SlideShare a Scribd company logo
1 of 19
WORK PLAN-P2
helpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.uk
WORKPLAN
 Construction Planning is a fundamental
and challenging activity in the
management and execution of
construction projects.
 It involves:
1. Managerial factors
2. Technological factors
3. Social factors
WORKPLAN
Managerial
Factors
Technologica
l
Factors
Social
Factors
WORKPLAN-PART 2
 In addition to the problem of estimating the
expected duration of an activity.
 Some scheduling procedures explicitly
consider the uncertainty in activity duration
estimates.
 This is achieved by using the probabilistic
distribution of activity durations.
 That is, the duration of a particular activity
is assumed to be a random variable that is
distributed in a particular fashion.
WORKPLAN
 For example, an activity duration might be
assumed to be distributed as:
 a normal
 or a beta distributed random variable as
illustrated in Figure-below.
WORKPLAN-PART 2
WORKPLAN
 This figure shows the probability or chance
of experiencing a particular activity
duration based on a probabilistic
distribution.
 The beta distribution is often used to
characterize activity durations.
 Since it can have an absolute minimum
and an absolute maximum of possible
duration times.
WORKPLAN
 The normal distribution is a good
approximation to the beta distribution in the
centre of the distribution.
 It is easy to work with.
 Therefore, it is often used as an
approximation.
WORKPLAN
 If a standard random variable is used
to characterize the distribution of
activity durations, then only a few
parameters are required to calculate
the probability of any particular
duration.
WORKPLAN
 Still, the estimation problem is increased
considerably since more than one
parameter is required to characterize most
of the probabilistic distribution used to
represent activity durations.
 For the beta distribution, three or four
parameters are required depending on its
generality, whereas the normal distribution
requires two parameters.
WORKPLAN
 As an example, the normal distribution is
characterized by two parameters.
 representing the average duration,
 and the standard deviation of the duration,
respectively,
 Alternatively, the variance of the distribution
could be used to describe or characterize the
variability of duration times.
 The variance is the value of the standard
deviation multiplied by itself.
WORKPLAN
 From historical data, these two
parameters can be estimated as:
Equation (2) and (3)
WORKPLAN
 where we assume that n different
observations xk of the random variable x are
available.
 This estimation process might be applied to
activity durations directly.
 so that xk would be a record of an activity
duration Dij on a past project).
WORKPLAN
 Or to the estimation of the distribution of
productivities (so that xk would be a record
of the productivity in an activity Pi on a past
project).
 Which, in turn, is used to estimate durations
using Equation(4).
WORKPLAN
 If more accuracy is desired, the estimation
equations for mean and standard deviation,
Equations (2) and (3) would be used to
estimate the mean and standard deviation of
the reciprocal of productivity to avoid non-
linear effects.
 Using estimates of productivities, the
standard deviation of activity duration would
be calculated as:
WORKPLAN
 where is the estimated standard deviation
of the reciprocal of productivity that is
calculated from Equation (3) by substituting
1/P for x.
 Equation (4)
WORKPLAN
 Estimating Resource Requirements for Work
Activities
WORKPLAN
 where Rkij are the resources of type k
required by activity ij,
 Dij is the duration of activity ij,
 Nij is the number of standard crews
allocated to activity ij,
 and Ukij is the amount of resource type k
used per standard crew.
WORKPLAN
 For example, if an activity required eight
hours with two crews assigned
 and each crew required three workers,
the effort would be R = 8*2*3 = 48 labour-
hours.

More Related Content

What's hot

TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectWanBK Leo
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartVinay Prajapati
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chartdanishrafiq
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Chandra Shekar Immani
 
Applications of pert
Applications of pertApplications of pert
Applications of pertnitigga92
 
pert chart guide for dummies
pert chart guide for dummiespert chart guide for dummies
pert chart guide for dummiesRabin Awal
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 
Project management teaching
Project management   teachingProject management   teaching
Project management teachingCHIRANJAN SAHA
 

What's hot (20)

PERT
PERTPERT
PERT
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
 
P E R T
P E R TP E R T
P E R T
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Pert2
Pert2Pert2
Pert2
 
Gantt pert
Gantt pertGantt pert
Gantt pert
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert+cpm
Pert+cpmPert+cpm
Pert+cpm
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
Applications of pert
Applications of pertApplications of pert
Applications of pert
 
pert chart guide for dummies
pert chart guide for dummiespert chart guide for dummies
pert chart guide for dummies
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
PERT
PERTPERT
PERT
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
 

Similar to 140 workplan

Project management chapter 11
Project management chapter 11Project management chapter 11
Project management chapter 11VancityInstitute
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1M.D.Giri Reddy
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
A Fresh Take on Project Forensics
A Fresh Take on Project ForensicsA Fresh Take on Project Forensics
A Fresh Take on Project ForensicsAcumen
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...IAEME Publication
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET Journal
 
The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?
The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?
The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?Gan Chun Chet
 
Sub project management
Sub   project managementSub   project management
Sub project managementsmumbahelp
 
IRJET-Load Forecasting using Fuzzy Logic
IRJET-Load Forecasting using Fuzzy LogicIRJET-Load Forecasting using Fuzzy Logic
IRJET-Load Forecasting using Fuzzy LogicIRJET Journal
 

Similar to 140 workplan (20)

PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Project management chapter 11
Project management chapter 11Project management chapter 11
Project management chapter 11
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1Pearson1e ch14 appendix_14_1
Pearson1e ch14 appendix_14_1
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
A Fresh Take on Project Forensics
A Fresh Take on Project ForensicsA Fresh Take on Project Forensics
A Fresh Take on Project Forensics
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
PMBOK7-201-300.pdf
PMBOK7-201-300.pdfPMBOK7-201-300.pdf
PMBOK7-201-300.pdf
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
 
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
 
SE chapters 24-25
SE chapters 24-25SE chapters 24-25
SE chapters 24-25
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Solow1957
Solow1957Solow1957
Solow1957
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
Balco ps user manual
Balco ps user manualBalco ps user manual
Balco ps user manual
 
Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan
 
The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?
The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?
The Prediction Of Time Trending Techniques. Is It A Reasonable Estimate?
 
Sub project management
Sub   project managementSub   project management
Sub project management
 
IRJET-Load Forecasting using Fuzzy Logic
IRJET-Load Forecasting using Fuzzy LogicIRJET-Load Forecasting using Fuzzy Logic
IRJET-Load Forecasting using Fuzzy Logic
 

More from Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvementDr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-writeDr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sectorDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projectsDr Fereidoun Dejahang
 

More from Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 

Recently uploaded

AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 

Recently uploaded (20)

AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 

140 workplan

  • 2. WORKPLAN  Construction Planning is a fundamental and challenging activity in the management and execution of construction projects.  It involves: 1. Managerial factors 2. Technological factors 3. Social factors
  • 4. WORKPLAN-PART 2  In addition to the problem of estimating the expected duration of an activity.  Some scheduling procedures explicitly consider the uncertainty in activity duration estimates.  This is achieved by using the probabilistic distribution of activity durations.  That is, the duration of a particular activity is assumed to be a random variable that is distributed in a particular fashion.
  • 5. WORKPLAN  For example, an activity duration might be assumed to be distributed as:  a normal  or a beta distributed random variable as illustrated in Figure-below.
  • 7. WORKPLAN  This figure shows the probability or chance of experiencing a particular activity duration based on a probabilistic distribution.  The beta distribution is often used to characterize activity durations.  Since it can have an absolute minimum and an absolute maximum of possible duration times.
  • 8. WORKPLAN  The normal distribution is a good approximation to the beta distribution in the centre of the distribution.  It is easy to work with.  Therefore, it is often used as an approximation.
  • 9. WORKPLAN  If a standard random variable is used to characterize the distribution of activity durations, then only a few parameters are required to calculate the probability of any particular duration.
  • 10. WORKPLAN  Still, the estimation problem is increased considerably since more than one parameter is required to characterize most of the probabilistic distribution used to represent activity durations.  For the beta distribution, three or four parameters are required depending on its generality, whereas the normal distribution requires two parameters.
  • 11. WORKPLAN  As an example, the normal distribution is characterized by two parameters.  representing the average duration,  and the standard deviation of the duration, respectively,  Alternatively, the variance of the distribution could be used to describe or characterize the variability of duration times.  The variance is the value of the standard deviation multiplied by itself.
  • 12. WORKPLAN  From historical data, these two parameters can be estimated as: Equation (2) and (3)
  • 13. WORKPLAN  where we assume that n different observations xk of the random variable x are available.  This estimation process might be applied to activity durations directly.  so that xk would be a record of an activity duration Dij on a past project).
  • 14. WORKPLAN  Or to the estimation of the distribution of productivities (so that xk would be a record of the productivity in an activity Pi on a past project).  Which, in turn, is used to estimate durations using Equation(4).
  • 15. WORKPLAN  If more accuracy is desired, the estimation equations for mean and standard deviation, Equations (2) and (3) would be used to estimate the mean and standard deviation of the reciprocal of productivity to avoid non- linear effects.  Using estimates of productivities, the standard deviation of activity duration would be calculated as:
  • 16. WORKPLAN  where is the estimated standard deviation of the reciprocal of productivity that is calculated from Equation (3) by substituting 1/P for x.  Equation (4)
  • 17. WORKPLAN  Estimating Resource Requirements for Work Activities
  • 18. WORKPLAN  where Rkij are the resources of type k required by activity ij,  Dij is the duration of activity ij,  Nij is the number of standard crews allocated to activity ij,  and Ukij is the amount of resource type k used per standard crew.
  • 19. WORKPLAN  For example, if an activity required eight hours with two crews assigned  and each crew required three workers, the effort would be R = 8*2*3 = 48 labour- hours.