1. ID Task Name Duration Start Finish
1 PENGADAAN DAN PEMASANGAN OSP FO
STTF-1 2023
67 days Mon 2/13/23 Thu 4/20/23
2 PREPARING 4 days Mon 2/13/23 Thu 2/16/23
3 SURVEY + Pengurusan Izin 4 days Mon 2/13/23 Thu 2/16/23
4 MATERIAL DELIVERY & PERMIT 35 days Mon 2/13/23 Sun 3/19/23
5 Material Tiang 7 Mtr untuk Ternate &Sosasiu 15 days Mon 2/13/23 Mon 2/27/23
6 Material Kabel FO untuk Ternate &Sosasiu 15 days Mon 2/13/23 Mon 2/27/23
7 Material Accessories untuk Ternate &Sosasiu 15 days Mon 2/13/23 Mon 2/27/23
8 Material Tiang 7 Mtr untuk Sanana & Taliyabu 35 days Mon 2/13/23 Sun 3/19/23
9 Material Kabel FO untuk Sanana & Taliyabu 35 days Mon 2/13/23 Sun 3/19/23
10 Material Accessories untuk Sanana & Taliyabu35 days Mon 2/13/23 Sun 3/19/23
11 R7 MDO TNT SAMISI MAUPANGGA 3 days Tue 2/28/23 Thu 3/2/23
12 Tarik Kabel FO 1 day Tue 2/28/23 Tue 2/28/23
13 Installing ODP 1 day Wed 3/1/23 Wed 3/1/23
14 Test Commisioning 1 day Thu 3/2/23 Thu 3/2/23
15 R7 MDO TNT FATIMA TIJORAH 3 days Tue 2/28/23 Thu 3/2/23
16 Pekerjaan Tanam Tiang 1 day Tue 2/28/23 Tue 2/28/23
17 Tarik Kabel FO 1 day Tue 2/28/23 Tue 2/28/23
18 Installing ODP 1 day Wed 3/1/23 Wed 3/1/23
19 Test Commisioning 1 day Thu 3/2/23 Thu 3/2/23
20 R7 MDO TNT EA BANTAL 3 days Tue 2/28/23 Thu 3/2/23
21 Pekerjaan Tanam Tiang 1 day Tue 2/28/23 Tue 2/28/23
22 Tarik Kabel FO 1 day Tue 2/28/23 Tue 2/28/23
23 Installing ODP 1 day Wed 3/1/23 Wed 3/1/23
24 Test Commisioning 1 day Thu 3/2/23 Thu 3/2/23
25 R7 MDO TNT YUNITA 3 days Fri 3/3/23 Sun 3/5/23
26 Tarik Kabel FO 1 day Fri 3/3/23 Fri 3/3/23
27 Installing ODP 1 day Sat 3/4/23 Sat 3/4/23
28 Test Commisioning 1 day Sun 3/5/23 Sun 3/5/23
29 R7 MDO TNT YUNITA SYARIF 3 days Fri 3/3/23 Sun 3/5/23
30 Tarik Kabel FO 1 day Fri 3/3/23 Fri 3/3/23
31 Installing ODP 1 day Sat 3/4/23 Sat 3/4/23
TIM SURVEI
LOGISTIK
LOGISTIK
LOGISTIK
7 ORANG TEAM GELAR KABE
JOINTING-A
WASPANG
7 ORANG TEAM GELAR KABE
7 ORANG TEAM GELAR KABE
JOINTING-B
WASPANG
7 ORANG TEAM GELAR KABE
7 ORANG TEAM GELAR KABE
7 ORANG TEAM GELAR K
WASPANG
7 ORANG TEAM G
JOINTING-A
WASPAN
7 ORANG TEAM G
JOINTING-A
S M T W T F S S M T W T F S S M T W T F S S M
Feb 6, '23 Feb 13, '23 Feb 20, '23 Feb 27, '23 Mar 6, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 1
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
2. ID Task Name Duration Start Finish
32 Test Commisioning 1 day Sun 3/5/23 Sun 3/5/23
33 R7 MDO TNT BENGKEL ART 3 days Fri 3/3/23 Sun 3/5/23
34 Tarik Kabel FO 1 day Fri 3/3/23 Fri 3/3/23
35 Installing ODP 1 day Sat 3/4/23 Sat 3/4/23
36 Test Commisioning 1 day Sun 3/5/23 Sun 3/5/23
37 R7 MDO TNT KASMAN MUHAMMAD 4 days Mon 3/6/23 Thu 3/9/23
38 Pekerjaan Tanam Tiang 1 day Mon 3/6/23 Mon 3/6/23
39 Tarik Kabel FO 1 day Tue 3/7/23 Tue 3/7/23
40 Installing ODP 1 day Wed 3/8/23 Wed 3/8/23
41 Test Commisioning 1 day Thu 3/9/23 Thu 3/9/23
42 R7 MDO TNT TRIANINGSIH 3 days Mon 3/6/23 Wed 3/8/23
43 Tarik Kabel FO 1 day Mon 3/6/23 Mon 3/6/23
44 Installing ODP 1 day Tue 3/7/23 Tue 3/7/23
45 Test Commisioning 1 day Wed 3/8/23 Wed 3/8/23
46 R7 MDO TNT RIFA ABDULLAH 3 days Mon 3/6/23 Wed 3/8/23
47 Pekerjaan Tanam Tiang 1 day Mon 3/6/23 Mon 3/6/23
48 Tarik Kabel FO 1 day Mon 3/6/23 Mon 3/6/23
49 Installing ODP 1 day Tue 3/7/23 Tue 3/7/23
50 Test Commisioning 1 day Wed 3/8/23 Wed 3/8/23
51 R7 MDO TNT AMIR MAHMUD 5 days Thu 3/9/23 Mon 3/13/23
52 Pekerjaan Tanam Tiang 1 day Thu 3/9/23 Thu 3/9/23
53 Tarik Kabel FO 2 days Fri 3/10/23 Sat 3/11/23
54 Installing ODP 1 day Sun 3/12/23 Sun 3/12/23
55 Test Commisioning 1 day Mon 3/13/23 Mon 3/13/23
56 R7 MDO SSI SAFRUDIN MACHLY 3 days Tue 3/14/23 Thu 3/16/23
57 Pekerjaan Tanam Tiang 1 day Tue 3/14/23 Tue 3/14/23
58 Tarik Kabel FO 1 day Tue 3/14/23 Tue 3/14/23
59 Installing ODP 1 day Wed 3/15/23 Wed 3/15/23
60 Test Commisioning 1 day Thu 3/16/23 Thu 3/16/23
61 R7 MDO SSI KASMALUDIN 3 days Fri 3/17/23 Sun 3/19/23
62 Tarik Kabel FO 1 day Fri 3/17/23 Fri 3/17/23
63 Installing ODP 1 day Sat 3/18/23 Sat 3/18/23
WASPAN
7 ORANG TEAM G
7 ORANG TE
WASPAN
7 OR
7
7 OR
J
7 OR
7 OR
J
S M T W T F S S M T W T F S S M T W T F S S M
Feb 6, '23 Feb 13, '23 Feb 20, '23 Feb 27, '23 Mar 6, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 2
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
3. ID Task Name Duration Start Finish
64 Test Commisioning 1 day Sun 3/19/23 Sun 3/19/23
65 R7 MDO LBH ASRULLAH LA ABU 4 days Mon 3/20/23 Thu 3/23/23
66 Pekerjaan Tanam Tiang 1 day Mon 3/20/23 Mon 3/20/23
67 Tarik Kabel FO 1 day Tue 3/21/23 Tue 3/21/23
68 Installing ODP 1 day Wed 3/22/23 Wed 3/22/23
69 Test Commisioning 1 day Thu 3/23/23 Thu 3/23/23
70 FEEDER DESA GORABATI -2 14 days Tue 2/28/23 Mon 3/13/23
71 Pekerjaan Tanam Tiang 1 day Tue 2/28/23 Tue 2/28/23
72 Tarik Kabel FO 6 days Wed 3/1/23 Mon 3/6/23
73 Pembuatan Handhole 2 days Tue 3/7/23 Wed 3/8/23
74 Pembuatan fondasi dan Pemasangan ODC 3 days Thu 3/9/23 Sat 3/11/23
75 Installing ODC 1 day Sun 3/12/23 Sun 3/12/23
76 Test Commisioning 1 day Mon 3/13/23 Mon 3/13/23
77 R7 MDO SSI DESA DOYADO 5 days Tue 3/7/23 Sat 3/11/23
78 Tarik Kabel FO 3 days Tue 3/7/23 Thu 3/9/23
79 Installing ODP 1 day Fri 3/10/23 Fri 3/10/23
80 Test Commisioning 1 day Sat 3/11/23 Sat 3/11/23
81 R7 MDO SSI DESA GORABATI -2 16 days Tue 2/28/23 Wed 3/15/23
82 Pekerjaan Tanam Tiang 6 days Tue 2/28/23 Sun 3/5/23
83 Tarik Kabel FO 5 days Mon 3/6/23 Fri 3/10/23
84 Installing ODP 4 days Sat 3/11/23 Tue 3/14/23
85 Test Commisioning 1 day Wed 3/15/23 Wed 3/15/23
86 R7 MDO SSI FOBAHARU SOASIU 11 days Sat 3/11/23 Tue 3/21/23
87 Pekerjaan Tanam Tiang 6 days Sat 3/11/23 Thu 3/16/23
88 Tarik Kabel FO 3 days Fri 3/17/23 Sun 3/19/23
89 Installing ODP 1 day Mon 3/20/23 Mon 3/20/23
90 Test Commisioning 1 day Tue 3/21/23 Tue 3/21/23
91 R7 MDO SNN WAIHAMA 15 days Mon 3/20/23 Mon 4/3/23
92 Pekerjaan Tanam Tiang 5 days Mon 3/20/23 Fri 3/24/23
93 Tarik Kabel FO 6 days Sat 3/25/23 Thu 3/30/23
94 Installing ODP 3 days Fri 3/31/23 Sun 4/2/23
95 Test Commisioning 1 day Mon 4/3/23 Mon 4/3/23
7 ORANG TEAM GELAR KABE
7 OR
7 ORANG
7 ORA
S M T W T F S S M T W T F S S M T W T F S S M
Feb 6, '23 Feb 13, '23 Feb 20, '23 Feb 27, '23 Mar 6, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 3
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
4. ID Task Name Duration Start Finish
96 R7 MDO SNN MANGON SATU SANANA 9 days Fri 3/31/23 Sat 4/8/23
97 Pekerjaan Tanam Tiang 3 days Fri 3/31/23 Sun 4/2/23
98 Tarik Kabel FO 2 days Mon 4/3/23 Tue 4/4/23
99 2 days Wed 4/5/23 Thu 4/6/23
100 Test Commisioning 2 days Fri 4/7/23 Sat 4/8/23
101 R7 MDO MGL TALIYABU MANGOLE 10 days Mon 3/20/23 Wed 3/29/23
102 Pekerjaan Tanam Tiang 4 days Mon 3/20/23 Thu 3/23/23
103 Tarik Kabel FO 2 days Fri 3/24/23 Sat 3/25/23
104 Installing ODP 1 day Sun 3/26/23 Sun 3/26/23
105 Test Commisioning 3 days Mon 3/27/23 Wed 3/29/23
106 PEKERJAAN ADMINISTRASI TAHAP
PERTAMA
12 days Wed 3/22/23 Sun 4/2/23
107 BAUT 5 days Wed 3/22/23 Sun 3/26/23
108 REKON 5 days Mon 3/27/23 Fri 3/31/23
109 BAST 2 days Sat 4/1/23 Sun 4/2/23
110 PEKERJAAN ADMINISTRASI TAHAP KEDUA 12 days Sun 4/9/23 Thu 4/20/23
111 BAUT 5 days Sun 4/9/23 Thu 4/13/23
112 REKON 5 days Fri 4/14/23 Tue 4/18/23
113 BAST 2 days Wed 4/19/23 Thu 4/20/23
WASP
S M T W T F S S M T W T F S S M T W T F S S M
Feb 6, '23 Feb 13, '23 Feb 20, '23 Feb 27, '23 Mar 6, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 4
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
5. LOGISTIK
LOGISTIK
LOGISTIK
G TEAM GELAR KABEL + TANAM TIANG A
NTING-A
WASPANG
G TEAM GELAR KABEL + TANAM TIANG A
G TEAM GELAR KABEL + TANAM TIANG A
NTING-B
WASPANG
G TEAM GELAR KABEL + TANAM TIANG A
G TEAM GELAR KABEL + TANAM TIANG A
RANG TEAM GELAR KABEL + TANAM TIANG A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Mar 6, '23 Mar 13, '23 Mar 20, '23 Mar 27, '23 Apr 3, '23 Apr 10, '23 Apr 17, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 5
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
6. WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Mar 6, '23 Mar 13, '23 Mar 20, '23 Mar 27, '23 Apr 3, '23 Apr 10, '23 Apr 17, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 6
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
7. WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
7 ORANG TEAM GELAR KABEL + TANAM TIANG A
JOINTING-A
WASPANG
G TEAM GELAR KABEL + TANAM TIANG B
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
JOINTING-B
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG C
7 ORANG TEAM GELAR KABEL + TANAM TIANG C
JOINTING-C
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG C
7 ORANG TEAM GELAR KABEL + TANAM TIANG C
JOINTING-C
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG D
7 ORANG TEAM GELAR KABEL + TANAM TIANG D
JOINTING-D
WASPANG
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Mar 6, '23 Mar 13, '23 Mar 20, '23 Mar 27, '23 Apr 3, '23 Apr 10, '23 Apr 17, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 7
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018
8. 7 ORANG TEAM GELAR KABEL + TANAM TIANG D
7 ORANG TEAM GELAR KABEL + TANAM TIANG D
JOINTING-D
WASPANG
7 ORANG TEAM GELAR KABEL + TANAM TIANG B
7 ORANG TEAM GELAR KABEL + TANAM TIANG B,WASPANG
JOINTING-C
WASPANG
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Mar 6, '23 Mar 13, '23 Mar 20, '23 Mar 27, '23 Apr 3, '23 Apr 10, '23 Apr 17, '23
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Page 8
Project: PENGADAAN DAN PEMASANGAN
PT2/PT3 OSP FO STTF 2019 4 LOKASI SUMAGO
Date: 27 November 2018