Redlands-Alabama intersection construction schedule as of 11.17.14
1. Redlands Blvd.
Alabama St.
Construction
Schedule
Update
Upcoming Construction Activities:
oNovember 22nd- Base paving will be installed.
oNovember 26th- Temporary striping will be
installed. Barricades will be placed around power
poles to facilitate traffic flow.
oPost Thanksgiving- Barricades & existing power
poles 11/17/2014
ttoo bbee rreemmoovveedd..
*Check back for more details about the construction schedule post-
Thanksgiving.
Olivia Crowley,
Community Relations Coordinator
909-798-7584 ext. 3
*Construction schedule is
subject to change based
on conditions in the field.