SlideShare a Scribd company logo
1 of 48
Download to read offline
Hitec Diesel Rotary UPS systems
Case Study:
The Malaga Data Centre, Perth, WA
A comparison between the original static UPS and standby
diesel generator design and the high-voltage Hitec Diesel
Rotary UPS solution installed
Ride through systems DRUPS systems
www.hitec-ups.com
• The Hitec Organisation in APAC
• The Hitec Diesel Rotary UPS System
• Malaga Case Study - Data Centre Design Criteria
- The Original SUPS Scheme
- The HV DRUPS approach
- Reducing CAPEX
- Meeting TIA 942 / Tier III
- Sustainability and efficiency
- The completed facility
- Awards
The Hitec Organisation
in APAC
HITEC + HOTEC,
Taiwan
HITEC + Power Partners,
Singapore
HITEC Malaysia
Hisec, Japan
Hitec+ Metrowest,
Australia + NZ
Hi-Rel, India
HPS, South Korea
Matech, Thailand
Hitec in Asia Pacific
Wide Regional Presence
PBG
Indonesia
DP Consulting, Vietnam
Taiwan: 197
China: 28
Singapore: 46
Malaysia: 9
Australia: 20
India: 8
South Korea: 47
Thailand: 16
Asia Installed Base: 371 units
Hitec in Asia Pacific
Large installed based
• Sales and Marketing
• Technical and Design Assistance
• Project Engineering
• Project Management
• After Sales Support
• Service and Maintenance
• Strategic and Consumable Spares
Hitec in Asia Pacific
Hitec’s Regional Support
The Hitec
Diesel Rotary UPS system
The Hitec DRUPS system
• A complete solution that utilises
stored mechanical energy
to provide continuous power.
• Combines the functionality of
both a UPS and a Standby Diesel Engine in a single module.
• Provides high quality power to support all types of load,
including critical cooling loads and those with a leading
power factor i.e. Blade Servers.
• Suitable for both HV and LV and 50/60 Hz applications.
• A highly reliable tried and tested design.
Standby Diesel
UPS Inverters
Air Conditioning
SwitchboardsPFC
Standby Batteries
Spark-proof Lighting
Busduct & Cabling
Fire Protection
& Security
Static UPS
+
The Hitec DRUPS system
Ways in which UPS can be achieved
Hitec DRUPS
The Hitec DRUPS system
Ways in which UPS can be achieved
Hitec DRUPS
Standby Diesel
Static UPS
UPS Inverters
Air Conditioning
SwitchboardsPFC
Standby Batteries
Spark-proof Lighting
Busduct & Cabling
Fire Protection
& Security
The Hitec DRUPS system
Ways in which UPS can be achieved
Case Study:
The Malaga Data Centre,
WA
• Co-location Facility
• Minimal build cost
• UTI Tier III / TIA 942 Certified
• 3000m² of raised floor
• Load to increase over time (3-4 Year Build-out)
• Initial floor loading of 750 Watts/m²
• Ultimate floor loading 1500 Watts/m²
• Pay as you go approach to infrastructure
• Was fully designed around SUPS plus standby generators
Data Centre Criteria
The Original Scheme
LV Switchgear
Standby Generators
Static
UPS #1
Static
UPS #2
TxTx
The Original Scheme
Floor plan and plantroom take-up
for the SUPS and diesel generator scheme
Issues with the SUPS and diesel generator scheme:
• Cost and availability of the 22kV to 415V transformers
• Restricted space for up to 5 standby diesel generators
• Cooling (recirculation) issues for the diesel generators
• Very high nominal (In) and short-circuit (Isc) currents
• Reliability, control and cost of the ATS switches
• Capacity, quantity and space required for the reticulation
• LV switchgear expanding beyond the available space
• Space and cooling required for the SUPS and batteries
• Chillers unsported by UPS power
The Original Scheme
The DRUPS challenge!
• Resolve the transformer delivery issue
• Rationalise the distribution scheme, reduce reticulation
• Remove the ATS control and reduce high fault currents
• Support (if possible increase) the avialable UPS power
• Provide continuous power to the chillers
• Reduce the total building load and increase efficiency
• Resolve the spatial and cooling issues with the generators
• If possible increase useable raised floor area
• Deliver a scalable solution – Pay as you Grow!
The DRUPS Approach
A B
A B
A B
The DRUPS approach
Removing transformers, simplifying the
scheme, reducing reticulation, increase
UPS power
SUPS + DG’s DRUPS
Total UPS Load 4161.9 kW 4161.9 kW
Total Cooling Load 1872.9 kW* 1664.8 kW
Total Building Load 187.5 kW 187.5 kW
Grand Total 6222.3 kW 6014.2 kW
*Cooling Load is less for DRUPS
as it requires no AC and can
operate at ambient
Reducing the Building Load
SUPS versus DRUPS
Ventialtion and cooling
Reverse the modules, remotely sited
radiators and a plantroom approach
Space and Expansion
Individual fire rated DRUPS rooms,
seperate switchgear rooms, redundant
control and rooms
Original SUPS Requirement
• 12 x 500 kVA SUPS Modules 2(4 +1)
• 5 x 2.5 MVA Standby Diesel Generators (N+1)
Alternative DRUPS Requirement
• 5 x 2.3 MVA DRUPS Modules (N+1)
Is this the totality of the comparison?
Reducing CAPEX
Power Equipment Summary
Reducing CAPEX
Removal of the ‘Big Ticket’ items
• 22kV/415V Transformers
• Main LV Switchboards
• Diesel Generators
• Paralleling Switchboard
• SUPS Modules + Batteries
• SUPS Output Switchboard
X X
X
X X
X X
X X
X
Reducing CAPEX
Simplify distribution, reduce In and Isc
• 7000A Busduct
• 20 x 1C 400mm²
• 20 x 1C 500mm²
• 4000A Mains/Gen ATS’s + Controls
One SUPS String
• 20 x 1C 500mm²
• 4000A Mains/Gen ATS + Controls
• 4 x 3C 300mm² + 3 x 1C 400mm² N+PE
• 5+1 500 kVA SUPS
• 4 x 3C 300mm² + 3 x 1C 400mm² N+PE
• 6000A rated SUPS O/P switchboard
Reducing CAPEX
Rationalise reticulation, remove ATS’
Reducing CAPEX
Comprehensive evaluation of approaches
SUPS Equipment Removed
• 22kV/415V Transformers
• Main LV Switchboards
• Diesel Generators
• Paralleling Switchboard
• SUPS Modules + Batteries
• SUPS Output Switchboard
• ATS Switches and Controls
• High Current LV Busduct
• High Current LV Cabling
Reducing CAPEX
Comprehensive evaluation of approaches
Addition of:
• Up to 5No 2.3 MVA Hitec DRUPS Modules
• Ancillary DRUPS Equipments
• 22kV UPS Input / Output Switchgear
• Low-current high-voltage cabling
• 22kV to 415 power transformers
• Dual Redundant Control Scheme (Tier III)
Reducing CAPEX
Comprehensive evaluation of approaches
Tier Classification:
• System component redundancy:
N+1 requirement: for both UPS and
Generation equipment, as site Generation is
considered to be the primary power source.
• Multiple distribution paths,
enabling…
• Concurrent Maintainability:
“Any component necessary to support the IT
processing environment can be maintained
without impact on the IT environment.”
But…
• System not ‘Fault Tolerant’:
“The site is susceptible to disruption from
unplanned activities.”
UTI Tier III
Concurrent Maintainabililty
DRUPS2
DRUPS5
DRUPS3
DRUPS4
DRUPS1
• System
Component
Redundancy
(N+1)

UPS Input
Switchboard
Separate UPS Output
Switchboards
System ‘A’ System ‘B’
22kV
‘A’
22kV
‘B’
LV Loads
‘A’
LV Loads
‘B’
The DRUPS Approach
Concurrent Maintainability
DRUPS2
DRUPS5
DRUPS3
DRUPS4
DRUPS1
UPS Input
Switchboard
Separate UPS Output
Switchboards
System ‘A’ System ‘B’
22kV
‘A’
22kV
‘B’
LV Loads
‘A’
LV Loads
‘B’
The DRUPS Approach
Concurrent Maintainability
• Multiple
Distribution
Paths

DRUPS2
DRUPS5
DRUPS3
DRUPS4
DRUPS1
• Concurrent
Maintainability

UPS Input
Switchboard
Separate UPS Output
Switchboards
System ‘A’ System ‘B’
22kV
‘A’
22kV
‘B’
LV Loads
‘A’
LV Loads
‘B’
The DRUPS Approach
Concurrent Maintainability
DRUPS2
DRUPS5
DRUPS6
DRUPS3
DRUPS4
DRUPS1
UPS Input
Switchboard
Separate UPS Output
Switchboards
System ‘A’ System ‘B’
22kV
‘A’
22kV
‘B’
LV Loads
‘A’
LV Loads
‘B’
The DRUPS Approach
Concurrent Maintainability
• Concurrent
Maintainability

DRUPS2
DRUPS5
DRUPS3
DRUPS4
DRUPS1
UPS Input
Switchboard
Separate UPS Output
Switchboards
System ‘A’ System ‘B’
22kV
‘A’
22kV
‘B’
LV Loads
‘A’
LV Loads
‘B’
The DRUPS Approach
Concurrent Maintainability
• Concurrent
Maintainability

DRUPS2
DRUPS5
DRUPS3
DRUPS4
DRUPS1
UPS Input
Switchboard
Separate UPS Output
Switchboards
System ‘A’ System ‘B’
22kV
‘A’
22kV
‘B’
LV Loads
‘A’
LV Loads
‘B’
The DRUPS Approach
Concurrent Maintainability
• Concurrent
Maintainability

Bypass Control
Panel
Q3
Q4
Dual Redundant Modbus+ Networks
Unit
Control
Panel
PLC
Bypass
Control
Panel
Dual PLCs
To other
modules
Modbus+Network
Bypass
Control
Panel
Dual PLCs
Unit
Control
Panel
PLC
Modbus+Network
Fibre Optic
Unit Control
Panel
Unit Control
Panel
Bypass Control
Panel
The DRUPS Approach
Dual Redundant Control Scheme (Tier III)
Increasing lettable space
Reducing Total Plantroom Area
LV Switchgear
Standby Generators
Static
UPS #1
Static
UPS #2
TxTx
Increasing lettable space
The Static UPS approach
• 9MVA Static UPS and Diesel Generator arrangement
• Total space required =1,762m²
DRUPS Modules,
HV Switchgear
and Controls
SwGr
‘A’
SwGr
‘B’
• 9 MVA Diesel Rotary UPS solution
• Total space required = 1,228m²
• Total Space saved = 534m² (30% Space Saving)
Data Centre Expansion
Increasing lettable space
The Diesel Rotary UPS approach
Calculating Carbon Footprint
Operating efficiency is the key to calculating a ‘systems’ Carbon Footprint
Increasing Effiency
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
1 2 3 4 5 6 7 8 9 10
DRUPS Static UPS
$1,939K
$895K
High Efficiency = Low Life Cost
Comparative running costs at 50% load based
on 9.5 cents/kWhr (AIR 2.5%) for a UPS requirement of 1600kW
Cost€’s
Year
Saving of $1,044K over a 10 Year Period
Increasing Effiency
• Reduced CAPEX
• Simplified the reticulation and reduced fault current
• Used fewer components increased the lettable area
• Reduced the connections between supply and Load
• Provided continuous support to the total facility
• Lowered the overall building load
• Increased environmental and operating efficiency
• Reduced the carbon footprint and OPEX
• Increases the overall system reliability
• Considered as the ‘GREEN’ sustainable power approach
So why HV Hitec DRUPS?
The Completed Installation
The Completed Installation
The Completed Installation
Awards
Excellence in Energy Efficiency
Awards
Best Building Fit Out Over $20M
Questions

More Related Content

What's hot

Standby power systems for hospitals
Standby power systems for hospitalsStandby power systems for hospitals
Standby power systems for hospitals
michaeljmack
 
Generator 101 power point
Generator 101 power pointGenerator 101 power point
Generator 101 power point
Jorge Palgan
 
Evaluation of standby power system architectures
Evaluation of standby power system architecturesEvaluation of standby power system architectures
Evaluation of standby power system architectures
michaeljmack
 
AMSC D-VAR STATCOM Systems - Intro
AMSC D-VAR STATCOM Systems - IntroAMSC D-VAR STATCOM Systems - Intro
AMSC D-VAR STATCOM Systems - Intro
Paul Chang
 
Cirrascale forest container march 2011
Cirrascale forest container march 2011Cirrascale forest container march 2011
Cirrascale forest container march 2011
Muchamad Jainuri
 
Commercial Overview SCS Session 1 Server Rack Strategies
Commercial Overview   SCS Session 1   Server Rack StrategiesCommercial Overview   SCS Session 1   Server Rack Strategies
Commercial Overview SCS Session 1 Server Rack Strategies
paul_mathews
 

What's hot (20)

Standby power systems for hospitals
Standby power systems for hospitalsStandby power systems for hospitals
Standby power systems for hospitals
 
Generator 101 power point
Generator 101 power pointGenerator 101 power point
Generator 101 power point
 
Critical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearCritical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgear
 
Standby Systems
Standby SystemsStandby Systems
Standby Systems
 
Evaluation of standby power system architectures
Evaluation of standby power system architecturesEvaluation of standby power system architectures
Evaluation of standby power system architectures
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System Design
 
Modular Data Center Design
Modular Data Center DesignModular Data Center Design
Modular Data Center Design
 
Asc 4 data sheet 4921240529 uk (1)
Asc 4 data sheet 4921240529 uk (1)Asc 4 data sheet 4921240529 uk (1)
Asc 4 data sheet 4921240529 uk (1)
 
Data Center Optimization Best Practices
Data Center Optimization Best PracticesData Center Optimization Best Practices
Data Center Optimization Best Practices
 
NFPA 110 Overview
NFPA 110 OverviewNFPA 110 Overview
NFPA 110 Overview
 
AMSC D-VAR STATCOM Systems - Intro
AMSC D-VAR STATCOM Systems - IntroAMSC D-VAR STATCOM Systems - Intro
AMSC D-VAR STATCOM Systems - Intro
 
Data Center Cooling Design - Datacenter-serverroom
Data Center Cooling Design - Datacenter-serverroomData Center Cooling Design - Datacenter-serverroom
Data Center Cooling Design - Datacenter-serverroom
 
Phase 4
Phase 4Phase 4
Phase 4
 
Cirrascale forest container march 2011
Cirrascale forest container march 2011Cirrascale forest container march 2011
Cirrascale forest container march 2011
 
Ever Green Dc
Ever Green DcEver Green Dc
Ever Green Dc
 
Corporate Profile of Silicon Technologies, Karachi, Pakistan 2017
Corporate Profile of Silicon Technologies, Karachi, Pakistan 2017Corporate Profile of Silicon Technologies, Karachi, Pakistan 2017
Corporate Profile of Silicon Technologies, Karachi, Pakistan 2017
 
Maximum Load The Wrong Specification for Pulsed Power Webinar
Maximum Load   The Wrong Specification for Pulsed Power WebinarMaximum Load   The Wrong Specification for Pulsed Power Webinar
Maximum Load The Wrong Specification for Pulsed Power Webinar
 
Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power
 
D Var Statcom Introduction
D Var Statcom IntroductionD Var Statcom Introduction
D Var Statcom Introduction
 
Commercial Overview SCS Session 1 Server Rack Strategies
Commercial Overview   SCS Session 1   Server Rack StrategiesCommercial Overview   SCS Session 1   Server Rack Strategies
Commercial Overview SCS Session 1 Server Rack Strategies
 

Viewers also liked

Navigating the ios
Navigating the iosNavigating the ios
Navigating the ios
Yaser Rahmati
 
[ppt] MPM Self-Introduction - AKBAR SUKASDI
[ppt] MPM Self-Introduction - AKBAR SUKASDI[ppt] MPM Self-Introduction - AKBAR SUKASDI
[ppt] MPM Self-Introduction - AKBAR SUKASDI
Akbar Pamungkas Sukasdi
 
Master version draft final
Master version draft finalMaster version draft final
Master version draft final
irbgcpartners
 
13 0716 session 1 & 2 webinars-final
13 0716 session 1 & 2 webinars-final13 0716 session 1 & 2 webinars-final
13 0716 session 1 & 2 webinars-final
CleantechOpen
 
Mercenaries Unleashed, 2016
Mercenaries Unleashed, 2016Mercenaries Unleashed, 2016
Mercenaries Unleashed, 2016
Russel Harland
 
GPP Final Draft for Scott Wells
GPP Final Draft for Scott WellsGPP Final Draft for Scott Wells
GPP Final Draft for Scott Wells
Scott Wells
 
Career Profile - Anshuman Jain
Career Profile - Anshuman JainCareer Profile - Anshuman Jain
Career Profile - Anshuman Jain
Anshuman Jain
 
ISON Technologies Overview Presentation
ISON Technologies Overview PresentationISON Technologies Overview Presentation
ISON Technologies Overview Presentation
Chhavi Tiwari Sood
 
Journal of International Business Research and Marketing (3)
Journal of International Business Research and Marketing (3)Journal of International Business Research and Marketing (3)
Journal of International Business Research and Marketing (3)
Katerina Panarina
 

Viewers also liked (20)

Navigating the ios
Navigating the iosNavigating the ios
Navigating the ios
 
[ppt] MPM Self-Introduction - AKBAR SUKASDI
[ppt] MPM Self-Introduction - AKBAR SUKASDI[ppt] MPM Self-Introduction - AKBAR SUKASDI
[ppt] MPM Self-Introduction - AKBAR SUKASDI
 
Master version draft final
Master version draft finalMaster version draft final
Master version draft final
 
Beyondfreud
BeyondfreudBeyondfreud
Beyondfreud
 
13 0716 session 1 & 2 webinars-final
13 0716 session 1 & 2 webinars-final13 0716 session 1 & 2 webinars-final
13 0716 session 1 & 2 webinars-final
 
Pre Internship Vaibhav Gupta Samtel
Pre Internship Vaibhav Gupta SamtelPre Internship Vaibhav Gupta Samtel
Pre Internship Vaibhav Gupta Samtel
 
Gilda's Club 2011 "Live! From South Florida...It's Saturday Night!" Virtual ...
Gilda's Club 2011 "Live! From South Florida...It's Saturday Night!"  Virtual ...Gilda's Club 2011 "Live! From South Florida...It's Saturday Night!"  Virtual ...
Gilda's Club 2011 "Live! From South Florida...It's Saturday Night!" Virtual ...
 
Mercenaries Unleashed, 2016
Mercenaries Unleashed, 2016Mercenaries Unleashed, 2016
Mercenaries Unleashed, 2016
 
GPP Final Draft for Scott Wells
GPP Final Draft for Scott WellsGPP Final Draft for Scott Wells
GPP Final Draft for Scott Wells
 
Spark - Volume 3
Spark - Volume 3Spark - Volume 3
Spark - Volume 3
 
tema 3 tema 1
tema 3 tema 1tema 3 tema 1
tema 3 tema 1
 
Foreign Educational Institutions In India Vaibhav Gupta
Foreign Educational Institutions In India   Vaibhav GuptaForeign Educational Institutions In India   Vaibhav Gupta
Foreign Educational Institutions In India Vaibhav Gupta
 
47035 0 mma
47035 0 mma47035 0 mma
47035 0 mma
 
Career Profile - Anshuman Jain
Career Profile - Anshuman JainCareer Profile - Anshuman Jain
Career Profile - Anshuman Jain
 
Publication listing
Publication listingPublication listing
Publication listing
 
Spartacus and the slave war
Spartacus and the slave warSpartacus and the slave war
Spartacus and the slave war
 
ISON Technologies Overview Presentation
ISON Technologies Overview PresentationISON Technologies Overview Presentation
ISON Technologies Overview Presentation
 
Excise law
Excise lawExcise law
Excise law
 
Application Security Vulnerabilities: OWASP Top 10 -2007
Application Security Vulnerabilities: OWASP Top 10  -2007Application Security Vulnerabilities: OWASP Top 10  -2007
Application Security Vulnerabilities: OWASP Top 10 -2007
 
Journal of International Business Research and Marketing (3)
Journal of International Business Research and Marketing (3)Journal of International Business Research and Marketing (3)
Journal of International Business Research and Marketing (3)
 

Similar to Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

Global General Presentation 2011
Global General Presentation 2011Global General Presentation 2011
Global General Presentation 2011
vikings28
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System
Sarthak Panigrahi
 
Case studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programCase studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response program
Zondits
 
schneider-electric-storage.pptx
schneider-electric-storage.pptxschneider-electric-storage.pptx
schneider-electric-storage.pptx
Poooi2
 
DeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdfDeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdf
bayu162365
 
AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015
johnwrightsmith
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard Design
Living Online
 

Similar to Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722 (20)

Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
 
Global General Presentation 2011
Global General Presentation 2011Global General Presentation 2011
Global General Presentation 2011
 
Data Center UPS System Upgrade
Data Center UPS System UpgradeData Center UPS System Upgrade
Data Center UPS System Upgrade
 
Wind turbine retrofit
Wind turbine retrofitWind turbine retrofit
Wind turbine retrofit
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System
 
Telehousenorth2presentationford sd2015
Telehousenorth2presentationford sd2015Telehousenorth2presentationford sd2015
Telehousenorth2presentationford sd2015
 
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative coolingTelehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
 
Virtualization for efficiency: by Kathrin Winkler, The green grid
Virtualization for efficiency: by Kathrin Winkler, The green gridVirtualization for efficiency: by Kathrin Winkler, The green grid
Virtualization for efficiency: by Kathrin Winkler, The green grid
 
Case studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programCase studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response program
 
schneider-electric-storage.pptx
schneider-electric-storage.pptxschneider-electric-storage.pptx
schneider-electric-storage.pptx
 
Design drivers for monitoring critical infrastructure
Design drivers for monitoring critical infrastructureDesign drivers for monitoring critical infrastructure
Design drivers for monitoring critical infrastructure
 
ComRent Capabilities Overview v10 Solar
ComRent Capabilities Overview v10 SolarComRent Capabilities Overview v10 Solar
ComRent Capabilities Overview v10 Solar
 
DeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdfDeployingAnAdvancedDistribution.pdf
DeployingAnAdvancedDistribution.pdf
 
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia LaboratoryRT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
 
OPAL-RT & Hydro-Quebec - HYPERSIM
OPAL-RT & Hydro-Quebec - HYPERSIMOPAL-RT & Hydro-Quebec - HYPERSIM
OPAL-RT & Hydro-Quebec - HYPERSIM
 
AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard Design
 
Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...
 

Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722

  • 1. Hitec Diesel Rotary UPS systems Case Study: The Malaga Data Centre, Perth, WA A comparison between the original static UPS and standby diesel generator design and the high-voltage Hitec Diesel Rotary UPS solution installed Ride through systems DRUPS systems www.hitec-ups.com
  • 2. • The Hitec Organisation in APAC • The Hitec Diesel Rotary UPS System • Malaga Case Study - Data Centre Design Criteria - The Original SUPS Scheme - The HV DRUPS approach - Reducing CAPEX - Meeting TIA 942 / Tier III - Sustainability and efficiency - The completed facility - Awards
  • 4. HITEC + HOTEC, Taiwan HITEC + Power Partners, Singapore HITEC Malaysia Hisec, Japan Hitec+ Metrowest, Australia + NZ Hi-Rel, India HPS, South Korea Matech, Thailand Hitec in Asia Pacific Wide Regional Presence PBG Indonesia DP Consulting, Vietnam
  • 5. Taiwan: 197 China: 28 Singapore: 46 Malaysia: 9 Australia: 20 India: 8 South Korea: 47 Thailand: 16 Asia Installed Base: 371 units Hitec in Asia Pacific Large installed based
  • 6. • Sales and Marketing • Technical and Design Assistance • Project Engineering • Project Management • After Sales Support • Service and Maintenance • Strategic and Consumable Spares Hitec in Asia Pacific Hitec’s Regional Support
  • 8. The Hitec DRUPS system • A complete solution that utilises stored mechanical energy to provide continuous power. • Combines the functionality of both a UPS and a Standby Diesel Engine in a single module. • Provides high quality power to support all types of load, including critical cooling loads and those with a leading power factor i.e. Blade Servers. • Suitable for both HV and LV and 50/60 Hz applications. • A highly reliable tried and tested design.
  • 9. Standby Diesel UPS Inverters Air Conditioning SwitchboardsPFC Standby Batteries Spark-proof Lighting Busduct & Cabling Fire Protection & Security Static UPS + The Hitec DRUPS system Ways in which UPS can be achieved
  • 10. Hitec DRUPS The Hitec DRUPS system Ways in which UPS can be achieved
  • 11. Hitec DRUPS Standby Diesel Static UPS UPS Inverters Air Conditioning SwitchboardsPFC Standby Batteries Spark-proof Lighting Busduct & Cabling Fire Protection & Security The Hitec DRUPS system Ways in which UPS can be achieved
  • 12. Case Study: The Malaga Data Centre, WA
  • 13. • Co-location Facility • Minimal build cost • UTI Tier III / TIA 942 Certified • 3000m² of raised floor • Load to increase over time (3-4 Year Build-out) • Initial floor loading of 750 Watts/m² • Ultimate floor loading 1500 Watts/m² • Pay as you go approach to infrastructure • Was fully designed around SUPS plus standby generators Data Centre Criteria
  • 15. LV Switchgear Standby Generators Static UPS #1 Static UPS #2 TxTx The Original Scheme Floor plan and plantroom take-up for the SUPS and diesel generator scheme
  • 16. Issues with the SUPS and diesel generator scheme: • Cost and availability of the 22kV to 415V transformers • Restricted space for up to 5 standby diesel generators • Cooling (recirculation) issues for the diesel generators • Very high nominal (In) and short-circuit (Isc) currents • Reliability, control and cost of the ATS switches • Capacity, quantity and space required for the reticulation • LV switchgear expanding beyond the available space • Space and cooling required for the SUPS and batteries • Chillers unsported by UPS power The Original Scheme
  • 17. The DRUPS challenge! • Resolve the transformer delivery issue • Rationalise the distribution scheme, reduce reticulation • Remove the ATS control and reduce high fault currents • Support (if possible increase) the avialable UPS power • Provide continuous power to the chillers • Reduce the total building load and increase efficiency • Resolve the spatial and cooling issues with the generators • If possible increase useable raised floor area • Deliver a scalable solution – Pay as you Grow! The DRUPS Approach
  • 18. A B A B A B The DRUPS approach Removing transformers, simplifying the scheme, reducing reticulation, increase UPS power
  • 19. SUPS + DG’s DRUPS Total UPS Load 4161.9 kW 4161.9 kW Total Cooling Load 1872.9 kW* 1664.8 kW Total Building Load 187.5 kW 187.5 kW Grand Total 6222.3 kW 6014.2 kW *Cooling Load is less for DRUPS as it requires no AC and can operate at ambient Reducing the Building Load SUPS versus DRUPS
  • 20. Ventialtion and cooling Reverse the modules, remotely sited radiators and a plantroom approach
  • 21. Space and Expansion Individual fire rated DRUPS rooms, seperate switchgear rooms, redundant control and rooms
  • 22. Original SUPS Requirement • 12 x 500 kVA SUPS Modules 2(4 +1) • 5 x 2.5 MVA Standby Diesel Generators (N+1) Alternative DRUPS Requirement • 5 x 2.3 MVA DRUPS Modules (N+1) Is this the totality of the comparison? Reducing CAPEX Power Equipment Summary
  • 23. Reducing CAPEX Removal of the ‘Big Ticket’ items • 22kV/415V Transformers • Main LV Switchboards • Diesel Generators • Paralleling Switchboard • SUPS Modules + Batteries • SUPS Output Switchboard X X X X X X X X X X
  • 24. Reducing CAPEX Simplify distribution, reduce In and Isc • 7000A Busduct • 20 x 1C 400mm² • 20 x 1C 500mm² • 4000A Mains/Gen ATS’s + Controls
  • 25. One SUPS String • 20 x 1C 500mm² • 4000A Mains/Gen ATS + Controls • 4 x 3C 300mm² + 3 x 1C 400mm² N+PE • 5+1 500 kVA SUPS • 4 x 3C 300mm² + 3 x 1C 400mm² N+PE • 6000A rated SUPS O/P switchboard Reducing CAPEX Rationalise reticulation, remove ATS’
  • 27. SUPS Equipment Removed • 22kV/415V Transformers • Main LV Switchboards • Diesel Generators • Paralleling Switchboard • SUPS Modules + Batteries • SUPS Output Switchboard • ATS Switches and Controls • High Current LV Busduct • High Current LV Cabling Reducing CAPEX Comprehensive evaluation of approaches
  • 28. Addition of: • Up to 5No 2.3 MVA Hitec DRUPS Modules • Ancillary DRUPS Equipments • 22kV UPS Input / Output Switchgear • Low-current high-voltage cabling • 22kV to 415 power transformers • Dual Redundant Control Scheme (Tier III) Reducing CAPEX Comprehensive evaluation of approaches
  • 29. Tier Classification: • System component redundancy: N+1 requirement: for both UPS and Generation equipment, as site Generation is considered to be the primary power source. • Multiple distribution paths, enabling… • Concurrent Maintainability: “Any component necessary to support the IT processing environment can be maintained without impact on the IT environment.” But… • System not ‘Fault Tolerant’: “The site is susceptible to disruption from unplanned activities.” UTI Tier III Concurrent Maintainabililty
  • 30. DRUPS2 DRUPS5 DRUPS3 DRUPS4 DRUPS1 • System Component Redundancy (N+1)  UPS Input Switchboard Separate UPS Output Switchboards System ‘A’ System ‘B’ 22kV ‘A’ 22kV ‘B’ LV Loads ‘A’ LV Loads ‘B’ The DRUPS Approach Concurrent Maintainability
  • 31. DRUPS2 DRUPS5 DRUPS3 DRUPS4 DRUPS1 UPS Input Switchboard Separate UPS Output Switchboards System ‘A’ System ‘B’ 22kV ‘A’ 22kV ‘B’ LV Loads ‘A’ LV Loads ‘B’ The DRUPS Approach Concurrent Maintainability • Multiple Distribution Paths 
  • 32. DRUPS2 DRUPS5 DRUPS3 DRUPS4 DRUPS1 • Concurrent Maintainability  UPS Input Switchboard Separate UPS Output Switchboards System ‘A’ System ‘B’ 22kV ‘A’ 22kV ‘B’ LV Loads ‘A’ LV Loads ‘B’ The DRUPS Approach Concurrent Maintainability
  • 33. DRUPS2 DRUPS5 DRUPS6 DRUPS3 DRUPS4 DRUPS1 UPS Input Switchboard Separate UPS Output Switchboards System ‘A’ System ‘B’ 22kV ‘A’ 22kV ‘B’ LV Loads ‘A’ LV Loads ‘B’ The DRUPS Approach Concurrent Maintainability • Concurrent Maintainability 
  • 34. DRUPS2 DRUPS5 DRUPS3 DRUPS4 DRUPS1 UPS Input Switchboard Separate UPS Output Switchboards System ‘A’ System ‘B’ 22kV ‘A’ 22kV ‘B’ LV Loads ‘A’ LV Loads ‘B’ The DRUPS Approach Concurrent Maintainability • Concurrent Maintainability 
  • 35. DRUPS2 DRUPS5 DRUPS3 DRUPS4 DRUPS1 UPS Input Switchboard Separate UPS Output Switchboards System ‘A’ System ‘B’ 22kV ‘A’ 22kV ‘B’ LV Loads ‘A’ LV Loads ‘B’ The DRUPS Approach Concurrent Maintainability • Concurrent Maintainability 
  • 36. Bypass Control Panel Q3 Q4 Dual Redundant Modbus+ Networks Unit Control Panel PLC Bypass Control Panel Dual PLCs To other modules Modbus+Network Bypass Control Panel Dual PLCs Unit Control Panel PLC Modbus+Network Fibre Optic Unit Control Panel Unit Control Panel Bypass Control Panel The DRUPS Approach Dual Redundant Control Scheme (Tier III)
  • 37. Increasing lettable space Reducing Total Plantroom Area
  • 38. LV Switchgear Standby Generators Static UPS #1 Static UPS #2 TxTx Increasing lettable space The Static UPS approach • 9MVA Static UPS and Diesel Generator arrangement • Total space required =1,762m²
  • 39. DRUPS Modules, HV Switchgear and Controls SwGr ‘A’ SwGr ‘B’ • 9 MVA Diesel Rotary UPS solution • Total space required = 1,228m² • Total Space saved = 534m² (30% Space Saving) Data Centre Expansion Increasing lettable space The Diesel Rotary UPS approach
  • 40. Calculating Carbon Footprint Operating efficiency is the key to calculating a ‘systems’ Carbon Footprint Increasing Effiency
  • 41. 0 500,000 1,000,000 1,500,000 2,000,000 2,500,000 1 2 3 4 5 6 7 8 9 10 DRUPS Static UPS $1,939K $895K High Efficiency = Low Life Cost Comparative running costs at 50% load based on 9.5 cents/kWhr (AIR 2.5%) for a UPS requirement of 1600kW Cost€’s Year Saving of $1,044K over a 10 Year Period Increasing Effiency
  • 42. • Reduced CAPEX • Simplified the reticulation and reduced fault current • Used fewer components increased the lettable area • Reduced the connections between supply and Load • Provided continuous support to the total facility • Lowered the overall building load • Increased environmental and operating efficiency • Reduced the carbon footprint and OPEX • Increases the overall system reliability • Considered as the ‘GREEN’ sustainable power approach So why HV Hitec DRUPS?
  • 47. Awards Best Building Fit Out Over $20M