Applications of pert
1. APPLICATION OF
PERT IN PROJECT
MANAGEMENT
Presented by-
Zulfequar Ali (26)
Harshita Ankit (27)
Amit Soren (28)
Shruti Sagar (29)
Nidhi Prawina Tigga
(30)
1
2
3
4
5 6
142 weeks
2. Introduction to PERT
“Project Evaluation and review Technique"
Schedules method originally to plan of
manufacturing project.
Employs a network interrelated activities.
Coordinates optimum cost and time criteri
a.
Emphasizes the relationship between time
each activity takes and cost associated
for the completion of the entire project.
3. Applications in Project Management
PERT is used to plan, schedule and
control a wide variety of project:
• R & D of new products and processes
• Construction of buildings and highways
• Maintenance of large and complex
equipment
• Design and installation of new systems
4. Example: Riverwalk Associates
Riverwalk Associates is in the business of building
elaborate parade floats. Its crew has a new float to
build and want to use PERT to help them manage
the project .
The table on the next slide shows the activities that
comprise the project. Each activity’s estimated
completion time (in weeks) and immediate
predecessors are listed as well.
The project manager wants to know the probability
to complete the project in 26 weeks, the possible
activities and find which activities is the critical path.
6. Activity Expected Time and
Variances
ACTIVITY (i)
te = (tO + 4tm + tp)/6
EXPECTED TIME (te)
s2
i = ((tp-tO)/6)2
VARIANCE
(week2)
A 6 4/9
B 4 4/9
C 3 0
D 5 1/9
E 1 1/36
F 4 1/9
G 2 4/9
H 6 1/9
I 5 1
J 3 1/9
8. Contin.
We got the critical path A-C-F-I-K = 23 weeks
= tp – to2 = 1.41
6
Calculating the probability to complete the project
within the stipulated time(26 weeks)-
Z = (TA - TE)/ = (26-23)/1.41= 2.12approx.
In accordance to the 50% table,
Table value= .4830
= .4830+.5 =.9830= 98.30%
Therefore the probability for completing the project
within 26 weeks is 98.30%.