SlideShare a Scribd company logo
1 of 31
Download to read offline
Foundation design for tall buildings
From Pile Groups to Piled Rafts
Benoît Latapie
Technical Manager – Ground Engineering
16 November 2016 1
Underground Infrastructure and Deep Foundations UAE
1. Introduction to Combined Pile Raft Foundations (CPRF)
2. Foundation design procedure / Case study
3. Existing buildings on CPRF in Dubai
4. Why carry out a preliminary test pile early and to failure?
5. Benefits of using BS8004:2015
6. Common ME practice VS Atkins geotechnical approach
7. Conclusions
8. References
Foundation design for tall buildings
16 November 2016 2
From Pile Groups to Piled Rafts – Contents
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0 1 2 3 4 5 6 7 8 9 10
Pile spacing in multiples of its diameter Ø
Negligible pile interaction
Intro. to Combined Pile Raft Foundation
16 November 2016 3
Pile group interaction
Shearstressnormalisedbyshearstressatpile/rockinterface(-)
Most CPRF have average
pile spacing larger than 5Ø
Typical range of fully
piled foundations
High pile interaction
Piles close to each other
are not efficient.
Larger pile spacing have
the following benefits:
• Decreases pile-to-pile
interactions
• Increases pile
utilisation
• Increases foundation
efficiency
After the studies of Cooke (1974), Frank (1974) and Baguelin et al. (1975).
• Composite foundation that combines the bearing resistance of both raft and piles
• Building loads shared between the piles and the raft
• Piles are settlement reducers
• The raft provides additional load capacity to the piles
• Stiffness governs the design over bearing capacity
Intro. to Combined Pile Raft Foundation
16 November 2016 4
Design philosophy
Piled foundation design = Capacity Limiting + Settlement Check
CPRF design = Settlement Limiting + Capacity Check
Intro. to Combined Pile Raft Foundation
16 November 2016 5
The different types of foundations using rafts and piles
Source:Burland,J.,Chapman,T.,Skinner,H.D.andBrown,
M.,2012.ICEManualofGeotechnicalEngineering.
Piles located to reduce
shear and bending in raft.
Pile capacity fully
mobilised.
B - Pile-enhanced raft
Piles at larger spacing than
conventional pile group.
Piles located to minimise
differential settlement.
Intro. to Combined Pile Raft Foundation
16 November 2016 6
The different types of foundations using rafts and piles
Source: Burland, J., Chapman, T., Skinner, H.D. and Brown, M., 2012. ICE Manual of Geotechnical Engineering.
C - raft-enhanced pile group
Intro. to Combined Pile Raft Foundation
16 November 2016 7
Complex soil-structure interaction mechanisms
1. Raft–soil interaction: The contact stresses between the raft and
the soil are transmitted into the soil and settlement of the raft
takes place.
2. Raft–soil–raft interaction: Interaction takes place through the soil
with other parts of the raft.
3. Raft–soil–pile interaction: The raft contact stresses are also
transmitted through the soil and interact with the piles.
4. Raft–pile interaction: Loads are transmitted into the piles directly
by the raft.
5. Pile–soil interaction: The pile loads disperse into the ground
surrounding the piles.
6. Pile–soil–pile interaction: Interaction takes place between each
pile through the soil to other piles.
7. Pile–soil–raft interaction: Interaction also takes place between
each pile through the soil to the underside of the raft.
Source: Burland, J., Chapman, T., Skinner, H.D. and Brown,
M., 2012. ICE Manual of Geotechnical Engineering.
1. Introduction to Combined Pile Raft Foundations (CPRF)
2. Foundation design procedure / Case study
3. Existing buildings on CPRF in Dubai
4. Why carry out a preliminary test pile early and to failure?
5. Benefits of using BS8004:2015
6. Common ME practice VS Atkins geotechnical approach
7. Conclusions
8. References
Foundation design for tall buildings
16 November 2016 8
From Pile Groups to Piled Rafts – Contents
9
Foundation Design Procedure
16 November 2016
Outputs from the geotechnical analysis
For all structural elements, deflections, axial
forces, shear forces and bending moment
diagrams are available in the output.
Confidential project – case study
16 November 2016 10
Confidential project – case study
11
Plaxis 3D settlements
Maximum settlement: 42mm
16 November 2016
Confidential project – case study
16 November 2016 12
SAFE settlements with Springs from Plaxis 3D
Maximum settlement: 47mm
Confidential project – case study
16 November 2016 13
SAFE settlements with Springs from SI Report
Maximum settlement: 13mm
1. Introduction to Combined Pile Raft Foundations (CPRF)
2. Foundation design procedure / Case study
3. Existing buildings on CPRF in Dubai
4. Why carry out a preliminary test pile early and to failure?
5. Benefits of using BS8004:2015
6. Common ME practice VS Atkins geotechnical approach
7. Conclusions
8. References
Foundation design for tall buildings
16 November 2016 14
From Pile Groups to Piled Rafts – Contents
Existing tall buildings with CPRF in Dubai
16 November 2016 15
A few numbers from published literature
Building Height
Foundation System
(dimensions)
Predicted
Settlement
Built
Emirates Twin Towers 355m
Combined Piled Raft Foundation
(1.2mØ, 45m piles & 1.5m thick raft)
140mm
(1/378)
Burj Khalifa 828m
Combined Piled Raft Foundation
(1.5mØ, 50m piles & 3.7m thick raft)
80mm
(1/250)
OnHold
Pentominium Tower 516m
Combined Piled Raft Foundation
(1.2-1.5mØ, 32-42m piles & 5m thick raft)
92mm
Nakheel Tall Tower 1,000m
Combined Piled Raft Foundation
(2.8mx1.2m, up to 58m barrettes & up to 8m thick raft)
Up to
100mm
Existing CPRF arrangements in Dubai 1/2
16 November 2016 16
Emirates Twin Towers Burj Khalifa
Contours of maximum axial load [kN]
Typ. layout of one tower
Existing CPRF arrangements in Dubai 2/2
16 November 2016 17
Pentominium Tower (on hold) Nakheel Tall Tower (on hold)
1. Introduction to Combined Pile Raft Foundations (CPRF)
2. Foundation design procedure / Case study
3. Existing buildings on CPRF in Dubai
4. Why carry out a preliminary test pile early and to failure?
5. Benefits of using BS8004:2015
6. Common ME practice VS Atkins geotechnical approach
7. Conclusions
8. References
Foundation design for tall buildings
16 November 2016 18
From Pile Groups to Piled Rafts – Contents
Recommendations – PTP to failure
16 November 2016 19
Recommendations – PTP to failure
16 November 2016 20
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
0 10 20 30 40 50 60 70 80 90 100
TotalAxialLoad[MN]–Example,typical
Deflection at Pile's Head [mm] – Example, typical
Pile Load Test To Failure
Conservative Pile Load Test
Recommendations – PTP to failure
16 November 2016 21
Optimised
working load
We propose to test the pile
to geotechnical failure
FoS=2
FoS=2
Conservative test stops
at empirical capacity
Under estimated
working load
1. Introduction to Combined Pile Raft Foundations (CPRF)
2. Foundation design procedure / Case study
3. Existing buildings on CPRF in Dubai
4. Why carry out a preliminary test pile early and to failure?
5. Benefits of using BS8004:2015
6. Common ME practice VS Atkins geotechnical approach
7. Conclusions
8. References
Foundation design for tall buildings
16 November 2016 22
From Pile Groups to Piled Rafts – Contents
Benefits of using BS 8004:2015
16 November 2016 23
Time for an update?
https://login.dm.gov.ae/wps/wcm/connect/29d53e7c-7f22-4c42-aded-
066727d87c0f/Structural+Codes+%26+guidelines+4.pdf?MOD=AJPERES
• BS 8004:2015 was updated in line with the Eurocodes
• Partial factors may be reduced if pile load tests are carried out
• Clear and detailed guidance on foundation design
• Piled rafts are addressed with reference to
ICE Manual of Geotechnical Engineering (2012), Volume II, Chapter 56 is provided.
Benefits of using BS 8004:2015
16 November 2016 24
Time for an update?
Benefits of using BS 8004:2015
16 November 2016 25
Partial factors reduction based on in situ pile testing
• Two partial factors are used in pile design to BS 8004:2015 (or/and BS EN 1997-1)
 γRd model factor, used to obtain the characteristic ultimate pile
compressive resistance Rc,k
 γs and γb partial resistance factors for shaft and end bearing respectively.
Partial
factor
Default
Value
Testing to BS 8004:2015
(i.e. UK NA to BS EN 1997-1)
Revised
Value
Saving
γRd 1.4
Maintained load test taken to the required
unfactored ultimate resistance
1.2 14%
γs 1.6 Explicit verification of SLS:
Working test on 1% of constructed piles to loads
not less than 1.5 times the representative load.
1.4 12%
γb 2.0 1.7 15%
Total SAVING
Minimum 25%
1. Introduction to Combined Pile Raft Foundations (CPRF)
2. Foundation design procedure / Case study
3. Existing buildings on CPRF in Dubai
4. Why carry out a preliminary test pile early and to failure?
5. Benefits of using BS8004:2015
6. Common ME practice VS Atkins geotechnical approach
7. Conclusions
8. References
Foundation design for tall buildings
16 November 2016 26
From Pile Groups to Piled Rafts – Contents
Common geotechnical approach in ME
• Early stage project involvement
• Desk study
• Design/scoping and specification of high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
27
STANDALONE
GROUND
INVESTIGATION
CONTRACTOR
CONSERVATIVE / UN-ECONOMIC / RISKY SOLUTION
ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION
• Early stage project involvement
• Desk study
• Design/scoping and specification of high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
Atkins proposal to reduce geotechnical risk
28
SPECIALISTGEOTECHNICAL
CONSULTANT
By GI Contractor
1. Foundation design for tall buildings is complex and requires sophisticated analyses
2. 3D FE analyses encompass soil-structure interactions
3. CPRF are economical and proven in Dubai
4. Preliminary test piles with O-cells help reduce cost and risk
5. BS8004:2015 is recommended for the design of foundations
6. Ignoring project specific data raises the foundation risk
7. Employing a specialist geotechnical consultant is recommended to maximise
opportunities
Conclusions
16 November 2016 29
• BS 8004:2015 Code of practice for foundations
• Haberfield, C.M. and Paul, D.R. 2011. Footing Design of the Nakheel Tower, Dubai,
UAE in Workshop on soil-structure interaction and retaining walls. Proceedings of the
Technical Meeting TC207 ISSMGE, Dubrovnik, pp 35 to 52.
• Poulos, H.G. and Bunce, G., 2008. Foundation design for the Burj Dubai–the world’s
tallest building. 6th International Conference on Case Histories in Geotechnical
Engineering, Arlington, VA.
• Poulos, H.G. and Davids, A.J., 2005. Foundation design for the Emirates twin towers,
Dubai. Canadian Geotechnical Journal, 42(3), pp.716-730.
• Ibrahim, K., Bunce, G. and Murrells, C., 2009, December. Foundation design for the
Pentominium tower in Dubai, UAE. In Proceedings of the Institution of Civil
Engineers-Civil Engineering (Vol. 162, No. 6, pp. 25-33). Thomas Telford Ltd.
References
16 November 2016 30
Foundation design for tall buildings
From Pile Groups to Piled Rafts
Benoît Latapie
Technical Manager – Ground Engineering
benoit.latapie@atkinsglobal.com
16 November 2016 31
Underground Infrastructure and Deep Foundations UAE
QUESTIONS?

More Related Content

What's hot

Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practiceWeb2Present
 
Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014ILIAS MICHALIS
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete RoadwaysJill Reeves
 
PCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. ReconstructionPCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. ReconstructionJill Reeves
 
Major structure - Decoded
Major structure - DecodedMajor structure - Decoded
Major structure - DecodedChandanKriss
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011ILIAS MICHALIS
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipmentsR VIJAYAKUMAR
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsPath Marketing Inc.
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodeSAT Journals
 
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...IRJET Journal
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular ConcreteJill Reeves
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationGihan Anuradha Bombuwala
 
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Dr. Amarjeet Singh
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaStephen McKnight
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Lecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copyLecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copytaye2020
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeJill Reeves
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 

What's hot (20)

Offshore pile design according to international practice
Offshore pile design according to international practiceOffshore pile design according to international practice
Offshore pile design according to international practice
 
Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete Roadways
 
PCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. ReconstructionPCC Pavement: Repair vs. Overlay vs. Reconstruction
PCC Pavement: Repair vs. Overlay vs. Reconstruction
 
Major structure - Decoded
Major structure - DecodedMajor structure - Decoded
Major structure - Decoded
 
Paper European Conference Athens 2011
Paper European Conference Athens 2011Paper European Conference Athens 2011
Paper European Conference Athens 2011
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipments
 
Culvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & ApplicationsCulvert Design 201 Structural Design, Durability & Applications
Culvert Design 201 Structural Design, Durability & Applications
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing method
 
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training Presentation
 
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
Sustainable Solution for Shoring Method of Cross-Creek Bridge in Ankeng MRT S...
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Lecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copyLecture01 140412064456-phpapp02 - copy
Lecture01 140412064456-phpapp02 - copy
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel Bridge
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 

Similar to 161115 FDTB - from pile group to piled raft_Benoit Latapie

The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsChris Bridges
 
Effect of long term loading on horizontal uplift capacity of rectangular plat...
Effect of long term loading on horizontal uplift capacity of rectangular plat...Effect of long term loading on horizontal uplift capacity of rectangular plat...
Effect of long term loading on horizontal uplift capacity of rectangular plat...Nirjhar Basak
 
BOS_Foundationl Engineering PPT.pptx
BOS_Foundationl Engineering PPT.pptxBOS_Foundationl Engineering PPT.pptx
BOS_Foundationl Engineering PPT.pptxMrBhaskarWabhitkar
 
Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...
Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...
Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...Geological Survey of Sweden
 
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENABenoit Latapie
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structuresEva Lantsoght
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraProSIM R & D Pvt. Ltd.
 
Numerical simulation and optimization of pile design
Numerical simulation and optimization of pile designNumerical simulation and optimization of pile design
Numerical simulation and optimization of pile designIRJET Journal
 
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptxVIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptxnorzilanoh1
 
Sand Control
Sand Control Sand Control
Sand Control petroEDGE
 
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdfNeohChengAik
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanEr.Karan Chauhan
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureIJERA Editor
 

Similar to 161115 FDTB - from pile group to piled raft_Benoit Latapie (20)

The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankments
 
Effect of long term loading on horizontal uplift capacity of rectangular plat...
Effect of long term loading on horizontal uplift capacity of rectangular plat...Effect of long term loading on horizontal uplift capacity of rectangular plat...
Effect of long term loading on horizontal uplift capacity of rectangular plat...
 
Shib
ShibShib
Shib
 
BOS_Foundationl Engineering PPT.pptx
BOS_Foundationl Engineering PPT.pptxBOS_Foundationl Engineering PPT.pptx
BOS_Foundationl Engineering PPT.pptx
 
Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...
Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...
Experiences from International Test and Storage Projects. Auli Niemi, Uppsala...
 
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA
 
Load testing of structures
Load testing of structuresLoad testing of structures
Load testing of structures
 
What PINS expects from applications
What PINS expects from applicationsWhat PINS expects from applications
What PINS expects from applications
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Numerical simulation and optimization of pile design
Numerical simulation and optimization of pile designNumerical simulation and optimization of pile design
Numerical simulation and optimization of pile design
 
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptxVIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
Sand Control
Sand Control Sand Control
Sand Control
 
Roy Shilling
Roy ShillingRoy Shilling
Roy Shilling
 
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
00-Slides-IEM Course-Site Supervision-Displ Piles-18 Jun 22 - Copy.pdf
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan Chauhan
 
ShortPresentationUTCB.pptx
ShortPresentationUTCB.pptxShortPresentationUTCB.pptx
ShortPresentationUTCB.pptx
 
Bridge report
Bridge reportBridge report
Bridge report
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
 

161115 FDTB - from pile group to piled raft_Benoit Latapie

  • 1. Foundation design for tall buildings From Pile Groups to Piled Rafts Benoît Latapie Technical Manager – Ground Engineering 16 November 2016 1 Underground Infrastructure and Deep Foundations UAE
  • 2. 1. Introduction to Combined Pile Raft Foundations (CPRF) 2. Foundation design procedure / Case study 3. Existing buildings on CPRF in Dubai 4. Why carry out a preliminary test pile early and to failure? 5. Benefits of using BS8004:2015 6. Common ME practice VS Atkins geotechnical approach 7. Conclusions 8. References Foundation design for tall buildings 16 November 2016 2 From Pile Groups to Piled Rafts – Contents
  • 3. 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0 1 2 3 4 5 6 7 8 9 10 Pile spacing in multiples of its diameter Ø Negligible pile interaction Intro. to Combined Pile Raft Foundation 16 November 2016 3 Pile group interaction Shearstressnormalisedbyshearstressatpile/rockinterface(-) Most CPRF have average pile spacing larger than 5Ø Typical range of fully piled foundations High pile interaction Piles close to each other are not efficient. Larger pile spacing have the following benefits: • Decreases pile-to-pile interactions • Increases pile utilisation • Increases foundation efficiency After the studies of Cooke (1974), Frank (1974) and Baguelin et al. (1975).
  • 4. • Composite foundation that combines the bearing resistance of both raft and piles • Building loads shared between the piles and the raft • Piles are settlement reducers • The raft provides additional load capacity to the piles • Stiffness governs the design over bearing capacity Intro. to Combined Pile Raft Foundation 16 November 2016 4 Design philosophy Piled foundation design = Capacity Limiting + Settlement Check CPRF design = Settlement Limiting + Capacity Check
  • 5. Intro. to Combined Pile Raft Foundation 16 November 2016 5 The different types of foundations using rafts and piles Source:Burland,J.,Chapman,T.,Skinner,H.D.andBrown, M.,2012.ICEManualofGeotechnicalEngineering.
  • 6. Piles located to reduce shear and bending in raft. Pile capacity fully mobilised. B - Pile-enhanced raft Piles at larger spacing than conventional pile group. Piles located to minimise differential settlement. Intro. to Combined Pile Raft Foundation 16 November 2016 6 The different types of foundations using rafts and piles Source: Burland, J., Chapman, T., Skinner, H.D. and Brown, M., 2012. ICE Manual of Geotechnical Engineering. C - raft-enhanced pile group
  • 7. Intro. to Combined Pile Raft Foundation 16 November 2016 7 Complex soil-structure interaction mechanisms 1. Raft–soil interaction: The contact stresses between the raft and the soil are transmitted into the soil and settlement of the raft takes place. 2. Raft–soil–raft interaction: Interaction takes place through the soil with other parts of the raft. 3. Raft–soil–pile interaction: The raft contact stresses are also transmitted through the soil and interact with the piles. 4. Raft–pile interaction: Loads are transmitted into the piles directly by the raft. 5. Pile–soil interaction: The pile loads disperse into the ground surrounding the piles. 6. Pile–soil–pile interaction: Interaction takes place between each pile through the soil to other piles. 7. Pile–soil–raft interaction: Interaction also takes place between each pile through the soil to the underside of the raft. Source: Burland, J., Chapman, T., Skinner, H.D. and Brown, M., 2012. ICE Manual of Geotechnical Engineering.
  • 8. 1. Introduction to Combined Pile Raft Foundations (CPRF) 2. Foundation design procedure / Case study 3. Existing buildings on CPRF in Dubai 4. Why carry out a preliminary test pile early and to failure? 5. Benefits of using BS8004:2015 6. Common ME practice VS Atkins geotechnical approach 7. Conclusions 8. References Foundation design for tall buildings 16 November 2016 8 From Pile Groups to Piled Rafts – Contents
  • 9. 9 Foundation Design Procedure 16 November 2016 Outputs from the geotechnical analysis For all structural elements, deflections, axial forces, shear forces and bending moment diagrams are available in the output.
  • 10. Confidential project – case study 16 November 2016 10
  • 11. Confidential project – case study 11 Plaxis 3D settlements Maximum settlement: 42mm 16 November 2016
  • 12. Confidential project – case study 16 November 2016 12 SAFE settlements with Springs from Plaxis 3D Maximum settlement: 47mm
  • 13. Confidential project – case study 16 November 2016 13 SAFE settlements with Springs from SI Report Maximum settlement: 13mm
  • 14. 1. Introduction to Combined Pile Raft Foundations (CPRF) 2. Foundation design procedure / Case study 3. Existing buildings on CPRF in Dubai 4. Why carry out a preliminary test pile early and to failure? 5. Benefits of using BS8004:2015 6. Common ME practice VS Atkins geotechnical approach 7. Conclusions 8. References Foundation design for tall buildings 16 November 2016 14 From Pile Groups to Piled Rafts – Contents
  • 15. Existing tall buildings with CPRF in Dubai 16 November 2016 15 A few numbers from published literature Building Height Foundation System (dimensions) Predicted Settlement Built Emirates Twin Towers 355m Combined Piled Raft Foundation (1.2mØ, 45m piles & 1.5m thick raft) 140mm (1/378) Burj Khalifa 828m Combined Piled Raft Foundation (1.5mØ, 50m piles & 3.7m thick raft) 80mm (1/250) OnHold Pentominium Tower 516m Combined Piled Raft Foundation (1.2-1.5mØ, 32-42m piles & 5m thick raft) 92mm Nakheel Tall Tower 1,000m Combined Piled Raft Foundation (2.8mx1.2m, up to 58m barrettes & up to 8m thick raft) Up to 100mm
  • 16. Existing CPRF arrangements in Dubai 1/2 16 November 2016 16 Emirates Twin Towers Burj Khalifa Contours of maximum axial load [kN] Typ. layout of one tower
  • 17. Existing CPRF arrangements in Dubai 2/2 16 November 2016 17 Pentominium Tower (on hold) Nakheel Tall Tower (on hold)
  • 18. 1. Introduction to Combined Pile Raft Foundations (CPRF) 2. Foundation design procedure / Case study 3. Existing buildings on CPRF in Dubai 4. Why carry out a preliminary test pile early and to failure? 5. Benefits of using BS8004:2015 6. Common ME practice VS Atkins geotechnical approach 7. Conclusions 8. References Foundation design for tall buildings 16 November 2016 18 From Pile Groups to Piled Rafts – Contents
  • 19. Recommendations – PTP to failure 16 November 2016 19
  • 20. Recommendations – PTP to failure 16 November 2016 20
  • 21. 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 0 10 20 30 40 50 60 70 80 90 100 TotalAxialLoad[MN]–Example,typical Deflection at Pile's Head [mm] – Example, typical Pile Load Test To Failure Conservative Pile Load Test Recommendations – PTP to failure 16 November 2016 21 Optimised working load We propose to test the pile to geotechnical failure FoS=2 FoS=2 Conservative test stops at empirical capacity Under estimated working load
  • 22. 1. Introduction to Combined Pile Raft Foundations (CPRF) 2. Foundation design procedure / Case study 3. Existing buildings on CPRF in Dubai 4. Why carry out a preliminary test pile early and to failure? 5. Benefits of using BS8004:2015 6. Common ME practice VS Atkins geotechnical approach 7. Conclusions 8. References Foundation design for tall buildings 16 November 2016 22 From Pile Groups to Piled Rafts – Contents
  • 23. Benefits of using BS 8004:2015 16 November 2016 23 Time for an update? https://login.dm.gov.ae/wps/wcm/connect/29d53e7c-7f22-4c42-aded- 066727d87c0f/Structural+Codes+%26+guidelines+4.pdf?MOD=AJPERES
  • 24. • BS 8004:2015 was updated in line with the Eurocodes • Partial factors may be reduced if pile load tests are carried out • Clear and detailed guidance on foundation design • Piled rafts are addressed with reference to ICE Manual of Geotechnical Engineering (2012), Volume II, Chapter 56 is provided. Benefits of using BS 8004:2015 16 November 2016 24 Time for an update?
  • 25. Benefits of using BS 8004:2015 16 November 2016 25 Partial factors reduction based on in situ pile testing • Two partial factors are used in pile design to BS 8004:2015 (or/and BS EN 1997-1)  γRd model factor, used to obtain the characteristic ultimate pile compressive resistance Rc,k  γs and γb partial resistance factors for shaft and end bearing respectively. Partial factor Default Value Testing to BS 8004:2015 (i.e. UK NA to BS EN 1997-1) Revised Value Saving γRd 1.4 Maintained load test taken to the required unfactored ultimate resistance 1.2 14% γs 1.6 Explicit verification of SLS: Working test on 1% of constructed piles to loads not less than 1.5 times the representative load. 1.4 12% γb 2.0 1.7 15% Total SAVING Minimum 25%
  • 26. 1. Introduction to Combined Pile Raft Foundations (CPRF) 2. Foundation design procedure / Case study 3. Existing buildings on CPRF in Dubai 4. Why carry out a preliminary test pile early and to failure? 5. Benefits of using BS8004:2015 6. Common ME practice VS Atkins geotechnical approach 7. Conclusions 8. References Foundation design for tall buildings 16 November 2016 26 From Pile Groups to Piled Rafts – Contents
  • 27. Common geotechnical approach in ME • Early stage project involvement • Desk study • Design/scoping and specification of high quality GI • Carry out GI • Full time GI supervision • Factual reporting by contractor • Review of factual reporting • Interpretation • Ground model + parameters + design 27 STANDALONE GROUND INVESTIGATION CONTRACTOR CONSERVATIVE / UN-ECONOMIC / RISKY SOLUTION
  • 28. ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION • Early stage project involvement • Desk study • Design/scoping and specification of high quality GI • Carry out GI • Full time GI supervision • Factual reporting by contractor • Review of factual reporting • Interpretation • Ground model + parameters + design Atkins proposal to reduce geotechnical risk 28 SPECIALISTGEOTECHNICAL CONSULTANT By GI Contractor
  • 29. 1. Foundation design for tall buildings is complex and requires sophisticated analyses 2. 3D FE analyses encompass soil-structure interactions 3. CPRF are economical and proven in Dubai 4. Preliminary test piles with O-cells help reduce cost and risk 5. BS8004:2015 is recommended for the design of foundations 6. Ignoring project specific data raises the foundation risk 7. Employing a specialist geotechnical consultant is recommended to maximise opportunities Conclusions 16 November 2016 29
  • 30. • BS 8004:2015 Code of practice for foundations • Haberfield, C.M. and Paul, D.R. 2011. Footing Design of the Nakheel Tower, Dubai, UAE in Workshop on soil-structure interaction and retaining walls. Proceedings of the Technical Meeting TC207 ISSMGE, Dubrovnik, pp 35 to 52. • Poulos, H.G. and Bunce, G., 2008. Foundation design for the Burj Dubai–the world’s tallest building. 6th International Conference on Case Histories in Geotechnical Engineering, Arlington, VA. • Poulos, H.G. and Davids, A.J., 2005. Foundation design for the Emirates twin towers, Dubai. Canadian Geotechnical Journal, 42(3), pp.716-730. • Ibrahim, K., Bunce, G. and Murrells, C., 2009, December. Foundation design for the Pentominium tower in Dubai, UAE. In Proceedings of the Institution of Civil Engineers-Civil Engineering (Vol. 162, No. 6, pp. 25-33). Thomas Telford Ltd. References 16 November 2016 30
  • 31. Foundation design for tall buildings From Pile Groups to Piled Rafts Benoît Latapie Technical Manager – Ground Engineering benoit.latapie@atkinsglobal.com 16 November 2016 31 Underground Infrastructure and Deep Foundations UAE QUESTIONS?