I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model

4,400 views

Published on

Pipe spool fabrication is major component of construction operations on large industrial projects. The nature of spooling is relatively short term involving complex construction process and riddled with uncertainty due to the intrinsic unique nature of its outputs and the numerous factors affecting its activities.

With this in mind, it is important for all stakeholders to have a good grasp of the performance of pipe fabrication shops and their ability to meet the site pipe installation schedules.

Published in: Technology, Business
0 Comments
12 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
4,400
On SlideShare
0
From Embeds
0
Number of Embeds
185
Actions
Shares
0
Downloads
0
Comments
0
Likes
12
Embeds 0
No embeds

No notes for slide
  • The ability of computer based modeling and simulation to model resource and activity interactions, queuing, and uncertainties renders it a good fit for modeling the pipe spool fabrication process.
  • extended visits to multiple mega industrial projects were conducted to observe and document pipe spool fabrication activitiesBenchmarking for every activity was conducted via numerous observations of the activity being performed on different spools of varying characteristics. Both crew composition information and productivity figures were collected. In this paper we will not deal with the analysis of the observed productivity data; this matter will be dealt with at a different time. Instead, for this paper, we will assume the resulting productivity norms deduced from the observations as our activity productivity norms for the tasks. The simulator was developed as a discrete event simulation model with spools as the main entity. For the welding tasks, welds are the entities - where spools are split into their constituent welds - in order to process welds individually and collect their artificial history.
  • Spool data required: spool ID, current spool status, line class, material type, paint code, surface area, spool specific priority information Joint data required: weld type, inch-dia, post weld heat treatment (PWHT) requirement and non-destructive testing (NDT) requirements
  • For the purpose of this paper, we will only cover the main activities of the pipe spool fabrication process, and not include logistical activities such as crane and trailer operations.
  • I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model

    1. 1. RAMZI LABBAN DR. SIMAAN M. ABOURIZK MANAGER, COMPUTER MODELING & SIMULATION CCC PHD CANDIDATE UNIVERSITY OF ALBERTA PROFESSOR UNIVERSITY OF ALBERTA MR. ZUHAIR HADDAD DR. AMR EL-SERSY VICE PRESIDENT, CORPORATE AFFAIRS & CIO CCC GROUP MANAGER, LEARNING & INNOVATION CCC
    2. 2. Agenda • Introduction • Pipe Spool Fabrication Model – – – – – • • • • • Background Simulator Design and Development Product Definitions Process Definitions (Activity Flow, Resources) Model Structure (Parameters Interface, DES Model, Outputs) Potential Benefits Future Work Conclusions Acknowledgements Q&A
    3. 3. Introduction • Pipe spool fabrication – A major component of construction operations on large industrial projects – Relatively short term, complex construction process – Riddled with uncertainty due to the intrinsic unique nature of its outputs and the numerous factors affecting its activities • Important for all stakeholders to have a good grasp of the performance of pipe fabrication shops and their ability to meet the site pipe installation schedules
    4. 4. Pipe Spool Fabrication Model Background • Activities in pipe fabrication shops include: – Cut, bevel, fit-up, welding, QC inspection, post weld heat treatment, non-destructive testing, painting • These activities are repeatedly performed by a specific type of crew on pipe spools for a certain duration
    5. 5. Pipe Spool Fabrication Model Background • Forecasting pipe spool fabrication activity completion and optimizing resource allocation and utilization are complicated by two main factors: – very large number of spools – diverse characteristics and resource requirements for each spool • A complex task well suited to computer modeling and simulation
    6. 6. Pipe Spool Fabrication Model Simulator Design and Development • Abstraction of the real world situation into a simulation model representing the operations of a pipe spool fabrication shop: – Product definitions • Spool characteristics • Joint characteristics – Process definitions • Activities and their flow • Resources
    7. 7. Pipe Spool Fabrication Model Product Definitions • Spool and joint characteristics required for simulating the fabrication activities were specified Spool ID Stauts A140-A141-B92SL-15139D-S101 3 Weld # 2 4 5 A140-A141-B92SL-15139D-S102 3 A140-A141-B92SL-15139D-S103 3 Material CS Weld Type SB SB SB CS CS Paint Code Surface Area Priority 6D 0.03 180 Weld Inch-Dia PWHT Req'd NDT Req'd 0.75 0 0 0.75 0 0 0.75 0 0 6D 0.01 180 6D 0.15 180 Two-level hierarchy for spools and their relevant joints
    8. 8. Pipe Spool Fabrication Model Process Definitions • Major pipe spool fabrication activities to be simulated and their flow were identified:  Cut  Bevel  Fit-up (& tack welding)  Welding (auto and manual)  QC inspection  Post weld heat treatment (PWHT)  Non-destructive testing (NDT)  Painting • For each activity, the type of resource (crew) required and its relevant productivity were also identified
    9. 9. Pipe Spool Fabrication Model Activity Flow
    10. 10. Pipe Spool Fabrication Model Resources • Each pipe fabrication activity is associated with a resource type • Each resource type is typically a crew composed of a group of workers required to perform a specific task Worker Worker Worker Worker Worker Worker Worker Worker Worker Crew Type Type 1 Type 2 Type 3 Type 4 Type 5 Type 6 Type 7 Type 8 Type 9 Cut 1 2 1 2 Bevel 1 Fit-up 2 2 1 4 Weld Size 1 1 1 Weld Size 2 2 2 PWHT 1 2 Painting 1 3 4 Typical crew compositions on a large industrial construction project
    11. 11. Pipe Spool Fabrication Model Resources • Workers available over the duration of the project make up the required crews (resources) for the fabrication activities Worker Type 1 2 3 5 6 7 1 21 85 80 37 90 92 2 23 90 82 38 95 99 3 25 95 85 40 100 112 Month 4 5 25 25 95 100 86 104 41 42 100 110 129 135 6 25 100 104 42 110 135 7 25 100 104 42 110 135 Typical worker availability over time on an industrial project 8 25 100 104 42 110 135
    12. 12. Pipe Spool Fabrication Model Model Structure Spool Engineering Data Pipe Fabrication Schedule Spool Priority Lists Crew (Resource) Database Parameters Input Interface Spool Progress Data To-Date DES Model Simulation Outputs
    13. 13. Pipe Spool Fabrication Model Parameters Interface
    14. 14. Pipe Spool Fabrication Model DES Model Pipe Fabrication Activity Flow DES Model
    15. 15. Pipe Spool Fabrication Model Outputs • The simulator produces a comprehensive set of data comprised of the artificial history of the simulated pipe fabrication operations • The result set contains a record of the activities performed on the corresponding entities (spools or welds) utilizing the required resources Scenario # 1304152 1304152 1304152 1304152 Spool ID Weld No A140-A141-B92SL-15139D-S101 2 A140-A141-B92SL-15139D-S101 4 A140-A141-B92SL-15139D-S101 5 A140-A141-B92SL-15139D-S101 Activity Start Date and Time Welding 03/04/2013 11:01 Welding 03/04/2013 11:01 Welding 03/03/2013 15:01 Painting 3/14/13 8:00 End Date and Time Resources 03/04/2013 11:23 1 03/04/2013 11:23 1 03/03/2013 15:23 1 3/16/13 10:00 1 • For each entity/activity/resource occurrence, the data contains a start date and time, an end date and time, and a number of resources utilized for the duration
    16. 16. Potential Benefits • The model provides stakeholders and end users with a tool to proactively perform low level resource planning on pipe fabrication activities on large industrial projects • The model can be run during the different phases of a project: – Ahead of the project in predictive mode – During execution to aid in optimization and forecasting – Retrospectively for change impact assessment and/or lessons-learned analysis
    17. 17. Future Work • The pipe spool fabrication model described in this paper is a first step at aiding in the management of pipe spool fabrication operations • Further development and enhancements to this model include: – A material constraint module – A pipe installation simulation model covering pipe spool construction activities until spools are installed in place on site and given final release
    18. 18. Conclusions • This paper presented a special purpose discrete event simulation model for managing pipe spool fabrication operations in pipe fabrication shops on industrial projects • The simulation model helps stakeholders manage their activities and perform low level resource planning for all shop pipe spool fabrication activities • The main benefits of the model are – predictive analysis of fabrication resource requirements – managing operations and forecasting resource and time requirements during project execution – Retrospective analysis
    19. 19. Acknowledgements • The pipe fabrication model described in this paper was developed and implemented at Consolidated Contractors Group (CCC) to aid in estimating, planning and managing pipe fabrication operations on large industrial construction projects
    20. 20. Thank you! Any questions?

    ×