SlideShare a Scribd company logo
1 of 33
1
Project
Implementation and
management
Module 5 Session 7
2
Summary
 This session covers the aspects of project
implementation and management from
activation onwards, including factors that affect
project implementation.
 Project management as a concept is
considered.
 The characteristic of a good project manager
are discussed.
3
Contents
 Introduction to Project Implementation
 Project Activation
 Project Operation
 Approaches to Project Implementation
 Project Implementation Plan
 Factors Affecting Project Implementation
 Project Management Defined
 Aspects of Project Management
 Characteristics of a good Project Manager
4
Project Implementation
 Process whereby “project inputs are
converted to project outputs”. May be looked
at as:
 Putting in action the activities of the project.
 Putting into practice what was proposed in the
project document (i.e. transforming the
project proposal into the actual project.)
 Management of the project or executing the
project intentions.
5
Project Implementation (cont.)
 Implementation usually done by implementing
agency (organization) that prepared the project
and received funding for it.
 Other organizations that participate in the
implementation of the project
 by way of collaboration, say by according good
working relationship, extending technical advice or
seconding their staff to the project
are referred to as co-operating agencies.
6
Project Implementation phase
involves:
 Project activation, and
 Project operation
Project activation
 This means making arrangements to have the
project started. It involves coordination and
allocation of resources to make project operational.
Project operation
 This is practical management of a project. Here,
project inputs are transformed into outputs to
achieve immediate objectives.
7
Project operation and
maintenance
Operation and maintenance
 To attain value and maximum returns, the
district/municipality or the beneficiaries organize
for the facility to have the project properly
managed and maintained regularly.
 An operation and maintenance manual is
prepared by the contractor and handed to the
district / beneficiaries.
8
Approaches to project
implementation
Top-down approach
 Implementation mainly done by agencies from
outside the community with limited involvement by
the beneficiaries.
Bottom-up approach
 Beneficiaries implement the project. Outside
agencies may provide the financial resources and
technical assistance.
Collaborative participatory approach
 Both top-down and bottom-up approaches to
project implementation are applied in the process.
9
Project implementation plan
(PIP)
 If PIP not carried out during the project
design process and embodied in the
project documents, it is carried out at the
project activation stage.
10
Project implementation plan
includes:
a) The project implementation schedule
This is concerned with:
 What activities can produce expected
project outputs?
 What is the sequence of these activities?
 What is the time frame for these activities?
 Who will be responsible for carrying out
each activity?
11
Project implementation plan
includes:
 The following methods may be used to
answer the above questions:
 Gantt chart
 Critical Path Method (CPM) or Net work
analysis
 Project Evaluation and Review Techniques
(PERT)
 Simple formats
12
What is a GANTT Chart?
 The Gantt chart is also referred to as the
progress chart.
 It is a chart showing the timing of project
activities using horizontal bars.
 It is one of the techniques of project
scheduling, which depicts the frequency of
activities and determines the period of time
for implementation.
13
How to determine a GANTT chart
 Determine the parts or implementation
phases of the project and the sequence in
which the associated activities shall be
carried out
 Then estimate the amount of time required
for each activity
 List the activities that can be carried out at
the same time and identify those to be carried
out sequentially
14
How to construct a GANTT chart
 Time represented on the horizontal axis, and
activities on the vertical axis.
 Bars are entered to indicate the time period
allocated for each activity and the state of
progress at any particular point in time.
15
Example: Maize farming project
Activity
 Marketing
 Threshing
 Harvesting
 Weeding
 Planting
 Preparing seedbed
J F M A M J J A S O N D
Time period/ months
16
The Simple Format
ACTIVITY STARTING
DATE
ENDING
DATE
COST RESPONSIBLE
PERSON
REMARKS
- Preparing seed bed
- Planning
- Weeding
- Harvesting
- Storage
- Threshing
- Marketing
17
Practical
Develop
 a Gantt chart
 Simple Format
project implementation schedules in relation
to the identified projects in the project
identification session.
18
Project implementation plan
(cont.)
b) The role of the implementing agency
 The specific responsibilities of the key staff
during project implementation and
monitoring are outlined.
c) Beneficiary participation
 The involvement of the beneficiaries in
planning and implementation and what is
expected of them is spelt out.
19
Project implementation plan
(cont.)
d) Organizational structure and staffing
Here the following are sought:
 Project structure for purposes of management
 Qualifications and skills for the staff
 Job descriptions and specifications for the staff
 Technical assistance if needed
e) Financial management
This looks at funds management, accounting
period, financial reports and statements and how
often they will be made?
20
Project implementation plan
(cont.)
f) Reporting system
This looks at who will be reporting to whom and
how often. There is need to design standard
reporting formats.
g) Sustainability
The concept of sustainability is based on belief that
project should result in benefits that have lasting
effect. Project should be sustained beyond the life
of funding - especially if it is a grant.
Project should not exhaust the available resources
like raw materials and labor.
21
Project implementation plan
(cont.)
Time control and remedial action
Time taken to implement project activities is one
measure of successfulness of supervision or
monitoring of project implementation.
Supervisor pays particular attention to time
control measures, time scheduling and its
supervision, time extension and postponement,
damages for non-completion and defect or
warranty period.
22
Project implementation plan
(cont.)
Supervision of implementation of project
schedule
This involves a set of checks and balances to
ensure that the schedule is being adhered to.
To ensure that the time schedule is being
adhered to, the project activity time listing can be
of great importance.
23
Project Activity Time Listing
Activity
earliest time
Activity
latest time
Activity
code
Activity
Description
Activity
duration
Start Finish Start Finish
Progress
remark
24
Practical
 Using the Project Activity Time Listing,
develop a Project Activity Time Listing table
in relation to the Identified project in project
identification session, and fill it in.
25
Factors affecting project
implementation
 Factors that lead to
success of projects
 Political Commitment
 Simplicity of Design
 Careful preparation
 Good management
 Involvement of
beneficiaries/community
 Factors and problems
that lead to failure of
projects
 Financial Problems
 Management problems
 Technical problems
 Political problems
26
Factors affecting project
implementation
Other typical implementation problems
 Poor scheduling of projects leading to delays in
 Poor scheduling of projects leading to delays in
implementation.
 Misallocation of funds
 Delay and sometimes lack of counterpart funding
 Lack of accountability and transparency
 Bureaucracy in decision-making.
 Selfishness/nepotism/favoritism by some project
managers.
27
Factors affecting project
implementation
Other typical implementation problems (cont.)
 Weak monitoring systems
 Natural calamities like drought, earthquakes,
landslides, and hailstorms.
 Policy changes
 Migration of beneficiaries
 Lack of team work
 Lack of incentives for implementers.
 etc
28
Project management
Management may be defined as;
 Getting things done from the available
resources, the way you want them to be done.
Project management defined
 Project Management is an all-embracing term
covering the management of every detail of a
project (Project cycle) and may be defined as,
“the process of planning and directing a project
from its inception to its final completion”.
29
Project management (cont.)
Project management decisions - a necessary
function for setting up a project. It is concerned with:
 Forecasting
 Setting objectives
 Policy making
Planning - determines success/failure of project. It
has three (3) main aspects:
 Programming
 Scheduling and
 Budgeting
30
Project management (cont.)
Project control - To control is to compare
actual with planned achievements and take action
to correct any adverse deviations. It involves:
 Plans of Operation
These are the result of the planning process of Project
management.
 Review and Updating
Review is necessary to determine whether the project is
proceeding according to plan or not. Updating is
recording the state of the project as shown by the
reviews, or of making amendments.
31
Project management (cont.)
Project Action - When review has shown a
project to be deviating from plan, action is
required to restore the operation to its planned
characteristics.
32
A good project manager should:
 have working knowledge in several fields
 be able to understand general managerial
problems
 have active interest in training and
developing subordinates
 be able to delegate some tasks to
subordinates
Characteristics of a good
project manager
33
A good project manager should:
 know the project and understand its objectives
 know the systematic process for managing
projects
 be able to answer the following questions:
 What is the project for?
 Why is it required?
 Whom does it serve?
 How is it justified?
 How is it going to be used?
Characteristics of a good
project manager (cont.)

More Related Content

What's hot

What's hot (20)

05. Project And Organizational Structure
05. Project And Organizational Structure05. Project And Organizational Structure
05. Project And Organizational Structure
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENT
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
project appraisal
project appraisal project appraisal
project appraisal
 
Chap03 the project management process groups
Chap03 the project management process groupsChap03 the project management process groups
Chap03 the project management process groups
 
Project Management
Project ManagementProject Management
Project Management
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and Analysis
 
Planning
PlanningPlanning
Planning
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Project termination
Project terminationProject termination
Project termination
 
Presentation on project appraisal
Presentation on project appraisalPresentation on project appraisal
Presentation on project appraisal
 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
 
Ppt on project appraisal
Ppt on project appraisalPpt on project appraisal
Ppt on project appraisal
 
Project organization
Project organizationProject organization
Project organization
 
Project management structures
Project management structuresProject management structures
Project management structures
 
Project monitoring
Project monitoringProject monitoring
Project monitoring
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 

Similar to Project implementation

Project implimentation
Project implimentationProject implimentation
Project implimentationMazhar Poohlah
 
Project integration management
Project integration managementProject integration management
Project integration managementEhsan Ullah
 
Introduction Construction Planning and Management
Introduction Construction Planning and Management Introduction Construction Planning and Management
Introduction Construction Planning and Management Akhil Shetty
 
ASSIGNMENT-1 PROFESSIONAL PRACTICE
ASSIGNMENT-1 PROFESSIONAL PRACTICEASSIGNMENT-1 PROFESSIONAL PRACTICE
ASSIGNMENT-1 PROFESSIONAL PRACTICEMichele Thomas
 
Arega Siyum D/r revised
Arega  Siyum D/r revisedArega  Siyum D/r revised
Arega Siyum D/r revisedFiker Love
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Managementchaitanyakrsk
 
Za project & project cycle management
Za   project & project cycle managementZa   project & project cycle management
Za project & project cycle managementhamza khwaja
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptAynetuTerefe2
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 NotesSamarthVarpe
 
Project management.docx
Project management.docxProject management.docx
Project management.docxHumaRazi1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
Project Management
Project ManagementProject Management
Project Managementirfan ali
 

Similar to Project implementation (20)

Project implimentation
Project implimentationProject implimentation
Project implimentation
 
Project Management
Project ManagementProject Management
Project Management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Introduction Construction Planning and Management
Introduction Construction Planning and Management Introduction Construction Planning and Management
Introduction Construction Planning and Management
 
Project management revised
Project management revisedProject management revised
Project management revised
 
ASSIGNMENT-1 PROFESSIONAL PRACTICE
ASSIGNMENT-1 PROFESSIONAL PRACTICEASSIGNMENT-1 PROFESSIONAL PRACTICE
ASSIGNMENT-1 PROFESSIONAL PRACTICE
 
Arega Siyum D/r revised
Arega  Siyum D/r revisedArega  Siyum D/r revised
Arega Siyum D/r revised
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
Za project & project cycle management
Za   project & project cycle managementZa   project & project cycle management
Za project & project cycle management
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).ppt
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project management
Project managementProject management
Project management
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
 
Project management.docx
Project management.docxProject management.docx
Project management.docx
 
Project management – standard for today´s modern company
Project management – standard for today´s modern companyProject management – standard for today´s modern company
Project management – standard for today´s modern company
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management
Project ManagementProject Management
Project Management
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 

Project implementation

  • 2. 2 Summary  This session covers the aspects of project implementation and management from activation onwards, including factors that affect project implementation.  Project management as a concept is considered.  The characteristic of a good project manager are discussed.
  • 3. 3 Contents  Introduction to Project Implementation  Project Activation  Project Operation  Approaches to Project Implementation  Project Implementation Plan  Factors Affecting Project Implementation  Project Management Defined  Aspects of Project Management  Characteristics of a good Project Manager
  • 4. 4 Project Implementation  Process whereby “project inputs are converted to project outputs”. May be looked at as:  Putting in action the activities of the project.  Putting into practice what was proposed in the project document (i.e. transforming the project proposal into the actual project.)  Management of the project or executing the project intentions.
  • 5. 5 Project Implementation (cont.)  Implementation usually done by implementing agency (organization) that prepared the project and received funding for it.  Other organizations that participate in the implementation of the project  by way of collaboration, say by according good working relationship, extending technical advice or seconding their staff to the project are referred to as co-operating agencies.
  • 6. 6 Project Implementation phase involves:  Project activation, and  Project operation Project activation  This means making arrangements to have the project started. It involves coordination and allocation of resources to make project operational. Project operation  This is practical management of a project. Here, project inputs are transformed into outputs to achieve immediate objectives.
  • 7. 7 Project operation and maintenance Operation and maintenance  To attain value and maximum returns, the district/municipality or the beneficiaries organize for the facility to have the project properly managed and maintained regularly.  An operation and maintenance manual is prepared by the contractor and handed to the district / beneficiaries.
  • 8. 8 Approaches to project implementation Top-down approach  Implementation mainly done by agencies from outside the community with limited involvement by the beneficiaries. Bottom-up approach  Beneficiaries implement the project. Outside agencies may provide the financial resources and technical assistance. Collaborative participatory approach  Both top-down and bottom-up approaches to project implementation are applied in the process.
  • 9. 9 Project implementation plan (PIP)  If PIP not carried out during the project design process and embodied in the project documents, it is carried out at the project activation stage.
  • 10. 10 Project implementation plan includes: a) The project implementation schedule This is concerned with:  What activities can produce expected project outputs?  What is the sequence of these activities?  What is the time frame for these activities?  Who will be responsible for carrying out each activity?
  • 11. 11 Project implementation plan includes:  The following methods may be used to answer the above questions:  Gantt chart  Critical Path Method (CPM) or Net work analysis  Project Evaluation and Review Techniques (PERT)  Simple formats
  • 12. 12 What is a GANTT Chart?  The Gantt chart is also referred to as the progress chart.  It is a chart showing the timing of project activities using horizontal bars.  It is one of the techniques of project scheduling, which depicts the frequency of activities and determines the period of time for implementation.
  • 13. 13 How to determine a GANTT chart  Determine the parts or implementation phases of the project and the sequence in which the associated activities shall be carried out  Then estimate the amount of time required for each activity  List the activities that can be carried out at the same time and identify those to be carried out sequentially
  • 14. 14 How to construct a GANTT chart  Time represented on the horizontal axis, and activities on the vertical axis.  Bars are entered to indicate the time period allocated for each activity and the state of progress at any particular point in time.
  • 15. 15 Example: Maize farming project Activity  Marketing  Threshing  Harvesting  Weeding  Planting  Preparing seedbed J F M A M J J A S O N D Time period/ months
  • 16. 16 The Simple Format ACTIVITY STARTING DATE ENDING DATE COST RESPONSIBLE PERSON REMARKS - Preparing seed bed - Planning - Weeding - Harvesting - Storage - Threshing - Marketing
  • 17. 17 Practical Develop  a Gantt chart  Simple Format project implementation schedules in relation to the identified projects in the project identification session.
  • 18. 18 Project implementation plan (cont.) b) The role of the implementing agency  The specific responsibilities of the key staff during project implementation and monitoring are outlined. c) Beneficiary participation  The involvement of the beneficiaries in planning and implementation and what is expected of them is spelt out.
  • 19. 19 Project implementation plan (cont.) d) Organizational structure and staffing Here the following are sought:  Project structure for purposes of management  Qualifications and skills for the staff  Job descriptions and specifications for the staff  Technical assistance if needed e) Financial management This looks at funds management, accounting period, financial reports and statements and how often they will be made?
  • 20. 20 Project implementation plan (cont.) f) Reporting system This looks at who will be reporting to whom and how often. There is need to design standard reporting formats. g) Sustainability The concept of sustainability is based on belief that project should result in benefits that have lasting effect. Project should be sustained beyond the life of funding - especially if it is a grant. Project should not exhaust the available resources like raw materials and labor.
  • 21. 21 Project implementation plan (cont.) Time control and remedial action Time taken to implement project activities is one measure of successfulness of supervision or monitoring of project implementation. Supervisor pays particular attention to time control measures, time scheduling and its supervision, time extension and postponement, damages for non-completion and defect or warranty period.
  • 22. 22 Project implementation plan (cont.) Supervision of implementation of project schedule This involves a set of checks and balances to ensure that the schedule is being adhered to. To ensure that the time schedule is being adhered to, the project activity time listing can be of great importance.
  • 23. 23 Project Activity Time Listing Activity earliest time Activity latest time Activity code Activity Description Activity duration Start Finish Start Finish Progress remark
  • 24. 24 Practical  Using the Project Activity Time Listing, develop a Project Activity Time Listing table in relation to the Identified project in project identification session, and fill it in.
  • 25. 25 Factors affecting project implementation  Factors that lead to success of projects  Political Commitment  Simplicity of Design  Careful preparation  Good management  Involvement of beneficiaries/community  Factors and problems that lead to failure of projects  Financial Problems  Management problems  Technical problems  Political problems
  • 26. 26 Factors affecting project implementation Other typical implementation problems  Poor scheduling of projects leading to delays in  Poor scheduling of projects leading to delays in implementation.  Misallocation of funds  Delay and sometimes lack of counterpart funding  Lack of accountability and transparency  Bureaucracy in decision-making.  Selfishness/nepotism/favoritism by some project managers.
  • 27. 27 Factors affecting project implementation Other typical implementation problems (cont.)  Weak monitoring systems  Natural calamities like drought, earthquakes, landslides, and hailstorms.  Policy changes  Migration of beneficiaries  Lack of team work  Lack of incentives for implementers.  etc
  • 28. 28 Project management Management may be defined as;  Getting things done from the available resources, the way you want them to be done. Project management defined  Project Management is an all-embracing term covering the management of every detail of a project (Project cycle) and may be defined as, “the process of planning and directing a project from its inception to its final completion”.
  • 29. 29 Project management (cont.) Project management decisions - a necessary function for setting up a project. It is concerned with:  Forecasting  Setting objectives  Policy making Planning - determines success/failure of project. It has three (3) main aspects:  Programming  Scheduling and  Budgeting
  • 30. 30 Project management (cont.) Project control - To control is to compare actual with planned achievements and take action to correct any adverse deviations. It involves:  Plans of Operation These are the result of the planning process of Project management.  Review and Updating Review is necessary to determine whether the project is proceeding according to plan or not. Updating is recording the state of the project as shown by the reviews, or of making amendments.
  • 31. 31 Project management (cont.) Project Action - When review has shown a project to be deviating from plan, action is required to restore the operation to its planned characteristics.
  • 32. 32 A good project manager should:  have working knowledge in several fields  be able to understand general managerial problems  have active interest in training and developing subordinates  be able to delegate some tasks to subordinates Characteristics of a good project manager
  • 33. 33 A good project manager should:  know the project and understand its objectives  know the systematic process for managing projects  be able to answer the following questions:  What is the project for?  Why is it required?  Whom does it serve?  How is it justified?  How is it going to be used? Characteristics of a good project manager (cont.)