SlideShare a Scribd company logo
1 of 74
Download to read offline
PROJECT PLANNING AND
MANAGEMENT
PIYUSH KUMAR
ASST. PROFESSOR
LECTURE 1
• DEFINITION OF PROJECT
• PROJECT Vs. PROGRAM
• PROJECT VS OPRATIONAL PROCESS
• HISTORY OF PROJECT
• CHARACTERISTICS OF PROJECT
• CATEGORIES OF PROJECTS
• TYPES OF PROJECT
• PROJECT PLANNING
• PROJECT FORMULATION
• PROJECT FORMULATION STAGES
• STAKEHOLDERS & ORGANIZATIONAL STRUCTURE
• PROJECT LIFE CYCLE
• PROJECT MANAGEMENT PROCESS MAPPING
• DETAIL PROJECT REPORT
INTRODUCTION:
• One of the most important administrative developments in
the developed as well as in developing countries has been
doing initiation and growth of a large number of new
programs/projects in every field like agriculture, irrigation,
industry, community development, health & social welfare
etc.
• The principle aims and objectives of all these programs
have been to bring about overall changes in the existing
socio-economic structure in the country providing thereby
dignified way of life to a citizen as a unit and socio-
economic upliftment of the society.
The word project comes from the Latin word projectum from projicere,
"to throw something forwards“. The word "project" thus originally
meant "something that comes before anything else is done".
• Oxford English Dictionary which defines a Project as: An individual or
collaborative enterprise that is carefully planned to achieve a particular
aim.
• Definition by (Prof. Srinivasan Rengasamy 2017): “An activity (or, usually, a
number of related activities) carried out according to a plan in order to
achieve a definite objective within a certain time and which will cease
when the objective is achieved. A collection of linked activities, carried
out in an organized manner, with a clearly defined start point and end
point to achieve some specific results desired to satisfy some clearly
defined objectives.
• A project can be defined as a scientifically evolved work plan devised
to achieve specific objectives within a specific period of time.
DEFINITION OF A PROJECT:
Project in general refers to a new endeavor with specific objective and varies
so widely that it is very difficult to precisely define it.
Some of the commonly quoted definitions are as follows. Project is a
temporary endeavor undertaken to create a unique product or service or
result. (AMERICAN National Standard ANSI/PMI99-001-2004)
Project is a unique process, consist of a set of coordinated and controlled
activities with start and finish dates, undertaken to achieve an objective
confirming to specific requirements, including the constraints of time cost and
resource.
Examples of project include Developing a watershed, Creating irrigation
facility, Developing new variety of a crop, Developing new breed of an
animal, Developing agro processing Centre, Construction of farm/ building,
etc. It maybe noted that each of these projects differ in composition, type,
scope, size and time.
DEFINITION OF A PROJECT:
DEFINITION OF A PROJECT:
• A project is an investment of resources in a package of interrelated time
found activities. Thus a project becomes a time found task. A Project should
have definite beginning and an end.
• A project is a temporary endeavour undertaken to create an unique product
or service. Something with a beginning, middle and end. Something that has
a clear objective and somebody responsible for it.
• A group of activities that have to be performed in a logical sequence to
meet pre-set objectives outlined by the client. It may make it easier to
define if we instead list the characteristics of a project, which would
include:
 A start and a finish date
 A budget
 activities which are essentially unique and not repetitive
 Have definite objectives (goals) to achieve
 Requires set of resources.
 Involves risk and uncertainty.
 Requires cross-functional teams and interdisciplinary approach.
 a life cycle (which we will examine later)
Definition of Project
A project comprises a set of routine and interlinked activities, with a
goal, which has a definite goal and requires to be completed with a
stipulated time and resources. The projects may vary regarding size,
i.e. small, medium, large and very large. After the accomplishment
of the project, a final product is received.
Definition of Program
The program can be defined as a framework of plans of work, which
comprises of a set of projects that are complementary to one
another and aligned in proper sequence to achieve economies of
scale. Projects are grouped into a single program when the resultant
benefit of the collection supersedes the benefits of managing
individual projects. It consists of various projects which are started
to reach organizational goals.
Project vs. Program :
Differences Between Project and Program
1. The temporary activity, which is carried out to create a distinct product or
service, that has specified objectives, is called project. A bundle of projects
which are linked to one another, rationally to attain the combined benefits, is
called program.
2. While the project is content-specific, which focuses on delivering the required
result. Conversely, a program is context-specific, which links different projects
that are related to each other so as to achieve the ultimate goal of the
organization.
3. A project is distinct and is for specified duration. On the other extreme, a
program is everlasting and executed in the business to continuously obtain the
results of the entity.
4. A project deals with specific deliverables, whereas a program is concerned
with the benefits received, from implementing it.
5. The scope of the program is wider in comparison to the project, the project
works on a single functional unit, while the program works on various
functional units.
Project vs. Program :
The tasks performed by the project manager, to complete the project are
technical in nature. On the contrary, the tasks performed to implement the
program successfully, are strategic in nature.
There is a generation of specific output which is demanded by the project. In
contrast, the program produces the general outcomes which are necessary for
the growth and survival of the organization in the long run.
One can measure the effectiveness of the project by evaluating the product
quality, timeliness, cost efficiency, compliance and degree of customer
satisfaction. As opposed, to measure the effectiveness of the program, one
needs to check whether it fulfils the needs and benefits, for which it was
implemented.
Project vs. Program :
Projectvs.Program: Area of Comparison Programme. Project.
Objectives.
Outcomes – often intangible; difficult
to quantify; benefits often based on
changes to organizational culture and
behaviours; introducing new
capabilities into the organization;
tending towards subjective.
Outputs – tangible; relatively easy to
describe, define and measure; tending
towards objective.
Scope
Not tightly defined or bounded; likely
to change during the life cycle of the
program.
Strictly limited; tightly defined; not
likely to be subject to material change
during the life of the project.
Duration
Relatively long term – typically
eighteen months to three years.
Relatively short term – typically three
to six months.
Risk Profile
Program risk is more complex and
potentially the impact on the
organization if a risk materializes will be
greater relative to project risk.
Programme failure could result in
material financial, reputational or
operational loss. Reasons for failure
may not be identifiable
Project risk is relatively easy to identify
and manage. The project failure would
result in relatively limited impact on
the organization relative to program
risk. Reasons for failure can be
identified.
Area of Comparison Programme. Project.
Nature of the problem
Ill-defined; often disagreement between
key stakeholders on the nature and
definition of the problem.
Clearly defined.
Nature of the solution
A significant number of potential solutions
with often with disagreement between
stakeholders as to the preferred solution.
A relatively limited number of potential
solutions. .
Duration
Relatively long term – typically eighteen
months to three years.
Relatively short term – typically three to
six months.
Stakeholders
A significant number of diverse
stakeholders, the beneficiaries cannot be
identified, it is disproportionately divided
and unlimited
A relatively limited number of
stakeholders within defined boundaries
and communities. Scale is relatively
smaller and defined and limited.
Resources
Resources are constrained and limited;
there is competition for resources
between projects. Estimates are
unavailable
Resources to deliver the project can be
reasonably estimated in advance.
Resources are defined.
Relationship to
environment
Environment is dynamic; and programme
objectives need to be managed in the
context of the changing environment
within which the organization operates.
Unstable and broad. May or may not get
implemented.
Environment within which the project
takes place is understood and relatively
stable. It is accepted by the community
and is implemented only after its
feasibility is studied.
An ongoing work effort is generally a repetitive process because it
follows an organization’s existing procedures. The ongoing execution of
activities that produce the same result or product repetitively is what
Operations is all about.
Operations are the ongoing execution of activities that produce the
same output or provide a repetitive service. but projects are temporary
Operations do not produce new things, but they are necessary to
maintain and sustain the system.
Operations are used to run regular business models, achieve the goals of
the business, and support the business.
Operations don’t have a fixed budget or time duration.
Example of Project / Operations : A plumber may be doing a support work to
fix a leak. Each day he fixes leaks in 20 locations. Each leak may require a
different solution (some may need a new washer, or a new pipe, or some
putty), but it is still support work.
What is Operational process / work?
HISTORY OF PROJECT MANAGEMENT :
• As a discipline, Project Management developed from different fields of
application including construction, engineering, and defence. In the
United States, the forefather of project management is Henry Gantt,
called the father of planning and control techniques, who is famously
known for his use of the "Gantt" chart as a project management tool.
• The 1950s marked the beginning of the modern project management
era. Again, in the United States, prior to the 1950s, projects were
managed using mostly Gantt Charts, and informal techniques and
tools. At that time, two mathematical project scheduling models were
developed: (1) the "Program Evaluation and Review Technique" or
PERT, (2) the "Critical Path Method" or CPM. These mathematical
techniques quickly spread into many private enterprises.
GANTT CHART:
WHAT IS A PROJECT?
OUTPUT
(Objectives &
Scope)
Resource (Man
Power, facilities,
Money etc.)
TIME (Duration)
THREE
ELEMENTS OF
PROJECT:
• What will be the final
Output?
• Purpose & Scope
• Start Date?
• End Date?
• What are the requirements?
• How much the cost?
• Benefit from the project?
UNDERSTANDING OF CHARACTERISTICS OF PROJECT :
• Each and every project should have a package of interrelated activities.
 Identification of the poor
 Knowing their choice
 Arranging bank assets
 Follow up / advisory activities Evaluation
• Each activity is time found
• Each and every project should have a set of objectives to be achieved.
 E.g. Eradication poverty by distributing income-generating assets.
 E.I.P-Improving the environment in slums through providing basic amenities
like drinking water, drainage, street lights, toilets and community centers etc.
• Each and every project should be operated with constraints.
 E.g. Eradication of poverty within a democratic framework, within a time
frame, within a limited resource within the present bureaucratic setup.
• Each and every project should specify the (clientele) target group.
 E.g. Rural poor, Urban poor.
• Each and every project should have well defined time sequence of investments.
• Each and every project should have an in built arrangement to evaluate the
program.
DEVELOPMENT PROJECT TYPES:
 Agriculture & Rural Development
 Environmental Protection
 Housing & Urban Development
 Health & Family Planning
 Roads/Bridges/Ports
 Marketing
 Public Administration
 Banking & Capital Market Development
 Education & Training
 Power Generation
 Constrained by limited resources
 Scale of Project
 Planned, executed, and controlled
• Developing a new product or service.
• Designing a new transportation route.
• Developing or acquiring a new or modified information
system.
• Constructing a building or facility.
• Building a water system for a community.
• Implementing a new service procedure or process.
3. Project Life-cycle
Every project, from conception to completion, passes through various phases of a
life cycle synonymous to life cycle of living beings. There is no universal consensus
on the number of phases in a project cycle. An understanding of the life cycle is
important to successful completion of the project as it facilitates to understand the
logical sequence of events in the continuum of progress from start to finish, it is
possible to describe, in general term, the time phasing of project planning activities
common to most projects. The principal stages in the life of a project are :
Identification
Initial formulation/ Preparation
 Planning Evaluation (selection or rejection)/Appraisal
Implementation/ Execution phase
Completion and operation/evaluation/ controlling and monitoring phase
Project closure
Identification:
• Development projects are expressly designed to solve varied problems of
whether in the short or long run.
• The surveys or in depth studies would locate the problems and the project
planner will have to identify the projects that would solve the problems most
effectively.
• At this stage, we are concerned with the kind of action and type of project that
would be required in rather broad term. In other words the surveys and studies
will give us ideas and throw up suggestions which would be worked out in detail
later and then evaluated objectively before being accepted for implementation.
• The current socio-political economic situation has to be critically assessed.
• It will also be necessary to review it in its historical perspective necessitating the
undertaking of a survey of the behaviour and growth during the preceding
decades.
The initiation phase
The initiation phase is the first phase of the entire project management life cycle.
The goal of this phase is to define the project, develop a business case for it, and
get it approved. During this time, the project manager may do any of the
following:
Perform a feasibility study Create a project charter Identify key stakeholders
Select project management tools By the end of this phase, the project manager
should have a high-level understanding of the project purpose, goals,
requirements, and risks.
• Perform a feasibility study
• Create a project charter
• Identify key stakeholders
• Select project management tools
PROJECT LIFE CYCLE
The planning phase
The planning phase is critical to creating a project roadmap the entire team
can follow. This is where all of the details are outlined and goals are defined
in order to meet the requirements laid out by the organization. During this
phase, project managers will typically:
• Create a project plan
• Develop a resource plan
• Define goals and performance measures
• Communicate roles and responsibilities to team members
• Build out workflows
• Anticipate risks and create contingency plans
PROJECT PLANNING:
PLAN
• A plan is a set of decisions made on actions to be taken to reach a
goal. Planning is an active process and it is opposite of simply
allowing events to unfold.
• Plan (appoint in the planning process) is the set of operations
designed to meet a given goal.
• A plan can be a very formal document, or it can simply be the
clear understanding of the actions you are going to undertake.
• Both plan and planning is a never-ending activity. Your plan will
be shaped and reshaped by new forces and new information you
discover as you proceed with your action.
• Planning involves vision, discovery, decision making and action. It
is a purposeful way of looking at the future with the intent to
shape it.
PROJECT PLANNING:
PROJECT PLAN
• A project plan is "A formal, approved document used to
guide both project execution and project control. The
primary uses of the project plan are to document planning
assumptions and decisions, facilitate communication among
stakeholders, and document approved scope, cost, and
schedule baselines. A project plan may be summary or
detailed."
• "a statement of how and when a project's objectives are to
be achieved, by showing the major products, milestones,
activities and resources required on the project”.
PROJECT PLAN COMPONENTS:
PROJECT FORMULATION
Project formulation means developing our ideas in a good shape so as to
present it to decision-makers to take correct investment decisions. Thus,
project formulation refers to a series of steps to be taken to convert an idea
or aspiration into a feasible plan of action.
A Project Plan contains information that will help complete the project
successfully. Success factors can be quickly summarized by answering the
following questions:
• What and Why? - A project plan will contain a description of the project,
what is the Vision and why the project is being executed.
• Who? - Who will be involved and what will be their responsibilities within
the project
• When? - When will the project happen and also major milestones
• How? - How the project will be executed and controlled. Normally this
information refers mostly to the controlling of the project as the detailed
project actions will be detailed in other documents such as the IT plan, the
Procurement plan, the Construction plan, etc.
STAGES OF PROJECT FORMULATION:
1. FEASIBILITY ANALYSIS
2. TECHNO-ECONOMIC ANALYSIS
3. PROJECT DESIGN
4. INPUT ANALYSIS
5. FINANCIAL ANALYSIS
6. COST-BENEFIT ANALYSIS
7. PRE-INVESTMENT ANALYSIS
8. ENVIRONMENTAL ANALYSIS
1. FEASIBILITY ANALYSIS:
 First stage in project formulation.
• Examination to see whether to go in for a detailed investment proposal
or not.
• Screening for internal and external constraints.
 Conclusion could be:
• The project idea seems to be feasible
• The project idea is not a feasible one
• Unable to arrive at a conclusion for want of adequate data
2. TECHNO-ECONOMIC ANALYSIS:
• Screens the idea to-Estimate the potential of the demand
• Choice of optimal technology.
• This analysis gives the project a platform for preparation of detailed
project design/report.
3. PROJECT DESIGN:
• It is the heart of the project entity.
• It defines the sequence of events of the project.
• Time is allocated for each activity.
• It is presented in a form of a network drawing.
• It helps to identify project inputs, finance needed and cost-benefit profile of
the project
4. INPUT ANALYSIS:
• It assesses the input requirements during the construction and operation
of the project.
• It defines the inputs required for each activity.
• Inputs include materials, human resources.
• It evaluates the feasibility of the project from the point of view of the
availability of necessary resources.
• This aids in assessing the project cost.
5. FINANCIAL ANALYSIS:
6. COST-BENEFIT ANALYSIS:
• It involves estimating the project costs, operating cost and fund
requirements.
• It helps in comparing various project proposals on a common scale.
• Analytical tools used are discounted cash flow, and ratio analysis.
• Investment decisions involve commitment of resources in future, with a
long time horizon.
• It needs caution and foresight in developing financial forecasts
• The overall worth of a project is considered.
• The project design forms the basis of evaluation.
• It considers costs that all entities have to bear and the benefit
connected to it.
7. PRE- INVESTMENT ANALYSIS :
8. ENVIRONMENTAL ANALYSIS:
• The results obtained in previous stages are consolidated to arrive at clear
conclusions.
• Helps the project-sponsoring body, the project-implementing body and the
external consulting agencies to accept/reject the proposal.
• The EIA document itself is a technical tool that identifies, predicts, and
analyses impacts on the physical environment, as well as social, cultural,
and health impacts. If the EIA process is successful, it identifies alternatives
and mitigation measures to reduce the environmental impact of a proposed
project.
• It is essential that predicted impacts are evaluated in order to protect the
environment and the quality of life for humans and organisms.
The EIA explores both positive and negative impacts.
• EIA plays a significantly important role in 'Project and its related
environmental management'.
PROJECT STAKEHOLDERS:
Project stakeholders are individuals and organizations that are actively
involved in the project, or whose interests may be affected as a result of
project execution or project completion.
 Key stakeholders: Those who can significantly influence or are important
to the success of an activity.
 Primary stakeholders: Those who are ultimately affected by an activity.
 Secondary stakeholders: All other stakeholders than Primary
stakeholders.
• THE IMPORTANCE OF STAKEHOLDER ANALYSIS
To Know:
 Those around a project, who may affect or be affected by a project
 Opportunities and relationships to build upon in implementing a
project to help make it a success
 Who should be encouraged to participate in a project – Potential
conflicts and risks that could jeopardize a project, etc.
ORGANIZATIONAL STRUCTURE:
The structure of the performing organization often constitute
the availability of resources in a spectrum from functional to
projectized.
• Functional organization : Each employee has one clear
superior. Staff members are grouped by speciality/ functional
departments. ( Finance, Design, Procurement, Construction,
etc). Coordination happens between functional heads.
• Projectized organization : There is team of various specialties.
Team members are collocated and Project managers have a
great deal of independence / authority. Coordination happens
within the team.
PROJECT MANAGEMENT:
It is the application of knowledge, skills, tools and
techniques to project activities to meet project
requirements.
• Identifying requirements
• Establishing clear and achievable objectives
• Balancing the competing demands for quality, scope, time
and cost.
• Adapting the specifications, plans, and approach to the
different concerns and expectations of the various
stakeholders.
PROJECT MANAGEMENT:
Key areas to consider when looking at project management are management
of time, people, and other resources. In general terms, these activities can be
described as follows:
MANAGEMENT OF
TIME
MANAGEMENT OF PEOPLE MANAGEMENT OF OTHER
RESOURCES
Ensuring that the
Project completes its
work on time
Ensuring that people are available
at the right time
Ensuring that appropriate
resources are allocated
Scheduling use of
resources
Ensuring that personnel know
their roles and can perform their
functions properly
Ensuring that the
appropriate resources are
available at the right time
Rescheduling the
project in the light of
experience
Managing people’s expectations Reallocating resources in the
light of experience
Predicting problems
before they arise
Resolving conflicts between
people
Tailoring activities to limited
resources
Changing people’s roles in the light
of experience
Making maximum impact
with available resources
PROJECT MANAGEMENT ACTIVITIES :
• Planning the work or objectives
• Analysis & design of objectives and events
• Assessing and controlling risk (or Risk Management)
• Estimating resources
• Allocation of resources
• Organizing the work
• Acquiring human and material resources
• Assigning tasks
• Directing activities
• Controlling project execution
• Tracking and reporting progress
• Analysing the results based on the facts achieved
• Forecasting future trends in the project
• Quality Management
• Issues management
• Issue solving
• Defect prevention
• Identifying, managing & controlling changes
• Project closure
• Communicating to stakeholders
PROJECT LIFE CYCLE:
PROJECT MANAGEMENT PROCESSES:
PROJECT LIFE CYCLE:
PROJECT LIFE CYCLE
3. Project Execution
This stage is where the meat of the project happens. Deliverables
are built to make sure the project is meeting requirements. This is
where most of the time, money, and people are pulled into the
project.
Introductions: Who’s who?
Project background: Why are you doing this project? What are the goals?
Project scope: What exactly will you be doing? What kind of work is involved?
Project plan: How are we going to do this? What does the roadmap look like?
Roles: Who will be responsible for which elements of the project?
Communication: What kind of communication channels will be used? What
kind of meetings or status reports should your team expect?
Tools: What tools will be used to complete the project, and how will they be
used?
Next steps: What are the immediate action items that need to be completed?
Q&A: Open the floor for any questions
PROJECT LIFE CYCLE
4. Project Monitoring and Control
• Monitoring and control are sometimes combined with execution because
they often occur at the same time. As teams execute their project plan,
they must constantly monitor their own progress.
• To guaranteed delivery of what was promised, teams must monitor tasks
to prevent scope creep, calculate key performance indicators and track
variations from allotted cost and time. This constant vigilance helps keep
the project moving ahead smoothly.
5. Project Closure
• Teams close a project when they deliver the finished project to the
customer, communicating completion to stakeholders and releasing
resources to other projects. This vital step in the project lifecycle allows
the team to evaluate and document the project and move on the next
one, using previous project mistakes and successes to build stronger
processes and more successful teams.
• Although project management may seem overwhelming at times, breaking
it down into these five distinct cycles can help your team manage even the
most complex projects and use time and resources more wisely.
PROJECT LIFE CYCLE:
PROJECT REPORT:
It is a concise copy of detailed analysis done for the project.
• An entrepreneur/expert prepares the report before the investment in
project is done.
• The report assesses the demand for proposed product/service, works out
cost of investment and profitability on this investment.
• It acts as an instrument to convince investors to invest in the project.
• A project report gives information on the following:
• Economic aspects – present market, scope for growth, justification for
investment.
• Technical aspects – technology, machinery, equipment needed.
• Financial aspects – Total investment needed, entrepreneur’s
contribution, cost of capital and return on capital.
• Marketing aspects – Product details, justification for the choice of
product, sale.
• Managerial aspects – Qualifications, experience of people needed for
managerial posts.
CONTENT OF PROJECT REPORT:
• Objectives and scope of the report.
• Product characteristics (product design, specifications, quality standards, uses
and applications).
• Market position and trends (current capacity for production, potential demand,
sale prospects, price structure etc).
• Raw materials (types, quality, sources, price).
• Construction (process, production schedule, technique used.
• Plant and machinery (types, infrastructure support, cost).
• Land and building (Requirement, building construction schedule, choice of
location, cost).
• Financial implications (Capital structure, capital investment, project cost,
profitability).
• Marketing channels (marketing and advertising strategy).
• Personnel (Requirement of staff, skilled-unskilled labour, salary and wage
payment, qualifications, experience)
• The project report is submitted to financial institutions for grant of loan and
other financial assistance/concessions.
• The financial institutions ascertain from the report, whether the project can
generate enough funds to repay the borrowings in stipulated time frame
PROJECT MANAGEMENT PROCESS MAPPING:
KNOWLEDGE
AREA
PROCESSESS
PROJECT MANAGEMENT PROCESS GROUPS
1.
INITIATING PROCESS
GROUP
2.
PLANNING PROCESS GROUP
3. EXECUTING
PROCESS
GROUP
4. MONITORING &
CONTROL PROCESS
GROUP
5. CLOSING
PROCESS
GROUP
1. PROJECT
INTEGRATION
MANAGEMENT
• DEVELOP PROJECT
CHARTER
• DEVELOP
PRELIMINARY
PROJECT SCOPE
STATEMENTS
DEVELOPMENT PROJECT
MANAGEMENT PLAN
DIRECT AND
MANAGE
PROJECT
EXECUTION
• MONITOR &
CONTROL
PROJECT WORK
• INTEGRATED
CHANGE
CONTROL
CLOSE
PROJECT
2. PROJECT SCOPE
MANAGEMENT
• SCOPE PLANNING
• SCOPE DEFINITION
• CREATE WORK BREAK-DOWN
STRUCTURE
• SCOPE
VERIFICATION
• SCOPE CONTROL
3. PROJECT TIME
MANAGEMENT
• ACTIVITY DEFINITION
• ACTIVITY SEQUENCING
• ACTIVITY RESOURCE
• ESTIMATION
• ACTIVITY DURATION
ESTIMATION
• SCHEDULE DEVELOPMENT
SCHEDULE
CONTROL
4. PROJECT COST
MANAGEMENT
• COST ESTIMATING
• COST BUDGETING
COST CONTROL
5. PROJECT
QUALITY
MANAGEMENT
• QUALITY PLANNING PERFORM
QUALITY
ASSURANCE
PERFORM QUALITY
CONTROL
PROJECT MANAGEMENT PROCESS MAPPING:
KNOWLEDGE AREA
PROCESSESS
PROJECT MANAGEMENT PROCESS GROUPS
1.
INITIATING
PROCESS
GROUP
2.
PLANNING PROCESS
GROUP
3.
EXECUTING PROCESS
GROUP
4.
MONITORING &
CONTROL PROCESS
GROUP
5.
CLOSING
PROCESS
GROUP
6. PROJECT HUMAN
RESOURCE
MANAGEMENT
HUMAN RESOURCE
PLANNING
• ACQUIRE PROJECT
TEAM
• DEVELOP PROJECT
TEAM
• MANAGE PROJECT
TEAM
7. PROJECT
COMMUNICATIONS
MANAGEMENT
COMMUNICATIONS
PLANNING
• INFORMATION
DISTRIBUTION
• PERFORMANCE
REPORTING
• MANAGE
STAKEHOLDERS
8. PROJECT RISK
MANAGEMENT
• RISK MANAGEMENT
PLANNING
• RISK IDENTIFICATION
• QUALITATIVE RISK
ANALYSIS
• QUANTITATIVE RISK
ANALYSIS
RISK MONITORING
AND CONTROL
9. PROJECT
PROCUREMENT
MANAGEMENT
• PLAN PURCHASES
AND ACQUISITIONS
• PLAN
CONTRACTING
• REQUEST SELLER
• RESPONSE
• SELECT SELLERS
CONTRACT
ADMINISTRATION
CONTRACT
CLOSURE
Investment criteria
Investment
Criteria
Non Discounting
Criteria
Payback
Period
Accounting
rate of
return
Discounting Criteria
Net Present
Value
Benefit cost
ratio
Internal Rate
of return
Rate of Return (RoR)
A rate of return (RoR) is the net gain or loss on an investment
over a specified time period, expressed as a percentage of the
investment’s initial cost. Gains on investments are defined as
income received plus any capital gains realized on the sale of
the investment.
The rate of return is used to measure growth between
two periods, rather than over several periods.
The RoR can be used for many purposes, from evaluating
investment growth to year-over-year changes in company
revenues.
The RoR calculation does not consider the effects of
inflation.
What is the Payback Period?
The payback period
shows how long it takes
for a business to recoup
its investment. this type
of analysis allows firms
to compare alternative
investment
opportunities and
decide on a project that
returns its investment
in the shortest time, if
that criteria is
important to them.
Example: Consider the previous investment project. The initial cost is
$600 million. It has been decided that the project should be accepted if
the payback period is 3 years or less. Using the payback rule, should this
project be undertaken?
Year Cash Flow Accumulated Cash Flow
1 $200.00 $200
2 220.00
3 225.00
4 210.00
$420
$645 > $600
$855
ILLUSTRATION
Advantages and Disadvantages of the Payback Rule
Advantages
Simple & quick calculation
Disadvantages
Ignores time value of money
Ignore cash flow after payback period
Popular among many large companies, Commonly used when the:
 capital investment is small
 merits of the project are so obvious that more formal analysis is
unnecessary
An organization has to take many decisions regarding the expansion of
business and investment. In such cases, the organization will take the
help of NPV method and base its decision on the same.
Net present value is used in Capital budgeting to analyze the
profitability of a project or investment. It is calculated by taking the
difference between the present value of cash inflows and present value
of cash outflows over a period of time.
As the name suggests, net present value is nothing but net off of the
present value of cash inflows and outflows by discounting the flows at a
specified rate.
NPV ( Net Present Value )
Formula for NPV
NPV = (Cash flows)/( 1+r)i
i- Initial Investment
Cash flows= Cash flows in the time period
r = Discount rate
i = time period
As seen in the formula – To derive the present value of the cash flows we
need to discount them at a particular rate. This rate is derived considering
the return of investment with similar risk or cost of borrowing, for the
investment.
NPV takes into consideration the time value of money. The time value of money
simply means that a rupee today is of more value today than it will be tomorrow.
Consider it this way: You have Rs. 100 today and you can buy ten chocolates.
The same Rs. 100 will be able to get you not more than the same 5 chocolates
may be after one year. So the cash flows earned today are of more value than as
on a later date.
After discounting the cash flows over different periods, the initial investment is
deducted from it.
 If the result is a positive NPV then the project is accepted.
 If the NPV is negative the project is rejected.
 And if NPV is zero then the organization will stay indifferent.
ILLUSTRATION
Year Flow Present value Computation
0 -1000000 -1000000
1 100000 91743 100000/(1.09)
2 250000 210419 250000/(1.09)^2
3 350000 270264 350000/(1.09)^3
4 265000 187732 265000/(1.09)^4
5 415000 269721 415000/(1.09)^5
Let us say XYZ Ltd wants to do a project and so it is willing to invest Rs 10,00,000.
The investment is said to bring an inflow of Rs. 100,000 in first year, 250,000 in the second year, 350,000
in third year, 265,000 in fourth year and 415,000 in fifth year. Assuming the discount rate to be 9%. Let us
calculate NPV using the formula.
ILLUSTRATION
Here NPV is Rs. 29881.
The internal rate of return (IRR) is a metric used in capital budgeting to
estimate the profitability of potential investments. The internal rate of
return is a discount rate that makes the net present value (NPV) of all
cash flows from a particular project equal to zero. IRR calculations rely
on the same formula as NPV does.
Internal Rate of Return (IRR)
IRR=NPV=t=1∑T​(1+r)tCt​​−C0​=0
where:Ct​=net cash inflow during the period t
C0​=total initial investment costs
r=the discount rate, and
t=the number of time periods​ T
IRR=NPV= ∑ (Ct) - C0
T=1 (1+r)t
where:
Ct​=net cash inflow during the period t
C0​=total initial investment costs
r=the discount rate, and
t=the number of time periods​
What Does IRR Tell You?
You can think of the internal rate of return as the rate of growth a project is expected to
generate. While the actual rate of return that a given project ends up generating will often
differ from its estimated IRR, a project with a substantially higher IRR value than other
available options would still provide a much better chance of strong growth.
One popular use of IRR is comparing the profitability of establishing new operations with
that of expanding existing ones. For example, an energy company may use IRR in deciding
whether to open a new power plant or to renovate and expand a previously existing one.
While both projects are likely to add value to the company, it is likely that one will be the
more logical decision as prescribed by IRR.
Key Take aways:
• IRR is the rate of growth a project is expected to generate.
• IRR is calculated by the condition that the discount rate is set such that the NPV = 0 for
a project.
• IRR is used in capital budgeting to decide which projects or investments to undertake
and which to forgo.
Compute present values of each net cash flow. Multiply the net cash flow for each period
by its discount factor to obtain its present value. Sum the present values of each cash flow
to calculate the NPV. Find the IRR, the discount rate, that makes the NPV zero.
Cost Benefits Analysis (CBA)
Benefit Cost Analysis (BCA) is an economic tool for
government policy and investment project analysis used widely
Can incorporate environmental impacts of policies/projects
within CBA to correct for market failure
“Social” appraisal of policies and projects, carried out by
aggregation of benefits from, and costs of a policy/project over
individuals and over time
Welfare theoretic underpinning: Economic efficiency with a
temporal dimension
Relates to the environment in three ways:
 Projects/policies may have negative environmental
effects, i.e. negative externalities (public and private)
 Projects/policies may have positive externalities (public)
 Projects/policies may have both positive and negative
externalities (public and private)
Externalities should be included in CBA in order to
correct for market failure
Welfare Economics Background
CBA is firmly based in welfare theory in three ways
In terms of how gains and losses are measured
Consumers: Changes in consumer surplus as a result of changes in
quantity and quality of environmental goods
Producers: Changes in producer surplus as a result of changes in
prices and quantity and quality of inputs
Makes use of the opportunity cost (scarcity rents) concept to
asses costs of using scarce resources
What counts as costs and benefits
◦ Welfare economics evaluates alternative resource allocations in
terms of their effects on utility
◦ CBA includes any impact on utility whether or not they are
reflected in market prices
Welfare Economics Background
In terms of aggregation and comparison of costs and
benefits
◦ Policies and projects have a mixture of gains and losses across
individuals
◦ Gains and losses are calculated in money terms, added up and
compared to find out the net impact on welfare (net gain or
net loss)
◦ Measure of the change in social welfare is based on Kaldor-
Hick Criterion: Could gainers compensate the losers and still be
better off?
◦ This criterion considers economic efficiency but interpersonal
welfare impacts, i.e. Distribution of gains and losses are not
considered
Stages of CBA
Stage 1: Definition of policy/project:
◦ The reallocation of resources being proposed
◦ The population of gainers and losers being considered
Stage 2: Identification of policy/project impacts:
◦ Define all impacts that will result from policy/project
implementation
◦ Consider additionally (net impacts) and displacement (crowding
out)
Stage 3: Identification of economically relevant impacts:
Environmental impacts of a policy/project are relevant in
CBA if either
◦ They change the utility of at least one person in the society
◦ They change the quantity or quality of the output of some
positively valued commodity
Stage 4: Physical quantification of relevant impacts:
◦ Determine physical amounts of costs and benefits and when
they occur in time
◦ Use environmental impact analysis to estimate the impact of
policy/project on the environment
◦ Estimations will be made with uncertainty, calculate the
expected value of costs and benefits
Stage 5: Monetary valuation of relevant
effects
◦All physical measures of impacts should be
valued in common units to be comparable
◦Common unit = money
◦CBA analyst must
◦ Predict prices for value flows extending into the future
◦ Correct market prices where they are distorted
◦ Calculate prices where non exists using environmental
valuation methods
Stage 6: Discounting of costs and benefits:
◦ Once costs and benefits are expressed in monetary
units they should be converted to present value terms
by discounting
◦ PV= Xt[(1+r)-t] where X= cost or benefit; r = discount
rate; [(1+r)-t] discount factor; t= time
◦ The higher the value of t the lower the discount factor
◦ The higher the discount rate for a given t the lower
the discount factor
Stage 7:Applying the net present value test:
◦ Apply NPV test to choose those policies and projects that are
efficient in terms of their use of resources
◦ Where Bt = benefits of the project at period t, Ct = the costs of the
project at period t, r = the discount rate, n = the number of years
over which the project will operate
◦ NPV is the present value of the project’s/policy’s net benefit
stream, obtained by discounting the stream of net benefits
produced by the project/policy over its lifetime, back to its value in
the chosen base period, usually the present.
◦ If NPV>0 accept policy or project (Based in Kaldor-Hicks Criterion)
since it would improve social welfare
( )
( )∑= +
−n
t
t
tt
r
CB
0 1
Alternatives to NPV
Benefit – Cost ratio (BCR): It is the ratio of the sum of the
project’s or policy’s discounted benefits to the sum of its
discounted costs. If BCR>1 go ahead with the project/policy.
t
t
n
t
n
t
t
t
r
C
r
B
BCR
)1(
)(
)1(
)(
0
0
+
+
=
∑
∑
=
=
Stage 8: Sensitivity analysis:
◦ NPV test gives relative efficiency of a project given the data on
prices, environmental and economic impacts and discount rate
but any of these data might change due to uncertainty
◦ Recalculate NPV when the key parameters change to discover
which one(s) of them the NPV is most sensitive to
◦ Once the most sensitive parameter is identified direct forecasting
effort to improve best guess and more effort to manage these
parameters carefully
Total Economic Value (TEV)
Environmental goods are public goods, they are not traded in the
markets and hence they do not have readily available market prices
The value of environmental good is not only derived from its direct
consumption but also from its indirect consumption, as well as non-
use.
The broad concept of value is known as the Total Economic Value
(TEV)
Direct Use
Value
Indirect Use
Value
Actual use
Value
Option Value
Use Value
Existence
Value
Bequest
Value
Altruistic
Value
For Others
Non-use Value
Total Economic Value
TEV Deforestation
Direct use values: Timber values, fuelwood and charcoal
extraction, non-timber forest products (NTFP), biodiversity and
genetic information, tourism and recreational values.
Indirect use values: Protection of watersheds and the storage of
carbon and sequestration.
Option values: values reflecting a willingness to pay to conserve
the option of making use of the forest even though no current
use is made of it
Non-use values (also known as existence or passive use values):
these values reflect a willingness to pay for the forest in a
conserved or sustainable use state, but the willingness to pay is
unrelated to current or planned use of the forest.

More Related Content

What's hot

Types of project
Types of projectTypes of project
Types of projectakshay jain
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecyclerlabsza
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jIIT delhi
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager ProofHub
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project Implementation
Project ImplementationProject Implementation
Project ImplementationShidin Divakar
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
Project communication management
Project communication managementProject communication management
Project communication managementDikshant Ghimire
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Project management
Project managementProject management
Project managementSimran Kaur
 
Project Management
Project ManagementProject Management
Project Managementajithsrc
 

What's hot (20)

Types of project
Types of projectTypes of project
Types of project
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecycle
 
Project management
Project managementProject management
Project management
 
Project Life Cycle and Phases
Project Life Cycle and PhasesProject Life Cycle and Phases
Project Life Cycle and Phases
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Evolution of project management
Evolution of project managementEvolution of project management
Evolution of project management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
Project Planning and Development
Project Planning and DevelopmentProject Planning and Development
Project Planning and Development
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project planning
Project planning Project planning
Project planning
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Project communication management
Project communication managementProject communication management
Project communication management
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Project management
Project managementProject management
Project management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 

Similar to Project Planning and Management

Monitoring and Evaluation Unit 1.pptx
Monitoring and Evaluation Unit 1.pptxMonitoring and Evaluation Unit 1.pptx
Monitoring and Evaluation Unit 1.pptxVallentine Okumu
 
Project management
Project managementProject management
Project managementArsh Koul
 
PI class 1.pptx
PI class 1.pptxPI class 1.pptx
PI class 1.pptxAberraBeri
 
1. into. to project and project management (1)
1. into. to project and project management (1)1. into. to project and project management (1)
1. into. to project and project management (1)tehreem fatima
 
Chapter 1-Project Management power point pptx
Chapter 1-Project Management power point pptxChapter 1-Project Management power point pptx
Chapter 1-Project Management power point pptxAlwanYusuf
 
Project Management
Project ManagementProject Management
Project Managementirfan ali
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021Sprintzeal
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
CMGT 410 Week 1 Supporting Activity
CMGT 410 Week 1 Supporting ActivityCMGT 410 Week 1 Supporting Activity
CMGT 410 Week 1 Supporting Activitytmschaf
 
INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT Harihara puthiran
 
Project management chapter 1 notes
Project management chapter 1 notesProject management chapter 1 notes
Project management chapter 1 notesDreams Design
 
Project management material from chapter one up to chapter four
Project management material from chapter one up to chapter fourProject management material from chapter one up to chapter four
Project management material from chapter one up to chapter fourGetachewAbera3
 
Brief Introduction to Project Management
Brief Introduction to Project ManagementBrief Introduction to Project Management
Brief Introduction to Project ManagementWaleed Liaqat
 
ACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estateACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estatehando2845
 

Similar to Project Planning and Management (20)

Monitoring and Evaluation Unit 1.pptx
Monitoring and Evaluation Unit 1.pptxMonitoring and Evaluation Unit 1.pptx
Monitoring and Evaluation Unit 1.pptx
 
Project management
Project managementProject management
Project management
 
PI class 1.pptx
PI class 1.pptxPI class 1.pptx
PI class 1.pptx
 
Construction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & ResponsibilitiesConstruction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & Responsibilities
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
1. into. to project and project management (1)
1. into. to project and project management (1)1. into. to project and project management (1)
1. into. to project and project management (1)
 
PROJECT MANAGEMENT
PROJECT MANAGEMENTPROJECT MANAGEMENT
PROJECT MANAGEMENT
 
Chapter 1-Project Management power point pptx
Chapter 1-Project Management power point pptxChapter 1-Project Management power point pptx
Chapter 1-Project Management power point pptx
 
Unit-4.pptx
Unit-4.pptxUnit-4.pptx
Unit-4.pptx
 
Project Management
Project ManagementProject Management
Project Management
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
CMGT 410 Week 1 Supporting Activity
CMGT 410 Week 1 Supporting ActivityCMGT 410 Week 1 Supporting Activity
CMGT 410 Week 1 Supporting Activity
 
INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT
 
project managementUnit 1.pdf
project managementUnit 1.pdfproject managementUnit 1.pdf
project managementUnit 1.pdf
 
Project management chapter 1 notes
Project management chapter 1 notesProject management chapter 1 notes
Project management chapter 1 notes
 
Project management material from chapter one up to chapter four
Project management material from chapter one up to chapter fourProject management material from chapter one up to chapter four
Project management material from chapter one up to chapter four
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
Brief Introduction to Project Management
Brief Introduction to Project ManagementBrief Introduction to Project Management
Brief Introduction to Project Management
 
ACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estateACE-FUELS- 801- PROJECT MGT for real estate
ACE-FUELS- 801- PROJECT MGT for real estate
 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 

Recently uploaded (20)

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 

Project Planning and Management

  • 2. LECTURE 1 • DEFINITION OF PROJECT • PROJECT Vs. PROGRAM • PROJECT VS OPRATIONAL PROCESS • HISTORY OF PROJECT • CHARACTERISTICS OF PROJECT • CATEGORIES OF PROJECTS • TYPES OF PROJECT • PROJECT PLANNING • PROJECT FORMULATION • PROJECT FORMULATION STAGES • STAKEHOLDERS & ORGANIZATIONAL STRUCTURE • PROJECT LIFE CYCLE • PROJECT MANAGEMENT PROCESS MAPPING • DETAIL PROJECT REPORT
  • 3. INTRODUCTION: • One of the most important administrative developments in the developed as well as in developing countries has been doing initiation and growth of a large number of new programs/projects in every field like agriculture, irrigation, industry, community development, health & social welfare etc. • The principle aims and objectives of all these programs have been to bring about overall changes in the existing socio-economic structure in the country providing thereby dignified way of life to a citizen as a unit and socio- economic upliftment of the society.
  • 4. The word project comes from the Latin word projectum from projicere, "to throw something forwards“. The word "project" thus originally meant "something that comes before anything else is done". • Oxford English Dictionary which defines a Project as: An individual or collaborative enterprise that is carefully planned to achieve a particular aim. • Definition by (Prof. Srinivasan Rengasamy 2017): “An activity (or, usually, a number of related activities) carried out according to a plan in order to achieve a definite objective within a certain time and which will cease when the objective is achieved. A collection of linked activities, carried out in an organized manner, with a clearly defined start point and end point to achieve some specific results desired to satisfy some clearly defined objectives. • A project can be defined as a scientifically evolved work plan devised to achieve specific objectives within a specific period of time. DEFINITION OF A PROJECT:
  • 5. Project in general refers to a new endeavor with specific objective and varies so widely that it is very difficult to precisely define it. Some of the commonly quoted definitions are as follows. Project is a temporary endeavor undertaken to create a unique product or service or result. (AMERICAN National Standard ANSI/PMI99-001-2004) Project is a unique process, consist of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective confirming to specific requirements, including the constraints of time cost and resource. Examples of project include Developing a watershed, Creating irrigation facility, Developing new variety of a crop, Developing new breed of an animal, Developing agro processing Centre, Construction of farm/ building, etc. It maybe noted that each of these projects differ in composition, type, scope, size and time. DEFINITION OF A PROJECT:
  • 6. DEFINITION OF A PROJECT: • A project is an investment of resources in a package of interrelated time found activities. Thus a project becomes a time found task. A Project should have definite beginning and an end. • A project is a temporary endeavour undertaken to create an unique product or service. Something with a beginning, middle and end. Something that has a clear objective and somebody responsible for it. • A group of activities that have to be performed in a logical sequence to meet pre-set objectives outlined by the client. It may make it easier to define if we instead list the characteristics of a project, which would include:  A start and a finish date  A budget  activities which are essentially unique and not repetitive  Have definite objectives (goals) to achieve  Requires set of resources.  Involves risk and uncertainty.  Requires cross-functional teams and interdisciplinary approach.  a life cycle (which we will examine later)
  • 7. Definition of Project A project comprises a set of routine and interlinked activities, with a goal, which has a definite goal and requires to be completed with a stipulated time and resources. The projects may vary regarding size, i.e. small, medium, large and very large. After the accomplishment of the project, a final product is received. Definition of Program The program can be defined as a framework of plans of work, which comprises of a set of projects that are complementary to one another and aligned in proper sequence to achieve economies of scale. Projects are grouped into a single program when the resultant benefit of the collection supersedes the benefits of managing individual projects. It consists of various projects which are started to reach organizational goals. Project vs. Program :
  • 8. Differences Between Project and Program 1. The temporary activity, which is carried out to create a distinct product or service, that has specified objectives, is called project. A bundle of projects which are linked to one another, rationally to attain the combined benefits, is called program. 2. While the project is content-specific, which focuses on delivering the required result. Conversely, a program is context-specific, which links different projects that are related to each other so as to achieve the ultimate goal of the organization. 3. A project is distinct and is for specified duration. On the other extreme, a program is everlasting and executed in the business to continuously obtain the results of the entity. 4. A project deals with specific deliverables, whereas a program is concerned with the benefits received, from implementing it. 5. The scope of the program is wider in comparison to the project, the project works on a single functional unit, while the program works on various functional units. Project vs. Program :
  • 9. The tasks performed by the project manager, to complete the project are technical in nature. On the contrary, the tasks performed to implement the program successfully, are strategic in nature. There is a generation of specific output which is demanded by the project. In contrast, the program produces the general outcomes which are necessary for the growth and survival of the organization in the long run. One can measure the effectiveness of the project by evaluating the product quality, timeliness, cost efficiency, compliance and degree of customer satisfaction. As opposed, to measure the effectiveness of the program, one needs to check whether it fulfils the needs and benefits, for which it was implemented. Project vs. Program :
  • 10. Projectvs.Program: Area of Comparison Programme. Project. Objectives. Outcomes – often intangible; difficult to quantify; benefits often based on changes to organizational culture and behaviours; introducing new capabilities into the organization; tending towards subjective. Outputs – tangible; relatively easy to describe, define and measure; tending towards objective. Scope Not tightly defined or bounded; likely to change during the life cycle of the program. Strictly limited; tightly defined; not likely to be subject to material change during the life of the project. Duration Relatively long term – typically eighteen months to three years. Relatively short term – typically three to six months. Risk Profile Program risk is more complex and potentially the impact on the organization if a risk materializes will be greater relative to project risk. Programme failure could result in material financial, reputational or operational loss. Reasons for failure may not be identifiable Project risk is relatively easy to identify and manage. The project failure would result in relatively limited impact on the organization relative to program risk. Reasons for failure can be identified.
  • 11. Area of Comparison Programme. Project. Nature of the problem Ill-defined; often disagreement between key stakeholders on the nature and definition of the problem. Clearly defined. Nature of the solution A significant number of potential solutions with often with disagreement between stakeholders as to the preferred solution. A relatively limited number of potential solutions. . Duration Relatively long term – typically eighteen months to three years. Relatively short term – typically three to six months. Stakeholders A significant number of diverse stakeholders, the beneficiaries cannot be identified, it is disproportionately divided and unlimited A relatively limited number of stakeholders within defined boundaries and communities. Scale is relatively smaller and defined and limited. Resources Resources are constrained and limited; there is competition for resources between projects. Estimates are unavailable Resources to deliver the project can be reasonably estimated in advance. Resources are defined. Relationship to environment Environment is dynamic; and programme objectives need to be managed in the context of the changing environment within which the organization operates. Unstable and broad. May or may not get implemented. Environment within which the project takes place is understood and relatively stable. It is accepted by the community and is implemented only after its feasibility is studied.
  • 12. An ongoing work effort is generally a repetitive process because it follows an organization’s existing procedures. The ongoing execution of activities that produce the same result or product repetitively is what Operations is all about. Operations are the ongoing execution of activities that produce the same output or provide a repetitive service. but projects are temporary Operations do not produce new things, but they are necessary to maintain and sustain the system. Operations are used to run regular business models, achieve the goals of the business, and support the business. Operations don’t have a fixed budget or time duration. Example of Project / Operations : A plumber may be doing a support work to fix a leak. Each day he fixes leaks in 20 locations. Each leak may require a different solution (some may need a new washer, or a new pipe, or some putty), but it is still support work. What is Operational process / work?
  • 13. HISTORY OF PROJECT MANAGEMENT : • As a discipline, Project Management developed from different fields of application including construction, engineering, and defence. In the United States, the forefather of project management is Henry Gantt, called the father of planning and control techniques, who is famously known for his use of the "Gantt" chart as a project management tool. • The 1950s marked the beginning of the modern project management era. Again, in the United States, prior to the 1950s, projects were managed using mostly Gantt Charts, and informal techniques and tools. At that time, two mathematical project scheduling models were developed: (1) the "Program Evaluation and Review Technique" or PERT, (2) the "Critical Path Method" or CPM. These mathematical techniques quickly spread into many private enterprises.
  • 15. WHAT IS A PROJECT? OUTPUT (Objectives & Scope) Resource (Man Power, facilities, Money etc.) TIME (Duration) THREE ELEMENTS OF PROJECT: • What will be the final Output? • Purpose & Scope • Start Date? • End Date? • What are the requirements? • How much the cost? • Benefit from the project?
  • 16. UNDERSTANDING OF CHARACTERISTICS OF PROJECT : • Each and every project should have a package of interrelated activities.  Identification of the poor  Knowing their choice  Arranging bank assets  Follow up / advisory activities Evaluation • Each activity is time found • Each and every project should have a set of objectives to be achieved.  E.g. Eradication poverty by distributing income-generating assets.  E.I.P-Improving the environment in slums through providing basic amenities like drinking water, drainage, street lights, toilets and community centers etc. • Each and every project should be operated with constraints.  E.g. Eradication of poverty within a democratic framework, within a time frame, within a limited resource within the present bureaucratic setup. • Each and every project should specify the (clientele) target group.  E.g. Rural poor, Urban poor. • Each and every project should have well defined time sequence of investments. • Each and every project should have an in built arrangement to evaluate the program.
  • 17. DEVELOPMENT PROJECT TYPES:  Agriculture & Rural Development  Environmental Protection  Housing & Urban Development  Health & Family Planning  Roads/Bridges/Ports  Marketing  Public Administration  Banking & Capital Market Development  Education & Training  Power Generation
  • 18.  Constrained by limited resources  Scale of Project  Planned, executed, and controlled • Developing a new product or service. • Designing a new transportation route. • Developing or acquiring a new or modified information system. • Constructing a building or facility. • Building a water system for a community. • Implementing a new service procedure or process.
  • 19. 3. Project Life-cycle Every project, from conception to completion, passes through various phases of a life cycle synonymous to life cycle of living beings. There is no universal consensus on the number of phases in a project cycle. An understanding of the life cycle is important to successful completion of the project as it facilitates to understand the logical sequence of events in the continuum of progress from start to finish, it is possible to describe, in general term, the time phasing of project planning activities common to most projects. The principal stages in the life of a project are : Identification Initial formulation/ Preparation  Planning Evaluation (selection or rejection)/Appraisal Implementation/ Execution phase Completion and operation/evaluation/ controlling and monitoring phase Project closure
  • 20. Identification: • Development projects are expressly designed to solve varied problems of whether in the short or long run. • The surveys or in depth studies would locate the problems and the project planner will have to identify the projects that would solve the problems most effectively. • At this stage, we are concerned with the kind of action and type of project that would be required in rather broad term. In other words the surveys and studies will give us ideas and throw up suggestions which would be worked out in detail later and then evaluated objectively before being accepted for implementation. • The current socio-political economic situation has to be critically assessed. • It will also be necessary to review it in its historical perspective necessitating the undertaking of a survey of the behaviour and growth during the preceding decades.
  • 21. The initiation phase The initiation phase is the first phase of the entire project management life cycle. The goal of this phase is to define the project, develop a business case for it, and get it approved. During this time, the project manager may do any of the following: Perform a feasibility study Create a project charter Identify key stakeholders Select project management tools By the end of this phase, the project manager should have a high-level understanding of the project purpose, goals, requirements, and risks. • Perform a feasibility study • Create a project charter • Identify key stakeholders • Select project management tools
  • 23. The planning phase The planning phase is critical to creating a project roadmap the entire team can follow. This is where all of the details are outlined and goals are defined in order to meet the requirements laid out by the organization. During this phase, project managers will typically: • Create a project plan • Develop a resource plan • Define goals and performance measures • Communicate roles and responsibilities to team members • Build out workflows • Anticipate risks and create contingency plans
  • 24. PROJECT PLANNING: PLAN • A plan is a set of decisions made on actions to be taken to reach a goal. Planning is an active process and it is opposite of simply allowing events to unfold. • Plan (appoint in the planning process) is the set of operations designed to meet a given goal. • A plan can be a very formal document, or it can simply be the clear understanding of the actions you are going to undertake. • Both plan and planning is a never-ending activity. Your plan will be shaped and reshaped by new forces and new information you discover as you proceed with your action. • Planning involves vision, discovery, decision making and action. It is a purposeful way of looking at the future with the intent to shape it.
  • 25. PROJECT PLANNING: PROJECT PLAN • A project plan is "A formal, approved document used to guide both project execution and project control. The primary uses of the project plan are to document planning assumptions and decisions, facilitate communication among stakeholders, and document approved scope, cost, and schedule baselines. A project plan may be summary or detailed." • "a statement of how and when a project's objectives are to be achieved, by showing the major products, milestones, activities and resources required on the project”.
  • 26. PROJECT PLAN COMPONENTS: PROJECT FORMULATION Project formulation means developing our ideas in a good shape so as to present it to decision-makers to take correct investment decisions. Thus, project formulation refers to a series of steps to be taken to convert an idea or aspiration into a feasible plan of action. A Project Plan contains information that will help complete the project successfully. Success factors can be quickly summarized by answering the following questions: • What and Why? - A project plan will contain a description of the project, what is the Vision and why the project is being executed. • Who? - Who will be involved and what will be their responsibilities within the project • When? - When will the project happen and also major milestones • How? - How the project will be executed and controlled. Normally this information refers mostly to the controlling of the project as the detailed project actions will be detailed in other documents such as the IT plan, the Procurement plan, the Construction plan, etc.
  • 27. STAGES OF PROJECT FORMULATION: 1. FEASIBILITY ANALYSIS 2. TECHNO-ECONOMIC ANALYSIS 3. PROJECT DESIGN 4. INPUT ANALYSIS 5. FINANCIAL ANALYSIS 6. COST-BENEFIT ANALYSIS 7. PRE-INVESTMENT ANALYSIS 8. ENVIRONMENTAL ANALYSIS
  • 28. 1. FEASIBILITY ANALYSIS:  First stage in project formulation. • Examination to see whether to go in for a detailed investment proposal or not. • Screening for internal and external constraints.  Conclusion could be: • The project idea seems to be feasible • The project idea is not a feasible one • Unable to arrive at a conclusion for want of adequate data 2. TECHNO-ECONOMIC ANALYSIS: • Screens the idea to-Estimate the potential of the demand • Choice of optimal technology. • This analysis gives the project a platform for preparation of detailed project design/report.
  • 29. 3. PROJECT DESIGN: • It is the heart of the project entity. • It defines the sequence of events of the project. • Time is allocated for each activity. • It is presented in a form of a network drawing. • It helps to identify project inputs, finance needed and cost-benefit profile of the project 4. INPUT ANALYSIS: • It assesses the input requirements during the construction and operation of the project. • It defines the inputs required for each activity. • Inputs include materials, human resources. • It evaluates the feasibility of the project from the point of view of the availability of necessary resources. • This aids in assessing the project cost.
  • 30. 5. FINANCIAL ANALYSIS: 6. COST-BENEFIT ANALYSIS: • It involves estimating the project costs, operating cost and fund requirements. • It helps in comparing various project proposals on a common scale. • Analytical tools used are discounted cash flow, and ratio analysis. • Investment decisions involve commitment of resources in future, with a long time horizon. • It needs caution and foresight in developing financial forecasts • The overall worth of a project is considered. • The project design forms the basis of evaluation. • It considers costs that all entities have to bear and the benefit connected to it.
  • 31. 7. PRE- INVESTMENT ANALYSIS : 8. ENVIRONMENTAL ANALYSIS: • The results obtained in previous stages are consolidated to arrive at clear conclusions. • Helps the project-sponsoring body, the project-implementing body and the external consulting agencies to accept/reject the proposal. • The EIA document itself is a technical tool that identifies, predicts, and analyses impacts on the physical environment, as well as social, cultural, and health impacts. If the EIA process is successful, it identifies alternatives and mitigation measures to reduce the environmental impact of a proposed project. • It is essential that predicted impacts are evaluated in order to protect the environment and the quality of life for humans and organisms. The EIA explores both positive and negative impacts. • EIA plays a significantly important role in 'Project and its related environmental management'.
  • 32. PROJECT STAKEHOLDERS: Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.  Key stakeholders: Those who can significantly influence or are important to the success of an activity.  Primary stakeholders: Those who are ultimately affected by an activity.  Secondary stakeholders: All other stakeholders than Primary stakeholders. • THE IMPORTANCE OF STAKEHOLDER ANALYSIS To Know:  Those around a project, who may affect or be affected by a project  Opportunities and relationships to build upon in implementing a project to help make it a success  Who should be encouraged to participate in a project – Potential conflicts and risks that could jeopardize a project, etc.
  • 33. ORGANIZATIONAL STRUCTURE: The structure of the performing organization often constitute the availability of resources in a spectrum from functional to projectized. • Functional organization : Each employee has one clear superior. Staff members are grouped by speciality/ functional departments. ( Finance, Design, Procurement, Construction, etc). Coordination happens between functional heads. • Projectized organization : There is team of various specialties. Team members are collocated and Project managers have a great deal of independence / authority. Coordination happens within the team.
  • 34. PROJECT MANAGEMENT: It is the application of knowledge, skills, tools and techniques to project activities to meet project requirements. • Identifying requirements • Establishing clear and achievable objectives • Balancing the competing demands for quality, scope, time and cost. • Adapting the specifications, plans, and approach to the different concerns and expectations of the various stakeholders.
  • 35. PROJECT MANAGEMENT: Key areas to consider when looking at project management are management of time, people, and other resources. In general terms, these activities can be described as follows: MANAGEMENT OF TIME MANAGEMENT OF PEOPLE MANAGEMENT OF OTHER RESOURCES Ensuring that the Project completes its work on time Ensuring that people are available at the right time Ensuring that appropriate resources are allocated Scheduling use of resources Ensuring that personnel know their roles and can perform their functions properly Ensuring that the appropriate resources are available at the right time Rescheduling the project in the light of experience Managing people’s expectations Reallocating resources in the light of experience Predicting problems before they arise Resolving conflicts between people Tailoring activities to limited resources Changing people’s roles in the light of experience Making maximum impact with available resources
  • 36. PROJECT MANAGEMENT ACTIVITIES : • Planning the work or objectives • Analysis & design of objectives and events • Assessing and controlling risk (or Risk Management) • Estimating resources • Allocation of resources • Organizing the work • Acquiring human and material resources • Assigning tasks • Directing activities • Controlling project execution • Tracking and reporting progress • Analysing the results based on the facts achieved • Forecasting future trends in the project • Quality Management • Issues management • Issue solving • Defect prevention • Identifying, managing & controlling changes • Project closure • Communicating to stakeholders
  • 39. PROJECT LIFE CYCLE 3. Project Execution This stage is where the meat of the project happens. Deliverables are built to make sure the project is meeting requirements. This is where most of the time, money, and people are pulled into the project. Introductions: Who’s who? Project background: Why are you doing this project? What are the goals? Project scope: What exactly will you be doing? What kind of work is involved? Project plan: How are we going to do this? What does the roadmap look like? Roles: Who will be responsible for which elements of the project? Communication: What kind of communication channels will be used? What kind of meetings or status reports should your team expect? Tools: What tools will be used to complete the project, and how will they be used? Next steps: What are the immediate action items that need to be completed? Q&A: Open the floor for any questions
  • 40.
  • 41. PROJECT LIFE CYCLE 4. Project Monitoring and Control • Monitoring and control are sometimes combined with execution because they often occur at the same time. As teams execute their project plan, they must constantly monitor their own progress. • To guaranteed delivery of what was promised, teams must monitor tasks to prevent scope creep, calculate key performance indicators and track variations from allotted cost and time. This constant vigilance helps keep the project moving ahead smoothly. 5. Project Closure • Teams close a project when they deliver the finished project to the customer, communicating completion to stakeholders and releasing resources to other projects. This vital step in the project lifecycle allows the team to evaluate and document the project and move on the next one, using previous project mistakes and successes to build stronger processes and more successful teams. • Although project management may seem overwhelming at times, breaking it down into these five distinct cycles can help your team manage even the most complex projects and use time and resources more wisely.
  • 43. PROJECT REPORT: It is a concise copy of detailed analysis done for the project. • An entrepreneur/expert prepares the report before the investment in project is done. • The report assesses the demand for proposed product/service, works out cost of investment and profitability on this investment. • It acts as an instrument to convince investors to invest in the project. • A project report gives information on the following: • Economic aspects – present market, scope for growth, justification for investment. • Technical aspects – technology, machinery, equipment needed. • Financial aspects – Total investment needed, entrepreneur’s contribution, cost of capital and return on capital. • Marketing aspects – Product details, justification for the choice of product, sale. • Managerial aspects – Qualifications, experience of people needed for managerial posts.
  • 44. CONTENT OF PROJECT REPORT: • Objectives and scope of the report. • Product characteristics (product design, specifications, quality standards, uses and applications). • Market position and trends (current capacity for production, potential demand, sale prospects, price structure etc). • Raw materials (types, quality, sources, price). • Construction (process, production schedule, technique used. • Plant and machinery (types, infrastructure support, cost). • Land and building (Requirement, building construction schedule, choice of location, cost). • Financial implications (Capital structure, capital investment, project cost, profitability). • Marketing channels (marketing and advertising strategy). • Personnel (Requirement of staff, skilled-unskilled labour, salary and wage payment, qualifications, experience) • The project report is submitted to financial institutions for grant of loan and other financial assistance/concessions. • The financial institutions ascertain from the report, whether the project can generate enough funds to repay the borrowings in stipulated time frame
  • 45. PROJECT MANAGEMENT PROCESS MAPPING: KNOWLEDGE AREA PROCESSESS PROJECT MANAGEMENT PROCESS GROUPS 1. INITIATING PROCESS GROUP 2. PLANNING PROCESS GROUP 3. EXECUTING PROCESS GROUP 4. MONITORING & CONTROL PROCESS GROUP 5. CLOSING PROCESS GROUP 1. PROJECT INTEGRATION MANAGEMENT • DEVELOP PROJECT CHARTER • DEVELOP PRELIMINARY PROJECT SCOPE STATEMENTS DEVELOPMENT PROJECT MANAGEMENT PLAN DIRECT AND MANAGE PROJECT EXECUTION • MONITOR & CONTROL PROJECT WORK • INTEGRATED CHANGE CONTROL CLOSE PROJECT 2. PROJECT SCOPE MANAGEMENT • SCOPE PLANNING • SCOPE DEFINITION • CREATE WORK BREAK-DOWN STRUCTURE • SCOPE VERIFICATION • SCOPE CONTROL 3. PROJECT TIME MANAGEMENT • ACTIVITY DEFINITION • ACTIVITY SEQUENCING • ACTIVITY RESOURCE • ESTIMATION • ACTIVITY DURATION ESTIMATION • SCHEDULE DEVELOPMENT SCHEDULE CONTROL 4. PROJECT COST MANAGEMENT • COST ESTIMATING • COST BUDGETING COST CONTROL 5. PROJECT QUALITY MANAGEMENT • QUALITY PLANNING PERFORM QUALITY ASSURANCE PERFORM QUALITY CONTROL
  • 46. PROJECT MANAGEMENT PROCESS MAPPING: KNOWLEDGE AREA PROCESSESS PROJECT MANAGEMENT PROCESS GROUPS 1. INITIATING PROCESS GROUP 2. PLANNING PROCESS GROUP 3. EXECUTING PROCESS GROUP 4. MONITORING & CONTROL PROCESS GROUP 5. CLOSING PROCESS GROUP 6. PROJECT HUMAN RESOURCE MANAGEMENT HUMAN RESOURCE PLANNING • ACQUIRE PROJECT TEAM • DEVELOP PROJECT TEAM • MANAGE PROJECT TEAM 7. PROJECT COMMUNICATIONS MANAGEMENT COMMUNICATIONS PLANNING • INFORMATION DISTRIBUTION • PERFORMANCE REPORTING • MANAGE STAKEHOLDERS 8. PROJECT RISK MANAGEMENT • RISK MANAGEMENT PLANNING • RISK IDENTIFICATION • QUALITATIVE RISK ANALYSIS • QUANTITATIVE RISK ANALYSIS RISK MONITORING AND CONTROL 9. PROJECT PROCUREMENT MANAGEMENT • PLAN PURCHASES AND ACQUISITIONS • PLAN CONTRACTING • REQUEST SELLER • RESPONSE • SELECT SELLERS CONTRACT ADMINISTRATION CONTRACT CLOSURE
  • 47. Investment criteria Investment Criteria Non Discounting Criteria Payback Period Accounting rate of return Discounting Criteria Net Present Value Benefit cost ratio Internal Rate of return
  • 48. Rate of Return (RoR) A rate of return (RoR) is the net gain or loss on an investment over a specified time period, expressed as a percentage of the investment’s initial cost. Gains on investments are defined as income received plus any capital gains realized on the sale of the investment.
  • 49. The rate of return is used to measure growth between two periods, rather than over several periods. The RoR can be used for many purposes, from evaluating investment growth to year-over-year changes in company revenues. The RoR calculation does not consider the effects of inflation.
  • 50. What is the Payback Period? The payback period shows how long it takes for a business to recoup its investment. this type of analysis allows firms to compare alternative investment opportunities and decide on a project that returns its investment in the shortest time, if that criteria is important to them.
  • 51. Example: Consider the previous investment project. The initial cost is $600 million. It has been decided that the project should be accepted if the payback period is 3 years or less. Using the payback rule, should this project be undertaken? Year Cash Flow Accumulated Cash Flow 1 $200.00 $200 2 220.00 3 225.00 4 210.00 $420 $645 > $600 $855 ILLUSTRATION
  • 52. Advantages and Disadvantages of the Payback Rule Advantages Simple & quick calculation Disadvantages Ignores time value of money Ignore cash flow after payback period Popular among many large companies, Commonly used when the:  capital investment is small  merits of the project are so obvious that more formal analysis is unnecessary
  • 53. An organization has to take many decisions regarding the expansion of business and investment. In such cases, the organization will take the help of NPV method and base its decision on the same. Net present value is used in Capital budgeting to analyze the profitability of a project or investment. It is calculated by taking the difference between the present value of cash inflows and present value of cash outflows over a period of time. As the name suggests, net present value is nothing but net off of the present value of cash inflows and outflows by discounting the flows at a specified rate. NPV ( Net Present Value )
  • 54. Formula for NPV NPV = (Cash flows)/( 1+r)i i- Initial Investment Cash flows= Cash flows in the time period r = Discount rate i = time period As seen in the formula – To derive the present value of the cash flows we need to discount them at a particular rate. This rate is derived considering the return of investment with similar risk or cost of borrowing, for the investment.
  • 55. NPV takes into consideration the time value of money. The time value of money simply means that a rupee today is of more value today than it will be tomorrow. Consider it this way: You have Rs. 100 today and you can buy ten chocolates. The same Rs. 100 will be able to get you not more than the same 5 chocolates may be after one year. So the cash flows earned today are of more value than as on a later date. After discounting the cash flows over different periods, the initial investment is deducted from it.  If the result is a positive NPV then the project is accepted.  If the NPV is negative the project is rejected.  And if NPV is zero then the organization will stay indifferent. ILLUSTRATION
  • 56. Year Flow Present value Computation 0 -1000000 -1000000 1 100000 91743 100000/(1.09) 2 250000 210419 250000/(1.09)^2 3 350000 270264 350000/(1.09)^3 4 265000 187732 265000/(1.09)^4 5 415000 269721 415000/(1.09)^5 Let us say XYZ Ltd wants to do a project and so it is willing to invest Rs 10,00,000. The investment is said to bring an inflow of Rs. 100,000 in first year, 250,000 in the second year, 350,000 in third year, 265,000 in fourth year and 415,000 in fifth year. Assuming the discount rate to be 9%. Let us calculate NPV using the formula. ILLUSTRATION Here NPV is Rs. 29881.
  • 57. The internal rate of return (IRR) is a metric used in capital budgeting to estimate the profitability of potential investments. The internal rate of return is a discount rate that makes the net present value (NPV) of all cash flows from a particular project equal to zero. IRR calculations rely on the same formula as NPV does. Internal Rate of Return (IRR) IRR=NPV=t=1∑T​(1+r)tCt​​−C0​=0 where:Ct​=net cash inflow during the period t C0​=total initial investment costs r=the discount rate, and t=the number of time periods​ T IRR=NPV= ∑ (Ct) - C0 T=1 (1+r)t where: Ct​=net cash inflow during the period t C0​=total initial investment costs r=the discount rate, and t=the number of time periods​
  • 58. What Does IRR Tell You? You can think of the internal rate of return as the rate of growth a project is expected to generate. While the actual rate of return that a given project ends up generating will often differ from its estimated IRR, a project with a substantially higher IRR value than other available options would still provide a much better chance of strong growth. One popular use of IRR is comparing the profitability of establishing new operations with that of expanding existing ones. For example, an energy company may use IRR in deciding whether to open a new power plant or to renovate and expand a previously existing one. While both projects are likely to add value to the company, it is likely that one will be the more logical decision as prescribed by IRR.
  • 59. Key Take aways: • IRR is the rate of growth a project is expected to generate. • IRR is calculated by the condition that the discount rate is set such that the NPV = 0 for a project. • IRR is used in capital budgeting to decide which projects or investments to undertake and which to forgo. Compute present values of each net cash flow. Multiply the net cash flow for each period by its discount factor to obtain its present value. Sum the present values of each cash flow to calculate the NPV. Find the IRR, the discount rate, that makes the NPV zero.
  • 60. Cost Benefits Analysis (CBA) Benefit Cost Analysis (BCA) is an economic tool for government policy and investment project analysis used widely Can incorporate environmental impacts of policies/projects within CBA to correct for market failure “Social” appraisal of policies and projects, carried out by aggregation of benefits from, and costs of a policy/project over individuals and over time Welfare theoretic underpinning: Economic efficiency with a temporal dimension
  • 61. Relates to the environment in three ways:  Projects/policies may have negative environmental effects, i.e. negative externalities (public and private)  Projects/policies may have positive externalities (public)  Projects/policies may have both positive and negative externalities (public and private) Externalities should be included in CBA in order to correct for market failure
  • 62. Welfare Economics Background CBA is firmly based in welfare theory in three ways In terms of how gains and losses are measured Consumers: Changes in consumer surplus as a result of changes in quantity and quality of environmental goods Producers: Changes in producer surplus as a result of changes in prices and quantity and quality of inputs Makes use of the opportunity cost (scarcity rents) concept to asses costs of using scarce resources
  • 63. What counts as costs and benefits ◦ Welfare economics evaluates alternative resource allocations in terms of their effects on utility ◦ CBA includes any impact on utility whether or not they are reflected in market prices Welfare Economics Background
  • 64. In terms of aggregation and comparison of costs and benefits ◦ Policies and projects have a mixture of gains and losses across individuals ◦ Gains and losses are calculated in money terms, added up and compared to find out the net impact on welfare (net gain or net loss) ◦ Measure of the change in social welfare is based on Kaldor- Hick Criterion: Could gainers compensate the losers and still be better off? ◦ This criterion considers economic efficiency but interpersonal welfare impacts, i.e. Distribution of gains and losses are not considered
  • 65. Stages of CBA Stage 1: Definition of policy/project: ◦ The reallocation of resources being proposed ◦ The population of gainers and losers being considered Stage 2: Identification of policy/project impacts: ◦ Define all impacts that will result from policy/project implementation ◦ Consider additionally (net impacts) and displacement (crowding out)
  • 66. Stage 3: Identification of economically relevant impacts: Environmental impacts of a policy/project are relevant in CBA if either ◦ They change the utility of at least one person in the society ◦ They change the quantity or quality of the output of some positively valued commodity Stage 4: Physical quantification of relevant impacts: ◦ Determine physical amounts of costs and benefits and when they occur in time ◦ Use environmental impact analysis to estimate the impact of policy/project on the environment ◦ Estimations will be made with uncertainty, calculate the expected value of costs and benefits
  • 67. Stage 5: Monetary valuation of relevant effects ◦All physical measures of impacts should be valued in common units to be comparable ◦Common unit = money ◦CBA analyst must ◦ Predict prices for value flows extending into the future ◦ Correct market prices where they are distorted ◦ Calculate prices where non exists using environmental valuation methods
  • 68. Stage 6: Discounting of costs and benefits: ◦ Once costs and benefits are expressed in monetary units they should be converted to present value terms by discounting ◦ PV= Xt[(1+r)-t] where X= cost or benefit; r = discount rate; [(1+r)-t] discount factor; t= time ◦ The higher the value of t the lower the discount factor ◦ The higher the discount rate for a given t the lower the discount factor
  • 69. Stage 7:Applying the net present value test: ◦ Apply NPV test to choose those policies and projects that are efficient in terms of their use of resources ◦ Where Bt = benefits of the project at period t, Ct = the costs of the project at period t, r = the discount rate, n = the number of years over which the project will operate ◦ NPV is the present value of the project’s/policy’s net benefit stream, obtained by discounting the stream of net benefits produced by the project/policy over its lifetime, back to its value in the chosen base period, usually the present. ◦ If NPV>0 accept policy or project (Based in Kaldor-Hicks Criterion) since it would improve social welfare ( ) ( )∑= + −n t t tt r CB 0 1
  • 70. Alternatives to NPV Benefit – Cost ratio (BCR): It is the ratio of the sum of the project’s or policy’s discounted benefits to the sum of its discounted costs. If BCR>1 go ahead with the project/policy. t t n t n t t t r C r B BCR )1( )( )1( )( 0 0 + + = ∑ ∑ = =
  • 71. Stage 8: Sensitivity analysis: ◦ NPV test gives relative efficiency of a project given the data on prices, environmental and economic impacts and discount rate but any of these data might change due to uncertainty ◦ Recalculate NPV when the key parameters change to discover which one(s) of them the NPV is most sensitive to ◦ Once the most sensitive parameter is identified direct forecasting effort to improve best guess and more effort to manage these parameters carefully
  • 72. Total Economic Value (TEV) Environmental goods are public goods, they are not traded in the markets and hence they do not have readily available market prices The value of environmental good is not only derived from its direct consumption but also from its indirect consumption, as well as non- use. The broad concept of value is known as the Total Economic Value (TEV)
  • 73. Direct Use Value Indirect Use Value Actual use Value Option Value Use Value Existence Value Bequest Value Altruistic Value For Others Non-use Value Total Economic Value
  • 74. TEV Deforestation Direct use values: Timber values, fuelwood and charcoal extraction, non-timber forest products (NTFP), biodiversity and genetic information, tourism and recreational values. Indirect use values: Protection of watersheds and the storage of carbon and sequestration. Option values: values reflecting a willingness to pay to conserve the option of making use of the forest even though no current use is made of it Non-use values (also known as existence or passive use values): these values reflect a willingness to pay for the forest in a conserved or sustainable use state, but the willingness to pay is unrelated to current or planned use of the forest.