ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
1 1 Construction and Installation Activities (Just For ECN Works) Fri 10/31/08 Tue 11/17/09 5.1 422.8 days 100 629859.25
2 1.1 Start Of The Project Fri 10/31/08 Fri 10/31/08 0 0 days 0 0
3 1.2 Construction - Rectifier Passage 503-12 Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41
4 1.2.1 Operation Floor Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41
5 1.2.1.1 Installation - Electrical Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41
6 1.2.1.1.1 Installation - Cable Tray Sat 3/28/09 Tue 4/28/09 0 35.04 days 0.15 933.86
7 1.2.1.1.1.1 Cantilever supports installation Sat 3/28/09 Sat 4/18/09 E 0 2.42 days 97 nos. 0.03 158.33
8 1.2.1.1.1.2 Cable Tray installation Sun 4/19/09 Tue 4/28/09 E 0 10.5 days 420 mtr 0.12 775.53
9 1.2.1.1.2 Installation - Crane Bus Bars Tue 4/28/09 Wed 5/20/09 0 24.31 days 1.03 6515.55
10 1.2.1.1.2.1 Crane Bus Bar Supports installation Tue 4/28/09 Sun 5/3/09 E 0 5.22 days 87 nos. 0.09 543.99
11 1.2.1.1.2.2 Feed Junction Box Installation Sun 5/3/09 Wed 5/6/09 E 0 3.54 days 13 nos. 0.04 236.42
12 1.2.1.1.2.3 Disconnect Switch Instalation Wed 5/6/09 Thu 5/7/09 E 0 1.56 days 7 nos. 0.02 132.64
13 1.2.1.1.2.4 Interconnection cable, cableways installation Thu 5/7/09 Mon 5/11/09 E 0 3.99 days 60 nos. 0.25 1605
14 1.2.1.1.2.5 Crane feeder cables Mon 5/11/09 Wed 5/20/09 E 0 10 days 1080 mtr 0.63 3997.5
15 1.3 Construction - Potroom No. 1 (501-12A) Mon 11/24/08 Wed 7/29/09 1.92 273.91 days 11.41 71862.2
16 1.3.1 Pot 22 Mon 11/24/08 Wed 6/10/09 0.74 219.91 days 2.88 18111.55
17 1.3.1.1 SLI DELIVERABLES Mon 11/24/08 Mon 11/24/08 0 0 days 0 0
18 1.3.1.1.1 POT 22 Area Available for MPEI Construction Mon 11/24/08 Mon 11/24/08 0 0 days 0 0
19 1.3.1.2 Basement Floor Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18
20 1.3.1.2.1 Installation - Electrical Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18
21 1.3.1.2.1.1 Installation - Lighting System Tue 12/30/08 Sun 2/8/09 0.61 43.76 days 0.61 3873.42
22 1.3.1.2.1.1.1 PVC conduit and boxes Tue 12/30/08 Sun 1/4/09 E 0.04 5.67 days 75 mtr 0.04 243.05
23 1.3.1.2.1.1.2 Single Core Wires Sun 1/25/09 Tue 1/27/09 E 0.02 2.51 days 165 mtr 0.02 122.11
24 1.3.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Tue 1/27/09 Wed 1/28/09 E 0.02 0.35 days 18 nos. 0.02 145.32
25 1.3.1.2.1.1.4 Lighting Feeder cables / wires Wed 1/28/09 Sun 2/8/09 E 0.53 11.91 days 1400 mtr 0.53 3362.94
26 1.3.1.2.1.2 Installation - Emergency Shutdown Tue 4/21/09 Sun 5/3/09 0.01 12.97 days 0.6 3795.76
27 1.3.1.2.1.2.1 PVC conduit and boxes Tue 4/21/09 Wed 4/22/09 I 0.01 0.76 days 12 mtr 0.01 63.96
28 1.3.1.2.1.2.2 Instrument cables Wed 4/22/09 Sun 5/3/09 I 0 12.21 days 1944 mtr 0.59 3731.8
29 1.3.1.3 Operation Floor Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.66 10442.38
30 1.3.1.3.1 Air Compressed System - Piping Sat 4/11/09 Sat 4/18/09 0 9 days 0.05 333.13
31 1.3.1.3.1.1 2" Equal Tee Sat 4/11/09 Tue 4/14/09 P 0 4 days 11 nos 0.03 213.2
32 1.3.1.3.1.2 2" Plug Tue 4/14/09 Tue 4/14/09 P 0 1 day 9 nos 0.01 79.95
33 1.3.1.3.1.3 1/2" Ball valve Tue 4/14/09 Wed 4/15/09 P 0 1 day 2 nos 0 10.66
34 1.3.1.3.1.4 2" x 1" Reducer Wed 4/15/09 Thu 4/16/09 P 0 1 day 2 nos 0 10.66
35 1.3.1.3.1.5 1" x 1/2" Reducer Thu 4/16/09 Sat 4/18/09 P 0 1 day 2 nos 0 10.66
36 1.3.1.3.1.6 1/2" Nipple Sat 4/18/09 Sat 4/18/09 P 0 1 day 2 nos 0 8
37 1.3.1.3.2 Delivery of sub station 305-51 from SNCLavalin to
Astaldi
Tue 3/31/09 Tue 3/31/09 0 0 days 0 0
38 1.3.1.3.3 Installation - Electrical Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.61 10109.25
39 1.3.1.3.3.1 Installation - Lighting System Tue 12/2/08 Sun 12/7/08 0.08 5.04 days 0.08 523.22
40 1.3.1.3.3.1.1 Rigid Steel Conduit Tue 12/2/08 Thu 12/4/08 E 0.03 1.66 days 26 mtr 0.03 157.5
41 1.3.1.3.3.1.2 Single Core Wires Thu 12/4/08 Thu 12/4/08 E 0.03 0.79 days 300 mtr 0.03 188.82
42 1.3.1.3.3.1.3 High Bay Lighting fixtures including supports and fixings Thu 12/4/08 Sun 12/7/08 E 0.02 1.59 days 6 nos. 0.02 155.58
43 1.3.1.3.3.1.4 Lighting Feeder cables / wires Sun 12/7/08 Sun 12/7/08 E 0 1 day 8 mtr 0 21.32
44 1.3.1.3.3.2 Installation - Crane Bus Bars Sat 1/10/09 Mon 5/25/09 0.02 150.24 days 0.51 3205.04
45 1.3.1.3.3.2.1 Crane Bus Bar Supports installation Sat 1/10/09 Sat 1/10/09 E 0.02 0.69 days 16 nos. 0.02 96.37
46 1.3.1.3.3.2.2 Feed Junction Box Installation Sat 1/10/09 Sun 1/11/09 E 0 1.33 days 4 nos. 0.01 70.89
47 1.3.1.3.3.2.3 Disconnect Switch Instalation Sun 1/11/09 Mon 1/12/09 E 0 0.5 days 1 nos. 0 17.32
48 1.3.1.3.3.2.4 Interconnection cable, cableways installation Mon 1/12/09 Mon 1/12/09 E 0 1 day 5 nos. 0.02 133.25
49 1.3.1.3.3.2.5 Crane Power Feeder Cable Wed 5/20/09 Sat 5/23/09 E 0 2.64 days 350 mtr 0.42 2626.04
50 1.3.1.3.3.2.6 Cable Termination Sat 5/23/09 Mon 5/25/09 E 0 3 days 15 nos. 0.04 261.17
51 1.3.1.3.3.3 Installation - Socket / Welding Outlet Mon 1/26/09 Sun 3/15/09 0.02 52.75 days 0.06 381.71
52 1.3.1.3.3.3.1 Rigid Steel Conduit Mon 1/26/09 Tue 1/27/09 E 0.01 1.8 days 15 mtr 0.01 78.35
53 1.3.1.3.3.3.2 Single Core Wires Sat 3/14/09 Sun 3/15/09 E 0 1.33 days 50 mtr 0 27.82
54 1.3.1.3.3.3.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 23.98
55 1.3.1.3.3.3.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.29 days 2 nos. 0 27.05
56 1.3.1.3.3.3.5 Socket Feeder cables Thu 1/29/09 Thu 1/29/09 E 0 0.52 days 60 mtr 0.04 224.5
57 1.3.1.3.3.4 Installation - Local Junction Box Sun 5/3/09 Wed 6/10/09 0 42.95 days 0.95 5999.29
10/31
11/24
11/24
Installation extended
Material by Astaldi
Material by SNC
3/31
Waiting for cable tray to be installed
No junction box available
No disconnect switch installation available
No cables and cable tray
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 1 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
58 1.3.1.3.3.4.1 Rigid Steel Conduit Sun 5/3/09 Sun 5/10/09 E 0 7.62 days 140 mtr 0.12 744.6
59 1.3.1.3.3.4.2 Junction Box Sun 5/10/09 Tue 5/12/09 E 0 3.81 days 28 nos. 0.06 372.3
60 1.3.1.3.3.4.3 Feeder cables Tue 5/12/09 Wed 5/20/09 E 0 8.72 days 1020 mtr 0.53 3358.01
61 1.3.1.3.3.4.4 Cable Termination Mon 5/25/09 Wed 6/10/09 E 0 18 days 88 nos. 0.24 1524.38
62 1.3.2 Pot 44 Tue 1/6/09 Sat 6/27/09 0.83 189.12 days 2.48 15600.06
63 4.5.2.1 SLI DELIVERABLES Tue 2/3/09 Tue 2/3/09 0 0 days 0 0
64 1.3.2.1.1 POT 44 Area Available for MPEI Construction Tue 2/3/09 Tue 2/3/09 0 0 days 0 0
65 1.3.2.2 Basement Floor Tue 2/3/09 Sun 5/10/09 0.8 106.72 days 1.4 8789.57
66 1.3.2.2.1 Installation - Electrical Tue 2/3/09 Sun 5/10/09 0.8 106.72 days 1.4 8789.57
67 1.3.2.2.1.1 Installation - Lighting System Tue 2/3/09 Mon 4/20/09 0.79 84.77 days 0.79 4975.16
68 1.3.2.2.1.1.1 PVC conduit and boxes Tue 2/3/09 Wed 2/4/09 E 0.05 2.37 days 95 mtr 0.05 303.81
69 1.3.2.2.1.1.2 Single Core Wires Wed 2/4/09 Sat 2/7/09 E 0.04 2.35 days 322 mtr 0.04 240.01
70 1.3.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Sat 2/7/09 Mon 2/9/09 E 0.04 2.1 days 34 nos. 0.04 267.7
71 1.3.2.2.1.1.4 Lighting Feeder cables / wires Mon 2/9/09 Mon 4/20/09 E 0.66 11.51 days 1738 mtr 0.66 4163.64
72 1.3.2.2.1.2 Installation - Emergency Shutdown Sat 2/21/09 Sun 5/10/09 0.01 87.34 days 0.61 3814.41
73 1.3.2.2.1.2.1 PVC conduit and boxes Sat 2/21/09 Sat 2/21/09 I 0.01 0.76 days 12 mtr 0.01 63.96
74 1.3.2.2.1.2.2 Instrument cables Wed 4/29/09 Sun 5/10/09 I 0 12.21 days 1944 mtr 0.59 3731.8
75 1.3.2.2.1.2.3 Remote ASI Panel /Cabinet Sun 5/10/09 Sun 5/10/09 I 0 0.33 days 1 mtr 0 18.66
76 1.3.2.3 Operation Floor Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.08 6810.49
77 1.3.2.3.1 Air Compressed System - Piping Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.08 6810.49
78 1.3.2.3.1.1 2" Equal Tee Tue 4/14/09 Sat 4/18/09 P 0 4 days 11 nos 0.03 213.2
79 1.3.2.3.1.2 2" Plug Sat 4/18/09 Sat 4/18/09 P 0 1 day 9 nos 0.01 79.95
80 1.3.2.3.1.3 1/2" Ball valve Sat 4/18/09 Sun 4/19/09 P 0 1 day 2 nos 0 10.66
81 1.3.2.3.1.4 2" x 1" Reducer Sun 4/19/09 Mon 4/20/09 P 0 1 day 2 nos 0 10.66
82 1.3.2.3.1.5 1" x 1/2" Reducer Mon 4/20/09 Tue 4/21/09 P 0 1 day 2 nos 0 10.66
83 1.3.2.3.1.6 1/2" Nipple Tue 4/21/09 Wed 4/22/09 P 0 1 day 2 nos 0 8
84 1.3.2.3.1.7 Installation - Electrical Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.03 6477.36
85 1.3.2.3.1.7.1 Installation - Crane Bus Bars Tue 1/6/09 Sat 1/10/09 0.02 2.97 days 0.02 96.37
86 1.3.2.3.1.7.1.1 Crane Bus Bar Supports installation Tue 1/6/09 Sat 1/10/09 E 0.02 2.97 days 16 nos. 0.02 96.37
87 1.3.2.3.1.7.2 Installation - Socket / Welding Outlet Sun 3/22/09 Sun 4/19/09 0.02 31.02 days 0.06 381.71
88 1.3.2.3.1.7.2.1 Rigid Steel Conduit Sun 3/22/09 Sun 3/22/09 E 0.01 0.84 days 15 mtr 0.01 78.35
89 1.3.2.3.1.7.2.2 Single Core Wires Mon 3/23/09 Mon 3/23/09 E 0 0.36 days 50 mtr 0 27.82
90 1.3.2.3.1.7.2.3 Junction Box Sat 4/18/09 Sat 4/18/09 E 0 0.5 days 2 nos. 0 23.98
91 1.3.2.3.1.7.2.4 Welding outlet / Socket Outlet Sat 4/18/09 Sat 4/18/09 E 0 0.29 days 2 nos. 0 27.05
92 1.3.2.3.1.7.2.5 Socket Feeder cables Sat 4/18/09 Sun 4/19/09 E 0 0.52 days 60 mtr 0.04 224.5
93 1.3.2.3.1.7.3 Installation - Local Junction Box Thu 4/16/09 Sat 6/27/09 0 79.12 days 0.95 5999.29
94 6.73 Rigid Steel Conduit Thu 4/16/09 Thu 4/23/09 E 0 7.83 days 140 mtr 0.12 744.6
95 3.81 Junction Box Tue 5/12/09 Sat 5/16/09 E 0 3.81 days 28 nos. 0.06 372.3
96 8.72 Feeder cables Sat 5/16/09 Sun 5/24/09 E 0 8.72 days 1020 mtr 0.53 3358.01
97 18 Cable Termination Wed 6/10/09 Sat 6/27/09 E 0 18 days 88 nos. 0.24 1524.38
98 1.3.3 Pot 66 Thu 2/12/09 Mon 7/13/09 0.07 166.78 days 2.85 17950.19
99 4.5.2.1 SLI DELIVERABLES Thu 2/12/09 Thu 2/12/09 0 0 days 0 0
100 1.3.3.1.1 POT 66 Area Available for MPEI Construction Thu 2/12/09 Thu 2/12/09 0 0 days 0 0
101 1.3.3.2 Basement Floor Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 1.31 8278.18
102 1.3.3.2.1 Installation - Electrical Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 1.31 8278.18
103 1.3.3.2.1.1 Installation - Lighting System Tue 4/7/09 Wed 5/6/09 0 32.47 days 0.71 4482.42
104 1.3.3.2.1.1.1 PVC conduit and boxes Tue 4/7/09 Wed 4/22/09 E 0 16.38 days 558 mtr 0.28 1777.29
105 1.3.3.2.1.1.2 Single Core Wires Wed 4/22/09 Wed 4/22/09 E 0 0.92 days 132 mtr 0.02 96.85
106 1.3.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Wed 4/22/09 Thu 4/23/09 E 0 0.91 days 12 nos. 0.02 99.43
107 1.3.3.2.1.1.4 Lighting Feeder cables / wires Wed 4/29/09 Wed 5/6/09 E 0 7.99 days 1050 mtr 0.4 2508.86
108 1.3.3.2.1.2 Installation - Emergency Shutdown Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 0.6 3795.76
109 1.3.3.2.1.2.1 PVC conduit and boxes Sat 2/28/09 Sat 2/28/09 I 0.01 0.76 days 12 mtr 0.01 63.96
110 1.3.3.2.1.2.2 Instrument cables Tue 5/5/09 Sun 5/17/09 I 0 12.21 days 1944 mtr 0.59 3731.8
111 1.3.3.3 Operation Floor Tue 3/24/09 Mon 7/13/09 0.05 122.87 days 1.54 9672
112 1.3.3.3.1 Air Compressed System - Piping Sat 4/18/09 Sun 4/26/09 0 9 days 0.05 333.13
113 1.3.3.3.1.1 2" Equal Tee Sat 4/18/09 Tue 4/21/09 P 0 4 days 11 nos 0.03 213.2
114 1.3.3.3.1.2 2" Plug Tue 4/21/09 Wed 4/22/09 P 0 1 day 9 nos 0.01 79.95
115 1.3.3.3.1.3 1/2" Ball valve Wed 4/22/09 Wed 4/22/09 P 0 1 day 2 nos 0 10.66
116 1.3.3.3.1.4 2" x 1" Reducer Wed 4/22/09 Thu 4/23/09 P 0 1 day 2 nos 0 10.66
2/3
Material by Astaldi
Material by SNC
Material by SNC
2/12
Material by Astaldi
Material by SNC
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 2 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
117 1.3.3.3.1.5 1" x 1/2" Reducer Thu 4/23/09 Sat 4/25/09 P 0 1 day 2 nos 0 10.66
118 1.3.3.3.1.6 1/2" Nipple Sat 4/25/09 Sun 4/26/09 P 0 1 day 2 nos 0 8
119 1.3.3.3.2 Installation - Electrical Tue 3/24/09 Mon 7/13/09 0.05 122.87 days 1.48 9338.88
120 1.3.3.3.2.1 Installation - Lighting System Tue 3/24/09 Thu 5/7/09 0.05 49.56 days 0.08 523.22
121 1.3.3.3.2.1.1 Rigid Steel Conduit Tue 3/24/09 Tue 3/24/09 E 0.03 0.7 days 26 mtr 0.03 157.5
122 1.3.3.3.2.1.2 Single Core Wires Wed 3/25/09 Wed 3/25/09 E 0.03 1.04 days 300 mtr 0.03 188.82
123 1.3.3.3.2.1.3 High Bay Lighting fixtures including supports and fixings Sun 4/19/09 Sun 4/19/09 E 0 0.84 days 6 nos. 0.02 155.58
124 1.3.3.3.2.1.4 Lighting Feeder cables / wires Wed 5/6/09 Thu 5/7/09 E 0 1 day 8 mtr 0 21.32
125 1.3.3.3.2.2 Installation - Cable Tray Sat 4/18/09 Wed 4/29/09 0 12.4 days 0.06 401.4
126 1.3.3.3.2.2.1 Cantilever supports installation Sat 4/18/09 Sun 4/19/09 E 0 0.21 days 22 nos. 0 22.95
127 1.3.3.3.2.2.2 Cable Tray installation Tue 4/28/09 Wed 4/29/09 E 0 1.65 days 202 mtr 0.06 378.46
128 1.3.3.3.2.3 Installation - Blower and Transformer Feeder Tue 4/7/09 Mon 4/13/09 0 5.85 days 0.43 2725.18
129 1.3.3.3.2.3.1 Blower Feeder, Transformer Feeder Tue 4/7/09 Mon 4/13/09 E 0 5.85 days 700 mtr 0.43 2725.18
130 1.3.3.3.2.4 Installation - Local Junction Box Thu 4/16/09 Mon 7/13/09 0 97.03 days 0.9 5689.08
131 1.3.3.3.2.4.1 Rigid Steel Conduit Thu 4/16/09 Wed 4/22/09 E 0 7.08 days 130 mtr 0.11 691.83
132 1.3.3.3.2.4.2 Junction Box Wed 4/22/09 Sun 4/26/09 E 0 3.54 days 26 nos. 0.05 345.92
133 1.3.3.3.2.4.3 Feeder cables Wed 4/29/09 Wed 5/6/09 E 0 8.12 days 948 mtr 0.5 3126.95
134 1.3.3.3.2.4.4 Cable Termination Sat 6/27/09 Mon 7/13/09 E 0 18 days 88 nos. 0.24 1524.38
135 1.3.4 Pot 88 Thu 2/19/09 Wed 7/29/09 0.29 177.03 days 3.21 20200.41
136 4.5.2.1 SLI DELIVERABLES Thu 2/19/09 Thu 2/19/09 0 0 days 0 0
137 1.3.4.1.1 POT 88 Area Available for MPEI Construction Thu 2/19/09 Thu 2/19/09 0 0 days 0 0
138 1.3.4.2 Basement Floor Sat 3/14/09 Sat 5/23/09 0.29 78.51 days 1.32 8308.64
139 1.3.4.2.1 Installation - Electrical Sat 3/14/09 Sat 5/23/09 0.29 78.51 days 1.32 8308.64
140 1.3.4.2.1.1 Installation - Lighting System Sat 3/14/09 Mon 5/11/09 0.28 64.57 days 0.71 4494.23
141 1.3.4.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.45 days 560 mtr 0.28 1784.88
142 1.3.4.2.1.1.2 Single Core Wires Thu 5/7/09 Thu 5/7/09 E 0 0.96 days 137 mtr 0.02 101.06
143 1.3.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Tue 5/5/09 Wed 5/6/09 E 0 0.91 days 12 nos. 0.02 99.43
144 1.3.4.2.1.1.4 Lighting Feeder cables / wires Sun 5/3/09 Mon 5/11/09 E 0 7.99 days 1050 mtr 0.4 2508.86
145 1.3.4.2.1.2 Installation - Emergency Shutdown Tue 3/24/09 Sat 5/23/09 0.01 66.89 days 0.61 3814.41
146 1.3.4.2.1.2.1 PVC conduit and boxes Tue 3/24/09 Tue 3/24/09 I 0.01 0.76 days 12 mtr 0.01 63.96
147 1.3.4.2.1.2.2 Instrument cables Tue 5/12/09 Sat 5/23/09 I 0 12.21 days 1944 mtr 0.59 3731.8
148 1.3.4.2.1.2.3 Remote ASI Panel /Cabinet Sat 5/23/09 Sat 5/23/09 I 0 0.33 days 1 mtr 0 18.66
149 1.3.4.3 Operation Floor Mon 4/13/09 Wed 7/29/09 0 118.93 days 1.89 11891.76
150 1.3.4.3.1 Air Compressed System - Piping Tue 4/21/09 Wed 4/29/09 0 9 days 0.05 333.13
151 1.3.4.3.1.1 2" Equal Tee Tue 4/21/09 Sat 4/25/09 P 0 4 days 11 nos 0.03 213.2
152 1.3.4.3.1.2 2" Plug Sat 4/25/09 Sun 4/26/09 P 0 1 day 9 nos 0.01 79.95
153 1.3.4.3.1.3 1/2" Ball valve Sun 4/26/09 Sun 4/26/09 P 0 1 day 2 nos 0 10.66
154 1.3.4.3.1.4 2" x 1" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66
155 1.3.4.3.1.5 1" x 1/2" Reducer Mon 4/27/09 Tue 4/28/09 P 0 1 day 2 nos 0 10.66
156 1.3.4.3.1.6 1/2" Nipple Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 8
157 1.3.4.3.2 Installation - Electrical Mon 4/13/09 Wed 7/29/09 0 118.93 days 1.84 11558.64
158 1.3.4.3.2.1 Installation - Lighting System Sat 4/18/09 Sat 5/9/09 0 23.13 days 0.14 887.79
159 1.3.4.3.2.1.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/18/09 E 0 0.7 days 25 mtr 0.03 157.5
160 1.3.4.3.2.1.2 Single Core Wires Sat 4/18/09 Sun 4/19/09 E 0 1.04 days 300 mtr 0.03 188.82
161 1.3.4.3.2.1.3 High Bay Lighting fixtures including supports and fixings Sun 4/19/09 Mon 4/20/09 E 0 0.84 days 6 nos. 0.02 155.58
162 1.3.4.3.2.1.4 Lighting Feeder cables / wires Thu 5/7/09 Sat 5/9/09 E 0 0.7 days 100 mtr 0.06 385.89
163 1.3.4.3.2.2 Installation - Cable Tray Sun 4/19/09 Thu 4/30/09 0 13.84 days 0.06 401.4
164 1.3.4.3.2.2.1 Cantilever supports installation Sun 4/19/09 Sun 4/19/09 E 0 0.21 days 22 nos. 0 22.95
165 1.3.4.3.2.2.2 Cable Tray installation Wed 4/29/09 Thu 4/30/09 E 0 1.65 days 202 mtr 0.06 378.46
166 1.3.4.3.2.3 Installation - Crane Bus Bars Tue 5/5/09 Tue 5/26/09 0 23.36 days 0.43 2703.64
167 1.3.4.3.2.3.1 Disconnect Switch Instalation Tue 5/5/09 Tue 5/5/09 E 0 0.5 days 1 nos. 0 17.32
168 1.3.4.3.2.3.2 Interconnection cable, cableways installation Tue 5/5/09 Wed 5/6/09 E 0 1 day 5 nos. 0.02 133.25
169 1.3.4.3.2.3.3 Crane Power Feeder Cable Wed 5/6/09 Sat 5/9/09 E 0 2.48 days 330 mtr 0.39 2466.88
170 1.3.4.3.2.3.4 Cable Termination Mon 5/25/09 Tue 5/26/09 E 0 0.99 days 5 nos. 0.01 86.19
171 1.3.4.3.2.4 Installation - Blower and Transformer Feeder Mon 4/13/09 Sat 4/18/09 0 5.85 days 0.43 2725.18
172 1.3.4.3.2.4.1 Blower Feeder, Transformer Feeder Mon 4/13/09 Sat 4/18/09 E 0 5.85 days 700 mtr 0.43 2725.18
173 1.3.4.3.2.5 Installation - Socket / Welding Outlet Wed 4/22/09 Sat 4/25/09 0 2.51 days 0.06 381.71
174 1.3.4.3.2.5.1 Rigid Steel Conduit Wed 4/22/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35
2/19
2/19
Material by Astaldi
Material by SNC
Material by SNC
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 3 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
175 1.3.4.3.2.5.2 Single Core Wires Thu 4/23/09 Thu 4/23/09 E 0 0.36 days 50 mtr 0 27.82
176 1.3.4.3.2.5.3 Junction Box Thu 4/23/09 Thu 4/23/09 E 0 0.5 days 2 nos. 0 23.98
177 1.3.4.3.2.5.4 Welding outlet / Socket Outlet Thu 4/23/09 Sat 4/25/09 E 0 0.29 days 2 nos. 0 27.05
178 1.3.4.3.2.5.5 Socket Feeder cables Sat 4/25/09 Sat 4/25/09 E 0 0.52 days 60 mtr 0.04 224.5
179 1.3.4.3.2.6 Installation - Local Junction Box Wed 4/22/09 Wed 7/29/09 0 107.95 days 0.71 4458.92
180 1.3.4.3.2.6.1 Rigid Steel Conduit Wed 4/22/09 Wed 4/29/09 E 0 7.62 days 140 mtr 0.12 744.6
181 1.3.4.3.2.6.2 Junction Box Wed 4/29/09 Sun 5/3/09 E 0 3.81 days 28 nos. 0.06 372.3
182 1.3.4.3.2.6.3 Feeder cables Sun 5/3/09 Thu 5/7/09 E 0 4.72 days 550 mtr 0.29 1817.64
183 1.3.4.3.2.6.4 Cable Termination Mon 7/13/09 Wed 7/29/09 E 0 18 days 88 nos. 0.24 1524.38
184 1.4 Construction - Potroom No. 2 (501-22A) Sat 11/22/08 Sun 6/14/09 3.16 226.15 days 11.78 74187.76
185 1.4.1 Pot 22 Sat 11/22/08 Sat 5/30/09 0.75 209.84 days 3.26 20550.51
186 1.4.1.1 SLI DELIVERABLES Sat 11/22/08 Sat 11/22/08 0 0 days 0 0
187 1.4.1.1.1 POT 22 Area Available for MPEI Construction Sat 11/22/08 Sat 11/22/08 0 0 days 0 0
188 1.4.1.2 Basement Floor Sat 11/22/08 Tue 4/21/09 0.63 167.68 days 1.22 7669.18
189 1.4.1.2.1 Installation - Electrical Sat 11/22/08 Tue 4/21/09 0.63 167.68 days 1.22 7669.18
190 1.4.1.2.1.1 Installation - Lighting System Sat 11/22/08 Thu 2/5/09 0.61 84.89 days 0.61 3873.42
191 1.4.1.2.1.1.1 PVC conduit and boxes Sat 11/22/08 Sun 11/23/08 E 0.04 2.28 days 75 mtr 0.04 243.05
192 1.4.1.2.1.1.2 Single Core Wires Thu 11/27/08 Sat 11/29/08 E 0.02 0.82 days 165 mtr 0.02 122.11
193 1.4.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Wed 11/26/08 Thu 11/27/08 E 0.02 1.26 days 18 nos. 0.02 145.32
194 1.4.1.2.1.1.4 Lighting Feeder cables / wires Thu 1/29/09 Thu 2/5/09 E 0.53 8.53 days 1400 mtr 0.53 3362.94
195 1.4.1.2.1.2 Installation - Emergency Shutdown Thu 2/12/09 Tue 4/21/09 0.01 75.97 days 0.6 3795.76
196 1.4.1.2.1.2.1 PVC conduit and boxes Thu 2/12/09 Thu 2/12/09 I 0.01 0.76 days 12 mtr 0.01 63.96
197 1.4.1.2.1.2.2 Instrument cables Sat 4/11/09 Tue 4/21/09 I 0 12.21 days 1944 mtr 0.59 3731.8
198 1.4.1.3 Operation Floor Sat 11/22/08 Sat 5/30/09 0.13 209.84 days 2.05 12881.33
199 1.4.1.3.1 Air Compressed System - Piping Tue 4/14/09 Wed 4/22/09 0 9 days 0.05 333.13
200 1.4.1.3.1.1 2" Equal Tee Tue 4/14/09 Sat 4/18/09 P 0 4 days 11 nos 0.03 213.2
201 1.4.1.3.1.2 2" Plug Sat 4/18/09 Sat 4/18/09 P 0 1 day 9 nos 0.01 79.95
202 1.4.1.3.1.3 1/2" Ball valve Sat 4/18/09 Sun 4/19/09 P 0 1 day 2 nos 0 10.66
203 1.4.1.3.1.4 2" x 1" Reducer Sun 4/19/09 Mon 4/20/09 P 0 1 day 2 nos 0 10.66
204 1.4.1.3.1.5 1" x 1/2" Reducer Mon 4/20/09 Tue 4/21/09 P 0 1 day 2 nos 0 10.66
205 1.4.1.3.1.6 1/2" Nipple Tue 4/21/09 Wed 4/22/09 P 0 1 day 2 nos 0 8
206 1.4.1.3.2 Installation - Electrical Sat 11/22/08 Sat 5/30/09 0.13 209.84 days 1.99 12548.21
207 1.4.1.3.2.1 Installation - Lighting System Sat 11/22/08 Tue 12/2/08 0.08 12.4 days 0.08 501.9
208 1.4.1.3.2.1.1 Rigid Steel Conduit Sat 11/22/08 Sat 11/22/08 E 0.03 0.71 days 26 mtr 0.03 157.5
209 1.4.1.3.2.1.2 Single Core Wires Mon 12/1/08 Tue 12/2/08 E 0.03 0.92 days 300 mtr 0.03 188.82
210 1.4.1.3.2.1.3 High Bay Lighting fixtures including supports and fixings Tue 12/2/08 Tue 12/2/08 E 0.02 0.77 days 6 nos. 0.02 155.58
211 1.4.1.3.2.2 Installation - Crane Bus Bars Thu 12/4/08 Wed 5/13/09 0.03 176.84 days 0.9 5665.31
212 1.4.1.3.2.2.1 Crane Bus Bar Supports installation Thu 12/4/08 Tue 12/9/08 E 0.02 4.84 days 16 nos. 0.02 96.37
213 1.4.1.3.2.2.2 Feed Junction Box Installation Tue 12/9/08 Wed 12/10/08 E 0.01 1.38 days 4 nos. 0.01 70.89
214 1.4.1.3.2.2.3 Disconnect Switch Instalation Wed 12/10/08 Wed 12/10/08 E 0 0.46 days 1 nos. 0 17.32
215 1.4.1.3.2.2.4 Interconnection cable, cableways installation Wed 5/6/09 Thu 5/7/09 E 0 1 day 5 nos. 0.02 133.25
216 1.4.1.3.2.2.5 Crane Power Feeder Cable Thu 5/7/09 Tue 5/12/09 E 0 5.2 days 682 mtr 0.82 5172.5
217 1.4.1.3.2.2.6 Cable Termination Tue 5/12/09 Wed 5/13/09 E 0 2.01 days 10 nos. 0.03 174.98
218 1.4.1.3.2.3 Installation - Socket / Welding Outlet Tue 12/9/08 Wed 2/4/09 0.02 63.41 days 0.06 381.71
219 1.4.1.3.2.3.1 Rigid Steel Conduit Tue 12/9/08 Wed 12/10/08 E 0.01 0.87 days 15 mtr 0.01 78.35
220 1.4.1.3.2.3.2 Single Core Wires Mon 2/2/09 Tue 2/3/09 E 0 0.46 days 50 mtr 0 27.82
221 1.4.1.3.2.3.3 Junction Box Tue 2/3/09 Tue 2/3/09 E 0 0.91 days 2 nos. 0 23.98
222 1.4.1.3.2.3.4 Welding outlet / Socket Outlet Tue 2/3/09 Wed 2/4/09 E 0 0.65 days 2 nos. 0 27.05
223 1.4.1.3.2.3.5 Socket Feeder cables Wed 2/4/09 Wed 2/4/09 E 0 0.52 days 60 mtr 0.04 224.5
224 1.4.1.3.2.4 Installation - Local Junction Box Mon 4/6/09 Sat 5/30/09 0 59.84 days 0.95 5999.29
225 1.4.1.3.2.4.1 Rigid Steel Conduit Mon 4/6/09 Mon 4/13/09 E 0 7.62 days 140 mtr 0.12 744.6
226 1.4.1.3.2.4.2 Junction Box Mon 4/13/09 Thu 4/16/09 E 0 3.81 days 28 nos. 0.06 372.3
227 1.4.1.3.2.4.3 Feeder cables Thu 4/16/09 Thu 4/23/09 E 0 8.72 days 1020 mtr 0.53 3358.01
228 1.4.1.3.2.4.4 Cable Termination Wed 5/13/09 Sat 5/30/09 E 0 18 days 88 nos. 0.24 1524.38
229 1.4.2 Pot 44 Sat 12/27/08 Tue 5/12/09 0.81 150.59 days 2.18 13753.32
230 1.4.2.1 SLI DELIVERABLES Fri 1/23/09 Fri 1/23/09 0 0 days 0 0
231 1.4.2.1.1 POT 44 Area Available for MPEI Construction Fri 1/23/09 Fri 1/23/09 0 0 days 0 0
232 1.4.2.2 Basement Floor Sat 12/27/08 Mon 4/27/09 0.78 134.2 days 1.37 8641.5
233 1.4.2.2.1 Installation - Electrical Sat 12/27/08 Mon 4/27/09 0.78 134.2 days 1.37 8641.5
11/22
11/22
Electrical rooms not ready
Material by Astaldi
Material by SNC
No cable and cable trays
junction box details to be submitted
Material not yet approved by SNC
1/23
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 4 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
234 1.4.2.2.1.1 Installation - Lighting System Sat 12/27/08 Sun 2/15/09 0.77 55.26 days 0.77 4827.09
235 1.4.2.2.1.1.1 PVC conduit and boxes Sat 12/27/08 Mon 12/29/08 E 0.05 2.33 days 95 mtr 0.05 303.81
236 1.4.2.2.1.1.2 Single Core Wires Sat 1/24/09 Sat 1/24/09 E 0.03 1.21 days 228 mtr 0.03 168.43
237 1.4.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Wed 1/21/09 Thu 1/22/09 E 0.03 1.77 days 24 nos. 0.03 191.21
238 1.4.2.2.1.1.4 Lighting Feeder cables / wires Thu 2/5/09 Sun 2/15/09 E 0.66 9.93 days 1738 mtr 0.66 4163.64
239 1.4.2.2.1.2 Installation - Emergency Shutdown Thu 2/19/09 Mon 4/27/09 0.01 74.3 days 0.61 3814.41
240 1.4.2.2.1.2.1 PVC conduit and boxes Thu 2/19/09 Thu 2/19/09 I 0.01 0.76 days 12 mtr 0.01 63.96
241 1.4.2.2.1.2.2 Instrument cables Wed 4/15/09 Mon 4/27/09 I 0 12.21 days 1944 mtr 0.59 3731.8
242 1.4.2.2.1.2.3 Remote ASI Panel /Cabinet Mon 4/27/09 Mon 4/27/09 I 0 0.33 days 1 mtr 0 18.66
243 1.4.2.3 Operation Floor Sat 12/27/08 Tue 5/12/09 0.03 150.59 days 0.81 5111.82
244 1.4.2.3.1 Air Compressed System - Piping Sat 4/18/09 Wed 5/6/09 0 21 days 0.05 333.13
245 1.4.2.3.1.1 2" Equal Tee Sat 4/18/09 Tue 4/21/09 P 0 4 days 11 nos 0.03 213.2
246 1.4.2.3.1.2 2" Plug Sun 5/3/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95
247 1.4.2.3.1.3 1/2" Ball valve Mon 5/4/09 Mon 5/4/09 P 0 1 day 2 nos 0 10.66
248 1.4.2.3.1.4 2" x 1" Reducer Mon 5/4/09 Tue 5/5/09 P 0 1 day 2 nos 0 10.66
249 1.4.2.3.1.5 1" x 1/2" Reducer Mon 5/4/09 Tue 5/5/09 P 0 1 day 2 nos 0 10.66
250 1.4.2.3.1.6 1/2" Nipple Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 8
251 1.4.2.3.2 Installation - Electrical Sat 12/27/08 Tue 5/12/09 0.03 150.59 days 0.76 4778.69
252 1.4.2.3.2.1 Installation - Crane Bus Bars Sat 12/27/08 Sun 12/28/08 0.02 0.99 days 0.02 96.37
253 1.4.2.3.2.1.1 Crane Bus Bar Supports installation Sat 12/27/08 Sun 12/28/08 E 0.02 0.99 days 16 nos. 0.02 96.37
254 1.4.2.3.2.2 Installation - Socket / Welding Outlet Sat 1/24/09 Wed 2/4/09 0.02 14.14 days 0.06 381.71
255 1.4.2.3.2.2.1 Rigid Steel Conduit Sat 1/24/09 Tue 1/27/09 E 0.01 5 days 15 mtr 0.01 78.35
256 1.4.2.3.2.2.2 Single Core Wires Tue 1/27/09 Wed 1/28/09 E 0 0.84 days 50 mtr 0 27.82
257 1.4.2.3.2.2.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.72 days 2 nos. 0 23.98
258 1.4.2.3.2.2.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 27.05
259 1.4.2.3.2.2.5 Socket Feeder cables Wed 2/4/09 Wed 2/4/09 E 0 0.29 days 60 mtr 0.04 224.5
260 1.4.2.3.2.3 Installation - Local Junction Box Mon 4/13/09 Tue 5/12/09 0 32.53 days 0.68 4300.62
261 1.4.2.3.2.3.1 Rigid Steel Conduit Mon 4/13/09 Sat 4/18/09 E 0 6 days 110 mtr 0.09 586.3
262 1.4.2.3.2.3.2 Junction Box Sat 4/18/09 Tue 4/21/09 E 0 3.81 days 28 nos. 0.06 372.3
263 1.4.2.3.2.3.3 Feeder cables Tue 4/21/09 Sun 4/26/09 E 0 4.72 days 550 mtr 0.29 1817.64
264 1.4.2.3.2.3.4 Cable Termination Sun 4/26/09 Tue 5/12/09 E 0 18 days 88 nos. 0.24 1524.38
265 1.4.3 Pot 66 Sat 1/31/09 Thu 5/28/09 0.79 130.65 days 2.84 17917.57
266 1.4.3.1 SLI DELIVERABLES Sat 1/31/09 Sat 1/31/09 0 0 days 0 0
267 1.4.3.1.1 POT 66 Area Available for MPEI Construction Sat 1/31/09 Sat 1/31/09 0 0 days 0 0
268 1.4.3.2 Basement Floor Sun 3/1/09 Thu 5/7/09 0.71 75.42 days 1.31 8282.39
269 1.4.3.2.1 Installation - Electrical Sun 3/1/09 Thu 5/7/09 0.71 75.42 days 1.31 8282.39
270 1.4.3.2.1.1 Installation - Lighting System Sat 3/14/09 Wed 4/22/09 0.71 43.74 days 0.71 4486.63
271 1.4.3.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.38 days 558 mtr 0.28 1777.29
272 1.4.3.2.1.1.2 Single Core Wires Sun 4/19/09 Sun 4/19/09 E 0.02 0.96 days 135 mtr 0.02 101.06
273 1.4.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 4/16/09 Sat 4/18/09 E 0.02 0.91 days 12 nos. 0.02 99.43
274 1.4.3.2.1.1.4 Lighting Feeder cables / wires Tue 4/14/09 Wed 4/22/09 E 0.4 7.99 days 1050 mtr 0.4 2508.86
275 1.4.3.2.1.2 Installation - Emergency Shutdown Sun 3/1/09 Thu 5/7/09 0 75.42 days 0.6 3795.76
276 1.4.3.2.1.2.1 PVC conduit and boxes Sun 3/1/09 Mon 3/2/09 I 0 0.76 days 12 mtr 0.01 63.96
277 1.4.3.2.1.2.2 Instrument cables Mon 4/27/09 Thu 5/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8
278 1.4.3.3 Operation Floor Tue 3/24/09 Thu 5/28/09 0.08 72.53 days 1.53 9635.17
279 1.4.3.3.1 Air Compressed System - Piping Tue 4/21/09 Thu 5/14/09 0 26 days 0.05 333.13
280 1.4.3.3.1.1 2" Equal Tee Tue 4/21/09 Sat 4/25/09 P 0 4 days 11 nos 0.03 213.2
281 1.4.3.3.1.2 2" Plug Mon 5/11/09 Tue 5/12/09 P 0 1 day 9 nos 0.01 79.95
282 1.4.3.3.1.3 1/2" Ball valve Tue 5/12/09 Tue 5/12/09 P 0 1 day 2 nos 0 10.66
283 1.4.3.3.1.4 2" x 1" Reducer Tue 5/12/09 Wed 5/13/09 P 0 1 day 2 nos 0 10.66
284 1.4.3.3.1.5 1" x 1/2" Reducer Tue 5/12/09 Wed 5/13/09 P 0 1 day 2 nos 0 10.66
285 1.4.3.3.1.6 1/2" Nipple Wed 5/13/09 Thu 5/14/09 P 0 1 day 2 nos 0 8
286 1.4.3.3.2 Installation - Electrical Tue 3/24/09 Thu 5/28/09 0.08 72.53 days 1.48 9302.05
287 1.4.3.3.2.1 Installation - Lighting System Tue 3/24/09 Tue 4/21/09 0.08 31.28 days 0.14 887.79
288 1.4.3.3.2.1.1 Rigid Steel Conduit Tue 3/24/09 Tue 3/24/09 E 0.03 0.7 days 26 mtr 0.03 157.5
289 1.4.3.3.2.1.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0.03 1.04 days 300 mtr 0.03 188.82
290 1.4.3.3.2.1.3 High Bay Lighting fixtures including supports and fixings Mon 4/20/09 Mon 4/20/09 E 0.02 0.84 days 6 nos. 0.02 155.58
291 1.4.3.3.2.1.4 Lighting Feeder cables / wires Mon 4/20/09 Tue 4/21/09 E 0 0.7 days 98 mtr 0.06 385.89
On going
On going
Material by Astaldi
Material by SNC
Material by SNC
No manlift available
1/31
Material by Astaldi
Material by SNC
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 5 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
292 1.4.3.3.2.2 Installation - Blower and Transformer Feeder Sat 4/18/09 Thu 4/23/09 0 5.85 days 0.43 2725.18
293 1.4.3.3.2.2.1 Blower Feeder, Transformer Feeder Sat 4/18/09 Thu 4/23/09 E 0 5.85 days 700 mtr 0.43 2725.18
294 1.4.3.3.2.3 Installation - Local Junction Box Sat 4/18/09 Thu 5/28/09 0 44.53 days 0.9 5689.08
295 1.4.3.3.2.3.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/25/09 E 0 7.08 days 130 mtr 0.11 691.83
296 1.4.3.3.2.3.2 Junction Box Sat 4/25/09 Tue 4/28/09 E 0 3.54 days 26 nos. 0.05 345.92
297 1.4.3.3.2.3.3 Feeder cables Tue 4/28/09 Tue 5/5/09 E 0 8.12 days 948 mtr 0.5 3126.95
298 1.4.3.3.2.3.4 Cable Termination Tue 5/12/09 Thu 5/28/09 E 0 18 days 88 nos. 0.24 1524.38
299 1.4.4 Pot 88 Sun 1/25/09 Sun 6/14/09 0.81 155.19 days 3.49 21966.37
300 1.4.4.1 SLI DELIVERABLES Thu 2/5/09 Thu 2/5/09 0 0 days 0 0
301 1.4.4.1.1 POT 88 Area Available for MPEI Construction Thu 2/5/09 Thu 2/5/09 0 0 days 0 0
302 1.4.4.2 Basement Floor Sat 3/14/09 Tue 5/19/09 0.71 74.18 days 1.32 8308.64
303 1.4.4.2.1 Installation - Electrical Sat 3/14/09 Tue 5/19/09 0.71 74.18 days 1.32 8308.64
304 1.4.4.2.1.1 Installation - Lighting System Sat 3/14/09 Sat 3/28/09 0.71 16.45 days 0.71 4494.23
305 1.4.4.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.45 days 560 mtr 0.28 1784.88
306 1.4.4.2.1.1.2 Single Core Wires Sun 3/15/09 Sun 3/15/09 E 0.02 0.96 days 137 mtr 0.02 101.06
307 1.4.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Sun 3/22/09 Sun 3/22/09 E 0.02 0.91 days 12 nos. 0.02 99.43
308 1.4.4.2.1.1.4 Lighting Feeder cables / wires Sat 3/21/09 Sat 3/28/09 E 0.4 7.99 days 1050 mtr 0.4 2508.86
309 1.4.4.2.1.2 Installation - Emergency Shutdown Thu 4/30/09 Tue 5/19/09 0 21.22 days 0.61 3814.41
310 1.4.4.2.1.2.1 PVC conduit and boxes Thu 4/30/09 Thu 4/30/09 I 0 0.76 days 12 mtr 0.01 63.96
311 1.4.4.2.1.2.2 Instrument cables Thu 5/7/09 Tue 5/19/09 I 0 12.21 days 1944 mtr 0.59 3731.8
312 1.4.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 5/19/09 Tue 5/19/09 I 0 0.33 days 1 mtr 0 18.66
313 1.4.4.3 Operation Floor Sun 1/25/09 Sun 6/14/09 0.09 155.19 days 2.17 13657.73
314 1.4.4.3.1 Air Compressed System - Piping Sat 4/25/09 Sat 5/16/09 0 23 days 0.05 333.13
315 1.4.4.3.1.1 2" Equal Tee Sat 4/25/09 Tue 4/28/09 P 0 4 days 11 nos 0.03 213.2
316 1.4.4.3.1.2 2" Plug Tue 4/28/09 Wed 4/29/09 P 0 1 day 9 nos 0.01 79.95
317 1.4.4.3.1.3 1/2" Ball valve Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66
318 1.4.4.3.1.4 2" x 1" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66
319 1.4.4.3.1.5 1" x 1/2" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66
320 1.4.4.3.1.6 1/2" Nipple Thu 5/14/09 Sat 5/16/09 P 0 1 day 2 nos 0 8
321 1.4.4.3.2 Installation - Electrical Sun 1/25/09 Sun 6/14/09 0.09 155.19 days 2.12 13324.6
322 1.4.4.3.2.1 Installation - Lighting System Mon 3/23/09 Tue 4/21/09 0.08 33.27 days 0.14 887.79
323 1.4.4.3.2.1.1 Rigid Steel Conduit Mon 3/23/09 Mon 3/23/09 E 0.03 0.7 days 25 mtr 0.03 157.5
324 1.4.4.3.2.1.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0.03 1.04 days 300 mtr 0.03 188.82
325 1.4.4.3.2.1.3 High Bay Lighting fixtures including supports and fixings Mon 4/20/09 Tue 4/21/09 E 0.02 0.84 days 6 nos. 0.02 155.58
326 1.4.4.3.2.1.4 Lighting Feeder cables / wires Tue 4/21/09 Tue 4/21/09 E 0 0.7 days 100 mtr 0.06 385.89
327 1.4.4.3.2.2 Installation - Cable Tray Sun 4/19/09 Wed 4/29/09 0 12.65 days 0.06 382.29
328 1.4.4.3.2.2.1 Cantilever supports installation Sun 4/19/09 Sun 4/19/09 E 0 0.35 days 32 nos. 0.01 38.24
329 1.4.4.3.2.2.2 Cable Tray installation Tue 4/28/09 Wed 4/29/09 E 0 1.5 days 189 mtr 0.05 344.05
330 1.4.4.3.2.3 Installation - Crane Bus Bars Sun 1/25/09 Thu 5/14/09 0.02 121.87 days 0.71 4488.71
331 1.4.4.3.2.3.1 Crane Bus Bar Supports installation Sun 1/25/09 Mon 1/26/09 E 0.02 1.94 days 16 nos. 0.02 96.37
332 1.4.4.3.2.3.2 Feed Junction Box Installation Mon 1/26/09 Mon 1/26/09 E 0 0.33 days 1 nos. 0 17.59
333 1.4.4.3.2.3.3 Disconnect Switch Instalation Tue 5/5/09 Tue 5/5/09 E 0 0.5 days 1 nos. 0 17.32
334 1.4.4.3.2.3.4 Interconnection cable, cableways installation Tue 5/5/09 Wed 5/6/09 E 0 1 day 5 nos. 0.02 133.25
335 1.4.4.3.2.3.5 Crane Power Feeder Cable Wed 5/6/09 Sun 5/10/09 E 0 4.16 days 550 mtr 0.66 4138
336 1.4.4.3.2.3.6 Cable Termination Wed 5/13/09 Thu 5/14/09 E 0 0.99 days 5 nos. 0.01 86.19
337 1.4.4.3.2.4 Installation - Blower and Transformer Feeder Thu 4/23/09 Tue 4/28/09 0 5.85 days 0.43 2725.18
338 1.4.4.3.2.4.1 Blower Feeder, Transformer Feeder Thu 4/23/09 Tue 4/28/09 E 0 5.85 days 700 mtr 0.43 2725.18
339 1.4.4.3.2.5 Installation - Socket / Welding Outlet Sun 4/19/09 Tue 4/21/09 0 2.51 days 0.06 381.71
340 1.4.4.3.2.5.1 Rigid Steel Conduit Sun 4/19/09 Sun 4/19/09 E 0 0.84 days 15 mtr 0.01 78.35
341 1.4.4.3.2.5.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0 0.36 days 50 mtr 0 27.82
342 1.4.4.3.2.5.3 Junction Box Mon 4/20/09 Mon 4/20/09 E 0 0.5 days 2 nos. 0 23.98
343 1.4.4.3.2.5.4 Welding outlet / Socket Outlet Mon 4/20/09 Mon 4/20/09 E 0 0.29 days 2 nos. 0 27.05
344 1.4.4.3.2.5.5 Socket Feeder cables Mon 4/20/09 Tue 4/21/09 E 0 0.52 days 60 mtr 0.04 224.5
345 1.4.4.3.2.6 Installation - Local Junction Box Sat 4/18/09 Sun 6/14/09 0 62.53 days 0.71 4458.92
346 1.4.4.3.2.6.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/25/09 E 0 7.62 days 140 mtr 0.12 744.6
347 1.4.4.3.2.6.2 Junction Box Sat 4/25/09 Tue 4/28/09 E 0 3.81 days 28 nos. 0.06 372.3
348 1.4.4.3.2.6.3 Feeder cables Wed 4/29/09 Mon 5/4/09 E 0 4.72 days 550 mtr 0.29 1817.64
349 1.4.4.3.2.6.4 Cable Termination Thu 5/28/09 Sun 6/14/09 E 0 18 days 88 nos. 0.24 1524.38
350 1.5 Construction - South Qtr. Passageway 503-22 Sat 2/28/09 Wed 5/13/09 0 83.5 days 2.69 16954.65
Electrical room not ready
Material not approved
2/5
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 6 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
351 1.5.1 SLI DELIVERABLES Sat 2/28/09 Sat 2/28/09 0 0 days 0 0
352 1.5.1.1 1st- QTR Passageway Available for MPEI Construction Sat 2/28/09 Sat 2/28/09 0 0 days 0 0
353 1.5.2 Operation Floor Sun 4/5/09 Wed 5/13/09 0 43.5 days 2.69 16954.65
354 1.5.2.1 Installation - Electrical (Operation Floor) Sun 4/5/09 Wed 5/13/09 0 43.5 days 2.69 16954.65
355 1.5.2.1.1 Installation - Lighting System Wed 4/8/09 Sun 5/3/09 0 26.19 days 0.16 1030.61
356 1.5.2.1.1.1 High Bay Lighting fixtures including supports and fixings Wed 4/8/09 Sat 4/11/09 E 0 2 days 9 nos. 0.04 234.52
357 1.5.2.1.1.2 Rigid Steel Conduit Sat 4/11/09 Mon 4/13/09 E 0 2.76 days 55 mtr 0.05 330.99
358 1.5.2.1.1.3 Single Core Wires Mon 4/13/09 Tue 4/14/09 E 0 1.66 days 150 mtr 0.02 97.33
359 1.5.2.1.1.4 Lighting Feeder cables / wires Sat 5/2/09 Sun 5/3/09 E 0 0.69 days 90 mtr 0.06 367.77
360 1.5.2.1.2 Installation - Cable Tray Sun 4/5/09 Sat 5/2/09 0 30.5 days 0.55 3457.17
361 1.5.2.1.2.1 Cantilever supports installation Sun 4/5/09 Sat 4/11/09 E 0 6.5 days 265 nos. 0.09 577.64
362 1.5.2.1.2.2 Cable tray installation Sat 4/11/09 Sat 5/2/09 E 0 24 days 1591 mtr 0.46 2879.53
363 1.5.2.1.3 Installation - Crane Bus Bars Sat 4/11/09 Wed 5/13/09 0 37 days 1.98 12466.87
364 1.5.2.1.3.1 Feed Junction Box Installation Sat 4/11/09 Tue 4/14/09 E 0 4 days 8 nos. 0.02 138.58
365 1.5.2.1.3.2 Disconnect Switch Instalation Tue 4/14/09 Wed 4/15/09 E 0 1 day 4 nos. 0.01 69.29
366 1.5.2.1.3.3 Interconnection cable, cableways installation Wed 4/15/09 Tue 5/12/09 E 0 30 days 600 mtr 1.9 11992.5
367 1.5.2.1.3.4 Cable termination Tue 5/12/09 Wed 5/13/09 E 0 2 days 15 nos 0.04 266.5
368 1.6 Construction - Potroom No. 1 (501-12B) Fri 3/6/09 Thu 8/13/09 0 178.05 days 11.32 71304.69
369 1.6.1 Pot 110 Fri 3/6/09 Wed 6/3/09 0 99.05 days 2.99 18863.48
370 4.7.1.1 SLI DELIVERABLES Fri 3/6/09 Fri 3/6/09 0 0 days 0 0
371 4.7.1.1.1 POT 110 Area Available for MPEI Construction Fri 3/6/09 Fri 3/6/09 0 0 days 0 0
372 1.6.1.2 Basement Floor Sat 4/25/09 Sat 5/30/09 0 39.22 days 1.12 7043.12
373 1.6.1.2.1 Installation - Electrical Sat 4/25/09 Sat 5/30/09 0 39.22 days 1.12 7043.12
374 1.6.1.2.1.1 Installation - Lighting System Thu 5/7/09 Mon 5/18/09 0 12.7 days 0.51 3228.7
375 1.6.1.2.1.1.1 PVC conduit and boxes Thu 5/7/09 Sat 5/9/09 E 0 1.96 days 66 mtr 0.03 212.67
376 1.6.1.2.1.1.2 Single Core Wires Sat 5/9/09 Sun 5/10/09 E 0 1.12 days 156 mtr 0.02 117.9
377 1.6.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 5/7/09 Sat 5/9/09 E 0 1.12 days 15 nos. 0.02 122.38
378 1.6.1.2.1.1.4 Lighting Feeder cables / wires Mon 5/11/09 Mon 5/18/09 E 0 8.84 days 1167 mtr 0.44 2775.76
379 1.6.1.2.1.2 Installation - Emergency Shutdown Sat 4/25/09 Sat 5/30/09 0 39.22 days 0.61 3814.41
380 1.6.1.2.1.2.1 PVC conduit and boxes Sat 4/25/09 Sat 4/25/09 I 0 0.76 days 12 mtr 0.01 63.96
381 1.6.1.2.1.2.2 Instrument cables Mon 5/18/09 Sat 5/30/09 I 0 12.21 days 1944 mtr 0.59 3731.8
382 1.6.1.2.1.2.3 Remote ASI Panel /Cabinet Sat 5/30/09 Sat 5/30/09 I 0 0.33 days 1 mtr 0 18.66
383 1.6.1.3 Operation Floor Sat 4/11/09 Wed 6/3/09 0 59.05 days 1.88 11820.37
384 1.6.1.3.1 Installation - Electrical Sat 4/11/09 Wed 6/3/09 0 59.05 days 1.82 11487.24
385 1.6.1.3.1.1 Installation - Lighting System Sat 4/18/09 Mon 5/4/09 0 17.64 days 0.37 2341.92
386 1.6.1.3.1.1.1 Rigid Steel Conduit Sat 4/18/09 Sun 4/19/09 E 0 1.4 days 52 mtr 0.05 315
387 1.6.1.3.1.1.2 Single Core Wires Sun 4/19/09 Thu 4/23/09 E 0 5.04 days 1410 mtr 0.15 915.03
388 1.6.1.3.1.1.3 Junction Box Thu 4/23/09 Thu 4/23/09 E 0 0.22 days 2 nos. 0.01 36.35
389 1.6.1.3.1.1.4 High Bay Lighting fixtures including supports and fixings Thu 4/23/09 Sun 4/26/09 E 0 1.64 days 12 nos. 0.05 303.76
390 1.6.1.3.1.1.5 Lighting Feeder cables / wires Sun 5/3/09 Mon 5/4/09 E 0 1.4 days 196 mtr 0.12 771.78
391 1.6.1.3.1.2 Installation - Cable Tray Sat 4/11/09 Mon 5/4/09 0 25.35 days 0.02 110.86
392 1.6.1.3.1.2.1 Cantilever supports installation Sat 4/11/09 Sun 4/12/09 E 0 0.07 days 9 nos. 0 7.65
393 1.6.1.3.1.2.2 Cable Tray installation Mon 5/4/09 Mon 5/4/09 E 0 0.45 days 55 mtr 0.02 103.22
394 1.6.1.3.1.3 Installation - Blower and Transformer Feeder Tue 4/28/09 Mon 5/4/09 0 5.85 days 0.42 2653.46
395 1.6.1.3.1.3.1 Blower Feeder, Transformer Feeder Tue 4/28/09 Mon 5/4/09 E 0 5.85 days 700 mtr 0.42 2653.46
396 1.6.1.3.1.4 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 2.51 days 0.06 381.71
397 1.6.1.3.1.4.1 Rigid Steel Conduit Thu 4/23/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35
398 1.6.1.3.1.4.2 Junction Box Thu 4/23/09 Sat 4/25/09 E 0 0.5 days 2 nos. 0 23.98
399 1.6.1.3.1.4.3 Single Core Wires Sat 4/25/09 Sat 4/25/09 E 0 0.36 days 50 mtr 0 27.82
400 1.6.1.3.1.4.4 Welding outlet / Socket Outlet Sat 4/25/09 Sat 4/25/09 E 0 0.29 days 2 nos. 0 27.05
401 1.6.1.3.1.4.5 Socket Feeder cables Sat 4/25/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5
402 1.6.1.3.1.5 Installation - Local Junction Box Thu 4/30/09 Wed 6/3/09 0 38.15 days 0.95 5999.29
403 1.6.1.3.1.5.1 Rigid Steel Conduit Thu 4/30/09 Thu 5/7/09 E 0 7.62 days 140 mtr 0.12 744.6
404 1.6.1.3.1.5.2 Junction Box Thu 5/7/09 Sun 5/10/09 E 0 3.81 days 28 nos. 0.06 372.3
405 1.6.1.3.1.5.3 Feeder cables Sun 5/10/09 Mon 5/18/09 E 0 8.72 days 1020 mtr 0.53 3358.01
406 1.6.1.3.1.5.4 Cable Termination Mon 5/18/09 Wed 6/3/09 E 0 18 days 88 nos. 0.24 1524.38
407 1.6.1.3.2 Air Compressed System - Piping Sat 4/25/09 Thu 4/30/09 0 6 days 0.05 333.13
408 1.6.1.3.2.1 2" Equal Tee Sat 4/25/09 Tue 4/28/09 P 0 4 days 11 nos 0.03 213.2
409 1.6.1.3.2.2 2" Plug Sun 4/26/09 Mon 4/27/09 P 0 1 day 9 nos 0.01 79.95
410 1.6.1.3.2.3 1/2" Ball valve Mon 4/27/09 Tue 4/28/09 P 0 1 day 2 nos 0 10.66
2/28
3/6
3/6
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 7 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
411 1.6.1.3.2.4 2" x 1" Reducer Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 10.66
412 1.6.1.3.2.5 1" x 1/2" Reducer Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 10.66
413 1.6.1.3.2.6 1/2" Nipple Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 8
414 1.6.2 Pot 132 Tue 3/31/09 Sat 6/20/09 0 89.73 days 3.95 24908.58
415 1.6.2.1 SLI DELIVERABLES Tue 3/31/09 Tue 3/31/09 0 0 days 0 0
416 1.6.2.1.1 POT 132 Area Available for MPEI Construction Tue 3/31/09 Tue 3/31/09 0 0 days 0 0
417 1.6.2.2 Basement Floor Sat 4/25/09 Wed 6/3/09 0 44.13 days 1.25 7885.02
418 1.6.2.2.1 Installation - Electrical Sat 4/25/09 Wed 6/3/09 0 44.13 days 1.25 7885.02
419 1.6.2.2.1.1 Installation - Lighting System Sat 5/9/09 Sat 5/23/09 0 14.96 days 0.65 4089.26
420 1.6.2.2.1.1.1 PVC conduit and boxes Sat 5/9/09 Mon 5/11/09 E 0 2.45 days 84 mtr 0.04 265.83
421 1.6.2.2.1.1.2 Single Core Wires Mon 5/11/09 Tue 5/12/09 E 0 1.4 days 198 mtr 0.02 147.37
422 1.6.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Sun 5/10/09 Mon 5/11/09 E 0 1.4 days 19 nos. 0.02 152.97
423 1.6.2.2.1.1.4 Lighting Feeder cables / wires Tue 5/12/09 Sat 5/23/09 E 0 11.22 days 1478 mtr 0.56 3523.08
424 1.6.2.2.1.2 Installation - Emergency Shutdown Sat 4/25/09 Wed 6/3/09 0 44.13 days 0.6 3795.76
425 1.6.2.2.1.2.1 PVC conduit and boxes Sat 4/25/09 Tue 4/28/09 I 0 4 days 12 mtr 0.01 63.96
426 1.6.2.2.1.2.2 Instrument cables Mon 5/25/09 Wed 6/3/09 I 0 11 days 1944 mtr 0.59 3731.8
427 1.6.2.3 Operation Floor Sun 4/12/09 Sat 6/20/09 0 76.98 days 2.7 17023.57
428 1.6.2.3.1 Installation - Electrical Sun 4/12/09 Sat 6/20/09 0 76.98 days 2.65 16690.44
429 1.6.2.3.1.1 Installation - Lighting System Sun 4/19/09 Mon 5/4/09 0 16.94 days 0.14 887.79
430 1.6.2.3.1.1.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 0.7 days 25 mtr 0.03 157.5
431 1.6.2.3.1.1.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.04 days 300 mtr 0.03 188.82
432 1.6.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 4/21/09 Tue 4/21/09 E 0 0.84 days 6 nos. 0.02 155.58
433 1.6.2.3.1.1.4 Lighting Feeder cables / wires Mon 5/4/09 Mon 5/4/09 E 0 0.7 days 100 mtr 0.06 385.89
434 1.6.2.3.1.2 Installation - Cable Tray Sun 4/12/09 Sun 5/10/09 0 31.68 days 0.02 110.86
435 1.6.2.3.1.2.1 Cantilever supports installation Sun 4/12/09 Sun 4/12/09 E 0 0.07 days 9 nos. 0 7.65
436 1.6.2.3.1.2.2 Cable Tray installation Sat 5/9/09 Sun 5/10/09 E 0 1 day 55 mtr 0.02 103.22
437 1.6.2.3.1.3 Installation - Crane Bus Bars Sun 5/3/09 Mon 5/11/09 0 9.19 days 1.06 6657.33
438 1.6.2.3.1.3.1 Crane Bus Bar Supports installation Sun 5/3/09 Sun 5/3/09 E 0 0.96 days 16 nos. 0.02 96.37
439 1.6.2.3.1.3.2 Feed Junction Box Installation Sun 5/3/09 Mon 5/4/09 E 0 0.33 days 1 nos. 0 17.59
440 1.6.2.3.1.3.3 Disconnect Switch Instalation Mon 5/4/09 Mon 5/4/09 E 0 0.5 days 1 nos. 0 17.32
441 1.6.2.3.1.3.4 Interconnection cable, cableways installation Mon 5/4/09 Tue 5/5/09 E 0 1 day 5 nos. 0.03 159.9
442 1.6.2.3.1.3.5 Crane Power Feeder Cable Tue 5/5/09 Mon 5/11/09 E 0 6.4 days 840 mtr 1.01 6366.15
443 1.6.2.3.1.4 Installation - Blower and Transformer Feeder Mon 5/4/09 Sat 5/9/09 0 5.85 days 0.42 2653.46
444 1.6.2.3.1.4.1 Blower Feeder, Transformer Feeder Mon 5/4/09 Sat 5/9/09 E 0 5.85 days 700 mtr 0.42 2653.46
445 1.6.2.3.1.5 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 2.51 days 0.06 381.71
446 1.6.2.3.1.5.1 Rigid Steel Conduit Thu 4/23/09 Sat 4/25/09 E 0 0.84 days 15 mtr 0.01 78.35
447 1.6.2.3.1.5.2 Single Core Wires Sat 4/25/09 Sat 4/25/09 E 0 0.36 days 50 mtr 0 27.82
448 1.6.2.3.1.5.3 Junction Box Sat 4/25/09 Sun 4/26/09 E 0 0.5 days 2 nos. 0 23.98
449 1.6.2.3.1.5.4 Welding outlet / Socket Outlet Sun 4/26/09 Sun 4/26/09 E 0 0.29 days 2 nos. 0 27.05
450 1.6.2.3.1.5.5 Socket Feeder cables Sun 4/26/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5
451 1.6.2.3.1.6 Installation - Local Junction Box Thu 5/7/09 Sat 6/20/09 0 48.53 days 0.95 5999.29
452 1.6.2.3.1.6.1 Rigid Steel Conduit Thu 5/7/09 Wed 5/13/09 E 0 7.62 days 140 mtr 0.12 744.6
453 1.6.2.3.1.6.2 Junction Box Wed 5/13/09 Sun 5/17/09 E 0 3.81 days 28 nos. 0.06 372.3
454 1.6.2.3.1.6.3 Feeder cables Sun 5/17/09 Mon 5/25/09 E 0 8.72 days 1020 mtr 0.53 3358.01
455 1.6.2.3.1.6.4 Cable Termination Wed 6/3/09 Sat 6/20/09 E 0 18 days 88 nos. 0.24 1524.38
456 1.6.2.3.2 Air Compressed System - Piping Tue 4/28/09 Mon 5/4/09 0 6 days 0.05 333.13
457 1.6.2.3.2.1 2" Equal Tee Tue 4/28/09 Sat 5/2/09 P 0 4 days 11 nos 0.03 213.2
458 1.6.2.3.2.2 2" Plug Thu 4/30/09 Thu 4/30/09 P 0 1 day 9 nos 0.01 79.95
459 1.6.2.3.2.3 1/2" Ball valve Thu 4/30/09 Sat 5/2/09 P 0 1 day 2 nos 0 10.66
460 1.6.2.3.2.4 2" x 1" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66
461 1.6.2.3.2.5 1" x 1/2" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66
462 1.6.2.3.2.6 1/2" Nipple Sun 5/3/09 Mon 5/4/09 P 0 1 day 2 nos 0 8
463 1.6.3 Pot 154 Wed 4/22/09 Mon 7/20/09 0 98.19 days 2.11 13302.51
464 1.6.3.1 SLI DELIVERABLES Wed 4/22/09 Wed 4/22/09 0 0 days 0 0
465 1.6.3.1.1 POT 154 Area Available for MPEI Construction Wed 4/22/09 Wed 4/22/09 0 0 days 0 0
466 1.6.3.2 Basement Floor Tue 4/28/09 Wed 6/10/09 0 47.67 days 1.16 7280.3
467 1.6.3.2.1 Installation - Electrical Tue 4/28/09 Wed 6/10/09 0 47.67 days 1.16 7280.3
468 1.6.3.2.1.1 Installation - Lighting System Mon 5/11/09 Sun 5/31/09 0 22.03 days 0.55 3465.89
469 1.6.3.2.1.1.1 PVC conduit and boxes Mon 5/11/09 Wed 5/13/09 E 0 2.03 days 69 mtr 0.03 220.26
470 1.6.3.2.1.1.2 Single Core Wires Wed 5/13/09 Thu 5/14/09 E 0 1.2 days 167 mtr 0.02 126.32
3/31
4/22
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 8 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
471 1.6.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Mon 5/11/09 Tue 5/12/09 E 0 1.19 days 16 nos. 0.02 130.03
472 1.6.3.2.1.1.4 Lighting Feeder cables / wires Sat 5/23/09 Sun 5/31/09 E 0 9.52 days 1244 mtr 0.47 2989.28
473 1.6.3.2.1.2 Installation - Emergency Shutdown Tue 4/28/09 Wed 6/10/09 0 47.67 days 0.61 3814.41
474 1.6.3.2.1.2.1 PVC conduit and boxes Tue 4/28/09 Wed 4/29/09 I 0 0.76 days 12 mtr 0.01 63.96
475 1.6.3.2.1.2.2 Instrument cables Sun 5/31/09 Wed 6/10/09 I 0 12.21 days 1944 mtr 0.59 3731.8
476 1.6.3.2.1.2.3 Remote ASI Panel /Cabinet Wed 6/10/09 Wed 6/10/09 I 0 0.33 days 1 mtr 0 18.66
477 1.6.3.3 Operation Floor Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.96 6022.21
478 1.6.3.3.1 Installation - Electrical Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.9 5689.08
479 1.6.3.3.1.1 Installation - Local Junction Box Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.9 5689.08
480 1.6.3.3.1.1.1 Rigid Steel Conduit Thu 4/30/09 Thu 5/7/09 E 0 7.08 days 130 mtr 0.11 691.83
481 1.6.3.3.1.1.2 Junction Box Thu 5/7/09 Mon 5/11/09 E 0 3.54 days 26 nos. 0.05 345.92
482 1.6.3.3.1.1.3 Feeder cables Mon 5/11/09 Mon 5/18/09 E 0 8.12 days 948 mtr 0.5 3126.95
483 1.6.3.3.1.1.4 Cable Termination Sat 7/4/09 Mon 7/20/09 E 0 18 days 88 nos. 0.24 1524.38
484 1.6.3.3.2 Air Compressed System - Piping Sat 5/2/09 Thu 5/7/09 0 7 days 0.05 333.13
485 1.6.3.3.2.1 2" Equal Tee Sat 5/2/09 Tue 5/5/09 P 0 4 days 11 nos 0.03 213.2
486 1.6.3.3.2.2 2" Plug Mon 5/4/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95
487 1.6.3.3.2.3 1/2" Ball valve Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66
488 1.6.3.3.2.4 2" x 1" Reducer Wed 5/6/09 Thu 5/7/09 P 0 1 day 2 nos 0 10.66
489 1.6.3.3.2.5 1" x 1/2" Reducer Wed 5/6/09 Thu 5/7/09 P 0 1 day 2 nos 0 10.66
490 1.6.3.3.2.6 1/2" Nipple Thu 5/7/09 Thu 5/7/09 P 0 1 day 2 nos 0 8
491 1.6.4 Pot 176 Thu 5/14/09 Thu 8/13/09 0 101.65 days 2.26 14230.11
492 1.6.4.1 SLI DELIVERABLES Thu 5/14/09 Thu 5/14/09 0 0 days 0 0
493 1.6.4.1.1 POT 176 Area Available for MPEI Construction Thu 5/14/09 Thu 5/14/09 0 0 days 0 0
494 1.6.4.2 Basement Floor Thu 5/14/09 Wed 6/17/09 0 37.36 days 1.28 8072.21
495 1.6.4.2.1 Installation - Electrical Thu 5/14/09 Wed 6/17/09 0 37.36 days 1.28 8072.21
496 1.6.4.2.1.1 Installation - Lighting System Mon 5/18/09 Tue 6/2/09 0 17.21 days 0.68 4276.45
497 1.6.4.2.1.1.1 PVC conduit and boxes Mon 5/18/09 Wed 5/20/09 E 0 2.59 days 88 mtr 0.04 281.02
498 1.6.4.2.1.1.2 Single Core Wires Wed 5/20/09 Thu 5/21/09 E 0 1.44 days 205 mtr 0.02 151.59
499 1.6.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Mon 5/18/09 Tue 5/19/09 E 0 1.47 days 20 nos. 0.03 160.62
500 1.6.4.2.1.1.4 Lighting Feeder cables / wires Sat 5/23/09 Tue 6/2/09 E 0 11.73 days 1544 mtr 0.58 3683.22
501 1.6.4.2.1.2 Installation - Emergency Shutdown Thu 5/14/09 Wed 6/17/09 0 37.36 days 0.6 3795.76
502 1.6.4.2.1.2.1 PVC conduit and boxes Thu 5/14/09 Thu 5/14/09 I 0 0.76 days 12 mtr 0.01 63.96
503 1.6.4.2.1.2.2 Instrument cables Sat 6/6/09 Wed 6/17/09 I 0 12.21 days 1944 mtr 0.59 3731.8
504 1.6.4.3 Operation Floor Thu 5/14/09 Thu 8/13/09 0 101.65 days 0.98 6157.91
505 1.6.4.3.1 Installation - Electrical Thu 5/14/09 Thu 8/13/09 0 101.65 days 0.92 5824.78
506 1.6.4.3.1.1 Installation - Lighting System Sat 5/23/09 Tue 5/26/09 0 3.28 days 0.14 887.79
507 1.6.4.3.1.1.1 Rigid Steel Conduit Sat 5/23/09 Sun 5/24/09 E 0 0.7 days 26 mtr 0.03 157.5
508 1.6.4.3.1.1.2 Single Core Wires Sun 5/24/09 Mon 5/25/09 E 0 1.04 days 300 mtr 0.03 188.82
509 1.6.4.3.1.1.3 High Bay Lighting fixtures including supports and fixings Mon 5/25/09 Mon 5/25/09 E 0 0.84 days 6 nos. 0.02 155.58
510 1.6.4.3.1.1.4 Lighting Feeder cables / wires Mon 5/25/09 Tue 5/26/09 E 0 0.7 days 98 mtr 0.06 385.89
511 1.6.4.3.1.2 Installation - Crane Bus Bars Thu 5/14/09 Thu 5/14/09 0 0.96 days 0.02 96.37
512 1.6.4.3.1.2.1 Crane Bus Bar Supports installation Thu 5/14/09 Thu 5/14/09 E 0 0.96 days 16 nos. 0.02 96.37
513 1.6.4.3.1.3 Installation - Socket / Welding Outlet Thu 5/14/09 Sun 5/17/09 0 2.99 days 0.06 381.71
514 1.6.4.3.1.3.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/14/09 E 0 1 day 15 mtr 0.01 78.35
515 1.6.4.3.1.3.2 Single Core Wires Thu 5/14/09 Sat 5/16/09 E 0 0.84 days 50 mtr 0 27.82
516 1.6.4.3.1.3.3 Junction Box Sat 5/16/09 Sat 5/16/09 E 0 0.36 days 2 nos. 0 23.98
517 1.6.4.3.1.3.4 Welding outlet / Socket Outlet Sat 5/16/09 Sun 5/17/09 E 0 0.5 days 2 nos. 0 27.05
518 1.6.4.3.1.3.5 Socket Feeder cables Sun 5/17/09 Sun 5/17/09 E 0 0.29 days 60 mtr 0.04 224.5
519 1.6.4.3.1.4 Installation - Local Junction Box Wed 6/10/09 Thu 8/13/09 0 71.65 days 0.71 4458.92
520 1.6.4.3.1.4.1 Rigid Steel Conduit Wed 6/10/09 Wed 6/17/09 E 0 7.62 days 140 mtr 0.12 744.6
521 1.6.4.3.1.4.2 Junction Box Wed 6/17/09 Sun 6/21/09 E 0 3.81 days 28 nos. 0.06 372.3
522 1.6.4.3.1.4.3 Feeder cables Sun 6/21/09 Wed 6/24/09 E 0 4.72 days 550 mtr 0.29 1817.64
523 1.6.4.3.1.4.4 Cable Termination Tue 7/28/09 Thu 8/13/09 E 0 18 days 88 nos. 0.24 1524.38
524 1.6.4.3.2 Air Compressed System - Piping Thu 5/14/09 Wed 5/20/09 0 7 days 0.05 333.13
525 1.6.4.3.2.1 2" Equal Tee Thu 5/14/09 Mon 5/18/09 P 0 4 days 11 nos 0.03 213.2
526 1.6.4.3.2.2 2" Plug Sat 5/16/09 Sun 5/17/09 P 0 1 day 9 nos 0.01 79.95
527 1.6.4.3.2.3 1/2" Ball valve Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66
528 1.6.4.3.2.4 2" x 1" Reducer Tue 5/19/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66
529 1.6.4.3.2.5 1" x 1/2" Reducer Tue 5/19/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66
5/14
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 9 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
530 1.6.4.3.2.6 1/2" Nipple Tue 5/19/09 Wed 5/20/09 P 0 1 day 2 nos 0 8
531 1.7 Construction - Potroom No. 2 (501-22B) Sat 2/28/09 Wed 7/8/09 0 145.65 days 11.3 71167.76
532 1.7.1 Pot 110 Sat 2/28/09 Mon 6/22/09 0 127.65 days 3.05 19187.68
533 4.5.2.1 SLI DELIVERABLES Sat 2/28/09 Sat 2/28/09 0 0 days 0 0
534 1.7.1.1.1 POT 110 Area Available for MPEI Construction Sat 2/28/09 Sat 2/28/09 0 0 days 0 0
535 1.7.1.2 Basement Floor Thu 4/30/09 Tue 5/26/09 0 27.67 days 1.12 7043.12
536 1.7.1.2.1 Installation - Electrical Thu 4/30/09 Tue 5/26/09 0 27.67 days 1.12 7043.12
537 1.7.1.2.1.1 Installation - Lighting System Thu 5/7/09 Sun 5/24/09 0 18.29 days 0.51 3228.7
538 1.7.1.2.1.1.1 PVC conduit and boxes Thu 5/7/09 Sat 5/9/09 E 0 1.96 days 66 mtr 0.03 212.67
539 1.7.1.2.1.1.2 Single Core Wires Sat 5/9/09 Sun 5/10/09 E 0 1.12 days 156 mtr 0.02 117.9
540 1.7.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 5/7/09 Sat 5/9/09 E 0 1.12 days 15 nos. 0.02 122.38
541 1.7.1.2.1.1.4 Lighting Feeder cables / wires Sat 5/16/09 Sun 5/24/09 E 0 8.84 days 1167 mtr 0.44 2775.76
542 1.7.1.2.1.2 Installation - Emergency Shutdown Thu 4/30/09 Tue 5/26/09 0 27.67 days 0.61 3814.41
543 1.7.1.2.1.2.1 PVC conduit and boxes Thu 4/30/09 Sat 5/2/09 I 0 0.76 days 12 mtr 0.01 63.96
544 1.7.1.2.1.2.2 Instrument cables Thu 5/14/09 Mon 5/25/09 I 0 12.21 days 1944 mtr 0.59 3731.8
545 1.7.1.2.1.2.3 Remote ASI Panel /Cabinet Mon 5/25/09 Tue 5/26/09 I 0 0.33 days 1 mtr 0 18.66
546 1.7.1.3 Operation Floor Mon 4/13/09 Mon 6/22/09 0 77.65 days 1.93 12144.56
547 1.7.1.3.1 Installation - Electrical Mon 4/13/09 Mon 6/22/09 0 77.65 days 1.88 11811.44
548 1.7.1.3.1.1 Installation - Lighting System Sun 4/19/09 Mon 4/27/09 0 9.7 days 0.37 2341.92
549 1.7.1.3.1.1.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 1.4 days 52 mtr 0.05 315
550 1.7.1.3.1.1.2 Single Core Wires Mon 4/20/09 Sat 4/25/09 E 0 5.04 days 1410 mtr 0.15 915.03
551 1.7.1.3.1.1.3 Junction Box Sat 4/25/09 Sat 4/25/09 E 0 0.22 days 2 nos. 0.01 36.35
552 1.7.1.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sat 4/25/09 Sun 4/26/09 E 0 1.64 days 12 nos. 0.05 303.76
553 1.7.1.3.1.1.5 Lighting Feeder cables / wires Sun 4/26/09 Mon 4/27/09 E 0 1.4 days 196 mtr 0.12 771.78
554 1.7.1.3.1.2 Installation - Cable Tray Mon 4/13/09 Sat 5/16/09 0 35.66 days 0.06 382.29
555 1.7.1.3.1.2.1 Cantilever supports installation Mon 4/13/09 Tue 4/14/09 E 0 0.35 days 32 nos. 0.01 38.24
556 1.7.1.3.1.2.2 Cable Tray installation Thu 5/14/09 Sat 5/16/09 E 0 1.5 days 189 mtr 0.05 344.05
557 1.7.1.3.1.3 Installation - Blower and Transformer Feeder Sat 5/9/09 Thu 5/14/09 0 5.85 days 0.42 2653.46
558 1.7.1.3.1.3.1 Blower Feeder, Transformer Feeder Sat 5/9/09 Thu 5/14/09 E 0 5.85 days 700 mtr 0.42 2653.46
559 1.7.1.3.1.4 Installation - Socket / Welding Outlet Sun 4/19/09 Wed 4/22/09 0 3.23 days 0.07 434.47
560 1.7.1.3.1.4.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 0.84 days 15 mtr 0.01 78.35
561 1.7.1.3.1.4.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.08 days 50 mtr 0.01 80.59
562 1.7.1.3.1.4.3 Junction Box Tue 4/21/09 Tue 4/21/09 E 0 0.5 days 2 nos. 0 23.98
563 1.7.1.3.1.4.4 Welding outlet / Socket Outlet Tue 4/21/09 Tue 4/21/09 E 0 0.29 days 2 nos. 0 27.05
564 1.7.1.3.1.4.5 Socket Feeder cables Tue 4/21/09 Wed 4/22/09 E 0 0.52 days 60 mtr 0.04 224.5
565 1.7.1.3.1.5 Installation - Local Junction Box Sat 4/25/09 Mon 6/22/09 0 64.91 days 0.95 5999.29
566 1.7.1.3.1.5.1 Rigid Steel Conduit Sat 4/25/09 Sat 5/2/09 E 0 7.62 days 140 mtr 0.12 744.6
567 1.7.1.3.1.5.2 Junction Box Sat 5/2/09 Tue 5/5/09 E 0 3.81 days 28 nos. 0.06 372.3
568 1.7.1.3.1.5.3 Feeder cables Sat 5/16/09 Sun 5/24/09 E 0 8.72 days 1020 mtr 0.53 3358.01
569 1.7.1.3.1.5.4 Cable Termination Sun 6/7/09 Mon 6/22/09 E 0 18 days 88 nos. 0.24 1524.38
570 1.7.1.3.2 Air Compressed System - Piping Tue 4/28/09 Sat 5/16/09 0 20 days 0.05 333.13
571 1.7.1.3.2.1 2" Equal Tee Tue 4/28/09 Sat 5/2/09 P 0 4 days 11 nos 0.03 213.2
572 1.7.1.3.2.2 2" Plug Thu 4/30/09 Thu 4/30/09 P 0 1 day 9 nos 0.01 79.95
573 1.7.1.3.2.3 1/2" Ball valve Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66
574 1.7.1.3.2.4 2" x 1" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66
575 1.7.1.3.2.5 1" x 1/2" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66
576 1.7.1.3.2.6 1/2" Nipple Sat 5/16/09 Sat 5/16/09 P 0 1 day 2 nos 0 8
577 1.7.2 Pot 132 Wed 3/18/09 Mon 6/22/09 0 106.98 days 3.87 24355.97
578 4.5.2.1 SLI DELIVERABLES Wed 3/18/09 Wed 3/18/09 0 0 days 0 0
579 1.7.2.1.1 POT 132 Area Available for MPEI Construction Wed 3/18/09 Wed 3/18/09 0 0 days 0 0
580 1.7.2.2 Basement Floor Sat 5/9/09 Mon 6/1/09 0 25.6 days 1.26 7938.4
581 1.7.2.2.1 Installation - Electrical Sat 5/9/09 Mon 6/1/09 0 25.6 days 1.26 7938.4
582 1.7.2.2.1.1 Installation - Lighting System Sat 5/9/09 Sun 5/31/09 0 23.88 days 0.66 4142.64
583 1.7.2.2.1.1.1 PVC conduit and boxes Sat 5/9/09 Mon 5/11/09 E 0 2.45 days 84 mtr 0.04 265.83
584 1.7.2.2.1.1.2 Single Core Wires Mon 5/11/09 Tue 5/12/09 E 0 1.4 days 198 mtr 0.02 147.37
585 1.7.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Sun 5/10/09 Mon 5/11/09 E 0 1.4 days 19 nos. 0.02 152.97
586 1.7.2.2.1.1.4 Lighting Feeder cables / wires Wed 5/20/09 Sun 5/31/09 E 0 11.39 days 1498 mtr 0.57 3576.46
587 1.7.2.2.1.2 Installation - Emergency Shutdown Tue 5/19/09 Mon 6/1/09 0 13.79 days 0.6 3795.76
588 1.7.2.2.1.2.1 PVC conduit and boxes Tue 5/19/09 Wed 5/20/09 I 0 0.76 days 12 mtr 0.01 63.96
2/28
2/28
3/18
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 10 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
589 1.7.2.2.1.2.2 Instrument cables Thu 5/21/09 Mon 6/1/09 I 0 12.21 days 1944 mtr 0.59 3731.8
590 1.7.2.3 Operation Floor Tue 4/14/09 Mon 6/22/09 0 77.3 days 2.61 16417.57
591 1.7.2.3.1 Installation - Electrical Tue 4/14/09 Mon 6/22/09 0 77.3 days 2.55 16084.45
592 1.7.2.3.1.1 Installation - Lighting System Mon 4/20/09 Mon 4/27/09 0 7.6 days 0.14 887.79
593 1.7.2.3.1.1.1 Rigid Steel Conduit Mon 4/20/09 Mon 4/20/09 E 0 0.7 days 25 mtr 0.03 157.5
594 1.7.2.3.1.1.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.04 days 300 mtr 0.03 188.82
595 1.7.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 4/21/09 Wed 4/22/09 E 0 0.84 days 6 nos. 0.02 155.58
596 1.7.2.3.1.1.4 Lighting Feeder cables / wires Sun 4/26/09 Mon 4/27/09 E 0 0.7 days 100 mtr 0.06 385.89
597 1.7.2.3.1.2 Installation - Cable Tray Tue 4/14/09 Wed 5/20/09 0 41.16 days 0.06 382.29
598 1.7.2.3.1.2.1 Cantilever supports installation Tue 4/14/09 Tue 4/14/09 E 0 0.35 days 32 nos. 0.01 38.24
599 1.7.2.3.1.2.2 Cable Tray installation Tue 5/19/09 Wed 5/20/09 E 0 1.5 days 189 mtr 0.05 344.05
600 1.7.2.3.1.3 Installation - Crane Bus Bars Thu 5/14/09 Sun 5/24/09 0 9.48 days 0.91 5727.14
601 1.7.2.3.1.3.1 Crane Bus Bar Supports installation Thu 5/14/09 Sat 5/16/09 E 0 0.96 days 16 nos. 0.02 96.37
602 1.7.2.3.1.3.2 Feed Junction Box Installation Sat 5/16/09 Sun 5/17/09 E 0 0.67 days 2 nos. 0.01 35.71
603 1.7.2.3.1.3.3 Disconnect Switch Instalation Sun 5/17/09 Sun 5/17/09 E 0 0.5 days 1 nos. 0 17.32
604 1.7.2.3.1.3.4 Interconnection cable, cableways installation Sun 5/17/09 Mon 5/18/09 E 0 1 day 5 nos. 0.03 159.9
605 1.7.2.3.1.3.5 Crane Power Feeder Cable Mon 5/18/09 Sat 5/23/09 E 0 5.36 days 700 mtr 0.85 5331.65
606 1.7.2.3.1.3.6 Cable Termination Sat 5/23/09 Sun 5/24/09 E 0 0.99 days 5 nos. 0.01 86.19
607 1.7.2.3.1.4 Installation - Blower and Transformer Feeder Thu 5/14/09 Tue 5/19/09 0 5.85 days 0.42 2653.46
608 1.7.2.3.1.4.1 Blower Feeder, Transformer Feeder Thu 5/14/09 Tue 5/19/09 E 0 5.85 days 700 mtr 0.42 2653.46
609 1.7.2.3.1.5 Installation - Socket / Welding Outlet Mon 4/20/09 Wed 4/22/09 0 3.23 days 0.07 434.47
610 1.7.2.3.1.5.1 Rigid Steel Conduit Mon 4/20/09 Tue 4/21/09 E 0 0.84 days 15 mtr 0.01 78.35
611 1.7.2.3.1.5.2 Single Core Wires Tue 4/21/09 Tue 4/21/09 E 0 1.08 days 50 mtr 0.01 80.59
612 1.7.2.3.1.5.3 Junction Box Tue 4/21/09 Wed 4/22/09 E 0 0.5 days 2 nos. 0 23.98
613 1.7.2.3.1.5.4 Welding outlet / Socket Outlet Wed 4/22/09 Wed 4/22/09 E 0 0.29 days 2 nos. 0 27.05
614 1.7.2.3.1.5.5 Socket Feeder cables Wed 4/22/09 Wed 4/22/09 E 0 0.52 days 60 mtr 0.04 224.5
615 1.7.2.3.1.6 Installation - Local Junction Box Sat 5/2/09 Mon 6/22/09 0 57.29 days 0.95 5999.29
616 1.7.2.3.1.6.1 Rigid Steel Conduit Sat 5/2/09 Sat 5/9/09 E 0 7.62 days 140 mtr 0.12 744.6
617 1.7.2.3.1.6.2 Junction Box Sat 5/9/09 Tue 5/12/09 E 0 3.81 days 28 nos. 0.06 372.3
618 1.7.2.3.1.6.3 Feeder cables Sun 5/24/09 Sun 5/31/09 E 0 8.72 days 1020 mtr 0.53 3358.01
619 1.7.2.3.1.6.4 Cable Termination Sun 6/7/09 Mon 6/22/09 E 0 18 days 88 nos. 0.24 1524.38
620 1.7.2.3.2 Air Compressed System - Piping Sat 5/2/09 Sun 5/17/09 0 17 days 0.05 333.13
621 1.7.2.3.2.1 2" Equal Tee Sat 5/2/09 Tue 5/5/09 P 0 4 days 11 nos 0.03 213.2
622 1.7.2.3.2.2 2" Plug Mon 5/4/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95
623 1.7.2.3.2.3 1/2" Ball valve Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66
624 1.7.2.3.2.4 2" x 1" Reducer Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66
625 1.7.2.3.2.5 1" x 1/2" Reducer Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66
626 1.7.2.3.2.6 1/2" Nipple Sat 5/16/09 Sun 5/17/09 P 0 1 day 2 nos 0 8
627 1.7.3 Pot 154 Sun 4/5/09 Tue 6/30/09 0 95.61 days 2.15 13530.95
628 4.5.2.1 SLI DELIVERABLES Sun 4/5/09 Sun 4/5/09 0 0 days 0 0
629 1.7.3.1.1 POT 154 Area Available for MPEI Construction Sun 4/5/09 Sun 4/5/09 0 0 days 0 0
630 1.7.3.2 Basement Floor Mon 5/11/09 Mon 6/8/09 0 30.69 days 1.18 7412.38
631 1.7.3.2.1 Installation - Electrical Mon 5/11/09 Mon 6/8/09 0 30.69 days 1.18 7412.38
632 1.7.3.2.1.1 Installation - Lighting System Mon 5/11/09 Thu 5/21/09 0 11.21 days 0.57 3597.96
633 1.7.3.2.1.1.1 PVC conduit and boxes Mon 5/11/09 Wed 5/13/09 E 0 2.03 days 69 mtr 0.03 220.26
634 1.7.3.2.1.1.2 Single Core Wires Wed 5/13/09 Thu 5/14/09 E 0 1.2 days 167 mtr 0.02 126.32
635 1.7.3.2.1.1.3 Lighting Feeder cables / wires Wed 5/13/09 Thu 5/14/09 E 0 0.17 days 16 mtr 0.01 53.38
636 1.7.3.2.1.1.4 Crane feeder cables Thu 5/14/09 Thu 5/21/09 E 0 8 days 1244 mtr 0.51 3198
637 1.7.3.2.1.2 Installation - Emergency Shutdown Wed 5/20/09 Mon 6/8/09 0 20.57 days 0.61 3814.41
638 1.7.3.2.1.2.1 PVC conduit and boxes Wed 5/20/09 Wed 5/20/09 I 0 0.76 days 12 mtr 0.01 63.96
639 1.7.3.2.1.2.2 Instrument cables Wed 5/27/09 Mon 6/8/09 I 0 12.21 days 1944 mtr 0.59 3731.8
640 1.7.3.2.1.2.3 Remote ASI Panel /Cabinet Mon 6/8/09 Mon 6/8/09 I 0 0.33 days 1 mtr 0 18.66
641 1.7.3.3 Operation Floor Wed 4/22/09 Tue 6/30/09 0 76.23 days 0.97 6118.57
642 1.7.3.3.1 Installation - Electrical Sat 5/9/09 Tue 6/30/09 0 57.67 days 0.92 5785.45
643 1.7.3.3.1.1 Installation - Crane Bus Bars Sat 5/16/09 Sun 5/17/09 0 0.96 days 0.02 96.37
644 1.7.3.3.1.1.1 Crane Bus Bar Supports installation Sat 5/16/09 Sun 5/17/09 E 0 0.96 days 16 nos. 0.02 96.37
645 1.7.3.3.1.2 Installation - Local Junction Box Sat 5/9/09 Tue 6/30/09 0 57.67 days 0.9 5689.08
646 1.7.3.3.1.2.1 Rigid Steel Conduit Sat 5/9/09 Thu 5/14/09 E 0 7.08 days 130 mtr 0.11 691.83
647 1.7.3.3.1.2.2 Junction Box Thu 5/14/09 Mon 5/18/09 E 0 3.54 days 26 nos. 0.05 345.92
4/5
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 11 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
648 1.7.3.3.1.2.3 Feeder cables Sun 5/31/09 Mon 6/8/09 E 0 8.12 days 948 mtr 0.5 3126.95
649 1.7.3.3.1.2.4 Cable Termination Sun 6/14/09 Tue 6/30/09 E 0 18 days 88 nos. 0.24 1524.38
650 1.7.3.3.2 Air Compressed System - Piping Wed 4/22/09 Mon 5/18/09 0 28.9 days 0.05 333.13
651 1.7.3.3.2.1 2" Equal Tee Wed 4/22/09 Sun 4/26/09 P 0 4 days 11 nos 0.03 213.2
652 1.7.3.3.2.2 2" Plug Thu 4/23/09 Sat 4/25/09 P 0 1 day 9 nos 0.01 79.95
653 1.7.3.3.2.3 1/2" Ball valve Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66
654 1.7.3.3.2.4 2" x 1" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66
655 1.7.3.3.2.5 1" x 1/2" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66
656 1.7.3.3.2.6 1/2" Nipple Sun 5/17/09 Mon 5/18/09 P 0 1 day 2 nos 0 8
657 1.7.4 Pot 176 Thu 4/23/09 Wed 7/8/09 0 84.94 days 2.24 14093.16
658 1.7.4.1 SLI DELIVERABLES Thu 4/23/09 Thu 4/23/09 0 0 days 0 0
659 1.7.4.1.1 POT 176 Area Available for MPEI Construction Thu 4/23/09 Thu 4/23/09 0 0 days 0 0
660 1.7.4.2 Basement Floor Wed 5/13/09 Sun 6/14/09 0 35.54 days 1.29 8125.59
661 1.7.4.2.1 Installation - Electrical Wed 5/13/09 Sun 6/14/09 0 35.54 days 1.29 8125.59
662 1.7.4.2.1.1 Installation - Lighting System Wed 5/13/09 Thu 5/28/09 0 17.91 days 0.69 4329.83
663 1.7.4.2.1.1.1 PVC conduit and boxes Wed 5/13/09 Sat 5/16/09 E 0 2.59 days 88 mtr 0.04 281.02
664 1.7.4.2.1.1.2 Single Core Wires Sat 5/16/09 Sun 5/17/09 E 0 1.44 days 205 mtr 0.02 151.59
665 1.7.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Wed 5/13/09 Sat 5/16/09 E 0 1.47 days 20 nos. 0.03 160.62
666 1.7.4.2.1.1.4 Lighting Feeder cables / wires Mon 5/18/09 Thu 5/28/09 E 0 11.9 days 1554 mtr 0.59 3736.6
667 1.7.4.2.1.2 Installation - Emergency Shutdown Wed 5/20/09 Sun 6/14/09 0 26.69 days 0.6 3795.76
668 1.7.4.2.1.2.1 PVC conduit and boxes Wed 5/20/09 Thu 5/21/09 I 0 0.76 days 12 mtr 0.01 63.96
669 1.7.4.2.1.2.2 Instrument cables Wed 6/3/09 Sun 6/14/09 I 0 12.21 days 1944 mtr 0.59 3731.8
670 1.7.4.3 Operation Floor Thu 4/23/09 Wed 7/8/09 0 84.94 days 0.95 5967.57
671 1.7.4.3.1 Installation - Electrical Thu 4/23/09 Wed 7/8/09 0 84.94 days 0.89 5634.45
672 1.7.4.3.1.1 Installation - Lighting System Thu 4/23/09 Mon 4/27/09 0 4.59 days 0.1 644.69
673 1.7.4.3.1.1.1 Rigid Steel Conduit Thu 4/23/09 Sat 4/25/09 E 0 2 days 26 mtr 0.03 173.22
674 1.7.4.3.1.1.2 Single Core Wires Sat 4/25/09 Sun 4/26/09 E 0 1.04 days 300 mtr 0.03 188.82
675 1.7.4.3.1.1.3 Junction Box Sun 4/26/09 Sun 4/26/09 E 0 0.64 days 6 nos. 0.02 105.75
676 1.7.4.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 4/26/09 Mon 4/27/09 E 0 0.84 days 6 nos. 0.02 155.58
677 1.7.4.3.1.1.5 Lighting Feeder cables / wires Mon 4/27/09 Mon 4/27/09 E 0 0.07 days 8 mtr 0 21.32
678 1.7.4.3.1.2 Installation - Crane Bus Bars Sun 5/17/09 Mon 5/18/09 0 0.96 days 0.02 96.37
679 1.7.4.3.1.2.1 Crane Bus Bar Supports installation Sun 5/17/09 Mon 5/18/09 E 0 0.96 days 16 nos. 0.02 96.37
680 1.7.4.3.1.3 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 3.23 days 0.07 434.47
681 1.7.4.3.1.3.1 Rigid Steel Conduit Thu 4/23/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35
682 1.7.4.3.1.3.2 Single Core Wires Thu 4/23/09 Sat 4/25/09 E 0 1.08 days 50 mtr 0.01 80.59
683 1.7.4.3.1.3.3 Junction Box Sat 4/25/09 Sun 4/26/09 E 0 0.5 days 2 nos. 0 23.98
684 1.7.4.3.1.3.4 Welding outlet / Socket Outlet Sun 4/26/09 Sun 4/26/09 E 0 0.29 days 2 nos. 0 27.05
685 1.7.4.3.1.3.5 Socket Feeder cables Sun 4/26/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5
686 1.7.4.3.1.4 Installation - Local Junction Box Thu 5/14/09 Wed 7/8/09 0 60.59 days 0.71 4458.92
687 1.7.4.3.1.4.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/21/09 E 0 7.62 days 140 mtr 0.12 744.6
688 1.7.4.3.1.4.2 Junction Box Thu 5/21/09 Mon 5/25/09 E 0 3.81 days 28 nos. 0.06 372.3
689 1.7.4.3.1.4.3 Feeder cables Mon 6/8/09 Thu 6/11/09 E 0 4.72 days 550 mtr 0.29 1817.64
690 1.7.4.3.1.4.4 Cable Termination Mon 6/22/09 Wed 7/8/09 E 0 18 days 88 nos. 0.24 1524.38
691 1.7.4.3.2 Air Compressed System - Piping Sun 4/26/09 Tue 5/19/09 0 25.9 days 0.05 333.13
692 1.7.4.3.2.1 2" Equal Tee Sun 4/26/09 Wed 4/29/09 P 0 4 days 11 nos 0.03 213.2
693 1.7.4.3.2.2 2" Plug Mon 4/27/09 Tue 4/28/09 P 0 1 day 9 nos 0.01 79.95
694 1.7.4.3.2.3 1/2" Ball valve Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66
695 1.7.4.3.2.4 2" x 1" Reducer Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66
696 1.7.4.3.2.5 1" x 1/2" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66
697 1.7.4.3.2.6 1/2" Nipple Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 8
698 1.8 Construction - Crane Workshop 512-1 Thu 1/15/09 Sat 4/25/09 0.01 109.95 days 1.53 9660.25
699 1.8.1 SLI DELIVERABLES Thu 1/15/09 Thu 1/15/09 0 0 days 0 0
700 1.8.1.1 Crane Work shop Building Avaialbale for MPEI
Construction
Thu 1/15/09 Thu 1/15/09 0 0 days 0 0
701 1.8.2 Installation - Electrical Sat 2/7/09 Sat 4/25/09 0.01 84.95 days 1.53 9660.25
702 1.8.2.1 Installation - Crane Bus Bars Sat 2/7/09 Sat 4/25/09 0.01 84.95 days 1.53 9660.25
703 1.8.2.1.1 Crane Bus Bar Supports installation Sat 2/7/09 Sat 2/7/09 E 0.01 0.59 days 14 nos. 0.01 83.09
704 1.8.2.1.2 Feed Junction Box Installation Tue 4/14/09 Tue 4/14/09 E 0 0.28 days 1 nos. 0 16.98
705 1.8.2.1.3 Disconnect Switch Instalation Tue 4/14/09 Wed 4/15/09 E 0 0.88 days 4 nos. 0.01 68.6
706 1.8.2.1.4 Crane Power Feeder Cable Wed 4/15/09 Wed 4/22/09 E 0 8.1 days 1110 mtr 1.46 9192.25
4/23
1/15
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 12 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
707 1.8.2.1.5 Cable Termination Wed 4/22/09 Sat 4/25/09 E 0 2.4 days 23 nos. 0.05 299.33
708 1.9 Construction - Central Passageway 503-32 Sat 3/7/09 Mon 5/11/09 0 73.11 days 0.72 4515.6
709 4.5.2.1 SLI DELIVERABLES Sat 3/7/09 Sat 3/7/09 0 0 days 0 0
710 1.9.1.1 Central Passageway Available for MPEI Construction Sat 3/7/09 Sat 3/7/09 0 0 days 0 0
711 1.9.2 Operation Floor Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.72 4515.6
712 1.9.2.1 Installation - Electrical Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.72 4515.6
713 1.9.2.1.1 Installation - Lighting System Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.14 851.68
714 1.9.2.1.1.1 Rigid Steel Conduit Mon 4/13/09 Thu 4/16/09 E 0 4.26 days 50 mtr 0.05 298.96
715 1.9.2.1.1.2 Single Core Wires Thu 4/16/09 Sun 4/19/09 E 0 2 days 153 mtr 0.02 99.67
716 1.9.2.1.1.3 Lighting Feeder cables / wires Sun 5/10/09 Mon 5/11/09 E 0 1 day 110 mtr 0.07 453.05
717 1.9.2.1.2 Installation - Cable Tray Wed 4/29/09 Sun 5/10/09 0 12.11 days 0.17 1060.4
718 1.9.2.1.2.1 Cantilever supports installation Wed 4/29/09 Mon 5/4/09 E 0 5.19 days 140 nos. 0.05 304.29
719 1.9.2.1.2.2 Cable Tray installation Mon 5/4/09 Sun 5/10/09 E 0 6.92 days 420 mtr 0.12 756.11
720 1.9.2.1.3 Installation - Crane Bus Bars Tue 4/14/09 Tue 5/5/09 0 23.78 days 0.41 2603.52
721 1.9.2.1.3.1 Feed Junction Box Installation Tue 4/14/09 Wed 4/15/09 E 0 0.72 days 4 nos. 0.01 69.08
722 1.9.2.1.3.2 Disconnect Switch Instalation Wed 4/15/09 Thu 4/16/09 E 0 1.78 days 8 nos. 0.02 139.94
723 1.9.2.1.3.3 Interconnection cable, cableways installation Thu 4/16/09 Sun 4/19/09 E 0 2.97 days 15 nos. 0.06 395.75
724 1.9.2.1.3.4 Crane feeder cables Sat 5/2/09 Tue 5/5/09 E 0 5 days 800 0.32 1998.75
725 1.10 Construction - Potroom No. 1 (501-12C) Thu 5/21/09 Thu 9/24/09 0 139.9 days 12.01 75624.57
726 1.10.1 Pot 198 Thu 5/21/09 Sun 8/30/09 0 111.9 days 2.75 17348.11
727 4.5.2.1 SLI DELIVERABLES Thu 6/4/09 Thu 6/4/09 0 0 days 0 0
728 1.10.1.1.1 POT 198 Area Available for MPEI Construction Thu 6/4/09 Thu 6/4/09 0 0 days 0 0
729 1.10.1.2 Basement Floor Tue 6/2/09 Tue 6/23/09 0 23.06 days 1.15 7244.8
730 1.10.1.2.1 Installation - Electrical Tue 6/2/09 Tue 6/23/09 0 23.06 days 1.15 7244.8
731 1.10.1.2.1.1 Installation - Lighting System Tue 6/2/09 Thu 6/11/09 0 9.52 days 0.55 3449.04
732 1.10.1.2.1.1.1 PVC conduit and boxes Thu 6/4/09 Sat 6/6/09 E 0 2.03 days 68 mtr 0.03 220.26
733 1.10.1.2.1.1.2 Single Core Wires Sat 6/6/09 Sun 6/7/09 E 0 1.04 days 148 mtr 0.02 109.48
734 1.10.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 6/4/09 Sat 6/6/09 E 0 1.19 days 16 nos. 0.02 130.03
735 1.10.1.2.1.1.4 Lighting Feeder cables / wires Tue 6/2/09 Thu 6/11/09 E 0 9.52 days 1244 mtr 0.47 2989.28
736 1.10.1.2.1.2 Installation - Emergency Shutdown Thu 6/4/09 Tue 6/23/09 0 21.32 days 0.6 3795.76
737 1.10.1.2.1.2.1 PVC conduit and boxes Thu 6/4/09 Thu 6/4/09 I 0 0.76 days 12 mtr 0.01 63.96
738 1.10.1.2.1.2.2 Instrument cables Sat 6/13/09 Tue 6/23/09 I 0 12.21 days 1944 mtr 0.59 3731.8
739 1.10.1.3 Delivery of sub station 305-52 from SNCLavalin to Astaldi Thu 5/21/09 Thu 5/21/09 0 0 days 0 0
740 1.10.1.4 Operation Floor Thu 6/4/09 Sun 8/30/09 0 96.4 days 1.6 10103.31
741 1.10.1.4.1 Installation - Electrical Thu 6/4/09 Sun 8/30/09 0 96.4 days 1.55 9770.18
742 1.10.1.4.1.1 Installation - Crane Bus Bars Thu 6/4/09 Mon 6/15/09 0 12.27 days 0.53 3336.42
743 1.10.1.4.1.1.1 Crane Bus Bar Supports installation Thu 6/4/09 Thu 6/4/09 E 0 0.96 days 16 nos. 0.02 96.37
744 1.10.1.4.1.1.2 Feed Junction Box Installation Thu 6/4/09 Sun 6/7/09 E 0 1.67 days 5 nos. 0.01 89.01
745 1.10.1.4.1.1.3 Disconnect Switch Instalation Sun 6/7/09 Tue 6/9/09 E 0 3 days 6 nos. 0.02 103.94
746 1.10.1.4.1.1.4 Interconnection cable, cableways installation Tue 6/9/09 Wed 6/10/09 E 0 1 day 5 nos. 0.03 159.9
747 1.10.1.4.1.1.5 Crane Power Feeder Cable Wed 6/10/09 Sat 6/13/09 E 0 2.64 days 350 mtr 0.42 2626.04
748 1.10.1.4.1.1.6 Cable Termination Sat 6/13/09 Mon 6/15/09 E 0 3 days 15 nos. 0.04 261.17
749 1.10.1.4.1.2 Installation - Socket / Welding Outlet Thu 6/4/09 Sun 6/7/09 0 3.23 days 0.07 434.47
750 1.10.1.4.1.2.1 Rigid Steel Conduit Thu 6/4/09 Thu 6/4/09 E 0 0.84 days 15 mtr 0.01 78.35
751 1.10.1.4.1.2.2 Single Core Wires Thu 6/4/09 Sat 6/6/09 E 0 1.08 days 50 mtr 0.01 80.59
752 1.10.1.4.1.2.3 Junction Box Sat 6/6/09 Sun 6/7/09 E 0 0.5 days 2 nos. 0 23.98
753 1.10.1.4.1.2.4 Welding outlet / Socket Outlet Sun 6/7/09 Sun 6/7/09 E 0 0.29 days 2 nos. 0 27.05
754 1.10.1.4.1.2.5 Socket Feeder cables Sun 6/7/09 Sun 6/7/09 E 0 0.52 days 60 mtr 0.04 224.5
755 1.10.1.4.1.3 Installation - Local Junction Box Wed 6/17/09 Sun 8/30/09 0 82.03 days 0.95 5999.29
756 1.10.1.4.1.3.1 Rigid Steel Conduit Wed 6/17/09 Wed 6/24/09 E 0 7.62 days 140 mtr 0.12 744.6
757 1.10.1.4.1.3.2 Junction Box Wed 6/24/09 Sun 6/28/09 E 0 3.81 days 28 nos. 0.06 372.3
758 1.10.1.4.1.3.3 Feeder cables Sun 6/28/09 Sun 7/5/09 E 0 8.72 days 1020 mtr 0.53 3358.01
759 1.10.1.4.1.3.4 Cable Termination Thu 8/13/09 Sun 8/30/09 E 0 18 days 88 nos. 0.24 1524.38
760 1.10.1.4.2 Air Compressed System - Piping Thu 6/4/09 Tue 6/9/09 0 6 days 0.05 333.13
761 1.10.1.4.2.1 2" Equal Tee Thu 6/4/09 Mon 6/8/09 P 0 4 days 11 nos 0.03 213.2
762 1.10.1.4.2.2 2" Plug Sat 6/6/09 Sun 6/7/09 P 0 1 day 9 nos 0.01 79.95
763 1.10.1.4.2.3 1/2" Ball valve Sun 6/7/09 Mon 6/8/09 P 0 1 day 2 nos 0 10.66
764 1.10.1.4.2.4 2" x 1" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66
765 1.10.1.4.2.5 1" x 1/2" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66
3/7
6/4
5/21
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 13 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
766 1.10.1.4.2.6 1/2" Nipple Tue 6/9/09 Tue 6/9/09 P 0 1 day 2 nos 0 8
767 1.10.2 Pot 220 Wed 6/24/09 Tue 9/8/09 0 84.42 days 2.39 15074.31
768 4.5.2.1 SLI DELIVERABLES Thu 6/25/09 Thu 6/25/09 0 0 days 0 0
769 1.10.2.1.1 POT 220 Area Available for MPEI Construction Thu 6/25/09 Thu 6/25/09 0 0 days 0 0
770 1.10.2.2 Basement Floor Wed 6/24/09 Tue 7/7/09 0 14.57 days 1.22 7687.83
771 1.10.2.2.1 Installation - Electrical Wed 6/24/09 Tue 7/7/09 0 14.57 days 1.22 7687.83
772 1.10.2.2.1.1 Installation - Lighting System Wed 6/24/09 Sat 7/4/09 0 10.71 days 0.61 3873.42
773 1.10.2.2.1.1.1 PVC conduit and boxes Thu 6/25/09 Sat 6/27/09 E 0 2.24 days 76 mtr 0.04 243.05
774 1.10.2.2.1.1.2 Single Core Wires Sat 6/27/09 Sun 6/28/09 E 0 1.16 days 166 mtr 0.02 122.11
775 1.10.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 6/25/09 Sat 6/27/09 E 0 1.33 days 18 nos. 0.02 145.32
776 1.10.2.2.1.1.4 Lighting Feeder cables / wires Wed 6/24/09 Sat 7/4/09 E 0 10.71 days 1400 mtr 0.53 3362.94
777 1.10.2.2.1.2 Installation - Emergency Shutdown Thu 6/25/09 Tue 7/7/09 0 13.3 days 0.61 3814.41
778 1.10.2.2.1.2.1 PVC conduit and boxes Thu 6/25/09 Thu 6/25/09 I 0 0.76 days 12 mtr 0.01 63.96
779 1.10.2.2.1.2.2 Instrument cables Thu 6/25/09 Tue 7/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8
780 1.10.2.2.1.2.3 Remote ASI Panel /Cabinet Tue 7/7/09 Tue 7/7/09 I 0 0.33 days 1 mtr 0 18.66
781 1.10.2.3 Operation Floor Thu 6/25/09 Tue 9/8/09 0 83.15 days 1.17 7386.47
782 1.10.2.3.1 Installation - Electrical Thu 6/25/09 Tue 9/8/09 0 83.15 days 1.12 7053.35
783 1.10.2.3.1.1 Installation - Lighting System Thu 6/25/09 Sun 6/28/09 0 3.58 days 0.08 523.22
784 1.10.2.3.1.1.1 Rigid Steel Conduit Thu 6/25/09 Thu 6/25/09 E 0 0.7 days 26 mtr 0.03 157.5
785 1.10.2.3.1.1.2 Single Core Wires Thu 6/25/09 Sat 6/27/09 E 0 1.04 days 300 mtr 0.03 188.82
786 1.10.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Sat 6/27/09 Sun 6/28/09 E 0 0.84 days 6 nos. 0.02 155.58
787 1.10.2.3.1.1.4 Lighting Feeder cables / wires Sun 6/28/09 Sun 6/28/09 E 0 1 day 8 mtr 0 21.32
788 1.10.2.3.1.2 Installation - Crane Bus Bars Thu 6/25/09 Thu 6/25/09 0 0.96 days 0.02 96.37
789 1.10.2.3.1.2.1 Crane Bus Bar Supports installation Thu 6/25/09 Thu 6/25/09 E 0 0.96 days 16 nos. 0.02 96.37
790 1.10.2.3.1.3 Installation - Socket / Welding Outlet Thu 6/25/09 Sun 6/28/09 0 3.23 days 0.07 434.47
791 1.10.2.3.1.3.1 Rigid Steel Conduit Thu 6/25/09 Thu 6/25/09 E 0 0.84 days 15 mtr 0.01 78.35
792 1.10.2.3.1.3.2 Single Core Wires Thu 6/25/09 Sat 6/27/09 E 0 1.08 days 50 mtr 0.01 80.59
793 1.10.2.3.1.3.3 Junction Box Sat 6/27/09 Sun 6/28/09 E 0 0.5 days 2 nos. 0 23.98
794 1.10.2.3.1.3.4 Welding outlet / Socket Outlet Sun 6/28/09 Sun 6/28/09 E 0 0.29 days 2 nos. 0 27.05
795 1.10.2.3.1.3.5 Socket Feeder cables Sun 6/28/09 Sun 6/28/09 E 0 0.52 days 60 mtr 0.04 224.5
796 1.10.2.3.1.4 Installation - Local Junction Box Thu 6/25/09 Tue 9/8/09 0 83.15 days 0.95 5999.29
797 1.10.2.3.1.4.1 Rigid Steel Conduit Thu 6/25/09 Thu 7/2/09 E 0 7.62 days 140 mtr 0.12 744.6
798 1.10.2.3.1.4.2 Junction Box Thu 7/2/09 Sun 7/5/09 E 0 3.81 days 28 nos. 0.06 372.3
799 1.10.2.3.1.4.3 Feeder cables Sun 7/5/09 Mon 7/13/09 E 0 8.72 days 1020 mtr 0.53 3358.01
800 1.10.2.3.1.4.4 Cable Termination Sun 8/23/09 Tue 9/8/09 E 0 18 days 88 nos. 0.24 1524.38
801 1.10.2.3.2 Air Compressed System - Piping Thu 6/25/09 Tue 6/30/09 0 6 days 0.05 333.13
802 1.10.2.3.2.1 2" Equal Tee Thu 6/25/09 Mon 6/29/09 P 0 4 days 11 nos 0.03 213.2
803 1.10.2.3.2.2 2" Plug Sat 6/27/09 Sun 6/28/09 P 0 1 day 9 nos 0.01 79.95
804 1.10.2.3.2.3 1/2" Ball valve Sun 6/28/09 Mon 6/29/09 P 0 1 day 2 nos 0 10.66
805 1.10.2.3.2.4 2" x 1" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66
806 1.10.2.3.2.5 1" x 1/2" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66
807 1.10.2.3.2.6 1/2" Nipple Tue 6/30/09 Tue 6/30/09 P 0 1 day 2 nos 0 8
808 1.10.3 Pot 242 Thu 7/16/09 Thu 9/24/09 0 77.9 days 3.65 22993.46
809 1.10.3.1 SLI DELIVERABLES Thu 7/16/09 Thu 7/16/09 0 0 days 0 0
810 1.10.3.1.1 POT 242 Area Available for MPEI Construction Thu 7/16/09 Thu 7/16/09 0 0 days 0 0
811 1.10.3.2 Basement Floor Thu 7/16/09 Thu 7/30/09 0 15.82 days 1.15 7244.8
812 1.10.3.2.1 Installation - Electrical Thu 7/16/09 Thu 7/30/09 0 15.82 days 1.15 7244.8
813 1.10.3.2.1.1 Installation - Lighting System Thu 7/16/09 Thu 7/30/09 0 15.82 days 0.55 3449.04
814 1.10.3.2.1.1.1 PVC conduit and boxes Thu 7/16/09 Sat 7/18/09 E 0 2.03 days 68 mtr 0.03 220.26
815 1.10.3.2.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.04 days 148 mtr 0.02 109.48
816 1.10.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 7/16/09 Sat 7/18/09 E 0 1.19 days 16 nos. 0.02 130.03
817 1.10.3.2.1.1.4 Lighting Feeder cables / wires Wed 7/22/09 Thu 7/30/09 E 0 9.52 days 1244 mtr 0.47 2989.28
818 1.10.3.2.1.2 Installation - Emergency Shutdown Thu 7/16/09 Tue 7/28/09 0 12.97 days 0.6 3795.76
819 1.10.3.2.1.2.1 PVC conduit and boxes Thu 7/16/09 Thu 7/16/09 I 0 0.76 days 12 mtr 0.01 63.96
820 1.10.3.2.1.2.2 Instrument cables Thu 7/16/09 Tue 7/28/09 I 0 12.21 days 1944 mtr 0.59 3731.8
821 1.10.3.3 Operation Floor Thu 7/16/09 Thu 9/24/09 0 77.9 days 2.5 15748.66
822 1.10.3.3.1 Installation - Electrical Thu 7/16/09 Thu 9/24/09 0 77.9 days 2.45 15415.53
823 1.10.3.3.1.1 Installation - Lighting System Thu 7/16/09 Wed 7/22/09 0 6.48 days 0.26 1632.66
824 1.10.3.3.1.1.1 Rigid Steel Conduit Thu 7/16/09 Sat 7/18/09 E 0 1.4 days 52 mtr 0.05 315
6/25
7/16
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 14 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
825 1.10.3.3.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.04 days 300 mtr 0.03 188.82
826 1.10.3.3.1.1.3 Junction Box Sun 7/19/09 Sun 7/19/09 E 0 1 day 2 nos. 0.01 53.3
827 1.10.3.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 7/19/09 Tue 7/21/09 E 0 1.64 days 12 nos. 0.05 303.76
828 1.10.3.3.1.1.5 Lighting Feeder cables / wires Tue 7/21/09 Wed 7/22/09 E 0 1.4 days 196 mtr 0.12 771.78
829 1.10.3.3.1.2 Installation - Cable Tray Thu 7/16/09 Wed 7/22/09 0 6.3 days 0.02 110.86
830 1.10.3.3.1.2.1 Cantilever supports installation Thu 7/16/09 Thu 7/16/09 E 0 0.07 days 9 nos. 0 7.65
831 1.10.3.3.1.2.2 Cable Tray installation Tue 7/21/09 Wed 7/22/09 E 0 0.45 days 55 mtr 0.02 103.22
832 1.10.3.3.1.3 Installation - Blower and Transformer Feeder Thu 7/16/09 Tue 7/21/09 0 5.85 days 0.42 2653.46
833 1.10.3.3.1.3.1 Blower Feeder, Transformer Feeder Thu 7/16/09 Tue 7/21/09 E 0 5.85 days 700 mtr 0.42 2653.46
834 1.10.3.3.1.4 Installation - Local Junction Box Thu 7/16/09 Thu 9/24/09 0 77.9 days 1.75 11018.55
835 1.10.3.3.1.4.1 Rigid Steel Conduit Thu 7/16/09 Wed 7/22/09 E 0 7.5 days 130 mtr 0.96 6021.3
836 1.10.3.3.1.4.2 Junction Box Wed 7/22/09 Sun 7/26/09 E 0 3.54 days 26 nos. 0.05 345.92
837 1.10.3.3.1.4.3 Feeder cables Sun 7/26/09 Sun 8/2/09 E 0 8.12 days 948 mtr 0.5 3126.95
838 1.10.3.3.1.4.4 Cable Termination Tue 9/8/09 Thu 9/24/09 E 0 18 days 88 nos. 0.24 1524.38
839 1.10.3.3.2 Air Compressed System - Piping Thu 7/16/09 Thu 7/23/09 0 8 days 0.05 333.13
840 1.10.3.3.2.1 2" Equal Tee Thu 7/16/09 Mon 7/20/09 P 0 4 days 11 nos 0.03 213.2
841 1.10.3.3.2.2 2" Plug Mon 7/20/09 Tue 7/21/09 P 0 1 day 9 nos 0.01 79.95
842 1.10.3.3.2.3 1/2" Ball valve Tue 7/21/09 Tue 7/21/09 P 0 1 day 2 nos 0 10.66
843 1.10.3.3.2.4 2" x 1" Reducer Tue 7/21/09 Wed 7/22/09 P 0 1 day 2 nos 0 10.66
844 1.10.3.3.2.5 1" x 1/2" Reducer Tue 7/21/09 Wed 7/22/09 P 0 1 day 2 nos 0 10.66
845 1.10.3.3.2.6 1/2" Nipple Wed 7/22/09 Thu 7/23/09 P 0 1 day 2 nos 0 8
846 1.10.4 Pot 264 Thu 8/6/09 Thu 9/24/09 0 54.65 days 3.21 20208.7
847 4.5.2.1 SLI DELIVERABLES Thu 8/6/09 Thu 8/6/09 0 0 days 0 0
848 1.10.4.1.1 POT 264 Area Available for MPEI Construction Thu 8/6/09 Thu 8/6/09 0 0 days 0 0
849 1.10.4.2 Basement Floor Thu 8/6/09 Sat 8/22/09 0 17.52 days 1.25 7879.23
850 1.10.4.2.1 Installation - Electrical Thu 8/6/09 Sat 8/22/09 0 17.52 days 1.25 7879.23
851 1.10.4.2.1.1 Installation - Lighting System Thu 8/6/09 Sat 8/22/09 0 17.52 days 0.65 4064.82
852 1.10.4.2.1.1.1 PVC conduit and boxes Thu 8/6/09 Sat 8/8/09 E 0 2.38 days 81 mtr 0.04 258.24
853 1.10.4.2.1.1.2 Single Core Wires Sat 8/8/09 Sun 8/9/09 E 0 1.24 days 176 mtr 0.02 130.53
854 1.10.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 8/6/09 Sat 8/8/09 E 0 1.4 days 19 nos. 0.02 152.97
855 1.10.4.2.1.1.4 Lighting Feeder cables / wires Wed 8/12/09 Sat 8/22/09 E 0 11.22 days 1477 mtr 0.56 3523.08
856 1.10.4.2.1.2 Installation - Emergency Shutdown Thu 8/6/09 Tue 8/18/09 0 13.3 days 0.61 3814.41
857 1.10.4.2.1.2.1 PVC conduit and boxes Thu 8/6/09 Thu 8/6/09 I 0 0.76 days 12 mtr 0.01 63.96
858 1.10.4.2.1.2.2 Instrument cables Thu 8/6/09 Tue 8/18/09 I 0 12.21 days 1944 mtr 0.59 3731.8
859 1.10.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 8/18/09 Tue 8/18/09 I 0 0.33 days 1 mtr 0 18.66
860 1.10.4.3 Operation Floor Thu 8/6/09 Thu 9/24/09 0 54.65 days 1.96 12329.46
861 1.10.4.3.1 Installation - Electrical Thu 8/6/09 Thu 9/24/09 0 54.65 days 1.9 11996.34
862 1.10.4.3.1.1 Installation - Cable Tray Thu 8/6/09 Wed 8/12/09 0 6.3 days 0.02 110.86
863 1.10.4.3.1.1.1 Cantilever supports installation Thu 8/6/09 Thu 8/6/09 E 0 0.07 days 9 nos. 0 7.65
864 1.10.4.3.1.1.2 Cable Tray installation Tue 8/11/09 Wed 8/12/09 E 0 0.45 days 55 mtr 0.02 103.22
865 1.10.4.3.1.2 Installation - Crane Bus Bars Thu 8/6/09 Wed 8/12/09 0 7.45 days 0.69 4338.62
866 1.10.4.3.1.2.1 Crane Bus Bar Supports installation Thu 8/6/09 Thu 8/6/09 E 0 0.96 days 16 nos. 0.02 96.37
867 1.10.4.3.1.2.2 Disconnect Switch Instalation Thu 8/6/09 Sat 8/8/09 E 0 0.5 days 1 nos. 0 17.32
868 1.10.4.3.1.2.3 Interconnection cable, cableways installation Sat 8/8/09 Sun 8/9/09 E 0 1 day 5 nos. 0.03 159.9
869 1.10.4.3.1.2.4 Crane Power Feeder Cable Sun 8/9/09 Wed 8/12/09 E 0 4 days 525 mtr 0.63 3978.85
870 1.10.4.3.1.2.5 Cable Termination Wed 8/12/09 Wed 8/12/09 E 0 0.99 days 5 nos. 0.01 86.19
871 1.10.4.3.1.3 Installation - Blower and Transformer Feeder Thu 8/6/09 Tue 8/11/09 0 5.85 days 0.42 2653.46
872 1.10.4.3.1.3.1 Blower Feeder, Transformer Feeder Thu 8/6/09 Tue 8/11/09 E 0 5.85 days 700 mtr 0.42 2653.46
873 1.10.4.3.1.4 Installation - Socket / Welding Outlet Thu 8/6/09 Sun 8/9/09 0 3.23 days 0.07 434.47
874 1.10.4.3.1.4.1 Rigid Steel Conduit Thu 8/6/09 Thu 8/6/09 E 0 0.84 days 15 mtr 0.01 78.35
875 1.10.4.3.1.4.2 Single Core Wires Thu 8/6/09 Sat 8/8/09 E 0 1.08 days 50 mtr 0.01 80.59
876 1.10.4.3.1.4.3 Junction Box Sat 8/8/09 Sun 8/9/09 E 0 0.5 days 2 nos. 0 23.98
877 1.10.4.3.1.4.4 Welding outlet / Socket Outlet Sun 8/9/09 Sun 8/9/09 E 0 0.29 days 2 nos. 0 27.05
878 1.10.4.3.1.4.5 Socket Feeder cables Sun 8/9/09 Sun 8/9/09 E 0 0.52 days 60 mtr 0.04 224.5
879 1.10.4.3.1.5 Installation - Local Junction Box Thu 8/6/09 Thu 9/24/09 0 54.65 days 0.71 4458.92
880 1.10.4.3.1.5.1 Rigid Steel Conduit Thu 8/6/09 Thu 8/13/09 E 0 7.62 days 140 mtr 0.12 744.6
881 1.10.4.3.1.5.2 Junction Box Thu 8/13/09 Sun 8/16/09 E 0 3.81 days 28 nos. 0.06 372.3
882 1.10.4.3.1.5.3 Feeder cables Sun 8/16/09 Thu 8/20/09 E 0 4.72 days 550 mtr 0.29 1817.64
883 1.10.4.3.1.5.4 Cable Termination Tue 9/8/09 Thu 9/24/09 E 0 18 days 88 nos. 0.24 1524.38
884 1.10.4.3.2 Air Compressed System - Piping Thu 8/6/09 Tue 8/11/09 0 6 days 0.05 333.13
8/6
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 15 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ID WBS Task Name Start Finish Code Final %
From
Weight
Duration Quantity
(ECN)
Unit Weight M/H Final
885 1.10.4.3.2.1 2" Equal Tee Thu 8/6/09 Mon 8/10/09 P 0 4 days 11 nos 0.03 213.2
886 1.10.4.3.2.2 2" Plug Sat 8/8/09 Sun 8/9/09 P 0 1 day 9 nos 0.01 79.95
887 1.10.4.3.2.3 1/2" Ball valve Sun 8/9/09 Mon 8/10/09 P 0 1 day 2 nos 0 10.66
888 1.10.4.3.2.4 2" x 1" Reducer Mon 8/10/09 Tue 8/11/09 P 0 1 day 2 nos 0 10.66
889 1.10.4.3.2.5 1" x 1/2" Reducer Mon 8/10/09 Tue 8/11/09 P 0 1 day 2 nos 0 10.66
890 1.10.4.3.2.6 1/2" Nipple Tue 8/11/09 Tue 8/11/09 P 0 1 day 2 nos 0 8
891 1.11 Construction - Potroom No 2 (501-22C) Thu 5/14/09 Wed 8/19/09 0 107.9 days 11.61 73108.92
892 1.11.1 Pot 198 Thu 5/14/09 Thu 6/25/09 0 46.87 days 2.96 18614.31
893 4.5.2.1 SLI DELIVERABLES Thu 5/14/09 Thu 5/14/09 0 0 days 0 0
894 1.11.1.1.1 POT 198 Area Available for MPEI Construction Thu 5/14/09 Thu 5/14/09 0 0 days 0 0
895 1.11.1.2 Basement Floor Sat 5/16/09 Thu 6/25/09 0 45.16 days 1.15 7244.8
896 1.11.1.2.1 Installation - Electrical Sat 5/16/09 Thu 6/25/09 0 45.16 days 1.15 7244.8
897 1.11.1.2.1.1 Installation - Lighting System Sat 5/16/09 Sun 6/7/09 0 24.84 days 0.55 3449.04
898 1.11.1.2.1.1.1 PVC conduit and boxes Sat 5/16/09 Sun 5/17/09 E 0 2.03 days 68 mtr 0.03 220.26
899 1.11.1.2.1.1.2 Single Core Wires Sun 5/17/09 Mon 5/18/09 E 0 1.04 days 148 mtr 0.02 109.48
900 1.11.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Sat 5/16/09 Sun 5/17/09 E 0 1.19 days 16 nos. 0.02 130.03
901 1.11.1.2.1.1.4 Lighting Feeder cables / wires Thu 5/28/09 Sun 6/7/09 E 0 9.52 days 1244 mtr 0.47 2989.28
902 1.11.1.2.1.2 Installation - Emergency Shutdown Wed 6/10/09 Thu 6/25/09 0 16.44 days 0.6 3795.76
903 1.11.1.2.1.2.1 PVC conduit and boxes Wed 6/10/09 Wed 6/10/09 I 0 0.76 days 12 mtr 0.01 63.96
904 1.11.1.2.1.2.2 Instrument cables Sun 6/14/09 Thu 6/25/09 I 0 12.21 days 1944 mtr 0.59 3731.8
905 1.11.1.3 Operation Floor Thu 5/14/09 Thu 6/25/09 0 46.87 days 1.81 11369.5
906 1.11.1.3.1 Installation - Electrical Thu 5/14/09 Thu 6/25/09 0 46.87 days 1.75 11036.38
907 1.11.1.3.1.1 Installation - Crane Bus Bars Mon 5/18/09 Wed 5/27/09 0 11.13 days 0.73 4602.61
908 1.11.1.3.1.1.1 Crane Bus Bar Supports installation Mon 5/18/09 Mon 5/18/09 E 0 0.96 days 16 nos. 0.02 96.37
909 1.11.1.3.1.1.2 Feed Junction Box Installation Mon 5/18/09 Wed 5/20/09 E 0 1.67 days 5 nos. 0.01 89.01
910 1.11.1.3.1.1.3 Disconnect Switch Instalation Wed 5/20/09 Wed 5/20/09 E 0 0.5 days 1 nos. 0 17.32
911 1.11.1.3.1.1.4 Interconnection cable, cableways installation Wed 5/20/09 Thu 5/21/09 E 0 1 day 5 nos. 0.03 159.9
912 1.11.1.3.1.1.5 Crane Power Feeder Cable Thu 5/21/09 Mon 5/25/09 E 0 4 days 525 mtr 0.63 3978.85
913 1.11.1.3.1.1.6 Cable Termination Mon 5/25/09 Wed 5/27/09 E 0 3 days 15 nos. 0.04 261.17
914 1.11.1.3.1.2 Installation - Socket / Welding Outlet Thu 5/14/09 Sun 5/17/09 0 3.23 days 0.07 434.47
915 1.11.1.3.1.2.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/14/09 E 0 0.84 days 15 mtr 0.01 78.35
916 1.11.1.3.1.2.2 Single Core Wires Thu 5/14/09 Sat 5/16/09 E 0 1.08 days 50 mtr 0.01 80.59
917 1.11.1.3.1.2.3 Junction Box Sat 5/16/09 Sun 5/17/09 E 0 0.5 days 2 nos. 0 23.98
918 1.11.1.3.1.2.4 Welding outlet / Socket Outlet Sun 5/17/09 Sun 5/17/09 E 0 0.29 days 2 nos. 0 27.05
919 1.11.1.3.1.2.5 Socket Feeder cables Sun 5/17/09 Sun 5/17/09 E 0 0.52 days 60 mtr 0.04 224.5
920 1.11.1.3.1.3 Installation - Local Junction Box Thu 5/21/09 Thu 6/25/09 0 38.15 days 0.95 5999.29
921 1.11.1.3.1.3.1 Rigid Steel Conduit Thu 5/21/09 Thu 5/28/09 E 0 7.62 days 140 mtr 0.12 744.6
922 1.11.1.3.1.3.2 Junction Box Thu 5/28/09 Mon 6/1/09 E 0 3.81 days 28 nos. 0.06 372.3
923 1.11.1.3.1.3.3 Feeder cables Mon 6/1/09 Tue 6/9/09 E 0 8.72 days 1020 mtr 0.53 3358.01
924 1.11.1.3.1.3.4 Cable Termination Tue 6/9/09 Thu 6/25/09 E 0 18 days 88 nos. 0.24 1524.38
925 1.11.1.3.2 Air Compressed System - Piping Thu 5/14/09 Wed 5/20/09 0 6.35 days 0.05 333.13
926 1.11.1.3.2.1 2" Equal Tee Thu 5/14/09 Mon 5/18/09 P 0 4 days 11 nos 0.03 213.2
927 1.11.1.3.2.2 2" Plug Sat 5/16/09 Sun 5/17/09 P 0 1 day 9 nos 0.01 79.95
928 1.11.1.3.2.3 1/2" Ball valve Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66
929 1.11.1.3.2.4 2" x 1" Reducer Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66
930 1.11.1.3.2.5 1" x 1/2" Reducer Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66
931 1.11.1.3.2.6 1/2" Nipple Tue 5/19/09 Wed 5/20/09 P 0 1 day 2 nos 0 8
932 1.11.2 Pot 220 Wed 6/3/09 Sun 7/12/09 0 42.89 days 2.4 15091.58
933 4.5.2.1 SLI DELIVERABLES Thu 6/4/09 Thu 6/4/09 0 0 days 0 0
934 1.11.2.1.1 POT 220 Area Available for MPEI Construction Thu 6/4/09 Thu 6/4/09 0 0 days 0 0
935 1.11.2.2 Basement Floor Wed 6/3/09 Wed 7/1/09 0 32 days 1.22 7687.83
936 1.11.2.2.1 Installation - Electrical Wed 6/3/09 Wed 7/1/09 0 32 days 1.22 7687.83
937 1.11.2.2.1.1 Installation - Lighting System Wed 6/3/09 Sat 6/13/09 0 10.71 days 0.61 3873.42
938 1.11.2.2.1.1.1 PVC conduit and boxes Thu 6/4/09 Sat 6/6/09 E 0 2.24 days 76 mtr 0.04 243.05
939 1.11.2.2.1.1.2 Single Core Wires Sat 6/6/09 Sun 6/7/09 E 0 1.16 days 166 mtr 0.02 122.11
940 1.11.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports
and fixings
Thu 6/4/09 Sat 6/6/09 E 0 1.33 days 18 nos. 0.02 145.32
941 1.11.2.2.1.1.4 Lighting Feeder cables / wires Wed 6/3/09 Sat 6/13/09 E 0 10.71 days 1400 mtr 0.53 3362.94
942 1.11.2.2.1.2 Installation - Emergency Shutdown Wed 6/10/09 Wed 7/1/09 0 23.22 days 0.61 3814.41
943 1.11.2.2.1.2.1 PVC conduit and boxes Wed 6/10/09 Thu 6/11/09 I 0 0.76 days 12 mtr 0.01 63.96
5/14
6/4
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2009
Task
Baseline Task 2
Critical
Split
Progress
Milestone
Baseline Milestone 1
Summary
Baseline Summary 1
Rev. : 02
Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan
Page 16 Of 24
Project: C005 without subtotal
Date: Tue 3/31/09
ECN Plan For C-005 Final
ECN Plan For C-005 Final
ECN Plan For C-005 Final
ECN Plan For C-005 Final
ECN Plan For C-005 Final
ECN Plan For C-005 Final
ECN Plan For C-005 Final
ECN Plan For C-005 Final

More Related Content

Viewers also liked

Viewers also liked (8)

Španielsko
ŠpanielskoŠpanielsko
Španielsko
 
Ch09
Ch09Ch09
Ch09
 
Ch08
Ch08Ch08
Ch08
 
Ch06
Ch06Ch06
Ch06
 
Colours of light
Colours of lightColours of light
Colours of light
 
Module 2 guided reading ppt
Module 2 guided reading pptModule 2 guided reading ppt
Module 2 guided reading ppt
 
NEOPLASTIC DISEASE
NEOPLASTIC DISEASENEOPLASTIC DISEASE
NEOPLASTIC DISEASE
 
Google Loon presentation
Google Loon presentationGoogle Loon presentation
Google Loon presentation
 

Similar to ECN Plan For C-005 Final

Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Ali Yousef
 
Amp nema23 stepper_motor_specsheet
Amp nema23 stepper_motor_specsheetAmp nema23 stepper_motor_specsheet
Amp nema23 stepper_motor_specsheetElectromate
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Physics Deprt. Instruments list.
Physics Deprt. Instruments list.Physics Deprt. Instruments list.
Physics Deprt. Instruments list.AvinashPatil193268
 
Hu, Maria (Yue) Assign 2 B
Hu, Maria (Yue) Assign 2 BHu, Maria (Yue) Assign 2 B
Hu, Maria (Yue) Assign 2 BMarina Hu
 
Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates. Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates. QuarterlyEarningsReports3
 
Pilkinton tenant improvement schedule
Pilkinton tenant improvement schedulePilkinton tenant improvement schedule
Pilkinton tenant improvement scheduleTylerShisler
 
(1) McGill Pricelist - 13Jan023.pdf
(1) McGill Pricelist - 13Jan023.pdf(1) McGill Pricelist - 13Jan023.pdf
(1) McGill Pricelist - 13Jan023.pdfJrMerlinCabato2
 
Remote detection of weak aftershocks of the DPRK underground explosions using...
Remote detection of weak aftershocks of the DPRK underground explosions using...Remote detection of weak aftershocks of the DPRK underground explosions using...
Remote detection of weak aftershocks of the DPRK underground explosions using...Ivan Kitov
 
REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 Chandra sekhar sahoo
 
AWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion Table
AWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion TableAWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion Table
AWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion TableThorne & Derrick International
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxabirsengupta9
 
Pabrik kabel indonesia katalog low voltage eleqcable com
Pabrik kabel indonesia katalog low voltage eleqcable comPabrik kabel indonesia katalog low voltage eleqcable com
Pabrik kabel indonesia katalog low voltage eleqcable comTOKO BUNGA ONLINE JAKARTA
 

Similar to ECN Plan For C-005 Final (20)

Popop
PopopPopop
Popop
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
 
Amp nema23 stepper_motor_specsheet
Amp nema23 stepper_motor_specsheetAmp nema23 stepper_motor_specsheet
Amp nema23 stepper_motor_specsheet
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Presentase Performa Kapal
Presentase Performa KapalPresentase Performa Kapal
Presentase Performa Kapal
 
Physics Deprt. Instruments list.
Physics Deprt. Instruments list.Physics Deprt. Instruments list.
Physics Deprt. Instruments list.
 
Slide7 mp psht4of6
Slide7 mp psht4of6Slide7 mp psht4of6
Slide7 mp psht4of6
 
Hu, Maria (Yue) Assign 2 B
Hu, Maria (Yue) Assign 2 BHu, Maria (Yue) Assign 2 B
Hu, Maria (Yue) Assign 2 B
 
Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates. Historical IBM quarterly dividend rates and payable and records dates.
Historical IBM quarterly dividend rates and payable and records dates.
 
Pilkinton tenant improvement schedule
Pilkinton tenant improvement schedulePilkinton tenant improvement schedule
Pilkinton tenant improvement schedule
 
(1) McGill Pricelist - 13Jan023.pdf
(1) McGill Pricelist - 13Jan023.pdf(1) McGill Pricelist - 13Jan023.pdf
(1) McGill Pricelist - 13Jan023.pdf
 
Test
TestTest
Test
 
CPM
CPMCPM
CPM
 
Remote detection of weak aftershocks of the DPRK underground explosions using...
Remote detection of weak aftershocks of the DPRK underground explosions using...Remote detection of weak aftershocks of the DPRK underground explosions using...
Remote detection of weak aftershocks of the DPRK underground explosions using...
 
REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2 REDUCTION OF RE SLEEVING TIME IN LD2
REDUCTION OF RE SLEEVING TIME IN LD2
 
AWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion Table
AWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion TableAWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion Table
AWG (American Wire Gauge) To Metric (Sqmm Millimeters Squared) Conversion Table
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptx
 
Pabrik kabel indonesia katalog low voltage eleqcable com
Pabrik kabel indonesia katalog low voltage eleqcable comPabrik kabel indonesia katalog low voltage eleqcable com
Pabrik kabel indonesia katalog low voltage eleqcable com
 

ECN Plan For C-005 Final

  • 1. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 1 1 Construction and Installation Activities (Just For ECN Works) Fri 10/31/08 Tue 11/17/09 5.1 422.8 days 100 629859.25 2 1.1 Start Of The Project Fri 10/31/08 Fri 10/31/08 0 0 days 0 0 3 1.2 Construction - Rectifier Passage 503-12 Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41 4 1.2.1 Operation Floor Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41 5 1.2.1.1 Installation - Electrical Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41 6 1.2.1.1.1 Installation - Cable Tray Sat 3/28/09 Tue 4/28/09 0 35.04 days 0.15 933.86 7 1.2.1.1.1.1 Cantilever supports installation Sat 3/28/09 Sat 4/18/09 E 0 2.42 days 97 nos. 0.03 158.33 8 1.2.1.1.1.2 Cable Tray installation Sun 4/19/09 Tue 4/28/09 E 0 10.5 days 420 mtr 0.12 775.53 9 1.2.1.1.2 Installation - Crane Bus Bars Tue 4/28/09 Wed 5/20/09 0 24.31 days 1.03 6515.55 10 1.2.1.1.2.1 Crane Bus Bar Supports installation Tue 4/28/09 Sun 5/3/09 E 0 5.22 days 87 nos. 0.09 543.99 11 1.2.1.1.2.2 Feed Junction Box Installation Sun 5/3/09 Wed 5/6/09 E 0 3.54 days 13 nos. 0.04 236.42 12 1.2.1.1.2.3 Disconnect Switch Instalation Wed 5/6/09 Thu 5/7/09 E 0 1.56 days 7 nos. 0.02 132.64 13 1.2.1.1.2.4 Interconnection cable, cableways installation Thu 5/7/09 Mon 5/11/09 E 0 3.99 days 60 nos. 0.25 1605 14 1.2.1.1.2.5 Crane feeder cables Mon 5/11/09 Wed 5/20/09 E 0 10 days 1080 mtr 0.63 3997.5 15 1.3 Construction - Potroom No. 1 (501-12A) Mon 11/24/08 Wed 7/29/09 1.92 273.91 days 11.41 71862.2 16 1.3.1 Pot 22 Mon 11/24/08 Wed 6/10/09 0.74 219.91 days 2.88 18111.55 17 1.3.1.1 SLI DELIVERABLES Mon 11/24/08 Mon 11/24/08 0 0 days 0 0 18 1.3.1.1.1 POT 22 Area Available for MPEI Construction Mon 11/24/08 Mon 11/24/08 0 0 days 0 0 19 1.3.1.2 Basement Floor Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18 20 1.3.1.2.1 Installation - Electrical Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18 21 1.3.1.2.1.1 Installation - Lighting System Tue 12/30/08 Sun 2/8/09 0.61 43.76 days 0.61 3873.42 22 1.3.1.2.1.1.1 PVC conduit and boxes Tue 12/30/08 Sun 1/4/09 E 0.04 5.67 days 75 mtr 0.04 243.05 23 1.3.1.2.1.1.2 Single Core Wires Sun 1/25/09 Tue 1/27/09 E 0.02 2.51 days 165 mtr 0.02 122.11 24 1.3.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Tue 1/27/09 Wed 1/28/09 E 0.02 0.35 days 18 nos. 0.02 145.32 25 1.3.1.2.1.1.4 Lighting Feeder cables / wires Wed 1/28/09 Sun 2/8/09 E 0.53 11.91 days 1400 mtr 0.53 3362.94 26 1.3.1.2.1.2 Installation - Emergency Shutdown Tue 4/21/09 Sun 5/3/09 0.01 12.97 days 0.6 3795.76 27 1.3.1.2.1.2.1 PVC conduit and boxes Tue 4/21/09 Wed 4/22/09 I 0.01 0.76 days 12 mtr 0.01 63.96 28 1.3.1.2.1.2.2 Instrument cables Wed 4/22/09 Sun 5/3/09 I 0 12.21 days 1944 mtr 0.59 3731.8 29 1.3.1.3 Operation Floor Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.66 10442.38 30 1.3.1.3.1 Air Compressed System - Piping Sat 4/11/09 Sat 4/18/09 0 9 days 0.05 333.13 31 1.3.1.3.1.1 2" Equal Tee Sat 4/11/09 Tue 4/14/09 P 0 4 days 11 nos 0.03 213.2 32 1.3.1.3.1.2 2" Plug Tue 4/14/09 Tue 4/14/09 P 0 1 day 9 nos 0.01 79.95 33 1.3.1.3.1.3 1/2" Ball valve Tue 4/14/09 Wed 4/15/09 P 0 1 day 2 nos 0 10.66 34 1.3.1.3.1.4 2" x 1" Reducer Wed 4/15/09 Thu 4/16/09 P 0 1 day 2 nos 0 10.66 35 1.3.1.3.1.5 1" x 1/2" Reducer Thu 4/16/09 Sat 4/18/09 P 0 1 day 2 nos 0 10.66 36 1.3.1.3.1.6 1/2" Nipple Sat 4/18/09 Sat 4/18/09 P 0 1 day 2 nos 0 8 37 1.3.1.3.2 Delivery of sub station 305-51 from SNCLavalin to Astaldi Tue 3/31/09 Tue 3/31/09 0 0 days 0 0 38 1.3.1.3.3 Installation - Electrical Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.61 10109.25 39 1.3.1.3.3.1 Installation - Lighting System Tue 12/2/08 Sun 12/7/08 0.08 5.04 days 0.08 523.22 40 1.3.1.3.3.1.1 Rigid Steel Conduit Tue 12/2/08 Thu 12/4/08 E 0.03 1.66 days 26 mtr 0.03 157.5 41 1.3.1.3.3.1.2 Single Core Wires Thu 12/4/08 Thu 12/4/08 E 0.03 0.79 days 300 mtr 0.03 188.82 42 1.3.1.3.3.1.3 High Bay Lighting fixtures including supports and fixings Thu 12/4/08 Sun 12/7/08 E 0.02 1.59 days 6 nos. 0.02 155.58 43 1.3.1.3.3.1.4 Lighting Feeder cables / wires Sun 12/7/08 Sun 12/7/08 E 0 1 day 8 mtr 0 21.32 44 1.3.1.3.3.2 Installation - Crane Bus Bars Sat 1/10/09 Mon 5/25/09 0.02 150.24 days 0.51 3205.04 45 1.3.1.3.3.2.1 Crane Bus Bar Supports installation Sat 1/10/09 Sat 1/10/09 E 0.02 0.69 days 16 nos. 0.02 96.37 46 1.3.1.3.3.2.2 Feed Junction Box Installation Sat 1/10/09 Sun 1/11/09 E 0 1.33 days 4 nos. 0.01 70.89 47 1.3.1.3.3.2.3 Disconnect Switch Instalation Sun 1/11/09 Mon 1/12/09 E 0 0.5 days 1 nos. 0 17.32 48 1.3.1.3.3.2.4 Interconnection cable, cableways installation Mon 1/12/09 Mon 1/12/09 E 0 1 day 5 nos. 0.02 133.25 49 1.3.1.3.3.2.5 Crane Power Feeder Cable Wed 5/20/09 Sat 5/23/09 E 0 2.64 days 350 mtr 0.42 2626.04 50 1.3.1.3.3.2.6 Cable Termination Sat 5/23/09 Mon 5/25/09 E 0 3 days 15 nos. 0.04 261.17 51 1.3.1.3.3.3 Installation - Socket / Welding Outlet Mon 1/26/09 Sun 3/15/09 0.02 52.75 days 0.06 381.71 52 1.3.1.3.3.3.1 Rigid Steel Conduit Mon 1/26/09 Tue 1/27/09 E 0.01 1.8 days 15 mtr 0.01 78.35 53 1.3.1.3.3.3.2 Single Core Wires Sat 3/14/09 Sun 3/15/09 E 0 1.33 days 50 mtr 0 27.82 54 1.3.1.3.3.3.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 23.98 55 1.3.1.3.3.3.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.29 days 2 nos. 0 27.05 56 1.3.1.3.3.3.5 Socket Feeder cables Thu 1/29/09 Thu 1/29/09 E 0 0.52 days 60 mtr 0.04 224.5 57 1.3.1.3.3.4 Installation - Local Junction Box Sun 5/3/09 Wed 6/10/09 0 42.95 days 0.95 5999.29 10/31 11/24 11/24 Installation extended Material by Astaldi Material by SNC 3/31 Waiting for cable tray to be installed No junction box available No disconnect switch installation available No cables and cable tray Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 1 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 2. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 58 1.3.1.3.3.4.1 Rigid Steel Conduit Sun 5/3/09 Sun 5/10/09 E 0 7.62 days 140 mtr 0.12 744.6 59 1.3.1.3.3.4.2 Junction Box Sun 5/10/09 Tue 5/12/09 E 0 3.81 days 28 nos. 0.06 372.3 60 1.3.1.3.3.4.3 Feeder cables Tue 5/12/09 Wed 5/20/09 E 0 8.72 days 1020 mtr 0.53 3358.01 61 1.3.1.3.3.4.4 Cable Termination Mon 5/25/09 Wed 6/10/09 E 0 18 days 88 nos. 0.24 1524.38 62 1.3.2 Pot 44 Tue 1/6/09 Sat 6/27/09 0.83 189.12 days 2.48 15600.06 63 4.5.2.1 SLI DELIVERABLES Tue 2/3/09 Tue 2/3/09 0 0 days 0 0 64 1.3.2.1.1 POT 44 Area Available for MPEI Construction Tue 2/3/09 Tue 2/3/09 0 0 days 0 0 65 1.3.2.2 Basement Floor Tue 2/3/09 Sun 5/10/09 0.8 106.72 days 1.4 8789.57 66 1.3.2.2.1 Installation - Electrical Tue 2/3/09 Sun 5/10/09 0.8 106.72 days 1.4 8789.57 67 1.3.2.2.1.1 Installation - Lighting System Tue 2/3/09 Mon 4/20/09 0.79 84.77 days 0.79 4975.16 68 1.3.2.2.1.1.1 PVC conduit and boxes Tue 2/3/09 Wed 2/4/09 E 0.05 2.37 days 95 mtr 0.05 303.81 69 1.3.2.2.1.1.2 Single Core Wires Wed 2/4/09 Sat 2/7/09 E 0.04 2.35 days 322 mtr 0.04 240.01 70 1.3.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Sat 2/7/09 Mon 2/9/09 E 0.04 2.1 days 34 nos. 0.04 267.7 71 1.3.2.2.1.1.4 Lighting Feeder cables / wires Mon 2/9/09 Mon 4/20/09 E 0.66 11.51 days 1738 mtr 0.66 4163.64 72 1.3.2.2.1.2 Installation - Emergency Shutdown Sat 2/21/09 Sun 5/10/09 0.01 87.34 days 0.61 3814.41 73 1.3.2.2.1.2.1 PVC conduit and boxes Sat 2/21/09 Sat 2/21/09 I 0.01 0.76 days 12 mtr 0.01 63.96 74 1.3.2.2.1.2.2 Instrument cables Wed 4/29/09 Sun 5/10/09 I 0 12.21 days 1944 mtr 0.59 3731.8 75 1.3.2.2.1.2.3 Remote ASI Panel /Cabinet Sun 5/10/09 Sun 5/10/09 I 0 0.33 days 1 mtr 0 18.66 76 1.3.2.3 Operation Floor Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.08 6810.49 77 1.3.2.3.1 Air Compressed System - Piping Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.08 6810.49 78 1.3.2.3.1.1 2" Equal Tee Tue 4/14/09 Sat 4/18/09 P 0 4 days 11 nos 0.03 213.2 79 1.3.2.3.1.2 2" Plug Sat 4/18/09 Sat 4/18/09 P 0 1 day 9 nos 0.01 79.95 80 1.3.2.3.1.3 1/2" Ball valve Sat 4/18/09 Sun 4/19/09 P 0 1 day 2 nos 0 10.66 81 1.3.2.3.1.4 2" x 1" Reducer Sun 4/19/09 Mon 4/20/09 P 0 1 day 2 nos 0 10.66 82 1.3.2.3.1.5 1" x 1/2" Reducer Mon 4/20/09 Tue 4/21/09 P 0 1 day 2 nos 0 10.66 83 1.3.2.3.1.6 1/2" Nipple Tue 4/21/09 Wed 4/22/09 P 0 1 day 2 nos 0 8 84 1.3.2.3.1.7 Installation - Electrical Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.03 6477.36 85 1.3.2.3.1.7.1 Installation - Crane Bus Bars Tue 1/6/09 Sat 1/10/09 0.02 2.97 days 0.02 96.37 86 1.3.2.3.1.7.1.1 Crane Bus Bar Supports installation Tue 1/6/09 Sat 1/10/09 E 0.02 2.97 days 16 nos. 0.02 96.37 87 1.3.2.3.1.7.2 Installation - Socket / Welding Outlet Sun 3/22/09 Sun 4/19/09 0.02 31.02 days 0.06 381.71 88 1.3.2.3.1.7.2.1 Rigid Steel Conduit Sun 3/22/09 Sun 3/22/09 E 0.01 0.84 days 15 mtr 0.01 78.35 89 1.3.2.3.1.7.2.2 Single Core Wires Mon 3/23/09 Mon 3/23/09 E 0 0.36 days 50 mtr 0 27.82 90 1.3.2.3.1.7.2.3 Junction Box Sat 4/18/09 Sat 4/18/09 E 0 0.5 days 2 nos. 0 23.98 91 1.3.2.3.1.7.2.4 Welding outlet / Socket Outlet Sat 4/18/09 Sat 4/18/09 E 0 0.29 days 2 nos. 0 27.05 92 1.3.2.3.1.7.2.5 Socket Feeder cables Sat 4/18/09 Sun 4/19/09 E 0 0.52 days 60 mtr 0.04 224.5 93 1.3.2.3.1.7.3 Installation - Local Junction Box Thu 4/16/09 Sat 6/27/09 0 79.12 days 0.95 5999.29 94 6.73 Rigid Steel Conduit Thu 4/16/09 Thu 4/23/09 E 0 7.83 days 140 mtr 0.12 744.6 95 3.81 Junction Box Tue 5/12/09 Sat 5/16/09 E 0 3.81 days 28 nos. 0.06 372.3 96 8.72 Feeder cables Sat 5/16/09 Sun 5/24/09 E 0 8.72 days 1020 mtr 0.53 3358.01 97 18 Cable Termination Wed 6/10/09 Sat 6/27/09 E 0 18 days 88 nos. 0.24 1524.38 98 1.3.3 Pot 66 Thu 2/12/09 Mon 7/13/09 0.07 166.78 days 2.85 17950.19 99 4.5.2.1 SLI DELIVERABLES Thu 2/12/09 Thu 2/12/09 0 0 days 0 0 100 1.3.3.1.1 POT 66 Area Available for MPEI Construction Thu 2/12/09 Thu 2/12/09 0 0 days 0 0 101 1.3.3.2 Basement Floor Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 1.31 8278.18 102 1.3.3.2.1 Installation - Electrical Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 1.31 8278.18 103 1.3.3.2.1.1 Installation - Lighting System Tue 4/7/09 Wed 5/6/09 0 32.47 days 0.71 4482.42 104 1.3.3.2.1.1.1 PVC conduit and boxes Tue 4/7/09 Wed 4/22/09 E 0 16.38 days 558 mtr 0.28 1777.29 105 1.3.3.2.1.1.2 Single Core Wires Wed 4/22/09 Wed 4/22/09 E 0 0.92 days 132 mtr 0.02 96.85 106 1.3.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Wed 4/22/09 Thu 4/23/09 E 0 0.91 days 12 nos. 0.02 99.43 107 1.3.3.2.1.1.4 Lighting Feeder cables / wires Wed 4/29/09 Wed 5/6/09 E 0 7.99 days 1050 mtr 0.4 2508.86 108 1.3.3.2.1.2 Installation - Emergency Shutdown Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 0.6 3795.76 109 1.3.3.2.1.2.1 PVC conduit and boxes Sat 2/28/09 Sat 2/28/09 I 0.01 0.76 days 12 mtr 0.01 63.96 110 1.3.3.2.1.2.2 Instrument cables Tue 5/5/09 Sun 5/17/09 I 0 12.21 days 1944 mtr 0.59 3731.8 111 1.3.3.3 Operation Floor Tue 3/24/09 Mon 7/13/09 0.05 122.87 days 1.54 9672 112 1.3.3.3.1 Air Compressed System - Piping Sat 4/18/09 Sun 4/26/09 0 9 days 0.05 333.13 113 1.3.3.3.1.1 2" Equal Tee Sat 4/18/09 Tue 4/21/09 P 0 4 days 11 nos 0.03 213.2 114 1.3.3.3.1.2 2" Plug Tue 4/21/09 Wed 4/22/09 P 0 1 day 9 nos 0.01 79.95 115 1.3.3.3.1.3 1/2" Ball valve Wed 4/22/09 Wed 4/22/09 P 0 1 day 2 nos 0 10.66 116 1.3.3.3.1.4 2" x 1" Reducer Wed 4/22/09 Thu 4/23/09 P 0 1 day 2 nos 0 10.66 2/3 Material by Astaldi Material by SNC Material by SNC 2/12 Material by Astaldi Material by SNC Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 2 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 3. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 117 1.3.3.3.1.5 1" x 1/2" Reducer Thu 4/23/09 Sat 4/25/09 P 0 1 day 2 nos 0 10.66 118 1.3.3.3.1.6 1/2" Nipple Sat 4/25/09 Sun 4/26/09 P 0 1 day 2 nos 0 8 119 1.3.3.3.2 Installation - Electrical Tue 3/24/09 Mon 7/13/09 0.05 122.87 days 1.48 9338.88 120 1.3.3.3.2.1 Installation - Lighting System Tue 3/24/09 Thu 5/7/09 0.05 49.56 days 0.08 523.22 121 1.3.3.3.2.1.1 Rigid Steel Conduit Tue 3/24/09 Tue 3/24/09 E 0.03 0.7 days 26 mtr 0.03 157.5 122 1.3.3.3.2.1.2 Single Core Wires Wed 3/25/09 Wed 3/25/09 E 0.03 1.04 days 300 mtr 0.03 188.82 123 1.3.3.3.2.1.3 High Bay Lighting fixtures including supports and fixings Sun 4/19/09 Sun 4/19/09 E 0 0.84 days 6 nos. 0.02 155.58 124 1.3.3.3.2.1.4 Lighting Feeder cables / wires Wed 5/6/09 Thu 5/7/09 E 0 1 day 8 mtr 0 21.32 125 1.3.3.3.2.2 Installation - Cable Tray Sat 4/18/09 Wed 4/29/09 0 12.4 days 0.06 401.4 126 1.3.3.3.2.2.1 Cantilever supports installation Sat 4/18/09 Sun 4/19/09 E 0 0.21 days 22 nos. 0 22.95 127 1.3.3.3.2.2.2 Cable Tray installation Tue 4/28/09 Wed 4/29/09 E 0 1.65 days 202 mtr 0.06 378.46 128 1.3.3.3.2.3 Installation - Blower and Transformer Feeder Tue 4/7/09 Mon 4/13/09 0 5.85 days 0.43 2725.18 129 1.3.3.3.2.3.1 Blower Feeder, Transformer Feeder Tue 4/7/09 Mon 4/13/09 E 0 5.85 days 700 mtr 0.43 2725.18 130 1.3.3.3.2.4 Installation - Local Junction Box Thu 4/16/09 Mon 7/13/09 0 97.03 days 0.9 5689.08 131 1.3.3.3.2.4.1 Rigid Steel Conduit Thu 4/16/09 Wed 4/22/09 E 0 7.08 days 130 mtr 0.11 691.83 132 1.3.3.3.2.4.2 Junction Box Wed 4/22/09 Sun 4/26/09 E 0 3.54 days 26 nos. 0.05 345.92 133 1.3.3.3.2.4.3 Feeder cables Wed 4/29/09 Wed 5/6/09 E 0 8.12 days 948 mtr 0.5 3126.95 134 1.3.3.3.2.4.4 Cable Termination Sat 6/27/09 Mon 7/13/09 E 0 18 days 88 nos. 0.24 1524.38 135 1.3.4 Pot 88 Thu 2/19/09 Wed 7/29/09 0.29 177.03 days 3.21 20200.41 136 4.5.2.1 SLI DELIVERABLES Thu 2/19/09 Thu 2/19/09 0 0 days 0 0 137 1.3.4.1.1 POT 88 Area Available for MPEI Construction Thu 2/19/09 Thu 2/19/09 0 0 days 0 0 138 1.3.4.2 Basement Floor Sat 3/14/09 Sat 5/23/09 0.29 78.51 days 1.32 8308.64 139 1.3.4.2.1 Installation - Electrical Sat 3/14/09 Sat 5/23/09 0.29 78.51 days 1.32 8308.64 140 1.3.4.2.1.1 Installation - Lighting System Sat 3/14/09 Mon 5/11/09 0.28 64.57 days 0.71 4494.23 141 1.3.4.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.45 days 560 mtr 0.28 1784.88 142 1.3.4.2.1.1.2 Single Core Wires Thu 5/7/09 Thu 5/7/09 E 0 0.96 days 137 mtr 0.02 101.06 143 1.3.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Tue 5/5/09 Wed 5/6/09 E 0 0.91 days 12 nos. 0.02 99.43 144 1.3.4.2.1.1.4 Lighting Feeder cables / wires Sun 5/3/09 Mon 5/11/09 E 0 7.99 days 1050 mtr 0.4 2508.86 145 1.3.4.2.1.2 Installation - Emergency Shutdown Tue 3/24/09 Sat 5/23/09 0.01 66.89 days 0.61 3814.41 146 1.3.4.2.1.2.1 PVC conduit and boxes Tue 3/24/09 Tue 3/24/09 I 0.01 0.76 days 12 mtr 0.01 63.96 147 1.3.4.2.1.2.2 Instrument cables Tue 5/12/09 Sat 5/23/09 I 0 12.21 days 1944 mtr 0.59 3731.8 148 1.3.4.2.1.2.3 Remote ASI Panel /Cabinet Sat 5/23/09 Sat 5/23/09 I 0 0.33 days 1 mtr 0 18.66 149 1.3.4.3 Operation Floor Mon 4/13/09 Wed 7/29/09 0 118.93 days 1.89 11891.76 150 1.3.4.3.1 Air Compressed System - Piping Tue 4/21/09 Wed 4/29/09 0 9 days 0.05 333.13 151 1.3.4.3.1.1 2" Equal Tee Tue 4/21/09 Sat 4/25/09 P 0 4 days 11 nos 0.03 213.2 152 1.3.4.3.1.2 2" Plug Sat 4/25/09 Sun 4/26/09 P 0 1 day 9 nos 0.01 79.95 153 1.3.4.3.1.3 1/2" Ball valve Sun 4/26/09 Sun 4/26/09 P 0 1 day 2 nos 0 10.66 154 1.3.4.3.1.4 2" x 1" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66 155 1.3.4.3.1.5 1" x 1/2" Reducer Mon 4/27/09 Tue 4/28/09 P 0 1 day 2 nos 0 10.66 156 1.3.4.3.1.6 1/2" Nipple Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 8 157 1.3.4.3.2 Installation - Electrical Mon 4/13/09 Wed 7/29/09 0 118.93 days 1.84 11558.64 158 1.3.4.3.2.1 Installation - Lighting System Sat 4/18/09 Sat 5/9/09 0 23.13 days 0.14 887.79 159 1.3.4.3.2.1.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/18/09 E 0 0.7 days 25 mtr 0.03 157.5 160 1.3.4.3.2.1.2 Single Core Wires Sat 4/18/09 Sun 4/19/09 E 0 1.04 days 300 mtr 0.03 188.82 161 1.3.4.3.2.1.3 High Bay Lighting fixtures including supports and fixings Sun 4/19/09 Mon 4/20/09 E 0 0.84 days 6 nos. 0.02 155.58 162 1.3.4.3.2.1.4 Lighting Feeder cables / wires Thu 5/7/09 Sat 5/9/09 E 0 0.7 days 100 mtr 0.06 385.89 163 1.3.4.3.2.2 Installation - Cable Tray Sun 4/19/09 Thu 4/30/09 0 13.84 days 0.06 401.4 164 1.3.4.3.2.2.1 Cantilever supports installation Sun 4/19/09 Sun 4/19/09 E 0 0.21 days 22 nos. 0 22.95 165 1.3.4.3.2.2.2 Cable Tray installation Wed 4/29/09 Thu 4/30/09 E 0 1.65 days 202 mtr 0.06 378.46 166 1.3.4.3.2.3 Installation - Crane Bus Bars Tue 5/5/09 Tue 5/26/09 0 23.36 days 0.43 2703.64 167 1.3.4.3.2.3.1 Disconnect Switch Instalation Tue 5/5/09 Tue 5/5/09 E 0 0.5 days 1 nos. 0 17.32 168 1.3.4.3.2.3.2 Interconnection cable, cableways installation Tue 5/5/09 Wed 5/6/09 E 0 1 day 5 nos. 0.02 133.25 169 1.3.4.3.2.3.3 Crane Power Feeder Cable Wed 5/6/09 Sat 5/9/09 E 0 2.48 days 330 mtr 0.39 2466.88 170 1.3.4.3.2.3.4 Cable Termination Mon 5/25/09 Tue 5/26/09 E 0 0.99 days 5 nos. 0.01 86.19 171 1.3.4.3.2.4 Installation - Blower and Transformer Feeder Mon 4/13/09 Sat 4/18/09 0 5.85 days 0.43 2725.18 172 1.3.4.3.2.4.1 Blower Feeder, Transformer Feeder Mon 4/13/09 Sat 4/18/09 E 0 5.85 days 700 mtr 0.43 2725.18 173 1.3.4.3.2.5 Installation - Socket / Welding Outlet Wed 4/22/09 Sat 4/25/09 0 2.51 days 0.06 381.71 174 1.3.4.3.2.5.1 Rigid Steel Conduit Wed 4/22/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35 2/19 2/19 Material by Astaldi Material by SNC Material by SNC Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 3 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 4. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 175 1.3.4.3.2.5.2 Single Core Wires Thu 4/23/09 Thu 4/23/09 E 0 0.36 days 50 mtr 0 27.82 176 1.3.4.3.2.5.3 Junction Box Thu 4/23/09 Thu 4/23/09 E 0 0.5 days 2 nos. 0 23.98 177 1.3.4.3.2.5.4 Welding outlet / Socket Outlet Thu 4/23/09 Sat 4/25/09 E 0 0.29 days 2 nos. 0 27.05 178 1.3.4.3.2.5.5 Socket Feeder cables Sat 4/25/09 Sat 4/25/09 E 0 0.52 days 60 mtr 0.04 224.5 179 1.3.4.3.2.6 Installation - Local Junction Box Wed 4/22/09 Wed 7/29/09 0 107.95 days 0.71 4458.92 180 1.3.4.3.2.6.1 Rigid Steel Conduit Wed 4/22/09 Wed 4/29/09 E 0 7.62 days 140 mtr 0.12 744.6 181 1.3.4.3.2.6.2 Junction Box Wed 4/29/09 Sun 5/3/09 E 0 3.81 days 28 nos. 0.06 372.3 182 1.3.4.3.2.6.3 Feeder cables Sun 5/3/09 Thu 5/7/09 E 0 4.72 days 550 mtr 0.29 1817.64 183 1.3.4.3.2.6.4 Cable Termination Mon 7/13/09 Wed 7/29/09 E 0 18 days 88 nos. 0.24 1524.38 184 1.4 Construction - Potroom No. 2 (501-22A) Sat 11/22/08 Sun 6/14/09 3.16 226.15 days 11.78 74187.76 185 1.4.1 Pot 22 Sat 11/22/08 Sat 5/30/09 0.75 209.84 days 3.26 20550.51 186 1.4.1.1 SLI DELIVERABLES Sat 11/22/08 Sat 11/22/08 0 0 days 0 0 187 1.4.1.1.1 POT 22 Area Available for MPEI Construction Sat 11/22/08 Sat 11/22/08 0 0 days 0 0 188 1.4.1.2 Basement Floor Sat 11/22/08 Tue 4/21/09 0.63 167.68 days 1.22 7669.18 189 1.4.1.2.1 Installation - Electrical Sat 11/22/08 Tue 4/21/09 0.63 167.68 days 1.22 7669.18 190 1.4.1.2.1.1 Installation - Lighting System Sat 11/22/08 Thu 2/5/09 0.61 84.89 days 0.61 3873.42 191 1.4.1.2.1.1.1 PVC conduit and boxes Sat 11/22/08 Sun 11/23/08 E 0.04 2.28 days 75 mtr 0.04 243.05 192 1.4.1.2.1.1.2 Single Core Wires Thu 11/27/08 Sat 11/29/08 E 0.02 0.82 days 165 mtr 0.02 122.11 193 1.4.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Wed 11/26/08 Thu 11/27/08 E 0.02 1.26 days 18 nos. 0.02 145.32 194 1.4.1.2.1.1.4 Lighting Feeder cables / wires Thu 1/29/09 Thu 2/5/09 E 0.53 8.53 days 1400 mtr 0.53 3362.94 195 1.4.1.2.1.2 Installation - Emergency Shutdown Thu 2/12/09 Tue 4/21/09 0.01 75.97 days 0.6 3795.76 196 1.4.1.2.1.2.1 PVC conduit and boxes Thu 2/12/09 Thu 2/12/09 I 0.01 0.76 days 12 mtr 0.01 63.96 197 1.4.1.2.1.2.2 Instrument cables Sat 4/11/09 Tue 4/21/09 I 0 12.21 days 1944 mtr 0.59 3731.8 198 1.4.1.3 Operation Floor Sat 11/22/08 Sat 5/30/09 0.13 209.84 days 2.05 12881.33 199 1.4.1.3.1 Air Compressed System - Piping Tue 4/14/09 Wed 4/22/09 0 9 days 0.05 333.13 200 1.4.1.3.1.1 2" Equal Tee Tue 4/14/09 Sat 4/18/09 P 0 4 days 11 nos 0.03 213.2 201 1.4.1.3.1.2 2" Plug Sat 4/18/09 Sat 4/18/09 P 0 1 day 9 nos 0.01 79.95 202 1.4.1.3.1.3 1/2" Ball valve Sat 4/18/09 Sun 4/19/09 P 0 1 day 2 nos 0 10.66 203 1.4.1.3.1.4 2" x 1" Reducer Sun 4/19/09 Mon 4/20/09 P 0 1 day 2 nos 0 10.66 204 1.4.1.3.1.5 1" x 1/2" Reducer Mon 4/20/09 Tue 4/21/09 P 0 1 day 2 nos 0 10.66 205 1.4.1.3.1.6 1/2" Nipple Tue 4/21/09 Wed 4/22/09 P 0 1 day 2 nos 0 8 206 1.4.1.3.2 Installation - Electrical Sat 11/22/08 Sat 5/30/09 0.13 209.84 days 1.99 12548.21 207 1.4.1.3.2.1 Installation - Lighting System Sat 11/22/08 Tue 12/2/08 0.08 12.4 days 0.08 501.9 208 1.4.1.3.2.1.1 Rigid Steel Conduit Sat 11/22/08 Sat 11/22/08 E 0.03 0.71 days 26 mtr 0.03 157.5 209 1.4.1.3.2.1.2 Single Core Wires Mon 12/1/08 Tue 12/2/08 E 0.03 0.92 days 300 mtr 0.03 188.82 210 1.4.1.3.2.1.3 High Bay Lighting fixtures including supports and fixings Tue 12/2/08 Tue 12/2/08 E 0.02 0.77 days 6 nos. 0.02 155.58 211 1.4.1.3.2.2 Installation - Crane Bus Bars Thu 12/4/08 Wed 5/13/09 0.03 176.84 days 0.9 5665.31 212 1.4.1.3.2.2.1 Crane Bus Bar Supports installation Thu 12/4/08 Tue 12/9/08 E 0.02 4.84 days 16 nos. 0.02 96.37 213 1.4.1.3.2.2.2 Feed Junction Box Installation Tue 12/9/08 Wed 12/10/08 E 0.01 1.38 days 4 nos. 0.01 70.89 214 1.4.1.3.2.2.3 Disconnect Switch Instalation Wed 12/10/08 Wed 12/10/08 E 0 0.46 days 1 nos. 0 17.32 215 1.4.1.3.2.2.4 Interconnection cable, cableways installation Wed 5/6/09 Thu 5/7/09 E 0 1 day 5 nos. 0.02 133.25 216 1.4.1.3.2.2.5 Crane Power Feeder Cable Thu 5/7/09 Tue 5/12/09 E 0 5.2 days 682 mtr 0.82 5172.5 217 1.4.1.3.2.2.6 Cable Termination Tue 5/12/09 Wed 5/13/09 E 0 2.01 days 10 nos. 0.03 174.98 218 1.4.1.3.2.3 Installation - Socket / Welding Outlet Tue 12/9/08 Wed 2/4/09 0.02 63.41 days 0.06 381.71 219 1.4.1.3.2.3.1 Rigid Steel Conduit Tue 12/9/08 Wed 12/10/08 E 0.01 0.87 days 15 mtr 0.01 78.35 220 1.4.1.3.2.3.2 Single Core Wires Mon 2/2/09 Tue 2/3/09 E 0 0.46 days 50 mtr 0 27.82 221 1.4.1.3.2.3.3 Junction Box Tue 2/3/09 Tue 2/3/09 E 0 0.91 days 2 nos. 0 23.98 222 1.4.1.3.2.3.4 Welding outlet / Socket Outlet Tue 2/3/09 Wed 2/4/09 E 0 0.65 days 2 nos. 0 27.05 223 1.4.1.3.2.3.5 Socket Feeder cables Wed 2/4/09 Wed 2/4/09 E 0 0.52 days 60 mtr 0.04 224.5 224 1.4.1.3.2.4 Installation - Local Junction Box Mon 4/6/09 Sat 5/30/09 0 59.84 days 0.95 5999.29 225 1.4.1.3.2.4.1 Rigid Steel Conduit Mon 4/6/09 Mon 4/13/09 E 0 7.62 days 140 mtr 0.12 744.6 226 1.4.1.3.2.4.2 Junction Box Mon 4/13/09 Thu 4/16/09 E 0 3.81 days 28 nos. 0.06 372.3 227 1.4.1.3.2.4.3 Feeder cables Thu 4/16/09 Thu 4/23/09 E 0 8.72 days 1020 mtr 0.53 3358.01 228 1.4.1.3.2.4.4 Cable Termination Wed 5/13/09 Sat 5/30/09 E 0 18 days 88 nos. 0.24 1524.38 229 1.4.2 Pot 44 Sat 12/27/08 Tue 5/12/09 0.81 150.59 days 2.18 13753.32 230 1.4.2.1 SLI DELIVERABLES Fri 1/23/09 Fri 1/23/09 0 0 days 0 0 231 1.4.2.1.1 POT 44 Area Available for MPEI Construction Fri 1/23/09 Fri 1/23/09 0 0 days 0 0 232 1.4.2.2 Basement Floor Sat 12/27/08 Mon 4/27/09 0.78 134.2 days 1.37 8641.5 233 1.4.2.2.1 Installation - Electrical Sat 12/27/08 Mon 4/27/09 0.78 134.2 days 1.37 8641.5 11/22 11/22 Electrical rooms not ready Material by Astaldi Material by SNC No cable and cable trays junction box details to be submitted Material not yet approved by SNC 1/23 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 4 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 5. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 234 1.4.2.2.1.1 Installation - Lighting System Sat 12/27/08 Sun 2/15/09 0.77 55.26 days 0.77 4827.09 235 1.4.2.2.1.1.1 PVC conduit and boxes Sat 12/27/08 Mon 12/29/08 E 0.05 2.33 days 95 mtr 0.05 303.81 236 1.4.2.2.1.1.2 Single Core Wires Sat 1/24/09 Sat 1/24/09 E 0.03 1.21 days 228 mtr 0.03 168.43 237 1.4.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Wed 1/21/09 Thu 1/22/09 E 0.03 1.77 days 24 nos. 0.03 191.21 238 1.4.2.2.1.1.4 Lighting Feeder cables / wires Thu 2/5/09 Sun 2/15/09 E 0.66 9.93 days 1738 mtr 0.66 4163.64 239 1.4.2.2.1.2 Installation - Emergency Shutdown Thu 2/19/09 Mon 4/27/09 0.01 74.3 days 0.61 3814.41 240 1.4.2.2.1.2.1 PVC conduit and boxes Thu 2/19/09 Thu 2/19/09 I 0.01 0.76 days 12 mtr 0.01 63.96 241 1.4.2.2.1.2.2 Instrument cables Wed 4/15/09 Mon 4/27/09 I 0 12.21 days 1944 mtr 0.59 3731.8 242 1.4.2.2.1.2.3 Remote ASI Panel /Cabinet Mon 4/27/09 Mon 4/27/09 I 0 0.33 days 1 mtr 0 18.66 243 1.4.2.3 Operation Floor Sat 12/27/08 Tue 5/12/09 0.03 150.59 days 0.81 5111.82 244 1.4.2.3.1 Air Compressed System - Piping Sat 4/18/09 Wed 5/6/09 0 21 days 0.05 333.13 245 1.4.2.3.1.1 2" Equal Tee Sat 4/18/09 Tue 4/21/09 P 0 4 days 11 nos 0.03 213.2 246 1.4.2.3.1.2 2" Plug Sun 5/3/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95 247 1.4.2.3.1.3 1/2" Ball valve Mon 5/4/09 Mon 5/4/09 P 0 1 day 2 nos 0 10.66 248 1.4.2.3.1.4 2" x 1" Reducer Mon 5/4/09 Tue 5/5/09 P 0 1 day 2 nos 0 10.66 249 1.4.2.3.1.5 1" x 1/2" Reducer Mon 5/4/09 Tue 5/5/09 P 0 1 day 2 nos 0 10.66 250 1.4.2.3.1.6 1/2" Nipple Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 8 251 1.4.2.3.2 Installation - Electrical Sat 12/27/08 Tue 5/12/09 0.03 150.59 days 0.76 4778.69 252 1.4.2.3.2.1 Installation - Crane Bus Bars Sat 12/27/08 Sun 12/28/08 0.02 0.99 days 0.02 96.37 253 1.4.2.3.2.1.1 Crane Bus Bar Supports installation Sat 12/27/08 Sun 12/28/08 E 0.02 0.99 days 16 nos. 0.02 96.37 254 1.4.2.3.2.2 Installation - Socket / Welding Outlet Sat 1/24/09 Wed 2/4/09 0.02 14.14 days 0.06 381.71 255 1.4.2.3.2.2.1 Rigid Steel Conduit Sat 1/24/09 Tue 1/27/09 E 0.01 5 days 15 mtr 0.01 78.35 256 1.4.2.3.2.2.2 Single Core Wires Tue 1/27/09 Wed 1/28/09 E 0 0.84 days 50 mtr 0 27.82 257 1.4.2.3.2.2.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.72 days 2 nos. 0 23.98 258 1.4.2.3.2.2.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 27.05 259 1.4.2.3.2.2.5 Socket Feeder cables Wed 2/4/09 Wed 2/4/09 E 0 0.29 days 60 mtr 0.04 224.5 260 1.4.2.3.2.3 Installation - Local Junction Box Mon 4/13/09 Tue 5/12/09 0 32.53 days 0.68 4300.62 261 1.4.2.3.2.3.1 Rigid Steel Conduit Mon 4/13/09 Sat 4/18/09 E 0 6 days 110 mtr 0.09 586.3 262 1.4.2.3.2.3.2 Junction Box Sat 4/18/09 Tue 4/21/09 E 0 3.81 days 28 nos. 0.06 372.3 263 1.4.2.3.2.3.3 Feeder cables Tue 4/21/09 Sun 4/26/09 E 0 4.72 days 550 mtr 0.29 1817.64 264 1.4.2.3.2.3.4 Cable Termination Sun 4/26/09 Tue 5/12/09 E 0 18 days 88 nos. 0.24 1524.38 265 1.4.3 Pot 66 Sat 1/31/09 Thu 5/28/09 0.79 130.65 days 2.84 17917.57 266 1.4.3.1 SLI DELIVERABLES Sat 1/31/09 Sat 1/31/09 0 0 days 0 0 267 1.4.3.1.1 POT 66 Area Available for MPEI Construction Sat 1/31/09 Sat 1/31/09 0 0 days 0 0 268 1.4.3.2 Basement Floor Sun 3/1/09 Thu 5/7/09 0.71 75.42 days 1.31 8282.39 269 1.4.3.2.1 Installation - Electrical Sun 3/1/09 Thu 5/7/09 0.71 75.42 days 1.31 8282.39 270 1.4.3.2.1.1 Installation - Lighting System Sat 3/14/09 Wed 4/22/09 0.71 43.74 days 0.71 4486.63 271 1.4.3.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.38 days 558 mtr 0.28 1777.29 272 1.4.3.2.1.1.2 Single Core Wires Sun 4/19/09 Sun 4/19/09 E 0.02 0.96 days 135 mtr 0.02 101.06 273 1.4.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 4/16/09 Sat 4/18/09 E 0.02 0.91 days 12 nos. 0.02 99.43 274 1.4.3.2.1.1.4 Lighting Feeder cables / wires Tue 4/14/09 Wed 4/22/09 E 0.4 7.99 days 1050 mtr 0.4 2508.86 275 1.4.3.2.1.2 Installation - Emergency Shutdown Sun 3/1/09 Thu 5/7/09 0 75.42 days 0.6 3795.76 276 1.4.3.2.1.2.1 PVC conduit and boxes Sun 3/1/09 Mon 3/2/09 I 0 0.76 days 12 mtr 0.01 63.96 277 1.4.3.2.1.2.2 Instrument cables Mon 4/27/09 Thu 5/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8 278 1.4.3.3 Operation Floor Tue 3/24/09 Thu 5/28/09 0.08 72.53 days 1.53 9635.17 279 1.4.3.3.1 Air Compressed System - Piping Tue 4/21/09 Thu 5/14/09 0 26 days 0.05 333.13 280 1.4.3.3.1.1 2" Equal Tee Tue 4/21/09 Sat 4/25/09 P 0 4 days 11 nos 0.03 213.2 281 1.4.3.3.1.2 2" Plug Mon 5/11/09 Tue 5/12/09 P 0 1 day 9 nos 0.01 79.95 282 1.4.3.3.1.3 1/2" Ball valve Tue 5/12/09 Tue 5/12/09 P 0 1 day 2 nos 0 10.66 283 1.4.3.3.1.4 2" x 1" Reducer Tue 5/12/09 Wed 5/13/09 P 0 1 day 2 nos 0 10.66 284 1.4.3.3.1.5 1" x 1/2" Reducer Tue 5/12/09 Wed 5/13/09 P 0 1 day 2 nos 0 10.66 285 1.4.3.3.1.6 1/2" Nipple Wed 5/13/09 Thu 5/14/09 P 0 1 day 2 nos 0 8 286 1.4.3.3.2 Installation - Electrical Tue 3/24/09 Thu 5/28/09 0.08 72.53 days 1.48 9302.05 287 1.4.3.3.2.1 Installation - Lighting System Tue 3/24/09 Tue 4/21/09 0.08 31.28 days 0.14 887.79 288 1.4.3.3.2.1.1 Rigid Steel Conduit Tue 3/24/09 Tue 3/24/09 E 0.03 0.7 days 26 mtr 0.03 157.5 289 1.4.3.3.2.1.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0.03 1.04 days 300 mtr 0.03 188.82 290 1.4.3.3.2.1.3 High Bay Lighting fixtures including supports and fixings Mon 4/20/09 Mon 4/20/09 E 0.02 0.84 days 6 nos. 0.02 155.58 291 1.4.3.3.2.1.4 Lighting Feeder cables / wires Mon 4/20/09 Tue 4/21/09 E 0 0.7 days 98 mtr 0.06 385.89 On going On going Material by Astaldi Material by SNC Material by SNC No manlift available 1/31 Material by Astaldi Material by SNC Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 5 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 6. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 292 1.4.3.3.2.2 Installation - Blower and Transformer Feeder Sat 4/18/09 Thu 4/23/09 0 5.85 days 0.43 2725.18 293 1.4.3.3.2.2.1 Blower Feeder, Transformer Feeder Sat 4/18/09 Thu 4/23/09 E 0 5.85 days 700 mtr 0.43 2725.18 294 1.4.3.3.2.3 Installation - Local Junction Box Sat 4/18/09 Thu 5/28/09 0 44.53 days 0.9 5689.08 295 1.4.3.3.2.3.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/25/09 E 0 7.08 days 130 mtr 0.11 691.83 296 1.4.3.3.2.3.2 Junction Box Sat 4/25/09 Tue 4/28/09 E 0 3.54 days 26 nos. 0.05 345.92 297 1.4.3.3.2.3.3 Feeder cables Tue 4/28/09 Tue 5/5/09 E 0 8.12 days 948 mtr 0.5 3126.95 298 1.4.3.3.2.3.4 Cable Termination Tue 5/12/09 Thu 5/28/09 E 0 18 days 88 nos. 0.24 1524.38 299 1.4.4 Pot 88 Sun 1/25/09 Sun 6/14/09 0.81 155.19 days 3.49 21966.37 300 1.4.4.1 SLI DELIVERABLES Thu 2/5/09 Thu 2/5/09 0 0 days 0 0 301 1.4.4.1.1 POT 88 Area Available for MPEI Construction Thu 2/5/09 Thu 2/5/09 0 0 days 0 0 302 1.4.4.2 Basement Floor Sat 3/14/09 Tue 5/19/09 0.71 74.18 days 1.32 8308.64 303 1.4.4.2.1 Installation - Electrical Sat 3/14/09 Tue 5/19/09 0.71 74.18 days 1.32 8308.64 304 1.4.4.2.1.1 Installation - Lighting System Sat 3/14/09 Sat 3/28/09 0.71 16.45 days 0.71 4494.23 305 1.4.4.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.45 days 560 mtr 0.28 1784.88 306 1.4.4.2.1.1.2 Single Core Wires Sun 3/15/09 Sun 3/15/09 E 0.02 0.96 days 137 mtr 0.02 101.06 307 1.4.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Sun 3/22/09 Sun 3/22/09 E 0.02 0.91 days 12 nos. 0.02 99.43 308 1.4.4.2.1.1.4 Lighting Feeder cables / wires Sat 3/21/09 Sat 3/28/09 E 0.4 7.99 days 1050 mtr 0.4 2508.86 309 1.4.4.2.1.2 Installation - Emergency Shutdown Thu 4/30/09 Tue 5/19/09 0 21.22 days 0.61 3814.41 310 1.4.4.2.1.2.1 PVC conduit and boxes Thu 4/30/09 Thu 4/30/09 I 0 0.76 days 12 mtr 0.01 63.96 311 1.4.4.2.1.2.2 Instrument cables Thu 5/7/09 Tue 5/19/09 I 0 12.21 days 1944 mtr 0.59 3731.8 312 1.4.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 5/19/09 Tue 5/19/09 I 0 0.33 days 1 mtr 0 18.66 313 1.4.4.3 Operation Floor Sun 1/25/09 Sun 6/14/09 0.09 155.19 days 2.17 13657.73 314 1.4.4.3.1 Air Compressed System - Piping Sat 4/25/09 Sat 5/16/09 0 23 days 0.05 333.13 315 1.4.4.3.1.1 2" Equal Tee Sat 4/25/09 Tue 4/28/09 P 0 4 days 11 nos 0.03 213.2 316 1.4.4.3.1.2 2" Plug Tue 4/28/09 Wed 4/29/09 P 0 1 day 9 nos 0.01 79.95 317 1.4.4.3.1.3 1/2" Ball valve Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66 318 1.4.4.3.1.4 2" x 1" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66 319 1.4.4.3.1.5 1" x 1/2" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66 320 1.4.4.3.1.6 1/2" Nipple Thu 5/14/09 Sat 5/16/09 P 0 1 day 2 nos 0 8 321 1.4.4.3.2 Installation - Electrical Sun 1/25/09 Sun 6/14/09 0.09 155.19 days 2.12 13324.6 322 1.4.4.3.2.1 Installation - Lighting System Mon 3/23/09 Tue 4/21/09 0.08 33.27 days 0.14 887.79 323 1.4.4.3.2.1.1 Rigid Steel Conduit Mon 3/23/09 Mon 3/23/09 E 0.03 0.7 days 25 mtr 0.03 157.5 324 1.4.4.3.2.1.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0.03 1.04 days 300 mtr 0.03 188.82 325 1.4.4.3.2.1.3 High Bay Lighting fixtures including supports and fixings Mon 4/20/09 Tue 4/21/09 E 0.02 0.84 days 6 nos. 0.02 155.58 326 1.4.4.3.2.1.4 Lighting Feeder cables / wires Tue 4/21/09 Tue 4/21/09 E 0 0.7 days 100 mtr 0.06 385.89 327 1.4.4.3.2.2 Installation - Cable Tray Sun 4/19/09 Wed 4/29/09 0 12.65 days 0.06 382.29 328 1.4.4.3.2.2.1 Cantilever supports installation Sun 4/19/09 Sun 4/19/09 E 0 0.35 days 32 nos. 0.01 38.24 329 1.4.4.3.2.2.2 Cable Tray installation Tue 4/28/09 Wed 4/29/09 E 0 1.5 days 189 mtr 0.05 344.05 330 1.4.4.3.2.3 Installation - Crane Bus Bars Sun 1/25/09 Thu 5/14/09 0.02 121.87 days 0.71 4488.71 331 1.4.4.3.2.3.1 Crane Bus Bar Supports installation Sun 1/25/09 Mon 1/26/09 E 0.02 1.94 days 16 nos. 0.02 96.37 332 1.4.4.3.2.3.2 Feed Junction Box Installation Mon 1/26/09 Mon 1/26/09 E 0 0.33 days 1 nos. 0 17.59 333 1.4.4.3.2.3.3 Disconnect Switch Instalation Tue 5/5/09 Tue 5/5/09 E 0 0.5 days 1 nos. 0 17.32 334 1.4.4.3.2.3.4 Interconnection cable, cableways installation Tue 5/5/09 Wed 5/6/09 E 0 1 day 5 nos. 0.02 133.25 335 1.4.4.3.2.3.5 Crane Power Feeder Cable Wed 5/6/09 Sun 5/10/09 E 0 4.16 days 550 mtr 0.66 4138 336 1.4.4.3.2.3.6 Cable Termination Wed 5/13/09 Thu 5/14/09 E 0 0.99 days 5 nos. 0.01 86.19 337 1.4.4.3.2.4 Installation - Blower and Transformer Feeder Thu 4/23/09 Tue 4/28/09 0 5.85 days 0.43 2725.18 338 1.4.4.3.2.4.1 Blower Feeder, Transformer Feeder Thu 4/23/09 Tue 4/28/09 E 0 5.85 days 700 mtr 0.43 2725.18 339 1.4.4.3.2.5 Installation - Socket / Welding Outlet Sun 4/19/09 Tue 4/21/09 0 2.51 days 0.06 381.71 340 1.4.4.3.2.5.1 Rigid Steel Conduit Sun 4/19/09 Sun 4/19/09 E 0 0.84 days 15 mtr 0.01 78.35 341 1.4.4.3.2.5.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0 0.36 days 50 mtr 0 27.82 342 1.4.4.3.2.5.3 Junction Box Mon 4/20/09 Mon 4/20/09 E 0 0.5 days 2 nos. 0 23.98 343 1.4.4.3.2.5.4 Welding outlet / Socket Outlet Mon 4/20/09 Mon 4/20/09 E 0 0.29 days 2 nos. 0 27.05 344 1.4.4.3.2.5.5 Socket Feeder cables Mon 4/20/09 Tue 4/21/09 E 0 0.52 days 60 mtr 0.04 224.5 345 1.4.4.3.2.6 Installation - Local Junction Box Sat 4/18/09 Sun 6/14/09 0 62.53 days 0.71 4458.92 346 1.4.4.3.2.6.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/25/09 E 0 7.62 days 140 mtr 0.12 744.6 347 1.4.4.3.2.6.2 Junction Box Sat 4/25/09 Tue 4/28/09 E 0 3.81 days 28 nos. 0.06 372.3 348 1.4.4.3.2.6.3 Feeder cables Wed 4/29/09 Mon 5/4/09 E 0 4.72 days 550 mtr 0.29 1817.64 349 1.4.4.3.2.6.4 Cable Termination Thu 5/28/09 Sun 6/14/09 E 0 18 days 88 nos. 0.24 1524.38 350 1.5 Construction - South Qtr. Passageway 503-22 Sat 2/28/09 Wed 5/13/09 0 83.5 days 2.69 16954.65 Electrical room not ready Material not approved 2/5 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 6 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 7. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 351 1.5.1 SLI DELIVERABLES Sat 2/28/09 Sat 2/28/09 0 0 days 0 0 352 1.5.1.1 1st- QTR Passageway Available for MPEI Construction Sat 2/28/09 Sat 2/28/09 0 0 days 0 0 353 1.5.2 Operation Floor Sun 4/5/09 Wed 5/13/09 0 43.5 days 2.69 16954.65 354 1.5.2.1 Installation - Electrical (Operation Floor) Sun 4/5/09 Wed 5/13/09 0 43.5 days 2.69 16954.65 355 1.5.2.1.1 Installation - Lighting System Wed 4/8/09 Sun 5/3/09 0 26.19 days 0.16 1030.61 356 1.5.2.1.1.1 High Bay Lighting fixtures including supports and fixings Wed 4/8/09 Sat 4/11/09 E 0 2 days 9 nos. 0.04 234.52 357 1.5.2.1.1.2 Rigid Steel Conduit Sat 4/11/09 Mon 4/13/09 E 0 2.76 days 55 mtr 0.05 330.99 358 1.5.2.1.1.3 Single Core Wires Mon 4/13/09 Tue 4/14/09 E 0 1.66 days 150 mtr 0.02 97.33 359 1.5.2.1.1.4 Lighting Feeder cables / wires Sat 5/2/09 Sun 5/3/09 E 0 0.69 days 90 mtr 0.06 367.77 360 1.5.2.1.2 Installation - Cable Tray Sun 4/5/09 Sat 5/2/09 0 30.5 days 0.55 3457.17 361 1.5.2.1.2.1 Cantilever supports installation Sun 4/5/09 Sat 4/11/09 E 0 6.5 days 265 nos. 0.09 577.64 362 1.5.2.1.2.2 Cable tray installation Sat 4/11/09 Sat 5/2/09 E 0 24 days 1591 mtr 0.46 2879.53 363 1.5.2.1.3 Installation - Crane Bus Bars Sat 4/11/09 Wed 5/13/09 0 37 days 1.98 12466.87 364 1.5.2.1.3.1 Feed Junction Box Installation Sat 4/11/09 Tue 4/14/09 E 0 4 days 8 nos. 0.02 138.58 365 1.5.2.1.3.2 Disconnect Switch Instalation Tue 4/14/09 Wed 4/15/09 E 0 1 day 4 nos. 0.01 69.29 366 1.5.2.1.3.3 Interconnection cable, cableways installation Wed 4/15/09 Tue 5/12/09 E 0 30 days 600 mtr 1.9 11992.5 367 1.5.2.1.3.4 Cable termination Tue 5/12/09 Wed 5/13/09 E 0 2 days 15 nos 0.04 266.5 368 1.6 Construction - Potroom No. 1 (501-12B) Fri 3/6/09 Thu 8/13/09 0 178.05 days 11.32 71304.69 369 1.6.1 Pot 110 Fri 3/6/09 Wed 6/3/09 0 99.05 days 2.99 18863.48 370 4.7.1.1 SLI DELIVERABLES Fri 3/6/09 Fri 3/6/09 0 0 days 0 0 371 4.7.1.1.1 POT 110 Area Available for MPEI Construction Fri 3/6/09 Fri 3/6/09 0 0 days 0 0 372 1.6.1.2 Basement Floor Sat 4/25/09 Sat 5/30/09 0 39.22 days 1.12 7043.12 373 1.6.1.2.1 Installation - Electrical Sat 4/25/09 Sat 5/30/09 0 39.22 days 1.12 7043.12 374 1.6.1.2.1.1 Installation - Lighting System Thu 5/7/09 Mon 5/18/09 0 12.7 days 0.51 3228.7 375 1.6.1.2.1.1.1 PVC conduit and boxes Thu 5/7/09 Sat 5/9/09 E 0 1.96 days 66 mtr 0.03 212.67 376 1.6.1.2.1.1.2 Single Core Wires Sat 5/9/09 Sun 5/10/09 E 0 1.12 days 156 mtr 0.02 117.9 377 1.6.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 5/7/09 Sat 5/9/09 E 0 1.12 days 15 nos. 0.02 122.38 378 1.6.1.2.1.1.4 Lighting Feeder cables / wires Mon 5/11/09 Mon 5/18/09 E 0 8.84 days 1167 mtr 0.44 2775.76 379 1.6.1.2.1.2 Installation - Emergency Shutdown Sat 4/25/09 Sat 5/30/09 0 39.22 days 0.61 3814.41 380 1.6.1.2.1.2.1 PVC conduit and boxes Sat 4/25/09 Sat 4/25/09 I 0 0.76 days 12 mtr 0.01 63.96 381 1.6.1.2.1.2.2 Instrument cables Mon 5/18/09 Sat 5/30/09 I 0 12.21 days 1944 mtr 0.59 3731.8 382 1.6.1.2.1.2.3 Remote ASI Panel /Cabinet Sat 5/30/09 Sat 5/30/09 I 0 0.33 days 1 mtr 0 18.66 383 1.6.1.3 Operation Floor Sat 4/11/09 Wed 6/3/09 0 59.05 days 1.88 11820.37 384 1.6.1.3.1 Installation - Electrical Sat 4/11/09 Wed 6/3/09 0 59.05 days 1.82 11487.24 385 1.6.1.3.1.1 Installation - Lighting System Sat 4/18/09 Mon 5/4/09 0 17.64 days 0.37 2341.92 386 1.6.1.3.1.1.1 Rigid Steel Conduit Sat 4/18/09 Sun 4/19/09 E 0 1.4 days 52 mtr 0.05 315 387 1.6.1.3.1.1.2 Single Core Wires Sun 4/19/09 Thu 4/23/09 E 0 5.04 days 1410 mtr 0.15 915.03 388 1.6.1.3.1.1.3 Junction Box Thu 4/23/09 Thu 4/23/09 E 0 0.22 days 2 nos. 0.01 36.35 389 1.6.1.3.1.1.4 High Bay Lighting fixtures including supports and fixings Thu 4/23/09 Sun 4/26/09 E 0 1.64 days 12 nos. 0.05 303.76 390 1.6.1.3.1.1.5 Lighting Feeder cables / wires Sun 5/3/09 Mon 5/4/09 E 0 1.4 days 196 mtr 0.12 771.78 391 1.6.1.3.1.2 Installation - Cable Tray Sat 4/11/09 Mon 5/4/09 0 25.35 days 0.02 110.86 392 1.6.1.3.1.2.1 Cantilever supports installation Sat 4/11/09 Sun 4/12/09 E 0 0.07 days 9 nos. 0 7.65 393 1.6.1.3.1.2.2 Cable Tray installation Mon 5/4/09 Mon 5/4/09 E 0 0.45 days 55 mtr 0.02 103.22 394 1.6.1.3.1.3 Installation - Blower and Transformer Feeder Tue 4/28/09 Mon 5/4/09 0 5.85 days 0.42 2653.46 395 1.6.1.3.1.3.1 Blower Feeder, Transformer Feeder Tue 4/28/09 Mon 5/4/09 E 0 5.85 days 700 mtr 0.42 2653.46 396 1.6.1.3.1.4 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 2.51 days 0.06 381.71 397 1.6.1.3.1.4.1 Rigid Steel Conduit Thu 4/23/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35 398 1.6.1.3.1.4.2 Junction Box Thu 4/23/09 Sat 4/25/09 E 0 0.5 days 2 nos. 0 23.98 399 1.6.1.3.1.4.3 Single Core Wires Sat 4/25/09 Sat 4/25/09 E 0 0.36 days 50 mtr 0 27.82 400 1.6.1.3.1.4.4 Welding outlet / Socket Outlet Sat 4/25/09 Sat 4/25/09 E 0 0.29 days 2 nos. 0 27.05 401 1.6.1.3.1.4.5 Socket Feeder cables Sat 4/25/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5 402 1.6.1.3.1.5 Installation - Local Junction Box Thu 4/30/09 Wed 6/3/09 0 38.15 days 0.95 5999.29 403 1.6.1.3.1.5.1 Rigid Steel Conduit Thu 4/30/09 Thu 5/7/09 E 0 7.62 days 140 mtr 0.12 744.6 404 1.6.1.3.1.5.2 Junction Box Thu 5/7/09 Sun 5/10/09 E 0 3.81 days 28 nos. 0.06 372.3 405 1.6.1.3.1.5.3 Feeder cables Sun 5/10/09 Mon 5/18/09 E 0 8.72 days 1020 mtr 0.53 3358.01 406 1.6.1.3.1.5.4 Cable Termination Mon 5/18/09 Wed 6/3/09 E 0 18 days 88 nos. 0.24 1524.38 407 1.6.1.3.2 Air Compressed System - Piping Sat 4/25/09 Thu 4/30/09 0 6 days 0.05 333.13 408 1.6.1.3.2.1 2" Equal Tee Sat 4/25/09 Tue 4/28/09 P 0 4 days 11 nos 0.03 213.2 409 1.6.1.3.2.2 2" Plug Sun 4/26/09 Mon 4/27/09 P 0 1 day 9 nos 0.01 79.95 410 1.6.1.3.2.3 1/2" Ball valve Mon 4/27/09 Tue 4/28/09 P 0 1 day 2 nos 0 10.66 2/28 3/6 3/6 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 7 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 8. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 411 1.6.1.3.2.4 2" x 1" Reducer Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 10.66 412 1.6.1.3.2.5 1" x 1/2" Reducer Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 10.66 413 1.6.1.3.2.6 1/2" Nipple Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 8 414 1.6.2 Pot 132 Tue 3/31/09 Sat 6/20/09 0 89.73 days 3.95 24908.58 415 1.6.2.1 SLI DELIVERABLES Tue 3/31/09 Tue 3/31/09 0 0 days 0 0 416 1.6.2.1.1 POT 132 Area Available for MPEI Construction Tue 3/31/09 Tue 3/31/09 0 0 days 0 0 417 1.6.2.2 Basement Floor Sat 4/25/09 Wed 6/3/09 0 44.13 days 1.25 7885.02 418 1.6.2.2.1 Installation - Electrical Sat 4/25/09 Wed 6/3/09 0 44.13 days 1.25 7885.02 419 1.6.2.2.1.1 Installation - Lighting System Sat 5/9/09 Sat 5/23/09 0 14.96 days 0.65 4089.26 420 1.6.2.2.1.1.1 PVC conduit and boxes Sat 5/9/09 Mon 5/11/09 E 0 2.45 days 84 mtr 0.04 265.83 421 1.6.2.2.1.1.2 Single Core Wires Mon 5/11/09 Tue 5/12/09 E 0 1.4 days 198 mtr 0.02 147.37 422 1.6.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Sun 5/10/09 Mon 5/11/09 E 0 1.4 days 19 nos. 0.02 152.97 423 1.6.2.2.1.1.4 Lighting Feeder cables / wires Tue 5/12/09 Sat 5/23/09 E 0 11.22 days 1478 mtr 0.56 3523.08 424 1.6.2.2.1.2 Installation - Emergency Shutdown Sat 4/25/09 Wed 6/3/09 0 44.13 days 0.6 3795.76 425 1.6.2.2.1.2.1 PVC conduit and boxes Sat 4/25/09 Tue 4/28/09 I 0 4 days 12 mtr 0.01 63.96 426 1.6.2.2.1.2.2 Instrument cables Mon 5/25/09 Wed 6/3/09 I 0 11 days 1944 mtr 0.59 3731.8 427 1.6.2.3 Operation Floor Sun 4/12/09 Sat 6/20/09 0 76.98 days 2.7 17023.57 428 1.6.2.3.1 Installation - Electrical Sun 4/12/09 Sat 6/20/09 0 76.98 days 2.65 16690.44 429 1.6.2.3.1.1 Installation - Lighting System Sun 4/19/09 Mon 5/4/09 0 16.94 days 0.14 887.79 430 1.6.2.3.1.1.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 0.7 days 25 mtr 0.03 157.5 431 1.6.2.3.1.1.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.04 days 300 mtr 0.03 188.82 432 1.6.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 4/21/09 Tue 4/21/09 E 0 0.84 days 6 nos. 0.02 155.58 433 1.6.2.3.1.1.4 Lighting Feeder cables / wires Mon 5/4/09 Mon 5/4/09 E 0 0.7 days 100 mtr 0.06 385.89 434 1.6.2.3.1.2 Installation - Cable Tray Sun 4/12/09 Sun 5/10/09 0 31.68 days 0.02 110.86 435 1.6.2.3.1.2.1 Cantilever supports installation Sun 4/12/09 Sun 4/12/09 E 0 0.07 days 9 nos. 0 7.65 436 1.6.2.3.1.2.2 Cable Tray installation Sat 5/9/09 Sun 5/10/09 E 0 1 day 55 mtr 0.02 103.22 437 1.6.2.3.1.3 Installation - Crane Bus Bars Sun 5/3/09 Mon 5/11/09 0 9.19 days 1.06 6657.33 438 1.6.2.3.1.3.1 Crane Bus Bar Supports installation Sun 5/3/09 Sun 5/3/09 E 0 0.96 days 16 nos. 0.02 96.37 439 1.6.2.3.1.3.2 Feed Junction Box Installation Sun 5/3/09 Mon 5/4/09 E 0 0.33 days 1 nos. 0 17.59 440 1.6.2.3.1.3.3 Disconnect Switch Instalation Mon 5/4/09 Mon 5/4/09 E 0 0.5 days 1 nos. 0 17.32 441 1.6.2.3.1.3.4 Interconnection cable, cableways installation Mon 5/4/09 Tue 5/5/09 E 0 1 day 5 nos. 0.03 159.9 442 1.6.2.3.1.3.5 Crane Power Feeder Cable Tue 5/5/09 Mon 5/11/09 E 0 6.4 days 840 mtr 1.01 6366.15 443 1.6.2.3.1.4 Installation - Blower and Transformer Feeder Mon 5/4/09 Sat 5/9/09 0 5.85 days 0.42 2653.46 444 1.6.2.3.1.4.1 Blower Feeder, Transformer Feeder Mon 5/4/09 Sat 5/9/09 E 0 5.85 days 700 mtr 0.42 2653.46 445 1.6.2.3.1.5 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 2.51 days 0.06 381.71 446 1.6.2.3.1.5.1 Rigid Steel Conduit Thu 4/23/09 Sat 4/25/09 E 0 0.84 days 15 mtr 0.01 78.35 447 1.6.2.3.1.5.2 Single Core Wires Sat 4/25/09 Sat 4/25/09 E 0 0.36 days 50 mtr 0 27.82 448 1.6.2.3.1.5.3 Junction Box Sat 4/25/09 Sun 4/26/09 E 0 0.5 days 2 nos. 0 23.98 449 1.6.2.3.1.5.4 Welding outlet / Socket Outlet Sun 4/26/09 Sun 4/26/09 E 0 0.29 days 2 nos. 0 27.05 450 1.6.2.3.1.5.5 Socket Feeder cables Sun 4/26/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5 451 1.6.2.3.1.6 Installation - Local Junction Box Thu 5/7/09 Sat 6/20/09 0 48.53 days 0.95 5999.29 452 1.6.2.3.1.6.1 Rigid Steel Conduit Thu 5/7/09 Wed 5/13/09 E 0 7.62 days 140 mtr 0.12 744.6 453 1.6.2.3.1.6.2 Junction Box Wed 5/13/09 Sun 5/17/09 E 0 3.81 days 28 nos. 0.06 372.3 454 1.6.2.3.1.6.3 Feeder cables Sun 5/17/09 Mon 5/25/09 E 0 8.72 days 1020 mtr 0.53 3358.01 455 1.6.2.3.1.6.4 Cable Termination Wed 6/3/09 Sat 6/20/09 E 0 18 days 88 nos. 0.24 1524.38 456 1.6.2.3.2 Air Compressed System - Piping Tue 4/28/09 Mon 5/4/09 0 6 days 0.05 333.13 457 1.6.2.3.2.1 2" Equal Tee Tue 4/28/09 Sat 5/2/09 P 0 4 days 11 nos 0.03 213.2 458 1.6.2.3.2.2 2" Plug Thu 4/30/09 Thu 4/30/09 P 0 1 day 9 nos 0.01 79.95 459 1.6.2.3.2.3 1/2" Ball valve Thu 4/30/09 Sat 5/2/09 P 0 1 day 2 nos 0 10.66 460 1.6.2.3.2.4 2" x 1" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66 461 1.6.2.3.2.5 1" x 1/2" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66 462 1.6.2.3.2.6 1/2" Nipple Sun 5/3/09 Mon 5/4/09 P 0 1 day 2 nos 0 8 463 1.6.3 Pot 154 Wed 4/22/09 Mon 7/20/09 0 98.19 days 2.11 13302.51 464 1.6.3.1 SLI DELIVERABLES Wed 4/22/09 Wed 4/22/09 0 0 days 0 0 465 1.6.3.1.1 POT 154 Area Available for MPEI Construction Wed 4/22/09 Wed 4/22/09 0 0 days 0 0 466 1.6.3.2 Basement Floor Tue 4/28/09 Wed 6/10/09 0 47.67 days 1.16 7280.3 467 1.6.3.2.1 Installation - Electrical Tue 4/28/09 Wed 6/10/09 0 47.67 days 1.16 7280.3 468 1.6.3.2.1.1 Installation - Lighting System Mon 5/11/09 Sun 5/31/09 0 22.03 days 0.55 3465.89 469 1.6.3.2.1.1.1 PVC conduit and boxes Mon 5/11/09 Wed 5/13/09 E 0 2.03 days 69 mtr 0.03 220.26 470 1.6.3.2.1.1.2 Single Core Wires Wed 5/13/09 Thu 5/14/09 E 0 1.2 days 167 mtr 0.02 126.32 3/31 4/22 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 8 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 9. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 471 1.6.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Mon 5/11/09 Tue 5/12/09 E 0 1.19 days 16 nos. 0.02 130.03 472 1.6.3.2.1.1.4 Lighting Feeder cables / wires Sat 5/23/09 Sun 5/31/09 E 0 9.52 days 1244 mtr 0.47 2989.28 473 1.6.3.2.1.2 Installation - Emergency Shutdown Tue 4/28/09 Wed 6/10/09 0 47.67 days 0.61 3814.41 474 1.6.3.2.1.2.1 PVC conduit and boxes Tue 4/28/09 Wed 4/29/09 I 0 0.76 days 12 mtr 0.01 63.96 475 1.6.3.2.1.2.2 Instrument cables Sun 5/31/09 Wed 6/10/09 I 0 12.21 days 1944 mtr 0.59 3731.8 476 1.6.3.2.1.2.3 Remote ASI Panel /Cabinet Wed 6/10/09 Wed 6/10/09 I 0 0.33 days 1 mtr 0 18.66 477 1.6.3.3 Operation Floor Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.96 6022.21 478 1.6.3.3.1 Installation - Electrical Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.9 5689.08 479 1.6.3.3.1.1 Installation - Local Junction Box Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.9 5689.08 480 1.6.3.3.1.1.1 Rigid Steel Conduit Thu 4/30/09 Thu 5/7/09 E 0 7.08 days 130 mtr 0.11 691.83 481 1.6.3.3.1.1.2 Junction Box Thu 5/7/09 Mon 5/11/09 E 0 3.54 days 26 nos. 0.05 345.92 482 1.6.3.3.1.1.3 Feeder cables Mon 5/11/09 Mon 5/18/09 E 0 8.12 days 948 mtr 0.5 3126.95 483 1.6.3.3.1.1.4 Cable Termination Sat 7/4/09 Mon 7/20/09 E 0 18 days 88 nos. 0.24 1524.38 484 1.6.3.3.2 Air Compressed System - Piping Sat 5/2/09 Thu 5/7/09 0 7 days 0.05 333.13 485 1.6.3.3.2.1 2" Equal Tee Sat 5/2/09 Tue 5/5/09 P 0 4 days 11 nos 0.03 213.2 486 1.6.3.3.2.2 2" Plug Mon 5/4/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95 487 1.6.3.3.2.3 1/2" Ball valve Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66 488 1.6.3.3.2.4 2" x 1" Reducer Wed 5/6/09 Thu 5/7/09 P 0 1 day 2 nos 0 10.66 489 1.6.3.3.2.5 1" x 1/2" Reducer Wed 5/6/09 Thu 5/7/09 P 0 1 day 2 nos 0 10.66 490 1.6.3.3.2.6 1/2" Nipple Thu 5/7/09 Thu 5/7/09 P 0 1 day 2 nos 0 8 491 1.6.4 Pot 176 Thu 5/14/09 Thu 8/13/09 0 101.65 days 2.26 14230.11 492 1.6.4.1 SLI DELIVERABLES Thu 5/14/09 Thu 5/14/09 0 0 days 0 0 493 1.6.4.1.1 POT 176 Area Available for MPEI Construction Thu 5/14/09 Thu 5/14/09 0 0 days 0 0 494 1.6.4.2 Basement Floor Thu 5/14/09 Wed 6/17/09 0 37.36 days 1.28 8072.21 495 1.6.4.2.1 Installation - Electrical Thu 5/14/09 Wed 6/17/09 0 37.36 days 1.28 8072.21 496 1.6.4.2.1.1 Installation - Lighting System Mon 5/18/09 Tue 6/2/09 0 17.21 days 0.68 4276.45 497 1.6.4.2.1.1.1 PVC conduit and boxes Mon 5/18/09 Wed 5/20/09 E 0 2.59 days 88 mtr 0.04 281.02 498 1.6.4.2.1.1.2 Single Core Wires Wed 5/20/09 Thu 5/21/09 E 0 1.44 days 205 mtr 0.02 151.59 499 1.6.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Mon 5/18/09 Tue 5/19/09 E 0 1.47 days 20 nos. 0.03 160.62 500 1.6.4.2.1.1.4 Lighting Feeder cables / wires Sat 5/23/09 Tue 6/2/09 E 0 11.73 days 1544 mtr 0.58 3683.22 501 1.6.4.2.1.2 Installation - Emergency Shutdown Thu 5/14/09 Wed 6/17/09 0 37.36 days 0.6 3795.76 502 1.6.4.2.1.2.1 PVC conduit and boxes Thu 5/14/09 Thu 5/14/09 I 0 0.76 days 12 mtr 0.01 63.96 503 1.6.4.2.1.2.2 Instrument cables Sat 6/6/09 Wed 6/17/09 I 0 12.21 days 1944 mtr 0.59 3731.8 504 1.6.4.3 Operation Floor Thu 5/14/09 Thu 8/13/09 0 101.65 days 0.98 6157.91 505 1.6.4.3.1 Installation - Electrical Thu 5/14/09 Thu 8/13/09 0 101.65 days 0.92 5824.78 506 1.6.4.3.1.1 Installation - Lighting System Sat 5/23/09 Tue 5/26/09 0 3.28 days 0.14 887.79 507 1.6.4.3.1.1.1 Rigid Steel Conduit Sat 5/23/09 Sun 5/24/09 E 0 0.7 days 26 mtr 0.03 157.5 508 1.6.4.3.1.1.2 Single Core Wires Sun 5/24/09 Mon 5/25/09 E 0 1.04 days 300 mtr 0.03 188.82 509 1.6.4.3.1.1.3 High Bay Lighting fixtures including supports and fixings Mon 5/25/09 Mon 5/25/09 E 0 0.84 days 6 nos. 0.02 155.58 510 1.6.4.3.1.1.4 Lighting Feeder cables / wires Mon 5/25/09 Tue 5/26/09 E 0 0.7 days 98 mtr 0.06 385.89 511 1.6.4.3.1.2 Installation - Crane Bus Bars Thu 5/14/09 Thu 5/14/09 0 0.96 days 0.02 96.37 512 1.6.4.3.1.2.1 Crane Bus Bar Supports installation Thu 5/14/09 Thu 5/14/09 E 0 0.96 days 16 nos. 0.02 96.37 513 1.6.4.3.1.3 Installation - Socket / Welding Outlet Thu 5/14/09 Sun 5/17/09 0 2.99 days 0.06 381.71 514 1.6.4.3.1.3.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/14/09 E 0 1 day 15 mtr 0.01 78.35 515 1.6.4.3.1.3.2 Single Core Wires Thu 5/14/09 Sat 5/16/09 E 0 0.84 days 50 mtr 0 27.82 516 1.6.4.3.1.3.3 Junction Box Sat 5/16/09 Sat 5/16/09 E 0 0.36 days 2 nos. 0 23.98 517 1.6.4.3.1.3.4 Welding outlet / Socket Outlet Sat 5/16/09 Sun 5/17/09 E 0 0.5 days 2 nos. 0 27.05 518 1.6.4.3.1.3.5 Socket Feeder cables Sun 5/17/09 Sun 5/17/09 E 0 0.29 days 60 mtr 0.04 224.5 519 1.6.4.3.1.4 Installation - Local Junction Box Wed 6/10/09 Thu 8/13/09 0 71.65 days 0.71 4458.92 520 1.6.4.3.1.4.1 Rigid Steel Conduit Wed 6/10/09 Wed 6/17/09 E 0 7.62 days 140 mtr 0.12 744.6 521 1.6.4.3.1.4.2 Junction Box Wed 6/17/09 Sun 6/21/09 E 0 3.81 days 28 nos. 0.06 372.3 522 1.6.4.3.1.4.3 Feeder cables Sun 6/21/09 Wed 6/24/09 E 0 4.72 days 550 mtr 0.29 1817.64 523 1.6.4.3.1.4.4 Cable Termination Tue 7/28/09 Thu 8/13/09 E 0 18 days 88 nos. 0.24 1524.38 524 1.6.4.3.2 Air Compressed System - Piping Thu 5/14/09 Wed 5/20/09 0 7 days 0.05 333.13 525 1.6.4.3.2.1 2" Equal Tee Thu 5/14/09 Mon 5/18/09 P 0 4 days 11 nos 0.03 213.2 526 1.6.4.3.2.2 2" Plug Sat 5/16/09 Sun 5/17/09 P 0 1 day 9 nos 0.01 79.95 527 1.6.4.3.2.3 1/2" Ball valve Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66 528 1.6.4.3.2.4 2" x 1" Reducer Tue 5/19/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66 529 1.6.4.3.2.5 1" x 1/2" Reducer Tue 5/19/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66 5/14 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 9 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 10. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 530 1.6.4.3.2.6 1/2" Nipple Tue 5/19/09 Wed 5/20/09 P 0 1 day 2 nos 0 8 531 1.7 Construction - Potroom No. 2 (501-22B) Sat 2/28/09 Wed 7/8/09 0 145.65 days 11.3 71167.76 532 1.7.1 Pot 110 Sat 2/28/09 Mon 6/22/09 0 127.65 days 3.05 19187.68 533 4.5.2.1 SLI DELIVERABLES Sat 2/28/09 Sat 2/28/09 0 0 days 0 0 534 1.7.1.1.1 POT 110 Area Available for MPEI Construction Sat 2/28/09 Sat 2/28/09 0 0 days 0 0 535 1.7.1.2 Basement Floor Thu 4/30/09 Tue 5/26/09 0 27.67 days 1.12 7043.12 536 1.7.1.2.1 Installation - Electrical Thu 4/30/09 Tue 5/26/09 0 27.67 days 1.12 7043.12 537 1.7.1.2.1.1 Installation - Lighting System Thu 5/7/09 Sun 5/24/09 0 18.29 days 0.51 3228.7 538 1.7.1.2.1.1.1 PVC conduit and boxes Thu 5/7/09 Sat 5/9/09 E 0 1.96 days 66 mtr 0.03 212.67 539 1.7.1.2.1.1.2 Single Core Wires Sat 5/9/09 Sun 5/10/09 E 0 1.12 days 156 mtr 0.02 117.9 540 1.7.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 5/7/09 Sat 5/9/09 E 0 1.12 days 15 nos. 0.02 122.38 541 1.7.1.2.1.1.4 Lighting Feeder cables / wires Sat 5/16/09 Sun 5/24/09 E 0 8.84 days 1167 mtr 0.44 2775.76 542 1.7.1.2.1.2 Installation - Emergency Shutdown Thu 4/30/09 Tue 5/26/09 0 27.67 days 0.61 3814.41 543 1.7.1.2.1.2.1 PVC conduit and boxes Thu 4/30/09 Sat 5/2/09 I 0 0.76 days 12 mtr 0.01 63.96 544 1.7.1.2.1.2.2 Instrument cables Thu 5/14/09 Mon 5/25/09 I 0 12.21 days 1944 mtr 0.59 3731.8 545 1.7.1.2.1.2.3 Remote ASI Panel /Cabinet Mon 5/25/09 Tue 5/26/09 I 0 0.33 days 1 mtr 0 18.66 546 1.7.1.3 Operation Floor Mon 4/13/09 Mon 6/22/09 0 77.65 days 1.93 12144.56 547 1.7.1.3.1 Installation - Electrical Mon 4/13/09 Mon 6/22/09 0 77.65 days 1.88 11811.44 548 1.7.1.3.1.1 Installation - Lighting System Sun 4/19/09 Mon 4/27/09 0 9.7 days 0.37 2341.92 549 1.7.1.3.1.1.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 1.4 days 52 mtr 0.05 315 550 1.7.1.3.1.1.2 Single Core Wires Mon 4/20/09 Sat 4/25/09 E 0 5.04 days 1410 mtr 0.15 915.03 551 1.7.1.3.1.1.3 Junction Box Sat 4/25/09 Sat 4/25/09 E 0 0.22 days 2 nos. 0.01 36.35 552 1.7.1.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sat 4/25/09 Sun 4/26/09 E 0 1.64 days 12 nos. 0.05 303.76 553 1.7.1.3.1.1.5 Lighting Feeder cables / wires Sun 4/26/09 Mon 4/27/09 E 0 1.4 days 196 mtr 0.12 771.78 554 1.7.1.3.1.2 Installation - Cable Tray Mon 4/13/09 Sat 5/16/09 0 35.66 days 0.06 382.29 555 1.7.1.3.1.2.1 Cantilever supports installation Mon 4/13/09 Tue 4/14/09 E 0 0.35 days 32 nos. 0.01 38.24 556 1.7.1.3.1.2.2 Cable Tray installation Thu 5/14/09 Sat 5/16/09 E 0 1.5 days 189 mtr 0.05 344.05 557 1.7.1.3.1.3 Installation - Blower and Transformer Feeder Sat 5/9/09 Thu 5/14/09 0 5.85 days 0.42 2653.46 558 1.7.1.3.1.3.1 Blower Feeder, Transformer Feeder Sat 5/9/09 Thu 5/14/09 E 0 5.85 days 700 mtr 0.42 2653.46 559 1.7.1.3.1.4 Installation - Socket / Welding Outlet Sun 4/19/09 Wed 4/22/09 0 3.23 days 0.07 434.47 560 1.7.1.3.1.4.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 0.84 days 15 mtr 0.01 78.35 561 1.7.1.3.1.4.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.08 days 50 mtr 0.01 80.59 562 1.7.1.3.1.4.3 Junction Box Tue 4/21/09 Tue 4/21/09 E 0 0.5 days 2 nos. 0 23.98 563 1.7.1.3.1.4.4 Welding outlet / Socket Outlet Tue 4/21/09 Tue 4/21/09 E 0 0.29 days 2 nos. 0 27.05 564 1.7.1.3.1.4.5 Socket Feeder cables Tue 4/21/09 Wed 4/22/09 E 0 0.52 days 60 mtr 0.04 224.5 565 1.7.1.3.1.5 Installation - Local Junction Box Sat 4/25/09 Mon 6/22/09 0 64.91 days 0.95 5999.29 566 1.7.1.3.1.5.1 Rigid Steel Conduit Sat 4/25/09 Sat 5/2/09 E 0 7.62 days 140 mtr 0.12 744.6 567 1.7.1.3.1.5.2 Junction Box Sat 5/2/09 Tue 5/5/09 E 0 3.81 days 28 nos. 0.06 372.3 568 1.7.1.3.1.5.3 Feeder cables Sat 5/16/09 Sun 5/24/09 E 0 8.72 days 1020 mtr 0.53 3358.01 569 1.7.1.3.1.5.4 Cable Termination Sun 6/7/09 Mon 6/22/09 E 0 18 days 88 nos. 0.24 1524.38 570 1.7.1.3.2 Air Compressed System - Piping Tue 4/28/09 Sat 5/16/09 0 20 days 0.05 333.13 571 1.7.1.3.2.1 2" Equal Tee Tue 4/28/09 Sat 5/2/09 P 0 4 days 11 nos 0.03 213.2 572 1.7.1.3.2.2 2" Plug Thu 4/30/09 Thu 4/30/09 P 0 1 day 9 nos 0.01 79.95 573 1.7.1.3.2.3 1/2" Ball valve Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66 574 1.7.1.3.2.4 2" x 1" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66 575 1.7.1.3.2.5 1" x 1/2" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66 576 1.7.1.3.2.6 1/2" Nipple Sat 5/16/09 Sat 5/16/09 P 0 1 day 2 nos 0 8 577 1.7.2 Pot 132 Wed 3/18/09 Mon 6/22/09 0 106.98 days 3.87 24355.97 578 4.5.2.1 SLI DELIVERABLES Wed 3/18/09 Wed 3/18/09 0 0 days 0 0 579 1.7.2.1.1 POT 132 Area Available for MPEI Construction Wed 3/18/09 Wed 3/18/09 0 0 days 0 0 580 1.7.2.2 Basement Floor Sat 5/9/09 Mon 6/1/09 0 25.6 days 1.26 7938.4 581 1.7.2.2.1 Installation - Electrical Sat 5/9/09 Mon 6/1/09 0 25.6 days 1.26 7938.4 582 1.7.2.2.1.1 Installation - Lighting System Sat 5/9/09 Sun 5/31/09 0 23.88 days 0.66 4142.64 583 1.7.2.2.1.1.1 PVC conduit and boxes Sat 5/9/09 Mon 5/11/09 E 0 2.45 days 84 mtr 0.04 265.83 584 1.7.2.2.1.1.2 Single Core Wires Mon 5/11/09 Tue 5/12/09 E 0 1.4 days 198 mtr 0.02 147.37 585 1.7.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Sun 5/10/09 Mon 5/11/09 E 0 1.4 days 19 nos. 0.02 152.97 586 1.7.2.2.1.1.4 Lighting Feeder cables / wires Wed 5/20/09 Sun 5/31/09 E 0 11.39 days 1498 mtr 0.57 3576.46 587 1.7.2.2.1.2 Installation - Emergency Shutdown Tue 5/19/09 Mon 6/1/09 0 13.79 days 0.6 3795.76 588 1.7.2.2.1.2.1 PVC conduit and boxes Tue 5/19/09 Wed 5/20/09 I 0 0.76 days 12 mtr 0.01 63.96 2/28 2/28 3/18 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 10 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 11. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 589 1.7.2.2.1.2.2 Instrument cables Thu 5/21/09 Mon 6/1/09 I 0 12.21 days 1944 mtr 0.59 3731.8 590 1.7.2.3 Operation Floor Tue 4/14/09 Mon 6/22/09 0 77.3 days 2.61 16417.57 591 1.7.2.3.1 Installation - Electrical Tue 4/14/09 Mon 6/22/09 0 77.3 days 2.55 16084.45 592 1.7.2.3.1.1 Installation - Lighting System Mon 4/20/09 Mon 4/27/09 0 7.6 days 0.14 887.79 593 1.7.2.3.1.1.1 Rigid Steel Conduit Mon 4/20/09 Mon 4/20/09 E 0 0.7 days 25 mtr 0.03 157.5 594 1.7.2.3.1.1.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.04 days 300 mtr 0.03 188.82 595 1.7.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 4/21/09 Wed 4/22/09 E 0 0.84 days 6 nos. 0.02 155.58 596 1.7.2.3.1.1.4 Lighting Feeder cables / wires Sun 4/26/09 Mon 4/27/09 E 0 0.7 days 100 mtr 0.06 385.89 597 1.7.2.3.1.2 Installation - Cable Tray Tue 4/14/09 Wed 5/20/09 0 41.16 days 0.06 382.29 598 1.7.2.3.1.2.1 Cantilever supports installation Tue 4/14/09 Tue 4/14/09 E 0 0.35 days 32 nos. 0.01 38.24 599 1.7.2.3.1.2.2 Cable Tray installation Tue 5/19/09 Wed 5/20/09 E 0 1.5 days 189 mtr 0.05 344.05 600 1.7.2.3.1.3 Installation - Crane Bus Bars Thu 5/14/09 Sun 5/24/09 0 9.48 days 0.91 5727.14 601 1.7.2.3.1.3.1 Crane Bus Bar Supports installation Thu 5/14/09 Sat 5/16/09 E 0 0.96 days 16 nos. 0.02 96.37 602 1.7.2.3.1.3.2 Feed Junction Box Installation Sat 5/16/09 Sun 5/17/09 E 0 0.67 days 2 nos. 0.01 35.71 603 1.7.2.3.1.3.3 Disconnect Switch Instalation Sun 5/17/09 Sun 5/17/09 E 0 0.5 days 1 nos. 0 17.32 604 1.7.2.3.1.3.4 Interconnection cable, cableways installation Sun 5/17/09 Mon 5/18/09 E 0 1 day 5 nos. 0.03 159.9 605 1.7.2.3.1.3.5 Crane Power Feeder Cable Mon 5/18/09 Sat 5/23/09 E 0 5.36 days 700 mtr 0.85 5331.65 606 1.7.2.3.1.3.6 Cable Termination Sat 5/23/09 Sun 5/24/09 E 0 0.99 days 5 nos. 0.01 86.19 607 1.7.2.3.1.4 Installation - Blower and Transformer Feeder Thu 5/14/09 Tue 5/19/09 0 5.85 days 0.42 2653.46 608 1.7.2.3.1.4.1 Blower Feeder, Transformer Feeder Thu 5/14/09 Tue 5/19/09 E 0 5.85 days 700 mtr 0.42 2653.46 609 1.7.2.3.1.5 Installation - Socket / Welding Outlet Mon 4/20/09 Wed 4/22/09 0 3.23 days 0.07 434.47 610 1.7.2.3.1.5.1 Rigid Steel Conduit Mon 4/20/09 Tue 4/21/09 E 0 0.84 days 15 mtr 0.01 78.35 611 1.7.2.3.1.5.2 Single Core Wires Tue 4/21/09 Tue 4/21/09 E 0 1.08 days 50 mtr 0.01 80.59 612 1.7.2.3.1.5.3 Junction Box Tue 4/21/09 Wed 4/22/09 E 0 0.5 days 2 nos. 0 23.98 613 1.7.2.3.1.5.4 Welding outlet / Socket Outlet Wed 4/22/09 Wed 4/22/09 E 0 0.29 days 2 nos. 0 27.05 614 1.7.2.3.1.5.5 Socket Feeder cables Wed 4/22/09 Wed 4/22/09 E 0 0.52 days 60 mtr 0.04 224.5 615 1.7.2.3.1.6 Installation - Local Junction Box Sat 5/2/09 Mon 6/22/09 0 57.29 days 0.95 5999.29 616 1.7.2.3.1.6.1 Rigid Steel Conduit Sat 5/2/09 Sat 5/9/09 E 0 7.62 days 140 mtr 0.12 744.6 617 1.7.2.3.1.6.2 Junction Box Sat 5/9/09 Tue 5/12/09 E 0 3.81 days 28 nos. 0.06 372.3 618 1.7.2.3.1.6.3 Feeder cables Sun 5/24/09 Sun 5/31/09 E 0 8.72 days 1020 mtr 0.53 3358.01 619 1.7.2.3.1.6.4 Cable Termination Sun 6/7/09 Mon 6/22/09 E 0 18 days 88 nos. 0.24 1524.38 620 1.7.2.3.2 Air Compressed System - Piping Sat 5/2/09 Sun 5/17/09 0 17 days 0.05 333.13 621 1.7.2.3.2.1 2" Equal Tee Sat 5/2/09 Tue 5/5/09 P 0 4 days 11 nos 0.03 213.2 622 1.7.2.3.2.2 2" Plug Mon 5/4/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95 623 1.7.2.3.2.3 1/2" Ball valve Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66 624 1.7.2.3.2.4 2" x 1" Reducer Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66 625 1.7.2.3.2.5 1" x 1/2" Reducer Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66 626 1.7.2.3.2.6 1/2" Nipple Sat 5/16/09 Sun 5/17/09 P 0 1 day 2 nos 0 8 627 1.7.3 Pot 154 Sun 4/5/09 Tue 6/30/09 0 95.61 days 2.15 13530.95 628 4.5.2.1 SLI DELIVERABLES Sun 4/5/09 Sun 4/5/09 0 0 days 0 0 629 1.7.3.1.1 POT 154 Area Available for MPEI Construction Sun 4/5/09 Sun 4/5/09 0 0 days 0 0 630 1.7.3.2 Basement Floor Mon 5/11/09 Mon 6/8/09 0 30.69 days 1.18 7412.38 631 1.7.3.2.1 Installation - Electrical Mon 5/11/09 Mon 6/8/09 0 30.69 days 1.18 7412.38 632 1.7.3.2.1.1 Installation - Lighting System Mon 5/11/09 Thu 5/21/09 0 11.21 days 0.57 3597.96 633 1.7.3.2.1.1.1 PVC conduit and boxes Mon 5/11/09 Wed 5/13/09 E 0 2.03 days 69 mtr 0.03 220.26 634 1.7.3.2.1.1.2 Single Core Wires Wed 5/13/09 Thu 5/14/09 E 0 1.2 days 167 mtr 0.02 126.32 635 1.7.3.2.1.1.3 Lighting Feeder cables / wires Wed 5/13/09 Thu 5/14/09 E 0 0.17 days 16 mtr 0.01 53.38 636 1.7.3.2.1.1.4 Crane feeder cables Thu 5/14/09 Thu 5/21/09 E 0 8 days 1244 mtr 0.51 3198 637 1.7.3.2.1.2 Installation - Emergency Shutdown Wed 5/20/09 Mon 6/8/09 0 20.57 days 0.61 3814.41 638 1.7.3.2.1.2.1 PVC conduit and boxes Wed 5/20/09 Wed 5/20/09 I 0 0.76 days 12 mtr 0.01 63.96 639 1.7.3.2.1.2.2 Instrument cables Wed 5/27/09 Mon 6/8/09 I 0 12.21 days 1944 mtr 0.59 3731.8 640 1.7.3.2.1.2.3 Remote ASI Panel /Cabinet Mon 6/8/09 Mon 6/8/09 I 0 0.33 days 1 mtr 0 18.66 641 1.7.3.3 Operation Floor Wed 4/22/09 Tue 6/30/09 0 76.23 days 0.97 6118.57 642 1.7.3.3.1 Installation - Electrical Sat 5/9/09 Tue 6/30/09 0 57.67 days 0.92 5785.45 643 1.7.3.3.1.1 Installation - Crane Bus Bars Sat 5/16/09 Sun 5/17/09 0 0.96 days 0.02 96.37 644 1.7.3.3.1.1.1 Crane Bus Bar Supports installation Sat 5/16/09 Sun 5/17/09 E 0 0.96 days 16 nos. 0.02 96.37 645 1.7.3.3.1.2 Installation - Local Junction Box Sat 5/9/09 Tue 6/30/09 0 57.67 days 0.9 5689.08 646 1.7.3.3.1.2.1 Rigid Steel Conduit Sat 5/9/09 Thu 5/14/09 E 0 7.08 days 130 mtr 0.11 691.83 647 1.7.3.3.1.2.2 Junction Box Thu 5/14/09 Mon 5/18/09 E 0 3.54 days 26 nos. 0.05 345.92 4/5 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 11 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 12. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 648 1.7.3.3.1.2.3 Feeder cables Sun 5/31/09 Mon 6/8/09 E 0 8.12 days 948 mtr 0.5 3126.95 649 1.7.3.3.1.2.4 Cable Termination Sun 6/14/09 Tue 6/30/09 E 0 18 days 88 nos. 0.24 1524.38 650 1.7.3.3.2 Air Compressed System - Piping Wed 4/22/09 Mon 5/18/09 0 28.9 days 0.05 333.13 651 1.7.3.3.2.1 2" Equal Tee Wed 4/22/09 Sun 4/26/09 P 0 4 days 11 nos 0.03 213.2 652 1.7.3.3.2.2 2" Plug Thu 4/23/09 Sat 4/25/09 P 0 1 day 9 nos 0.01 79.95 653 1.7.3.3.2.3 1/2" Ball valve Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66 654 1.7.3.3.2.4 2" x 1" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66 655 1.7.3.3.2.5 1" x 1/2" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66 656 1.7.3.3.2.6 1/2" Nipple Sun 5/17/09 Mon 5/18/09 P 0 1 day 2 nos 0 8 657 1.7.4 Pot 176 Thu 4/23/09 Wed 7/8/09 0 84.94 days 2.24 14093.16 658 1.7.4.1 SLI DELIVERABLES Thu 4/23/09 Thu 4/23/09 0 0 days 0 0 659 1.7.4.1.1 POT 176 Area Available for MPEI Construction Thu 4/23/09 Thu 4/23/09 0 0 days 0 0 660 1.7.4.2 Basement Floor Wed 5/13/09 Sun 6/14/09 0 35.54 days 1.29 8125.59 661 1.7.4.2.1 Installation - Electrical Wed 5/13/09 Sun 6/14/09 0 35.54 days 1.29 8125.59 662 1.7.4.2.1.1 Installation - Lighting System Wed 5/13/09 Thu 5/28/09 0 17.91 days 0.69 4329.83 663 1.7.4.2.1.1.1 PVC conduit and boxes Wed 5/13/09 Sat 5/16/09 E 0 2.59 days 88 mtr 0.04 281.02 664 1.7.4.2.1.1.2 Single Core Wires Sat 5/16/09 Sun 5/17/09 E 0 1.44 days 205 mtr 0.02 151.59 665 1.7.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Wed 5/13/09 Sat 5/16/09 E 0 1.47 days 20 nos. 0.03 160.62 666 1.7.4.2.1.1.4 Lighting Feeder cables / wires Mon 5/18/09 Thu 5/28/09 E 0 11.9 days 1554 mtr 0.59 3736.6 667 1.7.4.2.1.2 Installation - Emergency Shutdown Wed 5/20/09 Sun 6/14/09 0 26.69 days 0.6 3795.76 668 1.7.4.2.1.2.1 PVC conduit and boxes Wed 5/20/09 Thu 5/21/09 I 0 0.76 days 12 mtr 0.01 63.96 669 1.7.4.2.1.2.2 Instrument cables Wed 6/3/09 Sun 6/14/09 I 0 12.21 days 1944 mtr 0.59 3731.8 670 1.7.4.3 Operation Floor Thu 4/23/09 Wed 7/8/09 0 84.94 days 0.95 5967.57 671 1.7.4.3.1 Installation - Electrical Thu 4/23/09 Wed 7/8/09 0 84.94 days 0.89 5634.45 672 1.7.4.3.1.1 Installation - Lighting System Thu 4/23/09 Mon 4/27/09 0 4.59 days 0.1 644.69 673 1.7.4.3.1.1.1 Rigid Steel Conduit Thu 4/23/09 Sat 4/25/09 E 0 2 days 26 mtr 0.03 173.22 674 1.7.4.3.1.1.2 Single Core Wires Sat 4/25/09 Sun 4/26/09 E 0 1.04 days 300 mtr 0.03 188.82 675 1.7.4.3.1.1.3 Junction Box Sun 4/26/09 Sun 4/26/09 E 0 0.64 days 6 nos. 0.02 105.75 676 1.7.4.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 4/26/09 Mon 4/27/09 E 0 0.84 days 6 nos. 0.02 155.58 677 1.7.4.3.1.1.5 Lighting Feeder cables / wires Mon 4/27/09 Mon 4/27/09 E 0 0.07 days 8 mtr 0 21.32 678 1.7.4.3.1.2 Installation - Crane Bus Bars Sun 5/17/09 Mon 5/18/09 0 0.96 days 0.02 96.37 679 1.7.4.3.1.2.1 Crane Bus Bar Supports installation Sun 5/17/09 Mon 5/18/09 E 0 0.96 days 16 nos. 0.02 96.37 680 1.7.4.3.1.3 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 3.23 days 0.07 434.47 681 1.7.4.3.1.3.1 Rigid Steel Conduit Thu 4/23/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35 682 1.7.4.3.1.3.2 Single Core Wires Thu 4/23/09 Sat 4/25/09 E 0 1.08 days 50 mtr 0.01 80.59 683 1.7.4.3.1.3.3 Junction Box Sat 4/25/09 Sun 4/26/09 E 0 0.5 days 2 nos. 0 23.98 684 1.7.4.3.1.3.4 Welding outlet / Socket Outlet Sun 4/26/09 Sun 4/26/09 E 0 0.29 days 2 nos. 0 27.05 685 1.7.4.3.1.3.5 Socket Feeder cables Sun 4/26/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5 686 1.7.4.3.1.4 Installation - Local Junction Box Thu 5/14/09 Wed 7/8/09 0 60.59 days 0.71 4458.92 687 1.7.4.3.1.4.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/21/09 E 0 7.62 days 140 mtr 0.12 744.6 688 1.7.4.3.1.4.2 Junction Box Thu 5/21/09 Mon 5/25/09 E 0 3.81 days 28 nos. 0.06 372.3 689 1.7.4.3.1.4.3 Feeder cables Mon 6/8/09 Thu 6/11/09 E 0 4.72 days 550 mtr 0.29 1817.64 690 1.7.4.3.1.4.4 Cable Termination Mon 6/22/09 Wed 7/8/09 E 0 18 days 88 nos. 0.24 1524.38 691 1.7.4.3.2 Air Compressed System - Piping Sun 4/26/09 Tue 5/19/09 0 25.9 days 0.05 333.13 692 1.7.4.3.2.1 2" Equal Tee Sun 4/26/09 Wed 4/29/09 P 0 4 days 11 nos 0.03 213.2 693 1.7.4.3.2.2 2" Plug Mon 4/27/09 Tue 4/28/09 P 0 1 day 9 nos 0.01 79.95 694 1.7.4.3.2.3 1/2" Ball valve Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66 695 1.7.4.3.2.4 2" x 1" Reducer Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66 696 1.7.4.3.2.5 1" x 1/2" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66 697 1.7.4.3.2.6 1/2" Nipple Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 8 698 1.8 Construction - Crane Workshop 512-1 Thu 1/15/09 Sat 4/25/09 0.01 109.95 days 1.53 9660.25 699 1.8.1 SLI DELIVERABLES Thu 1/15/09 Thu 1/15/09 0 0 days 0 0 700 1.8.1.1 Crane Work shop Building Avaialbale for MPEI Construction Thu 1/15/09 Thu 1/15/09 0 0 days 0 0 701 1.8.2 Installation - Electrical Sat 2/7/09 Sat 4/25/09 0.01 84.95 days 1.53 9660.25 702 1.8.2.1 Installation - Crane Bus Bars Sat 2/7/09 Sat 4/25/09 0.01 84.95 days 1.53 9660.25 703 1.8.2.1.1 Crane Bus Bar Supports installation Sat 2/7/09 Sat 2/7/09 E 0.01 0.59 days 14 nos. 0.01 83.09 704 1.8.2.1.2 Feed Junction Box Installation Tue 4/14/09 Tue 4/14/09 E 0 0.28 days 1 nos. 0 16.98 705 1.8.2.1.3 Disconnect Switch Instalation Tue 4/14/09 Wed 4/15/09 E 0 0.88 days 4 nos. 0.01 68.6 706 1.8.2.1.4 Crane Power Feeder Cable Wed 4/15/09 Wed 4/22/09 E 0 8.1 days 1110 mtr 1.46 9192.25 4/23 1/15 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 12 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 13. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 707 1.8.2.1.5 Cable Termination Wed 4/22/09 Sat 4/25/09 E 0 2.4 days 23 nos. 0.05 299.33 708 1.9 Construction - Central Passageway 503-32 Sat 3/7/09 Mon 5/11/09 0 73.11 days 0.72 4515.6 709 4.5.2.1 SLI DELIVERABLES Sat 3/7/09 Sat 3/7/09 0 0 days 0 0 710 1.9.1.1 Central Passageway Available for MPEI Construction Sat 3/7/09 Sat 3/7/09 0 0 days 0 0 711 1.9.2 Operation Floor Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.72 4515.6 712 1.9.2.1 Installation - Electrical Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.72 4515.6 713 1.9.2.1.1 Installation - Lighting System Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.14 851.68 714 1.9.2.1.1.1 Rigid Steel Conduit Mon 4/13/09 Thu 4/16/09 E 0 4.26 days 50 mtr 0.05 298.96 715 1.9.2.1.1.2 Single Core Wires Thu 4/16/09 Sun 4/19/09 E 0 2 days 153 mtr 0.02 99.67 716 1.9.2.1.1.3 Lighting Feeder cables / wires Sun 5/10/09 Mon 5/11/09 E 0 1 day 110 mtr 0.07 453.05 717 1.9.2.1.2 Installation - Cable Tray Wed 4/29/09 Sun 5/10/09 0 12.11 days 0.17 1060.4 718 1.9.2.1.2.1 Cantilever supports installation Wed 4/29/09 Mon 5/4/09 E 0 5.19 days 140 nos. 0.05 304.29 719 1.9.2.1.2.2 Cable Tray installation Mon 5/4/09 Sun 5/10/09 E 0 6.92 days 420 mtr 0.12 756.11 720 1.9.2.1.3 Installation - Crane Bus Bars Tue 4/14/09 Tue 5/5/09 0 23.78 days 0.41 2603.52 721 1.9.2.1.3.1 Feed Junction Box Installation Tue 4/14/09 Wed 4/15/09 E 0 0.72 days 4 nos. 0.01 69.08 722 1.9.2.1.3.2 Disconnect Switch Instalation Wed 4/15/09 Thu 4/16/09 E 0 1.78 days 8 nos. 0.02 139.94 723 1.9.2.1.3.3 Interconnection cable, cableways installation Thu 4/16/09 Sun 4/19/09 E 0 2.97 days 15 nos. 0.06 395.75 724 1.9.2.1.3.4 Crane feeder cables Sat 5/2/09 Tue 5/5/09 E 0 5 days 800 0.32 1998.75 725 1.10 Construction - Potroom No. 1 (501-12C) Thu 5/21/09 Thu 9/24/09 0 139.9 days 12.01 75624.57 726 1.10.1 Pot 198 Thu 5/21/09 Sun 8/30/09 0 111.9 days 2.75 17348.11 727 4.5.2.1 SLI DELIVERABLES Thu 6/4/09 Thu 6/4/09 0 0 days 0 0 728 1.10.1.1.1 POT 198 Area Available for MPEI Construction Thu 6/4/09 Thu 6/4/09 0 0 days 0 0 729 1.10.1.2 Basement Floor Tue 6/2/09 Tue 6/23/09 0 23.06 days 1.15 7244.8 730 1.10.1.2.1 Installation - Electrical Tue 6/2/09 Tue 6/23/09 0 23.06 days 1.15 7244.8 731 1.10.1.2.1.1 Installation - Lighting System Tue 6/2/09 Thu 6/11/09 0 9.52 days 0.55 3449.04 732 1.10.1.2.1.1.1 PVC conduit and boxes Thu 6/4/09 Sat 6/6/09 E 0 2.03 days 68 mtr 0.03 220.26 733 1.10.1.2.1.1.2 Single Core Wires Sat 6/6/09 Sun 6/7/09 E 0 1.04 days 148 mtr 0.02 109.48 734 1.10.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 6/4/09 Sat 6/6/09 E 0 1.19 days 16 nos. 0.02 130.03 735 1.10.1.2.1.1.4 Lighting Feeder cables / wires Tue 6/2/09 Thu 6/11/09 E 0 9.52 days 1244 mtr 0.47 2989.28 736 1.10.1.2.1.2 Installation - Emergency Shutdown Thu 6/4/09 Tue 6/23/09 0 21.32 days 0.6 3795.76 737 1.10.1.2.1.2.1 PVC conduit and boxes Thu 6/4/09 Thu 6/4/09 I 0 0.76 days 12 mtr 0.01 63.96 738 1.10.1.2.1.2.2 Instrument cables Sat 6/13/09 Tue 6/23/09 I 0 12.21 days 1944 mtr 0.59 3731.8 739 1.10.1.3 Delivery of sub station 305-52 from SNCLavalin to Astaldi Thu 5/21/09 Thu 5/21/09 0 0 days 0 0 740 1.10.1.4 Operation Floor Thu 6/4/09 Sun 8/30/09 0 96.4 days 1.6 10103.31 741 1.10.1.4.1 Installation - Electrical Thu 6/4/09 Sun 8/30/09 0 96.4 days 1.55 9770.18 742 1.10.1.4.1.1 Installation - Crane Bus Bars Thu 6/4/09 Mon 6/15/09 0 12.27 days 0.53 3336.42 743 1.10.1.4.1.1.1 Crane Bus Bar Supports installation Thu 6/4/09 Thu 6/4/09 E 0 0.96 days 16 nos. 0.02 96.37 744 1.10.1.4.1.1.2 Feed Junction Box Installation Thu 6/4/09 Sun 6/7/09 E 0 1.67 days 5 nos. 0.01 89.01 745 1.10.1.4.1.1.3 Disconnect Switch Instalation Sun 6/7/09 Tue 6/9/09 E 0 3 days 6 nos. 0.02 103.94 746 1.10.1.4.1.1.4 Interconnection cable, cableways installation Tue 6/9/09 Wed 6/10/09 E 0 1 day 5 nos. 0.03 159.9 747 1.10.1.4.1.1.5 Crane Power Feeder Cable Wed 6/10/09 Sat 6/13/09 E 0 2.64 days 350 mtr 0.42 2626.04 748 1.10.1.4.1.1.6 Cable Termination Sat 6/13/09 Mon 6/15/09 E 0 3 days 15 nos. 0.04 261.17 749 1.10.1.4.1.2 Installation - Socket / Welding Outlet Thu 6/4/09 Sun 6/7/09 0 3.23 days 0.07 434.47 750 1.10.1.4.1.2.1 Rigid Steel Conduit Thu 6/4/09 Thu 6/4/09 E 0 0.84 days 15 mtr 0.01 78.35 751 1.10.1.4.1.2.2 Single Core Wires Thu 6/4/09 Sat 6/6/09 E 0 1.08 days 50 mtr 0.01 80.59 752 1.10.1.4.1.2.3 Junction Box Sat 6/6/09 Sun 6/7/09 E 0 0.5 days 2 nos. 0 23.98 753 1.10.1.4.1.2.4 Welding outlet / Socket Outlet Sun 6/7/09 Sun 6/7/09 E 0 0.29 days 2 nos. 0 27.05 754 1.10.1.4.1.2.5 Socket Feeder cables Sun 6/7/09 Sun 6/7/09 E 0 0.52 days 60 mtr 0.04 224.5 755 1.10.1.4.1.3 Installation - Local Junction Box Wed 6/17/09 Sun 8/30/09 0 82.03 days 0.95 5999.29 756 1.10.1.4.1.3.1 Rigid Steel Conduit Wed 6/17/09 Wed 6/24/09 E 0 7.62 days 140 mtr 0.12 744.6 757 1.10.1.4.1.3.2 Junction Box Wed 6/24/09 Sun 6/28/09 E 0 3.81 days 28 nos. 0.06 372.3 758 1.10.1.4.1.3.3 Feeder cables Sun 6/28/09 Sun 7/5/09 E 0 8.72 days 1020 mtr 0.53 3358.01 759 1.10.1.4.1.3.4 Cable Termination Thu 8/13/09 Sun 8/30/09 E 0 18 days 88 nos. 0.24 1524.38 760 1.10.1.4.2 Air Compressed System - Piping Thu 6/4/09 Tue 6/9/09 0 6 days 0.05 333.13 761 1.10.1.4.2.1 2" Equal Tee Thu 6/4/09 Mon 6/8/09 P 0 4 days 11 nos 0.03 213.2 762 1.10.1.4.2.2 2" Plug Sat 6/6/09 Sun 6/7/09 P 0 1 day 9 nos 0.01 79.95 763 1.10.1.4.2.3 1/2" Ball valve Sun 6/7/09 Mon 6/8/09 P 0 1 day 2 nos 0 10.66 764 1.10.1.4.2.4 2" x 1" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66 765 1.10.1.4.2.5 1" x 1/2" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66 3/7 6/4 5/21 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 13 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 14. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 766 1.10.1.4.2.6 1/2" Nipple Tue 6/9/09 Tue 6/9/09 P 0 1 day 2 nos 0 8 767 1.10.2 Pot 220 Wed 6/24/09 Tue 9/8/09 0 84.42 days 2.39 15074.31 768 4.5.2.1 SLI DELIVERABLES Thu 6/25/09 Thu 6/25/09 0 0 days 0 0 769 1.10.2.1.1 POT 220 Area Available for MPEI Construction Thu 6/25/09 Thu 6/25/09 0 0 days 0 0 770 1.10.2.2 Basement Floor Wed 6/24/09 Tue 7/7/09 0 14.57 days 1.22 7687.83 771 1.10.2.2.1 Installation - Electrical Wed 6/24/09 Tue 7/7/09 0 14.57 days 1.22 7687.83 772 1.10.2.2.1.1 Installation - Lighting System Wed 6/24/09 Sat 7/4/09 0 10.71 days 0.61 3873.42 773 1.10.2.2.1.1.1 PVC conduit and boxes Thu 6/25/09 Sat 6/27/09 E 0 2.24 days 76 mtr 0.04 243.05 774 1.10.2.2.1.1.2 Single Core Wires Sat 6/27/09 Sun 6/28/09 E 0 1.16 days 166 mtr 0.02 122.11 775 1.10.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 6/25/09 Sat 6/27/09 E 0 1.33 days 18 nos. 0.02 145.32 776 1.10.2.2.1.1.4 Lighting Feeder cables / wires Wed 6/24/09 Sat 7/4/09 E 0 10.71 days 1400 mtr 0.53 3362.94 777 1.10.2.2.1.2 Installation - Emergency Shutdown Thu 6/25/09 Tue 7/7/09 0 13.3 days 0.61 3814.41 778 1.10.2.2.1.2.1 PVC conduit and boxes Thu 6/25/09 Thu 6/25/09 I 0 0.76 days 12 mtr 0.01 63.96 779 1.10.2.2.1.2.2 Instrument cables Thu 6/25/09 Tue 7/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8 780 1.10.2.2.1.2.3 Remote ASI Panel /Cabinet Tue 7/7/09 Tue 7/7/09 I 0 0.33 days 1 mtr 0 18.66 781 1.10.2.3 Operation Floor Thu 6/25/09 Tue 9/8/09 0 83.15 days 1.17 7386.47 782 1.10.2.3.1 Installation - Electrical Thu 6/25/09 Tue 9/8/09 0 83.15 days 1.12 7053.35 783 1.10.2.3.1.1 Installation - Lighting System Thu 6/25/09 Sun 6/28/09 0 3.58 days 0.08 523.22 784 1.10.2.3.1.1.1 Rigid Steel Conduit Thu 6/25/09 Thu 6/25/09 E 0 0.7 days 26 mtr 0.03 157.5 785 1.10.2.3.1.1.2 Single Core Wires Thu 6/25/09 Sat 6/27/09 E 0 1.04 days 300 mtr 0.03 188.82 786 1.10.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Sat 6/27/09 Sun 6/28/09 E 0 0.84 days 6 nos. 0.02 155.58 787 1.10.2.3.1.1.4 Lighting Feeder cables / wires Sun 6/28/09 Sun 6/28/09 E 0 1 day 8 mtr 0 21.32 788 1.10.2.3.1.2 Installation - Crane Bus Bars Thu 6/25/09 Thu 6/25/09 0 0.96 days 0.02 96.37 789 1.10.2.3.1.2.1 Crane Bus Bar Supports installation Thu 6/25/09 Thu 6/25/09 E 0 0.96 days 16 nos. 0.02 96.37 790 1.10.2.3.1.3 Installation - Socket / Welding Outlet Thu 6/25/09 Sun 6/28/09 0 3.23 days 0.07 434.47 791 1.10.2.3.1.3.1 Rigid Steel Conduit Thu 6/25/09 Thu 6/25/09 E 0 0.84 days 15 mtr 0.01 78.35 792 1.10.2.3.1.3.2 Single Core Wires Thu 6/25/09 Sat 6/27/09 E 0 1.08 days 50 mtr 0.01 80.59 793 1.10.2.3.1.3.3 Junction Box Sat 6/27/09 Sun 6/28/09 E 0 0.5 days 2 nos. 0 23.98 794 1.10.2.3.1.3.4 Welding outlet / Socket Outlet Sun 6/28/09 Sun 6/28/09 E 0 0.29 days 2 nos. 0 27.05 795 1.10.2.3.1.3.5 Socket Feeder cables Sun 6/28/09 Sun 6/28/09 E 0 0.52 days 60 mtr 0.04 224.5 796 1.10.2.3.1.4 Installation - Local Junction Box Thu 6/25/09 Tue 9/8/09 0 83.15 days 0.95 5999.29 797 1.10.2.3.1.4.1 Rigid Steel Conduit Thu 6/25/09 Thu 7/2/09 E 0 7.62 days 140 mtr 0.12 744.6 798 1.10.2.3.1.4.2 Junction Box Thu 7/2/09 Sun 7/5/09 E 0 3.81 days 28 nos. 0.06 372.3 799 1.10.2.3.1.4.3 Feeder cables Sun 7/5/09 Mon 7/13/09 E 0 8.72 days 1020 mtr 0.53 3358.01 800 1.10.2.3.1.4.4 Cable Termination Sun 8/23/09 Tue 9/8/09 E 0 18 days 88 nos. 0.24 1524.38 801 1.10.2.3.2 Air Compressed System - Piping Thu 6/25/09 Tue 6/30/09 0 6 days 0.05 333.13 802 1.10.2.3.2.1 2" Equal Tee Thu 6/25/09 Mon 6/29/09 P 0 4 days 11 nos 0.03 213.2 803 1.10.2.3.2.2 2" Plug Sat 6/27/09 Sun 6/28/09 P 0 1 day 9 nos 0.01 79.95 804 1.10.2.3.2.3 1/2" Ball valve Sun 6/28/09 Mon 6/29/09 P 0 1 day 2 nos 0 10.66 805 1.10.2.3.2.4 2" x 1" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66 806 1.10.2.3.2.5 1" x 1/2" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66 807 1.10.2.3.2.6 1/2" Nipple Tue 6/30/09 Tue 6/30/09 P 0 1 day 2 nos 0 8 808 1.10.3 Pot 242 Thu 7/16/09 Thu 9/24/09 0 77.9 days 3.65 22993.46 809 1.10.3.1 SLI DELIVERABLES Thu 7/16/09 Thu 7/16/09 0 0 days 0 0 810 1.10.3.1.1 POT 242 Area Available for MPEI Construction Thu 7/16/09 Thu 7/16/09 0 0 days 0 0 811 1.10.3.2 Basement Floor Thu 7/16/09 Thu 7/30/09 0 15.82 days 1.15 7244.8 812 1.10.3.2.1 Installation - Electrical Thu 7/16/09 Thu 7/30/09 0 15.82 days 1.15 7244.8 813 1.10.3.2.1.1 Installation - Lighting System Thu 7/16/09 Thu 7/30/09 0 15.82 days 0.55 3449.04 814 1.10.3.2.1.1.1 PVC conduit and boxes Thu 7/16/09 Sat 7/18/09 E 0 2.03 days 68 mtr 0.03 220.26 815 1.10.3.2.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.04 days 148 mtr 0.02 109.48 816 1.10.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 7/16/09 Sat 7/18/09 E 0 1.19 days 16 nos. 0.02 130.03 817 1.10.3.2.1.1.4 Lighting Feeder cables / wires Wed 7/22/09 Thu 7/30/09 E 0 9.52 days 1244 mtr 0.47 2989.28 818 1.10.3.2.1.2 Installation - Emergency Shutdown Thu 7/16/09 Tue 7/28/09 0 12.97 days 0.6 3795.76 819 1.10.3.2.1.2.1 PVC conduit and boxes Thu 7/16/09 Thu 7/16/09 I 0 0.76 days 12 mtr 0.01 63.96 820 1.10.3.2.1.2.2 Instrument cables Thu 7/16/09 Tue 7/28/09 I 0 12.21 days 1944 mtr 0.59 3731.8 821 1.10.3.3 Operation Floor Thu 7/16/09 Thu 9/24/09 0 77.9 days 2.5 15748.66 822 1.10.3.3.1 Installation - Electrical Thu 7/16/09 Thu 9/24/09 0 77.9 days 2.45 15415.53 823 1.10.3.3.1.1 Installation - Lighting System Thu 7/16/09 Wed 7/22/09 0 6.48 days 0.26 1632.66 824 1.10.3.3.1.1.1 Rigid Steel Conduit Thu 7/16/09 Sat 7/18/09 E 0 1.4 days 52 mtr 0.05 315 6/25 7/16 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 14 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 15. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 825 1.10.3.3.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.04 days 300 mtr 0.03 188.82 826 1.10.3.3.1.1.3 Junction Box Sun 7/19/09 Sun 7/19/09 E 0 1 day 2 nos. 0.01 53.3 827 1.10.3.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 7/19/09 Tue 7/21/09 E 0 1.64 days 12 nos. 0.05 303.76 828 1.10.3.3.1.1.5 Lighting Feeder cables / wires Tue 7/21/09 Wed 7/22/09 E 0 1.4 days 196 mtr 0.12 771.78 829 1.10.3.3.1.2 Installation - Cable Tray Thu 7/16/09 Wed 7/22/09 0 6.3 days 0.02 110.86 830 1.10.3.3.1.2.1 Cantilever supports installation Thu 7/16/09 Thu 7/16/09 E 0 0.07 days 9 nos. 0 7.65 831 1.10.3.3.1.2.2 Cable Tray installation Tue 7/21/09 Wed 7/22/09 E 0 0.45 days 55 mtr 0.02 103.22 832 1.10.3.3.1.3 Installation - Blower and Transformer Feeder Thu 7/16/09 Tue 7/21/09 0 5.85 days 0.42 2653.46 833 1.10.3.3.1.3.1 Blower Feeder, Transformer Feeder Thu 7/16/09 Tue 7/21/09 E 0 5.85 days 700 mtr 0.42 2653.46 834 1.10.3.3.1.4 Installation - Local Junction Box Thu 7/16/09 Thu 9/24/09 0 77.9 days 1.75 11018.55 835 1.10.3.3.1.4.1 Rigid Steel Conduit Thu 7/16/09 Wed 7/22/09 E 0 7.5 days 130 mtr 0.96 6021.3 836 1.10.3.3.1.4.2 Junction Box Wed 7/22/09 Sun 7/26/09 E 0 3.54 days 26 nos. 0.05 345.92 837 1.10.3.3.1.4.3 Feeder cables Sun 7/26/09 Sun 8/2/09 E 0 8.12 days 948 mtr 0.5 3126.95 838 1.10.3.3.1.4.4 Cable Termination Tue 9/8/09 Thu 9/24/09 E 0 18 days 88 nos. 0.24 1524.38 839 1.10.3.3.2 Air Compressed System - Piping Thu 7/16/09 Thu 7/23/09 0 8 days 0.05 333.13 840 1.10.3.3.2.1 2" Equal Tee Thu 7/16/09 Mon 7/20/09 P 0 4 days 11 nos 0.03 213.2 841 1.10.3.3.2.2 2" Plug Mon 7/20/09 Tue 7/21/09 P 0 1 day 9 nos 0.01 79.95 842 1.10.3.3.2.3 1/2" Ball valve Tue 7/21/09 Tue 7/21/09 P 0 1 day 2 nos 0 10.66 843 1.10.3.3.2.4 2" x 1" Reducer Tue 7/21/09 Wed 7/22/09 P 0 1 day 2 nos 0 10.66 844 1.10.3.3.2.5 1" x 1/2" Reducer Tue 7/21/09 Wed 7/22/09 P 0 1 day 2 nos 0 10.66 845 1.10.3.3.2.6 1/2" Nipple Wed 7/22/09 Thu 7/23/09 P 0 1 day 2 nos 0 8 846 1.10.4 Pot 264 Thu 8/6/09 Thu 9/24/09 0 54.65 days 3.21 20208.7 847 4.5.2.1 SLI DELIVERABLES Thu 8/6/09 Thu 8/6/09 0 0 days 0 0 848 1.10.4.1.1 POT 264 Area Available for MPEI Construction Thu 8/6/09 Thu 8/6/09 0 0 days 0 0 849 1.10.4.2 Basement Floor Thu 8/6/09 Sat 8/22/09 0 17.52 days 1.25 7879.23 850 1.10.4.2.1 Installation - Electrical Thu 8/6/09 Sat 8/22/09 0 17.52 days 1.25 7879.23 851 1.10.4.2.1.1 Installation - Lighting System Thu 8/6/09 Sat 8/22/09 0 17.52 days 0.65 4064.82 852 1.10.4.2.1.1.1 PVC conduit and boxes Thu 8/6/09 Sat 8/8/09 E 0 2.38 days 81 mtr 0.04 258.24 853 1.10.4.2.1.1.2 Single Core Wires Sat 8/8/09 Sun 8/9/09 E 0 1.24 days 176 mtr 0.02 130.53 854 1.10.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 8/6/09 Sat 8/8/09 E 0 1.4 days 19 nos. 0.02 152.97 855 1.10.4.2.1.1.4 Lighting Feeder cables / wires Wed 8/12/09 Sat 8/22/09 E 0 11.22 days 1477 mtr 0.56 3523.08 856 1.10.4.2.1.2 Installation - Emergency Shutdown Thu 8/6/09 Tue 8/18/09 0 13.3 days 0.61 3814.41 857 1.10.4.2.1.2.1 PVC conduit and boxes Thu 8/6/09 Thu 8/6/09 I 0 0.76 days 12 mtr 0.01 63.96 858 1.10.4.2.1.2.2 Instrument cables Thu 8/6/09 Tue 8/18/09 I 0 12.21 days 1944 mtr 0.59 3731.8 859 1.10.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 8/18/09 Tue 8/18/09 I 0 0.33 days 1 mtr 0 18.66 860 1.10.4.3 Operation Floor Thu 8/6/09 Thu 9/24/09 0 54.65 days 1.96 12329.46 861 1.10.4.3.1 Installation - Electrical Thu 8/6/09 Thu 9/24/09 0 54.65 days 1.9 11996.34 862 1.10.4.3.1.1 Installation - Cable Tray Thu 8/6/09 Wed 8/12/09 0 6.3 days 0.02 110.86 863 1.10.4.3.1.1.1 Cantilever supports installation Thu 8/6/09 Thu 8/6/09 E 0 0.07 days 9 nos. 0 7.65 864 1.10.4.3.1.1.2 Cable Tray installation Tue 8/11/09 Wed 8/12/09 E 0 0.45 days 55 mtr 0.02 103.22 865 1.10.4.3.1.2 Installation - Crane Bus Bars Thu 8/6/09 Wed 8/12/09 0 7.45 days 0.69 4338.62 866 1.10.4.3.1.2.1 Crane Bus Bar Supports installation Thu 8/6/09 Thu 8/6/09 E 0 0.96 days 16 nos. 0.02 96.37 867 1.10.4.3.1.2.2 Disconnect Switch Instalation Thu 8/6/09 Sat 8/8/09 E 0 0.5 days 1 nos. 0 17.32 868 1.10.4.3.1.2.3 Interconnection cable, cableways installation Sat 8/8/09 Sun 8/9/09 E 0 1 day 5 nos. 0.03 159.9 869 1.10.4.3.1.2.4 Crane Power Feeder Cable Sun 8/9/09 Wed 8/12/09 E 0 4 days 525 mtr 0.63 3978.85 870 1.10.4.3.1.2.5 Cable Termination Wed 8/12/09 Wed 8/12/09 E 0 0.99 days 5 nos. 0.01 86.19 871 1.10.4.3.1.3 Installation - Blower and Transformer Feeder Thu 8/6/09 Tue 8/11/09 0 5.85 days 0.42 2653.46 872 1.10.4.3.1.3.1 Blower Feeder, Transformer Feeder Thu 8/6/09 Tue 8/11/09 E 0 5.85 days 700 mtr 0.42 2653.46 873 1.10.4.3.1.4 Installation - Socket / Welding Outlet Thu 8/6/09 Sun 8/9/09 0 3.23 days 0.07 434.47 874 1.10.4.3.1.4.1 Rigid Steel Conduit Thu 8/6/09 Thu 8/6/09 E 0 0.84 days 15 mtr 0.01 78.35 875 1.10.4.3.1.4.2 Single Core Wires Thu 8/6/09 Sat 8/8/09 E 0 1.08 days 50 mtr 0.01 80.59 876 1.10.4.3.1.4.3 Junction Box Sat 8/8/09 Sun 8/9/09 E 0 0.5 days 2 nos. 0 23.98 877 1.10.4.3.1.4.4 Welding outlet / Socket Outlet Sun 8/9/09 Sun 8/9/09 E 0 0.29 days 2 nos. 0 27.05 878 1.10.4.3.1.4.5 Socket Feeder cables Sun 8/9/09 Sun 8/9/09 E 0 0.52 days 60 mtr 0.04 224.5 879 1.10.4.3.1.5 Installation - Local Junction Box Thu 8/6/09 Thu 9/24/09 0 54.65 days 0.71 4458.92 880 1.10.4.3.1.5.1 Rigid Steel Conduit Thu 8/6/09 Thu 8/13/09 E 0 7.62 days 140 mtr 0.12 744.6 881 1.10.4.3.1.5.2 Junction Box Thu 8/13/09 Sun 8/16/09 E 0 3.81 days 28 nos. 0.06 372.3 882 1.10.4.3.1.5.3 Feeder cables Sun 8/16/09 Thu 8/20/09 E 0 4.72 days 550 mtr 0.29 1817.64 883 1.10.4.3.1.5.4 Cable Termination Tue 9/8/09 Thu 9/24/09 E 0 18 days 88 nos. 0.24 1524.38 884 1.10.4.3.2 Air Compressed System - Piping Thu 8/6/09 Tue 8/11/09 0 6 days 0.05 333.13 8/6 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 15 Of 24 Project: C005 without subtotal Date: Tue 3/31/09
  • 16. ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 885 1.10.4.3.2.1 2" Equal Tee Thu 8/6/09 Mon 8/10/09 P 0 4 days 11 nos 0.03 213.2 886 1.10.4.3.2.2 2" Plug Sat 8/8/09 Sun 8/9/09 P 0 1 day 9 nos 0.01 79.95 887 1.10.4.3.2.3 1/2" Ball valve Sun 8/9/09 Mon 8/10/09 P 0 1 day 2 nos 0 10.66 888 1.10.4.3.2.4 2" x 1" Reducer Mon 8/10/09 Tue 8/11/09 P 0 1 day 2 nos 0 10.66 889 1.10.4.3.2.5 1" x 1/2" Reducer Mon 8/10/09 Tue 8/11/09 P 0 1 day 2 nos 0 10.66 890 1.10.4.3.2.6 1/2" Nipple Tue 8/11/09 Tue 8/11/09 P 0 1 day 2 nos 0 8 891 1.11 Construction - Potroom No 2 (501-22C) Thu 5/14/09 Wed 8/19/09 0 107.9 days 11.61 73108.92 892 1.11.1 Pot 198 Thu 5/14/09 Thu 6/25/09 0 46.87 days 2.96 18614.31 893 4.5.2.1 SLI DELIVERABLES Thu 5/14/09 Thu 5/14/09 0 0 days 0 0 894 1.11.1.1.1 POT 198 Area Available for MPEI Construction Thu 5/14/09 Thu 5/14/09 0 0 days 0 0 895 1.11.1.2 Basement Floor Sat 5/16/09 Thu 6/25/09 0 45.16 days 1.15 7244.8 896 1.11.1.2.1 Installation - Electrical Sat 5/16/09 Thu 6/25/09 0 45.16 days 1.15 7244.8 897 1.11.1.2.1.1 Installation - Lighting System Sat 5/16/09 Sun 6/7/09 0 24.84 days 0.55 3449.04 898 1.11.1.2.1.1.1 PVC conduit and boxes Sat 5/16/09 Sun 5/17/09 E 0 2.03 days 68 mtr 0.03 220.26 899 1.11.1.2.1.1.2 Single Core Wires Sun 5/17/09 Mon 5/18/09 E 0 1.04 days 148 mtr 0.02 109.48 900 1.11.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Sat 5/16/09 Sun 5/17/09 E 0 1.19 days 16 nos. 0.02 130.03 901 1.11.1.2.1.1.4 Lighting Feeder cables / wires Thu 5/28/09 Sun 6/7/09 E 0 9.52 days 1244 mtr 0.47 2989.28 902 1.11.1.2.1.2 Installation - Emergency Shutdown Wed 6/10/09 Thu 6/25/09 0 16.44 days 0.6 3795.76 903 1.11.1.2.1.2.1 PVC conduit and boxes Wed 6/10/09 Wed 6/10/09 I 0 0.76 days 12 mtr 0.01 63.96 904 1.11.1.2.1.2.2 Instrument cables Sun 6/14/09 Thu 6/25/09 I 0 12.21 days 1944 mtr 0.59 3731.8 905 1.11.1.3 Operation Floor Thu 5/14/09 Thu 6/25/09 0 46.87 days 1.81 11369.5 906 1.11.1.3.1 Installation - Electrical Thu 5/14/09 Thu 6/25/09 0 46.87 days 1.75 11036.38 907 1.11.1.3.1.1 Installation - Crane Bus Bars Mon 5/18/09 Wed 5/27/09 0 11.13 days 0.73 4602.61 908 1.11.1.3.1.1.1 Crane Bus Bar Supports installation Mon 5/18/09 Mon 5/18/09 E 0 0.96 days 16 nos. 0.02 96.37 909 1.11.1.3.1.1.2 Feed Junction Box Installation Mon 5/18/09 Wed 5/20/09 E 0 1.67 days 5 nos. 0.01 89.01 910 1.11.1.3.1.1.3 Disconnect Switch Instalation Wed 5/20/09 Wed 5/20/09 E 0 0.5 days 1 nos. 0 17.32 911 1.11.1.3.1.1.4 Interconnection cable, cableways installation Wed 5/20/09 Thu 5/21/09 E 0 1 day 5 nos. 0.03 159.9 912 1.11.1.3.1.1.5 Crane Power Feeder Cable Thu 5/21/09 Mon 5/25/09 E 0 4 days 525 mtr 0.63 3978.85 913 1.11.1.3.1.1.6 Cable Termination Mon 5/25/09 Wed 5/27/09 E 0 3 days 15 nos. 0.04 261.17 914 1.11.1.3.1.2 Installation - Socket / Welding Outlet Thu 5/14/09 Sun 5/17/09 0 3.23 days 0.07 434.47 915 1.11.1.3.1.2.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/14/09 E 0 0.84 days 15 mtr 0.01 78.35 916 1.11.1.3.1.2.2 Single Core Wires Thu 5/14/09 Sat 5/16/09 E 0 1.08 days 50 mtr 0.01 80.59 917 1.11.1.3.1.2.3 Junction Box Sat 5/16/09 Sun 5/17/09 E 0 0.5 days 2 nos. 0 23.98 918 1.11.1.3.1.2.4 Welding outlet / Socket Outlet Sun 5/17/09 Sun 5/17/09 E 0 0.29 days 2 nos. 0 27.05 919 1.11.1.3.1.2.5 Socket Feeder cables Sun 5/17/09 Sun 5/17/09 E 0 0.52 days 60 mtr 0.04 224.5 920 1.11.1.3.1.3 Installation - Local Junction Box Thu 5/21/09 Thu 6/25/09 0 38.15 days 0.95 5999.29 921 1.11.1.3.1.3.1 Rigid Steel Conduit Thu 5/21/09 Thu 5/28/09 E 0 7.62 days 140 mtr 0.12 744.6 922 1.11.1.3.1.3.2 Junction Box Thu 5/28/09 Mon 6/1/09 E 0 3.81 days 28 nos. 0.06 372.3 923 1.11.1.3.1.3.3 Feeder cables Mon 6/1/09 Tue 6/9/09 E 0 8.72 days 1020 mtr 0.53 3358.01 924 1.11.1.3.1.3.4 Cable Termination Tue 6/9/09 Thu 6/25/09 E 0 18 days 88 nos. 0.24 1524.38 925 1.11.1.3.2 Air Compressed System - Piping Thu 5/14/09 Wed 5/20/09 0 6.35 days 0.05 333.13 926 1.11.1.3.2.1 2" Equal Tee Thu 5/14/09 Mon 5/18/09 P 0 4 days 11 nos 0.03 213.2 927 1.11.1.3.2.2 2" Plug Sat 5/16/09 Sun 5/17/09 P 0 1 day 9 nos 0.01 79.95 928 1.11.1.3.2.3 1/2" Ball valve Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66 929 1.11.1.3.2.4 2" x 1" Reducer Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66 930 1.11.1.3.2.5 1" x 1/2" Reducer Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66 931 1.11.1.3.2.6 1/2" Nipple Tue 5/19/09 Wed 5/20/09 P 0 1 day 2 nos 0 8 932 1.11.2 Pot 220 Wed 6/3/09 Sun 7/12/09 0 42.89 days 2.4 15091.58 933 4.5.2.1 SLI DELIVERABLES Thu 6/4/09 Thu 6/4/09 0 0 days 0 0 934 1.11.2.1.1 POT 220 Area Available for MPEI Construction Thu 6/4/09 Thu 6/4/09 0 0 days 0 0 935 1.11.2.2 Basement Floor Wed 6/3/09 Wed 7/1/09 0 32 days 1.22 7687.83 936 1.11.2.2.1 Installation - Electrical Wed 6/3/09 Wed 7/1/09 0 32 days 1.22 7687.83 937 1.11.2.2.1.1 Installation - Lighting System Wed 6/3/09 Sat 6/13/09 0 10.71 days 0.61 3873.42 938 1.11.2.2.1.1.1 PVC conduit and boxes Thu 6/4/09 Sat 6/6/09 E 0 2.24 days 76 mtr 0.04 243.05 939 1.11.2.2.1.1.2 Single Core Wires Sat 6/6/09 Sun 6/7/09 E 0 1.16 days 166 mtr 0.02 122.11 940 1.11.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Thu 6/4/09 Sat 6/6/09 E 0 1.33 days 18 nos. 0.02 145.32 941 1.11.2.2.1.1.4 Lighting Feeder cables / wires Wed 6/3/09 Sat 6/13/09 E 0 10.71 days 1400 mtr 0.53 3362.94 942 1.11.2.2.1.2 Installation - Emergency Shutdown Wed 6/10/09 Wed 7/1/09 0 23.22 days 0.61 3814.41 943 1.11.2.2.1.2.1 PVC conduit and boxes Wed 6/10/09 Thu 6/11/09 I 0 0.76 days 12 mtr 0.01 63.96 5/14 6/4 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 16 Of 24 Project: C005 without subtotal Date: Tue 3/31/09