SlideShare a Scribd company logo
1 of 7
Download to read offline
Stairs
1/7-Stairs
Stairs
2/7-Stairs
Design of step:
Steps are made of checkered plate
6/8 as shown
Assume o.w. of step = 20 kg / m
L.L = 300 → 500 kg / m2
F.C. may be used
W =
1000
20
+ (F.C. + L.L.) b
Calculate M =
8
2
wa
Q =
2
wa
Fbcx = 1.4 t/cm2
(lip is small, so neglect L.T.B.)
Check f, q, a
L
L
=
→
≤
300
δ
Width of stairs is about 1→1.5 m
Slope is 1:2 in most cases.
Design of stair beam: (Usually used as channel)
26.5
θ ≈
assume o.w. = 25 kg/m
weight of step, handrail, (all steel structure)
ws = 70 kg/m2
/hz proj
L.L = 300 → 500 kg / m2
F.C. = …….. if any
W =
1000
25
+ (70 + F.C. + L.L.) (a/2)
Draw M, Q, (neglect normal)
M =
8
2
wL
Q =
2
wL
Lu act = zero
b = 30 cm
Checkered plate
5-7
a
(6.00)
a
(4.50)
(3.00)
a
a
Beam at 1/2 floor level
R 1
M
2
M
w = ...... t/m'
1
2
Stairs
3/7-Stairs
Fbcx = 1.4 t/cm2
dmin of channel →
Check f, q, δ
Design of connection using butt weld:
h
hw=
h =
weld
h
2
cos
channel
C
1
3
°
2
Calculate Ix
Check y
I
M
x
= …..< 0.7 ft (allowable of good butt weld subjected to tension due
to moment or due to tension). Look ECP page
Design of beam at 1/2 floor height: (Usually IPE)
R = Reaction of stair beam
Calculate M, Q
If channel is flushed & checkered plate is
welded, so Lu act = zero
If we use grating Lu act = a
Design of connection between channel & I beam:
Force = Rt → Rss, Rb as before
3
2
1
0
L70*7
26.5
4
2
h-2t
a a
R RR R
Stairs
4/7-Stairs
Solved example:
It is required a complete design of stairs
(steps, beam of stairs with its connection &
beam at 1/2 floor height)
Given that: L.L. = 400 kg/m2
, F.C. =150
kg/m2
Solution:
Design of step:
Assume o.w. of step = 20 kg/m
Take shape of step as Z – section (assume b = 30cm) (checkered plate 6/8)
WDL = 20 + 150 * 0.3 = 65 kg/m
WLL = 400 * 0.3 = 120 kg/m
WT = 120 + 65 = 185 kg/m
M = 0.185 *
8
25
.
1 2
= 0.036 mt = 3.6 cmt
Q = 0.185 * (1.25/2) = 0.11 t
Ix =
12
6
.
0
*
30 3
(neglected) + 2








+ 2
3
5
.
2
*
4
.
4
*
6
.
0
12
4
.
4
*
6
.
0
= 41.52 cm4
Checks:
1. f =
52
.
41
7
.
4
*
6
.
3
= 0.41 t/cm2
< 1.4 t/cm2
(Lip is small, so we can neglect L.T.B)
2. q =
6
.
0
*
5
*
2
11
.
0
= 0.02 t/cm2
<<< 0.84 t/cm2
3. .
.L
L
δ = 3
4
10
*
52
.
41
*
2100
25
.
1
*
120
*
384
5
= 0.04 cm < =
300
125
0.42 cm
0.5
1.25
(6.00)
1.25
(4.50)
(3.00)
3.0
1.25
1.25
c
d
b
a
Beam B
1.0
1.0
Lip = 5cm
4.4
t = 0.6
30
Stairs
5/7-Stairs
Design of stair beam:
Assume o.w. = 25 kg/m
Weight of other steel structure is 70 kg/m
WDL = 25 + (70 + 150) * (1.25 / 2)
= 162.5 kg/m
WLL = 400 * (1.25 / 2) = 250 kg/m
Wtotal = 250 + 162.5 = 412.5 kg/m
M =
8
5
.
5
*
41
.
0 2
= 1.56 mt
Q = 0.41 * (5.5 / 2) = 1.13 t
Assume Fbcx = 1.4 t/cm2
Sx = 156 / 1.4 = 111 cm3
Choose channel 160
Checks:
Lu act = zero So No L.T.B.
f
t
c
=
05
.
1
05
.
1
75
.
0
5
.
6 −
−
= 4.48 < 10.9
w
w
t
d
= 11.6 / 0.75 = 15.5 < 82
Therefore, the section is not slender (simply symmetric channel)
1. f = 156 / 116 = 1.34 t/cm2
< 1.4 t/cm2
2. q =
75
.
0
*
16
13
.
1
= 0.09 t/cm2
< 0.84 t/cm2
3. 6
4
.
. 10
*
925
*
2100
5
.
5
*
25
.
0
*
384
5
=
L
L
δ = 1.53 cm < 550/300 = 1.83cm
1.13
w = 0.41 t/m'
1.56
1.41
Stairs
6/7-Stairs
Min channel:
94
.
9
2
2
=
− t
h
(From drawing)
cm
t 1
≈ h = 22 cm
Choose channel minimum 220
Design of connection butt weld:
M connection = 1.13 * 1.25 = 1.41 mt ο
25
.
13
2
=
θ
hweld =
25
.
13
cos
22
= 22.6 cm
Ix = 2
3
)
2
25
.
1
2
6
.
22
(
*
)
9
.
0
8
(
*
25
.
1
*
2
12
6
.
22
*
9
.
0
−
−
+ = 2888.4 cm4
f = 55
.
0
2
6
.
22
*
4
.
2888
141
= t/cm2
< 0.7*1.4 = 0.98 t/cm2
Design of connection between channel & beam at 1/2 floor beam:
R = 1.13 t (use only one angle)
Rss = 4
*
25
.
0
*
6
.
1
*
4
2
π
= 2.01t
tmin is smaller of 0.7 or 0.9 (tw of channel)
Rb = (0.8 * 3.6)*1.6*0.7 = 3.22 t
n = 1.13 / 2.01 = 0.56 use 2 bolts min
plate
Chequerd L70*7
=9.94
2
h-2t
30cm
5cm
L70*7
26.5
0
t=0.9
22.6
t=1.25
8
Stairs
7/7-Stairs
Design of beam B (at mid floor level)
Rtotal stair beam = 1.13 t, O.W. = 50 kg/m'
RLL stair beam = 0.25 * 5.5 / 2 = 0.69 t
(To be used in check of deflection)
Mconc = 2.385 x 2.25 – 1.13 x 1.25 – 0.05 x
1.252
/2= 3.83 mt
Q = 0.03 x 5 / 2 + 1.13 x 4 / 2 = 2.385 mt
Assume Fbcx = 0.64 Fy = 1.54 t/cm2
Sx = 383/ 1.54 = 259 cm3
choose IPE 220
Checks:
f
t
c
=
92
.
0
2
.
1
*
2
59
.
0
11 −
−
= 8.7 < 10.9 ,
w
w
t
d
= 21.2 / 0.59 =35.9 < 82
Assume using checkered plate welded to upper flange of beam
So Lu act = zero Fbcx = 0.64 Fy
1. f = 383 / 252 = 1.52 t/cm2
< 1.54 t/cm2
2. q =
2.38
22*0.59
= 0.18 t/cm2
< 0.84 t/cm2
3.51
0.69 1.725
0.54 0.56
0.69
0.69 0.69
1.25 1.25
3. deflection due to live load only " RLL stair beam "
ε
M = 3.51 * 2.5 – 0.56 * (0.25/2) – 0.54 * (0.5 + 1.25/3) – 1.725 * (0.25 +
1.25/2) – 0.69 * (0.25 + 1.25 + 1/3) = 5.43 m3
t
2770
*
2100
10
*
43
.
5 6
.
. =
L
L
δ = 0.93 cm < 550/300 = 1.67cm
1.25 1.25
1.13 1.13 1.13
1.00 1.00
0.5
0.05

More Related Content

Similar to Design of stairs

Diseno y-calculo-de-puentes
Diseno y-calculo-de-puentesDiseno y-calculo-de-puentes
Diseno y-calculo-de-puentescarlos
 
Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Mohammed Zakaria
 
Diesel Production: Equipments Design
Diesel Production: Equipments DesignDiesel Production: Equipments Design
Diesel Production: Equipments DesignPratik Patel
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxsubhashini214160
 
Transition.pptx
Transition.pptxTransition.pptx
Transition.pptx211Aqib
 
Calculo de losa aligerada
Calculo de losa aligeradaCalculo de losa aligerada
Calculo de losa aligeradaAntonio Zr
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school buildingRaghav Sankar
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingYash Patel
 
Building Workshop Politecnico Di Milano 2007-2008
Building Workshop Politecnico Di Milano 2007-2008Building Workshop Politecnico Di Milano 2007-2008
Building Workshop Politecnico Di Milano 2007-2008Pedro Pascual Ezama
 
Solucionario p2 conc. avanzado
Solucionario p2 conc. avanzadoSolucionario p2 conc. avanzado
Solucionario p2 conc. avanzadoomar julca mendoza
 

Similar to Design of stairs (20)

Muro contension raul1
Muro contension raul1Muro contension raul1
Muro contension raul1
 
Calculo de acero en vigas ok
Calculo de acero en vigas okCalculo de acero en vigas ok
Calculo de acero en vigas ok
 
Diseno y-calculo-de-puentes
Diseno y-calculo-de-puentesDiseno y-calculo-de-puentes
Diseno y-calculo-de-puentes
 
Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)
 
Puentes
PuentesPuentes
Puentes
 
Diesel Production: Equipments Design
Diesel Production: Equipments DesignDiesel Production: Equipments Design
Diesel Production: Equipments Design
 
2 compression
2  compression2  compression
2 compression
 
Shi20396 ch08
Shi20396 ch08Shi20396 ch08
Shi20396 ch08
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 
Transition.pptx
Transition.pptxTransition.pptx
Transition.pptx
 
Calculo de losa aligerada
Calculo de losa aligeradaCalculo de losa aligerada
Calculo de losa aligerada
 
Rc19 footing1
Rc19 footing1Rc19 footing1
Rc19 footing1
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending Scheduling
 
Isolated Footing
Isolated FootingIsolated Footing
Isolated Footing
 
Perhitungan struktur
Perhitungan strukturPerhitungan struktur
Perhitungan struktur
 
Building Workshop Politecnico Di Milano 2007-2008
Building Workshop Politecnico Di Milano 2007-2008Building Workshop Politecnico Di Milano 2007-2008
Building Workshop Politecnico Di Milano 2007-2008
 
Capítulo 08 parafusos
Capítulo 08   parafusosCapítulo 08   parafusos
Capítulo 08 parafusos
 
1622828460.pdf
1622828460.pdf1622828460.pdf
1622828460.pdf
 
Solucionario p2 conc. avanzado
Solucionario p2 conc. avanzadoSolucionario p2 conc. avanzado
Solucionario p2 conc. avanzado
 

More from Bahzad5

دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide LaboratoryBahzad5
 
2013 (Total Station & Civil 3D) فێرکاری
2013  (Total Station & Civil 3D) فێرکاری2013  (Total Station & Civil 3D) فێرکاری
2013 (Total Station & Civil 3D) فێرکاریBahzad5
 
Engineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریEngineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریBahzad5
 
(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەیBahzad5
 
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بیناBahzad5
 
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)Bahzad5
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTIONBahzad5
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Bahzad5
 
الشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةالشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةBahzad5
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 
2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاینBahzad5
 
Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Bahzad5
 
ڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانBahzad5
 
سەرەتاکانی دیزاین
سەرەتاکانی دیزاینسەرەتاکانی دیزاین
سەرەتاکانی دیزاینBahzad5
 
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەBahzad5
 
پرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریپرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریBahzad5
 
بناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundationبناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and FoundationBahzad5
 
slump test سڵەمپ تێست
slump test سڵەمپ تێستslump test سڵەمپ تێست
slump test سڵەمپ تێستBahzad5
 
Design of Storm Sewer System
Design of Storm Sewer SystemDesign of Storm Sewer System
Design of Storm Sewer SystemBahzad5
 
ڕۆنی بزوێنەر
ڕۆنی بزوێنەرڕۆنی بزوێنەر
ڕۆنی بزوێنەرBahzad5
 

More from Bahzad5 (20)

دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
2013 (Total Station & Civil 3D) فێرکاری
2013  (Total Station & Civil 3D) فێرکاری2013  (Total Station & Civil 3D) فێرکاری
2013 (Total Station & Civil 3D) فێرکاری
 
Engineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریEngineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاری
 
(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی
 
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
 
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)
 
الشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةالشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنية
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین
 
Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)
 
ڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکان
 
سەرەتاکانی دیزاین
سەرەتاکانی دیزاینسەرەتاکانی دیزاین
سەرەتاکانی دیزاین
 
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
 
پرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریپرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاری
 
بناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundationبناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundation
 
slump test سڵەمپ تێست
slump test سڵەمپ تێستslump test سڵەمپ تێست
slump test سڵەمپ تێست
 
Design of Storm Sewer System
Design of Storm Sewer SystemDesign of Storm Sewer System
Design of Storm Sewer System
 
ڕۆنی بزوێنەر
ڕۆنی بزوێنەرڕۆنی بزوێنەر
ڕۆنی بزوێنەر
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

Design of stairs

  • 2. Stairs 2/7-Stairs Design of step: Steps are made of checkered plate 6/8 as shown Assume o.w. of step = 20 kg / m L.L = 300 → 500 kg / m2 F.C. may be used W = 1000 20 + (F.C. + L.L.) b Calculate M = 8 2 wa Q = 2 wa Fbcx = 1.4 t/cm2 (lip is small, so neglect L.T.B.) Check f, q, a L L = → ≤ 300 δ Width of stairs is about 1→1.5 m Slope is 1:2 in most cases. Design of stair beam: (Usually used as channel) 26.5 θ ≈ assume o.w. = 25 kg/m weight of step, handrail, (all steel structure) ws = 70 kg/m2 /hz proj L.L = 300 → 500 kg / m2 F.C. = …….. if any W = 1000 25 + (70 + F.C. + L.L.) (a/2) Draw M, Q, (neglect normal) M = 8 2 wL Q = 2 wL Lu act = zero b = 30 cm Checkered plate 5-7 a (6.00) a (4.50) (3.00) a a Beam at 1/2 floor level R 1 M 2 M w = ...... t/m' 1 2
  • 3. Stairs 3/7-Stairs Fbcx = 1.4 t/cm2 dmin of channel → Check f, q, δ Design of connection using butt weld: h hw= h = weld h 2 cos channel C 1 3 ° 2 Calculate Ix Check y I M x = …..< 0.7 ft (allowable of good butt weld subjected to tension due to moment or due to tension). Look ECP page Design of beam at 1/2 floor height: (Usually IPE) R = Reaction of stair beam Calculate M, Q If channel is flushed & checkered plate is welded, so Lu act = zero If we use grating Lu act = a Design of connection between channel & I beam: Force = Rt → Rss, Rb as before 3 2 1 0 L70*7 26.5 4 2 h-2t a a R RR R
  • 4. Stairs 4/7-Stairs Solved example: It is required a complete design of stairs (steps, beam of stairs with its connection & beam at 1/2 floor height) Given that: L.L. = 400 kg/m2 , F.C. =150 kg/m2 Solution: Design of step: Assume o.w. of step = 20 kg/m Take shape of step as Z – section (assume b = 30cm) (checkered plate 6/8) WDL = 20 + 150 * 0.3 = 65 kg/m WLL = 400 * 0.3 = 120 kg/m WT = 120 + 65 = 185 kg/m M = 0.185 * 8 25 . 1 2 = 0.036 mt = 3.6 cmt Q = 0.185 * (1.25/2) = 0.11 t Ix = 12 6 . 0 * 30 3 (neglected) + 2         + 2 3 5 . 2 * 4 . 4 * 6 . 0 12 4 . 4 * 6 . 0 = 41.52 cm4 Checks: 1. f = 52 . 41 7 . 4 * 6 . 3 = 0.41 t/cm2 < 1.4 t/cm2 (Lip is small, so we can neglect L.T.B) 2. q = 6 . 0 * 5 * 2 11 . 0 = 0.02 t/cm2 <<< 0.84 t/cm2 3. . .L L δ = 3 4 10 * 52 . 41 * 2100 25 . 1 * 120 * 384 5 = 0.04 cm < = 300 125 0.42 cm 0.5 1.25 (6.00) 1.25 (4.50) (3.00) 3.0 1.25 1.25 c d b a Beam B 1.0 1.0 Lip = 5cm 4.4 t = 0.6 30
  • 5. Stairs 5/7-Stairs Design of stair beam: Assume o.w. = 25 kg/m Weight of other steel structure is 70 kg/m WDL = 25 + (70 + 150) * (1.25 / 2) = 162.5 kg/m WLL = 400 * (1.25 / 2) = 250 kg/m Wtotal = 250 + 162.5 = 412.5 kg/m M = 8 5 . 5 * 41 . 0 2 = 1.56 mt Q = 0.41 * (5.5 / 2) = 1.13 t Assume Fbcx = 1.4 t/cm2 Sx = 156 / 1.4 = 111 cm3 Choose channel 160 Checks: Lu act = zero So No L.T.B. f t c = 05 . 1 05 . 1 75 . 0 5 . 6 − − = 4.48 < 10.9 w w t d = 11.6 / 0.75 = 15.5 < 82 Therefore, the section is not slender (simply symmetric channel) 1. f = 156 / 116 = 1.34 t/cm2 < 1.4 t/cm2 2. q = 75 . 0 * 16 13 . 1 = 0.09 t/cm2 < 0.84 t/cm2 3. 6 4 . . 10 * 925 * 2100 5 . 5 * 25 . 0 * 384 5 = L L δ = 1.53 cm < 550/300 = 1.83cm 1.13 w = 0.41 t/m' 1.56 1.41
  • 6. Stairs 6/7-Stairs Min channel: 94 . 9 2 2 = − t h (From drawing) cm t 1 ≈ h = 22 cm Choose channel minimum 220 Design of connection butt weld: M connection = 1.13 * 1.25 = 1.41 mt ο 25 . 13 2 = θ hweld = 25 . 13 cos 22 = 22.6 cm Ix = 2 3 ) 2 25 . 1 2 6 . 22 ( * ) 9 . 0 8 ( * 25 . 1 * 2 12 6 . 22 * 9 . 0 − − + = 2888.4 cm4 f = 55 . 0 2 6 . 22 * 4 . 2888 141 = t/cm2 < 0.7*1.4 = 0.98 t/cm2 Design of connection between channel & beam at 1/2 floor beam: R = 1.13 t (use only one angle) Rss = 4 * 25 . 0 * 6 . 1 * 4 2 π = 2.01t tmin is smaller of 0.7 or 0.9 (tw of channel) Rb = (0.8 * 3.6)*1.6*0.7 = 3.22 t n = 1.13 / 2.01 = 0.56 use 2 bolts min plate Chequerd L70*7 =9.94 2 h-2t 30cm 5cm L70*7 26.5 0 t=0.9 22.6 t=1.25 8
  • 7. Stairs 7/7-Stairs Design of beam B (at mid floor level) Rtotal stair beam = 1.13 t, O.W. = 50 kg/m' RLL stair beam = 0.25 * 5.5 / 2 = 0.69 t (To be used in check of deflection) Mconc = 2.385 x 2.25 – 1.13 x 1.25 – 0.05 x 1.252 /2= 3.83 mt Q = 0.03 x 5 / 2 + 1.13 x 4 / 2 = 2.385 mt Assume Fbcx = 0.64 Fy = 1.54 t/cm2 Sx = 383/ 1.54 = 259 cm3 choose IPE 220 Checks: f t c = 92 . 0 2 . 1 * 2 59 . 0 11 − − = 8.7 < 10.9 , w w t d = 21.2 / 0.59 =35.9 < 82 Assume using checkered plate welded to upper flange of beam So Lu act = zero Fbcx = 0.64 Fy 1. f = 383 / 252 = 1.52 t/cm2 < 1.54 t/cm2 2. q = 2.38 22*0.59 = 0.18 t/cm2 < 0.84 t/cm2 3.51 0.69 1.725 0.54 0.56 0.69 0.69 0.69 1.25 1.25 3. deflection due to live load only " RLL stair beam " ε M = 3.51 * 2.5 – 0.56 * (0.25/2) – 0.54 * (0.5 + 1.25/3) – 1.725 * (0.25 + 1.25/2) – 0.69 * (0.25 + 1.25 + 1/3) = 5.43 m3 t 2770 * 2100 10 * 43 . 5 6 . . = L L δ = 0.93 cm < 550/300 = 1.67cm 1.25 1.25 1.13 1.13 1.13 1.00 1.00 0.5 0.05