1. ID Task
Mode
Task Name Duration Start Finish
1 Balance Work at MOL Site IK‐2587‐04 15 days Sat 18/09/21 Sat 02/10/21
2 Mobilization at Site 2 days Sat 18/09/21 Sun 19/09/21
3 Installation of Ladders 2 days Mon 20/09/21 Tue 21/09/21
4 NutBolt Tightning & Inspection 1 day Mon 20/09/21 Mon 20/09/21
5 Adjustment of small stairs 1 day Tue 21/09/21 Tue 21/09/21
6 Connection of Platform 6 days Wed 22/09/21 Mon 27/09/21
7 Welding at workshop 2 days Wed 22/09/21 Thu 23/09/21
8 Platform Plate Drilling at Site 2 days Fri 24/09/21 Sat 25/09/21
9 Bracing Beams between the old Platform & New Platform 2 days Sun 26/09/21 Mon 27/09/21
10 Installation of AFS 4 days Sun 26/09/21 Wed 29/09/21
11 Testing of AFS 2 days Thu 30/09/21 Fri 01/10/21
12 Demobilization 1 day Sat 02/10/21 Sat 02/10/21