incomplete Bill of Quantities, design & specifications, project management, quality control and safety and
reserves the right to withhold payment to the Consultant.
SM reserves the right, and the Consultant agrees as such, to inspect, test or analyze any goods/services,
through an appointed independent, appropriately qualified third party, and reject such that do not, in SM’s
sole discretion, comply with the contractual requirements, specifications and/or quality. In the event of the
Works being of correct specification and quality, the SM will cover the cost of such third party. The
converse shall also apply. Any goods/services that Senqu Municipality rejects for non-compliance with
regard to the above shall be held at the cost and risk of the Consultant, who shall, when called upon,
comply with contractual requirements at own cost.
Payments as the Consultant will be as follows:
 Design: 20%
 Procurement completion up to report stage: 10%
 Project Management: 60% (linked directly to Contractors performance)
 Practical Completion/Final documentation/ Structural Certificate (Where appropriate): 5%
 Final Completion Certificate: 5%
Payment on Turnkey (Design & Construct) will take place as follows-(Unless approved otherwise, in writing,
by the SM):-
 Design & documentation up to municipal approval (As per this agreement as Consultant): 10%
 Site establishment: 5%
 Construction (As per progress / BoQ): 75%
 Practical Completion: 5% (1st
retention release)
 Final Completion: 5% (2nd
retention release)
12 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
22. CONTRACTOR PAYMENTS
The Consultant shall ensure that contractor certificates for payment will be submitted as follows:-
 Certificate 1: Site establishment and percentage of P & G’s.
 Certificate 2 onwards: Materials on site and work verified done to date
 P & G’s are to be equally distributed over contract period on a percentage basis, including
Certificate 1, but excluding the last two retention certificates.
 Second final certificate: release of first retention (5%) AFTER receipt of the Practical Completion
Certificate.
 Final certificate: release of final retention (5%) AFTER receipt of the Final Completion Certificate.
 It must be noted that retention is to be deducted on an ongoing basis, to the value of 10% of the
TOTAL project value, including the last construction works certificate and the Site Establishment
certificate and excluding the separate retention release certificates.
 All the above must be done in a format approved by the municipality and must include progress
reports in the format approved by the municipality. [Annexure A & B & C]
Should any claims verified by the Consultant, be discovered before or after payment to the contractor, be
untrue, the SM reserves the right to hold the Consultant liable in all implications of such a matter and the
right to dismiss the consultant with immediate effect if discovered to be deliberate and to recover any costs
involved directly from the Consultant.
23. FAILURE TO COMPLY AND DELAYED EXECUTION
Should the Consultant fail to comply with any of the conditions of this agreement, SM shall be entitled,
without prejudice to any of its other rights, to cancel the appointment of the Consultant.
Upon any delay beyond the contract period, SM may, without prejudice to any other right and without
canceling the Consultants appointment, be entitled to arrange for the execution of the service(s) not
rendered or not rendered in conformity with this agreement or to cancel the appointment and without
prejudice to its other rights, be entitled to claim damages from the Consultant.
24. BREACH
If either party breaches these terms and conditions, as per this agreement, and fails to remedy such breach
within 30 calendar days of written notice from any other party calling for the breach to be remedied, then
the non-breaching party shall be entitled, without prejudice to any other rights that it may have in law,
whether under this agreement or otherwise, to cancel the appointment without notice or to claim immediate
specific performance of all the defaulting party's obligations, whether or not due for performance, in either
event without prejudice to the aggrieved party's right to claim damages.
25. DEATH, SEQUESTRATION, LIQUIDATION OR JUDICIAL MANAGEMENT
In the event of the death of a Consultant or the provisional or final sequestration of the Consultant or of its
cession or transfer of the appointment without the approval of SM or of the surrender of its business or it
reaching a compromise with its creditors or of the provisional or final liquidation of a Consultants company
or the placing of its affairs under judicial management, SM may, without prejudice to any other rights it may
have at law, exercise any of the following options:
- Cancel the appointment and accept any offer subsequently received to complete the services. In
such a case the Consultant shall not be relieved from liability for any claim which has arisen or may
arise against the Consultant in respect of goods/services not delivered or work not carried out by
the Consultant under the appointment.
13 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
- allow the executor, trustee, liquidator or judicial manager, as the case may be, for and on behalf of
and at the cost and expense of the business of the Consultant to carry on with and complete the
contract; or
- for and on behalf of and at the cost and expense of the business of the Consultant, itself carry on
with and complete the contract
26. DISPUTE RESOLUTION
Any unresolved dispute between the parties arising out or in connection with this SLA, including its
existence, application, breach, interpretation, validity, termination or cancellation, shall be referred to the
Senior Manager: Supply Chain Management of Senqu Municipality, who will have seven (7) working days
to resolve the dispute, and if not resolved, then the Municipal Manager, who will undertake to meet within
seven (7) working days after being requested by either party, in order to resolve the dispute.
Only thereafter, if nor resolved, shall the matter be submitted to and decided by arbitration in terms of the
Arbitration Act, 1965, of the Republic of South Africa, subject to the following provisions:
In the event of either party having a claim against the other party for a liquidated amount or an amount
which arises from a liquid document, then the party having such claim shall be entitled to institute action
therefore in a court of law rather than in terms of the above, notwithstanding the fact that the other party
may dispute such claim.
27. GOVERNING LAW
Is the law of South Africa, as amended time to time.
28. NOTICES AND CONTACT
Each party chooses as its address for all purposes under this SLA (“chosen address”), whether for serving
any court process or documents, giving any notice, or making any other communications of whatsoever
nature and for any other purpose arising from this SLA (“notice & contact”), as its domicilium citandi et
executandi. A domicilium citandi et executandi shall be chosen in the Republic of South Africa. This will be
inserted into this agreement below.
Any notice required or permitted under this SLA shall be valid and effective only if in writing, in terms of
“CORRESPONDENCE’ above.
Any party may, by notice to the other party, change its chosen address to another physical address in the
Republic of South Africa and such change shall take effect on the seventh (7) calendar day after the date of
receipt by the party who last receives the notice.
Any notice to a party contained in a correctly addressed envelope and delivered by hand to a responsible
person during ordinary business hours at its chosen address, shall also be deemed acceptable.
29. LIMITATION OF LIABILITY
Unless otherwise provided for in this agreement or in any further written agreement, neither party shall be
liable to the other for any indirect, consequential, special, incidental or punitive damages, including without
limitation, loss of use or lost business, revenue, profits, anticipated savings, reputation or goodwill arising in
connection with the Consultants appointment , services, related products, documentation and/ or the
intended use thereof under any theory, contract, warranty, strict liability or negligence even if the party has
been advised, knew or should have known of the possibility of such damages.
Nothing in this agreement shall restrict either party’s liability for:
(a) Fraud; or
14 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
(b) Death or personal injury caused by its negligence or intentional or willful act;
(c) Damage to real or tangible personal property caused by its negligence or intentional or willful
misconduct; or
(d) Any breach of obligations under this agreement in respect of confidentiality and intellectual
property; or
(e) Any other liability that cannot be excluded by law.
30. CONFIDENTIALITY
The parties agree that the terms of this SLA that all confidential and proprietary information of the parties
communicated to them in connection with this SLA/appointment shall be received in strict confidence and
be used only for the purposes of this SLA/appointment. Each party shall use the same means as it uses to
protect its own confidential information, but in no event less than reasonable means, to prevent the
disclosure and to protect the confidentiality of such information. No such information shall be disclosed by
the recipient party, its agents, representatives or employees without the prior written consent of the other
party.
These provisions do not apply to information which is:
- publicly known or becomes publicly known through no un-authorised act of the recipient party;
- rightfully received by the recipient party from an outside party;
- independently developed by the recipient party without use of the other party's information;
- disclosed by the other party to an outside party without similar restrictions;
- required to be disclosed pursuant to a requirement of a governmental agency or any applicable
law,; or
- Publicly disclosed with the other party's written consent.
_____________________________________________________________________________________
We, the undersigned, as mandated representatives, understand and agree to the terms of this Service
Level Agreement.
FOR SENQU MUNICIPALITY
NAME: SIGNATURE: DATE:
Cell: email:
CAPACITY
FOR CONSULTANT
NAME: SIGNATURE DATE
CAPACITY:
15 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management
SENQU MUNICIPALITY
ADDRESS: 19 MURRAY STREET
LADY GREY
9755
POSTAL ADDRESS: PO BOX 18
LADY GREY
9755
Fax: 051-6030445
Tel: 051- 6031300
COMPANY NAME ______________________________________________________________________
ADDRESS: ___________________________________________________________________________
POSTAL ADDRESS:____________________________________________________________________
Cell:_______________________ Tel: ________________________email:_________________________
WITNESS # 1:
NAME:
SIGNATURE:
WITNESS # 2:
NAME:
SIGNATURE:
16 | P a g e
Performance Service Level Agreement – Professional Services – Technical Services: Project Management

More Related Content

What's hot

Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Tendering clauses of contract
Tendering clauses of contractTendering clauses of contract
Tendering clauses of contractkkganimix
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
35 days bid procedure for construction project
35 days bid procedure for construction project35 days bid procedure for construction project
35 days bid procedure for construction projectMarvin M Gamboa
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
Construction contract
Construction contractConstruction contract
Construction contractAqsa Shafique
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 

What's hot (20)

M4ppt
M4pptM4ppt
M4ppt
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Tendering clauses of contract
Tendering clauses of contractTendering clauses of contract
Tendering clauses of contract
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
35 days bid procedure for construction project
35 days bid procedure for construction project35 days bid procedure for construction project
35 days bid procedure for construction project
 
Construction contract
Construction contract Construction contract
Construction contract
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Construction contract
Construction contractConstruction contract
Construction contract
 
contract procedure
contract procedurecontract procedure
contract procedure
 
ACH 216 Lecture 04b (Bidding) Part 1
ACH 216 Lecture 04b (Bidding) Part 1ACH 216 Lecture 04b (Bidding) Part 1
ACH 216 Lecture 04b (Bidding) Part 1
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Audit of contracts version 2
Audit of contracts version 2Audit of contracts version 2
Audit of contracts version 2
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Tender
TenderTender
Tender
 

Viewers also liked

Shaping Global and National Economies to Better Respond to Climate Challenge...
Shaping Global and National Economies to Better Respond  to Climate Challenge...Shaping Global and National Economies to Better Respond  to Climate Challenge...
Shaping Global and National Economies to Better Respond to Climate Challenge...Ngozi Okonjo-Iweala
 
CSCM Evaluate supplier performance
CSCM Evaluate supplier performanceCSCM Evaluate supplier performance
CSCM Evaluate supplier performanceEst
 
Dấu hiệu cảnh báo suy tim
Dấu hiệu cảnh báo suy timDấu hiệu cảnh báo suy tim
Dấu hiệu cảnh báo suy timlananhlt206
 
João gabriel da silva
João gabriel da silvaJoão gabriel da silva
João gabriel da silvaFABIANA
 
Cartaz ativ. pre escolar dezembro 2011-12
Cartaz ativ. pre  escolar dezembro 2011-12Cartaz ativ. pre  escolar dezembro 2011-12
Cartaz ativ. pre escolar dezembro 2011-12bibdjosei2006
 
Fundamentos de Gestion Empresarial
Fundamentos de Gestion EmpresarialFundamentos de Gestion Empresarial
Fundamentos de Gestion EmpresarialAngelDelgadoR
 
As Horas do Dia e o inicio do Sábado.
As Horas do Dia e o inicio do Sábado.As Horas do Dia e o inicio do Sábado.
As Horas do Dia e o inicio do Sábado.ASD Remanescentes
 
The Sourcing Of Outsourcing
The Sourcing Of OutsourcingThe Sourcing Of Outsourcing
The Sourcing Of OutsourcingJohn Meyerson
 
Como Transliteraram o Nome do Salvador?
Como Transliteraram o Nome do Salvador?Como Transliteraram o Nome do Salvador?
Como Transliteraram o Nome do Salvador?ASD Remanescentes
 
CSCM group project aug 2016
CSCM group project aug 2016CSCM group project aug 2016
CSCM group project aug 2016Est
 
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation ModelI3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation ModelCCT International
 
BIM project execution
BIM project executionBIM project execution
BIM project executionStephen Au
 

Viewers also liked (19)

Shaping Global and National Economies to Better Respond to Climate Challenge...
Shaping Global and National Economies to Better Respond  to Climate Challenge...Shaping Global and National Economies to Better Respond  to Climate Challenge...
Shaping Global and National Economies to Better Respond to Climate Challenge...
 
CSCM Evaluate supplier performance
CSCM Evaluate supplier performanceCSCM Evaluate supplier performance
CSCM Evaluate supplier performance
 
Vom Pfannkuchenbäcker zum Multihotelier.doc
Vom Pfannkuchenbäcker zum Multihotelier.docVom Pfannkuchenbäcker zum Multihotelier.doc
Vom Pfannkuchenbäcker zum Multihotelier.doc
 
Veterans day 2015
Veterans day 2015Veterans day 2015
Veterans day 2015
 
Dấu hiệu cảnh báo suy tim
Dấu hiệu cảnh báo suy timDấu hiệu cảnh báo suy tim
Dấu hiệu cảnh báo suy tim
 
Ejercicio2
Ejercicio2Ejercicio2
Ejercicio2
 
João gabriel da silva
João gabriel da silvaJoão gabriel da silva
João gabriel da silva
 
Cartaz ativ. pre escolar dezembro 2011-12
Cartaz ativ. pre  escolar dezembro 2011-12Cartaz ativ. pre  escolar dezembro 2011-12
Cartaz ativ. pre escolar dezembro 2011-12
 
Enigma google
Enigma googleEnigma google
Enigma google
 
Apresentação
ApresentaçãoApresentação
Apresentação
 
Fundamentos de Gestion Empresarial
Fundamentos de Gestion EmpresarialFundamentos de Gestion Empresarial
Fundamentos de Gestion Empresarial
 
Ptar
PtarPtar
Ptar
 
As Horas do Dia e o inicio do Sábado.
As Horas do Dia e o inicio do Sábado.As Horas do Dia e o inicio do Sábado.
As Horas do Dia e o inicio do Sábado.
 
The Sourcing Of Outsourcing
The Sourcing Of OutsourcingThe Sourcing Of Outsourcing
The Sourcing Of Outsourcing
 
Como Transliteraram o Nome do Salvador?
Como Transliteraram o Nome do Salvador?Como Transliteraram o Nome do Salvador?
Como Transliteraram o Nome do Salvador?
 
CSCM group project aug 2016
CSCM group project aug 2016CSCM group project aug 2016
CSCM group project aug 2016
 
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation ModelI3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model
 
ECG RỐI LOẠN NHỊP
ECG RỐI LOẠN NHỊPECG RỐI LOẠN NHỊP
ECG RỐI LOẠN NHỊP
 
BIM project execution
BIM project executionBIM project execution
BIM project execution
 

Similar to CSCM Sla cscm

CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxMeneerGultom
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKegler Brown Hill + Ritter
 
Construction practices
Construction practicesConstruction practices
Construction practicesArun Kurali
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation servicesabenyeung1
 
1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdfEphremZeleke3
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender NoticeSakshi Kirar
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
 
Presentation sidig med-jts
Presentation sidig med-jtsPresentation sidig med-jts
Presentation sidig med-jtsAnna Codazzi
 
Consultant contract for small assignments – time based
Consultant contract for small assignments – time basedConsultant contract for small assignments – time based
Consultant contract for small assignments – time basedJoy Irman
 

Similar to CSCM Sla cscm (20)

CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Document samples
Document samplesDocument samples
Document samples
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
 
1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
ICDS : Construction Contracts
ICDS : Construction ContractsICDS : Construction Contracts
ICDS : Construction Contracts
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
Presentation sidig med-jts
Presentation sidig med-jtsPresentation sidig med-jts
Presentation sidig med-jts
 
Consultant contract for small assignments – time based
Consultant contract for small assignments – time basedConsultant contract for small assignments – time based
Consultant contract for small assignments – time based
 
tendering
 tendering tendering
tendering
 
Cl report final
Cl report finalCl report final
Cl report final
 

More from Est

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017Est
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3Est
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4Est
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmEst
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM PartneringEst
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in constructionEst
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscmEst
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangementEst
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2Est
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016Est
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systemsEst
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmEst
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docxEst
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignmentEst
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MSEst
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrmEst
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergEst
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationEst
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communicationEst
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016Est
 

More from Est (20)

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscm
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM Partnering
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in construction
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscm
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangement
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systems
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscm
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignment
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MS
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrm
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerberg
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivation
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communication
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016
 

Recently uploaded

YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbaisonalikaur4
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILChristina Parmionova
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersCongressional Budget Office
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...Suhani Kapoor
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证mbetknu
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolSERUDS INDIA
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...narwatsonia7
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书mbetknu
 

Recently uploaded (20)

YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service MumbaiHigh Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
High Class Call Girls Mumbai Tanvi 9910780858 Independent Escort Service Mumbai
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists Lawmakers
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证
 
Start Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnoolStart Donating your Old Clothes to Poor People kurnool
Start Donating your Old Clothes to Poor People kurnool
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
No.1 Call Girls in Basavanagudi ! 7001305949 ₹2999 Only and Free Hotel Delive...
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书
 

CSCM Sla cscm

  • 1. 1 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management SERVICE LEVEL AGREEMENT PROFESSIONAL SERVICES – PERFORMANCE – CIVIL & BUILDING WORKS BETEWEEN SENQU MUNICIPALITY (Hereafter referred to as SM) AND (Hereafter referred to as the “Consultant”) DATE:_________________ PROJECT NAME NOTICE #: _________________________
  • 2. 2 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 1. PURPOSE The purpose of this Service Level Agreement is to enforce certain guidelines that the appointed consultant must consider and enforce throughout the project lifespan and responsibility period as defined within this agreement, and performance measurement and penalties of the consultant, as stipulated within this agreement. It is accepted that the Consultant is aware and understands all terms and abbreviations used within this SLA. 2. GENERAL The following general terms and conditions have been laid down for all construction or similar appointments. 1. Where such special conditions or procedures are in conflict with this SLA, the said special conditions or procedures shall apply but must be incorporated into the standard SLA (SAICE). 2. These SLA terms and conditions, may at SM’s sole discretion, be amended or supplemented and the service provider notified in writing within 5 working days thereof. The service provider will have a further 5 working days to accept/respond to such changes. 3. For purpose of this agreement the word “appointment” will be considered as the contract for professional services as required and tendered for by the Consultant, to the SM, in order to achieve construction completion in terms of objectives, budget, quality and quantity as per the successful construction bidders contract. 4. Reference to the GCC will include any other sector related contracts in common use. (eg JBCC) and terms identified within this contract related to the GCC will be replaced with the terms of the sector contract but conditions and penalties will remain the same. 5. Contract length will be from date of appointment to one calendar month after Final Completion is achieved, unless otherwise dictated in terms of this agreement or law. 6. The point of contact within the municipality will be the PMU manager, unless otherwise stated by the SM, in writing. 7. Principle Agent/ Team shall be considered to refer to Consultant, both being considered the same in terms of this Service Level Agreement. 3. CORRESPONDENCE All signed written correspondence, including faxes and e-mail received from the Consultant or the SM will be regarded as binding to the party and company whom he / she represents. Certain critical correspondences will be required on official letterhead from both parties. 4. REFERENCE DOCUMENTS Where the need arises to obtain reference/specification documents, the Consultant will do so from the relevant authority, at own cost. 5. PERIOD OF RESPONSIBILITY The period within which the total responsibility/accountability of the Consultants appointment is to remain valid and binding on the Consultant will be from the date of the signed letter of acceptance for the tender submitted, returned to SM, until 31 calendar days after the issue of the Final Completion Certificate date. The consultant will remain liable for design and construction for any further period as identified by the industry or law. This applies to the Works that the Consultant was appointed for in terms of the appointment. The SM retains the right to extend such period of contract accountability if there is any doubt on the quality of the Works or any associated matter, for any reasonable amount of time, at no cost to the SM, until the matter has been dealt with fully and in all respects, in terms of this agreement. Consultants will be required to attend any meeting considered as reasonable, requested by the SM, even after Final Completion, should any information be required for clarification.
  • 3. 3 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 6. PRICE a) Tendered prices are fixed and considered as the total cost (Including disbursements etc.) and only subject to adjustments in accordance with the actual increases resulting from the change of rendering costs for the execution of the contract upon prior approval of Contingency expenditure or a Variation Order, which may not exceed 20% of the total contract / tender value (Direct or Indirect cost). Any such adjustment will be done on a pro-rata scale, calculated in percentage, and reduced to figures (Including VAT). Any additional Works MUST be approved, in writing, by the SM BEFORE instruction is given to the contractor to continue with such works. b) The contract construction or management cost may not be exceeded by the Consultant without the express written permission of the SM. Should this occur without prior written permission, the Consultant will be held accountable for such costs. c) In the event of a contractor being removed from site in terms of the GCC or any other legislation, the Consultant may not retender the project without the express written permission of the SM. The Consultant must ensure that the construction site is safe and usable to the public (where applicable) at all times, until the SM has, in writing, issued further instructions. The Consultant will, within 10 working days, submit a revised construction cost to complete the project. 7. DESIGN Dependent on the urgency or nature of the Works, the Consultant is to consider the following in the design for the Works, without eroding quality or circumventing legislation:- 1. Labor intensive construction methods (LIC) using local labour/SMME’s 2. Sustainability of the project 3. Possible risks 4. Project objectives 5. Use of local suppliers where possible 6. Use of local registered contractors on the SM database as sub-contractors in order to develop accession in the CIDB rating. 7. Possible alternatives 8. Price (Value for money) 9. Contingencies and criteria for use thereof. 10. Future maintenance and operational cost 11. Environmental and other legislative requirements 12. Time frames 13. Cash flow predictions 14. CIDB considerations 15. Community considerations in terms of buy in (ISD) 16. Client liaison and design approval 17. Establish and confirm that the Contractor has sufficient resources and capacity to complete the project, aside from the CIDB rating. 8. DOCUMENTATION The Consultant will ensure that advertisements are placed in at least 2 registered newspapers for contracts under R 10 M and 3 registered newspapers if over R 10 M.
  • 4. 4 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management Minimum advertisement periods will be 21 days for values under R 10 m and 31 days for any value over R 10 M. Copies of the original newspaper advertisements must be given to the PMU Manager within 5 working days of their placement/publication. The Consultant will ensure a compulsory tender site meeting on all projects, unless agreed otherwise with the SM. The Consultant will ensure that accurate minutes and attendance registers are kept of all official meetings and distributed within 5 working days to all relevant parties as will be agreed upon at the first official site meeting. The Consultant (or representative) will be present at the official opening of tender documents (SM SCM processes) and will sign for receipt of the documents (Annexure E), after processed, before removal from the SM premises, for appraisal purposes. The Consultant will submit a tender evaluation report within 15 working days of official opening of the tender opening date, unless agreed otherwise with the PMU Manager. The capacity and the ability of the contractor must be assessed to ensure ability to complete the contract. This must include a similar report on all sub-contractors / SMEEs, including a background check on all parties for all responsive tenders. All SM Procurement policy and regulations must be strictly adhered to at all times. Construction Joint Venture agreements must be proven, verified and must be VAT registered in the name of the JV (No payment will be made until the JV is VAT registered). Sub-contractor (Annexure F) agreements and labour contracts (Annexure G) must be in place. Upon receipt of a Commencement Letter, the Consultant shall, in writing, inform the successful contractor and copy to the PMU Manager, to go ahead with the Works, within one working day of being instructed, in writing, from the SM. The Consultant will ensure that Site Establishment by the contractor takes place within 14 working days of appointment letter to the contractor unless otherwise agreed with the PMU Manager. The Consultant will ensure the following, but not limited to, is incorporated into the tender documentation:- 1. LIC – where possible 2. Risk will remain with the contractor until issue of the Final Completion Certificate and acceptance by SM, in writing as stated in this SLA. 3. Training – accredited/non-accredited 4. SMME’s & Local labour (Use, contracts, responsibilities etc) 5. Verified Bill of quantities 6. Latest GCC/JBCC (The contractor must be aware of non-performance and grounds for blacklisting at National Treasury) 7. Special Conditions of Contract – where required and in terms of this SLA. 8. Detailed description of the Works and specifications. 9. Legislative requirements 10. Appropriate penalty clauses (To be agreed upon by the SM – 0.0085 %/day based on total tendered-Ex Vat) 11. Expected project outcomes 12. Expected quality & quantity
  • 5. 5 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 13. Insurance, guarantees & sureties before site occupation. 14. Contract contingencies allocation (5% Max - To be approved by the PMU Manager) 15. The contractor will be expected to be on site no later than 14 working days of appointment date 16. Provision must be made for the payment of PSC seating allowances, by the contractor. 17. A provisional sum of R 5 000 must be set aside for a project handover ceremony. 18. The employment of a Community Liaison Officer (CLO) must be accommodated. 19. See “PAYMENT FOR SERVICES” 20. 10% Retention on total contract price. 21. Penalties (Calendar day based). 22. If a JV is acceptable in terms of the construction contract, a clause must be inserted holding the major JV holder liable in terms of the contract performance and financial impacts. 23. Ensure all workers are registered for UIF in terms of the Unemployment Insurance Act, 63 of 2001 and as amended. 24. Ensure workers are covered by IOD. The Consultant understands that “contingencies” are only a part of the construction value, if approved by the PMU Manager in writing, and the Consultant may not claim further expense on “contingencies” as in terms of this SLA the total value of the project is the tendered value, including “contingencies”, with exception of approved Variation Orders. See “ PRICE” The Consultant will ensure that the all surety, insurance, guarantee, acceptance letter, and relevant documents are received from the appointed contractor within 14 working days of official appointment date of the contractor, unless otherwise approved by the PMU Manager, in writing. The Consultant will ensure the validity of such surety and insurance. Original documents will be kept by the Senqu Municipality. The Consultant will ensure that the construction Tender Document is signed and witnessed by all parties within 5 working days of the contractor’s official appointment date. 9. The original signed copy will be kept by the Senqu Municipality. The consultant will ensure that the following documentation is supplied to the municipality, in hard and soft copy, within 15 working days of practical completion of the project, which is described as” completion of all practical works, including snag list and no further financial obligations to the SM other than final retention payment in terms of the contract”. The SM reserves the right to retain payment of the Consultant, without additional cost to the SM, until all required information as stipulated below is received.  Final “as build” plans  Final Bill of quantities  Confirmation letter with regard to no further financial implications on the part of the SM, with exception of final retention (5%) and the date payable of the retention.  Close out report on the project, as defined in “CONSTRUCTION” S 22.  A Structural Safety Certificate is required by the SM, issued by a competent registered structural engineer, where public buildings and bridges are part of or are the full scope of the project. The Structural Safety Certificate may be for an individual construction or a combination of constructions, providing each is identified individually on the certificate. Exemption is given for pipe/culvert crossings shorter than 25 meters or if in writing from the SM.  Project File (hard & soft copies) with the above documentation but inclusive of the following:- 1. Official correspondence from the Consultant to the Contractor and SM (Include emails) 2. Official correspondence from the Contractor and client (include emails)
  • 6. 6 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 3. Any other relative correspondence (outside service providers etc) 4. PSC attendance registers/minutes 5. Site meeting attendance registers/minutes 6. Any other official meeting attendance registers/minutes 7. Variation orders approved 8. Changes in scope of works (where applicable) and reasons 9. Summary of financials including VO’s and/or contingencies and VAT 10. Performance summary in terms of cost against production (value for money) 11. Summary of Sub Contractor / SMEE performance & payment. 10. GROUNDS FOR BLACKLISTING Failure to comply with any of the below will result in no final payment and possible National Treasury “black listing”. [Details may be obtained from the Municipal Finance Management Act: Circular 43 of 2007]  Committing an irregular practice/s as defined above.  Failing to achieve a specified goal as is stipulated in the tender document in terms of Regulation 15(1) of the Preferential Procurement Regulations.  Committing of any offence as set out in section 12 and 13 of the Prevention and Combating of Corrupt Activities Act 12 of 2004.  Persistent non–performance.  A conviction in respect of a related criminal activity, by a competent court of law, for which the sentence is a term of imprisonment of not less than six (6) months. Extract from MFMA Circular 43 of 2007: The Preferential Procurement Regulations prescribe requirements for developing and applying evaluation criteria and goals to achieve required outcomes. Should the municipality or entity discover that the bidder obtained preference on a fraudulent basis or has failed to attain specified goals during the performance of the contract then certain remedies are available to and need to be considered by the municipality or entity. Regulation 15 of the Preferential Procurement Regulations reads as follows: “15 (1) An organ of state must, upon detecting that a preference in terms of the Act and these regulations has been obtained on a fraudulent basis, or any specified goals are not attained in the performance of the contract, act against the person awarded the contract. (2) An organ of state may, in addition to any other remedy it may have against the person contemplated in sub-regulation (1) –  recover all costs, losses or damage it has incurred or suffered as a result of that person’s conduct;  cancel the contract and claim any damages which it has suffered as a result of having to make less favourable arrangements due to such cancellation;  impose a financial penalty more severe than the theoretical financial preference associated with the claim which was made in the tender; and  restrict the contractor, its shareholders and directors from obtaining business from any organ of state for a period not exceeding 10 years.” See attached circular : (Annexure H) 11. CONSTRUCTION The Consultant is to ensure the following (but not limited to) are implemented timeously and in accordance with legislation and required industry specifications, in order to achieve the highest quality for resources available:
  • 7. 7 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 1. The contractor supplies and enforces the required safety measures and requirements (including Health & Safety Plan) 2. The Consultant will ensure that the contractor takes all reasonable measures prescribed by law and/or any other reasonable measures necessary for the prevention of accidents during construction at Senqu Municipality premises or any other areas affected by the construction. 3. The Consultant must ensure that the contractor has adequate insurance cover at all times, and this will include cover for any sub-contractor/SMME used. This shall also cover public liability insurance. Proof thereof must be submitted in terms of the contractor’s tender document. 4. A site diary, with a triplicate carbon book specifically for instructions issued, must be implemented and kept up to date and safely on site at all times. (All instructions must be recorded in the triplicate book – original to consultant, copy to client) The SM will consider the instruction as not ever have been given, if not in writing as specified above, and therefore the Consultant will be liable for any cost that may be incurred if the Contractor implements such further instruction (s). Also refer to “PRICE” S (a) & (b). 5. Rain fall records must be kept. 6. A site equipment register must be kept. 7. A labour register must be kept and contain the following information:- a) Division in local and “imported” labour b) Name of each person c) Gender of each person d) Race of each person e) ID Number of each person f) Copy of the ID of each person g) UIF Payments h) Pay Rate (per hour) of each person i) Days worked per person j) Category of work (Unskilled, Semi-Skilled, Operator, Driver, Skilled, Professional) k) Total payment for local labour l) Total payment for ‘imported” labour m) Number of SMME’s used n) Payment to SMME’s o) Training (Number, type, length, cost and accredited or not) p) Copy of contracts with labour and SMME’s. 8. Labour must be sourced from the ward where the project is taking place and done in conjunction with the Ward Councilor through the CLO. 9. Labour rates paid must be in accordance to the amount stipulated by the Department of Labour, which may vary from time to time. 10. The SM will not be held liable for any costs that may arise (direct & non-direct) due to the project being shut down or delayed due to non-compliance of any construction, environmental, labour or any other relevant legislation. 11. The Consultant must ensure that the contractor’s Site Establishment is done in an acceptable manner, taking the local community and circumstances into consideration. 12. The Consultant will ensure that he / she have a representative on site at all times and that the contractor has a mandated representative on site at all times. 13. The Consultant agrees to allow SM to obtain a third party professional opinion, at any time during or after construction, in order to confirm quality / quantities, or any other part of the Works or documentation related to the Works. 14. The Consultant will at all times ensure the quality and quantities of the Works/ Materials are correct, within specifications and acceptable. Should it later emerge that this is not the case, the
  • 8. 8 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management municipality reserves the right to hold the Consultant fully accountable for the following and any other appropriate action in terms of this agreement:- a) All associated construction costs in correction Works to be done b) All administrative and/or legal costs c) Cost of any other professional opinion in order to evaluate works. d) Should evaluation reports on quality / quantity prove to be acceptable; the SM will pay the cost of such evaluation and if not, the Consultant will be liable for the costs. 15. The Consultant shall continually evaluate the performance of the contractor against established timeframes, milestones, cash flows, quality and performance to expenditure. 16. The Consultant will ensure that monthly technical and site meetings are held and that a Project Steering Committee is formed that includes the Ward Councillor. A seating allowance must be payable by the contractor, of a minimum of R 300 / person /meeting in order to cover travelling costs. This amount may be amended from time to time and the Consultant must request the amount prior to project costing. The seating allowance will not apply to officials of the municipality or any other government department or parastatal. All meetings will be held on site unless otherwise required by the SM. 17. The Consultant will submit all appropriate required reports monthly no later than 2 working days after calendar month end, in soft and hard copy to the PMU manager. 18. The Consultant must inform the PMU Manager and Ward Councillor immediately, in writing, in the event any of the following occurring:- a) Accidents/death on site b) Major change in scope of the Works required c) Any other change/incident that may affect the outcome or cost of the project. d) Any labour related matters that may delay or negatively affect the project. e) Any material supply matters that may delay or negatively affect the project. f) Damage to existing services. 19. The Consultant will issue a Practical Completion Certificate and a Final Completion Certificate at the appropriate stage of the construction contract. Any retention payment will be measured from the date of the Practical Completion Certificate for a period of one calendar year unless specified otherwise in the tender document. 20. The Consultant will ensure the implementation of the latest GCC/JBCC at all times. 21. The Consultant shall ensure return of all relevant contractual documentation to the contractor within a reasonable period of construction contract completion. (Sureties, guarantee’s etc.) 22. The Consultant shall, upon issue of the Final Completion Certificate, within 15 working days, provide the SM with a project “close out” report which will contain the following project information:- a) Back ground b) Objectives c) Budget (Payment certificates – Direct & Indirect – VOs- Contingencies etc.) d) Cash flow e) Milestones f) Weather g) Labour summary (numbers, payments, totals, man days, local, youth, sex etc.) h) Training summary i) Challenges/ targets j) Lessons learnt k) Photographs (before & after-date stamped with coordinates)
  • 9. 9 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management l) Recommendations m) General comments 12. CONSTRUCTION CONTRACT PERIOD & PENALTIES Failure by the Consultant to effect delivery of the construction contract within the specified period, as tendered by the construction contractor (this includes extension of time in accordance with the GCC), shall constitute a breach of contract, which breach shall entitle SM to:- a) Implement penalty costs on a daily basis of 0.0085 % of the Consultants accepted tender value (Before VAT – No VAT charged on penalties). This applies to calendar days. b) If determined as poor performance, in terms of Annexure D, may cancel the contract with the Consultant c) Hold the Consultant liable for all professional costs related to completing the tender in accordance with specifications; and should it be necessary, claim previous construction rectification costs from the Consultant. d) The Consultant will be blacklisted on the National Treasury database; e) Exercise any of its rights in terms of this agreement or relevant legislation. f) The SM will allow the Consultant an opportunity to mitigate their circumstances, in writing, before a final decision is made. 13. INFORMATION 1. The Consultant understands that the SM holds full copyright and ownership on all project related documentation, inclusive of designs, plans etc. 2. All information is to be considered as confidential. The Consultant may retain such information but may only make use thereof by express written permission of the SM. The information may be shared with other parties only with the express written permission of the SM. 14. LEGAL COMPLIANCE The Consultant hereby indemnifies and agrees to defend and hold SM harmless from any liability arising or alleged to arise out of any failure of construction works / services or to conform to any laws, orders, regulations, requirements or standards. 15. PERFORMANCE KPI’s are weighted and scored to a maximum of 5 points. Performance will be rated monthly, with or without the Consultant. The dates will be pre-arranged. All scores will be done in terms of Annexure D and scores will be converted to percentage to determine a total percentage based between compliance and satisfaction. Score categories vs performance is as follows:- PERFORMANCE RATING 0% 80% Unacceptable 81% 90% Poor 91% 92% Good
  • 10. 10 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 93% 96% Very Good 97% 100% Excellent In terms of this agreement, the SM reserves the right to terminate the Consultants contract for poor performance with regard to the above, should it become evident that the consultant cannot achieve at least “good” status before the half way point of the construction contract. In the event of termination due to non-performance of the service provider, no outstanding payment shall be considered until such time the construction contract has reached Final Completion Certificate stage and only then if there is funding available. Should there be any financial loss for the SM due to contract termination for poor performance; the SM reserves the right to recover such cost from the Consultant, with regard to professional and related costs, as well as any cost on construction, that is due to the poor performance of the Consultant on the project. 16. AVAILABILITY It is a condition of appointment that at any stage during the period of responsibility, the Consultant will make him/herself available, all reasonable hours, for inspection of the works or meetings, at any location deemed reasonable by the SM, at request of an authorized representative of SM or agent acting on behalf of SM. A minimum notice period of 48 hours will be allowed with the exception of what the SM considers as an emergency. 17. TRANSFER OF RISK The SM will only accept risk on the project upon receipt of the Practical Completion Certificate, final Bill of Quantities, final “as build” and letter of financial confirmation. [Refer ”DOCUMENTATION”]. Until the Practical Completion Certificate is received, all insurance and other risk remains with the Consultant who must ensure such in the Contractors tender document. 18. CESSION AGREEMENTS No cession agreements will be entertained, by the Consultant or the contractor, without the prior written consent of the municipality and these types of arrangements must be avoided if possible. 19. DESIGN & CONSTRUCT If the Consultant is appointed on a Turnkey / Principle Agent (Design & Construct) basis, all the requirements of this SLA will still apply to the Consultant but will also include the latest GCC/JBCC and other construction matters as referred to in this agreement. The Consultant will then be considered as a Contractor. Please see “PAYMENT” The SM still retains its rights within any other law aside from and within this agreement, in the event of a turnkey appointment. 20. PROFESSIONAL JOINT VENTURES The Consultant is allowed to engage into a joint venture on the following conditions:-  The JV partner (s) must also be a competent person in the same or other required discipline in order to meet the completion of the contract works.  No payment will be made unless the JV is VAT registered.  The JV must have tendered in accordance with SM procurement regulations.  The percentage value split must be indicated in the JV agreement. This percentage will determine the split in responsibility/accountability between the JV partners in terms of this SLA and any other recourse in terms of law.
  • 11. 11 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management  All JV partners must sign this SLA  There must be a bank account in the name of the JV 21. PAYMENT FOR SERVICES SM reserves the right to only pay for services, after verification by the PMU Manager, for both the Consultant and the Contractor, and within 30 days of date of invoice. Where possible, this will be shortened, in order to assist with cash flow. The SM reserves the right to withhold/delay payment from the Consultant and the Contractor, for the next Payment Certificate submitted, in the event that the labour and/or SMME’s on the project are not paid by month end by the Contractor on the previous certificate. The delayed payment will be determined by the number of days late payment to the labour and/or SMME’s after the stipulated month end. ie If only paid 6 days after month end, the Contractor payment for the next certificate will be intentionally delayed for 30 days plus 6 days etc.(30 + 6 = 36 days) Proof of timeous payment must be submitted to each Site Meeting failing which it will be considered that labour and SMME’s have not been paid. This will include sub- contractors. This must be included in the Construction tender document for the contractor. The SM guarantees payment to the Consultant for verified services in accordance to the above. The SM reserves the right not to pay the Consultant and the Contractor if Labour Reports (or any other requested report) are not received timeously, without penalty to the municipality. This must be included into the Construction tender document for the contractor. The SM reserves the right not to process payment in the event of any possible conflict with performance of the Consultant until such time that the matter is resolved or the SM has exercised its tights in terms of this agreement or applicable legislation. The SM will hold the Consultant liable for all costs that may occur due to inappropriate / mismatched / incomplete Bill of Quantities, design & specifications, project management, quality control and safety and reserves the right to withhold payment to the Consultant. SM reserves the right, and the Consultant agrees as such, to inspect, test or analyze any goods/services, through an appointed independent, appropriately qualified third party, and reject such that do not, in SM’s sole discretion, comply with the contractual requirements, specifications and/or quality. In the event of the Works being of correct specification and quality, the SM will cover the cost of such third party. The converse shall also apply. Any goods/services that Senqu Municipality rejects for non-compliance with regard to the above shall be held at the cost and risk of the Consultant, who shall, when called upon, comply with contractual requirements at own cost. Payments as the Consultant will be as follows:  Design: 20%  Procurement completion up to report stage: 10%  Project Management: 60% (linked directly to Contractors performance)  Practical Completion/Final documentation/ Structural Certificate (Where appropriate): 5%  Final Completion Certificate: 5% Payment on Turnkey (Design & Construct) will take place as follows-(Unless approved otherwise, in writing, by the SM):-  Design & documentation up to municipal approval (As per this agreement as Consultant): 10%  Site establishment: 5%  Construction (As per progress / BoQ): 75%  Practical Completion: 5% (1st retention release)  Final Completion: 5% (2nd retention release)
  • 12. 12 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management 22. CONTRACTOR PAYMENTS The Consultant shall ensure that contractor certificates for payment will be submitted as follows:-  Certificate 1: Site establishment and percentage of P & G’s.  Certificate 2 onwards: Materials on site and work verified done to date  P & G’s are to be equally distributed over contract period on a percentage basis, including Certificate 1, but excluding the last two retention certificates.  Second final certificate: release of first retention (5%) AFTER receipt of the Practical Completion Certificate.  Final certificate: release of final retention (5%) AFTER receipt of the Final Completion Certificate.  It must be noted that retention is to be deducted on an ongoing basis, to the value of 10% of the TOTAL project value, including the last construction works certificate and the Site Establishment certificate and excluding the separate retention release certificates.  All the above must be done in a format approved by the municipality and must include progress reports in the format approved by the municipality. [Annexure A & B & C] Should any claims verified by the Consultant, be discovered before or after payment to the contractor, be untrue, the SM reserves the right to hold the Consultant liable in all implications of such a matter and the right to dismiss the consultant with immediate effect if discovered to be deliberate and to recover any costs involved directly from the Consultant. 23. FAILURE TO COMPLY AND DELAYED EXECUTION Should the Consultant fail to comply with any of the conditions of this agreement, SM shall be entitled, without prejudice to any of its other rights, to cancel the appointment of the Consultant. Upon any delay beyond the contract period, SM may, without prejudice to any other right and without canceling the Consultants appointment, be entitled to arrange for the execution of the service(s) not rendered or not rendered in conformity with this agreement or to cancel the appointment and without prejudice to its other rights, be entitled to claim damages from the Consultant. 24. BREACH If either party breaches these terms and conditions, as per this agreement, and fails to remedy such breach within 30 calendar days of written notice from any other party calling for the breach to be remedied, then the non-breaching party shall be entitled, without prejudice to any other rights that it may have in law, whether under this agreement or otherwise, to cancel the appointment without notice or to claim immediate specific performance of all the defaulting party's obligations, whether or not due for performance, in either event without prejudice to the aggrieved party's right to claim damages. 25. DEATH, SEQUESTRATION, LIQUIDATION OR JUDICIAL MANAGEMENT In the event of the death of a Consultant or the provisional or final sequestration of the Consultant or of its cession or transfer of the appointment without the approval of SM or of the surrender of its business or it reaching a compromise with its creditors or of the provisional or final liquidation of a Consultants company or the placing of its affairs under judicial management, SM may, without prejudice to any other rights it may have at law, exercise any of the following options: - Cancel the appointment and accept any offer subsequently received to complete the services. In such a case the Consultant shall not be relieved from liability for any claim which has arisen or may arise against the Consultant in respect of goods/services not delivered or work not carried out by the Consultant under the appointment.
  • 13. 13 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management - allow the executor, trustee, liquidator or judicial manager, as the case may be, for and on behalf of and at the cost and expense of the business of the Consultant to carry on with and complete the contract; or - for and on behalf of and at the cost and expense of the business of the Consultant, itself carry on with and complete the contract 26. DISPUTE RESOLUTION Any unresolved dispute between the parties arising out or in connection with this SLA, including its existence, application, breach, interpretation, validity, termination or cancellation, shall be referred to the Senior Manager: Supply Chain Management of Senqu Municipality, who will have seven (7) working days to resolve the dispute, and if not resolved, then the Municipal Manager, who will undertake to meet within seven (7) working days after being requested by either party, in order to resolve the dispute. Only thereafter, if nor resolved, shall the matter be submitted to and decided by arbitration in terms of the Arbitration Act, 1965, of the Republic of South Africa, subject to the following provisions: In the event of either party having a claim against the other party for a liquidated amount or an amount which arises from a liquid document, then the party having such claim shall be entitled to institute action therefore in a court of law rather than in terms of the above, notwithstanding the fact that the other party may dispute such claim. 27. GOVERNING LAW Is the law of South Africa, as amended time to time. 28. NOTICES AND CONTACT Each party chooses as its address for all purposes under this SLA (“chosen address”), whether for serving any court process or documents, giving any notice, or making any other communications of whatsoever nature and for any other purpose arising from this SLA (“notice & contact”), as its domicilium citandi et executandi. A domicilium citandi et executandi shall be chosen in the Republic of South Africa. This will be inserted into this agreement below. Any notice required or permitted under this SLA shall be valid and effective only if in writing, in terms of “CORRESPONDENCE’ above. Any party may, by notice to the other party, change its chosen address to another physical address in the Republic of South Africa and such change shall take effect on the seventh (7) calendar day after the date of receipt by the party who last receives the notice. Any notice to a party contained in a correctly addressed envelope and delivered by hand to a responsible person during ordinary business hours at its chosen address, shall also be deemed acceptable. 29. LIMITATION OF LIABILITY Unless otherwise provided for in this agreement or in any further written agreement, neither party shall be liable to the other for any indirect, consequential, special, incidental or punitive damages, including without limitation, loss of use or lost business, revenue, profits, anticipated savings, reputation or goodwill arising in connection with the Consultants appointment , services, related products, documentation and/ or the intended use thereof under any theory, contract, warranty, strict liability or negligence even if the party has been advised, knew or should have known of the possibility of such damages. Nothing in this agreement shall restrict either party’s liability for: (a) Fraud; or
  • 14. 14 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management (b) Death or personal injury caused by its negligence or intentional or willful act; (c) Damage to real or tangible personal property caused by its negligence or intentional or willful misconduct; or (d) Any breach of obligations under this agreement in respect of confidentiality and intellectual property; or (e) Any other liability that cannot be excluded by law. 30. CONFIDENTIALITY The parties agree that the terms of this SLA that all confidential and proprietary information of the parties communicated to them in connection with this SLA/appointment shall be received in strict confidence and be used only for the purposes of this SLA/appointment. Each party shall use the same means as it uses to protect its own confidential information, but in no event less than reasonable means, to prevent the disclosure and to protect the confidentiality of such information. No such information shall be disclosed by the recipient party, its agents, representatives or employees without the prior written consent of the other party. These provisions do not apply to information which is: - publicly known or becomes publicly known through no un-authorised act of the recipient party; - rightfully received by the recipient party from an outside party; - independently developed by the recipient party without use of the other party's information; - disclosed by the other party to an outside party without similar restrictions; - required to be disclosed pursuant to a requirement of a governmental agency or any applicable law,; or - Publicly disclosed with the other party's written consent. _____________________________________________________________________________________ We, the undersigned, as mandated representatives, understand and agree to the terms of this Service Level Agreement. FOR SENQU MUNICIPALITY NAME: SIGNATURE: DATE: Cell: email: CAPACITY FOR CONSULTANT NAME: SIGNATURE DATE CAPACITY:
  • 15. 15 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management SENQU MUNICIPALITY ADDRESS: 19 MURRAY STREET LADY GREY 9755 POSTAL ADDRESS: PO BOX 18 LADY GREY 9755 Fax: 051-6030445 Tel: 051- 6031300 COMPANY NAME ______________________________________________________________________ ADDRESS: ___________________________________________________________________________ POSTAL ADDRESS:____________________________________________________________________ Cell:_______________________ Tel: ________________________email:_________________________ WITNESS # 1: NAME: SIGNATURE: WITNESS # 2: NAME: SIGNATURE:
  • 16. 16 | P a g e Performance Service Level Agreement – Professional Services – Technical Services: Project Management