SlideShare a Scribd company logo
1 of 14
Download to read offline
Transportation Problems
Dr. Deepa Chauhan
Transportation Problems
Initial Basic Feasible Solutions
By
Dr. Deepa Chauhan
Associate Professor,
Applied Science & Humanities Department,
Axis Institute of Technology, Kanpur
Transportation Problems
Dr. Deepa Chauhan
Methods of Finding an Initial Basic Feasible Solution
There are mainly three methods to find initial basic feasible solution to a transportation problem
a) North West Corner Method (NWCM)
b) Least Cost Method (LCM) or Method of Matrix Minima
c) Vogel’s Approximation Method (VAM)
Solution by transportation method involves making a transportation model in the form of a matrix,
finding an initial basic feasible solution, performing optimality test and moving towards an optimal
solution. Initially, Initial Basic Feasible Solution (IBFS) is obtained then the result is used
to calculate the optimal solution. The popular methods to find IBFS of transportation problem are
North West Corner Method (NWCM), Least Cost Method (LCM), and Vogel's
Approximation Method (VAM).
The Vogel approximation (Unit penalty) method is an iterative procedure for computing a basic
feasible solution of a transportation problem. This method is preferred over the two methods
discussed in the previous sections, because the initial basic feasible solution obtained by this
method is either optimal or very close to the optimal solution.
Transportation Problems
Dr. Deepa Chauhan
North West Corner Method (NWCM)
Example 1: Find the initial feasible solution by North West Corner Method
Warehouse→
Factory↓
W1 W2 W3 W4 Factory
Capacity
F1
F2
F3
19
70
40
30
30
8
50
40
70
10
60
20
7
9
18
Warehouse
Requirement
5 8 7 14 Total=34
Solution: The above problem is a balanced problem because factory capacity is equal to the
warehouse requirement. We prepare 3X4 table with 3 factories and 4 warehouses.
Start giving allocations from North West Corner, shown as below:
North-West Corner
Available↓
5 (19) 2 (30) 7
6 (30) 3 (40) 9
4 (70) 14 (20) 18
Requirement→ 5 8 7 14
Given solution is initial basic feasible solution as m+n-1=No of allocation=6
By multiplying each individual allocation by its corresponding unit cost and adding, we get the
Total Transportation Cost=5X19+2X30+6X30+3X40+4X70+14X20
=₹ 1015
Transportation Problems
Dr. Deepa Chauhan
Example 2: Find the initial feasible solution by North West Corner Method
W1 W2 W3 W4 Supply
F1
F2
F3
F4
48
45
50
52
60
55
65
64
56
53
60
55
58
60
62
61
140
260
360
220
Demand 200 320 250 210
Solution: Since the total demand is equal to the total supply (980), it is a balanced transportation
problem. Now complete allocation is shown as below:
W1 W2 W3 W4 Supply
F1 48 (140) 60 56 58 140
F2 45 (60) 55 (200) 53 60 260
F3 50 65 (120) 60 (240) 62 360
F4 52 64 55 (10) 61 (210) 220
Demand 200 320 250 210
Given solution is initial basic feasible solution as m+n-1=No of allocation=7
Total transportation cost=140X48+60X45+200X55+120X65+240X60+10X55+210X61
=₹ 55,980
Transportation Problems
Dr. Deepa Chauhan
Least Cost Method (LCM)
Example 1: Find the initial feasible solution by Least Cost Method
Warehouse→
Factory↓
W1 W2 W3 W4 Supply
F1
F2
F3
19
70
40
30
30
8
50
40
70
10
60
20
7
9
18
Demand 5 8 7 14 Total=34
Solution: The above problem is a balanced problem because factory capacity is equal to the
warehouse requirement. Allocations are started with least cost cell, as follows
Least Cost
Warehouse→
Factory↓
W1 W2 W3 W4 Supply
F1 19 30 50 10 (7) 7
F2 70 (2) 30 40 (7) 60 9
F3 40 (3) 8 (8) 70 20 (7) 18
Demand 5 8 7 14 Total=34
Given solution is initial basic feasible solution as m+n-1 (3+4-1=6) =No of allocation=6
Total Transportation Cost= 2x70+40x3+8x8+40x7+10x7+20x7
=₹ 814
Transportation Problems
Dr. Deepa Chauhan
Example 2: Using Least-cost method to solve initial solution of the following problem:
Destination
Source D1 D2 D3 Capacity
S1 10 13 6 10
S2 16 7 13 12
S3 8 22 2 8
Demand 6 11 13 30
Solution: The above problem is a balanced problem because demand is equal to supply. By least
cost method, allocations are as follows
Destination
Source D1 D2 D3 Capacity
S1 10 (5) 13 6 (5) 10
S2 16 (1) 7 (11) 13 12
S3 8 22 2 (8) 8
Demand 6 11 13 30
Given solution is initial basic feasible solution as m+n-1=No of allocation=5
Total Transportation Cost by LCM= 10x5+6x5+16x1+7x11+2x8= ₹ 189
Example 3: Find the initial feasible solution by Least Cost Method
Origin
Destination Supply
2 7 4 5
3 3 1 8
5 4 7 7
1 6 2 14
Demand 7 9 18
Transportation Problems
Dr. Deepa Chauhan
Solution:
Origin
Destination Supply
2 7 4 5
3 3 1 8
5 4 7 7
1 6 2 14
Demand 7 9 18 Total=34
The above problem is a balanced problem because demand is equal to supply. By least cost method,
allocations are as follows
Origin
Destination Supply
2 7 (2) 4 (3) 5
3 3 1 (8) 8
5 4 (7) 7 7
1 (7) 6 2 (7) 14
Demand 7 9 18 Total=34
Given solution is initial basic feasible solution as m+n-1=No of allocation=6
Total Transportation Cost by LCM= 7x2+4x3+1x8+4x7+1x7+2x7= ₹ 83
Transportation Problems
Dr. Deepa Chauhan
Vogel’s Approximation Method (VAM) or Unit Cost Penalty Method
Vogel’s approximation method is an analytic method and is preferred to the method described
earlier. Vogel’s approximation method makes effective use of the cost information and yields a
better initial solution than obtained by the other methods.
Example 1: Find the initial feasible solution by Vogel’s method
Warehouse→
Factory↓
W1 W2 W3 W4 Supply
F1
F2
F3
19
70
40
30
30
8
50
40
70
10
60
20
7
9
18
Demand 5 8 7 14 Total=34
Solution: The above problem is a balanced problem because supply is equal to the demand.
Step I: We first construct the cost and requirement table:
Table-1
Warehouse→
Factory↓
W1 W2 W3 W4 Supply
F1 19 30 50 10 7
F2 70 30 40 60 9
F3 40 8 70 20 18
Demand 5 8 7 14 Total=34
Transportation Problems
Dr. Deepa Chauhan
Step II: We add in above table one row and one column. The additional column is called row penalty
and additional row is called column penalty. In these added rows and columns, we find the
difference between the lowest and second lowest cost entries.
Table-2
Warehouse→
Factory↓
W1 W2 W3 W4 Supply Row
Penalties
F1 19 30 50 10 7
F2 70 30 40 60 9
F3 40 8 (8) 70 20 18
Demand 5 8 7 14 Total=34
Column
Penalties
Step III:
 We select the row or column from table for which penalty is maximum and accordingly allocate
maximum possible amount to cell with lowest cost.
 If there are more than one largest penalty rows or columns, select the row or column having
minimum cost.
 In case of tie in the minimum cost, select the cell which can have maximum allocation. If there is
tie among maximum allocation cell also, select the cell arbitrarily for allocation.
Table-3
Warehouse→
Factory↓
W1 W2 W3 W4 Supply Row
Penalties
F1 19 30 50 10 7 19-10=9
F2 70 30 40 60 9 40-30=10
F3 40 8 (8) 70 20 18 20-8=12
Demand 5 8 7 14 Total=34
Column
Penalties
40-19=21 30-8=22 50-40=10 20-10=10
Transportation Problems
Dr. Deepa Chauhan
Step IV: Now we delete that column or row on which the requirement is fulfilled and then we
construct reduced table
Table-4
Warehouse→
Factory↓
W1 W3 W4 Supply Row
Penalties
F1 19 (5) 50 10 7 19-10=9
F2 70 40 60 9 60-40=20
F3 40 70 20 10 40-20=20
Demand 5 7 14 Total=34
Column
Penalties
40-19=21 50-40=10 20-10=10
Step V: We repeat the step 3 and 4 till all the allocations are completed. The successive reduced
tables are shown below:
Table-5
Warehouse→
Factory↓
W3 W4 Supply Row
Penalties
F1 50 10 2 40
F2 40 60 9 20
F3 70 20 (10) 10 30
Demand 7 14 Total=34
Column
Penalties
50-40=10 20-10=10
Transportation Problems
Dr. Deepa Chauhan
Table-6
Warehouse→
Factory↓
W3 W4 Supply Row
Penalties
F1 50 10 (2) 2 40
F2 40 60 9 20
Demand 7 4 Total=34
Column
Penalties
50-40=10 60-10=50
Table-7
Warehouse→
Factory↓
W3 W4 Supply Row
Penalties
F2 40 (7) 60 (2) 9 20
Demand 7 2 Total=34
Column
Penalties
Step V: Finally we construct a table for giving required feasible solution
Given solution is initial basic feasible solution as m+n-1=No of allocation=6
Transportation cost by Vogel’s method
Z=5*19+10*2+40*7+60*2+8*8+20*10 = ₹ 779
Warehouse→
Factory↓
W1 W2 W3 W4 Supply
F1 19 (5) 30 50 10 (2) 7
F2 70 30 40 (7) 60 (2) 9
F3 40 8 (8) 70 20 (10) 18
Demand 5 8 7 14 Total=34
Transportation Problems
Dr. Deepa Chauhan
Example 2: Find the initial feasible solution by Vogel’s method
W X Y Z Availability
A 7 2 5 5 30
B 4 4 6 5 15
C 5 3 3 2 10
D 4 -1 4 2 20
Demand 20 25 15 15
Solution:
Table-1
W X Y Z Availability
A 7 2 5 5 30
B 4 4 6 5 15
C 5 3 3 2 10
D 4 -1 4 2 20
Demand 20 25 15 15 Total=75
The above problem is a balanced problem because availability is equal to the demand.
Table-2
W X Y Z Availability Row
Penalty
A 7 2 5 5 30 3
B 4 4 6 5 15 1
C 5 3 3 2 10 1
D 4 -1 (20) 4 2 20 3
Demand 20 25 15 15 Total=75
Column
Penalty
1 3 1 3
Transportation Problems
Dr. Deepa Chauhan
Table-3
W X Y Z Availability Row
Penalty
A 7 2 5 5 30 3
B 4 4 6 5 15 1
C 5 3 3 2 (10) 10 1
Demand 20 5 15 15 Total=75
Column
Penalty
1 1 2 3
Table-4
W X Y Z Availability Row
Penalty
A 7 2 (5) 5 5 30 3
B 4 4 6 5 15 1
Demand 20 5 15 5 Total=75
Column
Penalty
3 2 1 0
Table-5
W Y Z Availability Row
Penalty
A 7 5 5 25 2
B 4 (15) 6 5 15 1
Demand 20 15 5 Total=75
Column
Penalty
3 1 0
Transportation Problems
Dr. Deepa Chauhan
Table-6
Final table
W X Y Z Availability
A 7 (5) 2 (5) 5 (15) 5 (5) 30
B 4 (15) 4 6 5 15
C 5 3 3 2 (10) 10
D 4 -1 (20) 4 2 20
Demand 20 25 15 15 Total=75
Given solution is initial basic feasible solution as m+n-1=No of allocation=7
Total transportation cost=35+10+75+25+60+20-20= ₹ 205
W Y Z Availability
A 7 (5) 5 (15) 5 (5) 25
Demand 5 15 5 Total=75

More Related Content

What's hot

Vogel's Approximation Method
Vogel's Approximation MethodVogel's Approximation Method
Vogel's Approximation MethodUsharaniRavikumar
 
Transportation Method Operation Research
Transportation Method Operation ResearchTransportation Method Operation Research
Transportation Method Operation ResearchR A Shah
 
Simplex method concept,
Simplex method concept,Simplex method concept,
Simplex method concept,Dronak Sahu
 
Game Theory Operation Research
Game Theory Operation ResearchGame Theory Operation Research
Game Theory Operation ResearchR A Shah
 
Simplex method: Slack, Surplus & Artificial variable
Simplex method:  Slack, Surplus & Artificial variableSimplex method:  Slack, Surplus & Artificial variable
Simplex method: Slack, Surplus & Artificial variableDevyaneeDevyanee2007
 
Assignment problem
Assignment problemAssignment problem
Assignment problemAbu Bashar
 
Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation pptDeepika Bansal
 
Assignment Problem
Assignment ProblemAssignment Problem
Assignment ProblemNakul Bhardwaj
 
Lpp simplex method
Lpp simplex methodLpp simplex method
Lpp simplex methodSneha Malhotra
 
Duality
DualityDuality
DualitySachin MK
 
Duality in Linear Programming Problem
Duality in Linear Programming ProblemDuality in Linear Programming Problem
Duality in Linear Programming ProblemRAVI PRASAD K.J.
 
Duality in Linear Programming
Duality in Linear ProgrammingDuality in Linear Programming
Duality in Linear Programmingjyothimonc
 
North west corner method
North west corner method North west corner method
North west corner method Akash Jadhav
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem pptDr T.Sivakami
 
Assignment model
Assignment modelAssignment model
Assignment modelPalash Badal
 
Game theory (Operation Research)
Game theory (Operation Research)Game theory (Operation Research)
Game theory (Operation Research)kashif ayaz
 
Simplex Method Explained
Simplex Method ExplainedSimplex Method Explained
Simplex Method ExplainedAtif Shahzad
 
Decision theory
Decision theoryDecision theory
Decision theorySurekha98
 
Well done company case final [compatibility mode]
Well done company case final [compatibility mode]Well done company case final [compatibility mode]
Well done company case final [compatibility mode]RESHMI RAVEENDRAN
 

What's hot (20)

Vogel's Approximation Method
Vogel's Approximation MethodVogel's Approximation Method
Vogel's Approximation Method
 
Transportation Method Operation Research
Transportation Method Operation ResearchTransportation Method Operation Research
Transportation Method Operation Research
 
Simplex method concept,
Simplex method concept,Simplex method concept,
Simplex method concept,
 
Game Theory Operation Research
Game Theory Operation ResearchGame Theory Operation Research
Game Theory Operation Research
 
Simplex method: Slack, Surplus & Artificial variable
Simplex method:  Slack, Surplus & Artificial variableSimplex method:  Slack, Surplus & Artificial variable
Simplex method: Slack, Surplus & Artificial variable
 
Assignment problem
Assignment problemAssignment problem
Assignment problem
 
Assignment Problem
Assignment ProblemAssignment Problem
Assignment Problem
 
Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation ppt
 
Assignment Problem
Assignment ProblemAssignment Problem
Assignment Problem
 
Lpp simplex method
Lpp simplex methodLpp simplex method
Lpp simplex method
 
Duality
DualityDuality
Duality
 
Duality in Linear Programming Problem
Duality in Linear Programming ProblemDuality in Linear Programming Problem
Duality in Linear Programming Problem
 
Duality in Linear Programming
Duality in Linear ProgrammingDuality in Linear Programming
Duality in Linear Programming
 
North west corner method
North west corner method North west corner method
North west corner method
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem ppt
 
Assignment model
Assignment modelAssignment model
Assignment model
 
Game theory (Operation Research)
Game theory (Operation Research)Game theory (Operation Research)
Game theory (Operation Research)
 
Simplex Method Explained
Simplex Method ExplainedSimplex Method Explained
Simplex Method Explained
 
Decision theory
Decision theoryDecision theory
Decision theory
 
Well done company case final [compatibility mode]
Well done company case final [compatibility mode]Well done company case final [compatibility mode]
Well done company case final [compatibility mode]
 

Similar to Transportation Problem- Initial Basic Feasible Solution

Unbalanced Transportation Problem
Unbalanced Transportation ProblemUnbalanced Transportation Problem
Unbalanced Transportation ProblemDrDeepaChauhan
 
VOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHODVOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHODSwethaShree13
 
Lecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solutionLecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solutionAathi Suku
 
Transportation Problems-Maximum Profit
Transportation Problems-Maximum ProfitTransportation Problems-Maximum Profit
Transportation Problems-Maximum ProfitDrDeepaChauhan
 
transporation problem
transporation problemtransporation problem
transporation problemVivek Lohani
 
Optimal Solution by MODI Method
Optimal Solution by MODI MethodOptimal Solution by MODI Method
Optimal Solution by MODI MethodDrDeepaChauhan
 
Top schools in ghaziabad
Top schools in ghaziabadTop schools in ghaziabad
Top schools in ghaziabadEdhole.com
 
Transportation Problem
Transportation ProblemTransportation Problem
Transportation ProblemVivekSaurabh7
 
VAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation ProblemsVAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation ProblemsKarlo Maniego
 
Lecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdfLecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdfamrhebafamily
 
transportationoperationresearch-210111101338.pptx
transportationoperationresearch-210111101338.pptxtransportationoperationresearch-210111101338.pptx
transportationoperationresearch-210111101338.pptxProfessionalDeeksha
 
07. Transportation Problem.pptx
07. Transportation Problem.pptx07. Transportation Problem.pptx
07. Transportation Problem.pptxSupplierSepitengTerm
 
Classbfs121001503719748
Classbfs121001503719748Classbfs121001503719748
Classbfs121001503719748Raju Panthadi
 
Operations Research Modeling Toolset
Operations Research Modeling ToolsetOperations Research Modeling Toolset
Operations Research Modeling ToolsetFellowBuddy.com
 
North West Corner Method
North West Corner MethodNorth West Corner Method
North West Corner MethodUsharaniRavikumar
 
North West Corner Method
North West Corner MethodNorth West Corner Method
North West Corner MethodUsharaniRavikumar
 
QABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptxQABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptxhonakjannu789
 

Similar to Transportation Problem- Initial Basic Feasible Solution (20)

Unbalanced Transportation Problem
Unbalanced Transportation ProblemUnbalanced Transportation Problem
Unbalanced Transportation Problem
 
VOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHODVOGEL'S APPROXIMATION METHOD
VOGEL'S APPROXIMATION METHOD
 
Lecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solutionLecture 7 transportation problem finding initial basic feasible solution
Lecture 7 transportation problem finding initial basic feasible solution
 
Transportation Problems-Maximum Profit
Transportation Problems-Maximum ProfitTransportation Problems-Maximum Profit
Transportation Problems-Maximum Profit
 
transporation problem
transporation problemtransporation problem
transporation problem
 
Optimal Solution by MODI Method
Optimal Solution by MODI MethodOptimal Solution by MODI Method
Optimal Solution by MODI Method
 
Top schools in ghaziabad
Top schools in ghaziabadTop schools in ghaziabad
Top schools in ghaziabad
 
Transportation Problem
Transportation ProblemTransportation Problem
Transportation Problem
 
VAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation ProblemsVAM and MODI Method in Solving Transportation Problems
VAM and MODI Method in Solving Transportation Problems
 
Lecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdfLecture (3) _transportation problem31-10-2020.pdf
Lecture (3) _transportation problem31-10-2020.pdf
 
transportationoperationresearch-210111101338.pptx
transportationoperationresearch-210111101338.pptxtransportationoperationresearch-210111101338.pptx
transportationoperationresearch-210111101338.pptx
 
07. Transportation Problem.pptx
07. Transportation Problem.pptx07. Transportation Problem.pptx
07. Transportation Problem.pptx
 
Classbfs121001503719748
Classbfs121001503719748Classbfs121001503719748
Classbfs121001503719748
 
Transportation problem
Transportation problemTransportation problem
Transportation problem
 
Operations Research Modeling Toolset
Operations Research Modeling ToolsetOperations Research Modeling Toolset
Operations Research Modeling Toolset
 
North West Corner Method
North West Corner MethodNorth West Corner Method
North West Corner Method
 
North West Corner Method
North West Corner MethodNorth West Corner Method
North West Corner Method
 
Transportation technique
Transportation techniqueTransportation technique
Transportation technique
 
Assign transportation
Assign transportationAssign transportation
Assign transportation
 
QABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptxQABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptx
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEslot gacor bisa pakai pulsa
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Transportation Problem- Initial Basic Feasible Solution

  • 1. Transportation Problems Dr. Deepa Chauhan Transportation Problems Initial Basic Feasible Solutions By Dr. Deepa Chauhan Associate Professor, Applied Science & Humanities Department, Axis Institute of Technology, Kanpur
  • 2. Transportation Problems Dr. Deepa Chauhan Methods of Finding an Initial Basic Feasible Solution There are mainly three methods to find initial basic feasible solution to a transportation problem a) North West Corner Method (NWCM) b) Least Cost Method (LCM) or Method of Matrix Minima c) Vogel’s Approximation Method (VAM) Solution by transportation method involves making a transportation model in the form of a matrix, finding an initial basic feasible solution, performing optimality test and moving towards an optimal solution. Initially, Initial Basic Feasible Solution (IBFS) is obtained then the result is used to calculate the optimal solution. The popular methods to find IBFS of transportation problem are North West Corner Method (NWCM), Least Cost Method (LCM), and Vogel's Approximation Method (VAM). The Vogel approximation (Unit penalty) method is an iterative procedure for computing a basic feasible solution of a transportation problem. This method is preferred over the two methods discussed in the previous sections, because the initial basic feasible solution obtained by this method is either optimal or very close to the optimal solution.
  • 3. Transportation Problems Dr. Deepa Chauhan North West Corner Method (NWCM) Example 1: Find the initial feasible solution by North West Corner Method Warehouse→ Factory↓ W1 W2 W3 W4 Factory Capacity F1 F2 F3 19 70 40 30 30 8 50 40 70 10 60 20 7 9 18 Warehouse Requirement 5 8 7 14 Total=34 Solution: The above problem is a balanced problem because factory capacity is equal to the warehouse requirement. We prepare 3X4 table with 3 factories and 4 warehouses. Start giving allocations from North West Corner, shown as below: North-West Corner Available↓ 5 (19) 2 (30) 7 6 (30) 3 (40) 9 4 (70) 14 (20) 18 Requirement→ 5 8 7 14 Given solution is initial basic feasible solution as m+n-1=No of allocation=6 By multiplying each individual allocation by its corresponding unit cost and adding, we get the Total Transportation Cost=5X19+2X30+6X30+3X40+4X70+14X20 =₹ 1015
  • 4. Transportation Problems Dr. Deepa Chauhan Example 2: Find the initial feasible solution by North West Corner Method W1 W2 W3 W4 Supply F1 F2 F3 F4 48 45 50 52 60 55 65 64 56 53 60 55 58 60 62 61 140 260 360 220 Demand 200 320 250 210 Solution: Since the total demand is equal to the total supply (980), it is a balanced transportation problem. Now complete allocation is shown as below: W1 W2 W3 W4 Supply F1 48 (140) 60 56 58 140 F2 45 (60) 55 (200) 53 60 260 F3 50 65 (120) 60 (240) 62 360 F4 52 64 55 (10) 61 (210) 220 Demand 200 320 250 210 Given solution is initial basic feasible solution as m+n-1=No of allocation=7 Total transportation cost=140X48+60X45+200X55+120X65+240X60+10X55+210X61 =₹ 55,980
  • 5. Transportation Problems Dr. Deepa Chauhan Least Cost Method (LCM) Example 1: Find the initial feasible solution by Least Cost Method Warehouse→ Factory↓ W1 W2 W3 W4 Supply F1 F2 F3 19 70 40 30 30 8 50 40 70 10 60 20 7 9 18 Demand 5 8 7 14 Total=34 Solution: The above problem is a balanced problem because factory capacity is equal to the warehouse requirement. Allocations are started with least cost cell, as follows Least Cost Warehouse→ Factory↓ W1 W2 W3 W4 Supply F1 19 30 50 10 (7) 7 F2 70 (2) 30 40 (7) 60 9 F3 40 (3) 8 (8) 70 20 (7) 18 Demand 5 8 7 14 Total=34 Given solution is initial basic feasible solution as m+n-1 (3+4-1=6) =No of allocation=6 Total Transportation Cost= 2x70+40x3+8x8+40x7+10x7+20x7 =₹ 814
  • 6. Transportation Problems Dr. Deepa Chauhan Example 2: Using Least-cost method to solve initial solution of the following problem: Destination Source D1 D2 D3 Capacity S1 10 13 6 10 S2 16 7 13 12 S3 8 22 2 8 Demand 6 11 13 30 Solution: The above problem is a balanced problem because demand is equal to supply. By least cost method, allocations are as follows Destination Source D1 D2 D3 Capacity S1 10 (5) 13 6 (5) 10 S2 16 (1) 7 (11) 13 12 S3 8 22 2 (8) 8 Demand 6 11 13 30 Given solution is initial basic feasible solution as m+n-1=No of allocation=5 Total Transportation Cost by LCM= 10x5+6x5+16x1+7x11+2x8= ₹ 189 Example 3: Find the initial feasible solution by Least Cost Method Origin Destination Supply 2 7 4 5 3 3 1 8 5 4 7 7 1 6 2 14 Demand 7 9 18
  • 7. Transportation Problems Dr. Deepa Chauhan Solution: Origin Destination Supply 2 7 4 5 3 3 1 8 5 4 7 7 1 6 2 14 Demand 7 9 18 Total=34 The above problem is a balanced problem because demand is equal to supply. By least cost method, allocations are as follows Origin Destination Supply 2 7 (2) 4 (3) 5 3 3 1 (8) 8 5 4 (7) 7 7 1 (7) 6 2 (7) 14 Demand 7 9 18 Total=34 Given solution is initial basic feasible solution as m+n-1=No of allocation=6 Total Transportation Cost by LCM= 7x2+4x3+1x8+4x7+1x7+2x7= ₹ 83
  • 8. Transportation Problems Dr. Deepa Chauhan Vogel’s Approximation Method (VAM) or Unit Cost Penalty Method Vogel’s approximation method is an analytic method and is preferred to the method described earlier. Vogel’s approximation method makes effective use of the cost information and yields a better initial solution than obtained by the other methods. Example 1: Find the initial feasible solution by Vogel’s method Warehouse→ Factory↓ W1 W2 W3 W4 Supply F1 F2 F3 19 70 40 30 30 8 50 40 70 10 60 20 7 9 18 Demand 5 8 7 14 Total=34 Solution: The above problem is a balanced problem because supply is equal to the demand. Step I: We first construct the cost and requirement table: Table-1 Warehouse→ Factory↓ W1 W2 W3 W4 Supply F1 19 30 50 10 7 F2 70 30 40 60 9 F3 40 8 70 20 18 Demand 5 8 7 14 Total=34
  • 9. Transportation Problems Dr. Deepa Chauhan Step II: We add in above table one row and one column. The additional column is called row penalty and additional row is called column penalty. In these added rows and columns, we find the difference between the lowest and second lowest cost entries. Table-2 Warehouse→ Factory↓ W1 W2 W3 W4 Supply Row Penalties F1 19 30 50 10 7 F2 70 30 40 60 9 F3 40 8 (8) 70 20 18 Demand 5 8 7 14 Total=34 Column Penalties Step III:  We select the row or column from table for which penalty is maximum and accordingly allocate maximum possible amount to cell with lowest cost.  If there are more than one largest penalty rows or columns, select the row or column having minimum cost.  In case of tie in the minimum cost, select the cell which can have maximum allocation. If there is tie among maximum allocation cell also, select the cell arbitrarily for allocation. Table-3 Warehouse→ Factory↓ W1 W2 W3 W4 Supply Row Penalties F1 19 30 50 10 7 19-10=9 F2 70 30 40 60 9 40-30=10 F3 40 8 (8) 70 20 18 20-8=12 Demand 5 8 7 14 Total=34 Column Penalties 40-19=21 30-8=22 50-40=10 20-10=10
  • 10. Transportation Problems Dr. Deepa Chauhan Step IV: Now we delete that column or row on which the requirement is fulfilled and then we construct reduced table Table-4 Warehouse→ Factory↓ W1 W3 W4 Supply Row Penalties F1 19 (5) 50 10 7 19-10=9 F2 70 40 60 9 60-40=20 F3 40 70 20 10 40-20=20 Demand 5 7 14 Total=34 Column Penalties 40-19=21 50-40=10 20-10=10 Step V: We repeat the step 3 and 4 till all the allocations are completed. The successive reduced tables are shown below: Table-5 Warehouse→ Factory↓ W3 W4 Supply Row Penalties F1 50 10 2 40 F2 40 60 9 20 F3 70 20 (10) 10 30 Demand 7 14 Total=34 Column Penalties 50-40=10 20-10=10
  • 11. Transportation Problems Dr. Deepa Chauhan Table-6 Warehouse→ Factory↓ W3 W4 Supply Row Penalties F1 50 10 (2) 2 40 F2 40 60 9 20 Demand 7 4 Total=34 Column Penalties 50-40=10 60-10=50 Table-7 Warehouse→ Factory↓ W3 W4 Supply Row Penalties F2 40 (7) 60 (2) 9 20 Demand 7 2 Total=34 Column Penalties Step V: Finally we construct a table for giving required feasible solution Given solution is initial basic feasible solution as m+n-1=No of allocation=6 Transportation cost by Vogel’s method Z=5*19+10*2+40*7+60*2+8*8+20*10 = ₹ 779 Warehouse→ Factory↓ W1 W2 W3 W4 Supply F1 19 (5) 30 50 10 (2) 7 F2 70 30 40 (7) 60 (2) 9 F3 40 8 (8) 70 20 (10) 18 Demand 5 8 7 14 Total=34
  • 12. Transportation Problems Dr. Deepa Chauhan Example 2: Find the initial feasible solution by Vogel’s method W X Y Z Availability A 7 2 5 5 30 B 4 4 6 5 15 C 5 3 3 2 10 D 4 -1 4 2 20 Demand 20 25 15 15 Solution: Table-1 W X Y Z Availability A 7 2 5 5 30 B 4 4 6 5 15 C 5 3 3 2 10 D 4 -1 4 2 20 Demand 20 25 15 15 Total=75 The above problem is a balanced problem because availability is equal to the demand. Table-2 W X Y Z Availability Row Penalty A 7 2 5 5 30 3 B 4 4 6 5 15 1 C 5 3 3 2 10 1 D 4 -1 (20) 4 2 20 3 Demand 20 25 15 15 Total=75 Column Penalty 1 3 1 3
  • 13. Transportation Problems Dr. Deepa Chauhan Table-3 W X Y Z Availability Row Penalty A 7 2 5 5 30 3 B 4 4 6 5 15 1 C 5 3 3 2 (10) 10 1 Demand 20 5 15 15 Total=75 Column Penalty 1 1 2 3 Table-4 W X Y Z Availability Row Penalty A 7 2 (5) 5 5 30 3 B 4 4 6 5 15 1 Demand 20 5 15 5 Total=75 Column Penalty 3 2 1 0 Table-5 W Y Z Availability Row Penalty A 7 5 5 25 2 B 4 (15) 6 5 15 1 Demand 20 15 5 Total=75 Column Penalty 3 1 0
  • 14. Transportation Problems Dr. Deepa Chauhan Table-6 Final table W X Y Z Availability A 7 (5) 2 (5) 5 (15) 5 (5) 30 B 4 (15) 4 6 5 15 C 5 3 3 2 (10) 10 D 4 -1 (20) 4 2 20 Demand 20 25 15 15 Total=75 Given solution is initial basic feasible solution as m+n-1=No of allocation=7 Total transportation cost=35+10+75+25+60+20-20= ₹ 205 W Y Z Availability A 7 (5) 5 (15) 5 (5) 25 Demand 5 15 5 Total=75