SlideShare a Scribd company logo
1 of 19
Download to read offline
WELCOMEPMP Preparation Course [PMBOK V.6]
Perform Quantitative Risk Analysis
Sherif Sabri, PMP®
With
Sherif Sabri, PMP®
 OVERVIEW
Perform Quantitative Risk Analysis
 Perform Quantitative Risk Analysis - Inputs
 Perform Quantitative Risk Analysis - Tools & Techniques
 Perform Quantitative Risk Analysis - Outputs
Sherif Sabri, PMP®
OVERVIEW
Risk
Process No. (4)
Planning
Process No. (21)
performed
throughout
the project
Not required
for every
project
Is the process of numerically analyzing the combined effect of identified individual project
risks and other sources of uncertainty on overall project objectives.
The key benefits of this process is that
- It quantifies overall project risk exposure, and it can also provide additional quantitative risk
information to support risk response planning.
PERFORM QUANTITATIVE RISK ANALYSIS
Inputs Tools & Techniques Outputs
.1 Project management plan
• Risk management plan
• Scope baseline
• Schedule baseline
• Cost baseline
.2 Project documents
• Assumption log
• Basis of estimates
• Cost estimates
• Cost forecasts
• Duration estimates
• Milestone list
• Resource requirements
• Risk register
• Risk report
• Schedule forecasts
.3 EEF
.4 OPA
.1 Expert judgment
.2 Data gathering
• Interviews
.3 Interpersonal and team skills
• Facilitation
.4 Representations of uncertainty
.5 Data analysis
• Simulations
• Sensitivity analysis
• Decision tree analysis
• Influence diagrams
.1 Project documents updates
• Risk report
OVERVIEW
1-PROJECT MANAGEMENT PLAN
 Risk management plan: specifies whether quantitative risk analysis is required for the project.
It also details the resources available for the analysis and the expected frequency of analyses.
 Scope baseline: describes the starting point from which the effect of individual project risks and
other sources of uncertainty are evaluated.
 Schedule baseline: describes the starting point from which the effect of individual project risks
and other sources of uncertainty can be evaluated.
 Cost baseline: describes the starting point from which the effect of individual project risks and
other sources of uncertainty can be evaluated
Perform Quantitative Risk Analysis - Inputs
2-PROJECT DOCUMENTS
 Assumption log: Assumptions may form inputs to the quantitative risk analysis if they are assessed as posing a risk to
project objectives.
 Basis of estimates: used in the planning of the project may be reflected in variability modeled during a quantitative risk
analysis process.
 Cost estimates: provide the starting point from which cost variability is evaluated.
 Cost forecasts: Forecasts such as the project’s estimate to complete (ETC), estimate at completion (EAC), budget at
completion (BAC), and to-complete performance index (TCPI) may be compared to the results of a quantitative cost risk
analysis to determine the confidence level associated with achieving these targets.
 Duration estimates: provide the starting point from which schedule variability is evaluated.
 Milestone list: Significant events in the project define the schedule targets against which the results of a quantitative
schedule risk analysis are compared.
 Resource requirements: Resource requirements provide the starting point from which variability is evaluated.
 Risk register: contains details of individual project risks to be used as input for quantitative risk analysis.
 Risk report: describes sources of overall project risk and the current overall project risk status.
 Schedule forecasts: Forecasts may be compared to the results of a quantitative schedule risk analysis to determine the
confidence level associated with achieving these targets
Perform Quantitative Risk Analysis - Inputs
3- EEF
 Industry studies of similar projects
 Published material, including commercial risk databases or checklists.
4- OPA
 Information from similar completed projects.
Perform Quantitative Risk Analysis - Inputs
1-EXPERT JUDGMENT
For this process, expertise should be considered from individuals or groups with specialized
knowledge of or training in the following topics:
 Translating information on individual project risks and other sources of uncertainty into
numeric inputs for the quantitative risk analysis model,
 Modeling techniques that are appropriate in the context of the project,
 Identifying which tools would be most suitable for the selected modeling techniques
 Interpreting the outputs of quantitative risk analysis.
Perform Quantitative Risk Analysis - Tools & Techniques
2-DATA GATHERING
 Interviews: Structured or semi-structured interviews: can be used to assess the probability and
impacts of individual project risks.
The interviewer: should promote an environment of trust and confidentiality in the
interview setting to encourage honest and unbiased assessments.
3-INTERPERSONAL AND TEAM SKILLS
Facilitation: A skilled facilitator is useful for gathering input data during a dedicated risk workshop
involving project team members and other stakeholders.
Facilitated workshops: can improve effectiveness by establishing a clear understanding of the
purpose of the workshop, building consensus among participants, ensuring continued focus on the
task, and using creative approaches to deal with interpersonal conflict or sources of bias.
Perform Quantitative Risk Analysis - Tools & Techniques
4- Representations of Uncertainty
Where the duration, cost, or resource requirement for a planned activity is uncertain, the range of
possible values can be represented in the model as a probability distribution.
This may take several forms, the most commonly used are:
 Triangular,
 Beta,
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS
 Quantitative risk analysis uses a model that simulates the combined effects of individual
project risks and other sources of uncertainty to evaluate their potential impact on
achieving project objectives.
SIMULATION
 Simulations are typically performed using a Monte Carlo Analysis.
 When running a Monte Carlo analysis for cost risk, the simulation uses the project cost estimates.
 When running a Monte Carlo analysis for schedule risk, the schedule network diagram and duration
estimates are used.
 The output is a quantitative risk analysis model.
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS SIMULATION
An example S-curve from a Monte Carlo cost risk analysis
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS
 Helps to determine which individual project risks or other sources of uncertainty have the
most potential impact on project outcomes.
SENSITIVITY ANALYSIS
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS
 One typical display of sensitivity analysis is the tornado diagram, which presents the
calculated correlation coefficient for each element of the quantitative risk analysis model
that can influence the project outcome.
SENSITIVITY ANALYSIS
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS
 Are used to support selection of the best of several alternative courses of action.
 Alternative paths through the project are shown in the decision tree using branches
representing different decisions or events, each of which can have associated costs
and related individual project risks (including both threats and opportunities).
 The end-points of branches in the decision tree represent the outcome from following
that particular path, which can be negative or positive.
 The decision tree is evaluated by calculating the expected monetary value of each
branch, allowing the optimal path to be selected.
Decision tree analysis
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS
Decision tree analysis
Perform Quantitative Risk Analysis - Tools & Techniques
5-DATA ANALYSIS
 Are graphical aids to decision making under uncertainty.
 Represents a project or situation within the project as a set of entities, outcomes, and
influences, together with the relationships and effects between them.
Influence diagrams
Perform Quantitative Risk Analysis - Tools & Techniques
1-PROJECT DOCUMENTS UPDATES
 The risk report will typically include:
 Overall project risk exposure.
 Detailed probabilistic analysis of the project.
 Prioritized list of individual project risks.
 Trends in quantitative risk analysis results.
 Recommended risk responses.
The risk report will be updated to reflect the results of the quantitative risk analysis
Perform Quantitative Risk Analysis - Outputs
T H A N K S F O R W A T C H I N G
Together We will get it done
Sherif Sabri, PMP®

More Related Content

What's hot

Risk management ppt 111p (training module)
Risk management ppt 111p (training module)Risk management ppt 111p (training module)
Risk management ppt 111p (training module)
Sadia Razzaq
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
Hayat Denzi
 
Risk Management Process
Risk Management ProcessRisk Management Process
Risk Management Process
no suhaila
 

What's hot (20)

Risk Management 101
Risk Management 101Risk Management 101
Risk Management 101
 
Risk management ppt 111p (training module)
Risk management ppt 111p (training module)Risk management ppt 111p (training module)
Risk management ppt 111p (training module)
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
Audit sampling
Audit samplingAudit sampling
Audit sampling
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Risk Management Module Powerpoint Presentation Slides
Risk Management Module Powerpoint Presentation SlidesRisk Management Module Powerpoint Presentation Slides
Risk Management Module Powerpoint Presentation Slides
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Risk Appetite & Risk Tolerance: Improving their application from Abstract to ...
Risk Appetite & Risk Tolerance: Improving their application from Abstract to ...Risk Appetite & Risk Tolerance: Improving their application from Abstract to ...
Risk Appetite & Risk Tolerance: Improving their application from Abstract to ...
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation Slides
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Project risk management: Techniques and strategies
Project risk management: Techniques and strategiesProject risk management: Techniques and strategies
Project risk management: Techniques and strategies
 
Risk Management Process
Risk Management ProcessRisk Management Process
Risk Management Process
 
Auditing & Assurance Presentation
Auditing & Assurance PresentationAuditing & Assurance Presentation
Auditing & Assurance Presentation
 
Risk assessment and management
Risk assessment and managementRisk assessment and management
Risk assessment and management
 
Risk Overview & Risk management
Risk Overview & Risk managementRisk Overview & Risk management
Risk Overview & Risk management
 
Risk-management
 Risk-management Risk-management
Risk-management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 

Similar to Perform quantitative risk analysis

PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
MUST
 
Cost management
Cost managementCost management
Cost management
shkadry
 
R I S K M A N A G E M E N T
R I S K  M A N A G E M E N TR I S K  M A N A G E M E N T
R I S K M A N A G E M E N T
madhav shirur
 
software-project-management-unit-2.ppt
software-project-management-unit-2.pptsoftware-project-management-unit-2.ppt
software-project-management-unit-2.ppt
Maanbahadurkhadka
 
software-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfsoftware-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdf
Vinoth Kumar
 
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxTemplates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
mattinsonjanel
 
Logframework and swort thursday
Logframework and swort thursdayLogframework and swort thursday
Logframework and swort thursday
David mbwiga
 

Similar to Perform quantitative risk analysis (20)

Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis
 
Identify risks
Identify risksIdentify risks
Identify risks
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 
PetroSync - Project Risk Assessment & Management
PetroSync - Project Risk Assessment & ManagementPetroSync - Project Risk Assessment & Management
PetroSync - Project Risk Assessment & Management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
 
Cost management
Cost managementCost management
Cost management
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
 
R I S K M A N A G E M E N T
R I S K  M A N A G E M E N TR I S K  M A N A G E M E N T
R I S K M A N A G E M E N T
 
Introduction to Qualitative Risk Analysis for the PMP.pdf
Introduction to Qualitative Risk Analysis for the PMP.pdfIntroduction to Qualitative Risk Analysis for the PMP.pdf
Introduction to Qualitative Risk Analysis for the PMP.pdf
 
Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)
 
Plan risk management
Plan risk management Plan risk management
Plan risk management
 
software-project-management-unit-2.ppt
software-project-management-unit-2.pptsoftware-project-management-unit-2.ppt
software-project-management-unit-2.ppt
 
software-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdfsoftware-project-management-unit-2-220808125214-00921612 (1).pdf
software-project-management-unit-2-220808125214-00921612 (1).pdf
 
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docxTemplates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
Templates and ExamplesTEMPLATE RISK MANAGEMENT PLAN FOR .docx
 
Risk project management - Notes for the CAMP exam
Risk project management - Notes for the CAMP examRisk project management - Notes for the CAMP exam
Risk project management - Notes for the CAMP exam
 
Logframework and swort thursday
Logframework and swort thursdayLogframework and swort thursday
Logframework and swort thursday
 

More from Shereef Sabri

More from Shereef Sabri (9)

Project risk management overview
Project risk management overviewProject risk management overview
Project risk management overview
 
Plan risk responses
Plan risk responsesPlan risk responses
Plan risk responses
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management
 
Monitor risks
Monitor risks Monitor risks
Monitor risks
 
Implement risk responses
Implement risk responses Implement risk responses
Implement risk responses
 
Control procurement
Control procurement Control procurement
Control procurement
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements
 
Project procurement management overview
Project procurement management overviewProject procurement management overview
Project procurement management overview
 
Develop project charter
Develop project charterDevelop project charter
Develop project charter
 

Recently uploaded

February 2024 Recommendations for newsletter
February 2024 Recommendations for newsletterFebruary 2024 Recommendations for newsletter
February 2024 Recommendations for newsletter
ssuserdfec6a
 
KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...
KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...
KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...
Cara Menggugurkan Kandungan 087776558899
 
the Husband rolesBrown Aesthetic Cute Group Project Presentation
the Husband rolesBrown Aesthetic Cute Group Project Presentationthe Husband rolesBrown Aesthetic Cute Group Project Presentation
the Husband rolesBrown Aesthetic Cute Group Project Presentation
brynpueblos04
 

Recently uploaded (10)

Call Girls In Mumbai Just Genuine Call ☎ 7738596112✅ Call Girl Andheri East G...
Call Girls In Mumbai Just Genuine Call ☎ 7738596112✅ Call Girl Andheri East G...Call Girls In Mumbai Just Genuine Call ☎ 7738596112✅ Call Girl Andheri East G...
Call Girls In Mumbai Just Genuine Call ☎ 7738596112✅ Call Girl Andheri East G...
 
WOMEN EMPOWERMENT women empowerment.pptx
WOMEN EMPOWERMENT women empowerment.pptxWOMEN EMPOWERMENT women empowerment.pptx
WOMEN EMPOWERMENT women empowerment.pptx
 
SIKP311 Sikolohiyang Pilipino - Ginhawa.pptx
SIKP311 Sikolohiyang Pilipino - Ginhawa.pptxSIKP311 Sikolohiyang Pilipino - Ginhawa.pptx
SIKP311 Sikolohiyang Pilipino - Ginhawa.pptx
 
February 2024 Recommendations for newsletter
February 2024 Recommendations for newsletterFebruary 2024 Recommendations for newsletter
February 2024 Recommendations for newsletter
 
March 2023 Recommendations for newsletter
March 2023 Recommendations for newsletterMarch 2023 Recommendations for newsletter
March 2023 Recommendations for newsletter
 
KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...
KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...
KLINIK BATA Jual obat penggugur kandungan 087776558899 ABORSI JANIN KEHAMILAN...
 
2023 - Between Philosophy and Practice: Introducing Yoga
2023 - Between Philosophy and Practice: Introducing Yoga2023 - Between Philosophy and Practice: Introducing Yoga
2023 - Between Philosophy and Practice: Introducing Yoga
 
Pokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy TheoryPokemon Go... Unraveling the Conspiracy Theory
Pokemon Go... Unraveling the Conspiracy Theory
 
Dadar West Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Dadar West Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsDadar West Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Dadar West Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
 
the Husband rolesBrown Aesthetic Cute Group Project Presentation
the Husband rolesBrown Aesthetic Cute Group Project Presentationthe Husband rolesBrown Aesthetic Cute Group Project Presentation
the Husband rolesBrown Aesthetic Cute Group Project Presentation
 

Perform quantitative risk analysis

  • 1. WELCOMEPMP Preparation Course [PMBOK V.6] Perform Quantitative Risk Analysis Sherif Sabri, PMP® With Sherif Sabri, PMP®
  • 2.  OVERVIEW Perform Quantitative Risk Analysis  Perform Quantitative Risk Analysis - Inputs  Perform Quantitative Risk Analysis - Tools & Techniques  Perform Quantitative Risk Analysis - Outputs Sherif Sabri, PMP®
  • 3. OVERVIEW Risk Process No. (4) Planning Process No. (21) performed throughout the project Not required for every project
  • 4. Is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives. The key benefits of this process is that - It quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning. PERFORM QUANTITATIVE RISK ANALYSIS Inputs Tools & Techniques Outputs .1 Project management plan • Risk management plan • Scope baseline • Schedule baseline • Cost baseline .2 Project documents • Assumption log • Basis of estimates • Cost estimates • Cost forecasts • Duration estimates • Milestone list • Resource requirements • Risk register • Risk report • Schedule forecasts .3 EEF .4 OPA .1 Expert judgment .2 Data gathering • Interviews .3 Interpersonal and team skills • Facilitation .4 Representations of uncertainty .5 Data analysis • Simulations • Sensitivity analysis • Decision tree analysis • Influence diagrams .1 Project documents updates • Risk report OVERVIEW
  • 5. 1-PROJECT MANAGEMENT PLAN  Risk management plan: specifies whether quantitative risk analysis is required for the project. It also details the resources available for the analysis and the expected frequency of analyses.  Scope baseline: describes the starting point from which the effect of individual project risks and other sources of uncertainty are evaluated.  Schedule baseline: describes the starting point from which the effect of individual project risks and other sources of uncertainty can be evaluated.  Cost baseline: describes the starting point from which the effect of individual project risks and other sources of uncertainty can be evaluated Perform Quantitative Risk Analysis - Inputs
  • 6. 2-PROJECT DOCUMENTS  Assumption log: Assumptions may form inputs to the quantitative risk analysis if they are assessed as posing a risk to project objectives.  Basis of estimates: used in the planning of the project may be reflected in variability modeled during a quantitative risk analysis process.  Cost estimates: provide the starting point from which cost variability is evaluated.  Cost forecasts: Forecasts such as the project’s estimate to complete (ETC), estimate at completion (EAC), budget at completion (BAC), and to-complete performance index (TCPI) may be compared to the results of a quantitative cost risk analysis to determine the confidence level associated with achieving these targets.  Duration estimates: provide the starting point from which schedule variability is evaluated.  Milestone list: Significant events in the project define the schedule targets against which the results of a quantitative schedule risk analysis are compared.  Resource requirements: Resource requirements provide the starting point from which variability is evaluated.  Risk register: contains details of individual project risks to be used as input for quantitative risk analysis.  Risk report: describes sources of overall project risk and the current overall project risk status.  Schedule forecasts: Forecasts may be compared to the results of a quantitative schedule risk analysis to determine the confidence level associated with achieving these targets Perform Quantitative Risk Analysis - Inputs
  • 7. 3- EEF  Industry studies of similar projects  Published material, including commercial risk databases or checklists. 4- OPA  Information from similar completed projects. Perform Quantitative Risk Analysis - Inputs
  • 8. 1-EXPERT JUDGMENT For this process, expertise should be considered from individuals or groups with specialized knowledge of or training in the following topics:  Translating information on individual project risks and other sources of uncertainty into numeric inputs for the quantitative risk analysis model,  Modeling techniques that are appropriate in the context of the project,  Identifying which tools would be most suitable for the selected modeling techniques  Interpreting the outputs of quantitative risk analysis. Perform Quantitative Risk Analysis - Tools & Techniques
  • 9. 2-DATA GATHERING  Interviews: Structured or semi-structured interviews: can be used to assess the probability and impacts of individual project risks. The interviewer: should promote an environment of trust and confidentiality in the interview setting to encourage honest and unbiased assessments. 3-INTERPERSONAL AND TEAM SKILLS Facilitation: A skilled facilitator is useful for gathering input data during a dedicated risk workshop involving project team members and other stakeholders. Facilitated workshops: can improve effectiveness by establishing a clear understanding of the purpose of the workshop, building consensus among participants, ensuring continued focus on the task, and using creative approaches to deal with interpersonal conflict or sources of bias. Perform Quantitative Risk Analysis - Tools & Techniques
  • 10. 4- Representations of Uncertainty Where the duration, cost, or resource requirement for a planned activity is uncertain, the range of possible values can be represented in the model as a probability distribution. This may take several forms, the most commonly used are:  Triangular,  Beta, Perform Quantitative Risk Analysis - Tools & Techniques
  • 11. 5-DATA ANALYSIS  Quantitative risk analysis uses a model that simulates the combined effects of individual project risks and other sources of uncertainty to evaluate their potential impact on achieving project objectives. SIMULATION  Simulations are typically performed using a Monte Carlo Analysis.  When running a Monte Carlo analysis for cost risk, the simulation uses the project cost estimates.  When running a Monte Carlo analysis for schedule risk, the schedule network diagram and duration estimates are used.  The output is a quantitative risk analysis model. Perform Quantitative Risk Analysis - Tools & Techniques
  • 12. 5-DATA ANALYSIS SIMULATION An example S-curve from a Monte Carlo cost risk analysis Perform Quantitative Risk Analysis - Tools & Techniques
  • 13. 5-DATA ANALYSIS  Helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes. SENSITIVITY ANALYSIS Perform Quantitative Risk Analysis - Tools & Techniques
  • 14. 5-DATA ANALYSIS  One typical display of sensitivity analysis is the tornado diagram, which presents the calculated correlation coefficient for each element of the quantitative risk analysis model that can influence the project outcome. SENSITIVITY ANALYSIS Perform Quantitative Risk Analysis - Tools & Techniques
  • 15. 5-DATA ANALYSIS  Are used to support selection of the best of several alternative courses of action.  Alternative paths through the project are shown in the decision tree using branches representing different decisions or events, each of which can have associated costs and related individual project risks (including both threats and opportunities).  The end-points of branches in the decision tree represent the outcome from following that particular path, which can be negative or positive.  The decision tree is evaluated by calculating the expected monetary value of each branch, allowing the optimal path to be selected. Decision tree analysis Perform Quantitative Risk Analysis - Tools & Techniques
  • 16. 5-DATA ANALYSIS Decision tree analysis Perform Quantitative Risk Analysis - Tools & Techniques
  • 17. 5-DATA ANALYSIS  Are graphical aids to decision making under uncertainty.  Represents a project or situation within the project as a set of entities, outcomes, and influences, together with the relationships and effects between them. Influence diagrams Perform Quantitative Risk Analysis - Tools & Techniques
  • 18. 1-PROJECT DOCUMENTS UPDATES  The risk report will typically include:  Overall project risk exposure.  Detailed probabilistic analysis of the project.  Prioritized list of individual project risks.  Trends in quantitative risk analysis results.  Recommended risk responses. The risk report will be updated to reflect the results of the quantitative risk analysis Perform Quantitative Risk Analysis - Outputs
  • 19. T H A N K S F O R W A T C H I N G Together We will get it done Sherif Sabri, PMP®