SlideShare a Scribd company logo
GPS is a leading provider
of high quality power systems
Global Power Supply
Expansion or Upgrade
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Problems or challenges faced today with
upgrading or expanding an existing data
center and accomplishing this with zero to
little interruption to services and
maintaining business continuity.
Drivers
✦ Efficiency
Newer equipment provides increased efficiency
lowering cost of operations
✦ Reliability
Legacy or “end-of-life” equipment no longer is
serviceable or has spare parts
✦ Increased Capacity
Challenges
✦ N or N+1 Design
Data centers built in the late 90’s to early 2000
using Tier 2 design
✦ Physical Space Constraints
No room to install new until old is removedSelf-Contained 1000kVA UPS System
History of Data Center Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
When our centers were originally built it is often the
case the space allowed for electrical and cooling was
minimized to save money and to allocate space for the
revenue side of the equation, i.e., “white space”.
When we look to expand or upgrade we find that we
lack the needed space. Often it is necessary to remove
the old before installing the new.
✦ 80’s
Data centers were designed for 50W / Sq. Ft.
✦ 90’s
Design was increased to 90W / Sq. Ft.
✦ 2000’s
Design is 150W-200W / Sq. Ft.
✦ Where are we today?
Typical situation today with existing infrastructure.
✦ Equipment is obsolete and inefficient
✦ New equipment represents an opportunity
to become more efficient and bring our
operating costs down
✦ We lack the capacity necessary in either
power or cooling to meet todays and
tomorrows needs
✦ We are faced with a demanding era with
regard to reliability and in many cases N or
N+1 is not enough
✦ Build a new data center
✦ Cost prohibitive
✦ Time frame typically 18 months
✦ Remodel or Expand
✦ Lower cost than new
✦ Shorter timelines
✦ Challenge of little or no interruption
✦ Externalize Modular Solutions
✦ Short speed of deployment
✦ Controlled costs
✦ Revenue generating “white” space
Identify Your Options
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Critical Infrastructure Upgrade
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Processes associated with: Replace existing UPS System
Existing UPS Systems to be replaced Site completed with new UPS Systems
✦ Three phases for a successful project
✦ Discovery
✦ Planning
✦ Execution
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
UPS Replacement N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Utility
✦ Identify is the utility adequate for the expansion or upgrade
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
UPS Replacement N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Utility
✦ Identify is the utility adequate for the expansion or upgrade
✦ Identify is the generator adequate
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
UPS Replacement N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Utility
Electrical Distribution
✦ Identify is the utility adequate for the expansion or upgrade
✦ Identify is the generator adequate
✦ Identify main distribution switchgear capabilities and breaker
configuration
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
UPS Replacement N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Utility
Electrical Distribution
✦ Identify is the utility adequate for the expansion or upgrade
✦ Identify is the generator adequate
✦ Identify main distribution switchgear capabilities and breaker
configuration
✦ Identify and take reading of existing load to determine proper
size of temp UPS
Critical
Loads
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
UPS Replacement N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Utility
Electrical Distribution
✦ Identify is the utility adequate for the expansion or upgrade
✦ Identify is the generator adequate
✦ Identify main distribution switchgear capabilities and breaker
configuration
✦ Identify and take reading of existing load to determine proper
size of temp UPS
✦ Identify physical location of temp UPS
✦ Note rental UPS Systems come in both typical “indoor”
configurations as well as self-contained trailers designed for
installation outside of facility
✦ Note it’s also important to determine the conductors lengths
required for the location of “temp UPS”
Critical
Loads
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
UPS Replacement N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Utility
Electrical Distribution
✦ Identify is the utility adequate for the expansion or upgrade
✦ Identify is the generator adequate
✦ Identify main distribution switchgear capabilities and breaker
configuration
✦ Identify and take reading of existing load to determine proper
size of temp UPS
✦ Identify physical location of temp UPS
✦ Note rental UPS Systems come in both typical “indoor”
configurations as well as self-contained trailers designed for
installation outside of facility
✦ Note it’s also important to determine the conductors lengths
required for the location of “temp UPS”
✦ Temporary UPS installed feeding external maintenance bypass
Critical
Loads
Planning Phase
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
*NEMA 3 R – Cage and frame constructed for ease of movement – sizes up to 6,000A @ 480V
✦ Implementation of Temporary Generators
In stock up to 2 MW with capabilities to parallel
beyond that.
✦ Temporary Switchgear
Up to 6,000A @ 480V
*rentalized NEMA 3R cage and frame.
✦ Temporary UPS Systems
Self-contained UPS trailers or “indoor”
from small 10 kVA up to multi-megawatt.
✦ Power Distribution & Static Switches
UPS Replacement 2N Design
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Replace existing UPS System
Critical
Loads
Static
Bypass
UtilityUtility
Transfer
Switchgear
Alternate Power
Source
Electrical DistributionElectrical Distribution
Transfer
Switchgear
Alternate Power
Source
UPS
N
UPS
+1
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard Output Distribution Switchboard
PDUPDU
Non-Critical
Loads
Non-Critical
Loads
Static
Bypass
Maintenance
Bypass
Maintenance
Bypass
UPS Replacement Discovery Phase
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Project Description: Branch Circuit Discovery
✦ Single Corded Loads
• Implications of shutting down loads
• Controlled shut down and installation of static switch
Most problems are at the branch level. Working in tandem with the IT/Operations survey
and visually inspect each rack and connected loads. Goal is to identify:
✦ Dual Corded Loads
• Plugged into the A and B properly
• Many times we find they are plugged into the same circuit or not distributed properly.
Using an amp probe identify the load on the circuit. Can the circuit accept the entire
load? Often times we find that the load will exceed the circuit.
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
✦ Open feeder breaker from existing
UPS system to output panel
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
✦ Open feeder breaker from existing
UPS system to output panel
✦ Ensure rental UPS has picked up
the load
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
✦ Open feeder breaker from existing
UPS system to output panel
✦ Ensure rental UPS has picked up
the load
✦ Shutdown existing UPS System and
open AC & DC breakers
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
✦ Open feeder breaker from existing
UPS system to output panel
✦ Ensure rental UPS has picked up
the load
✦ Shutdown existing UPS System and
open AC & DC breakers
✦ Temporary UPS is on line and
carrying load transfer building load
back to utility
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
✦ Open feeder breaker from existing
UPS system to output panel
✦ Ensure rental UPS has picked up
the load
✦ Shutdown existing UPS System and
open AC & DC breakers
✦ Temporary UPS is on line and
carrying load transfer building load
back to utility
✦ Existing UPS are ready to be removed
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS System
Removed
UPS Replacement Execution
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Transfer “A” building load to generator
✦ Check rental UPS system and ensure
it is in bypass mode
✦ Place existing UPS system in bypass
✦ Close output breaker from the rental
UPS’s
✦ Open feeder breaker from existing
UPS system to output panel
✦ Ensure rental UPS has picked up
the load
✦ Shutdown existing UPS System and
open AC & DC breakers
✦ Temporary UPS is on line and
carrying load transfer building load
back to utility
✦ Existing UPS are ready to be removed
✦ Repeat these steps for “B” side of
data center
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
Critical
Loads
Static
Bypass
Utility
Transfer
Switchgear
Alternate Power
Source
Electrical Distribution
UPS
N
UPS
+1
Mechanical
Switchgear
Mechanical
Loads
Output Distribution Switchboard
PDU
Non-Critical
Loads
Maintenance
Bypass
Temporary UPS
UPS System
Removed
✦ CIMs - (critical infrastructure module)
✦ IT
✦ Electrical
✦ Cooling
✦ Integrated (“all in one”)
Externalize Your Infrastructure
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Expansion is necessary but time or space pose challenges
CIM Purpose-Built Solutions
Roof Top Installation
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
CIM Purpose-Built Solutions
Raised Platform
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
✦ Scalable by Design
✦ Concurrent Mfg
✦ Less Change Orders
✦ Less On-Site Hours
✦ Factory Built
Benefits of Modular Construction
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Expansion is necessary but time and space won’t allow.
✦ Lower CAPEX
✦ Predictive Schedule
✦ Predictive Cost
✦ Lower Safety Risk
✦ Reduced Onsite Waste
Speed of Deployment
Traditional
Modular
30% to 50%
Faster
Time Savings
GLOBAL POWER SUPPLY
Generating Solutions for Critical Facilities
Critical infrastructure modules can be deployed in 90 days.
GLOBAL POWER SUPPLY
Thank You
✦ Buy, Sell, Rent & Lease
✦ New, Surplus & Refurbished
✦ Generators, UPS & Cooling
www.globalpwr.com
(800) 706-0906
Any Questions?

More Related Content

What's hot

Residential Electrical Wiring Systems Basics
Residential Electrical Wiring Systems Basics Residential Electrical Wiring Systems Basics
Residential Electrical Wiring Systems Basics
Dr.Raja R
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
Hemendra Kumar Rajput
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
vishalgohel12195
 
Lightning protection system
Lightning protection system Lightning protection system
Lightning protection system
anjali s
 
Designing an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyDesigning an Uninterruptible Power Supply
Designing an Uninterruptible Power Supply
Leonardo ENERGY
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
Ameen San
 
FIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATIONFIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATION
ASGHAR KHALIL
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
Milind Punj
 
Fundamentals of Fire Alarm System
Fundamentals of Fire Alarm SystemFundamentals of Fire Alarm System
Fundamentals of Fire Alarm System
Subhendu Bikash Santra
 
Safe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and SwitchgearSafe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and Switchgear
Living Online
 
Protection basic
Protection basicProtection basic
Protection basic
BHAGWAN PRASAD
 
circuit breaker
circuit breakercircuit breaker
circuit breaker
pratikguptateddy
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
rohit nadella
 
Lightning protection
Lightning protectionLightning protection
Lightning protection
Vincent Wedelich, PE MBA
 
Relay
RelayRelay
Er. rahul sharma circuit breaker
Er. rahul sharma circuit breakerEr. rahul sharma circuit breaker
Er. rahul sharma circuit breaker
Rahul Ruddra
 
Electric substation
Electric substation Electric substation
Electric substation
ANNU KUMAR
 

What's hot (20)

Overhead lines electrical_hazards
Overhead lines electrical_hazardsOverhead lines electrical_hazards
Overhead lines electrical_hazards
 
Residential Electrical Wiring Systems Basics
Residential Electrical Wiring Systems Basics Residential Electrical Wiring Systems Basics
Residential Electrical Wiring Systems Basics
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
 
Lightning protection system
Lightning protection system Lightning protection system
Lightning protection system
 
Designing an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyDesigning an Uninterruptible Power Supply
Designing an Uninterruptible Power Supply
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
 
FIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATIONFIRE FIGHTING PRESENTATION
FIRE FIGHTING PRESENTATION
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
 
Fundamentals of Fire Alarm System
Fundamentals of Fire Alarm SystemFundamentals of Fire Alarm System
Fundamentals of Fire Alarm System
 
Safe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and SwitchgearSafe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and Switchgear
 
Protection basic
Protection basicProtection basic
Protection basic
 
circuit breaker
circuit breakercircuit breaker
circuit breaker
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
 
Lightning protection
Lightning protectionLightning protection
Lightning protection
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
Relay
RelayRelay
Relay
 
Er. rahul sharma circuit breaker
Er. rahul sharma circuit breakerEr. rahul sharma circuit breaker
Er. rahul sharma circuit breaker
 
Electric substation
Electric substation Electric substation
Electric substation
 

Viewers also liked

Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...
Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...
Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...Dony Afriansyah
 
Design Research for Emerging Markets
Design Research for Emerging MarketsDesign Research for Emerging Markets
Design Research for Emerging Markets
Andrew Harder
 
Should Colocation Data Centers Fear Consolidation? (SlideShare)
Should Colocation Data Centers Fear Consolidation? (SlideShare)Should Colocation Data Centers Fear Consolidation? (SlideShare)
Should Colocation Data Centers Fear Consolidation? (SlideShare)
SP Home Run Inc.
 
Can Data Center Consultants Build Enterprise Value? (SlideShare)
Can Data Center Consultants Build Enterprise Value? (SlideShare)Can Data Center Consultants Build Enterprise Value? (SlideShare)
Can Data Center Consultants Build Enterprise Value? (SlideShare)
SP Home Run Inc.
 
Lever Company Presentation January 2012 New
Lever Company Presentation January 2012 NewLever Company Presentation January 2012 New
Lever Company Presentation January 2012 New
Stefano Bruno
 
Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...
Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...
Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...
SP Home Run Inc.
 
Which New Jersey Data Centers Embrace Managed Services? (SlideShare)
Which New Jersey Data Centers Embrace Managed Services? (SlideShare)Which New Jersey Data Centers Embrace Managed Services? (SlideShare)
Which New Jersey Data Centers Embrace Managed Services? (SlideShare)
SP Home Run Inc.
 

Viewers also liked (7)

Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...
Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...
Bab ii bab i sistem kerja ups (uninterruptible power system) pada central con...
 
Design Research for Emerging Markets
Design Research for Emerging MarketsDesign Research for Emerging Markets
Design Research for Emerging Markets
 
Should Colocation Data Centers Fear Consolidation? (SlideShare)
Should Colocation Data Centers Fear Consolidation? (SlideShare)Should Colocation Data Centers Fear Consolidation? (SlideShare)
Should Colocation Data Centers Fear Consolidation? (SlideShare)
 
Can Data Center Consultants Build Enterprise Value? (SlideShare)
Can Data Center Consultants Build Enterprise Value? (SlideShare)Can Data Center Consultants Build Enterprise Value? (SlideShare)
Can Data Center Consultants Build Enterprise Value? (SlideShare)
 
Lever Company Presentation January 2012 New
Lever Company Presentation January 2012 NewLever Company Presentation January 2012 New
Lever Company Presentation January 2012 New
 
Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...
Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...
Comparing Software Defined Data Centers vs. Traditional Data Centers (SlideSh...
 
Which New Jersey Data Centers Embrace Managed Services? (SlideShare)
Which New Jersey Data Centers Embrace Managed Services? (SlideShare)Which New Jersey Data Centers Embrace Managed Services? (SlideShare)
Which New Jersey Data Centers Embrace Managed Services? (SlideShare)
 

Similar to Data Center UPS System Upgrade

Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722
Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722
Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722Chris Dow
 
Energy Storage solutions
Energy Storage solutionsEnergy Storage solutions
Energy Storage solutions
Schneider Electric
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
Schneider Electric
 
An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...
An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...
An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...
Sam Geoff
 
Low Complexity + Low Cost = High Availability
Low Complexity + Low Cost = High AvailabilityLow Complexity + Low Cost = High Availability
Low Complexity + Low Cost = High Availability
Uptime Institute
 
Schneider Electric Services_Modernization and Upgrade Solutions.pptx
Schneider Electric Services_Modernization and Upgrade Solutions.pptxSchneider Electric Services_Modernization and Upgrade Solutions.pptx
Schneider Electric Services_Modernization and Upgrade Solutions.pptx
Schneider Electric
 
Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power
 
Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design Considerations
Schneider Electric
 
Gps UPS Power When You Need It
Gps UPS Power When You Need ItGps UPS Power When You Need It
Gps UPS Power When You Need It
Global Power Supply
 
Gps 2018
Gps 2018Gps 2018
2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...
2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...
2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...
Sandia National Laboratories: Energy & Climate: Renewables
 
elcomponics
elcomponicselcomponics
elcomponics
pselcom
 
Off grid rooftop pv – elsol solar
Off grid rooftop pv – elsol solarOff grid rooftop pv – elsol solar
Off grid rooftop pv – elsol solarelsolsolar
 
All products brochure
All products brochureAll products brochure
All products brochureJason Becker
 
toaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdf
toaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdftoaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdf
toaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdf
JyotishkMalviya
 
Hacking the Conventional Data Center Infrastructure
Hacking the Conventional  Data Center InfrastructureHacking the Conventional  Data Center Infrastructure
Hacking the Conventional Data Center Infrastructure
Schneider Electric
 
KinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementKinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementRay Salmons
 
Greg Thomson - Community Microgrid - (17 oct 2014)
Greg Thomson - Community Microgrid - (17 oct 2014)Greg Thomson - Community Microgrid - (17 oct 2014)
Greg Thomson - Community Microgrid - (17 oct 2014)
annphancock
 
Versatile control of unidirectional ac–dc boost converters for power quality ...
Versatile control of unidirectional ac–dc boost converters for power quality ...Versatile control of unidirectional ac–dc boost converters for power quality ...
Versatile control of unidirectional ac–dc boost converters for power quality ...
IISTech2015
 

Similar to Data Center UPS System Upgrade (20)

Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722
Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722
Case Study - Fujitsu_Malaga_Perth - (TIA 942) - 20110722
 
Energy Storage solutions
Energy Storage solutionsEnergy Storage solutions
Energy Storage solutions
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
 
An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...
An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...
An Introduction to the Power Module Manufacturers XY Power-A Professional EV ...
 
Low Complexity + Low Cost = High Availability
Low Complexity + Low Cost = High AvailabilityLow Complexity + Low Cost = High Availability
Low Complexity + Low Cost = High Availability
 
Schneider Electric Services_Modernization and Upgrade Solutions.pptx
Schneider Electric Services_Modernization and Upgrade Solutions.pptxSchneider Electric Services_Modernization and Upgrade Solutions.pptx
Schneider Electric Services_Modernization and Upgrade Solutions.pptx
 
Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...
 
Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design Considerations
 
Gps UPS Power When You Need It
Gps UPS Power When You Need ItGps UPS Power When You Need It
Gps UPS Power When You Need It
 
Gps 2018
Gps 2018Gps 2018
Gps 2018
 
2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...
2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...
2014 PV Distribution System Modeling Workshop: High Penetration PV Control Co...
 
elcomponics
elcomponicselcomponics
elcomponics
 
ComRent Capabilities Overview v10 Solar
ComRent Capabilities Overview v10 SolarComRent Capabilities Overview v10 Solar
ComRent Capabilities Overview v10 Solar
 
Off grid rooftop pv – elsol solar
Off grid rooftop pv – elsol solarOff grid rooftop pv – elsol solar
Off grid rooftop pv – elsol solar
 
All products brochure
All products brochureAll products brochure
All products brochure
 
toaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdf
toaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdftoaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdf
toaz.info-foot-step-ppt-pr_a0b68b5bda776b607c301df6f3886c6a.pdf
 
Hacking the Conventional Data Center Infrastructure
Hacking the Conventional  Data Center InfrastructureHacking the Conventional  Data Center Infrastructure
Hacking the Conventional Data Center Infrastructure
 
KinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementKinetIQ Solutions Capability Statement
KinetIQ Solutions Capability Statement
 
Greg Thomson - Community Microgrid - (17 oct 2014)
Greg Thomson - Community Microgrid - (17 oct 2014)Greg Thomson - Community Microgrid - (17 oct 2014)
Greg Thomson - Community Microgrid - (17 oct 2014)
 
Versatile control of unidirectional ac–dc boost converters for power quality ...
Versatile control of unidirectional ac–dc boost converters for power quality ...Versatile control of unidirectional ac–dc boost converters for power quality ...
Versatile control of unidirectional ac–dc boost converters for power quality ...
 

Recently uploaded

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Data Center UPS System Upgrade

  • 1.
  • 2. GPS is a leading provider of high quality power systems Global Power Supply
  • 3. Expansion or Upgrade GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Problems or challenges faced today with upgrading or expanding an existing data center and accomplishing this with zero to little interruption to services and maintaining business continuity. Drivers ✦ Efficiency Newer equipment provides increased efficiency lowering cost of operations ✦ Reliability Legacy or “end-of-life” equipment no longer is serviceable or has spare parts ✦ Increased Capacity Challenges ✦ N or N+1 Design Data centers built in the late 90’s to early 2000 using Tier 2 design ✦ Physical Space Constraints No room to install new until old is removedSelf-Contained 1000kVA UPS System
  • 4. History of Data Center Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities When our centers were originally built it is often the case the space allowed for electrical and cooling was minimized to save money and to allocate space for the revenue side of the equation, i.e., “white space”. When we look to expand or upgrade we find that we lack the needed space. Often it is necessary to remove the old before installing the new. ✦ 80’s Data centers were designed for 50W / Sq. Ft. ✦ 90’s Design was increased to 90W / Sq. Ft. ✦ 2000’s Design is 150W-200W / Sq. Ft. ✦ Where are we today? Typical situation today with existing infrastructure. ✦ Equipment is obsolete and inefficient ✦ New equipment represents an opportunity to become more efficient and bring our operating costs down ✦ We lack the capacity necessary in either power or cooling to meet todays and tomorrows needs ✦ We are faced with a demanding era with regard to reliability and in many cases N or N+1 is not enough
  • 5. ✦ Build a new data center ✦ Cost prohibitive ✦ Time frame typically 18 months ✦ Remodel or Expand ✦ Lower cost than new ✦ Shorter timelines ✦ Challenge of little or no interruption ✦ Externalize Modular Solutions ✦ Short speed of deployment ✦ Controlled costs ✦ Revenue generating “white” space Identify Your Options GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities
  • 6. Critical Infrastructure Upgrade GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Processes associated with: Replace existing UPS System Existing UPS Systems to be replaced Site completed with new UPS Systems ✦ Three phases for a successful project ✦ Discovery ✦ Planning ✦ Execution
  • 7. Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass UPS Replacement N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Utility ✦ Identify is the utility adequate for the expansion or upgrade
  • 8. Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass UPS Replacement N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Utility ✦ Identify is the utility adequate for the expansion or upgrade ✦ Identify is the generator adequate
  • 9. Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass UPS Replacement N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Utility Electrical Distribution ✦ Identify is the utility adequate for the expansion or upgrade ✦ Identify is the generator adequate ✦ Identify main distribution switchgear capabilities and breaker configuration
  • 10. Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass UPS Replacement N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Utility Electrical Distribution ✦ Identify is the utility adequate for the expansion or upgrade ✦ Identify is the generator adequate ✦ Identify main distribution switchgear capabilities and breaker configuration ✦ Identify and take reading of existing load to determine proper size of temp UPS Critical Loads
  • 11. Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass UPS Replacement N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Utility Electrical Distribution ✦ Identify is the utility adequate for the expansion or upgrade ✦ Identify is the generator adequate ✦ Identify main distribution switchgear capabilities and breaker configuration ✦ Identify and take reading of existing load to determine proper size of temp UPS ✦ Identify physical location of temp UPS ✦ Note rental UPS Systems come in both typical “indoor” configurations as well as self-contained trailers designed for installation outside of facility ✦ Note it’s also important to determine the conductors lengths required for the location of “temp UPS” Critical Loads
  • 12. Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass UPS Replacement N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Utility Electrical Distribution ✦ Identify is the utility adequate for the expansion or upgrade ✦ Identify is the generator adequate ✦ Identify main distribution switchgear capabilities and breaker configuration ✦ Identify and take reading of existing load to determine proper size of temp UPS ✦ Identify physical location of temp UPS ✦ Note rental UPS Systems come in both typical “indoor” configurations as well as self-contained trailers designed for installation outside of facility ✦ Note it’s also important to determine the conductors lengths required for the location of “temp UPS” ✦ Temporary UPS installed feeding external maintenance bypass Critical Loads
  • 13. Planning Phase GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities *NEMA 3 R – Cage and frame constructed for ease of movement – sizes up to 6,000A @ 480V ✦ Implementation of Temporary Generators In stock up to 2 MW with capabilities to parallel beyond that. ✦ Temporary Switchgear Up to 6,000A @ 480V *rentalized NEMA 3R cage and frame. ✦ Temporary UPS Systems Self-contained UPS trailers or “indoor” from small 10 kVA up to multi-megawatt. ✦ Power Distribution & Static Switches
  • 14. UPS Replacement 2N Design GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Replace existing UPS System Critical Loads Static Bypass UtilityUtility Transfer Switchgear Alternate Power Source Electrical DistributionElectrical Distribution Transfer Switchgear Alternate Power Source UPS N UPS +1 UPS N UPS +1 Mechanical Switchgear Mechanical Switchgear Mechanical Loads Output Distribution Switchboard Output Distribution Switchboard PDUPDU Non-Critical Loads Non-Critical Loads Static Bypass Maintenance Bypass Maintenance Bypass
  • 15. UPS Replacement Discovery Phase GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Project Description: Branch Circuit Discovery ✦ Single Corded Loads • Implications of shutting down loads • Controlled shut down and installation of static switch Most problems are at the branch level. Working in tandem with the IT/Operations survey and visually inspect each rack and connected loads. Goal is to identify: ✦ Dual Corded Loads • Plugged into the A and B properly • Many times we find they are plugged into the same circuit or not distributed properly. Using an amp probe identify the load on the circuit. Can the circuit accept the entire load? Often times we find that the load will exceed the circuit.
  • 16. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 17. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 18. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 19. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 20. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s ✦ Open feeder breaker from existing UPS system to output panel Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 21. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s ✦ Open feeder breaker from existing UPS system to output panel ✦ Ensure rental UPS has picked up the load Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 22. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s ✦ Open feeder breaker from existing UPS system to output panel ✦ Ensure rental UPS has picked up the load ✦ Shutdown existing UPS System and open AC & DC breakers Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 23. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s ✦ Open feeder breaker from existing UPS system to output panel ✦ Ensure rental UPS has picked up the load ✦ Shutdown existing UPS System and open AC & DC breakers ✦ Temporary UPS is on line and carrying load transfer building load back to utility Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS
  • 24. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s ✦ Open feeder breaker from existing UPS system to output panel ✦ Ensure rental UPS has picked up the load ✦ Shutdown existing UPS System and open AC & DC breakers ✦ Temporary UPS is on line and carrying load transfer building load back to utility ✦ Existing UPS are ready to be removed Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS UPS System Removed
  • 25. UPS Replacement Execution GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities ✦ Transfer “A” building load to generator ✦ Check rental UPS system and ensure it is in bypass mode ✦ Place existing UPS system in bypass ✦ Close output breaker from the rental UPS’s ✦ Open feeder breaker from existing UPS system to output panel ✦ Ensure rental UPS has picked up the load ✦ Shutdown existing UPS System and open AC & DC breakers ✦ Temporary UPS is on line and carrying load transfer building load back to utility ✦ Existing UPS are ready to be removed ✦ Repeat these steps for “B” side of data center Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS Critical Loads Static Bypass Utility Transfer Switchgear Alternate Power Source Electrical Distribution UPS N UPS +1 Mechanical Switchgear Mechanical Loads Output Distribution Switchboard PDU Non-Critical Loads Maintenance Bypass Temporary UPS UPS System Removed
  • 26. ✦ CIMs - (critical infrastructure module) ✦ IT ✦ Electrical ✦ Cooling ✦ Integrated (“all in one”) Externalize Your Infrastructure GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Expansion is necessary but time or space pose challenges
  • 27. CIM Purpose-Built Solutions Roof Top Installation GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities
  • 28. CIM Purpose-Built Solutions Raised Platform GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities
  • 29. ✦ Scalable by Design ✦ Concurrent Mfg ✦ Less Change Orders ✦ Less On-Site Hours ✦ Factory Built Benefits of Modular Construction GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Expansion is necessary but time and space won’t allow. ✦ Lower CAPEX ✦ Predictive Schedule ✦ Predictive Cost ✦ Lower Safety Risk ✦ Reduced Onsite Waste
  • 30. Speed of Deployment Traditional Modular 30% to 50% Faster Time Savings GLOBAL POWER SUPPLY Generating Solutions for Critical Facilities Critical infrastructure modules can be deployed in 90 days.
  • 31. GLOBAL POWER SUPPLY Thank You ✦ Buy, Sell, Rent & Lease ✦ New, Surplus & Refurbished ✦ Generators, UPS & Cooling www.globalpwr.com (800) 706-0906 Any Questions?