Presentation from Simone Wilding, Head of National Infrastructure Case Management at the Planning Inspectorate, at 4th Annual Nationally Significant Infrastructure Projects Forum 2016.
VIP Call Girls Pune Vani 8617697112 Independent Escort Service Pune
What PINS expects from applications
1. 2016 Update &
What PINS expects from applications
Simone Wilding
Head of National Infrastructure Case Management
The Planning Inspectorate
2. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Outline
• Stocktake
• Forward Look
• Applications – what is PINS looking for?
• Lessons from practice
• Improvements – advice and tips
3. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Energy Transport Waste Waste
Water
Business &
Commercial
Total
Pre-Application 23 11* 2 2 38*
Live with PINS/SoS 15 3 18
Post Decision 30 16 2 1 49
Total 68 30 4 1 2 105
Judicial Review 5 2 1 1 9
Stocktake
* RIS impact not yet fully factored in
5. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
What PINS looks for
Compliant
Concise
Comprehensive
6. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Pre-application
Initial
meeting
EIA Scoping Consultation Address
consultation
issues
Draft
documents
Application
made
Making the most of pre-application
• Develop documents as project evolves – especially DCO and SoCG
• Grasp the nettle on difficult issues
• Maintain regular dialogue with PINS
Benefits
• Reduces risks of misunderstandings / missed issues appearing at examination
• Potential solutions to complex issues before examination
• Potential shorter examination, fewer examining inspectors
7. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
50 Decisions Overview
Most
documents
Fewest
documents
Most
Relevant Reps
Fewest
Relevant Reps
1 Thames Tideway
Tunnel
(2534)
Ipswich Rail
Chord
(143)
Navitus Bay
(2658)
Kings Lynn B
Connection
Project
(5)
2 Navitus Bay
(2025)
Kentish Flats
Extension
(158)
Thames Tideway
Tunnel
(1246)
A19 Coast Road
Junction
Improvement
(7)
3 Hinkley Point C
Connection
(1611)
North Doncaster
Rail Chord
(163)
Hinkley Point C
New Nuclear
Power Station
(1197)
Willington C Gas
Pipeline
(12)
8. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Shortest End-to-End
Positives to Emulate
No unanticipated issue
arose
Work closely with
statutory consultees
Comprehensive
answers to 1st Qs
A160-A180 Port of Immingham Improvement (picture: Google)
9. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Seek to avoid
- SPP
- IROPI & need for
compensation
- Caveated Crown
consent (s135)
Longest End-to-End
Able Marine Energy Park (artists impression: Google)
10. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Service improvements
• Advice Notes
• Good example documents
• Piloting earlier, combined
events in examinations
• Post decision case review
meetings – learn lessons
11. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
• Land Interests: identify all personally and
consult, ensure consistency with Book of
Reference
• DCO No1 application doc: Use ExM to
explain & justify
• Documents: clear, proportionate,
consistent with each other and well
structured
• SOCGs: signed by all parties: show what’s
agreed and where disagreeing
Top Tips
12. 4th Annual: Nationally Significant Infrastructure Projects Forum 2016, London, 9 February 2016
Questions?